Unit 1 Estimation of Earthwork: Structure
Unit 1 Estimation of Earthwork: Structure
Unit 1 Estimation of Earthwork: Structure
Structure
1.1 Introduction
Objectives
1.2 Estimation of Earthwork in Road and Railway Track
1.2.1 Calculating Cross-sectional Areas of Road Formations
1.2.2 Computing Volumetric Quantities of Earthwork along a Road Alignment
1.3 Estimation of Earthwork in Canals
1.4 Specifications of Earthwork in Roads, Rail Roads and Canals
1.5 Computation of Earthwork in Building Foundation Trenches
1.6 Summary
1.7 Answers to SAQs
1.1 INTRODUCTION
The types of earthwork that most commonly are to be dealt with by practicing
civil engineers comprise cutting and filling in the construction of embankments,
road and rail formations, canals; and in the foundations of a building as well as
finishing upto below floor levels. A good grounding in mensuration forms the
basic skill that every civil engineer should possess to be able to compute the
quantities involved in every type of earthwork. A reasonably developed faculty of
imagination is a welcome asset to comprehend the drawings pertaining to any
type of earthwork in order to be able to calculate the quantities with ease.
Objectives
After studying this unit, you should be able to
• calculate the earthwork, filling and cutting separately, that goes into
the making of a piece of work : road, rail track, canal, and a building,
• comprehend the various modes of mensuration that can be employed
in these calculations, and
• conceptualise the basic knowledge about the general specifications
that must be followed to bring any such earthwork to the standard
requirements.
5
Estimating and
Quantity Surveying-I 1.2.1 Calculating Cross-sectional Areas of Road Formations
Figure 1.1 shows a simple (typical) cross-section of road (or rail) formations
wholly in cutting : the same figure, when reversed vertically about line 1-3-4-6
represents the cross-section totally in filling. Herein the side slopes
(1 : z1 and 1 : z2) are taken different from each other as a generalization – usually
in simple cases, while the soil is homogeneous, z1 = z2 = z (say). Knowing the
formation width, depth of cutting (or height of filling), and side slopes the
sectional areas (A), as explained in Figure 1.1, works out to be :
(b × h) + z h2 . . . (1.1)
Note : z1 (or z2) is the side slope–Generally z1 = z2 = z
z1 h b z2h 6
G L
1 z1 2 5 z2
1 1
h
Road Formation
3 4
b
Cross sectional area, A of 1-3-4-6-1 = (Area 2-3-4-5) + (Area 1-2-3) + (Area 4-5-6)
1 1
= (b × h) +2 (z1h)h + 2 (z2h)h
= (b × h) + (zh)2—if z1 = z2 = z
sz ⎡ b⎤
= ⎢h − 2s ⎥
(s + z) ⎣ ⎦
1 ⎡ b ⎤ ⎡ sz ⎛ b ⎞⎤
Hence, Area ABJ = ⎢h − 2s ⎥ ⎢ (s + z) ⎜h − ⎟⎥
2 ⎣ ⎦⎣ ⎝ 2s ⎠⎦
z
= [2sh − b]2
8s ( s + z )
1 ⎛ 2hs + b ⎞ ⎡ z (2hs + b) ⎤
Hence, area DFN = ⎜ ⎟⎢ ⎥
2 ⎝ 2 s ⎠ ⎣ 2 ( s − z) ⎦
z
= (2 sh + b) 2
8 (s − z) s
7
Estimating and Therefore,
Quantity Surveying-I
z z
Total area A = (2 sh − b) 2 + (b × h) + (2 sh + b) 2 . . . (1.2)
8s (s + z) 8s (s − z)
s
1
Figure 1.3 : Cross-section of Road Formation in Filling (in Embankment) in a Hilly Terrain
with Marked Cross-slope of the Ground
Figure 1.4 presents the simplest case of a road section in a hilly region : in
actuality BC may not always equal to CD, and calculations will have to be
different as discussed below :
Area in filling = Area ABC,
Area in cutting = Area CDE
AG z1 AG z1
= , or = , or AG = z1 × h1
BG 1 h1 1
AG s AG z1 × h1
and = , or FG = =
FG 1 s s
BF = BG – FG
z1 h1 ⎡ z ⎤
= h1 − = h1 ⎢1 − 1 ⎥
s ⎣ s⎦
1 1 ⎡ z1 ⎤
∴ Area ABF = AG × BF = (z1 × h1 ) h1 ⎢1 − s ⎥
2 2 ⎣ ⎦
1 b ⎡ z1 ⎤
Area CBF = × b1 BF = 1 × h1 ⎢1 − s ⎥
2 2 ⎣ ⎦
∴ Area ABC (Filling) = Area ABF + Area CBF
1 ⎡ z1 ⎤
= ⎢1 − s ⎥ h1 [z1 h1 + b1]
2 ⎣ ⎦
1 ⎡ z1 ⎤ 2
= ⎢1 − s ⎥ [z1 h1 + h1 b1] . . . (1.3)
2 ⎣ ⎦
and, Area CDE (Cutting) = Area DEH + Area CDH . . . (1.4)
EI z
= 2
DI 1
EI z 2
or = , or EI = z 2 h2
h2 1
8
EI s EI z 2 h2 Estimation of
and, = , or HI = = Earthwork
HI 1 s s
z 2 h2 ⎛ z ⎞
HD = ID − IH = h2 − = h2 ⎜1 − 2 ⎟
s ⎝ s ⎠
1
∴ Area DFH = × IE × HD
2
1 ⎛ z ⎞
= z 2 h2 × h2 ⎜1 − 2 ⎟
2 ⎝ s ⎠
1
and, Area CDH = × b2 × HD
2
1 ⎛ z ⎞
= b2 × h2 ⎜1 − 2 ⎟
2 ⎝ s ⎠
1 ⎛ z ⎞
∴ Area CDE (i.e., from Eq. 1.4 ) = × h2 ⎜1 − 2 ⎟ ( z 2 h2 + b2 )
2 ⎝ s ⎠
1 ⎛ z2 ⎞ 2
= ⎜ 1 − s ⎟ ( z2 h2 + b2 h2 ) . . . (1.5)
2 ⎝ ⎠
L
Average cross-slope of the ground ⇒ 1 : s E
I
H
1
h1z1 s z2 h2
1
Formation level
B b1 C
G
s b2 D
z1 h2z2
1
h1 1 F
4
1
2
1 1 : 2⇒
1
G 2 ⇒1 : 2 2.8 m
1
12 m
2 6.0 m 6.0 m
3
2 2
= (2 × 4 × 2.8 − 12) 2 + 12 × 2.8 + (2 × 4 × 2.8 + 12) 2
8 × 4 ( 4 + 2) 8 × 4 ( 4 − 2)
Example 1.2
K J Formation level
L
M B H
C D E
.5 P
:2
1
Formation = 12m
G A N
Note : J is the projection of the mid-point on to the hilly slope of the formation width BE.
Figure 1.6 : Cross-section of a Hilly Road : Partly in Cutting and Partly in Banking (Filling)
(Example 1.2)
10
Solution Estimation of
Earthwork
To arrive at the required elements of Eqs. (1.3) and (1.4), some calculations,
with reference to Figure 1.6, are being made as follows :
PK 1 1
JD = 0.4 m, = =
JK s 5
JK 6
∴ PK = = = 1.2 m
s 5
BP = PK − KB = 1.2 − 0.4 = 0.8 m
JD BP BP
Also, = =
DC BC BD − DC
0.4 0 .8
∴ =
DC 6 − DC
which gives,
DC = 2 m
IE 1 1 EC
Further, = = ; or IE =
EC s 5 5
But, EC = 6 m + CD
= 6 + 5 JD = 6 + 5 × 0.4
=8m
8.0
∴ IE = GH = = 1.6 m
5
Now, with reference to the overall cross-slope of the hill, we can write :
FH 1
=
CH 5
FH 1 HE + EC
or = , or FH =
HE + EC 5 5
FH 1 HE
Also = , or FH =
HE 1.5 1.5
HE + EC HE
Hence, =
5 1 .5
HE + 8.0 HE
or, =
5 1.5
12
∴ HE = = 3.42 m
3 .5
3.42
FH = = 2.28 m
1 .5
AM 1 AM 1
= , also =
MC 1.5 MB 2.5
MC MB
∴ AM = =
5 2 .5
MB + BC MB
or, =
5 2 .5
where, BC = BD – CD
= 6.0 – 2.0 = 4.0 m 11
Estimating and MB + 4 MB
Quantity Surveying-I ∴ =
5 2.5
which gives, MB = 4.0 m
4 .0
Thus, AM = = 1 .6 m
2 .5
We have by now calculated the required data for use in the above
mentioned formulae, and the information is summed up as under :
z1 = 2.5; s1 = 5; h1 = AM = 1.6 m; b1 = BC = 4.0 m
1⎛ z ⎞ 2
Therefore, Area in cutting = ⎜1 − 1 ⎟ [ z 2 h2 + b2 h2 ]
2⎝ s⎠
1⎛ 1 .5 ⎞ 2
= ⎜1 − ⎟ [1.5 (2.28) + 8 × 2.28]
2⎝ 5 ⎠
1
= (0.7) (26.03) = 9.11 m 2
2
1⎛ z ⎞ 2
and, Area in filling = ⎜1 − 1 ⎟ [ z1 h1 + b1 h1 ]
2⎝ s⎠
1 ⎛ 2.5 ⎞ 2
= ⎜1 − ⎟ [ 2.5 (1.6) + 1.6 × 4]
2 ⎝ 5 ⎠
1
= (0.5) (12.8) = 3.2 m 2
2
1.2.2 Computing Volumetric Quantities of Earthwork along a
Road Alignment
A civil engineer (or the customer: the work executing agency, or the owner) is
ultimately interested in knowing the volumetric quantity of earthwork for which
arrangements are needed to be made, and payments made as per the agreement
entered between the parties. In general, there are three principal methods of
computation that are used, namely :
(a) Average cross-sectional area method,
(b) Mid-sectional area method, and
(c) Prismoidal formula method.
Average Cross-sectional Area Method
As the name of the procedure indicates the average cross-sectional area (A)
is computed between a given length (l) of the road to be multiplied by ‘l’
(the distance between the end sections), to obtain the volume of
earthwork (V) enclosed as shown in Figure 1.7. This Figure gives a
simplified case of a stretch of road that is fully in cutting and characterized
by a uniform longitudinal grade. In practice the end sections may be
composed of both the filling and cutting – in that case, again the average of
filling and cutting areas, respectively, are to be considered and multiplied
by “l” to obtain the respective volume of earthwork. It is to be understood
that ‘l’ is the regular chainage length at which cross-sections are profiled;
12
and any additional cross-sections are recorded at places where the Estimation of
Earthwork
longitudinal formation line registers a change in slope or the ground profile
(in longitudinal direction) shows natural changes in grade. Such additional
cross-sections help one to attain a better accuracy in the computation of
volumes of earth by changing the values of ‘l’ appropriately at such
locations as mentioned above. The view will change in its contours, as can
be easily understood, according to whether the road is entirely in filling or
partly so.
Cro
E ss-
s ect
ion
al a
r ea
1:z
EF
G
F H H= A
b z 2
2 G 1: h
2
A
zh
1
1:
C
are ro ss-s
z
a, A ec
B C ti o n a
D
=A l zh
1 1
B D
b 1:
1 z h
C 1
A +A
1 2 ×l
Volume between the end sections = V =
2
A +A
Average cross-sectional area = A = 1 2
2
Figure 1.7 : Isometric View of a Road, Fully in Cutting, with End-section ‘l’ Metres Apart
= (b1 h1 + z h12 )
[In compound cases we can have side slopes as z1 and z2; and
not z1 = z2 = z.]
∴ Average area of cross-section along the length (l) of the road stretch,
A1 + A2
A=
2
And, the required volume of earthwork,
13
Estimating and
⎛ A + A2 ⎞
Quantity Surveying-I V =⎜ 1 ⎟l
⎝ 2 ⎠
(b1 h1 + z h12 ) + (b2 h2 + z h22 )
= ×l . . . (1.6)
2
It may again be pointed out, the areas A1 and A2 can as well be
calculated through the use of graphical constructions.
These computations can be tabulated as shown below for the ease of
recording and inspection, and quick totalling up (its format can be changed,
say, if z1 ≠ z2 etc.) :
Quantity of
Consecutive Chainages
Area of Side Triangle,
Height or Depth
(m2)
(m)
(m)
(A)
In In
Cutting Filling
It is quite evident that the grand total of last two sub-columns gives the
required quantity of earthwork in cutting and embankment (i.e. filling),
respectively.
Mid-sectional Area Method
In this method, the required volume of earthwork is calculated by
considering the area of cross-section profiled at the mid-point (Am) of length
‘l’ of the road stretch. Or, it is calculated as shown below :
Let the bottom width of the mid-section be = bm
Height (or depth) of the section be = hm
h1 + h2
∴ hm =
2
Am = b × hm + z hm2
A survey was conducted for the proposed road through a given area, and
following data recorded :
Chainage 0 25 50 75 100 125 150 175
(m)
RL of Ground 104.0 104.40 104.55 104.80 105.10 105.80 105.60 105.10
(m)
RL of Proposed – – – – 104.80 – – –
Formation (m)
Proposed Rising Gradient of 1 m in 150
Gradient of
Road
Chainage 200 225 250 275 300 325 350
(m)
RL of Ground 104.70 104.70 104.10 103.80 103.80 104.40 103.70
(m)
RL of Proposed – – – – – – –
Formation
(m)
Proposed Falling Gradient 1 m in 200
Gradient of
Road
[Note : RLs of proposed formation at chainage 100 m is prefixed herein to meet some
field requirements, whereas RLs at other chainages are to be calculated as per the
proposed gradient of the road.]
16
Figure 1.8(a) : Determination of Formation Levels; and hence Depth of Cutting and Height Estimation of
of Embankment at Chainage Points (Example 1.3) Earthwork
105.5 105.6
Ground Line
104.3 104.4
R.L.
Ground Line
105.3
L1
R.L.
104.13
Formation Line L2
Formation
105 105.13
Line
105.1
104.0
Chainage
25
Ox = 14.06 m x = 10.94 m
Chainage 1 2
X4 = 7.35 m
Enlarged Profile;
Chainage 150 to 175
After the ground profile is drawn, comes the turn of drawing the formation
line as per the proposed grade/grades over the various stretches of the
alignment. In this particular example it has been arranged to let the line pass
through the given obligatory point as shown in the Figure 1.8. RLs of the
longitudinal formation line at various chainage points can then be read off
from the graph or can be calculated as per the gradient of the line – the
latter being a more accurate procedure.
Knowing, by now, the RLs of the ground and the corresponding formation
line, one can calculate the required depth of cutting or filling (as the case
may be) at various chainage points, and enter the figures appropriately as
shown in the Figure. As is observed by inspection, the present formation
line intersects the ground profile at two points (L1 and L2) – it necessitates
determining the chainages of these intersection points (where, obviously,
there will neither be cutting nor filling involved) to allow computing
earthwork between the intersection point and the adjacent chainage points,
respectively, for better accuracy of estimation work. Figure 1.8 also depicts
graphical constructions (to enlarged scale) to determine the chainages
(RDs, i.e. reduced distances in the terminology of surveying and levelling)
of these points, L1 and L2 – 14.06 m (0 + 14.06), and 167.65 m
(150 + 17.65), respectively. For the sake of still higher accuracy (which,
generally, may not be required at all in actual field conditions), however,
one can arrive at these figures by calculations as well. Assuming the two
triangles (to the right and left of point L1 in Figure 1.8 – enlarged profiles,
to be similar, one can write :
0.13 0.1
= , where x1 + x2 = 25
x1 x2
0.1 0.1
or x2 = x1 ; or 25 − x1 = x1
0.13 0.13
or 0.13 × 25 − 0.13 x1 = 0.1 x1
0.13 × 25
or x1 = = 14.13 m ( ≈ 14.06 m)
0.23
17
Estimating and
Quantity Surveying-I
∴ x2 = 25 − 14.13 = 10.87 m (≈ 10.94 m)
Assuming suitable rates for earthwork in cutting and filling, say, Rs. A and Rs. B
18
per m³, respectively, one can calculate the cost of total earthwork, as shown Estimation of
Earthwork
below :
Abstract of Estimated Cost of Earthwork for Road
Item Particulars Quantity Unit Rate Per Amount
No. (Rs.) (Rs.)
1 Earthwork in 605.51 m3 A m3 (605.51) A
Cutting
2 Earthwork in 2584.29 m3 B m3 (2584.29) B
Filling
Total = [6.05.51 A + 2584.29 B]
= C (say)
⎛ 3 ⎞
Add 3% of contingencies ⎜= × C ⎟ = D (say)
⎝ 100 ⎠
⎛ 2 ⎞
Add 2% of Work-charged Establishment ⎜= × C ⎟ = E (say)
⎝ 100 ⎠
Grand Total = (C + D + E)
1:z 1:z h
FSL = Full Supply Level
Canal Bed
zh b zh
Free Board
FSL
Bank Bank
Canal Bed
Figure 1.10 : Canal in Partial Cutting in a Plain Area – Spoil Banks Functioning as Water
Retaining Banks
b1 b2
1:z
z 1:z h
1:z
1
1:z Canal Bed
GL
b1 b2
zh zh y
GL
b1 b2
1 : z1 1 : z1 1 : z1 1 : z1
h
GL
1 : z2 1 : z2
z1 h z1 h y
Canal Bed
z2 y b z2 y
21
Estimating and (c) Canal (in Plain Area) – Partly in Cutting and Partly in Filling
Quantity Surveying-I
Figure 1.11 : Canal Bed at Ground Level, Above GL or Below GL
With reference to Figure 1.11(a), when the canal bed is at ground level (GL), the
quantity of earthwork (V) between two adjacent chainage points (distance, l,
apart) can be computed as,
⎡ ⎛1 ⎞⎤
V = ⎢ (b1 × b2 ) h + 4 ⎜ × zh × h ⎟ ⎥l
⎣ ⎝2 ⎠⎦
Similarly, when the canal section is totally in cutting (Figure 1.9), the required
quantity, is calculated as
⎡ ⎛1 ⎞⎤
V = ⎢b × h + 2 ⎜ zh × h ⎟ ⎥ l
⎣ ⎝2 ⎠⎦
or, V = [b × h + z h 2 ] l . . . (1.8)
For a canal section totally above the GL, we can write for the total filling
(Figure 1.11(b)),
⎡ ⎛1 ⎞ ⎛1 ⎞ ⎤
V = ⎢ (b1 + b2 ) h + 4 ⎜ zh × h ⎟ + 2 ⎜ zy × y ⎟ + by + ( b1 + 2 zh + b2 + 2 zh ) y⎥ l
⎣ ⎝2 ⎠ ⎝2 ⎠ ⎦
For a more general case, canal section partly in cutting and partly in filling, as in
Figure 1.11(c), one can write :
Volume in cutting,
VC = (by + z2 y 2 ) l . . . (1.10)
⎡ ⎛1 ⎞⎤
VF = ⎢(b1 + b2 ) h + 4 ⎜ z1 h × h ⎟⎥ l
⎣ ⎝2 ⎠⎦
= [(b1 + b2 ) h + 2 z1 h 2 ] l . . . (1.11)
It is obvious that while tabulating the results, for a given length of work, the
columns of tabulation framework will be provided according to the formula used
for the computational purposes.
Example 1.4
22
With reference to the construction of a distributory (branch of a canal), Estimation of
Earthwork
whose proposed bed slope is 1 in 5000, following survey data was made
available for a portion of the work :
The bed width is to be maintained at 4.5 m with the section being fully in
banking. The top width of the side banks is to be kept as 2.25 m, with the
side slopes at 1 : 1.5. The full supply depth of water is 1.25 m with a
free-board of 0.5 m.
Borrow pits are to be dug on both sides of the distributory leaving a clear
distance of 5 m from the toe of the bank, limiting the depth of borrow pits
to 30 cm, with width that may exceed 1.5 m. As the lift (to be paid to the
contractor) of earthwork increases with the height of the embankment, it is
required to workout the quantity of earthwork (filling) in stages of 1.5 m
from the GL.
Prepare a bill of quantities, and an abstract of cost of earthwork – rate for
each item depends on the required specifications (detailed in contract
documents).
Solution
The proposed bed levels and the height of filling from the GL to the bed (at
each chainage) are calculated as follows :
[Note : For every 300 m longitudinal distance there is a fall of 0.06 m in the bed level (at
the given slope of 1: 5000).]
Figure 1.12 presents the canal cross-section (which is totally in filling) with
essential details. Herein head lead, distance from the centre-line of a
borrow pit to the centre-line of the adjacent bank, is indicated which is a 23
Estimating and function of y (which in turn varies from chainage to chainage as shown in
Quantity Surveying-I
the above table) – this head lead is to be paid for as a carriage over which
the earth is to be carried along the horizontal distance.
24
Estimation of
Earthwork
Figure 1.12 : Canal Section (with Borrow Pits) – Example 1.4
Using Eq. (1.9), without the multiplier “l”, one can calculate the sectional
areas (filling) at various chainages.
Full Sectional Area (in Filling) at Chainage “o”, A0 (Figure 1.12)
= [(2 × 2.25) 1.75 + 1.5 (1.75) 2 + 1.5 (1.75 + 1.5) 2
+ (2 × 2.25 + 2 × 1.5 × 1.75 + 4.5) × 1.5]
= [(7.875 + 4.593 + 15.843 + (14.25) × 1.5]
= 12.468 + 15.843 + 21.375
= 49.686 m 2
Area ABCD (i.e. upto line DC –1.5 m above GL – from top line AB)
– for full canal cross-section (Figure 1.13),
⎡ ⎛1 ⎞⎤
= 2 ⎢2.25 × 1.75 + 2 + ⎜ × 2.625 × 1.75 ⎟⎥
⎣ ⎝2 ⎠⎦
= 2 [3.937 + 4.593]
= 17.06 m2
2.25 m
A B
0.25 m
F
E
1.75 m
1 : 1.5
1.5 m
D C
0.375 y
1.75 × 1.5 = 2.625
Here, y = 1.5 m
1.39 m
.5
:1
1.75 m
1
0.36 m
D
C
1.39 × 1.5 = 2.085 m
1.5 m
y = 1.14 m
1 : 1.5
1.75 m
1.50 m
0.28 m
D1 C1
D C
2.625 m 1.5 m y = 1.78 m
0.42 m
1 ⎧⎡ 4.5 ⎤
+ ⎨ ⎢ 2 × 2.625 + 2.25 +
2 ⎩⎣ 2 ⎥⎦
⎡ 4.5 ⎤⎫
+ 2 ⎢ 2 × 2.625 + 2.25 + + 0.42 ⎥ ⎬ × 0.28
⎣ 2 ⎦⎭
= 2 [3.937 + 4.593]
+ [5.25 + 2.25 + 2.25 + 5.25 + 2.25 + 2.25 + 0.42] × 0.28
26
= 17.06 + 5.577 Estimation of
Earthwork
= 22.637 m2
Area ABEF (AB to 3 m above GL)
⎧1 ⎫
= 2 ⎨ [2.25 + (0.795 + 2.25 + 0.795)] × 0.53⎬
⎩ 2 ⎭
= [6.09] × 0.53
= 3.227 m2
Full Sectional Area at Chainage ‘900 m’, A900 (Figure 1.16)
2.25 m B
A
0.37 m
F E
0.555 m
1 : 1.5
1.5 m 1.75 m
0.12 m
2.625 m
C1
D1
D
C
0.18 m
1.5 m y = 1.62 m
1 : 1.5
1.61 m 1.75 m
1.5 m
0.14 m
D C
2.25 m 1.5 m
2.415 m y = 1.36 m
1 : 1.5
1.5 m 1.75 m
1.55 m 0.20 m
D C
1.5 m
2.325 m
y = 1.30 m
28
⎡1 ⎤ Estimation of
= 2 ⎢ {(2.25) + (2 × 0.075 + 2.25)} × 0.05⎥ Earthwork
⎣2 ⎦
= 0.232 m2
Full Sectional Area at Chainage “1800 m”, A1800 (Figure 1.19)
= 12.468 + 1.5 (1.75 + 1.54) 2 + (14.25) × 1.54
= 12.468 + 16.236 + 21.945
= 50.649 m2
A 2.25 m
B
0.29 m
F E
0.435 m
1 : 1.5
1.75 m
1.5 m
0.04 m
2.625 m
D1 C1
D
C
1.5 m
0.06 m
y = 1.54 m
Chainage Total Area Total Area Col. (2) – Mean Length of Quantity of
between Top between Top Col. (3) Area Reach Earthwork
of Bank to of Bank to 3 m = Col. (5) ×
1.5 m above above GL Col. (6)
GL
(m) (m2) (m2) (m2) (m) m3
1 2 3 4 5 6 7
Total = 28,041 m3
1 2 3 4 5
0 1.31 – – –
Total = 2187 m3
Borrow Pits
Borrow pits (as per the given design) are made (on both sides of the
distributory as given in the problem) which are not to exceed 30 cm in
depth. This, therefore, is treated as work of surface excavation, and is paid
for in m2.
30
It is usual, unless otherwise stated, to assume the cross-sectional area of a Estimation of
Earthwork
borrow pit (that falls on either side of the earthwork) to be equal to half the
cross-sectional area of the distributory at a given chainage. Therefore, we
have :
Chainage Sectional Area (m2) Width of Borrow Average Width Total Surface
of a Borrow Pit = Pit, of Pit Area of Pits
(Total Cross- Col. (2) = Col. (4)
sectional Area of x = ×length
Depth of Pit
Distributory) / 2
(m) (m) (m)
(m2)
1 2 3 4 5
0 49.684 24.84
= 24.84 = 82.8
2 0.3
300 41.241 68.73
= 20.62
2
Average of 2 × 81.42 × 1800
600 56.524 94.2 values in = 293112
= 28.26
2 Col. (3)
900 52.588 87.63 569.93
= 26.29 = 81.42
2 7
1200 46.356 77.27
= 23.18
2
1500 44.946 74.90
= 22.47
2
1800 50.649 84.4
= 25.32
2
By now, all the required quantities stand calculated, and the following bill
of quantities is made for working out the cost of each item of work and of
the total work :
Knowing the rates for different items of work, as per applicable Schedule of
Rates, Abstract of Estimated Cost of Works of Example 1.4 can be tabulated
according to the following Proforma.
Abstract of Estimated Cost of Works of Example 1.4
Item No. Particulars Quantity Unit Rate Per Amount
Total
Add 3% for Contingencies
Add 2% for Workcharged Establishment
Grand Total (say, to be rounded off)
[Note : It is to be noted that, unlike in road/rail work, canals incorporate falls along their
alignment. Therefore, at those chainages, where a fall is positioned, that particular
cross-section is to be considered twice – once with the cross-section at the chainage
previous to it, and secondly with the one at the following chainage – to compute the
earthwork.]
33
Estimating and As is well understood, cuttings as per design vis-à-vis a given work, shall
Quantity Surveying-I
be done from top to bottom – in no case shall under-cutting or under-mining
be allowed to be indulged in. The sides of all excavations shall be dressed
up or trimmed, and the bed (bottom) shall be levelled (or graded if required)
as per the intended design.
In the case of hard rock, that requires blasting to be resorted to, the cutting
depth (for the sake of measurement) shall be measured upto the actual
levels if it was an unavoidable outcome of the operation.
Excavation over an area (in soft or hard soil) shall consist of excavation for
basements, water tanks, septic tanks, etc.; excavation in foundation trenches
that are more than 1.5 m in width or/and 10 m2 in plan; and also those
excavations that are more than 1.5 m in breadth (width) or/and 10 m2 in
plan and exceeding 30 cm in depth. If these items of earthwork in cutting in
firm soils, the sides of the trench shall be cut vertical upto a depth of 2 m
from the bottom. In case of greater depth, it is important to widen the trench
by providing steps of 50 cm on either side after every 2 m from the bottom,
or allow side slopes of 1 : 4. For soft, loose or slushy soils either the width
of the steps shall be increased suitably or sides given appropriate slope or
the soil is shored up. The bed of the excavation (after the designed profile is
achieved) shall be consolidated by watering and ramming. Soft/defective
areas/spots shall be dug out and filled with levelling concrete.
All excavated earth, it is to be ensured, shall not be dumped within 1 m of
the edges of trenches, and shall be disposed off as per the agreement
between the contractor and the executing agency.
If different rates of payment are to be paid to the contractor according to the
different classes of earth to be excavated, it is customary not to execute any
work except, at first, the work to be paid at the lowest rate till the whole
quantity at this rate has been billed – however, exceptions can be made by
the authorized officer according to difficult/hard field conditions. The same
procedure shall be followed for each succeeding higher rates as per varying
classification.
The rate of payment for excavation/cutting must include lead and lift, as
well as dressing the bed and sides of the cutting. Spoil from a given cutting
shall be carried into the adjoining embankment (if any) upto the usual lead
distance.
Filling
Before any earthwork (including cutting) is commenced, the entire area
(falling under the designed profile) shall be cleared of shrubs, grass, etc.
and trees and saplings; and the rubbish shall be removed upto distance
falling beyond the boundary of the area under clearance. The roots of the
trees shall be extracted from upto a minimum of 60 cm below the ground
level or a minimum of 30 cm below the formation level, whichever is lower
– all the hollows shall be filled up with earth, levelled and rammed. In case
Archaeological monuments fall within the area (or adjacent to it), necessary
fencing around these be provided as a measure of protection.
Masonry pillars shall be erected at appropriate points in the area to
delineate the earthwork area, as well as serve as benchmarks. Necessary
earthwork profiles shall be set up with the help of bamboo posts, pegs and
34
strings – or “burjis” shall be erected to indicate the required formation Estimation of
Earthwork
levels. All this arrangement shall be maintained during the execution of the
work.
Ground levels shall be taken at adequately close intervals to also
incorporate local pits, mounds, and undulations.
Earth from cutting (if of required quality) shall be directly used for filling,
and no claim for double handling of earth shall be accepted. Filling shall be
done in regular horizontal layers – each layer not to exceed 20 cm in
height. All this earth has to be free from grass, rubbish, roots; and lumps
and clods exceeding 8 cm in any dimension have to be broken down. Each
layer that is laid shall be consolidated by ramming (and for certain works
water is to be used in this process). The surface of the finished filling work
(embankment) shall be neatly dressed. Finished formation levels shall be
built upto higher than the designed levels (say, by an allowance of 10% of
the total depth of filling) to allow future settlement for ordinary
consolidated fills. This allowance could be reduced to only 5% for fills
consolidated by heavy mechanical machinery. However, for works
consolidated by heavy mechanical machinery with optimum moisture
content being maintained, no such settlement allowance shall be made.
Rates for making payments shall cover cost of lead upto, say, 300 m; and a
lift of 1.5 m from the borrow pits. It is usual to use borrow pits for
measuring the quantity (m3) of earthwork used in filling; and no
measurements of finished work are used for payments. That is why sakhis
(i.e. dead man/tell tale/matams) – earth pillars are left out to help take
accurate measurements of earthwork dug out for the intended embankment
– these are removed after measurements are made; and the spoil is used up
in the embankment. It is understood that any excess quantity (i.e. greater
than given by the profile of the embankment) shall be excluded from the
borrow pit-based quantity.
In exceptional cases, where the basis of measurement has been agreed upon
to be based on the actual embankment profile, all measurements shall only
be taken after the bank has fully settled.
Wherever feasible, in case of high banks, continuous longitudinal earth
bunds (of appropriate dimensions) shall be made on the outer edges of the
top of the bank, and also cross bunds (at designed intervals) to impound
rain water (if any) in order to expedite the consolidation of the embankment
– it will entail extra payment of the contractor, at ordinary earthwork rates.
Lead for purposes of payment shall be measured from the centre line of
bank at right angles to itself. In situations where borrow pits may not be
situated opposite to embankments (where their spoil is intended to go in),
lead shall be measured from the centre of gravity of the fill to the centre of
gravity of the borrow pits.
Filling in approaches to bridges, in the backing of abutments and in
spandrils and haunches, shall proceed evenly with the masonry.
Earthwork Measurements : General Considerations
For every earthwork, length, breadth and depth shall be measured upto the
nearest cm if measurements are taken by tape. In the case of measurements
being taken by means of staff and level, the reading shall be noted correct to 35
Estimating and 5 mm depth of cutting, and height of filling also correct to 5 mm – the
Quantity Surveying-I
cubical measure (contents) shall be worked out to the nearest two places of
decimal of a cubic metre.
For excavations in trenches (or from borrow pits), that lie in a fairly
uniform ground, the measurement of cutting shall be made as usual. In
borrow pits, diagonal ridges, cross ridges, or dead-man (positions fixed by
the competent authority) shall be left for measurements after the completion
of the work. Deductions for such ridges and deadmen are to be made
appropriately to arrive at the correct quantities. However, no such
deductions are made if these are meant to be removed later on for the use of
this earth in the work profile itself.
When ordinary soil and hard rock are mixed in nature, the different kinds of
rock shall be stacked separately to be measured up – the net quantity of
each type shall be given by the measured loose quantity after applying
appropriate loosening factor (when in stacked form compared to the
unloosened volume).
In case the ground is not uniform, levels shall be taken before the start of
excavation work, after due site clearance, as well as after the completion of
work – and the quantity shall be worked out accordingly. For filling as well
this principle will apply equally.
Lift shall be measured from the ground level. Excavation upto 1.5 m depth
below the ground level and depositing the excavated material on the ground
shall comprise this lift. However, extra lift shall be measured in units of
1.5 m or part thereof (unless otherwise specified). While the ground slopes
in one direction, the inherent lift in the lead shall be accounted for wherever
appropriate.
30 cm Thick Brickwork
(Compound Wall)
DPC
Plinth
Ground Level
40 cm
50 cm 80 cm
Foundation Trench
20 cm 50
20 cm 60
20 cm 70
30 cm Lime Concrete (LC)
100 cm
37
Estimating and 30 cm Brickwork above GL
Quantity Surveying-I Centre Line
40-cm
Plinth
Coarse
Figure 1.21 : Plan of the Foundation Trench for a Straight Compound Wall (Figure 1.20)
Considering a foundation trench for a wall enclosing a rectangular area as shown
in Figure 1.22 – with uniform trench width and depth all around – one can discuss
two methods of calculating earthwork in excavation, viz, Centre-line method,
and Long-wall and Short-wall method.
b Short Wall
A B
E F
J K
Long Wall
l1
Centre Line
M L
H G
D C
l2
b/2
Figure 1.22 : Centre-line, Long and Short Wall, Method of Computing Earthwork
Centre-line Method
38
Dashed line EFGH (Figure 1.22) is the centre-line of the trench, dividing Estimation of
Earthwork
the width (b) of the trench into two equal halves. The total length of the
centre-line
= EF + FG + GH + HE
= 2 (EF) + 2 (FG)
= 2 (FG + EF)
⎡⎛ b⎞ ⎛ b ⎞⎤
= 2 ⎢⎜ l1 − 2 × ⎟ + ⎜ l2 + 2 × ⎟ ⎥
⎣⎝ 2⎠ ⎝ 2 ⎠⎦
= 2 ( l1 + l2 )
Taking the uniform depth of cutting all around as h, and width as b (as
shown in this Figure), and total Volume of excavation = [2 (l1 + l2 ) × b × h] .
In cases where the width (b) of the trench is not uniform, even though the
depth (h) is uniform, this method of Volume computation is not applicable.
Long-wall and Short-wall Method
In this Figure there are two long walls (BC and AD), and two short walls
(JK and ML) whose widths are same (b), and depths same (h). Volume of
excavation (V) can be worked out as given below :
Excavation in two long walls = 2 [l1 × b × h]
and, Excavation in two short walls = 2 [l2 × b × h]
∴ V = 2 [l1 b h + l2 b h]
= [2 (l1 + l2 ) × b × h],
Example 1.5
39
Estimating and X
Quantity Surveying-I a b
e W f
X
W = Grilled 30 cm
Window = 1m × 1m
Wall
4. 0 m
5.0 cm
5.0 m
D, Open Door = 1m × 2m
h g
D
d c
:
10 cm Projection
RCC (1 : 2 : 4) 5 cm thick lintel with
5 cm bearing on either side
W
2. 5 m
30 cm
DPC, 2.5 cm thick
Stone Masonry
in Mud
2.5 thick CC
Plinth
5 cm Thick LC
GL 10 cm 40 cm
50 cm GL
5 cm 5 cm
10 cm
7.5 cm thick Earth Filling
60 cm 1 : 3 : 6 LC
40
0.6 m Estimation of
5 + 2(0.3/2) + 2(0.6/2) = 5.9 m 0.5 m
E 0.4 m
Earthwork
F
J
I
60 cm
50 cm
40 cm
L K
H G
SAQ 1
(a) A road has been aligned along a given direction; the relevant survey
data, and also the proposed formation levels are tabulated as under :
Distance 0m 30 m 60 m 90 m 130 m 150 m 180 m
(Chainage)
NSL (Natural 111.87 m 111.87 m 115.62 m 114.50 m 116.31 m 113.90 m 115.20 m
Surface Level)
Proposed 111.87 m 111.87 m 111.97 m 112.07 m 112.203 m 112.203 m 112.203 m
Formation Level
Formation level at the 10th chainage point is 107.0 m; and the road is
in a downward gradient of 1 in 150, upto the chainage point 14, and
then the gradient changes to 1 in 100 (downwards). Formation width
of the road is 10 m, and side slopes of the banking are 2 : 1 (H : V).
Take the length of each chain 30.0 m.
Prepare a estimate of the earthwork at the rate 70/– per % m3.
Find also the cost of turfing the side slopes at the rate of
20/– per % m2. 43
Estimating and (d) A road in cutting has formation width of 4.0 m; side slope, s = 2;
Quantity Surveying-I
distance between two chainage points = 300 m; h1 = 1.5 m; and
h2 = 1.1 m. Using the trapezoidal formula, compute the volume of
earthwork in cutting.
1.6 SUMMARY
Earthwork is road/rail/canal – both as cutting and banking (filling) – is very often
being encountered by a practicing civil engineer. Also, earthwork in the
foundation trenches of buildings, as well as filling upto just below the floor level
forms the very first item in the estimate of quantities. The whole process of
computation demands mensurational skills and practice.
Every earthwork, as much as any other item of work, has to follow
general/specific specifications to bring the work to the desired standards.
A = (7.5 + h) h
h
7.5 m
Figure 1.24
Chainage (m) 0 30 60 90 130 150 180
Filling (m) – – – – – – –
Cutting (m) – – 3.65 2.43 4.107 1.697 2.997
2
Area (m ) – – 40.70 24.13 47.67 15.64 31.50
Mean Area – 20.35 32.42 35.90 31.66 23.57 –
(m2 )between
Chainage Points
Volume of – 20.35 × 32.42 × 35.90 × 31.66 × 23.57 × –
EW in Cutting 30 = 30 = 40 = 20 = 30 =
(m3) 610.50 972.6 1436 633.20 707.10
Figure 1.25
ac eg
=
x 20 − x
ac x
or =
eg 20 − x
2.85 x
=
0.55 20 − x
x
or 5.182 =
20 − x
or, 103.64 – 5.182 x = x
or 6.182 x = 103.64
45
Estimating and ∴ x = 16.76 m
Quantity Surveying-I
Now, the calculations after chainage 180 m are given as shown
below :
Abstract of Cost of EW
Total = 25000/–
[Note : One can include cutting (11.40 m3) and at an appropriate rate, calculate its cost as well.]
0 – – – – –
20 1.79 71.60
→
40 2.91 116.40
60 2.80 112.00
← As computed earlier –
80 2.41 96.40
←As computed earlier
46
Estimation of
200 5.37 214.8 Earthwork
Total = 1446.80 m2
47