Bill of Quantities: Prepared By: Checked By: Approved by
Bill of Quantities: Prepared By: Checked By: Approved by
Bill of Quantities: Prepared By: Checked By: Approved by
Rate(NRs) Amount
S.N. DESCRIPTION OF WORKS UNIT QUANTITY
In figure In words
1 SITE CLEARANCE WORK Sqm 3,146.53
2 EXCAVATION WORKS
3 SOLLING WORKS
Rate(NRs) Amount
S.N. DESCRIPTION OF WORKS UNIT QUANTITY
Fairface Brick work in Superstructure with 1:1:1 Lime Sand
11.1 Surki above Gnd Floor using chimney made brick &
including 30m transportation 0 (180.00) 15,067.58 (2,712,164.30)
9'' Brickwork in 1:6 cement mortar above groung floor in
11.2 outer boundary using chimney made brick & including 30m
transportaion 0 - 15,676.25 -
Inner Brick 4'' Brickwork in 1:4 cement mortar above
11.3 groung floor using chimney made brick & including 30m
transportaion 0 - 15,676.25 -
12 PLASTERING WORKS As per instructed by Project Manager or Site engineers.
12.5mm thick (1:4) C/S plaster inside and outside building
(a) including proper curing all complete for wall surface
without celling Sqm - - -
Rate(NRs) Amount
S.N. DESCRIPTION OF WORKS UNIT QUANTITY
12.5mm thick (1:4) C/S plaster on concrete surface with (
1:4) cement mortar Sqm 700.84
18 PAINTING WORKS As per instructed by Project Manager or Site engineers.
Two coats water proof cement paint application inside and
(a) outside building with good finish as per instruction all
complete Sqm 1,674.87
Supplying and applying of two coats of approved quality
(b) and colour ready made enamel paints over one coat of
wood primer with good finish as per instruction all
complete Sqm 2,054.61
Rate(NRs) Amount
S.N. DESCRIPTION OF WORKS UNIT QUANTITY
19 HAND RAILING WORKS As per instructed by Project Manager or Site engineers.
Making and fitting 1" x 1" size square pipe railing having
height 3'-0" to 3'-0" including 3" x 4" size seasoned saal
wood handrail on top of railing and brass caping on bottom
of each square pipe of railing with 1 coat primer and 2
coats enamel paint on railing and 3 coats chapra polish on
handrail all complete Sqm 553.00
20 MS GRILL FOR WINDOW As per instructed by Project Manager or Site engineers.
Rate(NRs) Amount
S.N. DESCRIPTION OF WORKS UNIT QUANTITY
Providing and properly appling two coat of hi-tech
chemical water proofing treatment by crystallizating
prepared at site just before application by mixing 2.5
volumes of chemical to one volume of water to form
smooth paintable/brushable slurry result on two surface of Sqft 701.76
RCC slab ,well damped after properly cleaned witk wire
brush.
( B ) Water supply line / sanitary line ( Drainage ) As per instructed by Project Manager or Site engineers.
a Providing and installation of gun metal gate valve
I) NB 40mm Sets 12.00
ii) NB 25mm Sets 18.00
b Providing and installation of water supply line GI Pipes of
class A with all nessary clamps fitting etc.all complete.
NB 15mm(1/2"dia.) Cold Pipe Line r.m 385.00
NB 20mm(3/4"dia.) Cold Pipe Line r.m 275.00
NB 25mm(1"dia.) Cold Pipe Line r.m 205.00
NB 40mm(1.5"dia.) Cold Pipe Line r.m 360.00
c
Providing and installation UVC Pipe-4 Kg/sq. cm Rain
water pipes with necessary all fittings as per detail
drawings I) OD - 100 Pic 85.00
d Soil and waste pipes
I) OD-75 r.m 37.00
ii) 4 inch valve bend Kg 42.00
e Providing & installation of water pump (1.5 HP) Sets 4.00
f Providing and Installation of 1000 Lt. PVC Water Tank all Liter 4,000.00
complete as per instructed by engineers.
Total Sanitary Works -
26 ELECTRICAL WORKS
( A ) Wiring of light/fan & power points:
Following Light /Power /fan Points shall cover all
necessary conduit, PVC duct, Bottom, HDP pipe 3/22
sliver wire. as per site condition with furniture layout and
As instructed by Project Manager or Site engineers..
( make: NS stander)
Light points
Light Point with 2 no 3/22 cable & junction boxes. Points 200.00
Power Points 10A 3 pin socket Light point with 7/22 cable
&junction Boxes Points 240.00
Light fixture of Approved Brand of Wipro,Havells with CFL
( B ) bulb or Philips equivalent brand Points 115.00
( C ) Ex-Fan Points Points 15.00
( D ) Switches, Light &Power and plug in sockets (North-
West or equivalent)
Supply of materials (Modular type light switches, light and
power sockets, weather proof plug-in-power sockets as
mentioned below, 18 SWG GI metal boxes, Screw and
other necessary materials) installation, interconnection
and commissioning. As per instructed by Project Manager
or Site engineers.
a 6 A 6 gang 1 way switch Sets 35.00
b 6 A 3 gang 1 way switch Sets 25.00
c 6 A 2 gang 1 way switch Sets 20.00
Rate(NRs) Amount
S.N. DESCRIPTION OF WORKS UNIT QUANTITY
( E ) Power Cable:
Supply of materials (cables,pipe,cable shoes) & laying ,
interconnection & testing of following size of pvc insulated
Cu. cable including digging,refilling, compction & cable
termination with cable shoes of suitable size using RM 3,500.00
crimping device. As per instructed by Project Manager or
Site engineers.
Rate(NRs) Amount
S.N. DESCRIPTION OF WORKS UNIT QUANTITY
Videocon 1.5ton Air Conditioner at Mayor, Vice Mayor ,
Executive Room and Meeting Hall ( According to market
(G) price) As per instructed by Project Manager or Site
engineers.
Sets 10.00
SUMMARY OF COST
S.N. Description Amount Remarks
Two Hundred Twenty Six Million Three Hundred Fifty Three Thousand Nine Hundred
Twenty and Paisa Thirty Seven only
ABSTRACT OF COST
7 Photography
Contract information
of construction
board activities. As per Nos. 1 25000.00 25000.00
instructed by Project Manager or Site
8 engineers. Job 1 100000.00 100000.00
9
Prepared Design By: Approved By:
Checked By:
Detail Project Report (DPR) of Godavari Municipality Building Bajarbarahi, Lalitpur
ABSTRACT OF COST
10
Prepared Design By: Approved By:
Checked By:
Detail Project Report (DPR) of Godavari Municipality Building Bajarbarahi, Lalitpur
ABSTRACT OF COST
11
Prepared Design By: Approved By:
Checked By:
Detail Project Report (DPR) of Godavari Municipality Building Bajarbarahi, Lalitpur
ABSTRACT OF COST
ABSTRACT OF COST
ABSTRACT OF COST
15
Prepared Design By: Approved By:
Checked By:
Detail Project Report (DPR) of Godavari Municipality Building Bajarbarahi, Lalitpur
ABSTRACT OF COST
Main PB
Incoming
40 A, 25KA, MCCB TP Moulded-1 set.
60A TPNE Copper bus bat with hardware and
1100 volt insulating -1 set.
0-500 Volt meter Digital Static unit with
selecting device-1 set.
Outgoing 14.00 5,590.00 78,260.00
6/16/20/60 A MCB Sets 14.00 225.00 3,150.00
Distribution Box Sets
Wiring of Telephone points
Following points shall cover all necessary
conduit, PVC duct, Bottom, HD pipe etc as per
site condition with furniture layout and As
instructed by Project Manager or Site
engineers.
Supply and materials and wiring in suitable
size medium presser PVC conduit concealed/
false ceiling without any joint in middle of the
span. As per instructed by Project Manager or
Site engineers.
150.00 320.00 48,000.00
Telephone points with CAT-5 Cable. Points 75.00 4,484.00 336,300.00
56''Celling Fans Sets 150.00 234.00 35,100.00
15 watt CFL Bulbs Sets 150.00 339.00 50,850.00
25 watt CFL Bulbs Sets 100.00 489.00 48,900.00
16
Prepared Design By: Approved By:
Checked By:
Detail Project Report (DPR) of Godavari Municipality Building Bajarbarahi, Lalitpur
ABSTRACT OF COST
17
Prepared Design By: Approved By:
Checked By:
Project :- Construction of Godavari Municipality Building Bajarbarahi, Lalitpur
Quantity Estimate
Length Area (Sq
S.N Description No Breadth (m) Height (m) Quantity Remarks
(m) m)
2 EXCAVATION WORKS
Raft Footing @ 3.6m depth 1.00 3142.00 1.00 3.60 11311.20
Raft Footing @ 2m depth 1.00 5323.00 1.00 2.00 10646.00
other area except building 1 511058 511058.00
Total 533015.20 Cum
3 Solling Works
At Footing
Raft Footing @ 3.6m depth 1.00 3142.00 1.00 0.07 204.23
Raft Footing @ 2m depth 1.00 5323.00 1.00 0.07 346.00
Total 550.23 Sqm
4 Back Filling
7 P.C.C WORKS
At Footing (1:3:6)
Raft Footing @ 3.6m depth 1.00 3142.00 0.10 314.20
Raft Footing @ 2m depth 1.00 5323.00 0.10 532.30
Total 846.50 Cum
18
Prepared /Design By: Approved By
Checked By:
Project :- Construction of Godavari Municipality Building Bajarbarahi, Lalitpur
Quantity Estimate
Length Area (Sq
S.N Description No Breadth (m) Height (m) Quantity Remarks
(m) m)
Main Beam
Ground Floor
Grid along F 1.00 330.00 0.30 0.60 59.40
Grid along G 1.00 361.20 0.30 0.60 65.02
Grid along H 1.00 395.60 0.30 0.60 71.21
Grid along 23-98 65.00 15.00 0.30 0.60 175.50
Radial Secondary Beam between grid F, G &H 35.00 13.50 0.23 0.50 54.34
Grid along A 1.00 121.00 0.30 0.60 21.78
Grid along B 1.00 121.00 0.30 0.30 10.89
Grid along C 1.00 121.00 0.30 0.30 10.89
Grid along D 1.00 121.00 0.30 0.30 10.89
Grid along E 1.00 93.00 0.30 0.30 8.37
Grid along 1,2,3,20,21,22 6.00 23.00 0.30 0.30 12.42
Grid along 4-19 16.00 26.60 0.30 0.30 38.30
First Floor
Grid along G 1.00 361.20 0.50 0.70 126.42
Grid along H 1.00 395.60 0.50 0.70 138.46
Grid along 23-98 65.00 6.30 0.50 0.70 143.33
Radial Secondary Beam between grid G &H 60.00 6.30 0.23 0.50 43.47
Grid along B 1.00 121.00 0.30 0.60 21.78
Grid along C 1.00 121.00 0.30 0.60 21.78
Grid along D 1.00 121.00 0.30 0.60 21.78
Grid along E 1.00 93.00 0.30 0.60 16.74
Grid along 1,2,3,20,21,22 6.00 15.10 0.30 0.60 16.31
Grid along 4-19 16.00 18.70 0.30 0.60 53.86
19
Prepared /Design By: Approved By
Checked By:
Project :- Construction of Godavari Municipality Building Bajarbarahi, Lalitpur
Quantity Estimate
Length Area (Sq
S.N Description No Breadth (m) Height (m) Quantity Remarks
(m) m)
Inclined beams along grids 1-98 88.00 15.80 0.30 0.60 250.27
Inclined beams along grids 1-98 in between 87.00 15.80 0.23 0.50 158.08
Total Beam Work 1753.11 Cum
Lintel and sill band
Ground Floor
Wall along grid G 1.00 361.20 0.23 0.15 24.92
Wall along grid H 1.00 395.60 0.23 0.15 27.30
Slab
Ground Floor
Slab 1.00 6708.00 1.00 0.13 838.50
20
Prepared /Design By: Approved By
Checked By:
Project :- Construction of Godavari Municipality Building Bajarbarahi, Lalitpur
Quantity Estimate
Length Area (Sq
S.N Description No Breadth (m) Height (m) Quantity Remarks
(m) m)
First Floor
Slab 1.00 4703.00 1.00 0.13 587.88
Deduction of void -1.00 73.00 1.00 0.13 -9.13
Deduction of Staircase -1.00 32.00 1.00 0.13 -4.00
Second Floor
Slab 1.00 1266.00 1.00 0.13 158.25
Deduction of Staircase -1.00 32.00 1.00 0.13 -4.00
Third Floor
Slab 1.00 1266.00 1.00 0.13 158.25
Total Slab Work 1725.75 Cum
Staircase
Basement Floor
Dog -legged stair 2.00 23.76 1.00 0.20 9.50
Straight stair 0.00 1.00 1.00 0.20 0.00
Ground Floor
Dog -legged stair 4.00 23.76 1.00 0.20 19.01
Straight stair 23.00 16.00 1.00 0.20 73.60
First Floor
Dog -legged stair 2.00 23.76 1.00 0.20 9.50
Straight stair 0.00 1.00 1.00 0.20 0.00
Second Floor
Dog -legged stair 2.00 23.76 1.00 0.20 9.50
Straight stair 0.00 1.00 1.00 0.20 0.00
Slab of Ramp
Ramp slab 2.00 120.00 1.00 0.30 72.00
Grand Total RCC Work 13513.56 Cum
9 REINFORCEMENT WORK
For Column
Grid A 22.00 0.60 0.60 2.00 105.60
Grid B 22.00 0.60 0.60 5.60 295.68
Grid C 22.00 0.60 0.60 9.20 485.76
Grid D 22.00 0.60 0.60 9.20 485.76
Grid E 16.00 0.60 0.60 5.60 215.04
Grid F(36-84) 39.00 0.60 0.60 3.60 336.96
Grid F(23-35,85-98) 26.00 0.60 0.60 2.00 124.80
Grid G(36-84) 39.00 0.60 0.60 7.20 673.92
Grid G(23-35,85-98) 26.00 0.60 0.60 5.6 349.44
21
Prepared /Design By: Approved By
Checked By:
Project :- Construction of Godavari Municipality Building Bajarbarahi, Lalitpur
Quantity Estimate
Length Area (Sq
S.N Description No Breadth (m) Height (m) Quantity Remarks
(m) m)
Beam
Grid along F 1.00 330.00 0.30 0.60 495.00
Grid along G 1.00 361.20 0.30 0.60 541.80
Grid along H 1.00 395.60 0.30 0.60 593.40
Grid along Beam
Cicumferential Secondary 23-98 between grid F 65.00 15.00 0.30 0.60 22.50
Cicumferential Secondary &G Beam between grid G 1.00 205.00 0.23 0.50 252.15
&H 1.00 214.20 0.23 0.50 263.47
Radial Secondary Beam between grid F, G &H 35.00 13.50 0.23 0.50 16.61
Grid along A 1.00 121.00 0.30 0.60 181.50
Grid along B 1.00 121.00 0.30 0.30 108.90
Grid along C 1.00 121.00 0.30 0.30 108.90
Grid along D 1.00 121.00 0.30 0.30 108.90
Grid along E 1.00 93.00 0.30 0.30 83.70
Grid along 1,2,3,20,21,22 6.00 23.00 0.30 0.30 20.70
Grid along 4-19 16.00 26.60 0.30 0.30 23.94
First Floor 0.00
Grid along G 1.00 361.20 0.50 0.70 686.28
Grid along H 1.00 395.60 0.50 0.70 751.64
Grid alongBeam
Cicumferential Secondary 23-98 between grid G 65.00 6.30 0.50 0.70 11.97
&H 1.00 361.20 0.23 0.50 444.28
Radial Secondary Beam between grid G &H 60.00 6.30 0.23 0.50 7.75
Grid along B 1.00 121.00 0.30 0.60 181.50
Grid along C 1.00 121.00 0.30 0.60 181.50
Grid along D 1.00 121.00 0.30 0.60 181.50
Grid along E 1.00 93.00 0.30 0.60 139.50
Grid along 1,2,3,20,21,22 6.00 15.10 0.30 0.60 22.65
Secondary BeamGrid alongalong 4-19 between grid
East-West 16.00 18.70 0.30 0.60 28.05
Secondary Beam 1,2,3,20,21,22
along East-West between grid 4.00 15.10 0.23 0.50 18.57
Secondary Beam along 4-19North south between 10.00 18.70 0.23 0.50 23.00
grid 1 -22 1.00 456.00 0.23 0.50 560.88
Second Floor 0.00
Grid along H 1.00 395.60 0.50 0.70 751.64
Grid along C 1.00 121.00 0.50 0.70 229.90
Grid along D 1.00 121.00 0.30 0.60 181.50
Grid along E 1.00 93.00 0.30 0.60 139.50
Grid along 1,2,3,20,21,22 6.00 7.10 0.30 0.60 10.65
Secondary BeamGrid alongalong 4-19 between grid
East-West 16.00 10.70 0.30 0.60 16.05
Secondary Beam 1,2,3,20,21,22
along East-West between grid 4.00 7.10 0.23 0.50 8.73
Secondary Beam along 4-19North south between 10.00 10.70 0.23 0.50 13.16
grid 1 -22 1.00 335.00 0.23 0.50 412.05
Third Floor 0.00
Grid along C 1.00 121.00 0.50 0.70 229.90
Grid along D 1.00 121.00 0.30 0.60 181.50
Grid along 1,2,3,20,21,22 6.00 7.10 0.30 0.60 10.65
Secondary BeamGrid alongalong 4-19 between grid
East-West 16.00 10.70 0.30 0.60 16.05
Secondary Beam 1,2,3,20,21,22
along East-West between grid 4.00 6.90 0.23 0.50 8.49
Secondary Beam along 4-19North south between 10.00 6.90 0.23 0.50 8.49
grid 1 -22 1.00 121.00 0.23 0.50 148.83
Inclined beams along grids 1-98 88.00 15.80 0.30 0.60 23.70
Inclined beams along grids 1-98 in between 87.00 15.80 0.23 0.50 19.43
7975.752 Sq m
Total Form Work for Beam
22
Prepared /Design By: Approved By
Checked By:
Project :- Construction of Godavari Municipality Building Bajarbarahi, Lalitpur
Quantity Estimate
Length Area (Sq
S.N Description No Breadth (m) Height (m) Quantity Remarks
(m) m)
Slab
Ground Floor
Slab 1.00 6708.00 1.00 1.00 6708.00
First Floor
Slab 1.00 4703.00 1.00 1.00 4703.00
Deduction of void -1.00 73.00 1.00 1.00 -73.00
Deduction of Staircase -1.00 32.00 1.00 1.00 -32.00
Second Floor
Slab 1.00 1266.00 1.00 1.00 1266.00
Deduction of Staircase -1.00 32.00 1.00 1.00 -32.00
Third Floor
Slab 1.00 1266.00 1.00 0.13 158.25
12698.25 Sq m
Total Form Work for Slab
Staircase
Basement Floor
Dog -legged stair 2.00 23.76 1.00 1.00 47.52
Straight stair 0.00 1.00 1.00 1.00 0.00
Ground Floor
Dog -legged stair 4.00 23.76 1.00 1.00 95.04
Straight stair 23.00 16.00 1.00 1.00 368.00
First Floor
Dog -legged stair 2.00 23.76 1.00 1.00 47.52
Straight stair 0.00 1.00 1.00 1.00 0.00
Second Floor
Dog -legged stair 2.00 23.76 1.00 1.00 47.52
Straight stair 0.00 1.00 1.00 1.00 0.00
23
Prepared /Design By: Approved By
Checked By:
Project :- Construction of Godavari Municipality Building Bajarbarahi, Lalitpur
Quantity Estimate
Length Area (Sq
S.N Description No Breadth (m) Height (m) Quantity Remarks
(m) m)
11 BRICK WORK
11.1 Ground Floor
Wall along grid G 1.00 361.20 0.23 3.00 249.23
Wall along grid H 1.00 395.60 0.23 3.00 272.96
Ground floor
Deduction of Doors and windows
V1(window) -22.00 1.20 0.23 0.50 -26.40
V2(window) -47.00 3.60 0.23 0.50 -169.20
W1(window) -4.00 2.40 0.23 1.00 -19.20
Door (D2) -12.00 2.40 0.23 1.00 -57.60
Door (D3) -4.00 2.40 0.23 1.00 -19.20
First Floor
Deduction of Doors and windows
W1(window) -4.00 2.40 0.23 1.00 -19.20
W2(window) -16.00 1.80 0.23 1.00 -57.60
Door (D3) -4.00 2.40 0.23 1.00 -19.20
Second Floor
Deduction of Doors and windows
W1(window) -8.00 2.40 0.23 1.00 -38.40
W2(window) -38.00 1.80 0.23 1.00 -136.80
Door (D3) -2.00 2.40 0.23 1.00 -9.60
15081.76 sqm
Total Wall Plaster
Column
Column
Grid A 22.00 0.60 0.60 2.00 81.84
Grid B 22.00 0.60 0.60 5.60 229.15
Grid C 22.00 0.60 0.60 9.20 376.46
Grid D 22.00 0.60 0.60 9.20 376.46
Grid E 16.00 0.60 0.60 5.60 166.66
Grid F(36-84) 39.00 0.60 0.60 3.60 261.14
Grid F(23-35,85-98) 26.00 0.60 0.60 2.00 96.72
Grid G(36-84) 39.00 0.60 0.60 7.20 522.29
Grid G(23-35,85-98) 26.00 0.60 0.60 5.6 270.82
Grid H(36-84) 39.00 0.60 0.60 10.80 783.43
Grid H(23-35,85-98) 26.00 0.60 0.60 9.20 444.91
Total plaster for Column 3609.89 sqm
25
Prepared /Design By: Approved By
Checked By:
Project :- Construction of Godavari Municipality Building Bajarbarahi, Lalitpur
Quantity Estimate
Length Area (Sq
S.N Description No Breadth (m) Height (m) Quantity Remarks
(m) m)
Inclined beams along grids 1-98 in between 87.00 15.80 0.23 0.50 549.84
Total plaster in beam sides 9683.79 sqm
Slab
Ground Floor
Slab 1.00 6708.00 1.00 0.13 6708.00
First Floor
Slab 1.00 4703.00 1.00 0.13 4703.00
Deduction of void 1.00 73.00 1.00 0.13 73.00
Deduction of Staircase 1.00 32.00 1.00 0.13 32.00
Second Floor
Slab 1.00 1266.00 1.00 0.13 1266.00
Deduction of Staircase 1.00 32.00 1.00 0.13 32.00
Third Floor
Slab 1.00 1266.00 1.00 0.13 1266.00
Total Plaster Work in slab 14080.00 sqm
Staircase
Basement Floor
Dog -legged stair 2.00 23.76 1.00 0.20 95.04
Straight stair 0.00 1.00 1.00 0.20
Ground Floor
Dog -legged stair 4.00 23.76 1.00 0.20 190.08
Straight stair 23.00 16.00 1.00 0.20 736.00
26
Prepared /Design By: Approved By
Checked By:
Project :- Construction of Godavari Municipality Building Bajarbarahi, Lalitpur
Quantity Estimate
Length Area (Sq
S.N Description No Breadth (m) Height (m) Quantity Remarks
(m) m)
First Floor
Dog -legged stair 2.00 23.76 1.00 0.20 95.04
Straight stair 0.00 1.00 1.00 0.20 0.00
Second Floor
Dog -legged stair 2.00 23.76 1.00 0.20 95.04
Straight stair 0.00 1.00 1.00 0.20 0.00
Slab of Ramp
Ramp slab 1.00 120.00 1.00 0.30 120.00 sqm
13 STONE WORK
Rubble stone masonryworks in 1:6 c/s mortar &
including 10m trasportation
Site wall 2.00 75.00 2.00 5.00 1500.00
Compound wall 2.00 210.00 2.00 5.00 4200.00
Total 5700.00 Cuft
161.56 Cu m
14 C.G.I SHEETS WORKS
Roof Top 1.00 470.00 13.00 6110.00
Total 6110.00 Sqm
15 TRUSS WORKS
25.00 482.20 12055.00 m
ISNB 65M purlin
Medium Black pipe per m wt 6.42 kg /m 77393.10 Kg
88.00 13 1144.00 m
ISNB 80M bottom chord
Medium Black pipe per m wt 8.36 kg /m 9563.84 Kg
88.00 13 1144.00 m
ISNB 65M top chord
Medium Black pipe per m wt 6.42 kg /m 7344.48 Kg
88.00 51 4488.00 m
ISNB 65M struts
Medium Black pipe per m wt 6.42 kg /m 28812.96 Kg
88.00 13 1131.68 m
ISMC 200 columns
channel per m wt 44.6 kg /m 50472.93 Kg
27
Prepared /Design By: Approved By
Checked By:
Project :- Construction of Godavari Municipality Building Bajarbarahi, Lalitpur
Quantity Estimate
Length Area (Sq
S.N Description No Breadth (m) Height (m) Quantity Remarks
(m) m)
17 FLOORING WORK
Ground Floor
Ground Floor
Slab 1.00 6708.00 1.00 0.08 503.10
First Floor
Slab 1.00 4703.00 1.00 0.08 352.73
Deduction of void 1.00 73.00 1.00 0.08 5.48
Deduction of Staircase 1.00 32.00 1.00 0.08 2.40
Second Floor
Slab 1.00 1266.00 1.00 0.08 94.95
Deduction of Staircase 1.00 32.00 1.00 0.08 2.40
Third Floor
Slab 1.00 1266.00 1.00 0.08 94.95
Total Flooring Work 1056.00 cum
17.2 6'' Sand Fiiling
Ground Floor
all 1.00 6708.00 1.00 0.15 1006.20
Total Sand Filling 1006.20 Cu m
18 PAINTING WORKS
Two coat plastic emulsion paint over one coat
18.1 primer (Astar) on new surface
wall 15081.76
column 3609.89
beam 9683.79
ceiling 14080.00
staicase 23683.20
28
Prepared /Design By: Approved By
Checked By:
Project :- Construction of Godavari Municipality Building Bajarbarahi, Lalitpur
Quantity Estimate
Length Area (Sq
S.N Description No Breadth (m) Height (m) Quantity Remarks
(m) m)
19 HANDRAIL WORKS
First Floor
Gents toilet 1.00 5.10 7.80 3.60 92.88
Total 1877.76 sqm
27 SANITARY WORK
a
Providing and installation of gun metal gate
valve
I) NB 40mm 12.00 12.00 Sets
ii) NB 25mm 18.00 18.00 Sets
b
CPVC Pipes & Fittings for hot and cold water
distribution system CPVC means Chlorinated
Poly Vinyl Chloride as per ASTM are as per
ASTM F 442, CPVC SOLVENT are as per ASTM F-
493 2846 (Flowguard : astral, ashivad, ajay,
marvel or eqv. - 0.00 -
CPVC Pipe SDR 13.5 (22.5 Kg/cm2) - 0.00 -
1/2" dia 717.38 717.38 Rm
3/4" dia 467.99 467.99 ,,
1" dia 430.79 430.79 ,,
1-1/4" dia 375.00 375.00 ,,
1-1/2" dia 250.00 250.00 ,,
2" dia 150.00 150.00 ,,
CPVC Ball Valve (CTS Sockets) - 0.00 -
1/2" 250.00 250.00 Nos
3/4" 125.00 125.00 Nos
1" 100.00 100.00 Nos
1-1/4" 75.00 75.00 Nos
1-1/2" 50.00 50.00 Nos
2" 25.00 25.00 Nos
CPVC Reducer Brass Coupling - 0.00 -
3/4" X 1/2" 250.00 250.00 Nos
1" X 1/2" 230.00 230.00 Nos
CPVC Tee - 0.00 -
1/2" 180.00 180.00 Nos
3/4" 150.00 150.00 Nos
1" 120.00 120.00 Nos
1-1/4" 100.00 100.00 Nos
1-1/2" 75.00 75.00 Nos
2" 50.00 50.00 Nos
CPVC Reducer Tee - 0.00 -
1/2" x 1/2" x 3/4" 150.00 150.00 Nos
3/4" x 3/4" x1/2" 150.00 150.00 Nos
3/4" x 1/2" x 3/4" 150.00 150.00 Nos
3/4" x 1/2" x 1/2" 150.00 150.00 Nos
1" x 1" x 3/4" 75.00 75.00 Nos
1-1/2" x 1-1/2" x 1" 75.00 75.00 Nos
2" x 2" x 1" 75.00 75.00 Nos
1-1/4" x 1-1/4" x 1/2" 75.00 75.00 Nos
30
Prepared /Design By: Approved By
Checked By:
Project :- Construction of Godavari Municipality Building Bajarbarahi, Lalitpur
Quantity Estimate
Length Area (Sq
S.N Description No Breadth (m) Height (m) Quantity Remarks
(m) m)
Providing & installation of water pump (1.5 HP) 4.00 4.00 Sets
Overhead Water Tank (1000 lit ) with Valve and
necessary fitting
4 4.00 nos
29 ELECTRICAL WORKS
Wiring of light/fan & power points:
Light points 200 200.00 Points
Power Points 240 240.00 Points
Light fixture of Approved Brand of
Wipro,Havells with CFL bulb or Philips
equivalent brand
115 115.00 Points
1X11 Watt Down lights with CFL bulb 86 86.00 Points
Ex-Fan fixtures: (Crompton or equivalent)
1500 RPM Heavy duty Auto Louver type 300
mm Exhaust fan with Housing complete set.
15 15.00 Points
Switches, Light &Power and plug in sockets
(North-West or equivalent)
32
Prepared /Design By: Approved By
Checked By:
Project :- Construction of Godavari Municipality Building Bajarbarahi, Lalitpur
Quantity Estimate
Length Area (Sq
S.N Description No Breadth (m) Height (m) Quantity Remarks
(m) m)
Modular type light switches, light and power
socket
6 A 6 gang 1 way switch 35 35.00 Points
6 A 3 gang 1 way switch 25 25.00 Points
6 A 2 gang 1 way switch 20 20.00 Points
Fan 25 25.00 Points
Earthing and Lighting protection system 2 2.00 Points
Electrical Main Panel 2 2.00 Points
Distribution Boards 4 4.00 Points
Wiring of Telephone points 18 18.00 Points
15 A power socket 60 60.00 Points
30 Insurance for the damage and loss of works,
plants and vehicles; personal injury, death of Job
labour, Employee & third party insurance 1 1
31 Provide and maintain Engineer's Office and
logistic facilities(SP6) & Provision for Expert
Services for monitoring construction process and PS
providing training (SP4) As per instructed by
Project Manager or Site engineers. 1 1
32
Photography of construction activities. As per
Job
instructed by Project Manager or Site engineers.
1 1
33
Supplying and placing of Project Sign Board As
per instructed by Project Manager or Site no
engineers. 1 1
34 Rain Water Harvesting 1 1 no
35 Emergency Exit 1 1
36 Passenger Elevator
33
Prepared /Design By: Approved By
Checked By:
R.A. Bldg. 072/73
D. Stone 36. Rubble stone masonry works in mud mortar & including 30m
Works trasportation 4846.43 Per cum. 137.37 Per cft. 5573.395 Per cum.
37. Rubble stone masonry works in 1:3 cement mortar on arch
and lintels & including 30m trasportation 12009.23 Per cum. 340.40 Per cft. 13810.615 Per cum.
38. Rubble stone masonry works in 1:4 cement mortar on arch
and lintels & including 30m trasportation 11534.94 Per cum. 326.95 Per cft. 13265.186 Per cum.
39. Rubble stone masonry works in 1:6 cement mortar on arch
and lintels & including 30m trasportation 10745.87 Per cum. 304.59 Per cft. 12357.746 Per cum.
40. Dressed stone masonry works in 1:6 cement mortar 7887.75 Per cum. 223.58 Per cft. 9070.913 Per cum.
41. Stone filling on trench and levelling transporting upto 30m 3540.66 Per cum. 100.36 Per cft. 4071.759 Per cum.
42. 1:4:8 P.C.C. work in foundation, walls and floor,etc. including
material collection and transportation upto 30m 9967.62 Per cum. 282.53 Per cft. 11462.764 Per cum.
43. 1:3:6 P.C.C. work in foundation, and floor, including material
collection and transportation upto 30m 10764.62 Per cum. 305.12 Per cft. 12379.314 Per cum.
44. 1:2:4 P.C.C. work in foundation and floor including material
collection & transportation upto 30m 12170.05 Per cum. 344.96 Per cft. 13995.557 Per cum.
E. 45. 1:2:4 P.C.C. work in superstructure slab, beams, columns,
Cement lintels etc. with transportation up to 30m 13989.45 Per cum. 396.53 Per cft. 16087.867 Per cum.
Concret 46. 1:1.5:3 P.C.C. work in superstructure slab, beams, columns,
e Works lintels etc. with transportation up to 30m 15241.01 Per cum. 432.00 Per cft. 17527.163 Per cum.
47. 1:1:2 P.C.C. work in superstructure slab, beams, columns,
lintels etc. with transportation up to 30m 18575.36 Per cum. 526.51 Per cft. 21361.662 Per cum.
48. Curtail, bent up, binding of MS bars according to the drawing for
RCC and its transportation up to 30m 98522.20 Per mt 98.52 Per kg 113300.530 Per mt
49. 6.35cm thick Reinforced Brick work in 1:3 cement mortar in
superstructure slab, lintels etc. with transportation 1047.46 Per sqm. 97.37 Per sft 1204.582 Per sqm.
50. Form work for beams, slab in structure including, screening, Per sqm.
fitting, oiling, dismantling, removing and transportation up to 30m 666.01 61.91 Per sft. 765.917 Per sqm.
51. Column post fitting and dismantling, removing with supplying Per sqm.
wood and transporting upto 30m 1053.73 97.95 Per sft. 1211.784 Per sqm.
52. Form work for structural beams installlation and dismantling, Per sqm.
F. Form removing and transporting upto 30m & up to 0.3m Ht of beams 1101.82 102.42 Per sft. 1267.093 Per sqm.
Work 53. Form work for structural beams installlation and dismantling, Per sqm.
removing and transporting upto 30m 847.66 78.79 Per sft. 974.804 Per sqm.
54. Form work for trench shuttering upto 1.5 to 3.0m depth and Per sqm.
transporting upto 30m 148.06 13.76 Per sft. 170.274 Per sqm.
55. Form work for open trench protection depth over 3.0m and Per sqm.
transporting upto 30m 157.61 14.65 Per sft. 181.247 Per sqm.
56. CGI Sheet Roofing with supplying all materials (26 Gauge Per sqm.
medium CGI) 765.59 71.16 Per sft. 880.423 Per sqm.
57.Fixing GI plain Sheet (0.28mm) Ridge cover with supplying all Per Rm.
materials 750.06 228.68 Per rft. 862.564 Per Rm.
G. Roof 58. Coloured CGI Sheet (26 Gauge medium) Roofing with supplying
Coverin all materials Per sqm.
g 868.93 80.77 Per sft. 999.268 Per sqm.
59.Fixing Coloured GI plain Sheet (0.35mm) Ridge cover with Per Rm.
supplying all materials 911.43 277.88 Per rft. 1048.147 Per Rm.
60.1:1:3 (Lime surki brk agg)10cm thick Lime concrete terracing Per sqm.
work with supplying all materials 3662.71 340.46 Per sft. 4212.119 Per sqm.
61. 20 cm thick wood Ceiling work, plankings with 40x20mm Biding Per sqm.
Joint with supplying all materials 5336.15 496.02 Per sft. 6136.577 Per sqm.
62. Sal wood work for choukosh[0.9x2.1m size &0.1x0.075m
section] 248358.09 Per cum. 7039.63 Per cft. 285611.799 Per cum.
63. 38 mm thick Salwood solid pannel shutter (size 1.07m x 1.982m Per sqm.
= 2.114 sq.m.) 12649.18 1175.79 Per sft. 14546.553 Per sqm.
64 . Openable glazed shutter with 38 x 75mm sal wood frame & 3 Per sqm.
mm thick glass 8632.94 802.47 Per sft. 9927.877 Per sqm.
65 . Openable glazed shutter with 38 x 75mm sal wood frame & 4 Per sqm.
mm thick glass 8706.16 809.27 Per sft. 10012.086 Per sqm.
66. Openable glazed shutter with 38 x 75mm sal wood frame &5 Per sqm.
mm thick glass 8821.23 819.97 Per sft. 10144.414 Per sqm.
67 . Openable glazed shutter with 38 x 75mm sal wood frame & 6 Per sqm.
mm thick glass 8894.46 826.78 Per sft. 10228.623 Per sqm.
H. Wood
Work
68. Flush shutter 38mm thick sal wood frame with 4mm thick Per sqm.
commercial plywood on both side of shutter 6824.68 634.38 Per sft. 7848.377 Per sqm.
69.3. Flush shutter 38mm thick sal wood frame with 3mm thick teak Per sqm.
plywood on both side of shutter 7559.46 702.68 Per sft. 8693.377 Per sqm.
70. a.38mm thick sal wood shutter with 28 Gauge GI Plain Sheet on Per sqm.
both side of shutter 6467.87 601.21 Per sft. 7438.047 Per sqm.
71. G.I. mosquito proof wire mess (24gauge) shutter works with Per sqm.
H. Wood 38mm thick sal wood frame 4746.82 441.24 Per sft. 5458.848 Per sqm.
Work
72 . Fixed glazed shutter with 3 mm thick glass 724.38 Per sqm. 67.32 Per sft. 833.039 Per sqm.
73. Fixed glazed shutter with 4 mm thick glass 874.88 Per sqm. 81.31 Per sft. 1006.114 Per sqm.
74. Fixed glazed shutter with 5 mm thick glass 1111.38 Per sqm. 103.29 Per sft. 1278.089 Per sqm.
75. Fixed glazed shutter with 6 mm thick glass 1261.88 Per sqm. 117.28 Per sft. 1451.164 Per sqm.
76 . Wooden partition with frames of 38x75 mm sections on
0.61x0.915m rooms fixed with commercial ply both side fixing with
listy 1673.37 Per sqm. 155.52 Per sft. 1924.370 Per sqm.
77 . Wooden partition with frames of 38x75 mm sections on
0.61x0.915m rooms fixed with 12mm thick hard board both side
2091.42 Per sqm. 194.37 Per sft. 2405.127 Per sqm.
fixing with listypartition with frames of 38x75 mm sections on
78. Wooden
0.61x0.915m rooms fixed with 19mm thick planks both side in lap
3114.31 Per sqm. 289.43 Per sft. 3581.455 Per sqm.
joint
79 . False ceiling with 50x75 mm sections sisau wood with
600x900mm openings fixed with 4mm thick Commercial plywood 2137.66 Per sqm. 198.67 Per sft. 2458.314 Per sqm.
80. False ceiling with 50x75 mm sections sal wood with
600x900mm openings fixed with 3mm thick Asbetos plain sheets
2224.10 Per sqm. 206.70 Per sft. 2557.714 Per sqm.
81. False ceiling with 50x75 mm sections sisau wood with
600x900mm openings fixed with 12mm thick Hard board 2352.94 Per sqm. 218.67 Per sft. 2705.876 Per sqm.
82 . Wooden rafter/purlins/beams making and fixing of saal wood
221269.12 Per cum. 6271.80 Per cft. 254459.488 Per cum.
83 . Wooden trussmaking and fixing of saal wood. 237837.20 Per cum. 6741.42 Per cft. 273512.780 Per cum.
84 . 25mm x150mm salwood eaves board making and fixing 5486.38 Per sqm. 509.89 Per sft. 6309.339 Per sqm.
85. 16-20 mm dia ms rod fixing on windows 110250.00 Per MT 110.25 Per kg. 126787.500 Per MT
86. 38mm(11/2") thick 1:2:4 Cement Concrete FLooring and Per sqm.
finishing with neat cement coat 602.08 55.97 Per sft. 692.397 Per sqm.
87. 50mm(2") thick 1:2:4 Cement Concrete FLooring and finishing Per sqm.
with neat cement coat 740.30 68.81 Per sft. 851.340 Per sqm.
88. 75mm(3") thick 1:2:4 Cement Concrete FLooring and finishing Per sqm.
with neat cement coat 1007.53 93.65 Per sft. 1158.657 Per sqm.
89. 25mm thick mosaic flooring with 20mm thick cement plaster
1:2:4 cement sand ratio & 5mm thick 1:1 white cement & marble Per sqm.
chipping surface course including by rubbing & polish to finish 1748.65 162.54 Per sft. 2010.952 Per sqm.
90. 25mm thick mosaic flooring with 6mm thick 1:1 white cement &
marble chipping over 19mm c/s plaster surface with rubbing & Per sqm.
polish to finish 3236.93 300.89 Per sft. 3722.470 Per sqm.
91. 20mm thick mosaic flooring with 6mm thick 1:1 white cement &
marble chipping over 12.5mm1:2 c/s plaster surface with rubbing Per sqm.
I. & polish to finish 3247.22 301.84 Per sft. 3734.309 Per sqm.
Flooring
Works 92. 20mm terrazo tile over 20mm1:4 c/s plaster surface with Per sqm.
rubbing & polish to finish
2714.38 252.31 Per sft. 3121.535 Per sqm.
93. 15mm thick marble (450x450mm) over 20mm1:2 surki with Per sqm.
rubbing & polish to finish also 3639.89 338.34 Per sft. 4185.875 Per sqm.
Per sqm.
94. Porcelain glazed tile over 20mm1:4 c/s mortar 2401.14 Per sqm. 223.20 Per sft. 2761.313 Per sqm.
95. 50 mm Flagstone paving on 1:4 c/s mortar 1930.58 Per sqm. 179.46 Per sft. 2220.169 Per sqm.
96. 50 mm down Flagstone paving on filled sand 1618.07 Per sqm. 150.41 Per sft. 1860.784 Per sqm.
97. 37.5 mm Flagstone paving on 1:4 cement mortar 1651.11 Per sqm. 153.48 Per sft. 1898.779 Per sqm.
98. 25 mm Flagstone paving on 1:4 cement mortar 1436.54 133.53 Per sft. 1652.020 Per sqm.
99. 25 mm Telia brick paving in 1:2 surki masala & tipkar in 1:2 Per sqm.
cement mortar 1579.47 146.82 Per sft. 1816.394 Per sqm.
100. Brick flat soling on 1:6 cement mortar and pointing in 1:2 Per sqm.
cement mortar on joints 1211.23 112.59 Per sft. 1392.917 Per sqm.
101. Brick edge soling on 1:6 cement mortar and pointing in 1:2 Per sqm.
cement mortar on joints works 1582.94 147.14 Per sft. 1820.380 Per sqm.
Per sqm.
102. Parketting with polishing after rubbing with sand paper works
2210.95 Per sqm. 205.52 Per sft. 2542.593 Per sqm.
103. Dry flat brick soling works 897.99 Per sqm. 83.47 Per sft. 1032.683 Per sqm.
104. Dry edge brick soling works 1555.46 144.59 Per sft. 1788.780 Per sqm.
105. Dry stone soling works 7549.84 Per Cum 214.00 Per cft. 8682.310 Per Cum
106. 125mm Edge Brick soling and pointing works in 1:3cement Per sqm.
mortar on joints after sand filling 1728.17 160.64 Per sft. 1987.390 Per sqm.
107. Pointing in 1:1cement mortar on joints works on paved stone Per sqm.
46cm X46cm 86.28 Per sqm. 8.02 Per sft. 99.223 Per sqm.
108. Filling with sand works 3499.38 Per cum. 325.28 Per sft. 4024.289 Per sqm.
109. 15-150 mm brick bat Filling works 1062.95 30.13 Per cft. 1222.387 Per cum.
Per sqm.
110. 3mm thick thin layer cement Punning (chipping )works 242.30 22.52 Per sft. 278.646 Per sqm.
Per sqm.
111. 12.5mm 1:3 cement sand plaster on ceiling 404.90 Per sqm. 37.64 Per sft. 465.635 Per sqm.
112. 12.5mm 1:4cement sand plaster works on ceiling 396.05 Per sqm. 36.81 Per sft. 455.457 Per sqm.
113. 12.5mm 1:4 cement sand plaster works except in ceiling 342.13 Per sqm. 31.80 Per sft. 393.449 Per sqm.
J. 114. 12.5mm 1:6 cement sand plaster works 320.33 29.78 Per sft. 368.378 Per sqm.
Per sqm.
Plasters 115. 12.5mm 1:2 Lime surki plaster works 336.96 31.32 Per sft. 387.505 Per sqm.
&
116. 20mm 1:3 cement sand plaster works 461.22 Per sqm. 42.87 Per sft. 530.406 Per sqm.
Pointing Per sqm.
Work : 117. 20mm 1:4cement sand plaster works except in ceiling 444.28 Per sqm. 41.30 Per sft. 510.923 Per sqm.
118. 20mm 1:6 cement sand plaster works except in ceiling 410.21 38.13 Per sft. 471.736 Per sqm.
_________ _________ __________
Prepared By Checked By Approved By
J.
Plasters
&
Pointing
Work :
R.A. Bldg. 072/73
119. 25mm mud plaster works with preparation of mud and surface Per sqm.
etc. 30m lead 362.41 Per sqm. 33.69 Per sft. 416.772 Per sqm.
120. 12 mm mud plaster works with preparation of mud and surface
278.88 Per sqm. 25.92 Per sft. 320.712 Per sqm.
etc. 30m lead
121. 2 coat white washing works in ceiling on new surface 32.73 Per sqm. 3.04 Per sft. 37.635 Per sqm.
122. 2 coat white washing works on other new surface 27.49 Per sqm. 2.55 Per sft. 31.610 Per sqm.
123. 3 coat white washing works in ceiling on new surface 66.06 Per sqm. 6.14 Per sft. 75.968 Per sqm.
124. 3 coat white washing works on other new surface 54.75 Per sqm. 5.09 Per sft. 62.959 Per sqm.
125. One White washing works on old surface 14.90 Per sqm. 1.39 Per sft. 17.136 Per sqm.
126. One coat distempering works over one coat astar 101.35 Per sqm. 9.42 Per sft. 116.553 Per sqm.
127. Two coat distemper works over one coat astar 141.60 13.16 Per sft. 162.840 Per sqm.
128 One coat water proof cement paint works over one coat astar Per sqm.
50.48 4.69 Per sft. 58.046 Per sqm.
Per sqm.
129. Two coat water proof cement paint works over one coat astar
117.07 10.88 Per sft. 134.625 Per sqm.
130. One coat readymade enamel paint over one coat primer Per sqm.
(Astar) on new surface 188.95 17.56 Per sft. 217.295 Per sqm.
K. 131. Two coat readymade enamel paint over one coat primer Per sqm.
Painting (Astar) on new surface 284.48 26.44 Per sft. 327.154 Per sqm.
Work 132. One coat plastic emulsion paint over one coat primer (Astar)
Per sqm.
on new surface 179.74 16.71 Per sft. 206.696 Per sqm.
133. Two coat plastic emulsion paint over one coat primer (Astar) Per sqm.
on new surface 275.41 25.60 Per sft. 316.717 Per sqm.
134. Two coat aluminium paint over one coat primer (Astar) on Per sqm.
new surface 264.85 24.62 Per sft. 304.572 Per sqm.
135. One coat double boiled linseed oiling work on new surface Per sqm.
44.10 4.10 Per sft. 50.715 Per sqm.
136. Two coat double boiled linseed oiling work on new surface Per sqm.
86.10 8.00 Per sft. 99.015 Per sqm.
Per sqm.
137. One coat varnishing work on new surface 68.78 Per sqm. 6.39 Per sft. 79.097 Per sqm.
138. Two coat varnishing work on new surface 132.86 12.35 Per sft. 152.789 Per sqm.
Per sqm.
139. One coat bitumen paint work on new surface 25.29 2.35 Per sft. 29.084 Per sqm.
Per sqm.
140. Two coat bitumen paint work on new surface 44.44 Per sqm. 4.13 Per sft. 51.106 Per sqm.
141. Three coat french(chapra) polish work on new surface 156.31 14.53 Per sft. 179.757 Per sqm.
142. One coat snowcem work after cement paint on new Per sqm.
plastered surface 78.83 7.33 Per sft. 90.649 Per sqm.
143. Two coat snowcem work after cement paint on new Per sqm.
plastered surface 141.88 13.19 Per sft. 163.156 Per sqm.
144. Flush pointing works in 1:1 cement sand mortar on brick Per sqm.
masonry work 231.88 21.55 Per sft. 266.664 Per sqm.
145. Ruled pointing works in 1:1 cement sand mortar on brick Per sqm.
masonry work 271.90 25.27 Per sft. 312.687 Per sqm.
146. Flush pointin g works in 1:2 cement sand mortar on Brick Per sqm.
masonry work 216.94 20.17 Per sft. 249.477 Per sqm.
147. Ruled pointing works in 1:2 cement sand mortar on Brick Per sqm.
masonry work 256.96 23.89 Per sft. 295.500 Per sqm.
148. Flush pointing works in 1:3 cement sand mortar on Brick Per sqm.
masonry work 209.01 19.43 Per sft. 240.357 Per sqm.
149. ruled pointing works in 1:3 cement sand mortar on Brick Per sqm.
masonry work 249.03 23.15 Per sft. 286.380 Per sqm.
150. Flush pointing works in 1:1:3 cement Lime sand mortar on Per sqm.
Brick masonry work 216.69 20.14 Per sft. 249.196 Per sqm.
151. Ruled pointing works in 1:1:3 cement Lime sand mortar on Per sqm.
Brick masonry work 239.87 22.30 Per sft. 275.855 Per sqm.
152. Flush pointing works in 1:1 Lime Surki mortar on Brick Per sqm.
L. masonry work 215.73 20.05 Per sft. 248.090 Per sqm.
Pointing 153. Ruled pointing works in 1:1 Lime Surki mortar on Brick Per sqm.
Works masonry work 255.75 23.77 Per sft. 294.113 Per sqm.
154. Flush pointing works in 1:2 Lime Surki mortar on Brick Per sqm.
masonry work 205.05 19.06 Per sft. 235.806 Per sqm.
155. Ruled pointing works in 1:2 Lime Surki mortar on Brick Per sqm.
masonry work 245.07 22.78 Per sft. 281.829 Per sqm.
156. Flush ruled pointing works in 1:1 c/s mortar on random rubble Per sqm.
masonry work 293.72 27.30 Per sft. 337.775 Per sqm.
157. Flush ruled pointing works in 1:2 c/s mortar on random rubble Per sqm.
masonry work 265.10 24.64 Per sft. 304.867 Per sqm.
157. Flush ruled pointing works in 1:3 c/s mortar on random rubble Per sqm.
masonry work 250.52 23.29 Per sft. 288.093 Per sqm.
158. Flush ruled pointing works in 1:3cement sand mortar on ashlar Per sqm.
masonry work 162.45 15.10 Per sft. 186.815 Per sqm.
164. Pointing works in 1:3cement sand mortar on 45x45cm Per sqm.
flagstone paving 86.28 Per sqm. 8.02 Per sft. 99.223 Per sqm.
165. Pointing works in 1:1cement sand mortar on telia bricks 184.20 Per sqm. 17.12 Per sft. 211.827 Per sqm.
166. 3mm Lime flushing plaster works 184.38 Per sqm. 17.14 Per sft. 212.037 Per sqm.
167. 3mm cement flushing plaster works 240.07 Per sqm. 22.32 Per sft. 276.080 Per sqm.
168. 2 cm thick DPC in 1:2 C/S with Water Proofing Compound
464.85 Per sqm. 43.21 Per sft. 534.575 Per sqm.
(WPC)
169. 2.5 cm thick DPC in 1:1.5:3 concrete with Water Proofing
517.93 Per sqm. 48.14 Per sft. 595.623 Per sqm.
Compound (WPC)
170. One coat Bitumenous paint on DPC and sand covering 173.59 Per sqm. 16.14 Per sft. 199.633 Per sqm.
171. One Layer 500 Gauge polythene sheet for DPC 127.50 Per sqm. 11.85 Per sft. 146.625 Per sqm.
0 172. One coat tar felt works with sand 773.73 Per sqm. 71.92 Per sft. 889.790 Per sqm.
173. Two coat tar felt works with sand 1196.06 Per sqm. 111.18 Per sft. 1375.470 Per sqm.
174. One coat damp Proof grade tar felt works with sand 974.20 Per sqm. 90.56 Per sft. 1120.331 Per sqm.
175. Two coat damp Proof grade tar felt works with sand 1792.19 Per sqm. 166.59 Per sft. 2061.019 Per sqm.
176. One coat rain seal or equivalent painting works 672.16 62.48 Per sft. 772.985 Per sqm.
177. Maintenance of wall in 1:6 C/S at corners with removal of old Per Cum. Per Cum.
bricks 18096.58 512.94 Per Cu ft. 20811.071
178. Maintenance of wall in 1:2 lime surki with removal of old bricks Per Cum. Per Cum.
at wall corners 18533.26 Per Sqm. 525.32 Per Cu ft. 21313.254 Per Sqm.
179. One coat Enamel paintings works after linseed oil flushing 186.42 17.33 Per Sq ft. 214.380
180. Dismantling of Cement Plaster and Disposing with Per Cum. Per Cum.
transportation of 10m. 72.04 2.04 Per Cu ft. 82.841
N. 181. Dismantling of Tile Roof and Disposing tile/Woods with Per Cum. Per Cum.
Mainten transportation of 10m. 103.06 Per Sqm. 2.92 Per Cu ft. 118.518 Per Sqm.
ance 182. Antitermite paint on wood 326.24 30.33 Per Sqft. 375.176
Work 183. Dismantling of Mud mortared wall and Disposing with
Per Cum. Per Cum.
transportation of 10m. 707.02 20.04 Per Cu ft. 813.073
184. Dismantling of Cement mortared wall and Disposing with Per Cum. Per Cum.
transportation of 10m. 1414.04 40.08 Per Cu ft. 1626.146
185. Dismantling of R.C.C./R.B.C. and Disposing with Per Cum. Per Cum.
transportation of 10m. 7337.00 207.96 Per Cu ft. 8437.550
186. Dismantling of P.C.C. and Disposing with transportation of Per Cum. Per Cum.
10m. 2668.00 75.62 Per Cu ft. 3068.200
187. 3 x 20mm Metal Grill including manufacturing, fitting, painting Per sqm.
with Aluminium paint, sand papering all complete 1790.95 166.48 Per sft. 2059.593 Per sqm.
188. 216. 4.5 x 20mm Metal Grill including manufacturing, fitting, Per sqm.
painting with Aluminium paint, sand papering all complete 3220.70 299.38 Per sft. 3703.805 Per sqm.
O. (Iron)
Steel 189. Iron tubular Truss including manufacturing, welding, supply of
Work material, painting and fixing all complete 139.44 Per
Per Rm.
kg 139.44 Per kg 160.355 Per kg
190. GI Barbed wire fencingworks 62.08 18.93 Per rft. 71.396 Per Rm.
191. Barbed wire fencing in 75x100x2100 Saal wood posts with Per Rm.
5rows & two cross bracings all complete 1374.18 418.96 Per rft. 1580.308 Per Rm.
192. M1 . Rain Water Pipe 90 mm dia. HDPE 296.49 Per Rmt. 90.39 Per Rft 340.964 Per Rmt.
P. 193. M11.Concrete Hollow Block Masonry works in 1:4 cement
2108.63 Per Sq.m. 196.15 Per Sq.ft. 2424.930 Per Sq.m.
Miscelan mortar
194. M12. 50mm thick inter locking concrete block work on 50mm
eous 195. 1420.41 Per sqm.. 132.13 Per sqft. 1633.474 Per sqm..
thick M13.
dust 60mm thick inter locking concrete block work on 50mm
1445.95 Per sqm. 134.38 Per sqft. 1662.848 Per sqm.
thick dust
District: Lalitpur
Fiscal Year: 074/075
Labour,Equipments & Material Rates for Official Use.
Rates
Total
S.N. Description of Resources Units Basic Rate(NRs) Rates(NRs) Remarks
A: Labours
1 Sk MD 908.00 908.00
2 Unsk MD 667.00 667.00
3 Coolies MD 667.00 667.00
B: Equipments 0.00
1 Water Pump Hrs 200.00 200.00
2 Truck Hrs 450.00 450.00
3 Road Roller Hrs 700.00 700.00
4 Machine to rub sandpaper hrs 150.00 150.00
C: Materials
1 Cement (Nepal made gen.) MT 15940.00 15940.00
2 Sand (Khani) cum 2787.12 2787.12
3 Aggregate 20- 40mm cum 2646.00 2646.00
10-20mm cum 2716.56 2716.56
6-10mm cum 2540.16 2540.16
4 Gravel (River/Quarry Local) cum 1587.60 1587.60
RATE ANALYSIS
District : Lalitpur
F/Y : 2073/2074
CIVIL WORKS :
Contents
CATEGO
RIES WORKS
A: Site clearance Works
B: Earth cutting and Filling Works
C: Brick Works
D: Stone Works
E: Cement Concrete Works
F: Form Works
G: Roofing Works
H: Wood Works
I: Flooring Works
J: Plastering Works
K: Painting Works
L: Pointing Works
M: Water Proofing Works
N: Maintenance works
O: Iron (Steel) Works
P: Miscellaneous Works
2073 Bhadra
_______________
____________ _______________
Approved By
Prepared By Checked By
Rate Analysis
3. Surface dressing, Pit filling, mud cutting works etc, (1sqm/10.76 sft)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: Unskilled 0.010 Nos. 667.00 6.67 6.67
Actual rate 6.67
Rate 15% contractor's overhead 1.00
Per sqm. Per sft. Total 7.67
6.67 0.62
4. Removal of grasses, small trees, levelling of undulated ground, landscaping all complete work, and disposal existing earth materials
away from construction site (thickness 15- 20 cm.)
(10sqm)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: Unskilled 0.230 Nos. 667.00 153.41 153.41
Actual rate 153.41
Rate 15% contractor's overhead 23.01
Per sqm. Per sft. Total 176.42
15.34 1.43
6. Earth work in excavation in hard soil soft rocks including 10m hauling, disposing & 1.5m lifting (1cu.m./35.28 cft)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: Coolies 0.800 Nos. 667.00 533.60 533.60
Tools & Equipments 3% of total labour cost 16.01 16.01
Actual rate 549.61
Rate 15% contractor's overhead 82.44
Per cum. Per cft. Total 632.05
549.61 15.58
_______________
____________ _______________
Approved By
Prepared By Checked By
Rate Analysis
7. Earth back filling with compaction in 6" layer with sprinkling water , transporting from 10m distance ( 1cu.m/35.28 cft )
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
a) Coolies 0.500 Nos. 667.00 333.50 333.50
Actual rate 333.50
Rate 15% contractor's overhead 50.03
Per cum. Per cft. Total 383.53
333.50 9.45
8. Earth filling with compaction in 6" layer without sprinkling water, transporting from 10m distance ( 1cu.m/35.28 cft )
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
a) Coolies 0.250 Nos. 667.00 166.75 166.75
Actual rate 166.75
Rate 15% contractor's overhead 25.01
Per cum. Per cft. Total 191.76
166.75 4.73
9. Pumping out water from trench -Put Qty according to capacity of pumpset ( 5000L/0.5 cum)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
a) pump Hours 0.500 Hours 200.00 100.000 100.000
Actual rate 100.000
Rate 15% contractor's overhead 15.000
Per 5000L Per Lit. Total 115.000
100.00 0.02
10. Sand filling with compaction in 6" layer, watering etc. transporting from 10m distance ( 1cu.m/35.28 cft )
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Coolies 0.700 Nos. 667.00 466.90 466.90
Materials Sand 1.100 cu.m. 2787.12 3065.83 3065.83
Actual rate 3532.73
Rate 15% contractor's overhead 529.91
Per cum. Per cft. Total 4062.64
3532.73 100.13
12. Brick work in 1:3 c/s mortar above Ground Floor using machine made brick & including 30m trasportation
( 1 cu.m./35.28 cft)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.50 Nos. 908.00 1362.00
b) Unskilled 2.20 Nos. 667.00 1467.40
c) Unskilled(for scafolding) 0.70 Nos. 667.00 466.90 3296.30
Bricks 530.000 Nos. 15.30 8109.00
Materials Cement 0.130 MT 15940.00 2072.20
Sand 0.270 Cub.M. 2787.12 752.52 10933.72
Sundries 3% of (c) 14.01 14.01
Actual rate 14244.03
Rate 15% contractor's overhead 2136.60
Per cum. Per cft. Total 16380.63
14244.03 403.74
_______________
____________ _______________
Approved By
Prepared By Checked By
Rate Analysis
13. Brick work in 1:4 cem mortar in Ground Floor using machine made brick & including 30m trasportation
( 1 cu.m./35.28 cft)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.50 Nos. 908.00 1362.00
b) Unskilled 2.20 Nos. 667.00 1467.40
c) Unskilled(for scafolding) 0.20 Nos. 667.00 133.40 2962.80
Bricks 530.000 Nos. 15.30 8109.00
Materials Cement 0.100 MT 15940.00 1594.00
Sand 0.270 Cub.M. 2787.12 752.52 10455.52
Sundries 3% of (c) 4.00 4.00
Actual rate 13422.32
Rate 15% contractor's overhead 2013.35
Per cum. Per cft. Total 15435.67
13422.32 380.45
14. Brick work in 1:4 cem mortar above Ground Floor using machine made brick & including 30m trasportation
( 1 cu.m./35.28 cft)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.50 Nos. 908.00 1362.00
b) Unskilled 2.20 Nos. 667.00 1467.40
c) Unskilled(for scafolding) 0.70 Nos. 667.00 466.90 3296.30
Bricks 530.000 Nos. 15.30 8109.00
Materials Cement 0.100 MT 15940.00 1594.00
Sand 0.270 Cub.M. 2787.12 752.52 10455.52
Sundries 3% of (c) 14.01 14.01
Actual rate 13765.83
Rate 15% contractor's overhead 2064.87
Per cum. Per cft. Total 15830.70
13765.83 390.19
15. B/W in 1:5 cement mortar on Ground Floor using machine made brick & including 30m trasportation
( 1 cu.m./35.28 cft)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.50 Nos. 908.00 1362.00
b) Unskilled 2.20 Nos. 667.00 1467.40
c) Unskilled(for scafolding) 0.20 Nos. 667.00 133.40 2962.80
Bricks 530.000 Nos. 15.30 8109.00
Materials Cement 0.090 MT 15940.00 1434.60
Sand 0.310 Cub.M. 2787.12 864.01 10407.61
Sundries 3% of (c) 4.00 4.00
Actual rate 13374.41
Rate 15% contractor's overhead 2006.16
Per cum. Per cft. Total 15380.57
13374.41 379.09
16. B/W in 1:5 cement mortar above Ground Floor using machine made brick & including 30m trasportation
( 1 cu.m./35.28 cft)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.50 Nos. 908.00 1362.00
b) Unskilled 2.20 Nos. 667.00 1467.40
c) Unskilled(for scafolding) 0.70 Nos. 667.00 466.90 3296.30
Bricks 530.000 Nos. 15.30 8109.00
Materials Cement 0.090 MT 15940.00 1434.60
Sand 0.310 Cub.M. 2787.12 864.01 10407.61
Sundries 3% of (c) 14.01 14.01
Actual rate 13717.91
Rate 15% contractor's overhead 2057.69
Per cum. Per cft. Total 15775.60
13717.91 388.83
17. B/W in 1:6 cement mortar in Ground Floor using machine made brick & including 30m trasportation
( 1 cu.m./35.28 cft)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.50 Nos. 908.00 1362.00
b) Unskilled 2.20 Nos. 667.00 1467.40
c) Unskilled(for scafolding) 0.20 Nos. 667.00 133.40 2962.80
Bricks 530.000 Nos. 15.30 8109.00
Materials Cement 0.070 MT 15940.00 1115.80
Sand 0.300 Cub.M. 2787.12 836.14 10060.94
Sundries 3% of (c) 4.00 4.00
Actual rate 13027.74
Rate 15% contractor's overhead 1954.16
Per cum. Per cft. Total 14981.90
13027.74 369.27
_______________
____________ _______________
Approved By
Prepared By Checked By
Rate Analysis
18. B/W in 1:6 cement mortar above Ground Floor using machine made brick & including 30m trasportation
( 1 cu.m./35.28 cft)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.500 Nos. 908.00 1362.00
b) Unskilled 2.200 Nos. 667.00 1467.40
c) Unskilled(for scafolding) 0.700 Nos. 667.00 466.90 3296.30
Bricks 530.000 Nos. 15.30 8109.00
Materials Cement 0.070 MT 15940.00 1115.80
Sand 0.300 Cub.M. 2787.12 836.14 10060.94
Sundries 3% of (c) 14.01 14.01
Actual rate 13371.24
Rate 15% contractor's overhead 2005.69
Per cum. Per cft. Total 15376.93
13371.24 379.00
19. Brick work in 1:3 cement mortar in ground floor using chimney made brick & including 30m trasportation
( 1 cu.m./35.28 cft)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.500 Nos. 908.00 1362.00
b) Unskilled 2.200 Nos. 667.00 1467.40
c) Unskilled(for scafolding) 0.200 Nos. 667.00 133.40 2962.80
Bricks 560.000 Nos. 14.00 7840.00
Materials Cement 0.130 MT 15940.00 2072.20
Sand 0.270 Cub.M. 2787.12 752.52 10664.72
Sundries 3% of (c) 4.00 4.00
Actual rate 13631.52
Rate 15% contractor's overhead 2044.73
Per cum. Per cft. Total 15676.25
13631.52 386.38
20. Brick work in 1:3 cement mortar above ground floor using chimney made brick & including 30m trasportation
( 1 cu.m./35.28 cft)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.500 Nos. 908.00 1362.00
b) Unskilled 2.200 Nos. 667.00 1467.40
c) Unskilled(for scafolding) 0.700 Nos. 667.00 466.90 3296.30
Bricks 560.000 Nos. 14.00 7840.00
Materials Cement 0.130 MT 15940.00 2072.20
Sand 0.270 Cub.M. 2787.12 752.52 10664.72
Sundries 3% of (c) 14.01 14.01
Actual rate 13975.03
Rate 15% contractor's overhead 2096.25
Per cum. Per cft. Total 16071.28
13975.03 396.12
21. Brick work in 1:4 cement mortar in ground floor using chimney made brick & including 30m trasportation
( 1 cu.m./35.28 cft)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.500 Nos. 908.00 1362.00
b) Unskilled 2.200 Nos. 667.00 1467.40
c) Unskilled(for scafolding) 0.200 Nos. 667.00 133.40 2962.80
Bricks 560.000 Nos. 14.00 7840.00
Materials Cement 0.100 MT 15940.00 1594.00
Sand 0.280 Cub.M. 2787.12 780.39 10214.39
Sundries 3% of (c) 4.00 4.00
Actual rate 13181.20
Rate 15% contractor's overhead 1977.18
Per cum. Per cft. Total 15158.37
13181.20 373.62
22. Brick work in 1:4 cement mortar above ground floor using chimney made brick & including 30m trasportation
( 1 cu.m./35.28 cft)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.500 Nos. 908.00 1362.00
b) Unskilled 2.200 Nos. 667.00 1467.40
c) Unskilled(for scafolding) 0.700 Nos. 667.00 466.90 3296.30
Bricks 560.000 Nos. 14.00 7840.00
Materials Cement 0.100 MT 15940.00 1594.00
Sand 0.280 Cub.M. 2787.12 780.39 10214.39
Sundries 3% of (c) 14.01 14.01
Actual rate 13524.70
Rate 15% contractor's overhead 2028.71
Per cum. Per cft. Total 15553.41
13524.70 383.35
_______________
____________ _______________
Approved By
Prepared By Checked By
Rate Analysis
23 . Half brick thick brick work in 1:4 cement mortar in all height using chimney made brick & including 30m trasportation
( 1 sqm/10.76 sft)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 0.350 Nos. 908.00 317.80
b) Unskilled 0.510 Nos. 667.00 340.17
c) Unskilled(for scafolding) 0.161 Nos. 667.00 107.39 765.36
Bricks 73.000 Nos. 14.00 1022.00
Materials Cement 0.010 MT 15940.00 159.40
Sand 0.040 Cub.M. 2787.12 111.48 1292.88
Sundries 3% of (c) 3.22 3.22
Actual rate 2061.46
Rate 15% contractor's overhead 309.22
Per sqm. Per sft. Total 2370.68
2061.46 191.59
24. Brick work in 1:6 cement mortar in ground floor using chimney made brick & including 30m trasportation
( 1 cu.m./35.28 cft)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.500 Nos. 908.00 1362.00
b) Unskilled 2.200 Nos. 667.00 1467.40
c) Unskilled(for scafolding) 0.200 Nos. 667.00 133.40 2962.80
Bricks 560.000 Nos. 14.00 7840.00
Materials Cement 0.070 MT 15940.00 1115.80
Sand 0.300 Cub.M. 2787.12 836.14 9791.94
Sundries 3% of (c) 4.00 4.00
Actual rate 12758.74
Rate 15% contractor's overhead 1913.81
Per cum. Per cft. Total 14672.55
12758.74 361.64
25. Brick work in 1:6 cement mortar in above ground floor using chimney made brick & including 30m trasportation
( 1 cu.m./35.28 cft)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.500 Nos. 908.00 1362.00
b) Unskilled 2.200 Nos. 667.00 1467.40
c) Unskilled(for scafolding) 0.700 Nos. 667.00 466.90 3296.30
Bricks 560.000 Nos. 14.00 7840.00
Materials Cement 0.070 MT 15940.00 1115.80
Sand 0.300 Cub.M. 2787.12 836.14 9791.94
Sundries 3% of (c) 14.01 14.01
Actual rate 13102.24
Rate 15% contractor's overhead 1965.34
Per cum. Per cft. Total 15067.58
13102.24 371.38
26. Brick work in 1:1:1 Lime Sand Surki in ground floor using chimney made brick & including 30m trasportation
( 1 cu.m./35.28 cft)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.500 Nos. 908.00 1362.00
b) Unskilled 2.200 Nos. 667.00 1467.40
c) Unskilled(for scafolding) 0.200 Nos. 667.00 133.40 2962.80
Bricks 560.000 Nos. 14.00 7840.00
Materials Lime 0.140 Cub.M. 16800.00 2352.00
Sand 0.140 Cub.M. 2787.12 390.20
Surki 0.140 Cub.M. 1541.03 215.74 10797.94
Sundries 3% of (c) 4.00 4.00
Actual rate 13764.74
Rate 15% contractor's overhead 2064.71
Per cum. Per cft. Total 15829.45
13764.74 390.16
_______________
____________ _______________
Approved By
Prepared By Checked By
Rate Analysis
27. B/W in 1:1:1 Lime Sand Surki above Gnd Floor using chimney made brick & including 30m trasportation
( 1 cu.m./35.28 cft)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.500 Nos. 908.00 1362.00
b) Unskilled 2.200 Nos. 667.00 1467.40
c) Unskilled(for scafolding) 0.700 Nos. 667.00 466.90 3296.30
Bricks 560.000 Nos. 14.00 7840.00
Materials Lime 0.140 Cub.M. 16800.00 2352.00
Sand 0.140 Cub.M. 2787.12 390.20
Surki 0.140 Cub.M. 1541.03 215.74 10797.94
Sundries 3% of (c) 14.01 14.01
Actual rate 14108.25
Rate 15% contractor's overhead 2116.24
Per cum. Per cft. Total 16224.49
14108.25 399.89
28. Brick work in 1:2 Lime Surki in ground floor using chimney made brick & including 30m trasportation
( 1 cu.m./35.28 cft)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.500 Nos. 908.00 1362.00
b) Unskilled 2.200 Nos. 667.00 1467.40
c) Unskilled(for scafolding) 0.200 Nos. 667.00 133.40 2962.80
Bricks 560.000 Nos. 14.00 7840.00
Materials Lime 0.140 Cub.M. 16800.00 2352.00
Surki 0.280 Cub.M. 1541.03 431.49 10623.49
Sundries 3% of (c) 4.00 4.00
Actual rate 13590.29
Rate 15% contractor's overhead 2038.54
Per cum. Per cft. Total 15628.83
13590.29 385.21
29. B/W in 1:2 Lime Surki above ground floor using chimney made brick & including 30m trasportation
( 1 cu.m./35.28 cft)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.500 Nos. 908.00 1362.00
b) Unskilled 2.200 Nos. 667.00 1467.40
c) Unskilled(for scafolding) 0.700 Nos. 667.00 466.90 3296.30
Bricks 560.000 Nos. 14.00 7840.00
Materials Lime 0.140 MT 16800.00 2352.00
Surki 0.280 Cub.M. 1541.03 431.49 10623.49
Sundries 3% of (c) 14.01 14.01
Actual rate 13933.80
Rate 15% contractor's overhead 2090.07
Per cum. Per cft. Total 16023.86
13933.80 394.95
30. Brick work in mud mortar in ground floor using chimney made brick & including 30m trasportation
( 1 cu.m./35.28 cft)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.000 Nos. 908.00 908.00
b) Unskilled 1.700 Nos. 667.00 1133.90
c)Unskilled(for scafolding) 0.200 Nos. 667.00 133.40 2175.30
Bricks 560.000 Nos. 14.00 7840.00
Materials Mud 0.420 Cub.M. 260.00 109.20 7949.20
Sundries 3% of (c) 4.00 4.00
Actual rate 10128.50
Rate 15% contractor's overhead 1519.28
Per cum. Per cft. Total 11647.78
10128.50 287.09
31. Brick work in mud mortar above ground floor using chimney made brick & including 30m trasportation
( 1 cu.m./35.28 cft)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.000 Nos. 908.00 908.00
b) Unskilled 1.700 Nos. 667.00 1133.90
c)Unskilled(for scafolding) 0.700 Nos. 667.00 466.90 2508.80
Bricks 560.000 Nos. 14.00 7840.00
Materials Mud 0.420 Cub.M. 260.00 109.20 7949.20
Sundries 3% of (c) 14.01 14.01
Actual rate 10472.01
Rate 15% contractor's overhead 1570.80
Per cum. Per cft. Total 12042.81
10472.01 296.83
_______________
____________ _______________
Approved By
Prepared By Checked By
Rate Analysis
D. Stone Works
32. Rubble stone masonryworks in 1:3 c/s mortar & including 10m trasportation ( 1 cu.m./35.28 cft)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.500 Nos. 908.00 1362.00
b) Unskilled 5.000 Nos. 667.00 3335.00 4697.00
Cement 0.194 MT 15940.00 3092.36
Materials Sand 0.420 Cub.M. 2787.12 1170.59
Blockstone 1.000 Cub.M. 2116.80 2116.80
Bundstone 0.100 Cub.M. 2116.80 211.68 6591.43
Actual rate 11288.43
Rate 15% contractor's overhead 1693.26
Per cum. Per cft. Total 12981.69
11288.43 319.97
33. Rubble stone masonryworks in 1:4 c/s mortar & including 10m trasportation ( 1 cu.m./35.28 cft)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.500 Nos. 908.00 1362.00
b) Unskilled 5.000 Nos. 667.00 3335.00 4697.00
Cement 0.159 MT 15940.00 2534.46
Materials Sand 0.440 Cub.M. 2787.12 1226.33
Blockstone 1.000 Cub.M. 2116.80 2116.80
Bundstone 0.100 Cub.M. 2116.80 211.68 6089.27
Actual rate 10786.27
Rate 15% contractor's overhead 1617.94
Per cum. Per cft. Total 12404.21
10786.27 305.73
34. Rubble stone masonryworks in 1:6 c/s mortar & including 10m trasportation ( 1 cu.m./35.28 cft)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.500 Nos. 908.00 1362.00
b) Unskilled 5.000 Nos. 667.00 3335.00 4697.00
Cement 0.106 MT 15940.00 1689.64
Materials Sand 0.470 Cub.M. 2787.12 1309.95
Blockstone 1.000 Cub.M. 2116.80 2116.80
Bundstone 0.100 Cub.M. 2116.80 211.68 5328.07
Actual rate 10025.07
Rate 15% contractor's overhead 1503.76
Per cum. Per cft. Total 11528.83
10025.07 284.16
35. Dry stone Rubble masonryworks & including 30m trasportation ( 1 cu.m./35.28 cft)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.000 Nos. 908.00 908.00
b) Unskilled 2.000 Nos. 667.00 1334.00 2242.00
Materials Blockstone 1.000 Cub.M. 2116.80 2116.80
Bundstone 0.100 Cub.M. 2116.80 211.68 2328.48
Actual rate 4570.48
Rate 15% contractor's overhead 685.57
Per cum. Per cft. Total 5256.05
4570.48 129.55
36. Rubble stone masonry works in mud mortar & including 30m trasportation ( 1 cu.m./35.28 cft)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.000 Nos. 908.00 908.00
b) Unskilled 2.250 Nos. 667.00 1500.75 2408.75
Materials Blockstone 1 Cub.M. 2116.80 2116.8
Bundstone 0.1 Cub.M. 2116.80 211.68
Mud 0.42 Cub.M. 260.00 109.2 2437.68
Actual rate 4846.43
Rate 15% contractor's overhead 726.96
Per cum. Per cft. Total 5573.39
4846.43 137.37
_______________
____________ _______________
Approved By
Prepared By Checked By
Rate Analysis
37. Rubble stone masonry works in 1:3 cement mortar on arch and lintels & including 30m trasportation ( 1 cu.m./35.28 cft)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 2.000 Nos. 908.00 1816.00
b) Unskilled 5.400 Nos. 667.00 3601.80 5417.80
Cement 0.194 MT 15940.00 3092.36
Materials Sand 0.420 Cub.M. 2787.12 1170.59
Blockstone 1.000 Cub.M. 2116.80 2116.80
Bundstone 0.100 Cub.M. 2116.80 211.68 6591.43
Actual rate 12009.23
Rate 15% contractor's overhead 1801.38
Per cum. Per cft. Total 13810.61
12009.23 340.40
38. Rubble stone masonry works in 1:4 cement mortar on arch and lintels & including 30m trasportation
( 1 cu.m./35.28 cft)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 2.000 Nos. 908.00 1816.00
b) Unskilled 5.400 Nos. 667.00 3601.80 5417.80
Cement 0.159 MT 15940.00 2534.46
Materials Sand 0.450 Cub.M. 2787.12 1254.20
Blockstone 1.000 Cub.M. 2116.80 2116.80
Bundstone 0.100 Cub.M. 2116.80 211.68 6117.14
Actual rate 11534.94
Rate 15% contractor's overhead 1730.24
Per cum. Per cft. Total 13265.19
11534.94 326.95
39. Rubble stone masonry works in 1:6 cement mortar on arch and lintels & including 30m trasportation
( 1 cu.m./35.28 cft)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 2.000 Nos. 908.00 1816.00
b) Unskilled 5.400 Nos. 667.00 3601.80 5417.80
Cement 0.106 MT 15940.00 1689.64
Materials Sand 0.470 Cub.M. 2787.12 1309.95
Blockstone 1.000 Cub.M. 2116.80 2116.80
Bundstone 0.100 Cub.M. 2116.80 211.68 5328.07
Actual rate 10745.87
Rate 15% contractor's overhead 1611.88
Per cum. Per cft. Total 12357.75
10745.87 304.59
40. Dressed stone masonry works in 1:6 cement mortar ( 10 cu.m./352.8 cft)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 15.000 Nos. 908.00 13620.00
b) Unskilled 30.000 Nos. 667.00 20010.00 33630.00
Cement 0.400 MT 15940.00 6376.00
Materials Sand 4.200 Cub.M. 2787.12 11705.90
Dressed stone 11.000 Cub.M. 2469.60 27165.60 45247.50
Actual rate 78877.50
Rate 15% contractor's overhead 11831.63
Per cum. Per cft. Total 90709.13
7887.75 223.58
41. Stone filling on trench and levelling transporting upto 30m ( 1 cu.m./35.28 cft)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 0.000 Nos. 908.00 0.00
b) Unskilled 1.500 Nos. 667.00 1000.50 1000.50
Materials Blockstone 1.000 Cub.M. 2116.80 2116.80
Bundstone 0.200 Cub.M. 2116.80 423.36 2540.16
Actual rate 3540.66
Rate 15% contractor's overhead 531.10
Per cum. Per cft. Total 4071.76
3540.66 100.36
_______________
____________ _______________
Approved By
Prepared By Checked By
Rate Analysis
42. 1:4:8 P.C.C. work in foundation, walls and floor,etc. including material collection and transportation upto 30m
( 1 cu.m./ 35.28 cft )
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.000 Nos. 908.00 908.00
b) Coolies 4.000 Nos. 667.00 2668.00 3576.00
Materials Cement 0.170 MT 15940.00 2709.80
Sand 0.470 Cub M 2787.12 1309.95
40 mm aggregate 0.650 Cub M 2646.00 1719.90
20 mm aggregate 0.240 Cub M 2716.56 651.97 6391.62
Actual rate 9967.62
Rate 15% contractor's overhead 1495.14
Per cum. Per cft. Total 11462.76
9967.62 282.53
43. 1:3:6 P.C.C. work in foundation, and floor, including material collection and transportation upto 30m
( 1 cu.m./ 35.28 cft )
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.000 Nos. 908.00 908.00
b) Coolies 4.000 Nos. 667.00 2668.00 3576.00
Materials Cement 0.220 MT 15940.00 3506.80
Sand 0.470 Cub M 2787.12 1309.95
40 mm aggregate 0.650 Cub M 2646.00 1719.90
20 mm aggregate 0.240 Cub M 2716.56 651.97 7188.62
Actual rate 10764.62
Rate 15% contractor's overhead 1614.69
Per cum. Per cft. Total 12379.31
10764.62 305.12
44. 1:2:4 P.C.C. work in foundation and floor including material collection & transportation upto 30m
( 1 cu.m./ 35.28 cft )
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.000 Nos. 908.00 908.00
b) Coolies 4.000 Nos. 667.00 2668.00 3576.00
Materials Cement 0.320 MT 15940.00 5100.80
Sand 0.445 Cu.m. 2787.12 1240.27
40 mm aggregate 0.520 Cu.m. 2646.00 1375.92
20 mm aggregate 0.220 Cu.m. 2716.56 597.64
10 mm aggregate 0.110 Cu.m. 2540.16 279.42 8594.05
Actual rate 12170.05
Rate 15% contractor's overhead 1825.51
Per cum. Per cft. Total 13995.56
12170.05 344.96
45. 1:2:4 P.C.C. work in superstructure slab, beams, columns, lintels etc. with transportation up to 30m
( 1 cu.m./ 35.28 cft )
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 0.800 Nos. 908.00 726.40
b) Coolies 7.000 Nos. 667.00 4669.00 5395.40
Materials Cement 0.320 MT 15940.00 5100.80
Sand 0.445 Cub M 2787.12 1240.27
40 mm aggregate 0.520 Cub M 2646.00 1375.92
20 mm aggregate 0.220 Cub M 2716.56 597.64
10 mm aggregate 0.110 Cub M 2540.16 279.42 8594.05
Actual rate 13989.45
Rate 15% contractor's overhead 2098.42
Per cum. Per cft. Total 16087.87
13989.45 396.53
_______________
____________ _______________
Approved By
Prepared By Checked By
Rate Analysis
46. 1:1.5:3 P.C.C. work in superstructure slab, beams, columns, lintels etc. with transportation up to 30m
( 1 cu.m./ 35.28 cft )
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 0.800 Nos. 908.00 726.40
b) Coolies 7.000 Nos. 667.00 4669.00 5395.40
Materials Cement 0.400 MT 15940.00 6376.00
Sand 0.425 Cub M 2787.12 1184.53
20 mm aggregate 0.570 Cub M 2716.56 1548.44
10 mm aggregate 0.290 Cub M 2540.16 736.65 9845.61
Actual rate 15241.01
Rate 15% contractor's overhead 2286.15
Per cum. Per cft. Total 17527.16
15241.01 432.00
47. 1:1:2 P.C.C. work in superstructure slab, beams, columns, lintels etc. with transportation up to 30m
(1 cu.m./ 35.28 cft )
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 0.800 Nos. 908.00 726.40
b) Coolies 7.000 Nos. 667.00 4669.00 5395.40
Materials Cement 0.610 MT 15940.00 9723.40
Sand 0.425 Cub M 2787.12 1184.53
20 mm aggregate 0.640 Cub M 2716.56 1738.60
10 mm aggregate 0.210 Cub M 2540.16 533.43 13179.96
Actual rate 18575.36
Rate 15% contractor's overhead 2786.30
Per cum. Per cft. Total 21361.66
18575.36 526.51
48. Curtail, bent up, binding of MS bars according to the drawing for RCC and its transportation up to 30m
( 1 MT =1000 kg )
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 12.000 Nos. 908.00 10896.00
b) Coolies 12.000 Nos. 667.00 8004.00 18900.00
Materials Tor steel/MS bar 1.050 MT 75000.00 78750.00
Binding Wires 10.000 Kg 87.22 872.20 79622.20
Actual rate 98522.20
Rate 15% contractor's overhead 14778.33
Per mt Per kg Total 113300.53
98522.20 98.52
49. 6.35cm thick Reinforced Brick work in 1:3 cement mortar in superstructure slab, lintels etc. with transportation
upto 30m(for 10 sq.m./ 107.58sft )
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.150 Nos. 908.00 1044.20
b) Coolies 3.000 Nos. 667.00 2001.00 3045.20
Materials Cement 0.100 MT 15940.00 1594.00
Sand 0.200 Cub M 2787.12 557.42
Local Bricks 377.000 Nos. 14.00 5278.00 7429.42
Actual rate 10474.62
Rate 15% contractor's overhead 1571.19
Per sqm. Per sft Total 12045.82
1047.46 97.37
_______________
____________ _______________
Approved By
Prepared By Checked By
Rate Analysis
F. Form Work
50. Form work for beams, slab in structure including, screening, fitting, oiling, dismantling, removing and transportation up to 30m
( 10 sq.m./ 107.58 sft )
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.720 Nos. 908.00 1561.76
b) Coolies 2.570 Nos. 667.00 1714.19 3275.95
Materials Wood (Local/Normal)* 0.070 Cub M 44452.80 3111.70
Nails 2.500 Kg 109.00 272.50 3384.20
Actual rate 6660.15
Rate 15% contractor's overhead 999.02
Per sqm. Per sft. Total 7659.17
666.01 61.91
* Asume that timber and ballies will become unserviceable after being used for 6 Times
\ Qty. of material = 0.526/8 = 0.07 Cu. m.
51. Column post fitting and dismantling, removing with supplying wood and transporting upto 30m ( 10 sq.m./ 107.58 sft )
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 3.748 Nos. 908.00 3403.18
b) Coolies 5.622 Nos. 667.00 3749.87 7153.06
Materials Wood (Ordinary) 0.070 Cub M 44452.80 3111.70
Nails 2.500 Kg 109.00 272.50 3384.20
Actual rate 10537.25
Rate 15% contractor's overhead 1580.59
Per sqm. Per sft. Total 12117.84
1053.73 97.95
52. Form work for structural beams installlation and dismantling, removing and transporting upto 30m & up to 0.3m Ht of beams
( 10 sq.m./ 107.58 sft )
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 4.000 Nos. 908.00 3632.00
b) Coolies 6.000 Nos. 667.00 4002.00 7634.00
Materials Wood (Local/Normal)* 0.070 Cub M 44452.80 3111.70
Nails 2.500 Kg 109.00 272.50 3384.20
Actual rate 11018.20
Rate 15% contractor's overhead 1652.73
Per sqm. Per sft. Total 12670.93
1101.82 102.42
53. Form work for structural beams installlation and dismantling, removing and transporting upto 30m
(0.3m to 0.8m Ht of beams) ( 10 sq.m./ 107.58 sft )
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 2.670 Nos. 908.00 2424.36
b) Coolies 4.000 Nos. 667.00 2668.00 5092.36
Materials Wood (Local/Normal)* 0.070 Cub M 44452.80 3111.70
Nails 2.500 Kg 109.00 272.50 3384.20
Actual rate 8476.56
Rate 15% contractor's overhead 1271.48
Per sqm. Per sft. Total 9748.04
847.66 78.79
54. Form work for trench shuttering upto 1.5 to 3.0m depth and transporting upto 30m (100 sq.m./ 1075.8 sft )
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 0.500 Nos. 908.00 454.00
b) Coolies 1.000 Nos. 667.00 667.00 1121.00
Materials Planks 4.160 Sq M 578.78 2407.72
55. Form work for open trench protection depth over 3.0m and transporting upto 30m ( 100 sq.m./ 1075.8 sft )
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.000 Nos. 908.00 908.00
b) Coolies 1.750 Nos. 667.00 1167.25 2075.25
Materials Planks 4.160 Sq M 578.78 2407.72
Walling Strut Wood
(Local/Normal) 0.254 Cub M 44452.80 11277.68 13685.40
Actual rate 15760.65
Rate 15% contractor's overhead 2364.10
Per sqm. Per sft. Total 18124.75
157.61 14.65
_______________
____________ _______________
Approved By
Prepared By Checked By
Rate Analysis
G. Roof Covering
56. CGI Sheet Roofing with supplying all materials (26 Gauge medium CGI) (10sq.m / 107.58 sq. ft)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.100 Nos. 908.00 998.80
b) Unskilled 1.250 Nos. 667.00 833.75 1832.55
CGI Sheet (26 Gauge) 12.000 Sq M 369.44 4433.30
Materials 8mm Nut Bolt 30.000 Nos. 28.00 840.00
J-Hook 25.000 Nos. 19.00 475.00
Bitumin washer 25.000 Nos. 3.00 75.00 5823.30
Actual rate 7655.85
Rate 15% contractor's overhead 1148.38
Per sqm. Per sft. Total 8804.23
765.59 71.16
57.Fixing GI plain Sheet (0.28mm) Ridge cover with supplying all materials (10Rm / 3.28 ft)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 2.000 Nos. 908.00 1816.00
b) Unskilled 3.000 Nos. 667.00 2001.00 3817.00
GI Sheet (28Gauge) 12.000 R M 304.63 3655.56
Materials 8mm Nut Bolt L.S. 28.00 28.00 3683.56
Actual rate 7500.56
Rate 15% contractor's overhead 1125.08
Per Rm. Per rft. Total 8625.64
750.06 228.68
58. Coloured CGI Sheet (26 Gauge medium) Roofing with supplying all materials (10sq.m / 107.58 sq. ft)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.100 Nos. 908.00 998.80
b) Unskilled 1.250 Nos. 667.00 833.75 1832.55
* CGI Sheet(0.35mm th total) 12.000 Sq M 455.56 5466.73
Materials 8mm Nut Bolt 30.000 Nos. 28.00 840.00
J-Hook 25.000 Nos. 19.00 475.00
Bitumin washer 25.000 Nos. 3.00 75.00 6856.73
Actual rate 8689.28
Rate 15% contractor's overhead 1303.39
Per sqm. Per sft. Total 9992.68
868.93 80.77
* 0.37mm base metal thickness(i.e.add 2mm for total thickness)
59.Fixing Coloured GI plain Sheet (0.35mm) Ridge cover with supplying all materials (10Rm / 3.28 ft)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 2.000 Nos. 908.00 1816.00
b) Unskilled 3.000 Nos. 667.00 2001.00 3817.00
GI Sheet(0.43mm) 12.000 R M 439.11 5269.32
Materials 8mm Nut Bolt L.S. 28.00 28.00 5297.32
Actual rate 9114.32
Rate 15% contractor's overhead 1367.15
Per Rm. Per rft. Total 10481.47
911.43 277.88
60.1:1:3 (Lime surki brk agg)10cm thick Lime concrete terracing work with supplying all materials (10sq.m / 107.58 sq. ft)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.500 Nos. 908.00 1362.00
b) Unskilled 12.000 Nos. 667.00 8004.00 9366.00
Brick Agg. 1.250 Cub M 1155.77 1444.71
Materials Lime 1.500 Cub M 16800.00 25200.00
Surki 0.400 Cub M 1541.03 616.41 27261.12
Actual rate 36627.12
Rate 15% contractor's overhead 5494.07
Per sqm. Per sft. Total 42121.19
3662.71 340.46
H. Wood Work
61. 20 cm thick wood Ceiling work, plankings with 40x20mm Biding Joint with supplying all materials (10sq.m / 107.58 sq. ft)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.880 Nos. 908.00 1707.04
b) Unskilled 1.500 Nos. 667.00 1000.50 2707.54
Wood Saal 0.260 Cub M 194040.00 50450.40
Materials Nails 0.400 Kg. 109.00 43.60
40mm screw 160.000 Nos. 1.00 160.00 50654.00
Actual rate 53361.54
Rate 15% contractor's overhead 8004.23
Per sqm. Per sft. Total 61365.77
5336.15 496.02
_______________
____________ _______________
Approved By
Prepared By Checked By
Rate Analysis
62. Sal wood work for choukosh[0.9x2.1m size &0.1x0.075m section] ( 1cu.m./ 35.28 cft )
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 34.000 Nos. 908.00 30872.00
b) Coolies 3.400 Nos. 667.00 2267.80 33139.80
Materials Sal wood 1.100 Cub M 194040.00 213444.00
Hold fast 92.000 Nos. 17.29 1590.29
Screw 184.000 Nos. 1.00 184.00 215218.29
Actual rate 248358.09
Rate 15% contractor's overhead 37253.71
Per cum. Per cft. Total 285611.80
248358.09 7039.63
63. 38 mm thick Salwood solid pannel shutter (size 1.07m x 1.982m = 2.114 sq.m.) Rate analysis for 2.114 sq.m. / 22.7255 sft.
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 10.000 Nos. 908.00 9080.00
b) Coolies 1.000 Nos. 667.00 667.00 9747.00
Materials Sal wood 0.084 Cub M 194040.00 16299.36
100mm hinges 6.000 Nos. 27.00 162.00
150mm tower bolt 1.000 No 65.00 65.00
300mm tower bolt 1.000 No 103.00 103.00
300mm locking set 1.000 No 252.00 252.00
Handles (Good Quality) 2.000 Nos. 46.00 92.00
Screw nails 1.000 LS 20.00 20.00 16993.36
Actual rate 26740.36
Rate 15% contractor's overhead 4011.05
Per sqm. Per sft. Total 30751.41
12649.18 1175.79
64 . Openable glazed shutter with 38 x 75mm sal wood frame & 3 mm thick glass
(for rate analysis 1.829 x 1.22 = 2.23 sq m / 23.97 sft. )
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 9.000 Nos. 908.00 8172.00
b) Coolies 0.900 Nos. 667.00 600.30 8772.30
Materials Sal wood 0.049 Cub M 194040.00 9507.96
3 mm glass 1.085 sq.m. 537.50 583.19
75mm hinges 8.000 Nos. 15.00 120.00
100mm tower bolt 4.000 Nos. 39.00 156.00
Handles (Good Quality) 2.000 Nos. 46.00 92.00
Screw nails 1.000 LS 20.00 20.00 10479.15
Actual rate 19251.45
Rate 15% contractor's overhead 2887.72
Per sqm. Per sft. Total 22139.16
8632.94 802.47
65 . Openable glazed shutter with 38 x 75mm sal wood frame & 4 mm thick glass
(for rate analysis 1.829 x 1.22 = 2.23 sq m / 23.97 sft. )
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 9.000 Nos. 908.00 8172.00
b) Coolies 0.900 Nos. 667.00 600.30 8772.30
Materials Sal wood 0.049 Cub M 194040.00 9507.96
4 mm glass 1.085 sq.m. 688.00 746.48
75mm hinges 8.000 Nos. 15.00 120.00
100mm tower bolt 4.000 Nos. 39.00 156.00
Handles (Good Quality) 2.000 Nos. 46.00 92.00
Screw nails 1.000 LS 20.00 20.00 10642.44
Actual rate 19414.74
Rate 15% contractor's overhead 2912.21
Per sqm. Per sft. Total 22326.95
8706.16 809.27
_______________
____________ _______________
Approved By
Prepared By Checked By
Rate Analysis
66. Openable glazed shutter with 38 x 75mm sal wood frame &5 mm thick glass
(for rate analysis 1.829 x 1.22 = 2.23 sq m / 23.97 sft. )
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 9.000 Nos. 908.00 8172.00
b) Coolies 0.900 Nos. 667.00 600.30 8772.30
Materials Sal wood 0.049 Cub M 194040.00 9507.96
5 mm glass 1.085 sq.m. 924.50 1003.08
75mm hinges 8.000 Nos. 15.00 120.00
100mm tower bolt 4.000 Nos. 39.00 156.00
Handles (Good Quality) 2.000 Nos. 46.00 92.00
Screw nails 1.000 LS 20.00 20.00 10899.04
Actual rate 19671.34
Rate 15% contractor's overhead 2950.70
Per sqm. Per sft. Total 22622.04
8821.23 819.97
67 . Openable glazed shutter with 38 x 75mm sal wood frame & 6 mm thick glass
(for rate analysis 1.829 x 1.22 = 2.23 sq m / 23.97 sft. )
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 9.000 Nos. 908.00 8172.00
b) Coolies 0.900 Nos. 667.00 600.30 8772.30
Materials Sal wood 0.049 Cub M 194040.00 9507.96
6 mm glass 1.085 sq.m. 1075.00 1166.38
75mm hinges 8.000 Nos. 15.00 120.00
100mm tower bolt 4.000 Nos. 39.00 156.00
Handles (Good Quality) 2.000 Nos. 46.00 92.00
Screw nails 1.000 LS 20.00 20.00 11062.34
Actual rate 19834.64
Rate 15% contractor's overhead 2975.20
Per sqm. Per sft. Total 22809.83
8894.46 826.78
68. Flush shutter 38mm thick sal wood frame with 4mm thick commercial plywood on both side of shutter
(for rate analysis 1.092 x 2.058 = 2.245sq m/24.13 sft)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 7.000 Nos. 908.00 6356.00
b) Coolies 0.700 Nos. 667.00 466.90 6822.90
Materials Sal wood 0.0346 Cub M 194040.00 6713.78
4mm com.plywood 4.650 sq.m. 247.25 1149.71
100mm hinges 3.000 Nos. 27.00 81.00
150mm tower bolt 2.000 Nos. 65.00 130.00
Mortish lock 1.000 Nos. 404.00 404.00
Screw nails 1.000 LS 20.00 20.00 8498.50
Actual rate 15321.40
Rate Rate 15% contractor's overhead 2298.21
Per sqm. Per sft. Total 17619.61
6824.68 634.38
69.3. Flush shutter 38mm thick sal wood frame with 3mm thick teak plywood on both side of shutter
(for rate analysis 1.092 x 2.058 = 2.245sq m/24.13 sft)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 7.000 Nos. 908.00 6356.00
b) Coolies 0.700 Nos. 667.00 466.90 6822.90
Materials Sal wood 0.0346 Cub M 194040.00 6713.78
3mm teak ply 4.650 sq.m. 602.00 2799.30
100mm hinges 3.000 Nos. 27.00 81.00
150mm tower bolt 2.000 Nos. 65.00 130.00
Mortish lock 1.000 Nos. 404.00 404.00
Screw nails 1.000 LS 20.00 20.00 10148.08
Actual rate 16970.98
Rate Rate 15% contractor's overhead 2545.65
Per sqm. Per sft. Total 19516.63
7559.46 702.68
70. a.38mm thick sal wood shutter with 28 Gauge GI Plain Sheet on both side of shutter
(for rate analysis 1.092 x 2.058 = 2.245sq m/24.13 sft)
_______________
____________ _______________
Approved By
Prepared By Checked By
Rate Analysis
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 7.000 Nos. 908.00 6356.00
b) Coolies 0.700 Nos. 667.00 466.90 6822.90
Materials Sal wood 0.0346 Cub M 194040.00 6713.78
28 Gauge GI Sheet 4.650 sq.m. 74.98 348.68
100mm hinges 3.000 Nos. 27.00 81.00
150mm tower bolt 2.000 Nos. 65.00 130.00
Mortish lock 1.000 Nos. 404.00 404.00
Screw nails 1.000 LS 20.00 20.00 7697.46
Actual rate 14520.36
Rate Rate 15% contractor's overhead 2178.05
Per sqm. Per sft. Total 16698.42
6467.87 601.21
71. G.I. mosquito proof wire mess (24gauge) shutter works with 38mm thick sal wood frame
(for rate analysis 1.092 x 2.058 = 2.245sq m/24.13 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 5.000 Nos. 908.00 4540.00
b) Coolies 0.500 Nos. 667.00 333.50 4873.50
Materials Sal wood 0.026 Cub M 194040.00 5045.04
24 gau.GI wiremess 2.130 sq.m. 116.00 247.08
100mm hinges 3.000 Nos 27.00 81.00
150mm tower bolt 2.000 Nos 65.00 130.00
Handles (Good Quality) 2.000 Nos 46.00 92.00
Spring (simple) 1.000 No 173.00 173.00
Screw nails 1.000 LS 15.00 15.00 5783.12
Actual rate 10656.62
Rate 15% contractor's overhead 1598.49
Per sqm. Per sft. Total 12255.11
4746.82 441.24
72 . Fixed glazed shutter with 3 mm thick glass (for 1 sq.m 10.76 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 0.060 Nos. 908.00 54.48
b) Coolies 0.006 Nos. 667.00 4.00 58.48
Materials 3 mm thick glass 1.000 S.m. 537.50 537.50
wooden listy 4.050 m 28.00 113.40
Screw nails 1.000 LS 15.00 15.00 665.90
Actual rate 724.38
Rate Rate 15% contractor's overhead 108.66
Per sqm. Per sft. Total 833.04
724.38 67.32
73. Fixed glazed shutter with 4 mm thick glass (for 1 sq.m 10.76 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 0.060 Nos. 908.00 54.48
b) Coolies 0.006 Nos. 667.00 4.00 58.48
Materials 4 mm thick glass 1.000 S.m. 688.00 688.00
wooden listy 4.050 m 28.00 113.40
Screw nails 1.000 LS 15.00 15.00 816.40
Actual rate 874.88
Rate Rate 15% contractor's overhead 131.23
Per sqm. Per sft. Total 1006.11
874.88 81.31
74. Fixed glazed shutter with 5 mm thick glass ( for 1 sq.m 10.76 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 0.060 Nos. 908.00 54.48
b) Coolies 0.006 Nos. 667.00 4.00 58.48
Materials 5 mm thick glass 1.000 S.m. 924.50 924.50
wooden listy 4.050 m 28.00 113.40
Screw nails 1.000 LS 15.00 15.00 1052.90
Actual rate 1111.38
Rate Rate 15% contractor's overhead 166.71
Per sqm. Per sft. Total 1278.09
1111.38 103.29
_______________
____________ _______________
Approved By
Prepared By Checked By
Rate Analysis
75. Fixed glazed shutter with 6 mm thick glass (for 1 sq.m 10.76 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 0.060 Nos. 908.00 54.48
b) Coolies 0.006 Nos. 667.00 4.00 58.48
Materials 6 mm thick glass 1.000 S.m. 1075.00 1075.00
wooden listy 4.050 m 28.00 113.40
Screw nails 1.000 LS 15.00 15.00 1203.40
Actual rate 1261.88
Rate Rate 15% contractor's overhead 189.28
Per sqm. Per sft. Total 1451.16
1261.88 117.28
76 . Wooden partition with frames of 38x75 mm sections on 0.61x0.915m rooms fixed with commercial ply both side fixing with listy
9.75mx3.65m=35.58sqm (382.84sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 23.000 Nos. 908.00 20884.00
b) Coolies 2.300 Nos. 667.00 1534.10 22418.10
Materials Wood Local 0.350 Cum 44452.80 15558.48
4mm ply 75.000 sqm 247.25 18543.75
wooden listy 100.000 Rm 28.00 2800.00
Ordinary nails 2.000 Kg 109.00 218.00 37120.23
Actual rate 59538.33
Rate Rate 15% contractor's overhead 8930.75
Per sqm. Per sft. Total 68469.08
1673.37 155.52
_______________
____________ _______________
Approved By
Prepared By Checked By
Rate Analysis
77 . Wooden partition with frames of 38x75 mm sections on 0.61x0.915m rooms fixed with 12mm thick hard board both side fixing
with listy
9.75mx3.65m=35.58sqm (382.84sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 23.000 Nos. 908.00 20884.00
b) Coolies 2.300 Nos. 667.00 1534.10 22418.10
Materials Wood 0.340 Cum 44452.80 15113.95
Hard board 75.000 sqm 451.50 33862.50
wooden listy 100.000 Rm 28.00 2800.00
Ordinary nails 2.000 Kg 109.00 218.00 51994.45
Actual rate 74412.55
Rate Rate 15% contractor's overhead 11161.88
Per sqm. Per sft. Total 85574.43
2091.42 194.37
78. Wooden partition with frames of 38x75 mm sections on 0.61x0.915m rooms fixed with 19mm thick planks both side in lap joint
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 30.000 Nos. 908.00 27240.00
b) Coolies 3.000 Nos. 667.00 2001.00 29241.00
Materials Wood Local 1.767 Cum 44452.80 78548.10
wooden listy 100.000 Rm 28.00 2800.00
Ordinary nails 2.000 Kg 109.00 218.00 81566.10
Actual rate 110807.10
Rate Rate 15% contractor's overhead 16621.06
Per sqm. Per sft. Total 127428.16
3114.31 289.43
79 . False ceiling with 50x75 mm sections sisau wood with 600x900mm openings fixed with 4mm thick Commercial plywood
9.75mx3.65m=35.58sqm (382.84sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 23.000 Nos. 908.00 20884.00
b) Coolies 2.300 Nos. 667.00 1534.10 22418.10
Materials Sisau Wood 0.450 Cum 92010.24 41404.61
4mm Ply 37.500 sqm 247.25 9271.88
wooden listy 100.000 Rm 28.00 2800.00
Ordinary nails 1.500 Kg 109.00 163.50 53639.98
Actual rate 76058.08
Rate Rate 15% contractor's overhead 11408.71
Per sqm. Per sft. Total 87466.80
2137.66 198.67
80. False ceiling with 50x75 mm sections sal wood with 600x900mm openings fixed with 3mm thick Asbetos plain sheets
9.75mx3.65m=35.58sqm (382.84sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 23.000 Nos. 908.00 20884.00
b) Coolies 2.300 Nos. 667.00 1534.10 22418.10
Materials Sisau Wood 0.450 Cum 92010.24 41404.61
3mm asbetos sheet 37.500 sqm 329.26 12347.25
wooden listy 100.000 Rm 28.00 2800.00
Ordinary nails 1.500 Kg 109.00 163.50 56715.36
Actual rate 79133.46
Rate Rate 15% contractor's overhead 11870.02
Per sqm. Per sft. Total 91003.48
2224.10 206.70
81. False ceiling with 50x75 mm sections sisau wood with 600x900mm openings fixed with 12mm thick Hard board
9.75mx3.65m=35.58sqm (382.84sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 23.000 Nos. 908.00 20884.00
b) Coolies 2.300 Nos. 667.00 1534.10 22418.10
Materials Sisau Wood 0.450 Cum 92010.24 41404.61
Hard board 12 mm 37.500 sqm 451.50 16931.25
wooden listy 100.000 Rm 28.00 2800.00
Ordinary nails 1.500 Kg 109.00 163.50 61299.36
Actual rate 83717.46
Rate Rate 15% contractor's overhead 12557.62
Per sqm. Per sft. Total 96275.08
2352.94 218.67
_______________
____________ _______________
Approved By
Prepared By Checked By
Rate Analysis
I. Flooring works
86. 38mm(11/2") thick 1:2:4 Cement Concrete FLooring and finishing with neat cement coat (for 10 sqm /107.58 sft)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.250 Nos. 908.00 1135.00
b) Coolies 2.000 Nos. 667.00 1334.00 2469.00
Materials Cement 0.130 MT 15940.00 2072.20
Sand 0.180 Cub M 2787.12 501.68
12 mm aggregate 0.360 Cub M 2716.56 977.96 3551.84
Actual rate 6020.84
Rate 15% contractor's overhead 903.13
Per sqm. Per sft. Total 6923.97
602.08 55.97
_______________
____________ _______________
Approved By
Prepared By Checked By
Rate Analysis
87. 50mm(2") thick 1:2:4 Cement Concrete FLooring and finishing with neat cement coat (for 10 sqm/ 107.58 sft)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.250 Nos. 908.00 1135.00
b) Coolies 2.500 Nos. 667.00 1667.50 2802.50
Materials Cement 0.170 MT 15940.00 2709.80
Sand 0.230 Cub M 2787.12 641.04
12 mm aggregate 0.460 Cub M 2716.56 1249.62 4600.46
Actual rate 7402.96
Rate 15% contractor's overhead 1110.44
Per sqm. Per sft. Total 8513.40
740.30 68.81
88. 75mm(3") thick 1:2:4 Cement Concrete FLooring and finishing with neat cement coat (for 10 sqm /107.58 sft)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.250 Nos. 908.00 1135.00
b) Coolies 3.000 Nos. 667.00 2001.00 3136.00
Materials Cement 0.260 MT 15940.00 4144.40
Sand 0.340 Cub M 2787.12 947.62
20 mm aggregate 0.680 Cub M 2716.56 1847.26 6939.28
Actual rate 10075.28
Rate 15% contractor's overhead 1511.29
Per sqm. Per sft. Total 11586.57
1007.53 93.65
89. 25mm thick mosaic flooring with 20mm thick cement plaster 1:2:4 cement sand ratio & 5mm thick 1:1 white cement & marble
chipping surface course including by rubbing & polish to finish
(10 sqm/ 107.58 sft )
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 2.500 Nos. 908.00 2270.00
b) Coolies 16.000 Nos. 667.00 10672.00 12942.00
Materials Cement 0.065 mt 15940.00 1036.10
Sand 0.088 cub m 2787.12 245.27
12.5mm aggregate 0.176 cub m 2716.56 478.11
White cement 0.061 Mt 26375.00 1608.88
Marble chips 0.061 Mt 13728.00 837.41
Axalic acid 0.365 kg 115.00 41.98
Wax polish 0.118 kg 200.00 23.60
Turpentine 0.538 lit. 229.00 123.20
Carborendom stone 1.000 LS 150.00 150.00 4544.54
Actual rate 17486.54
Rate 15% contractor's overhead 2622.98
Per sqm. Per sft. Total 20109.52
1748.65 162.54
90. 25mm thick mosaic flooring with 6mm thick 1:1 white cement & marble chipping over 19mm c/s plaster surface with rubbing &
polish to finish
(10 sqm/ 107.58 sft )
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 3.500 Nos. 908.00 3178.00
b) Coolies 36.000 Nos. 667.00 24012.00 27190.00
Materials Cement 0.121 mt 15940.00 1928.74
Sand 0.165 cub m 2787.12 459.87
White cement 0.069 Mt 26375.00 1819.88
Marble chips 3mm 0.047 Mt 13728.00 645.22
Axalic acid 0.340 kg 115.00 39.10
Wax polish 0.110 kg 200.00 22.00
turpentine 0.500 lit. 229.00 114.50
Carborendom stone 1.000 LS 150.00 150.00 5179.31
Actual rate 32369.31
Rate 15% contractor's overhead 4855.40
Per sqm. Per sft. Total 37224.70
3236.93 300.89
_______________
____________ _______________
Approved By
Prepared By Checked By
Rate Analysis
91. 20mm thick mosaic flooring with 6mm thick 1:1 white cement & marble chipping over 12.5mm1:2 c/s plaster surface with
rubbing & polish to finish
(10 sqm/ 107.58 sft )
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 3.500 Nos. 908.00 3178.00
b) Coolies 36.000 Nos. 667.00 24012.00 27190.00
Materials Cement 0.089 mt 15940.00 1418.66
Sand 0.122 cub m 2787.12 340.03
White cement 0.089 Mt 26375.00 2347.38
Marble chips 3mm 0.061 Mt 13728.00 837.41
Axalic acid 0.365 kg 115.00 41.98
Wax polish 0.118 kg 200.00 23.60
turpentine 0.538 lit. 229.00 123.20
Carborendom stone 1.000 LS 150.00 150.00 5282.25
Actual rate 32472.25
Rate 15% contractor's overhead 4870.84
Per sqm. Per sft. Total 37343.09
3247.22 301.84
92. 20mm terrazo tile over 20mm1:4 c/s plaster surface with rubbing & polish to finish (10 sqm/ 107.58 sft )
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 2.000 Nos. 908.00 1816.00
b) Coolies 12.600 Nos. 667.00 8404.20 10220.20
Materials Cement 0.081 mt 15940.00 1291.14
Sand 0.220 cub m 2787.12 613.17
20mm terrazotile 11.000 Sq M 516.00 5676.00
Axalic acid 0.365 kg 115.00 41.98
Wax polish 0.118 kg 200.00 23.60
turpentine 0.538 lit. 229.00 123.20
Carborendom stone 1.000 LS 150.00 150.00
Rubbing unskilled labour 13.500 Nos. 667.00 9004.50 16923.58
Actual rate 27143.78
Rate 15% contractor's overhead 4071.57
Per sqm. Per sft. Total 31215.35
2714.38 252.31
93. 15mm thick marble (450x450mm) over 20mm1:2 surki with rubbing & polish to finish also (10 sqm/ 107.58 sft )
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 2.000 Nos. 908.00 1816.00
b) Coolies 8.000 Nos. 667.00 5336.00 7152.00
Materials Lime 0.091 Cub M 16800.00 1528.80
25mm marble 11.000 Sq M 1644.75 18092.25
Surki 0.183 Cub M 1541.03 282.01
Axalic acid 0.370 kg 115.00 42.55
Wax polish 0.118 kg 200.00 23.60
turpentine 0.538 lit. 229.00 123.20
Carborendom stone 1.000 LS 150.00 150.00
Rubbing unskilled labour 13.500 Nos. 667.00 9004.50 29246.91
Actual rate 36398.91
Rate 15% contractor's overhead 5459.84
Per sqm. Per sft. Total 41858.75
3639.89 338.34
94. Porcelain glazed tile over 20mm1:4 c/s mortar (10 sqm/ 107.58 sft )
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 13.000 Nos. 908.00 11804.00
b) Coolies 4.500 Nos. 667.00 3001.50 14805.50
Materials Cement 0.056 mt 15940.00 892.64
Sand 0.152 cub m 2787.12 423.64
White cement 3.228 kg 26.38 85.14
Porcelain glaged tile 11.000 Sq M 709.50 7804.50 9205.92
Actual rate 24011.42
Rate 15% contractor's overhead 3601.71
Per sqm. Per sft. Total 27613.13
2401.14 223.20
95. 50 mm Flagstone paving on 1:4 c/s mortar (10 sqm/ 107.58 sft )
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 2.000 Nos. 908.00 1816.00
b) Coolies 4.500 Nos. 667.00 3001.50 4817.50
Materials Cement 0.063 mt 15940.00 1004.22
Sand 0.171 cub m 2787.12 476.60
50 mm thick flagstone 11.000 Sq M 1182.50 13007.50 14488.32
Actual rate 19305.82
Rate 15% contractor's overhead 2895.87
Per sqm. Per sft. Total 22201.69
1930.58 179.46
_______________
____________ _______________
Approved By
Prepared By Checked By
Rate Analysis
96. 50 mm down Flagstone paving on filled sand (10 sqm/ 107.58 sft )
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.000 Nos. 908.00 908.00
b) Coolies 3.000 Nos. 667.00 2001.00 2909.00
Materials Sand 0.710 cub m 2787.12 1978.86
50 mm down Flagstone 11.000 Sq M 1026.63 11292.88 13271.73
Actual rate 16180.73
Rate 15% contractor's overhead 2427.11
Per sqm. Per sft. Total 18607.84
1618.07 150.41
97. 37.5 mm Flagstone paving on 1:4 cement mortar (10 sqm/ 107.58 sft )
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 2.000 Nos. 908.00 1816.00
b) Coolies 4.500 Nos. 667.00 3001.50 4817.50
Cement 0.060 mt 15940.00 956.40
Materials Sand 0.165 cub m 2787.12 459.87
37.5mm Flagstone 11.000 Sq M 1021.25 11233.75 11693.62
Actual rate 16511.12
Rate 15% contractor's overhead 2476.67
Per sqm. Per sft. Total 18987.79
1651.11 153.48
98. 25 mm Flagstone paving on 1:4 cement mortar (10 sqm/ 107.58 sft )
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.500 Nos. 908.00 1362.00
b) Coolies 4.500 Nos. 667.00 3001.50 4363.50
Cement 0.056 mt 15940.00 892.64
Materials Sand 0.152 cub m 2787.12 423.64
25mm Flagstone 11.000 Sq M 870.75 9578.25 10001.89
Actual rate 14365.39
Rate 15% contractor's overhead 2154.81
Per sqm. Per sft. Total 16520.20
1436.54 133.53
99. 25 mm Telia brick paving in 1:2 surki masala & tipkar in 1:2 cement mortar (10 sqm/ 107.58 sft )
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 4.500 Nos. 908.00 4086.00
b) Coolies 4.500 Nos. 667.00 3001.50 7087.50
Materials Cement 0.016 mt 15940.00 255.04
Sand 0.110 cub m 2787.12 306.58
Lime 0.122 cub m 16800.00 2049.60
Surki 0.244 cub m 1541.03 376.01
Telia Bricks 25mm thick 440.000 Nos. 13.00 5720.00 8707.23
Actual rate 15794.73
Rate 15% contractor's overhead 2369.21
Per sqm. Per sft. Total 18163.94
1579.47 146.82
100. Brick flat soling on 1:6 cement mortar and pointing in 1:2 cement mortar on joints (10 sqm/ 107.58 sft )
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 2.250 Nos. 908.00 2043.00
b) Coolies 3.250 Nos. 667.00 2167.75 4210.75
Cement 0.078 mt 15940.00 1243.32
Materials Sand 0.229 cub m 2787.12 638.25
Local Bricks 430.000 Nos. 14.00 6020.00 7901.57
Actual rate 12112.32
Rate 15% contractor's overhead 1816.85
Per sqm. Per sft. Total 13929.17
1211.23 112.59
101. Brick edge soling on 1:6 cement mortar and pointing in 1:2 cement mortar on joints works (10 sqm/ 107.58 sft )
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.100 Nos. 908.00 998.80
b) Coolies 1.800 Nos. 667.00 1200.60 2199.40
Cement 0.121 mt 15940.00 1928.74
Materials Sand 0.431 cub m 2787.12 1201.25
Local Bricks 750.000 Nos. 14.00 10500.00 13629.99
Actual rate 15829.39
Rate 15% contractor's overhead 2374.41
Per sqm. Per sft. Total 18203.80
1582.94 147.14
_______________
____________ _______________
Approved By
Prepared By Checked By
Rate Analysis
102. Parketting with polishing after rubbing with sand paper works (10 sqm/ 107.58 sft )
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.750 Nos. 908.00 1589.00
b) Coolies 0.750 Nos. 667.00 500.25 2089.25
Parkette 10.500 Sq M 1870.50 19640.25
Materials Sand paper 1.000 LS 30.00 30.00
Wax polish 1.000 LS 50.00 50.00 19720.25
Machine to rub machine to sand paper 2.000 Hrs 150.00 300.00 300.00
Actual rate 22109.50
Rate 15% contractor's overhead 3316.43
Per sqm. Per sft. Total 25425.93
2210.95 205.52
103. Dry flat brick soling works (10 sqm/ 107.58 sft )
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 0.500 Nos. 908.00 454.00
b) Coolies 1.000 Nos. 667.00 667.00 1121.00
Local Bricks 420.000 Sq M 14.00 5880.00
Materials Sand 0.710 Cum 2787.12 1978.86 7858.86
Actual rate 8979.86
Rate 15% contractor's overhead 1346.98
Per sqm. Per sft. Total 10326.83
897.99 83.47
104. Dry edge brick soling works (10 sqm/ 107.58 sft )
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.000 Nos. 908.00 908.00
b) Coolies 3.250 Nos. 667.00 2167.75 3075.75
Bricks 750.000 Sq M 14.00 10500.00
Materials Sand 0.710 Cum 2787.12 1978.86 12478.86
Actual rate 15554.61
Rate 15% contractor's overhead 2333.19
Per sqm. Per sft. Total 17887.80
1555.46 144.59
106. 125mm Edge Brick soling and pointing works in 1:3cement mortar on joints after sand filling (10 sqm/ 107.58 sft )
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 2.000 Nos. 908.00 1816.00
b) Coolies 4.000 Nos. 667.00 2668.00 4484.00
Materials Cement 0.020 Mt 15940.00 318.80
Sand 0.710 Cum 2787.12 1978.86
Bricks 750.000 Nos. 14.00 10500.00 12797.66
Actual rate 17281.66
Rate 15% contractor's overhead 2592.25
Per sqm. Per sft. Total 19873.90
1728.17 160.64
_______________
____________ _______________
Approved By
Prepared By Checked By
Rate Analysis
107. Pointing in 1:1cement mortar on joints works on paved stone 46cm X46cm (10 sqm/ 107.58 sft )
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 0.500 Nos. 908.00 454.00
b) Coolies 0.500 Nos. 667.00 333.50 787.50
Materials Cement 4.200 Kg 15.94 66.95
Sand 0.003 Cum 2787.12 8.36 75.31
Actual rate 862.81
Rate 15% contractor's overhead 129.42
Per sqm. Per sft. Total 992.23
86.28 8.02
110. 3mm thick thin layer cement Punning (chipping )works (10 sqm/ 107.58 sft )
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.000 Nos. 908.00 908.00
b) Coolies 1.000 Nos. 667.00 667.00 1575.00
Materials Cement 53.200 Kg 15.94 848.01 848.01
Actual rate 2423.01
Rate 15% contractor's overhead 363.45
Per sqm. Per sft. Total 2786.46
242.30 22.52
_______________
____________ _______________
Approved By
Prepared By Checked By
Rate Analysis
112. 12.5mm 1:4cement sand plaster works on ceiling (for 100 sq.m/1075.8 sft.)
Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 15.000 Nos. 908.00 13620.00
b) Coolies 20.000 Nos. 667.00 13340.00 26960.00
Materials Cement 0.538 MT 15940.00 8575.72
Sand 1.460 Cub M 2787.12 4069.20 12644.92
Actual rate 39604.92
Rate 15% contractor's overhead 5940.74
Per sqm. Per sft. Total 45545.65
396.05 36.81
113. 12.5mm 1:4 cement sand plaster works except in ceiling (for 100 sq.m/1075.8 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 12.000 Nos. 908.00 10896.00
b) Coolies 16.000 Nos. 667.00 10672.00 21568.00
Materials Cement 0.538 Mt 15940.00 8575.72
Sand 1.460 Cub M 2787.12 4069.20 12644.92
Actual rate 34212.92
Rate 15% contractor's overhead 5131.94
Per sqm. Per sft. Total 39344.85
342.13 31.80
114. 12.5mm 1:6 cement sand plaster works (for 100 sq.m/1075.8 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 12.000 Nos. 908.00 10896.00
b) Coolies 16.000 Nos. 667.00 10672.00 21568.00
Materials Cement 0.382 Mt 15940.00 6089.08
Sand 1.570 Cub M 2787.12 4375.78 10464.86
Actual rate 32032.86
Rate 15% contractor's overhead 4804.93
Per sqm. Per sft. Total 36837.79
320.33 29.78
115. 12.5mm 1:2 Lime surki plaster works (for 100 sq.m/1075.8 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 12.000 Nos. 908.00 10896.00
b) Coolies 16.000 Nos. 667.00 10672.00 21568.00
Materials Lime 0.610 Cub M 16800.00 10248.00
Surki 1.220 Cub M 1541.03 1880.06 12128.06
Actual rate 33696.06
Rate 15% contractor's overhead 5054.41
Per sqm. Per sft. Total 38750.47
336.96 31.32
116. 20mm 1:3 cement sand plaster works (for 100 sq.m/1075.8 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 14.000 Nos. 908.00 12712.00
b) Coolies 19.000 Nos. 667.00 12673.00 25385.00
Materials Cement 0.960 Mt 15940.00 15302.40
Sand 1.950 Cub M 2787.12 5434.88 20737.28
Actual rate 46122.28
Rate 15% contractor's overhead 6918.34
Per sqm. Per sft. Total 53040.63
461.22 42.87
117. 20mm 1:4cement sand plaster works except in ceiling (for 100 sq.m/1075.8 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 14.000 Nos. 908.00 12712.00
b) Coolies 19.000 Nos. 667.00 12673.00 25385.00
Materials Cement 0.810 mt 15940.00 12911.40
Sand 2.200 Cub M 2787.12 6131.66 19043.06
Actual rate 44428.06
Rate 15% contractor's overhead 6664.21
Per sqm. Per sft. Total 51092.27
444.28 41.30
_______________
____________ _______________
Approved By
Prepared By Checked By
Rate Analysis
118. 20mm 1:6 cement sand plaster works except in ceiling (for 100 sq.m/1075.8 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 14.000 Nos. 908.00 12712.00
b) Coolies 19.000 Nos. 667.00 12673.00 25385.00
Materials Cement 0.570 mt 15940.00 9085.80
Sand 2.350 Cub M 2787.12 6549.73 15635.53
Actual rate 41020.53
Rate 15% contractor's overhead 6153.08
Per sqm. Per sft. Total 47173.61
410.21 38.13
119. 25mm mud plaster works with preparation of mud and surface etc. 30m lead (for 100 sq.m/1075.8 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 20.000 Nos. 908.00 18160.00
b) Coolies 25.000 Nos. 667.00 16675.00 34835.00
Materials Mud 3.000 Cub M 260.00 780.00
Rice straw 10.000 Kg. 5.00 50.00
Cow Dung 120.000 Kg. 4.80 576.00 1406.00
Actual rate 36241.00
Rate 15% contractor's overhead 5436.15
Per sqm. Per sft. Total 41677.15
362.41 33.69
120. 12 mm mud plaster works with preparation of mud and surface etc. 30m lead (for 100 sq.m/1075.8 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 15.000 Nos. 908.00 13620.00
b) Coolies 20.000 Nos. 667.00 13340.00 26960.00
Materials Mud 1.500 Cub M 260.00 390.00
Rice straw 50.000 Kg. 5.00 250.00
Cow Dung 60.000 Kg. 4.80 288.00 928.00
Actual rate 27888.00
Rate 15% contractor's overhead 4183.20
Per sqm. Per sft. Total 32071.20
278.88 25.92
K. Painting Work
121. 2 coat white washing works in ceiling on new surface (for 100 sq.m/1075.8 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.875 Nos. 908.00 1702.50
b) Coolies 1.375 Nos. 667.00 917.13 2619.63
Materials Gum 0.880 Kg. 217.00 190.96
White Lime 22.000 Kg. 21.00 462.00 652.96
Actual rate 3272.59
Rate 15% contractor's overhead 490.89
Per sqm. Per sft. Total 3763.47
32.73 3.04
122. 2 coat white washing works on other new surface (for 100 sq.m/1075.8 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.500 Nos. 908.00 1362.00
b) Coolies 1.100 Nos. 667.00 733.70 2095.70
Materials Gum 0.880 Kg. 217.00 190.96
White Lime 22.000 Kg. 21.00 462.00 652.96
Actual rate 2748.66
Rate 15% contractor's overhead 412.30
Per sqm. Per sft. Total 3160.96
27.49 2.55
123. 3 coat white washing works in ceiling on new surface (for 100 sq.m/1075.8 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 3.750 Nos. 908.00 3405.00
b) Coolies 3.375 Nos. 667.00 2251.13 5656.13
Materials Gum 1.280 Kg. 217.00 277.76
White Lime 32.000 Kg. 21.00 672.00 949.76
Actual rate 6605.89
Rate 15% contractor's overhead 990.88
Per sqm. Per sft. Total 7596.77
66.06 6.14
_______________
____________ _______________
Approved By
Prepared By Checked By
Rate Analysis
124. 3 coat white washing works on other new surface (for 100 sq.m/1075.8 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 3.000 Nos. 908.00 2724.00
b) Coolies 2.700 Nos. 667.00 1800.90 4524.90
Materials Gum 1.280 Kg. 217.00 277.76
White Lime 32.000 Kg. 21.00 672.00 949.76
Actual rate 5474.66
Rate 15% contractor's overhead 821.20
Per sqm. Per sft. Total 6295.86
54.75 5.09
125. One White washing works on old surface (for 100 sq.m/1075.8 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 0.800 Nos. 908.00 726.40
b) Coolies 0.700 Nos. 667.00 466.90 1193.30
Materials Gum 0.400 Kg. 217.00 86.80
White Lime 10.000 Kg. 21.00 210.00 296.80
Actual rate 1490.10
Rate 15% contractor's overhead 223.52
Per sqm. Per sft. Total 1713.62
14.90 1.39
126. One coat distempering works over one coat astar (for 100 sq.m/1075.8 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 4.000 Nos. 908.00 3632.00
b) Coolies 4.000 Nos. 667.00 2668.00 6300.00
Materials Astar 8.000 Ltr. 286.00 2288.00
Distamper Powder 6.500 Kg. 238.00 1547.00 3835.00
Actual rate 10135.00
Rate 15% contractor's overhead 1520.25
Per sqm. Per sft. Total 11655.25
101.35 9.42
127. Two coat distemper works over one coat astar (for 100 sq.m/1075.8 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 5.800 Nos. 908.00 5266.40
b) Coolies 5.800 Nos. 667.00 3868.60 9135.00
Materials Astar 8.000 Ltr. 286.00 2288.00
Distamper Powder 11.500 Kg. 238.00 2737.00 5025.00
Actual rate 14160.00
Rate 15% contractor's overhead 2124.00
Per sqm. Per sft. Total 16284.00
141.60 13.16
128 One coat water proof cement paint works over one coat astar
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.700 Nos. 908.00 1543.60
b) Coolies 1.700 Nos. 667.00 1133.90 2677.50
Materials Cement Paint 30.000 Ltr. 79.00 2370.00 2370.00
Actual rate 5047.50
Rate 15% contractor's overhead 757.13
Per sqm. Per sft. Total 5804.63
50.48 4.69
129. Two coat water proof cement paint works over one coat astar (for 100 sq.m/1075.8 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 5.000 Nos. 908.00 4540.00
b) Coolies 5.000 Nos. 667.00 3335.00 7875.00
Materials Cement Paint 48.500 Ltr. 79.00 3831.50 3831.50
Actual rate 11706.50
Rate 15% contractor's overhead 1755.98
Per sqm. Per sft. Total 13462.48
117.07 10.88
130. One coat readymade enamel paint over one coat primer (Astar) on new surface (for 100 sq.m/1075.8 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 8.000 Nos. 908.00 7264.00
b) Coolies 5.000 Nos. 667.00 3335.00 10599.00
Materials Primer 8.100 lit. 402.00 3256.20
Enamel 9.000 lit. 560.00 5040.00 8296.20
Actual rate 18895.20
Rate 15% contractor's overhead 2834.28
Per sqm. Per sft. Total 21729.48
188.95 17.56
_______________
____________ _______________
Approved By
Prepared By Checked By
Rate Analysis
131. Two coat readymade enamel paint over one coat primer (Astar) on new surface (for 100 sq.m/1075.8 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 12.000 Nos. 908.00 10896.00
b) Coolies 8.000 Nos. 667.00 5336.00 16232.00
Materials Primer 8.100 lit. 402.00 3256.20
Enamel 16.000 lit. 560.00 8960.00 12216.20
Actual rate 28448.20
Rate 15% contractor's overhead 4267.23
Per sqm. Per sft. Total 32715.43
284.48 26.44
132. One coat plastic emulsion paint over one coat primer (Astar) on new surface (for 100 sq.m/1075.8 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 8.000 Nos. 908.00 7264.00
b) Coolies 5.000 Nos. 667.00 3335.00 10599.00
Materials Primer 8.100 lit. 286.00 2316.60
Readymade Plastic Emulsion
paint 9.000 lit. 562.00 5058.00 7374.60
Actual rate 17973.60
Rate 15% contractor's overhead 2696.04
Per sqm. Per sft. Total 20669.64
179.74 16.71
133. Two coat plastic emulsion paint over one coat primer (Astar) on new surface (for 100 sq.m/1075.8 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 12.000 Nos. 908.00 10896.00
b) Coolies 8.000 Nos. 667.00 5336.00 16232.00
Materials Primer 8.100 lit. 286.00 2316.60
Readymade paint 16.000 lit. 562.00 8992.00 11308.60
Actual rate 27540.60
Rate 15% contractor's overhead 4131.09
Per sqm. Per sft. Total 31671.69
275.41 25.60
134. Two coat aluminium paint over one coat primer (Astar) on new surface (for 100 sq.m/1075.8 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 10.750 Nos. 908.00 9761.00
b) Coolies 10.750 Nos. 667.00 7170.25 16931.25
Materials Primer 8.100 lit. 402.00 3256.20
Aluminium paint 10.760 lit. 583.00 6273.08
Sand paper 4.000 Nos. 6.00 24.00 9553.28
Actual rate 26484.53
Rate 15% contractor's overhead 3972.68
Per sqm. Per sft. Total 30457.21
264.85 24.62
135. One coat double boiled linseed oiling work on new surface (for 100 sq.m/1075.8 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 2.000 Nos. 908.00 1816.00
b) Coolies 2.000 Nos. 667.00 1334.00 3150.00
Materials Linseed oil 6.000 lit. 210.00 1260.00 1260.00
Actual rate 4410.00
Rate 15% contractor's overhead 661.50
Per sqm. Per sft. Total 5071.50
44.10 4.10
_______________
____________ _______________
Approved By
Prepared By Checked By
Rate Analysis
136. Two coat double boiled linseed oiling work on new surface (for 100 sq.m/1075.8 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 4.000 Nos. 908.00 3632.00
b) Coolies 4.000 Nos. 667.00 2668.00 6300.00
Materials Linseed oil 11.000 lit. 210.00 2310.00 2310.00
Actual rate 8610.00
Rate 15% contractor's overhead 1291.50
Per sqm. Per sft. Total 9901.50
86.10 8.00
137. One coat varnishing work on new surface (for 100 sq.m/1075.8 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 3.000 Nos. 908.00 2724.00
b) Coolies 2.000 Nos. 667.00 1334.00 4058.00
Materials Varnish 6.000 lit. 470.00 2820.00 2820.00
Actual rate 6878.00
Rate 15% contractor's overhead 1031.70
Per sqm. Per sft. Total 7909.70
68.78 6.39
138. Two coat varnishing work on new surface (for 100 sq.m/1075.8 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 6.000 Nos. 908.00 5448.00
b) Coolies 4.000 Nos. 667.00 2668.00 8116.00
Materials Varnish 11.000 lit. 470.00 5170.00 5170.00
Actual rate 13286.00
Rate 15% contractor's overhead 1992.90
Per sqm. Per sft. Total 15278.90
132.86 12.35
139. One coat bitumen paint work on new surface (for 100 sq.m/1075.8 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.500 Nos. 908.00 1362.00
b) Coolies 1.000 Nos. 667.00 667.00 2029.00
Materials Bitumen Paint 7.000 lit. 68.00 476.00
Sand paper 4.000 Nos. 6.00 24.00 500.00
Actual rate 2529.00
Rate 15% contractor's overhead 379.35
Per sqm. Per sft. Total 2908.35
25.29 2.35
140. Two coat bitumen paint work on new surface (for 100 sq.m/1075.8 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 2.500 Nos. 908.00 2270.00
b) Coolies 2.000 Nos. 667.00 1334.00 3604.00
Materials Bitumen Paint 12.000 lit. 68.00 816.00
Sand paper 4.000 Nos. 6.00 24.00 840.00
Actual rate 4444.00
Rate 15% contractor's overhead 666.60
Per sqm. Per sft. Total 5110.60
44.44 4.13
141. Three coat french(chapra) polish work on new surface (for 100 sq.m/1075.8 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 10.000 Nos. 908.00 9080.00
b) Coolies 5.000 Nos. 667.00 3335.00 12415.00
Materials Chapra 2.000 kg 978.00 1956.00
Spirit 10.000 lit. 126.00 1260.00 3216.00
Actual rate 15631.00
Rate 15% contractor's overhead 2344.65
Per sqm. Per sft. Total 17975.65
156.31 14.53
_______________
____________ _______________
Approved By
Prepared By Checked By
Rate Analysis
142. One coat snowcem work after cement paint on new plastered surface (for 100 sq.m/1075.8 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 3.500 Nos. 908.00 3178.00
b) Coolies 3.500 Nos. 667.00 2334.50 5512.50
Materials Snowcem 30.000 lit. 79.00 2370.00 2370.00
Actual rate 7882.50
Rate 15% contractor's overhead 1182.38
Per sqm. Per sft. Total 9064.88
78.83 7.33
143. Two coat snowcem work after cement paint on new plastered surface (for 100 sq.m/1075.8 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 6.500 Nos. 908.00 5902.00
b) Coolies 6.500 Nos. 667.00 4335.50 10237.50
Materials Snowcem 50.000 lit. 79.00 3950.00 3950.00
Actual rate 14187.50
Rate 15% contractor's overhead 2128.13
Per sqm. Per sft. Total 16315.63
141.88 13.19
L. Pointing Works
144. Flush pointing works in 1:1 cement sand mortar on brick masonry work (for 100 sq.m/1075.8 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 10.500 Nos. 908.00 9534.00
b) Coolies 12.000 Nos. 667.00 8004.00 17538.00
Materials Cement 0.316 mt 15940.00 5037.04
Sand 0.220 Cub M 2787.12 613.17 5650.21
Actual rate 23188.21
Rate 15% contractor's overhead 3478.23
Per sqm. Per sft. Total 26666.44
231.88 21.55
145. Ruled pointing works in 1:1 cement sand mortar on brick masonry work (for 100 sq.m/1075.8 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 10.500 Nos. 908.00 9534.00
b) Coolies 18.000 Nos. 667.00 12006.00 21540.00
Materials Cement 0.316 mt 15940.00 5037.04
Sand 0.220 Cub M 2787.12 613.17 5650.21
Actual rate 27190.21
Rate 15% contractor's overhead 4078.53
Per sqm. Per sft. Total 31268.74
271.90 25.27
146. Flush pointin g works in 1:2 cement sand mortar on Brick masonry work (for 100 sq.m/1075.8 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 10.500 Nos. 908.00 9534.00
b) Coolies 12.000 Nos. 667.00 8004.00 17538.00
Materials Cement 0.210 mt 15940.00 3347.40
Sand 0.290 Cub M 2787.12 808.26 4155.66
Actual rate 21693.66
Rate 15% contractor's overhead 3254.05
Per sqm. Per sft. Total 24947.71
216.94 20.17
147. Ruled pointing works in 1:2 cement sand mortar on Brick masonry work (for 100 sq.m/1075.8 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 10.500 Nos. 908.00 9534.00
b) Coolies 18.000 Nos. 667.00 12006.00 21540.00
Materials Cement 0.210 mt 15940.00 3347.40
Sand 0.290 Cub M 2787.12 808.26 4155.66
Actual rate 25695.66
Rate 15% contractor's overhead 3854.35
Per sqm. Per sft. Total 29550.01
256.96 23.89
_______________
____________ _______________
Approved By
Prepared By Checked By
Rate Analysis
148. Flush pointing works in 1:3 cement sand mortar on Brick masonry work (for 100 sq.m/1075.8 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 10.500 Nos. 908.00 9534.00
b) Coolies 12.000 Nos. 667.00 8004.00 17538.00
Materials Cement 0.155 mt 15940.00 2470.70
Sand 0.320 Cub M 2787.12 891.88 3362.58
Actual rate 20900.58
Rate 15% contractor's overhead 3135.09
Per sqm. Per sft. Total 24035.67
209.01 19.43
149. ruled pointing works in 1:3 cement sand mortar on Brick masonry work (for 100 sq.m/1075.8 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 10.500 Nos. 908.00 9534.00
b) Coolies 18.000 Nos. 667.00 12006.00 21540.00
Materials Cement 0.155 mt 15940.00 2470.70
Sand 0.320 Cub M 2787.12 891.88 3362.58
Actual rate 24902.58
Rate 15% contractor's overhead 3735.39
Per sqm. Per sft. Total 28637.97
249.03 23.15
150. Flush pointing works in 1:1:3 cement Lime sand mortar on Brick masonry work (for 100 sq.m/1075.8 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 10.500 Nos. 908.00 9534.00
b) Coolies 12.000 Nos. 667.00 8004.00 17538.00
Materials Cement 0.125 mt 15940.00 1992.50
Lime 0.085 Cub M 16800.00 1428.00
Sand 0.255 Cub M 2787.12 710.72 4131.22
Actual rate 21669.22
Rate 15% contractor's overhead 3250.38
Per sqm. Per sft. Total 24919.60
216.69 20.14
151. Ruled pointing works in 1:1:3 cement Lime sand mortar on Brick masonry work (for 100 sq.m/1075.8 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 10.500 Nos. 908.00 9534.00
b) Coolies 18.000 Nos. 667.00 12006.00 21540.00
Materials Cement 0.125 mt 2469.60 308.70
Lime 0.085 Cub M 16800.00 1428.00
Sand 0.255 Cub M 2787.12 710.72 2447.42
Actual rate 23987.42
Rate 15% contractor's overhead 3598.11
Per sqm. Per sft. Total 27585.53
239.87 22.30
152. Flush pointing works in 1:1 Lime Surki mortar on Brick masonry work (for 100 sq.m/1075.8 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 10.500 Nos. 908.00 9534.00
b) Coolies 12.000 Nos. 667.00 8004.00 17538.00
Materials Lime 0.220 Cub M 16800.00 3696.00
Surki 0.220 Cub M 1541.03 339.03 4035.03
Actual rate 21573.03
Rate 15% contractor's overhead 3235.95
Per sqm. Per sft. Total 24808.98
215.73 20.05
153. Ruled pointing works in 1:1 Lime Surki mortar on Brick masonry work (for 100 sq.m/1075.8 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 10.500 Nos. 908.00 9534.00
b) Coolies 18.000 Nos. 667.00 12006.00 21540.00
Materials Lime 0.220 Cub M 16800.00 3696.00
Surki 0.220 Cub M 1541.03 339.03 4035.03
Actual rate 25575.03
Rate 15% contractor's overhead 3836.25
Per sqm. Per sft. Total 29411.28
255.75 23.77
_______________
____________ _______________
Approved By
Prepared By Checked By
Rate Analysis
154. Flush pointing works in 1:2 Lime Surki mortar on Brick masonry work (for 100 sq.m/1075.8 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 10.500 Nos. 908.00 9534.00
b) Coolies 12.000 Nos. 667.00 8004.00 17538.00
Materials Lime 0.150 Cub M 16800.00 2520.00
Surki 0.290 Cub M 1541.03 446.90 2966.90
Actual rate 20504.90
Rate 15% contractor's overhead 3075.73
Per sqm. Per sft. Total 23580.63
205.05 19.06
155. Ruled pointing works in 1:2 Lime Surki mortar on Brick masonry work (for 100 sq.m/1075.8 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 10.500 Nos. 908.00 9534.00
b) Coolies 18.000 Nos. 667.00 12006.00 21540.00
Materials Lime 0.150 Cub M 16800.00 2520.00
Surki 0.290 Cub M 1541.03 446.90 2966.90
Actual rate 24506.90
Rate 15% contractor's overhead 3676.03
Per sqm. Per sft. Total 28182.93
245.07 22.78
156. Flush ruled pointing works in 1:1 c/s mortar on random rubble masonry work (for 100 sq.m/1075.8 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 10.000 Nos. 908.00 9080.00
b) Coolies 14.000 Nos. 667.00 9338.00 18418.00
Materials Cement 0.612 mt 15940.00 9755.28
Sand 0.430 Cub M 2787.12 1198.46 10953.74
Actual rate 29371.74
Rate 15% contractor's overhead 4405.76
Per sqm. Per sft. Total 33777.50
293.72 27.30
157. Flush ruled pointing works in 1:2 c/s mortar on random rubble masonry work (for 100 sq.m/1075.8 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 10.000 Nos. 908.00 9080.00
b) Coolies 14.000 Nos. 667.00 9338.00 18418.00
Materials Cement 0.408 mt 15940.00 6503.52
Sand 0.570 Cub M 2787.12 1588.66 8092.18
Actual rate 26510.18
Rate 15% contractor's overhead 3976.53
Per sqm. Per sft. Total 30486.71
265.10 24.64
157. Flush ruled pointing works in 1:3 c/s mortar on random rubble masonry work (for 100 sq.m/1075.8 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 10.000 Nos. 908.00 9080.00
b) Coolies 14.000 Nos. 667.00 9338.00 18418.00
Materials Cement 0.306 mt 15940.00 4877.64
Sand 0.630 Cub M 2787.12 1755.89 6633.53
Actual rate 25051.53
Rate 15% contractor's overhead 3757.73
Per sqm. Per sft. Total 28809.25
250.52 23.29
158. Flush ruled pointing works in 1:3cement sand mortar on ashlar masonry work (for 100 sq.m/1075.8 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 8.000 Nos. 908.00 7264.00
b) Coolies 10.000 Nos. 667.00 6670.00 13934.00
Materials Cement 0.110 mt 15940.00 1753.40
Sand 0.200 Cub M 2787.12 557.42 2310.82
Actual rate 16244.82
Rate 15% contractor's overhead 2436.72
Per sqm. Per sft. Total 18681.55
162.45 15.10
164. Pointing works in 1:3cement sand mortar on 45x45cm flagstone paving (for 100 sq.m/1075.8 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 5.000 Nos. 908.00 4540.00
b) Coolies 5.000 Nos. 667.00 3335.00 7875.00
Materials Cement 0.042 mt 15940.00 669.48
Sand 0.030 Cub M 2787.12 83.61 753.09
Actual rate 8628.09
Rate 15% contractor's overhead 1294.21
Per sqm. Per sft. Total 9922.31
86.28 8.02
_______________
____________ _______________
Approved By
Prepared By Checked By
Rate Analysis
165. Pointing works in 1:1cement sand mortar on telia bricks (for 100 sq.m/1075.8 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 10.000 Nos. 908.00 9080.00
b) Coolies 10.000 Nos. 667.00 6670.00 15750.00
Materials Cement 0.150 mt 15940.00 2391.00
Sand 0.100 Cub M 2787.12 278.71 2669.71
Actual rate 18419.71
Rate 15% contractor's overhead 2762.96
Per sqm. Per sft. Total 21182.67
184.20 17.12
166. 3mm Lime flushing plaster works (for 100 sq.m/1075.8 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 10.000 Nos. 908.00 9080.00
b) Coolies 10.000 Nos. 667.00 6670.00 15750.00
Materials Lime 0.160 cum 16800.00 2688.00 2688.00
Actual rate 18438.00
Rate 15% contractor's overhead 2765.70
Per sqm. Per sft. Total 21203.70
184.38 17.14
167. 3mm cement flushing plaster works (for 100 sq.m/1075.8 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 10.000 Nos. 908.00 9080.00
b) Coolies 10.000 Nos. 667.00 6670.00 15750.00
Materials Cement 0.518 mt 15940.00 8256.92 8256.92
Actual rate 24006.92
Rate 15% contractor's overhead 3601.04
Per sqm. Per sft. Total 27607.96
240.07 22.32
_______________
____________ _______________
Approved By
Prepared By Checked By
Rate Analysis
168. 2 cm thick DPC in 1:2 C/S with Water Proofing Compound (WPC) (for rate analysis 10sq.m/ 107.58 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 0.750 Nos. 908.00 681.00
b) Coolies 0.800 Nos. 667.00 533.60 1214.60
Cement 0.135 MT 15940.00 2151.90
Materials Sand 0.180 cum 2787.12 501.68
WPC 2.700 Kg 289.00 780.30 3433.88
Actual rate 4648.48
Rate 15% contractor's overhead 697.27
Per sqm. Per sft. Total 5345.75
464.85 43.21
169. 2.5 cm thick DPC in 1:1.5:3 concrete with Water Proofing Compound (WPC) (for rate analysis 10sq.m/ 107.58 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.000 Nos. 908.00 908.00
b) Coolies 1.250 Nos. 667.00 833.75 1741.75
Cement ### MT 15940.00 1793.25
Materials Sand 0.113 cum 2787.12 314.94
12 mm aggregate 0.250 cum 2716.56 679.14
WPC 2.250 Kg 289.00 650.25 3437.58
Actual rate 5179.33
Rate 15% contractor's overhead 776.90
Per sqm. Per sft. Total 5956.23
517.93 48.14
_______________
____________ _______________
Approved By
Prepared By Checked By
Rate Analysis
170. One coat Bitumenous paint on DPC and sand covering (for rate analysis 10sq.m/ 107.58 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 0.000 Nos. 908.00 0.00
b) Coolies 0.600 Nos. 667.00 400.20 400.20
Bitumen 10.000 Kg 68.00 680.00
Materials Sand 0.020 cum 2787.12 55.74
Fire wood 30.000 Kg 20.00 600.00 1335.74
Actual rate 1735.94
Rate 15% contractor's overhead 260.39
Per sqm. Per sft. Total 1996.33
173.59 16.14
171. One Layer 500 Gauge polythene sheet for DPC (for rate analysis 10sq.m/ 107.58 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 0.600 Nos. 908.00 544.80
b) Coolies 0.600 Nos. 667.00 400.20 945.00
Materials Polythene sheet 11.000 Sqm 30.00 330.00 330.00
Actual rate 1275.00
Rate 15% contractor's overhead 191.25
Per sqm. Per sft. Total 1466.25
127.50 11.85
172. One coat tar felt works with sand (for rate analysis 10sq.m/ 107.58 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.100 Nos. 908.00 998.80
b) Coolies 3.500 Nos. 667.00 2334.50 3333.30
Bitumen 15.000 Kg 68.00 1020.00
Materials Sand 0.310 cum 2787.12 864.01
Tar Felt 11.000 sqm 120.00 1320.00
Fire wood 60.000 Kg 20.00 1200.00 4404.01
Actual rate 7737.31
Rate 15% contractor's overhead 1160.60
Per sqm. Per sft. Total 8897.90
773.73 71.92
173. Two coat tar felt works with sand (for rate analysis 10sq.m/ 107.58 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 2.300 Nos. 908.00 2088.40
b) Coolies 4.600 Nos. 667.00 3068.20 5156.60
Bitumen 25.000 Kg 68.00 1700.00
Materials Sand 0.310 cum 2787.12 864.01
Tar Felt 22.000 sqm 120.00 2640.00
Fire wood 80.000 Kg 20.00 1600.00 6804.01
Actual rate 11960.61
Rate 15% contractor's overhead 1794.09
Per sqm. Per sft. Total 13754.70
1196.06 111.18
_______________
____________ _______________
Approved By
Prepared By Checked By
Rate Analysis
174. One coat damp Proof grade tar felt works with sand (for rate analysis 10sq.m/ 107.58 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 2.350 Nos. 908.00 2133.80
b) Coolies 4.600 Nos. 667.00 3068.20 5202.00
Bitumen 17.000 Kg 68.00 1156.00
Materials Sand 0.310 cum 2787.12 864.01
Tar Felt 11.000 sqm 120.00 1320.00
Fire wood 60.000 Kg 20.00 1200.00 4540.01
Actual rate 9742.01
Rate 15% contractor's overhead 1461.30
Per sqm. Per sft. Total 11203.31
974.20 90.56
175. Two coat damp Proof grade tar felt works with sand (for rate analysis 10sq.m/ 107.58 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 3.500 Nos. 908.00 3178.00
b) Coolies 11.700 Nos. 667.00 7803.90 10981.90
Bitumen 27.000 Kg 68.00 1836.00
Materials Sand 0.310 cum 2787.12 864.01
Tar Felt 22.000 sqm 120.00 2640.00
Fire wood 80.000 Kg 20.00 1600.00 6940.01
Actual rate 17921.91
Rate 15% contractor's overhead 2688.29
Per sqm. Per sft. Total 20610.19
1792.19 166.59
176. One coat rain seal or equivalent painting works (for rate analysis 1sq.m/ 10.758 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 0.162 Nos. 908.00 147.10
b) Coolies 0.540 Nos. 667.00 360.18 507.28
Materials Rain seal paint 0.245 Ltr 673.00 164.89 164.89
Actual rate 672.16
Rate 15% contractor's overhead 100.82
Per sqm. Per sft. Total 772.99
672.16 62.48
N. Maintenance Work
177. Maintenance of wall in 1:6 C/S at corners with removal of old bricks (1Cum./35.28Cu ft)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 3.530 Nos. 908.00 3205.24
b) Unskilled 7.060 Nos. 667.00 4709.02 7914.26
a) Cement 0.084 M.Ton 15940.00 1338.96
b) Sand 0.360 Cub M. 2787.12 1003.36
Materials c) Bricks 560.000 Nos. 14.00 7840.00 10182.32
Actual rate 18096.58
Rate 15% contractor's overhead 2714.49
Per Cum. Per Cu ft. Total 20811.07
18096.58 512.94
178. Maintenance of wall in 1:2 lime surki with removal of old bricks at wall corners (10Cum./352.8Cu ft)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 35.280 Nos. 908.00 32034.24
b) Unskilled 70.560 Nos. 667.00 47063.52 79097.76
a) Lime 1.400 Cub M. 16800.00 23520.00
Materials b) Surki 2.800 Cub M. 1541.03 4314.88
c) Bricks 5600.000 Nos. 14.00 78400.00 106234.88
Actual rate 185332.64
Rate 15% contractor's overhead 27799.90
Per Cum. Per Cu ft. Total 213132.54
18533.26 525.32
179. One coat Enamel paintings works after linseed oil flushing (10Sqm./107.58 Sq ft)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 0.538 Nos. 908.00 488.50
b) Unskilled 0.538 Nos. 667.00 358.85 847.35
a) Linseed oil 0.538 Ltr 210.00 112.98
Materials b) Enamel 1.614 Ltr 560.00 903.84 1016.82
Actual rate 1864.17
Rate 15% contractor's overhead 279.63
Per Sqm. Per Sq ft. Total 2143.80
186.42 17.33
_______________
____________ _______________
Approved By
Prepared By Checked By
Rate Analysis
180. Dismantling of Cement Plaster and Disposing with transportation of 10m. ( 1cu.m/35.28 cft )
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: b) Unskilled 0.108 Nos. 667.00 72.04 72.04
Actual rate 72.04
Rate 15% contractor's overhead 10.81
Per Cum. Per Cu ft. Total 82.84
72.04 2.04
181. Dismantling of Tile Roof and Disposing tile/Woods with transportation of 10m. ( 1cu.m/35.28 cft )
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
a) Skilled 0.054 Nos. 908.00 49.03
Labours: b) Unskilled 0.081 Nos. 667.00 54.03 103.06
Actual rate 103.06
Rate 15% contractor's overhead 15.46
Per Cum. Per Cu ft. Total 118.52
103.06 2.92
183. Dismantling of Mud mortared wall and Disposing with transportation of 10m. ( 1cu.m/35.28 cft )
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: b) Unskilled 1.060 Nos. 667.00 707.02 707.02
Actual rate 707.02
Rate 15% contractor's overhead 106.05
Per Cum. Per Cu ft. Total 813.07
707.02 20.04
184. Dismantling of Cement mortared wall and Disposing with transportation of 10m. ( 1cu.m/35.28 cft )
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: b) Unskilled 2.120 Nos. 667.00 1414.04 1414.04
Actual rate 1414.04
Rate 15% contractor's overhead 212.11
Per Cum. Per Cu ft. Total 1626.15
1414.04 40.08
_______________
____________ _______________
Approved By
Prepared By Checked By
Rate Analysis
185. Dismantling of R.C.C./R.B.C. and Disposing with transportation of 10m. ( 1cu.m/35.28 cft )
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: b) Unskilled 11.000 Nos. 667.00 7337.00 7337.00
Actual rate 7337.00
Rate 15% contractor's overhead 1100.55
Per Cum. Per Cu ft. Total 8437.55
7337.00 207.96
186. Dismantling of P.C.C. and Disposing with transportation of 10m. ( 1cu.m/35.28 cft )
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: b) Unskilled 4.000 Nos. 667.00 2668.00 2668.00
Actual rate 2668.00
Rate 15% contractor's overhead 400.20
Per Cum. Per Cu ft. Total 3068.20
2668.00 75.62
188. 216. 4.5 x 20mm Metal Grill including manufacturing, fitting, painting with Aluminium paint, sand papering all complete
for 10 sq.m/107.58 sft.
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Materials Metal grill
4.5 x 20mm size 10.000 sq.m 3220.70 32207.00 32207.00
Actual rate 32207.00
Rate 15% contractor's overhead 4831.05
Per sqm. Per sft. Total 37038.05
3220.70 299.38
189. Iron tubular Truss including manufacturing, welding, supply of material, painting and fixing all complete
for 18.94 kg
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: Skilled 0.687 No. 908.00 623.80 1144.72
Unskilled 0.781 No. 667.00 520.93
Materials Black Pipe 18.940 Kg. 79.00 1496.26 1496.26
Actual rate 2640.98
Rate 15% contractor's overhead 396.15
Per kg Per kg Total 3037.13
139.44 139.44
Combined 50mmf &37.5mmf Black pipe(medium Class) with necessary nutbolts & Plates.
_______________
____________ _______________
Approved By
Prepared By Checked By
Rate Analysis
191. Barbed wire fencing in 75x100x2100 Saal wood posts with 5rows & two cross bracings all complete
(for 30 R m/98.4 Rft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.000 Nos. 908.00 908.00 908.00
Salwood 0.190 Cub M. 194040.00 36867.60
Materials Barbed wire 250.000 Rm 13.57 3392.86
U-Hook 77.000 Nos. 0.74 56.98 40317.44
Actual rate 41225.44
Rate 15% contractor's overhead 6183.82
Per Rm. Per rft. Total 47409.25
1374.18 418.96
P. Miscelaneous
192. M1 . Rain Water Pipe 90 mm dia. HDPE (100 RM/ 328 R Ft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 4.000 Nos. 908.00 3632.00
b) Coolies 6.000 Nos. 667.00 4002.00 7634.00
Materials 90 mm dia. HDPE Pipe 110.000 R M 200.00 22000.00
Bed Fitting 1.000 L S 5.00 5.00
Clamps 1.000 L S 10.00 10.00 22015.00
Actual rate 29649.00
15% contractor's overhead 4447.35
Rate Total 34096.35
Per Rmt. Per Rft
296.49 90.39
193. M11.Concrete Hollow Block Masonry works in 1:4 cement mortar Per sq.m
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 0.250 Nos. 908.00 227.00
b) Unskilled 0.250 Nos. 667.00 166.75 393.75
16"*8"*6" hollow block 19.000 Nos. 76.00 1444.00
Cement 0.010 MT 15940.00 159.40
Materials Sand 0.040 Cub.M. 2787.12 111.48
1714.88
Actual rate 2108.63
Rate 15% contractor's overhead 316.30
Per Sq.m. Per Sq.ft. Total 2424.93
2108.63 196.15
194. M12. 50mm thick inter locking concrete block work on 50mm thick dust per 10 sq.m
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.000 Nos. 908.00 908.00
b) Unskilled 10.000 Nos. 667.00 6670.00 7578.00
Interloking block 11.000 Sq.m 534.06 5874.66
Materials Stone dust 0.710 Cub.M. 1058.40 751.46
6626.12
Actual rate 14204.12
Rate 15% contractor's overhead 2130.62
Per sqm.. Per sqft. Total 16334.74
1420.41 132.13
195. M13. 60mm thick inter locking concrete block work on 50mm thick dust per 10 sq.m
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.000 Nos. 908.00 908.00
b) Unskilled 10.000 Nos. 667.00 6670.00 7578.00
Interloking block 11.000 Sq.m 557.28 6130.08
Materials Stone dust 0.710 Cub.M. 1058.40 751.46
6881.54
Actual rate 14459.54
Rate 15% contractor's overhead 2168.93
Per sqm. Per sqft. Total 16628.48
1445.95 134.38
_______________
____________ _______________
Approved By
Prepared By Checked By
17 !%X!% ;]=dL= ;fOhsf] ;fn sf7sf] kf]i6 tyf #ÆX#Æ ;fO{hsf] an':6/ /fvL #ÆX$Æ ;fO{hsf] ;fnsf] Xof08/]n
agfO{ h8fg ug]{ sfd .
b/ ljZn]if0fsf] nflu ( j=dL= lnOPsf]
b/ k|lt
;|f]t ;fwg tx÷lsl;d kl/df0f PsfO{ /sd k|To]s ;|f]t ;fwgsf] hDdf
PsfO{
l;kfn' 5.27 hjfg 908.00 4785.16
>lds
HofdL 0.52 hjfg 667.00 346.84 5132.00
lgdf{0f ;fdu|L ;fnsf] sf7 0.329 3=dL= 194040.00 63839.16 63839.16
jf:tljs b//]6 68971.16
b/ k|lt j=dL=sf] !%Ü 7]s]bf/ cf]e/x]8 10345.67
79316.83 Ö ?= 8812.98 k}= hDdf b/ /]6 79316.83
9
75 mm wallboard internal/
1.1 external layer with insulation sq. ft. 9.849 293.55 2891.17395
1.2 1.5" x 1.5" square pipe kg 12.08 100.00 1208.47
Transportation charge from
2 Kathmandu to site
75 mm wallboard internal/
external layer with insulation kg 44.60625 1.15 51.2971875
Description of work :- Providing and installing expansion joint including all Unit:- RM
Labour necessary
Unit axilliary and incidental
Quantity works etc.Amount
rate all Remarks
A
For labour 10% of material cost 450.00
Sub total (in Rs.) 450.00
Materials
B
Expansion joint Rm 1.00 4500.00 4500.00
Sub total (in Rs.) 4500.00
Equipments
C
For T & P 3% of material cost 135.00
Sub total (in Rs.) 135.00
Total of A+B+C (in Rs.) 5085.00
Overhead 15% 762.75
Grand Total (in Rs.) 5847.75
Unit rate (in Rs.) 5847.75
Rate Analysis(Transportation)
Travel Time (T) for truck to be used for this activity shall be determined as follows:
T = 2 * { d1/v1 + d2/v2 + d3/v3 + …………. Dn/vn}, where d1, d2, d3 … dn and v1, v2, v3……vn are the
streches of distances to be travelled and corresponding average speeds on these streches.
Activity Nos 8.04.03 Using 8 tonne Capacity Trunk
1 . Transportation of Excavation Soil by Truck
Unit 1 m3
MOPPW : Norms for rate analysis as per standard specifications for Road and Bridge Works
Activity No. - 8.04.03, SPEC. Clause No. - 800(2)
Source Name Khola/River/ F/Y: 072/73
Lead Distance 4 Km
Description Unit Gravel Road Metallic Road Total Length
Distance from source to site KM 1 3 4
Average speed of truck KM/Hr 25 40
0.23 Hrs.