Question Calculate Rate Analysis For Size Stone Masonry (SSM) in CM 1:6 in Foundation Sol

Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

Rate Analysis for SSM Cement mortar = CM

Question Calculate rate analysis for size stone masonry (SSM) in CM 1:6 in foundation

Sol:- Consider first = 10cum Unit = 1cum


a) Materials = quantity b) Labour = quantity in no's
1 Cement 0.57 -17bags Head mason half
2 sand 3.42cum Mason 10
3 Aggregate 12.5cum Mazdor 15

NOTE:
For size stone masonry in founation the stones
Therefore it is considered as 25% for 10cum.
25/100 x 10 + 10 = 12.5 cum. 25/100 x10
2.5 + 10 = 12.5 cum

Calculation of materials :
Volume of mortar for 10cum is 4.0 cum ( mentioned in SR Book)
1 Cement = 4/ 7 x 1 = 0.57cum
( Volume of 1 bag cement= .0347) cement - 1
No.of cement bag =0.57/0.347 =17 bags sand - 6

2 Sand = 4/7 x 6 = 3.42cum

Sl.No Particulars Quantity Unit rate Total Amount in Rs.


a Materials
cement 17 bags Rs. 350/bags 5,950
Sand 3.42cum Rs.1350/cum 4617
Aggregate 12.5cum Rs.750/cum 6875
17,442

b Labours
Head mason 1/2 Rs.600/day 300
Mason 10 Rs500/day 5000
Mazdor 15 Rs.300/day 4500
9800
Lumpsum (LS) 1/2%(a+b) 137
9937

c Add 1% water chargers = 1/100 x (a+b) = 17,442+9937


.01 x 27379 = 273.79 app 274

d Add 10% overhead profit = 10/100 x ( a+b+c)


.1 x ( 27653) = 2765

Net total amt = a+b+c+d = 30418

rate per unit for 10cum = 30418/10 = 3041/cum