BSBMGT517 Manage operational plan
Student’s declaration:
By submitting this assessment, you acknowledge and agree to the following conditions.
Check all boxes if you agree.
ILSC Greystone CollegeBSBMGT517 Manage Operational Plan Project template guide V2.0420
Task 2 –Knowledge Questions Template
Please provide answers to the following 9questions:
2. Describe how operational plans are developed through the basic strategic planning
approach.
The basic strategic planning approach requires you to identify your purpose (mission
statement), select the goals your organization must reach. Identify specific strategies to
implement to reach each goal, identify actions to each strategy and monitor and update
the plan.
S Alan C
3. Describe how operational plans are developed through the goal-based planning
approach.
The goal based planning approach requires you to external and internal assessment to
identify strength, weakness, opportunities and threats. Strategic analyses to identify and
prioritize goals, design programs to achieve goals, update statements, establish actions
plans with objective, prepare a plan for recorded issues, goals, strategic and action plans,
develop a one year operational plan from multiyear strategic plan, develop budgets,
implement the operational plan and monitor and review the plan.
S Alan C
Greystone College Australia BSBMGT517 Manage Operational Plan Assessment Templates V2.0420
2
4. Describe how operational plans are developed through the alignment planning
approach.
The alignment planning approach requires a planning group outline the organization’s
mission, programs, resources, and requirements. Identify what strategy and program are
working well and what needs improvement, determine what improvements need to be
implemented and include the improvement as strategies in the strategic plan.
S Alan C
5. Describe how operational plans are developed through the scenario planning
approach.
This approach ensures planners truly undertake strategic thinking and is useful in
identifying strategic issues and goals.
Basis but adequate response, could have included: Examining external forces, look for
common strategies and select the scenario to adopt.
Alan C
Greystone College Australia BSBMGT517 Manage Operational Plan Assessment Templates V2.0420
3
8. List the main expenditure categories that would be included in a budget.
9 Questions Total
Greystone College Australia BSBMGT517 Manage Operational Plan Assessment Templates V2.0420
4
BizOps Enterprises Operational plan and Executive briefings
BSBMGT517
MANAGE OPERATIONAL PLAN
Greystone College Australia BSBMGT517 Manage Operational Plan Assessment Templates V2.0420
5
Contents
Assessment Templates .............................................................................................................. 1
BSBMGT517 Manage operational plan...................................................................................... 1
Submitting your assessment .............................................................................................. 1
Task 2 – Knowledge Questions Template........................................................................... 2
9 Questions Total ................................................................................................................ 4
Task 3 - Project: Managing an operational plan at work.................................................... 4
1. RESEARCH & ANALYSIS ................................................................................................... 7
2. OPERATIONAL PLAN........................................................................................................ 7
Mission................................................................................................................................ 7
Objectives & Resources .......................................................................................................... 8
3. CONSULTATION PLAN ................................................................................................. 121
4. CONTINGENCY PLAN ................................................................................................... 132
5. BRIEFING: PROCUREMENT OF DELIVERY VANS .......................................................... 154
6. BRIEFING: INTELLECTUAL PROPERTY GUIDELINES ..................................................... 165
7. BRIEFING: RETAIL OUTLET WORK TEAMS ................................................................... 166
8. MONITORING PROCESS .............................................................................................. 187
9. BUDGET ....................................................................................................................... 209
10. PROGRESS REPORT (31st July) ................................................................................... 23
11. OPERATIONAL COACHING PLAN ........................................................................... 2423
Risks: ................................................................................ Error! Bookmark not defined.24
12. INFORMATION MANAGEMENT GUIDELINES ........................................................ 2625
13. IMPLEMENTATION STRATEGY: Operational Plan - Sales staff .............................. 2726
BizOps recruitment policies: ............................................................................................. 28
Greystone College Australia BSBMGT517 Manage Operational Plan Assessment Templates V2.0420
6
1. RESEARCH& ANALYSIS
Suppliers What are the Research from The budget for the van is $42,680 per
specifications of online resources vehicle
the van? In order to reduce the individual carbon
Which supplier Quotes of required footprint and comply our company
should we choose? delivery van sustainability environmental policy, it
What type of van better to choose environmental friendly
should we choose? transport such as electric vans.
How many vans Nissan is one of the suppliers who
should we provide eco-friendly vans
purchase?
Sign What type of sign Research from Vinyl graphics are cost effective, come in
writer writer should we online resources the brightest colors, are the tough-nest
choose? Information from and the longest lasting type of vehicle
What kind of logo sign writer graphic
we used? Advice from
How much is it to marketing group S Alan C
have marketing for the logo style
decals attached to and details
the vans?
2. OPERATIONAL PLAN
Mission:
Need to be completed and resubmitted AC
Resubmitted and successfully graded : S Alan C 8/10/20
Greystone College Australia BSBMGT517 Manage Operational Plan Assessment Templates V2.0420
7
BizOps is committed to:
• providing high quality and innovative products and services to customers.
• meeting the changing needs of customers.
• offering innovative product solutions.
• delivering speedy and personalized service.
• employing professional and enthusiastic staff.
• providing clean and ‘green’ products and services.
• adopting sustainable work practices.
• undertaking continuous improvement processes.
S Alan C 8/10/20
In 2015–2020 BizOps will consolidate its position in the market as a lead retailer for ‘green’
and sustainable solutions for high quality exclusive products. To do this, BizOps will focus on
the following business goals:
Financial stability:
➢ Increase revenue by 15% (compared to the previous 12 months) by the end of the
financial year.
➢ Maintain annual profit levels of 15% of revenue for all products and services,
calculated at the end of each financial year.
➢ Reinvest 75% of profit back into the business at the end of each financial year.
Market position:
➢ Maintain the number one rating in the annual national industry customer service
awards.
➢ Launch new high-quality exclusive consumer products to meet customer demand,
ahead of competitors, within budget and by the agreed deadlines.
Right people:
➢ Provide induction training at the commencement of employment to train new
employees to be knowledgeable, helpful and enthusiastic.
➢ Provide the physical, human and time resources to support an annual professional
development program for all BizOps employees.
Greystone College Australia BSBMGT517 Manage Operational Plan Assessment Templates V2.0420
8
➢ Communication systems are in use to reduce travel and time commitments of outlet
managers. S Alan C 8/10/20
Expert and knowledgeable staff:
➢ BizOps employs multiskilled retail sales staff capable of providing after sales product
support to customers.
S Alan C 8/10/20
Greystone College Australia BSBMGT517 Manage Operational Plan Assessment Templates V2.0420
9
No. Activity Resources Procedures Responsible When Budget KPI
Define specifications Minutes Have a meeting with Marketing 01 July Budget of the All members
of the van representatives of outlets, supportive team project 7.5 to attend
marketing manager and Marketing million 50.000 meeting
1
operational service manager Manager Some per outlet according to
representatives of date and
the outlet time.
Research and define Marketing Have a meeting with Marketing team 02 July Budget of the All members
the van supplier group marketing group and define manager project 7.5 to attend
the supplier of the van million 50.000 meeting
2
per outlet according to
date and
time.
Contact the supplier Minutes Have a meeting with Marketing 03 July Budget of the All members
and get the quote of supplier and discuss the project 7.5 to attend
the van price of the van million 50.000 meeting
3
per outlet according to
date and
time.
Define specification of Minutes Have a meeting with Marketing 04 July Budget of the All members
decals attached to the sighwriter, marketing supportive team project 7.5 to attend
van manager and operational Marketing million 50.000 meeting
4
service manager manager per outlet according to
Representatives of date and
sighwriter time.
Greystone College Australia BSBMGT517 Manage Operational Plan Assessment Templates V2.0420
10
Complete a BizOps Purchase Complete a BizOps purchase Operation 05 July Budget of the Complete the
purchase order order order requisition form that manager project 7.5 purchase
requisition form requisition details the van specifications million 50.000 order
5
form including decals attached to per outlet requisition
the van and the date form correctly
required
Place the order Operational The purchasing officer will Operation team 06 July Budget of the Place the
team review the purchase double manager project 7.5 order of the
check the calculations for Accounting million 50.000 van by 10 July
accuracy, verify the department per outlet
signatures of approval are manager
6
authorized officials
Make sure the purchase
order requisition form is
accurate
Send the order to vendor
Receive the van when Operational Receive the van and check Operation team 30 July Budget of the Receive the
delivered team the specifications and decals manager project 7.5 van and
7 attached to the van million 50.000 decals
per outlet attached by
31 July
8 Forward the invoice to Email Forward the invoice to the Operation team 31 July Budget of the Forward the
the Finance manager finance manager manager project 7.5 invoice to
Finance team million 50.000 finance
manager per outlet manager by
31 July
Greystone College Australia BSBMGT517 Manage Operational Plan Assessment Templates V2.0420
11
3. CONSULTATION PLAN.
Consultation
Strategy Role Objective Methods
stakeholder
Liz Hitchens Marketing Define the specification and Meeting
manager decals of the van Email communication
Video or phone conference
Chang Lin Business Complete the purchase order Meeting Email communication
operations form and place the order Video or phone conference
manager
Aziz Singh Finance Forward the invoice to the Meeting
manager finance manager Email communication
Video or phone conference
Fatima Company Make sure the purchase order Meeting
Williams accountant requisition for are correct Email communication
Video or phone conference
HR Handling recruiting delivery Meeting
Gina Harris Manager drivers to fill vacancies Email communication
Provide the delivery driver job Video or phone conference
description, requirement and
responsibility to the
recruitment agency and hire
the right person in the right
position
S Alan C
Greystone College Australia BSBMGT517 Manage Operational Plan Assessment Templates V2.0420
12
4. CONTINGENCY PLAN
Greystone College Australia BSBMGT517 Manage Operational Plan Assessment Templates V2.0420
13
The budgeted cost per Medium Medium 1. Pre-order 3. To meet Operations manager
vehicle of $42,680 is from the suppliers
based on the current different company’
exchange rate of the suppliers s budget
Australian dollar. who has a
There is a risk the lower price
dollar value could drop
2. Contact
by 10–15% and suppliers for
increase the value of discounts
the vans by this
percentage
S Alan C 4. 5.
Can also look at risks
later as these two
sections are
interlinked. AC
Greystone College Australia BSBMGT517 Manage Operational Plan Assessment Templates V2.0420
14
5. BRIEFING:PROCUREMENT OF DELIVERY VANS
Ford currently owns the top spot for the most popular van in the UK. As of August, the Ford
Transit Custom had sold 2,439 models in 2018.
The Transit range is very popular. The original Ford Transit is the largest option and can stow
lengths of up to 4.2 metres. The smallest option is the Transit Courier, which is also known
for its superior fuel economy. The Ford Transit Connect is another firm favourite and can carry
up to 993kg of cargo. The advantage of ford van is that it has refined and powerful engine. It
has driver assist safety features and has practical well equipped cabin
Mercedes
As of 2018, the most sought-after Mercedes van is the Sprinter. In fact, it’s number two in
the top 10 list of most popular UK vans. It comes in various styles including the Panel, Crew,
Tourer and Dropside.
Other top choices include the Vito, which can carry between 727 and 1,129kg, and the Citan,
which is the lightest option available from Mercedes.
Nissan
Nissan’s range of vans features a selection of different sizes. The most compact option is the
NV200, which is capable of carrying loads of up to 795kg and boasts a 5.3m turning radius.
The NV400 is another popular choice with plenty of load space, a carry capacity of 2200kg
and a streamlined design.
Toyota
There’s no denying that the Toyota Hilux is a popular van on UK roads. It can carry loads of
up to 1,130kg.
The Toyota Proace, with a maximum load of 1,200kgs, is another winning model to consider.
Here are the references of specialist advice that contributed to these recommendations:
⚫ Car dealer
⚫ The car specialist
⚫ Online resources and reports
Recommendations of a procurement process that aligns with the purchasing policy and
purchasing procedures
Finally I recommend purchasing from Nissan, Purchase requisition preparation involves the
following:
Greystone College Australia BSBMGT517 Manage Operational Plan Assessment Templates V2.0420
15
⚫ All BizOps employees who require a product or service must complete a BizOps purchase
order requisition form that details the items for purchase and the date required.
⚫ All completed purchase order requisition forms are to be approved by an authorized
delegate.
On receipt of a completed purchase order requisition form, the purchasing officer will:
S Alan C
Intellectual property issues that may be associated with the supply of the design:
1. Prepairing a written agreement with signWriter Company and state that the
specifications of design are not disclose, use or sale to a third party.
2. Apply for a trademark for the logo to prevent other companies from using the same
logo.
3. Make sure the vans have the appropriate license such as advertising license or
vehicle decal license before attaching marketing decal to the vans
S Alan C
7. BRIEFING:RETAIL OUTLET WORK TEAMS
BizOps enterprise is launching a new delivery service. The operational plan has as a goal
purchase and decal 150 delivery vans until 13rd of September 2019. This new deliverer
services will be undertaking and coordinated from each outlet. This new service will need a
staff and the suggestion would be to offer new positions for current staff because they
already understand company’s structure and customers.
Greystone College Australia BSBMGT517 Manage Operational Plan Assessment Templates V2.0420
16
It is important for an amazing result to prevent any type of injury to our staff, vans and goods
damages and delivery delay. To help us delivery the best service a “Guide to safe work-related
driving “was created and need to be followed, also each store will be responsible about
compliance with WHS.
Aspects of the operational plan that will need to be implemented at each retail outlet
⚫ The retail store should make sure the store can open to the public on time
⚫ The store manager should organize the meeting with staffs so that they will be aware of
the everything that is going through during operational plans
⚫ Recruit new people or providing training for new staffs
WHS risk assessment and legislative review of the issues associated with having retail staff
operating delivery vans
Accident: Staff without professional training will lead to accident while operating the van.
Delivery delay: staff without properly training may lead to delay in delivery
Customer dissatisfaction: Due to the delivery not on time, customer may feel dissatisfied as
a result of low quality customer service.
S Alan C
Greystone College Australia BSBMGT517 Manage Operational Plan Assessment Templates V2.0420
17
8. MONITORING PROCESS
Monitoring process
No. Activity Resources Procedures Responsible When Budget KPI
Define Minutes Have a meeting Marketing 01 Budget of All members 30 % of 65% of 100%
specifications of with supportive July the to attend meetings meetings meetings
the van representatives team project 7.5 meeting programme programme programmed
of outlets, Marketing million according to d& d& & completed
1
marketing Manager Some 50.000 per date and completed completed
manager and representative outlet time.
operational s of the outlet
service manager
Research and Marketing Have a meeting Marketing 02 Budget of All members 30 % of 65% of 100%
define the van group with marketing team manager July the to attend meetings meetings meetings
supplier group and project 7.5 meeting programme programme programmed
2
define the million according to d& d& & completed
supplier of the 50.000 per date and completed completed
van outlet time.
Contact the Minutes Have a meeting Marketing 03 Budget of All members 30 % of 65% of 100%
supplier and get with supplier July the to attend meetings meetings meetings
the quote of the and discuss the project 7.5 meeting programme programme programmed
3
van price of the van million according to d& d& & completed
50.000 per date and completed completed
outlet time.
Define Minutes Have a meeting Marketing 04 Budget of All members 30 % of 65% of 100%
specification of with sign supportive July the to attend meetings meetings meetings
4
decals attached writers, team project 7.5 meeting programme programme programmed
to the van marketing million according to & completed
S Alan C
9. BUDGET
Budget
Variance
Operational plan progress activities Comments/Recommendations
Favorable/unfa
vorable
The order for 150 vans has been placed An increase of $2,558 for each van
with a purchase value of $45,238 for each unfavorable according to the budget. Report on
van. increase as budget risk.
There is shortfall in supply and only 67
Follow up with the supplier and make
vans have been delivered. The remainder
Unfavorable sure the remaining vans to be
should be delivered in two months.
delivered.
All of the supplied vans should be decaled Only 67 vans delivered and available
in the next 30 days. Unfavorable for decal. The remaining van only can
be decaled on August - 30 September
The remainder of the decaled vans should
be decaled within 30 days of their Van decal is not a time consuming job
Favorable
delivery. and can be done within designed time.
S Alan C
S Alan C
BizOps aims to manage its information and information systems effectively so it can:
• ensure the right information is captured at the right time
• demonstrate accountability and provide transparency in its decision-making processes
• improve access, retrieval and reuse of information for those who require it
• ensure accuracy, consistency and currency of business records
• ease of navigation through BizOps records and information
• improve security of records that, for confidentiality or privacy reasons, require additional protection
S Alan C
Principles
• BizOps will meet its legal obligations and organisational requirements with respect to information management.
• All records created by staff (including contractors) in the course of their duties remain the physical and intellectual property of BizOps. Personal
use of records and information is prohibited unless approved by the Business Operations Manager or senior management.
• Record keeping is planned to ensure that all BizOps records embody the required characteristics; authenticity, integrity, reliability and usability.
• All staff are trained in their record-keeping responsibilities and supported appropriately.
• All staff will follow this policy.
• All documents in the information systems will be available for access and use unless privacy or confidentiality issues have been defined and
agreed with the Business Operations Manager.
Roles and responsibilities
All staff are responsible for:
• creating full and accurate records
S Alan C