Pre-Installation
System
© Siemens, 2002
10093864
07558641
07414803
03078565
© Siemens, 2002
All documents may only be used for rendering
services on Siemens Healthcare Products. Any
document in electronic form may be printed
once. Copy and distribution of electronic docu-
ments and hardcopies is prohibited. Offenders
will be liable for damages. All other rights are re-
served.
2002
2 Copyright / Version / Disclaimer
1Copyright / Version / Disclaimer
Copyright
“© Siemens, 2002“ refers to the copyright of a Siemens entity such as Siemens Aktienge-
sellschaft - Germany, Siemens Shenzhen Magnetic Resonance Ltd. - China, Siemens
Shanghai Medical Equipment Ltd. - China, Siemens Medical Solutions USA Inc. - USA
and/or Siemens Healthcare Diagnostics Inc. - USA.
Document Version
Siemens reserves the right to change its products and services at any time.
In addition, manuals are subject to change without notice. The hardcopy documents corre-
spond to the version at the time of system delivery and/or printout. Versions to hardcopy
documentation are not automatically distributed. Please contact your local Siemens office
to order current version or refer to our website http://www.healthcare.siemens.com.
Disclaimer
Siemens provides this documentation “as is“ without the assumption of any liability under
any theory of law.
The installation and service of equipment described herein requires superior understand-
ing of our equipment and may only be performed by qualified personnel who are specially
trained for such installation and/or service.
requirements. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4
Required Aids and Tools . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4
Additionally Required Documents. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4
Ceiling Substructure . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4
Notes . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5
Safety information . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5
Product-specific Remarks . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5
General information . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6
All tools, measuring equipment and aids, with the exception of the standard installation tool
kit, are listed and specified in the Service Tools Catalogue.
1. Only the case with the chain hoists is needed from this installation kit.
• Project plan
• Installation Protocol
Ceiling Substructure 0
• Prior to beginning the installation, make absolutely sure that the ceiling substructure
(e.g. Unistrut) has been properly installed.
Notes 1.1
Safety information 0
When performing work steps and tests, the general safety guidelines for medical products
must be observed.
Product-specific Remarks 0
Conventions
General information 0
Limit value for over 3 mm over 3 mm over over over over over
the nominal to 6 mm to 6 mm 30 mm to 120 mm to 400 mm to 1000 mm 2000 mm
range 120 mm 400 mm 1000 mm to to
2000 mm 4000 mm
Permissible ± 0,5 mm ± 1 mm ± 1,5 mm ± 2,5 mm ± 4 mm ± 6 mm ± 8 mm
tolerance
These tolerances apply for all dimensions listed in these instructions as long as no other
tolerance is expressly listed next to the value.
Screw material
Nominal thread
diameter Brass
Iron/steel per DIN 267
CuZn alloy
Hardness rating 4.6 4.8 5.8 8.8 10.9 12.9
M3 0,5 0,67 0,83 1,3 1,9 2,2 0,62
M 3.5 0,76 1,0 1,3 2,0 2,8 3,4 0,95
M4 1,1 1,5 1,9 3,0 4,2 5,1 1,4
M5 2,2 3,0 3,7 6,0 8,4 10,1 2,8
M6 3,8 5,1 6,4 10,2 14,4 17,3 4,8
M8 9,5 12,6 15,8 25,3 35,6 42,7 11,9
M 10 18,7 24,8 31,1 49,8 70,0 84,0 23,3
M 12 32,9 43,8 54,8 87,6 123,3 147,9 41,1
If no other information is provided, use the corresponding torque values for hardness rating
8.8 when checking torque values.
A tolerance of ± 10% is permitted for torque values.
Preparations 0
• Take the two longitudinal rail holders (Fig. 2 / p. 7) out of the transport crate for the
chain hoists (Fig. 3 / p. 7).
EH111509-111201-00-02
NOTE The two dimensions: 2400mm to the end of the rail and 97
mm to the outside edge of the rail (reference point), starting
from the orientation point in each instance, absolutely must
be observed.
The 2nd line on the drilling template (97 mm distance from
the OP) corresponds to the outside edge of the foot-end lon-
gitudinal rail.
• Project the mark on the drilling template (Fig. 5 / p. 8) for the outside edge of the longi-
tudinal rail onto the ceiling sub-construction (Unistrut rails) using a plumb bob or a laser.
- The distances are each measured from the outermost edges.
97 mm
OP
FOOT END
EH111509-181202-00-06
• Insert the Unistrut nuts into the sub-construction (e.g. Unistrut) to install the rail holders
for the rail .
• Loosely secure one rail using two rail holders in the Unistrut rail with two M10x70 Allen
screws each.
EH111509-101201-00-03
• Insert additional Unistrut nuts into the Unistrut rails accordign to the planned number of
mounint points(Fig. 7 / p. 9).
• Insert a corresponding number of tabs (Fig. 7 / p. 9).
• Secure the longitudinal rails with the clamping pieces (Fig. 7 / p. 9) and M10x35 Allen
screws.
• Insert the orange, self-adhesive colored strips included in the shipment into the 3 longi-
tudinal rails.
• It may be necessary to realign the longitudinal rail per the Project Plan.
• Remove the two longitudinal rail holders.
• Installation of the middle longitudinal rail is performed in the same way as the foot-end
longitudinal rail.
Note: The end of the pinion rack must be flush with the end of the longitudinal
rail on the operator side. The pinion rack is about 15 cm too short on the end of
the back.
• Determine the required spacing to the middle longitudinal rail; to do this, place the two
spacer gauges (Fig. 9 / p. 10) at the ends on the top of the longitudinal rails.
Abstandslehre
spacer
EH111509-260302-00-02
EH111509-300103-00-03
• Install the mounting bracket (1/Fig. 11 / p. 12) with one M10 Allen screw on the on-site
sub-construction (Unistrut rail).
1
2
5
EH111509-300103-00-05
• Tighten the clamping pieces on all three longitudinal rails (without torque).
1
3
2
EH111509-300103-00-04
• Aling the rotating laser beam (Fig. 13 / p. 14) approx.10 to 20 cm under the bottom
edge of the rail; to do this, loosen the two knurled screws on the base plate and move
the base plate with the laser accordingly.
EH111509-300103-00-06
• Determine the lowest point of the longitudinal rails with the rotation laser; to do this,
- place a ruler on the bottom of the longitudinal rail.
- At all 21 mounting points (or 9 additional mounting points for the “Longitudinal Rail
Extension” option), read the distance to the laser mark and transcribe this to the
dimensional drawing (1/Fig. 15 / p. 15).
- Determine the lowest point of the longitudinal rails.
- Starting from the lowest point, adapt all other mounting points with the shims pro-
vided; tolerance: +/-1mm over the entire length of the rail.
EH111509-181202-00-07
97 mm
2400 mm
EH111509-021202-00-02
1
T • Install an end stop in each end of all the other rails (2/Fig. 16 / p. 16).
3
1
EH111509-111201-00-01
NOTE The toothed belt is no longer needed for Aristos FX Plus sys-
tems.
• To install a second end stop, insert the drilling template (1/Fig. 19 / p. 18) in each of the
ends of the longitudinal rails.
• Secure the spacer gauge (300 mm) (2/Fig. 19 / p. 18) on the drilling template with 2
Allen screws (3/Fig. 19 / p. 18).
• Use the rotation laser or a plumb bob to project the back of the stop (Fig. 20 / p. 19)
onto the floor.
• The distance of the reference point to the table orientaiton point (2400 mm) absolutely
must be maintained; because of this, the table must be moved accordingly by the
dimension X (Fig. 20 / p. 19).
• To install a second end stop, insert the drilling template (Fig. 22 / p. 20) only at the
head-end of each transverse carriage.
• Secure the spacer gauge (423 mm) on the drilling template using two Allen screws.
Advance Note 0
Preparation 0
• Check the extension kit (Part No.: 75 58 658) for completeness per the following table.
Installation 0
• Insert one rail connection piece (1/Fig. 25 / p. 23) into the profile on the top of the longi-
tudinal rail extension (2/Fig. 25 / p. 23).
2
1
EH111509-181202-00-02
T • Secure the extension with 6 clamping pieces as shown in the following figure.
EH111509-181202-00-03
• Position the 4 spacer gauges shipped along with the standard rails at the beginning and
end of the extension as shown in the following figure and align the middle and head-end
extensions to it.
Abstandslehre
spacer
EH111509-260302-00-02
EH111509-181202-00-04
T • Secure the rail connection pieces in the standard rails with two M8 set screws each
(1/Fig. 30 / p. 26).
EH111509-181202-00-05
• The prepared and installed pinion rack must be located in the middle longitudinal rail
extension.
• Check for flush positioning of the pinion racks in the longitudinal direction (no gap