SHUWEIHAT-3 IPP

FIELD CHANGE ORDER


FORMAT NO: S3-IMS-L4-112-MOC-F-002 REV: 03 EFFECTIVE DATE: 25-10-2020 PAGE 1 OF 1
PREPARED BY: MA REVIEWED BY: EM AND PM APPROVED BY: PGM AND EMD

FCO NO. _

Originator: Mayur R. Gupta__ Department / Section : Maintenance . Elec._Date: 7 th Dec. 2020

Area:_ Water Treatment Plant_ Equipment: Micro filter cartridge

Requirement : (Please tick -  as applicable)


x Improve reliability
Safety need
x Operational flexibility
x Cost saving
x Environmental Improvement

1. Brief description: (Please attach additional sheet, if more space is needed)


Ref. FCR Dated 23rd Dec. 2019 attached.
For alternate mitigation plan for extending the FCR Originator proposed the life of the
cartridges and reducing biological matter, Below two options and the same are being
proposed for implementation in a phased manner based on the outcome.
1. Ultra Filtration Disinfection Technology
2. Magnetic Fields Suppress
1. Ultra Filtration Disinfection Technology
LIT UV Europe vendor has offered a UV reactor chamber along with Control system for
controlling UV lamp intensity as per the flow. The unit consist of a compact duplex steel
reactor with seven low-pressure high-output amalgam UV lamps DV 700HO-32 protected by
Quartz sleeves and control panel with multi touch display. Details of the equipment
supplied are provided in the offer.

2. Magnetic Field Suppress:


- Why Unit No. 3 is required ?
- Arrangement of Power supply for the units to be worked out.
-
CARDIS ASPAR is Australian company providing anti scaling system
SHUWEIHAT ASIA POWER COMPANY
SHUWEIHAT ASIA O&M COMPANY
DOC. NO: SAPCO / SAOM-IMS-MOC-F-
REV: 02 EFFECTIVE DATE: 30-01-2020 PAGE 2 OF 4
028
APPROVED BY: PGM AND
PREPARED BY: MA REVIEWED BY: EM AND PM
EMD
FIELD CHANGE ORDER

Samples were collected from below three different locations for understanding the
presence / growth of microbiological matter.
1. Sea water inlet (Pre-filter inlet)
2. RO Supply pump outlet to MCF
3. SWRO Inlet (MCF Outlet)
As per analysis report total bacterial count is 110,82 and 170 CFU/ml. Pseudomonas
bacteria presence is found in sample 2 and sample 3 (20and 87 CFU/100ml respectively)

One CARDIFFAIR unit can drive two coils. OEM has recommended 6 units as per the
attached P&ID, hence 12 coils will be required. Each coil will require 300 mtr. Cable (6
Sqmm – single core – 84 strands, Flexible).
Questions Clarifications from OEM
1. Dimensional Details of control Unit, - 280mm (H) X 370mm (W) X 190mm
Installation recommendations, (D) – IP68 rated
operating temperature range, - Unit requires 230V AC, 50Hz.
Details of power supply Operating temperature range of the
requirement, installation in any unit is 15 degree Celsius to 85
additional Panel if required degree Celsius. Wall mounting
fittings for the enclosure to be
provided by the
2. Material / Preparation required for - Details provided by the vendor.
installation at site. Details of coil to BOQ prepared accordingly. Ref.
be arranged. BOQ items.
3. Can we install the units by our self - Cardiffair ASRAPS employee
or will it require engineer ? required to supervise the
installation of the units and then
certify the commissioning once the
units are installed and operational
SHUWEIHAT ASIA POWER COMPANY
SHUWEIHAT ASIA O&M COMPANY
DOC. NO: SAPCO / SAOM-IMS-MOC-F-
REV: 02 EFFECTIVE DATE: 30-01-2020 PAGE 3 OF 4
028
APPROVED BY: PGM AND
PREPARED BY: MA REVIEWED BY: EM AND PM
EMD
FIELD CHANGE ORDER

Existing sketch and specifications:________ (Attachment)

Suggested sketch and specifications:_______ (Attachment)

2. Technical Note:

3. Cost Estimation Details:


SHUWEIHAT ASIA POWER COMPANY
SHUWEIHAT ASIA O&M COMPANY
DOC. NO: SAPCO / SAOM-IMS-MOC-F-
REV: 02 EFFECTIVE DATE: 30-01-2020 PAGE 4 OF 4
028
APPROVED BY: PGM AND
PREPARED BY: MA REVIEWED BY: EM AND PM
EMD
FIELD CHANGE ORDER

Cost of Modification: Date:

Material Cost
Option 1 (UV Filter installation)
S. No Description Qty Rate/Unit Total Cost
(USD) (USD)
1 5C X 25Sqmm, Cu Cable, Un armored – 150Mtr.
Solid cable
2 Instrumentation Cable. (Signals to be 150
transferred not known) Cable available Mtr.
at site. To be checked.
3 GRP Pipe cutting and flange
installation.
4 Reactor vessel installation
5 Supply of Reactor Vessel along with
Electrical Panel and Spare parts.
6

Option 2 Supply for CARDIFFAIR ASRAPS


1 Supply of ASRAPS Ultimate Control 6 Nos. 7,200 43,200
Units including wall mounted fittings.
2 Supervisors for installation works –
Cardiffair staff – 2 personals. Charges
include flight, accommodation rolls 1 Lot 23,720 23,720
and meals.
1 X Cardiffair staff member – 15 days
1 Cardiffair staff member – 20 days

 CICPA Cost and COVID 19


quarantine procedure and cost
to be discussed.
3 6Sqmm – 84 Strands single core 36 rolls
flexible cable 100mtr. Cable rolls. (300
SHUWEIHAT ASIA POWER COMPANY
SHUWEIHAT ASIA O&M COMPANY
DOC. NO: SAPCO / SAOM-IMS-MOC-F-
REV: 02 EFFECTIVE DATE: 30-01-2020 PAGE 5 OF 4
028
APPROVED BY: PGM AND
PREPARED BY: MA REVIEWED BY: EM AND PM
EMD
FIELD CHANGE ORDER

mtr. Per coil)


4 Accessories / Miscellaneous items
1. 20mm PVC Standard 90 degree
bend – Qty??
2. Conduit Rigid 20 M/D 6 m
length – Qty??
3. 20mm PVC couplings plain grey
– Qty??
4. 20mm Half SADDLE Zinc Plated
– Qty??
5. Corrugated conduit grey 20mm
(in lieu of bends) – Qty ??
6. US Switch for UK Plug – Qty??
7. 6mm2 Copper Cable jointer –
Qty??
8. Electrical Tape for cable jointer
insulation. Qty???
9. Tape for wrapping coil (details
and quantity required from
Vendor). Qty???
10. Metallic Cable ties Long X
10mm Wide. Qty ???

5 Scaffolding for carrying out the work. 1 Lot


Based on site condition.
6

Total Material Cost


Labour Cost
1
2
3
4
Total Labour Cost
Total Modification Cost
Budget Code:
SHUWEIHAT ASIA POWER COMPANY
SHUWEIHAT ASIA O&M COMPANY
DOC. NO: SAPCO / SAOM-IMS-MOC-F-
REV: 02 EFFECTIVE DATE: 30-01-2020 PAGE 6 OF 4
028
APPROVED BY: PGM AND
PREPARED BY: MA REVIEWED BY: EM AND PM
EMD
FIELD CHANGE ORDER

ORIGINATOR SIGNATURE

4. HSE Evaluation:
Health Impact:

Safety Impact

Environment Impact

Signature (HSE Engineer)

5. Performance Evaluation:

Signature (Performance Engineer)

6. Production Manager – Remarks

Signature (Production Manager)

7. Engineering Manager – Remarks


SHUWEIHAT ASIA POWER COMPANY
SHUWEIHAT ASIA O&M COMPANY
DOC. NO: SAPCO / SAOM-IMS-MOC-F-
REV: 02 EFFECTIVE DATE: 30-01-2020 PAGE 7 OF 4
028
APPROVED BY: PGM AND
PREPARED BY: MA REVIEWED BY: EM AND PM
EMD
FIELD CHANGE ORDER

Signature (Engineering Manager)

8. Plant General Manager - Remarks

Signature (Plant General Manager)

9. SAPCO – Remarks

Signature (SAPCO)

10. Remarks - Field Change order is closed.

Signature (Engineering Manager / Production Manager)

You might also like