Arabian Consolidated Industrial Cleaning Services - Tandheef

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 3
At a glance
Powered by AI
The audit checklist outlines important safety requirements that must be followed when conducting bundle pulling work, such as having the proper work permits and JSA, conducting pre-lift meetings, ensuring qualified operators and teams, and barricading the work area.

The crane must be in good working condition with no leaks, on a stable surface, outriggers fully extended, load indicators calibrated, and safety features like alarms and lights functioning properly. A valid inspection log and qualified operator are also required.

The work area for the lift must be clear of obstructions, personnel have safe access and egress, and adequate visibility and lighting. Wind speed must also be acceptable for the lift to proceed safely.

ARABIAN CONSOLIDATED INDUSTRIAL CLEANING SERVICES - TANDHEEF

HSE DEPARTMENT
AUDIT CHECK LIST FOR BUNDLE PULLING

Project: Project Number :


Date : Location / Area :
Activity : Equipment :
Foreman : Auditor :

Safety Violations: Unsafe conditions / Unsafe Acts

Bundle Pulling YES NO N/A


Work Permit
Correct work permit at job site?
Are all permit conditions met at job site?
Are gas tests being conducted as per work permit?
JSA (Job Safety Analysis)
Is the JSA attached with permit and posted at the job site when required?
Does the job site "In-Charge" understand the contents of the JSA?
Communication
Has lift supervisor and appropriate lift team been nominated and available at the
location?
Has pre-lift meeting been conducted with lift team and been understood?
Have the primary & secondary means of communication been established when
required?
Have safety barriers erected for lift zone & signage been put in place?
Bundle Puller
Is the correct Bundle Puller being used in good condition?
Has it been approved and certified by the client
Is there a qualified and competent bundle pulling supervisor/foreman?
Is there a qualified and competent bundle pulling team?
Barricading and Signage
Is the barricading of such nature that it stops unauthorized entry?
Does the barricaded area have a "gate" for entering the job site?
Is there a "gate" watch to prevent unauthorized entry to the job site?
Are signs warning of the dangers and that heavy lifting is in progress posted?
Equipment
Is the rigging fit for purpose and recently inspected?
Is certification available for crane, sling and rigging?
Is there any evidence of leakage (oil, hydraulic) under or around the crane?
Is crane on a firm/stable surface and level?
Does outriggers are fully extended and outriggers pad provided?
Is reversing horn fitted and in good working condition?
Is there a properly inspected and fully charged fire extinguisher on the crane?
Is crane grounded to the right point?
SWL printed on boom?
Is Load weight indicator, Load radius indicator, Boom angle indicator working properly?
AUDIT CHECK LIST FOR BUNDLE PULLING YES NO N/A
Equipment (Cont..)
Are the tires completely off the ground if on outriggers?
Does the crane have a hoist limiting (anti two-block) device and working properly?
Does the crane have some type of load indicating system? Has the load indicating
system been calibrated?
Is the appropriate load chart available in the cab and being used?
Are all brakes and clutches in good working order?
Are all gauges and control panel lights in working order?
Does the load movement indicator (LMI) calibrated and working?
Is the safety alarm functioning correctly?
Is emergency (Red) beacon working?
Is there a Crane inspection log?
Is yellow beacon working ?
Are cab glass clean, free of cracks and unobstructed by posters, curtains, shades, etc?
Environment
Is the wind speed acceptable for the lift?
Is there adequate light & visibility to complete the lift?
Is there clear visibility? (No dust storm)
Rigging
Are all slings equipped with legible tags showing the safe working load?

Are wire rope slings in good condition? Check for storage conditions, broken
strands, condition of sleeves, kinks, etc.
Are synthetic slings in good condition? Checked for rips, cuts, tears, melted fibers
etc?

Is all lifting gear inspected, certified and color coded?


Lifting Operation
Is the area for lifting load & the lifting route clear of obstructions and personnel?
Is the area for landing the load clear, strong enough, properly prepared & is there
any risk of the load becoming unstable after landing?
Is there safe access & egress to attach and recover lift rigging?
Adequate tail (counterweight/winch) swing clearance?
Are required number of tag lines used to control loads being lifted?
Traveling
If warningasignals
Crane are available, are they used when approaching workmen, blind
corners, etc.?
Is the (lattice) boom as low as safely practicable?
Has telescopic boom been lowered to the traveling position?
Is flag man/banks man is used to guide the crane?
Supervision
Does crane operator have valid license and certificate (Saudi license & TUV certified)?
Is there a lift plan available if required?
Is Crane Inspected and sticker posted on it?
Are riggers and banks man trained and certified?
Are riggers and banks man wearing green fluorescent vest ?
Is anyone working or walking under suspended load?