Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                

Annex "A" Test Procedures For High Strain Dynamic Testing (Pda) Principles of High Strain Dynamic Testing

Download as pdf or txt
Download as pdf or txt
You are on page 1of 11

,.

Annex"A" of D.O. No.~s. 2016


Page 1 of 11

ANNEX "A"

TEST PROCEDURES FOR HIGH STRAIN DYNAMIC TESTING (PDA)

PRINCIPLES OF HIGH STRAIN DYNAMIC TESTING

The High Strain Dynamic Tests are performed using the Pile Driving Analyzer (PDA)
PAK, PAL-K or PAX Model manufactured by Pile Dynamics Inc. (POI), USA, which
utilizes the Case Method~ to obtain quick quantitative results at the site. Force and
velocity records are continuously viewed from the PDA monitor for each blow to
evaluate data quality, the maximum hammer transfer energy delivered to the pile, pile
integrity, pile stresses, and other pertinent information.

During the test, the PDA machine processes the record almost instantaneously and
calculates values with some simplifying assumptions using the Case Method. The
results can be viewed on the screen to indicate values such as 1) maximum mobilized
capacity for the specific blow (RMX); 2) the pile integrity factor (BTA); 3) maximum
average pile compressive stress (CSX); 4) maximum delivered energy (EMX), etc. PDA
testing is based on the principles of One-Dimensional Wave Mechanics (lDWM).

TEST PILE PREPARATION

The top length, defined as the "test area" (1.5 to 2.5 pile diameter extension plus 300
mm surface dearance for installation of gages) should be encased with steel casing to
avoid damaging the pile head and shall be free from water, dirt or other debris. The
concrete at the pile top impact area must be flat or level. (See Figure 1)

••

t=-- --.."...
11m III1lkER I'lATE llOmm JItIa(
CUSHIOII CPIl\'IIlOll !"-r'l
~ 11m _ 'IIIlH DOWELS
'It£IlEI I>-l'IlE DI'IlIEltR

BORED PILE PREPARATION FOR PDA TESTING


_-1
,.

Annex "A" of D.O. No. ~'J .5. 2016


Page 2 of 11

Hammer guide should be assembled to ensure the same and concentric impact of the
hammer unto the pile.

Four windows (about 200mm2), one each at four sides of the shaft at 90 degrees apart
must be cut open in the steel casing to expose the concrete to allow installation of
gages.

A steel cap cover shall be placed on top of the pile cushion for uniform impact
distribution and to hold the pile cushion in place during testing. The size of the pile
cushion should be roughly the same as the diameter of the pile while the steel cap
cover should tightly fit the pile top.

TEST REQUIREMENTS

Prior to the dynamic test, the testing Engineer must be provided with soil boring data,
shaft installation records, concrete properties (strength, etc) and details regarding the
anticipated dynamic loading equipment.

The steel or concrete ram weight for testing the bored pile shall have a weight of at
least 1.5% to 2% of the required ultimate pile bearing capacity as per plan.

At the time of testing, the bored pile shall have attained its 28 days compressive
strength. Waiting period is essential to allow the previously disturbed soil to set-up and
develop a natural bonding with the pile.

To fully activate the ultimate capacity of the pile, settlement should be:

Skin quake = 2.54 mm; shaking at the skin or pile shaft caused by dynamic
wave or velocity

Toe quake = 0/120; shaking at the pile toe caused by dynamic wave or
velocity

EQUIPMENT

1. Pile Driving Analyzer (PDA) with four (4) Strain transducers and two (2)
Piezoelectric accelerometers
2. CAPWAPsoftware program
3. Surveying instrument to monitor the pile settlement after every blow
4. Hammer
5. Hammer guide
6. Cushion (50mm thick timber)
7. Steel plate cap cover
8. Crane
9. Computer
,.

Annex "A" of D.O. No. 3'1 .5. 2016


Page 3 of 11

PILE TESTING PROCEDURE

Field instrumentation involves the attachment of four (4) strain transducers and two (2)
piezoelectric accelerometers on diametrically opposite sides of the pile near the top. In
general, these gages are 1.5 to 2.5 pile diameter (1.50-2.50) from the top. These are
then attached to the POA machine by connecting cables which will record the
force/Velocity traces of the wave according to the actual reactions of the pile.

When the gages have been placed in position and the Pile Driving Analyzer (POA) had
been calibrated, the input data such as Project Name (PJ), Pile Number (PN), pile length
from the location of sensor to pile tip (LE), pile cross-sectional area in sq. cm at the
transducers location (AR), pile modulus (EM), damping factor (JC), and embedded
length of pile where resistance is measured (LP), will be encoded to the POA. The Test
Engineer shall instruct the client's crane operator regarding the drop height to release
the steel ram weight to strike the test pile. The hammer shall be dropped from a
gradual height increase as instructed by the Test Engineer. Usually 2 to 3 hammer
blows will be applied. The data for each hammer blow will be viewed at the POA
monitor. The pile settlement for each blow shall be monitored at the surveying
instrument during testing.

A representative blow will be selected from the total number of blows having the largest
value of maximum delivered energy (EMX), a 100 % pile integrity factor (BTA) and a
force-velocity proportionality equal to 1. The data shall be subjected for further analysis
using the Case Pile Wave Analysis Program (C4PWAP)2.

ACCEPTANCE AND REJECTION

The acceptance and rejection of a pile shall be based on the result of CAPWAPanalysis.
Pile which attained the required ultimate pile bearing capacity and with impedance
changtl of less than -10% will be accepted. Piles with impedance change of greater
than -10% are considered to have serious defects and need further evaluation by the
Geotechnical Consultant and the designer. Piles which failed to attain the required
ultimate pile capacity and/or piles with impedance change of greater than -25% shall be
automatically rejected.

REPORTS

• Description of test conducted including methodology, equipment and


photographs.
• Complete test data of all trials/blows such as height of fall, mobilized capacity,
wave speed, BTA and pile settlement, etc .
• Complete CAPWAPresult.
• Evaluation and Recommendation.

1 The "Case Metho(r refers to the methods developed at the Case Institute of Technology
beginning in the 1960's. The objective is to calculate pile bearing capacity in real time for every
hammer blow from pile top force and acceleration measurement. Today, the term "Case Method"
refers to both measurement techniques and interpretations of soil effects, pile stresses, pile
integrity and hammer performance by means of a Pile Driving Analyzer.
·.

Annex"Jj{' of D.O. No.~s. 2016


Page 4 of 11

:z C4PWAp, Case Pile Wave Analysis Program, is an iterative tool mainly used for capacity
determination. CAPWAPcombines measured force and velodty data with wave equation analysis
to calculate the soil resistance force acting on the pile. After the data had been obtained in the
field by PDA, this software program tries to match the measured force and/or velocity by
numerically modeling the soil and pile system.

3 A negative (-) impedance change suggests a decrease in pile cross-sectional area, a reduction
on concrete modulus, or a combination of both. A pOSitive (+) impedance change suggests an
increase in cross-sectional area or bulging.
Annex"B" of D.O.No.~s. 2016
Page 5 of 11

ANNEX "B"

CROSSHOLE SONIC LOGGING (CSL) TEST PROCEDURE FOR BORED PILES

PRINCIPLES OF CROSSHOLE LOGGING (CSL) TESTING

The Crosshole Sonic Logging (CSL) method is a downhole variation of the ultrasonic
pulse velocity test using Crosshole Analyzer (CHA) manufactured by Pile Dynamics, Inc.,
USA or its equivalent. Ultrasonic transmitter and receiver probes are lowered down on
the parallel tubes in the concrete (bored pile) to be tested, and the transit time of an
ultrasonic pulse through the material between the tubes is measured by a data
acquisition system. Water in the tubes provides acoustic coupling to the surrounding
material. A continuous series of measurements is made as the probes are raised up
from the tubes, providing a vertical profile of signal transit time.

The ultrasonic pulse velocity (UPV) is a function of concrete modulus, density, and
Poisson's ratio, so the uniformity of the material can be assessed from the uniformity of
the CSL profile. Irregularities such as soil inclusions, low modulus concrete, and voids
will be readily detected and located by the increase in pulse transit time that they
cause.

TEST PILE PREPARATION

Piles intended for Sonic Logging test are installed with 50mm inside diameter G.I. pipe
access tubes at quadrant location. Minimum thickness of the tube is about 5mm. These
tubes are preplaced as attached to the reinforcing cage prior to concreting. The tubes
are installed continuously from bottom to the top of the pile and parallel to each other.
The bottom ends of the tubes are provided with sealed cap or plugged to avoid
intrusion and contamination of concrete during pouring and vibration. The tubes are
fitted with robust couplings for extension to ensure that they remain watertight and to
prevent slurry and grout ingress during pouring and curing of the concrete. The top of
the tubes are plugged or secured to prevent entry of foreign objects, which could block
the tubes prior to testing.

EQUIPMENT

1. Crosshole Analyzer (CHA)


2. Transmitter and receiver probes
3. Meter-wheel device
4. Computer
5. GI pipes (min. thickness=5mm)
·.

Annex "8"of D.O. No. .1' .5. 2016


Page 6 of 11

PILE TESTING PROCEDURE

Prior to actual testing, all the access tubes were first checked to ensure that the tubes
are not contaminated or blocked, and that they are reasonably straight, clean and free
from any internal defects for the clear passage of the probes. This is done using a
dummy probe to test access and at the same time record length of each tube.
The temperature of the water in the tubes is also checked. If the temperature exceeds
the operating limits of the apparatus at 60°C (as when the concrete is only a few days
old) then the test will have to be postponed until the pile has cooled down.

The access tubes are identified in the field as numbers 1, 2, 3, & 4. These are
numbered sequentially in the clockwise direction.

Prior to the test, the tubes are filled to the top with clear water. To ensure good
acoustic coupling between the probes and the water In the tubes, the probes are
cleaned and made fully saturated before each immersion.

The transmitter and receiver probes are then inserted inside the first two selected tubes
for logging. If all the tubes are clear (not blocked), the tests normally start from the
bottom progressing to the top. On the other hand, if any or all the bottoms of the tubes
are blocked (i.e., bottoms are not in same elevation), then, tests are conducted starting
from the top to bottom. A specific scan would then stop at the higher elevation of the
two tubes being used, and this will now be reflected as the bottom of the specific record
(but does not necessarily be the bottom of the pile). Measured pile length will therefore
be shorter than actual. The cables of the probes are then made to run over the meter-
wheel device for depth encoding. (See figure 2)

CROSSHOLE lOGGING (CSl) TEST


TYPICAL SITE SETUP AND TYPICAL SCAN CONFIGURATION

SCHEMATIC OF SYSTEM SETUP

mEL~
1ICCf!S~

SCHEMATIC OF
TYPICAL SCAN CONFIGURATION

Before commencing the logging, data FklItJut as to the project details, pile name, scans
10 (I.e., 2-3, 1-2, etc.), are inputted as part of the record.
..
Annex"B" of D.O. No.~s. 2016
Page 7 of 11

The equipment is then armed and recording is done by steadily pulling the probe cables
simultaneously over the depth-encoding device. A speed of ascent appropriate to the
method adopted for ultrasonic pulse generation is maintained until the probes are
above the top of the pile. Enough time is allowed for any electronic data processing to
finish before ending the recording process.

This process is repeated in all combinations of the access tubes. A total of six (6) scans
or sonic maps are generated for the four access tubes of each pile.

ACCEPTANCE AND REJECTION

Pile is acceptable as to integrity if the results show no irregularities such as soil


intrusions, low modulus concrete and voids. If such irregularities are noted, the integrity
of piles needs to be evaluated by the geotechnical engineer/structural designer and the
Bureau of Design (for projects approved by the Central Office) for any possible
corrective measure. If the tubes are blocked and contaminated with concrete during
pouring, the DPWH shall adopt the low strain dynamic testing (PIT).

REPORTS

• Description of test conducted including methodology, equipment and


photographs.
• Complete test data (scans or sonic maps)
• Evaluation, analysis and recommendation.
·.

Annex"C" of D.O. No.~s. 2016


Page 8 of 11

Annex "C"

TEST METHODOLOGY OF LOW STRAIN DYNAMIC TESTING OR PILE


INTEGRITY TESTING (PIT):

PRINCIPLES OF LOW STRAIN PILE DYNAMIC TESTING

Low Strain Method, also referred to as a Non-Destructive Method, is an integrity test for
pile foundations, which is performed using a Pile Integrity Tester (PI7) manufactured by
Pile Dynamics Inc. (POI), USA.

Integrity testing is performed by affIXing an accelerometer to the pile top and striking
the pile with hand-held hammer with 1 to 2 Ibs mass. The acoustic wave produced by
the impact propagates down to the bottom end of the pile and the acceleration record
created from each hammer impact is integrated to velocity and displayed on the high
resolution screen of PIT. The Pulse Echo Method (PEM) records the pile top velocity as a
function of time. The Transient ResponseMethod (TRM) displays the mobility, i.e. the
ratio of frequency spectra of pile top velocity and force. The data are later transferred
to a computer for analysis and graphical output. A velocity record from a perfect pile
shaft exhibits the impact, followed by a flat zero response, until a reflection from the
toe is observed with the velocity profile similar to that of the impact event.
Variations in shape and material quality of the pile produce reflection as they return to
the surface. Surface variations are recorded until all primary reflections have been
observed. The deepest reflection is the pile toe, and the last to be observed. Given
estimates of the wave speed (c) and the pile length (L), the toe reflection is expected at
the time 2L/c after the impact.

TEST PILE PREPARATION

1. Remove the contaminated or loose materials and chip-off of the pile top to the
required pile cut-off levels. Portion of the pile top surface will be evened out using
a grinder so that the accelerometer could be attached and the hammer impact can
be applied to a very clean, flat, dry and hard surface to have a uniform hammer
impact. The test should be conducted at least 7 days after the concrete pouring of
bored pile.
2. The accelerometer should be firmly attached using a thin layer of petroleum jelly,
clay or pliable wax as bonding material in order to accurately measure the high-
frequency motion during impact and reflection.

EQUIPMENT

1. Pile Integrity Tester (PIT)


2. Hand-held hammer
3. PITPLOT
4. Computer
5. Grinder
·.

Annex"C" of D.O. No.~s. 2016


Page 9 of 11

PILE TESTING PROCEDURE

1. The PIT which is a sonic test is done by applying five (5) blows each in every
location and averaged by the PIT. This technique is useful in separating the effects
of random mechanical and electronic noise from the relevant reflections.
Instrumental hand-held hammer with 1 and 2 Ibs mass shall be used for the tests.
2. The sonic test shall be repeated four (4) times at locations diametrically opposite
sides (E, W, N, 5), so that problems associated with poor accelerometer
attachment or "unlucky" accelerometer placement or hammer hit spot will be
avoided. The acceleration record is numerically integrated to produce the velocity
signal.

3. The data are collected and further analyzed using PIT collector's processing and
enhancement facilities (PITPLOT)1.

ACCEPTANCE AND REJEcnON

Concrete bored piles with only insignificant reflections other than the pile toe and with a
clear pile toe reflection may be accepted (See Figure 3). Where no clear toe reflection
is apparent, the experienced test engineer shall state to which depth the test appears to
be conclusive. Where significant reflections from locations above the pile toe are
obselVed, a quantification of the irregularity must be conducted by the Test Engineer.
If such reflection indicates a significant pile impedance reduction, the pile must be
rejected. If the record is complex the results may be deemed questionable.
Construction records (concrete usage, grout pressure records, soil borings) may be
valuable in results interpretation or additional numerical analysis modeling may be used
to quantify the record. The results will be subjected for further review/approval by the
Implementing Office.

~ I 53.6ft.

MEASURED PILE TOP VELOCITY RECORD rOR SOUND PILE

Figure 3
..
Annex"C" of D.O. No.~s. 2016
Page 10 of 11

REPORTS

• Description of test conducted including methodology, equipment and


photographs.
• Complete test data of all trials
• Complete PITPLOTgraphical results
• Evaluation and Recommendation.

1 PITis a state-of- the- art device for integrity testing.

ZPITPLOT ~i1e Integrity Testing Plotter Program


,.

Annex "0" of D.O. No. ~S. 2016


Page 11 of 11

Annex "D"

The minimum requirements for Geotechnical Firms to perform the Pile Integrity Test
(CSL or Low Strain) and PDATest are as follows:

1. Company profile of the Geotechnical Consulting Firm


2. Certificate and proof of training attended by the Geotechnical Consultant and
Technician
3. At least five (5) years experience in pile testing of Geotechnical Consultant and
Technician duly employed by the Geotechnical Consulting Firm
4. Certification of ownership of testing equipments
6. Description of testing machinesfequipments and test methodologies.

You might also like