Aracterization of Waste in Projects
Aracterization of Waste in Projects
Aracterization of Waste in Projects
projects *
ALFRED0 SERPELL
Department of Construction Engineering and Management, Catholic University of Chile,
Santiago, Chile
ADRIANO VENTURI & JEANETTE CONTRERAS
School of Civil Construction, Catholic University of Chile, Santiago, Chile
1 INTRODUCTION
Since the beginning of a construction job, projectkte management has to deal with
many factors - most of them caused by their own actions or inaction - that nega-
tively affect the construction process, producing different types of waste that can
convert a good ’to be’ project into a bad ‘it was’ project. In most cases, construction
managers do not know or recognize the factors that produce waste nor have they
measurements of their importance. It can be said that most of the factors are not eas-
ily visible. Thus, the identification of these factors and their causes, and the rneas-
urement of their importance is a useful information that would allow management to
act in advance to reduce their negative effects.
During the last 5 years, consulting services have been provided by a consulting
group at the Department of Construction Engineering and Management of the
Catholic University of Chile, to more than 40 construction sites that have started
programs to improve their site performance, most of them successfully. Seventeen of
these construction sites were high rise building construction projects and were se-
lected for studying purposes.
This consulting experience has generated a great amount of information on wasted
resources and time in building construction projects. The information obtained has
been processed to study the types of waste that have occurred during construction
work, and their relative importance.
67
68 A. Serpell et al.
actions to reduce any identified waste. Supporting information from visual observa-
tions and, sometimes, from other parallel studies, is also incorporated in the qualita-
tive analysis.
The information provided by work sampling presents some limitations that should
be considered. The most important are as follows:
- It does not show clearly and precisely the origin of waste;
- It only measures work time utilization, but it doesn’t directly provide production
rates, which should be measured in other ways;
- It doesn’t provide measurements of waste of materials or equipment.
Despite these limitations, the information obtained using the described approach
has been extremely useful to achieve the stated objectives. The application of judge-
ment and experience allows consultants to identify and detect situations that are pro-
ducing waste and to point out the main causes that are producing them.
Figure 1 presents the construction production process on which this work has been
based. The proposed model is an open and dynamic system inside an environment
that conditions its status and behaviour. Part of this environment is controllable by
the system but other factors are outside of its control.
The main and most critical components of the construction process as portrayed in
the figure, are:
This study deals with the identification of the most relevant factors that produce
waste of productive time in building construction works. This waste comes from
flow activities, conversion activities and management activities. Their occurrence is
generally manifested by two common construction situations: work inactivity and in-
effective work. Figure 2 shows the classification adopted in this study after review-
ing the information collected from the building construction projects.
The classification shown in the figure presents some limitations that should be
considered:
-Slow work: This waste of time is related to the efficiency of processes, con-
struction equipment, and personnel. Then it is difficult to measure it because it is first
necessary to know the optimal efficiency that could be reached, which is not always
possible;
- Rework: Not always is the result of labor ineffectiveness; uncontrolled problems
like weather conditions, earthquakes, etc. also result in rework, although they can be
prevented.
The most important causes of wasted time identified by the study were classified as
shown in Figure 3.
Characterization of waste in building construction projects 7 I
Waiting time
Idle time
Traveling
Resting
Physiological needs
Reworking
Working slowly
Inventing work
Figure 2. Categories of wastes of productive time.
Lack of resources
Flows
Lack of information
Inapropriate method
Isad allocation
Decision making
CAUSES Poor distribution
Ineffective control
This section presents a summary of the most relevant results obtained from the
analysis of information.
Characterization of waste in building construction projects 73
pected result is the low value of rework, a factor that has been observed more critical
that is shown here. One possible explanation of this outcome is the fact that work
sampling is not the most appropriated tool to detect and measure this type of waste.
The causes that were found accountable of the waiting time, are presented in Fig-
ure 6. The graphic displays the total frequency of occasions where each factor was
identified as responsible of waiting conditions. Overmanning clearly was the most
critical factor, which is consistent with other observations. There is a general agree-
ment that Chilean building construction projects normally have more people than
needed, especially unqualified people. Foremen like to have a surplus of people to
face potential risks in their work.
Figure 7 shows the factors that are responsible for idle time. The most important
factors by far are: lack of supervision and overmanning. The lack of supervision has
two components:
-Workers stop when they are not controlled; a cultural and educational related
problem;
- Workers cannot work because they are waiting for instructions that supervisors
should give them.
Overmanning also produces idle time when there are more workers than work to
do, a common problem as mentioned before.
Finally, the main causes of travelling time are presented in Figure 8. Again, over-
manning appeared as the most frequent factor, followed by lack of supervision,
workers’ attitude, materials supply and site working conditions.
Characterization of waste in building construction projects 75
equipment -
aste
Nn mntive
Figure 11. Cause-effect diagram for the main causes of construction waste.
7 CONCLUSIONS
The information provided in this chapter can be very valuable for site managers in
many ways. First, they will be able to inform themselves about the main waste fac-
tors in construction work. Thus they may become better informed managers, who
know what are the problems they face, a requisite to solve any problem. Second, they
Characterization of waste in building construction projects 77
can then focus their attention on these potential risks of unproductive time and act ef-
fectively to reduce both the risks and their impacts.
Planning is the key managerial function that should be used to be effective in re-
ducing or eliminating these waste factors. Most of the factors shown in Figure 11 are
clear demonstrations of a lack of adequate planning. Resources not available, super-
vision not available or inadequate, poor layout distribution, overmanning, lack of
progress, poor allocation of work, are all planning deficiencies.
As reported by Serpell et al. (1995) project planning faces several problems in
construction. The most frequently are related to a poor definition of job objectives,
insufficient use of computer planning systems and the reduced availability of plan-
ning and control data. What might be the main problem is the lack of time that site
managers have to plan. Generally, they are assigned to the project team a short time
before the project starts. Later, after the project is under execution, traditional priori-
ties and habits restrict their available time for planning. These problems has also
been addressed by Howell & Ballard (1994).
Then, to be effective in addressing these problems, planning should be an activity
of every site manager, from project managers to foremen. Although professionals
normally have received planning instruction, general foremen and foremen have not.
Then we need to educate and train our first line managers, to make them able to carry
out effective planning.
The major planning focus at this level should be on short-term planning. Most of
the wastes that take place at construction sites on day to day operations are the result
of lack of effective short-term planning. A simple, but effective tool to carry out
Short-term planning has been used successfully in construction works as shown by
Serpell(l993).
Finally, this work, still underway, contributes in that it is a systematic attempt to
observe and measure wastes in construction processes. Outcomes of the study will
help in the understanding of the nature of the construction production process. This
understanding is necessary to create a much needed theoretical framework of con-
struction.
ACKNOWLEDGEMENTS
REFERENCES
Howell, G. & Ballard, G. 1994. Implementing Lean Construction: Stabilizing Work Flow. 2nd.
Annual Conference of the International Group of Lean Construction, Santiago, Chile.
Serpell, A., Crovetto, J. & Seymour, D. 1995. A Current Vision of Construction Management
Practices in Chile. Unpublished paper submitted to the CIB Working Commission 65 Organi-
zation & Management of Construction Symposium to be held in Glasgow, Scotland, 1996.
Serpell, A. 1993. Construction Operations Management (in Spanish), Ediciones Universidad
Catdica de Chile, Santiago, Chile.