6.E Installation Qualification (IQ) : Here You Will Find Answers To The Following Questions
6.E Installation Qualification (IQ) : Here You Will Find Answers To The Following Questions
6.E Installation Qualification (IQ) : Here You Will Find Answers To The Following Questions
6.E
Installation qualification is the documented evidence that the equipment com-
plies with the requirements made of it in terms of identity, installation, conformity
with the guidelines and documentation. Installation qualification takes place after
delivery of the equipment, at the same time as installation/assembly of the equip-
ment at the place of installation. In the case of preassembled equipment, the
installation qualification can be carried out, at least partially, at the supplier's
premises (for example: water treatment system).
During installation qualification, the equipment is tested for conformity with
the user requirements and for proper installation. During installation qualification,
the overall scope of delivery of the equipment is identified and confirmation is
given that all components of the delivery correspond to the specifications defined
in the technical specification during the planning phase. The essential elements of
installation qualification are summarised in figure 6.E-2.
In this qualification phase, particular attention is placed on the technical docu-
mentation, the scope of which is to be described precisely during design qualifica-
tion and which is to be provided by the supplier (see chapter 6.D Design qualifica-
tion (DQ) and chapter 4.F Technical documentation). To ensure a good customer-
supplier relationship, it is recommended that the exact time of provision of the
technical documentation be defined. It is not always advisable to deliver this at the
same time as the equipment, as foreseeable (planned) adaptations also involve
changes to the documentation. Figure 6.E-3 shows an overview of the scope of
the technical documentation.
Acceptance at the supplier's premises (Factory Acceptance Test, FAT ) is
optional. Acceptance after delivery of the pharmaceutical process equipment (Site
Acceptance Test, SAT ) is legally required and includes all characteristics approved
in the user specifications and specified in the technical specifications and order.
U. Reuter GMP Manual (Base) © Maas & Peither GMP Publishing (1)
6 Qualification
(2) GMP Manual (Base) © Maas & Peither GMP Publishing U. Reuter
6.E Installation qualification (IQ)
6.E
are summarised in a single document.
C. Oechslein GMP Manual (Base) © Maas & Peither GMP Publishing (3)
6 Qualification
Record compiled
(Date/signature)
1. Scope
This test protocol is an integral part of the qualification plan in accordance with qualifica-
tion master plan 0915 and is valid at the Ixberg site for the qualification of new and exist-
ing manufacturing and control equipment for pharmaceutical products. It does not re-
late to the qualification of computer systems. This document must also be used if the
qualification (or parts thereof ) is to be carried out by external companies or consultants.
2. Test item
Subject of the test is all energy and utilities connections of the facility to be qualified.
3. Performance of test
Using the manufacturer's documentation (e.g. certificates), it must be checked if all prod-
uct contact materials, lubricants and other quality relevant materials meet the require-
ments of the DQ. The materials actually used, including the surface properties (e.g.
roughness, or inertisation) are to be entered in the test list.
(4) GMP Manual (Base) © Maas & Peither GMP Publishing C. Oechslein
6.E Installation qualification (IQ)
4. Test list
4.1
6.E
4.2
4.3
4.4
4.5
Lubricant
4.8
4.9
4.10
4.11
4.13
4.14
4.15
4.16
C. Oechslein GMP Manual (Base) © Maas & Peither GMP Publishing (5)
6 Qualification
5. Test result
❍ Accepted
(6) GMP Manual (Base) © Maas & Peither GMP Publishing C. Oechslein
6.E Installation qualification (IQ)
Record compiled
(Date/signature)
6.E
(Date/signature)
1. Scope
This test protocol is an integral part of the qualification plan in accordance with quali-
fication master plan 0915 and is valid at the Ixberg site for the qualification of new and
existing manufacturing and control equipment for pharmaceutical products. It does
not relate to the qualification of computer systems.
This document must also be used if the qualification (or parts thereof ) is to be carried
out by external companies or consultants.
2. Test item
Subject of the test is all utilities connections of the facility to be qualified.
3. Performance of test
All utilities connections available on the equipment are
• identified and labelled (in accordance with SOP 03567),
• compared with the DQ specifications
• compared with the manufacturer's documentation
• professionally connected to the corresponding house connections.
C. Oechslein GMP Manual (Base) © Maas & Peither GMP Publishing (7)
6 Qualification
4. Test list
(in accordance
Actual value
Test feature
Acceptance
Connected
with § DQ)
Signature
Labelling
criterion
Date
6.E
Energy form
4.1
4.2
4.3
4.4
4.5
4.6
4.8
4.9
4.10
4.11
4.12
5. Test result
❍ Accepted
Figure 6.E-5 IQ test protocol 2: Utilities (energy and media) supply (cont.)
(8) GMP Manual (Base) © Maas & Peither GMP Publishing C. Oechslein
6.E Installation qualification (IQ)
Record compiled
(Date/signature)
6.E
(Date/signature)
1. Scope
This test protocol is an integral part of the qualification plan in accordance with qualifi-
cation master plan 0915 and is valid at the Ixberg site for the qualification of new and
existing manufacturing and control equipment for pharmaceutical products. It does
not relate to the qualification of computer systems. This document must also be used if
the qualification (or parts thereof ) is to be carried out by external companies or consult-
ants.
2. Test item
Subject of the test is all measuring and control points of the facility to be qualified.
3. Performance of test
All M&C points available on the equipment are
• identified and labelled (in accordance with SOP 03568),
• compared with the DQ specifications
• compared with the manufacturer's documentation
• assessed as to whether calibration is required,
• initial calibration is carried out in accordance with SOP 98765.
Figure 6.E-6 IQ test protocol 3: Measuring and control technology points and
initial calibration
C. Oechslein GMP Manual (Base) © Maas & Peither GMP Publishing (9)
6 Qualification
4. Test list
(in accordance with § DQ)
Acceptance criterion
Require calibration
Initial calibration
Actual value
Test feature
Signature
Labelling
6.E
Date
M&C point
4.1
4.2
4.3
4.4
4.5
4.6
5. Test result
❍ Accepted
Figure 6.E-6 IQ test protocol 3: Measuring and control technology points and
initial calibration (cont.)
(10) GMP Manual (Base) © Maas & Peither GMP Publishing C. Oechslein