Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                

Bill of Quantities: Prepared By: Checked By: Approved by

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 82

Bill of Quantities

Project :- Construction of Godavari Municipality Building Bajarbarahi, Lalitpur

Rate(NRs) Amount
S.N. DESCRIPTION OF WORKS UNIT QUANTITY
In figure In words
1 SITE CLEARANCE WORK Sqm 3,146.53
2 EXCAVATION WORKS
3 SOLLING WORKS

Brick Soling for R.C.C.for foundation footing, column,


beam & floor as per drawing and instruction all complete Sqm -
4 Back Filling
Providing and laying to Back Fill the foundation area below
plinth level in perfect line & level as per the design,
drawing, specification & instruction of engineer Cum 103.04
5 Transporting and disposing the surplus earth and debris

Transporting and disposing the surplus earth and debris


from the site including re-excavating the deposited soil
excavated earlier if any, transporting, loading, laying, at all
depth and height, stacking, levelinh, and dressing both the
areas for leads as per the design ,drawing, specification &
instruction of engineer Cum -
6 shoring work

Providing and fixing shoring work for full protection on


required periphery of proposed building for retaining soil
and preventing damages of neighbouring property all
complete. Note:Conractor must submit his own design and
implementing procedure for shoring work. Cum -
7 P.C.C WORKS
P.C.C. (1:2:4) for footing of foundation with proper mixing
and compaction including curing as per drawing and
instruction all complete Cum 103.04
8 R.C.C WORKS

(1:1.5:3) R.C.C.for foundation footing column, beam,slab


etc with proper mixing by mixer machine and compaction
by vibrator including proper curing as per drawing and
instruction all complete (including testing of concrete
cubes) Cum Err:509
9 REINFORCEMENT WORK

Supplying, cutting, bending, placing in position as shown in M.T Err:509


drawing and binding by plain wire of reinforcement steel
bars for R.C.C. works all complete
10 FORM WORK As per instructed by Project Manager or Site engineers.
Making proper form work including supplies & selection of
material, fixing, nailing, according to drawing, placing
seperators, dismantling forms and hauling up to 30 meter
distance all complete
Form work for base P.C.C. of foundation footing Sqm -
Form work for column Sqm 216.36
Form work for Beam Sqm Err:509
Form work for roofing slab and Staicase Sqm Err:509
11 BRICKS WORKS

Prepared By: Checked By: Approved By:


Bill of Quantities
Project :- Construction of Godavari Municipality Building Bajarbarahi, Lalitpur

Rate(NRs) Amount
S.N. DESCRIPTION OF WORKS UNIT QUANTITY
Fairface Brick work in Superstructure with 1:1:1 Lime Sand
11.1 Surki above Gnd Floor using chimney made brick &
including 30m transportation 0 (180.00) 15,067.58 (2,712,164.30)
9'' Brickwork in 1:6 cement mortar above groung floor in
11.2 outer boundary using chimney made brick & including 30m
transportaion 0 - 15,676.25 -
Inner Brick 4'' Brickwork in 1:4 cement mortar above
11.3 groung floor using chimney made brick & including 30m
transportaion 0 - 15,676.25 -
12 PLASTERING WORKS As per instructed by Project Manager or Site engineers.
12.5mm thick (1:4) C/S plaster inside and outside building
(a) including proper curing all complete for wall surface
without celling Sqm - - -

(b) 12 mm thick (1:4) C/S plaster inside and outside building


including proper curing all complete for concrete surface Sqm - - -
12.5mm thick (1:4) C/S plaster on concrete surface with (
1:4) cement mortar Sqm - - -
13 STONE WORKS

Stone masonry work with first class brick in (1:6) cement


mortar in foundation with proper curing all complete Cum 56.57
14 C.G.I SHEETS WORKS Sqm 300.29
15 TRUSS-WORK MT
3'' Steel truss work at top of the building Kg 4,091.00
5'' Steel column at top of the building Kg 4,671.00
16 WOOD WORK As per instructed by Project Manager or Site engineers.
Making and fitting sal wood door frame having (3"x 4")
wood size with good finish from approved wood including
(a) necessary hardware Cum 7.47

Making and fitting 38 mm thick sal wood panelled door


(b) shutter including necessary brass fittings all complete Sqm 31.97

Making and fitting 6 mm water proof thick commercial ply


flush shutte at one side and 4mm (ply both sides) in 38
mm thick sal wood frame including necessary brass fittings
(c) as per instruction all complete Sqm 35.99
Making and fitting 6 mm thick glazed shutter in 38 x 75
mm thick sal wood frame including necessary brass fittings
(d) as per instruction all complete Sqm 147.07
17 FLOORING WORK As per instructed by Project Manager or Site engineers.
75mm P.C.C. (1:2:4) in floor with proper mixing by mixer
(a) machine and compaction by vibrator machine including
proper curing all complete Sqm 753.05
(b) 6'' sand filling Cum 38.49
15 PLASTERING WORKS As per instructed by Project Manager or Site engineers.
12.5mm thick (1:4) C/S plaster inside and outside building
(a) including proper curing all complete for wall surface
without celling Sqm 1,157.69

(b) 12 mm thick (1:4) C/S plaster inside and outside building


including proper curing all complete for concrete surface Sqm 598.87

Prepared By: Checked By: Approved By:


Bill of Quantities
Project :- Construction of Godavari Municipality Building Bajarbarahi, Lalitpur

Rate(NRs) Amount
S.N. DESCRIPTION OF WORKS UNIT QUANTITY
12.5mm thick (1:4) C/S plaster on concrete surface with (
1:4) cement mortar Sqm 700.84
18 PAINTING WORKS As per instructed by Project Manager or Site engineers.
Two coats water proof cement paint application inside and
(a) outside building with good finish as per instruction all
complete Sqm 1,674.87
Supplying and applying of two coats of approved quality
(b) and colour ready made enamel paints over one coat of
wood primer with good finish as per instruction all
complete Sqm 2,054.61

Prepared By: Checked By: Approved By:


Bill of Quantities
Project :- Construction of Godavari Municipality Building Bajarbarahi, Lalitpur

Rate(NRs) Amount
S.N. DESCRIPTION OF WORKS UNIT QUANTITY
19 HAND RAILING WORKS As per instructed by Project Manager or Site engineers.

Making and fitting 1" x 1" size square pipe railing having
height 3'-0" to 3'-0" including 3" x 4" size seasoned saal
wood handrail on top of railing and brass caping on bottom
of each square pipe of railing with 1 coat primer and 2
coats enamel paint on railing and 3 coats chapra polish on
handrail all complete Sqm 553.00
20 MS GRILL FOR WINDOW As per instructed by Project Manager or Site engineers.

Supplying, fabrication of 3 x 20 mm MS grill and fitting in


window including cleaning by sand paper, applying one
coat metal primer and two coats aluminium paints all
complete Sqm 110.23
21 MS COLLAPSIBLE GATE As per instructed by Project Manager or Site engineers.

Supplying, fabrication and fitting of MS collapsible gate


including cleaning by sand paper, applying one coat metal
primer and two coats aluminium paints all complete Sqm 11.72
22 TILES WORKS As per instructed by Project Manager or Site engineers.
(a) 8"x12" Tile on wall surface Sqm 364.81
(b) 12"x12" Tile on floor surface Sqm 171.67
23 MARBAL LAYING AND PLACING
Total Civil Works for building
24 FURNITURE WORKS & CAPETTING WORKS As per instructed by Project Manager or Site engineers.
Mayor ,Vice Mayor ,Excective & Office
Three Seater Sofa Nos 60.00
Office table(6'0"x4'0") all complete Nos 75.00
Counters(6'x2'6"x3') Nos 25.00
Chairs Nos 350.00
Meeting
A grade-room Table
Luxury (10'x4'x3')
Chairs for Mayor,Vice Mayor ,Excective Nos 18.00
Office Nos 7.00
B- grade- Luxury Chairs for Office Nos 15.00
Preparation of floor areas to receive new carpet tiles,
Provide Carpet tiles, Adhesive and all Accessories as per
specifications m2 667.91 -
Total Furniture Works -
25 SANITARY WORKS As per instructed by Project Manager or Site engineers.
Supply and installation of the following bathroom fixtures
as
Waterper closet
the specification
set consists andofinstruction
white glazed all complete
China Procelain Sets 30.00
European
Urinal set oftype commode
consists of white of glazed
Hindustan
ChinaSanitary
ProcelainWareFlat Sets
(EWClarge no. 20007) of size Sanitary
510mm W x 800mm H x 750mm 14.00
back
Wash basin of Hindustan Ware (no. 60002 Urinal
D
flatwith 'P' ORset
back-large)
consists
'S'oftrap
size
of white
syphony
590mm white
W x
glazed
glazed vitreous
390mm vitreous
H x 375mm
China Sets
ChinaD 32.00
procelain
procelain
Toilet mirror single
12.0 litrehole
consists oflavatory
capacity basin
cistern
mirror size of H.S.L.
(Cistern WB
no. 21001).
(600x500mm) No.
ofWare)
float
with auto
10046India cistern
(Approx. (no. 61002,
510mmx380mm) Hindustan
C.P.base Sanitary
pillar Sets 24.00
glass
fittings
Glass-shelf with
including plastic
of size Cil mounted
brackets
120mm back
standard forcocks
size mirror for hot
ofbottle
GI flush
and cold water, counter &x 480mm
nessary of brass trap Sets 34.00
pipes, andetc.all
syphoney spreaders with brass unions and necessary
complete.
Providing and installation of floor trap set consisting of Sets 60.00
fittings all complete
nahani trapand
Providing or floor
fixingtrap
toiletof taps
size with
100x50 mm of PVCfittings
all necessary body
with all nessary fitting.necessary fittings. Sets 24.00
with
Soapshort
Traybody bib cock CP taps Sets 24.00
Towel rod Sets 24.00

Prepared By: Checked By: Approved By:


Bill of Quantities
Project :- Construction of Godavari Municipality Building Bajarbarahi, Lalitpur

Rate(NRs) Amount
S.N. DESCRIPTION OF WORKS UNIT QUANTITY
Providing and properly appling two coat of hi-tech
chemical water proofing treatment by crystallizating
prepared at site just before application by mixing 2.5
volumes of chemical to one volume of water to form
smooth paintable/brushable slurry result on two surface of Sqft 701.76
RCC slab ,well damped after properly cleaned witk wire
brush.

( B ) Water supply line / sanitary line ( Drainage ) As per instructed by Project Manager or Site engineers.
a Providing and installation of gun metal gate valve
I) NB 40mm Sets 12.00
ii) NB 25mm Sets 18.00
b Providing and installation of water supply line GI Pipes of
class A with all nessary clamps fitting etc.all complete.
NB 15mm(1/2"dia.) Cold Pipe Line r.m 385.00
NB 20mm(3/4"dia.) Cold Pipe Line r.m 275.00
NB 25mm(1"dia.) Cold Pipe Line r.m 205.00
NB 40mm(1.5"dia.) Cold Pipe Line r.m 360.00
c
Providing and installation UVC Pipe-4 Kg/sq. cm Rain
water pipes with necessary all fittings as per detail
drawings I) OD - 100 Pic 85.00
d Soil and waste pipes
I) OD-75 r.m 37.00
ii) 4 inch valve bend Kg 42.00
e Providing & installation of water pump (1.5 HP) Sets 4.00
f Providing and Installation of 1000 Lt. PVC Water Tank all Liter 4,000.00
complete as per instructed by engineers.
Total Sanitary Works -
26 ELECTRICAL WORKS
( A ) Wiring of light/fan & power points:
Following Light /Power /fan Points shall cover all
necessary conduit, PVC duct, Bottom, HDP pipe 3/22
sliver wire. as per site condition with furniture layout and
As instructed by Project Manager or Site engineers..
( make: NS stander)

Light points
Light Point with 2 no 3/22 cable & junction boxes. Points 200.00
Power Points 10A 3 pin socket Light point with 7/22 cable
&junction Boxes Points 240.00
Light fixture of Approved Brand of Wipro,Havells with CFL
( B ) bulb or Philips equivalent brand Points 115.00
( C ) Ex-Fan Points Points 15.00
( D ) Switches, Light &Power and plug in sockets (North-
West or equivalent)
Supply of materials (Modular type light switches, light and
power sockets, weather proof plug-in-power sockets as
mentioned below, 18 SWG GI metal boxes, Screw and
other necessary materials) installation, interconnection
and commissioning. As per instructed by Project Manager
or Site engineers.
a 6 A 6 gang 1 way switch Sets 35.00
b 6 A 3 gang 1 way switch Sets 25.00
c 6 A 2 gang 1 way switch Sets 20.00

Prepared By: Checked By: Approved By:


Bill of Quantities
Project :- Construction of Godavari Municipality Building Bajarbarahi, Lalitpur

Rate(NRs) Amount
S.N. DESCRIPTION OF WORKS UNIT QUANTITY
( E ) Power Cable:
Supply of materials (cables,pipe,cable shoes) & laying ,
interconnection & testing of following size of pvc insulated
Cu. cable including digging,refilling, compction & cable
termination with cable shoes of suitable size using RM 3,500.00
crimping device. As per instructed by Project Manager or
Site engineers.

( F) Earthing and Lighting protection system


Supply of materials necessary for earthing system loke
copper plate (600X600X6 mm), salt, charcoal dust 25mm
wide copper strip & copper nut, bolts, spring washer, bolts
watering 30mm dia PVC pipe & its installation in a whole of
90X90X150 cm with layers of materials (as per site
condition contractor can installed the 2235mm long 25mm sets 2.00
dia copper Grounding Rod and make the Bonding for Grid)
As per instructed by Project Manager or Site engineers.

Electrical Main Panel & Distribution Boards Circuit


( G ) Breakers: Merlin Gerlin/Legrand/ABB/Simens/Havels

Supply, delivery, Testing, installation and Commissioning


of the following floor/ Pad/ Wall Mounted Panel/
Distribution Board (440/400/230 V, 50 Hz) with transparent
acrylic and separate chamber for Bus bar enclosure made
from 16 SWG HRCA Sheet metal including necessary
cable. As per instructed by Project Manager or Site
engineers.

Main PB Incoming 40 A, 25KA, MCCB TP Moulded-1 set.


60A TPNE Copper bus bat with hardware and 1100 volt
insulating -1 set. 0-500 Volt meter Digital Static unit with
selecting device-1 set. Outgoing 6/16/20/60 A MCB
Sets 8.00
Distribution Box Sets 4.00
Wiring of Telephone points
Following points shall cover all necessary conduit, PVC
duct, Bottom, HD pipe etc as per site condition with
furniture layout and As instructed by Project Manager or
Site engineers.
Supply and materials and wiring in suitable size medium
presser PVC conduit concealed/ false ceiling without any
joint in middle of the span. As per instructed by Project
Manager or Site engineers.
Telephone points with CAT-5 Cable. Points 25.00
56''Celling Fans Sets 25.00
15 watt CFL Bulbs Sets 80.00
25 watt CFL Bulbs Sets 35.00
Weather proof light Sets 20.00

Prepared By: Checked By: Approved By:


Bill of Quantities
Project :- Construction of Godavari Municipality Building Bajarbarahi, Lalitpur

Rate(NRs) Amount
S.N. DESCRIPTION OF WORKS UNIT QUANTITY
Videocon 1.5ton Air Conditioner at Mayor, Vice Mayor ,
Executive Room and Meeting Hall ( According to market
(G) price) As per instructed by Project Manager or Site
engineers.
Sets 10.00

Vivitek H1060 3000ANSI Lumen DLP 1080p(1920x1080)


(H) White desktop projector Meeting hall , Revenue & Social Sets 7.00
Department ( Accoriding to market price) As per
instructed by Project Manager or Site engineers.
Total Electrical Works
24 Slope Protection works

Supply and place different size rockfilled gabion boxes of


hexagonal mesh with heavy coated GI wires, mesh size
100 mm x 120 mm, mesh wire 10 SWG, selvedge wire 8
SWG and binding wire 12 SWG . As per instructed by
Project Manager or Site engineers. m3 945.00
27 Insurance for the damage and loss of works, plants and Job 1
vehicles; personal injury, death of labour, Employee &
third party insurance
28 Provide and maintain Engineer's Office and logistic PS 1
facilities(SP6) & Provision for Expert Services for
monitoring construction process and providing training
(SP4) As per instructed by Project Manager or Site
engineers.
29 Photography of construction activities. As per instructed by no. 1
Project Manager or Site engineers.
30 Supplying and placing of Project Sign Board As per no. 1
instructed by Project Manager or Site engineers.
31 Rain Water Harvesting no. 1.00 1,000,000.00 1,000,000.00
32 Emergency Exit no. 1.00 2,500,000.00 2,500,000.00
33 Passenger Elevator
Grand Total
Add vat 13%
Contingencies (5 % of total estimated cost)
Consultant's supervision charge
Total Project Cost

Prepared By: Checked By: Approved By:


Godavari Municipality
Office of the Municipal Executive
Bajarbarahi, Lalitpur

Project :- Construction of Godavari Municipality Building Bajarbarahi, Lalitpur


Site: Bajarbarahi, Lalitpur

SUMMARY OF COST
S.N. Description Amount Remarks

A. Total cost of School Building


1 Civil Works Rs #NAME?
2 Sanitary Works Rs 1,570,332.61
3 Electrical Works Rs 2,920,019.25
4 Furniture Works Rs #NAME?
5 Others work ( Insurance, PS IteamS) Rs #NAME?
Sub - total Rs #NAME?
Adding 13 % for VAT Rs #NAME?
Adding Contingency@ 5% Rs #NAME?
Consultant's supervision charge Rs 1,500,000.00
Total cost of project Rs #NAME?

Two Hundred Twenty Six Million Three Hundred Fifty Three Thousand Nine Hundred
Twenty and Paisa Thirty Seven only

Prepared By: Checked By: Approved By:


Detail Project Report (DPR) of Godavari Municipality Building Bajarbarahi, Lalitpur

ABSTRACT OF COST

Project :- Construction of Godavari Municipality Building Bajarbarahi, Lalitpur

S.N. DESCRIPTION OF WORKS UNIT QUANTITY RATE AMOUNT REMARKS


Providing Insurance for Proposed Building,
A. General Items
Materials, Third Party(People and Property),
Employees and workers etc for complete
1 construction and liability period. PS 1 3169720.11 3169720.11
Contractor site facilities (LabourCamp and
2 Site Office)
Carry out tests for material and works as LS 1 450000.00 450000.00
required and instructed by the Project
3 Manager.
Supply Motorbikes ( Four stroke Engine & PS 1 1000000.00 1000000.00
Relocation
150 of the) utilities
CC or more including and services
fuel, as
lubricants
4 instructed by the
,maintenance andProject Manager
insurance all complete, PS 1 1000000.00 1000000.00
for the site supervision team of Technical
5 Team of Muncipalty
Engineers Faciliies Type A: Supply of labtop Nos. 2 250000.00 500000.00
and computers with printer accessories as per
6 Specification Nos. 2 90000.00 180000.00

7 Photography
Contract information
of construction
board activities. As per Nos. 1 25000.00 25000.00
instructed by Project Manager or Site
8 engineers. Job 1 100000.00 100000.00

Sub Total 6424720.11


B Building Construction
1 SITE CLEARANCE WORK Sqm 34,961.41 17.64 616,794.44
2 EXCAVATION WORKS Cum 533,015.20 632.05 336,891,830.75
3 SOLLING WORKS
Brick Soling for R.C.C.for foundation footing,
column, beam & floor as per drawing and
instruction all complete Sqm 550.23 1,032.68 568,208.20
4 Back Filling
Providing and laying to Back fill the foundation
area below plinth level in perfect line & level Cum
as per the design, drawing, specification &
instructions of engineer(building area) 108,497.16 191.76 20,805,686.64
5 Transporting and disposing the surplus earth
and debris

Transporting and disposing the surplus earth


and debris from the site including re-
excavating the deposited soil excavated
earlier if any, transporting, loading, laying at all Cum
depths and heights, stacking, leveling, and
dressing both the areas for leads as per the
design, drawing, specification & instructions of
engineer on safe place. 7,917.84 237.25 1,878,467.95
7 P.C.C WORKS

P.C.C. (1:2:4) for footing of foundation with


proper mixing and compaction including curing
as per drawing and instruction all complete Cum 846.50 13,995.56 11,847,238.64
8 R.C.C WORKS

(1:1.5:3) R.C.C.for foundation footing column,


beam,slab etc with proper mixing by mixer
machine and compaction by vibrator including
proper curing as per drawing and instruction
all complete (including testing of concrete
cubes) (M20) Cum - 17,527.16 -
1:1:2 P.C.C. work in superstructure slab,
beams, columns, lintels etc. with
transportation up to 30m (M25) Cum. 13,513.56 21,361.66 288,672,199.62
9 REINFORCEMENT WORK

9
Prepared Design By: Approved By:
Checked By:
Detail Project Report (DPR) of Godavari Municipality Building Bajarbarahi, Lalitpur

ABSTRACT OF COST

Project :- Construction of Godavari Municipality Building Bajarbarahi, Lalitpur

S.N. DESCRIPTION OF WORKS UNIT QUANTITY RATE AMOUNT REMARKS

Supplying, cutting, bending, placing in position


as shown in drawing and binding by plain wire M.T 1,533.47 113,300.53 173,742,736.21
of reinforcement steel bars for R.C.C. works
all complete
FORM WORK As per instructed by Project
10
Manager or Site engineers.

Making proper form work including supplies &


selection of material, fixing, nailing, according
to drawing, placing seperators, dismantling
forms and hauling up to 30 meter distance all
complete
Form work for base P.C.C. of foundation
footing Sqm 1,052.00 765.92 805,744.46
Form work for Shear Wall Sqm 3,255.84 1,211.78 3,945,375.50
Form work for column Sqm 4,657.92 1,211.78 5,644,393.91
Form work for Beam Sqm 7,975.75 1,267.09 10,106,015.86
Form work for roofing slab, Lintel Band,
Staicase and Others Sqm 28,098.06 765.92 21,520,775.92
11 BRICKS WORKS
11.3 ALL brickworks with 1:4 cement mortar and
30m transportation cum 1,346.73 15,553.41 20,946,215.85
PLASTERING WORKS As per instructed by
Project Manager or Site engineers.
12
12.2 12.5 mm th.Plaster on 9'' and 4" wall surface
with ( 1:4) cement mortar Sqm 69,424.04 393.45 27,314,785.34
13 STONE WORKS
Rubble stone masonryworks in 1:6 c/s mortar
& including 10m trasportation Cum 161.56 11,528.83 1,862,650.52
14 C.G.I SHEETS WORKS Sqm 6,110.00 999.27 6,105,524.93
15 TRUSS-WORK kg 203,913.45 160.36 32,698,614.04
WOOD WORK As per instructed by Project
16
Manager or Site engineers.
Making and fitting sal wood door frame having
(3"x 4") wood size with good finish from
16.1 approved wood including necessary hardware
Cum 9.57 285,611.80 2,732,019.66
Making and fitting 38 mm thick sal wood
16.2 panelled door shutter including necessary
brass fittings all complete Sqm 91.20 9,927.88 905,422.34
Making and fitting 4 mm water proof thick
commercial ply flush shutte at one side and
16.3 4mm (ply both sides) in 38 mm thick sal wood
frame including necessary brass fittings as per
instruction all complete
Sqm - 7,848.38 -
Fixing glass of various thickness in frame
16.5 using glass thickness 4 mm. Sqm 325.20 1,006.11 327,188.37
FLOORING WORK As per instructed by
17
Project Manager or Site engineers.

17.1 75mm(3") thick 1:2:4 Cement Concrete


FLooring and finishing with neat cement coat Sqm 1,056.00 1,158.66 1,223,542.20
17.2 6'' sand filling Cum 1,006.20 4,062.64 4,087,830.18
PAINTING WORKS As per instructed by
18 Project Manager or Site engineers.

18.1 Two coat plastic emulsion paint over one


coat primer (Astar) on new surface Sqm 69,304.04 316.72 21,949,760.07

10
Prepared Design By: Approved By:
Checked By:
Detail Project Report (DPR) of Godavari Municipality Building Bajarbarahi, Lalitpur

ABSTRACT OF COST

Project :- Construction of Godavari Municipality Building Bajarbarahi, Lalitpur

S.N. DESCRIPTION OF WORKS UNIT QUANTITY RATE AMOUNT REMARKS

Supplying and applying of two coats of


18.2 approved quality and colour ready made
enamel paints over one coat of wood primer
with good finish as per instruction all complete Sqm 182.40 327.15 59,672.94
19
HAND RAILING WORKS As per instructed by
Project Manager or Site engineers.

Making and fitting 1" x 1" size square pipe


railing having height 3'-0" to 3'-0" including 3"
x 4" size seasoned saal wood handrail on top
of railing and brass caping on bottom of each
square pipe of railing with 1 coat primer and 2
coats enamel paint on railing and 3 coats
chapra polish on handrail all complete Sqm 41.86 8,812.98 368,915.44
MS GRILL FOR WINDOW As per instructed
20
by Project Manager or Site engineers.

Supplying, fabrication of 3 x 20 mm MS grill


and fitting in window including cleaning by
sand paper, applying one coat metal primer
and two coats aluminium paints all complete
Sqm Err:509 2,059.59 1.00
MS COLLAPSIBLE GATE As per instructed
by Project Manager or Site engineers.
21
Supplying, fabrication and fitting of MS
collapsible gate including cleaning by sand
paper, applying one coat metal primer and two
coats aluminium paints all complete Sqm Err:509 3,703.81 1.00
22 TILES WORKS As per instructed by Project
Manager or Site engineers.
22.1 8"x12" Tile on wall surface Sqm 1,877.76 3,121.54 5,861,493.73
22.2 12"x12" Tile on floor surface Sqm 729.92 3,121.54 2,278,470.89
23 MARBAL LAYING AND PLACING
13 mm thick marble (450 x450 mm) over 20
mm1:2 surki with rubbing & polish to finish
also Sqm 3694.86 4265.93 15,762,014.12

26 Expansion joint Run m 387.55 5847.75 2,266,295.51


1,023,795,886.26
SANITARY WORKS As per instructed by
Project Manager or Site engineers.
28
Supply and installation of the following
bathroom fixtures as per the specification and
instruction all complete 46.00 19,506.06 897,278.76
White glazed porcelain clay EWC
Constellation commode with 'P ' & 's ' trap
and seat cover set.(Hindware, Paryware,
Somany, cera or eqv.)
Sets 15.00 2,717.09 40,756.28
White glazed porcelain pan i)530mm size
white glazed without siphon Sets 40.00 4,493.28 179,731.02

11
Prepared Design By: Approved By:
Checked By:
Detail Project Report (DPR) of Godavari Municipality Building Bajarbarahi, Lalitpur

ABSTRACT OF COST

Project :- Construction of Godavari Municipality Building Bajarbarahi, Lalitpur

S.N. DESCRIPTION OF WORKS UNIT QUANTITY RATE AMOUNT REMARKS


Urinal set i) Porcelain clay white glaze large
flat back urinal 61×41×38 cm size (Hindware,
Paryware, Somany, cera or eqv.)

Sets 60.00 2,040.00 122,400.00


Wash basin set consists of white glazed
vitreous China procelain single hole lavatory
basin of H.S.L. WB No. 10046 (Approx. District
510mmx380mm) C.P. pillar cocks for hot and Rate
cold water, counter & nessary of brass bottle
trap syphoney etc.all complete.

Sets 61.00 805.00 49,105.00


Toilet mirror consists of mirror size
(600x500mm) of float glass India with plastic
mounted back base for mirror Sets 45.00 619.52 27,878.40
Glass-shelf of size 120mm x 480mm Sets 60.00 702.90 42,174.00
Providing and installation of floor trap set
consisting of nahani trap or floor trap of size
100x50 mm of PVC body with all nessary
fitting.necessary fittings.
Sets 24.00 401.50 9,636.00
Providing and fixing toilet taps with all
necessary fittings with short body bib cock CP
taps Sets 24.00 268.64 6,447.36
Soap Tray Sets 24.00 410.00 9,840.00
Towel rod Market
Sets 701.76 95.00 66,667.20
Rate
Providing and properly appling two coat of hi-
tech chemical water proofing treatment by
crystallizating prepared at site just before
application by mixing 2.5 volumes of chemical
to one volume of water to form smooth Sqft
paintable/brushable slurry result on two
surface of RCC slab ,well damped after
properly cleaned witk wire brush.

Water supply line / sanitary line


(B) ( Drainage ) As per instructed by Project
Manager or Site engineers.

Providing and installation of gun metal gate


a valve 12.00 8,000.00 96,000.00
I) NB 40mm Sets 18.00 2,240.00 40,320.00
ii) NB 25mm Sets
CPVC Pipes & Fittings for hot and cold water
distribution system CPVC means Chlorinated
Poly Vinyl Chloride as per ASTM are as per
ASTM F 442, CPVC SOLVENT are as per
b
ASTM F-493 2846 (Flowguard : astral,
ashivad, ajay, marvel or eqv.

CPVC Pipe SDR 13.5 (22.5 Kg/cm2) 717.38 129.88 93,173.83


1/2" dia Rm 467.99 180.97 84,690.64
3/4" dia ,, 430.79 237.25 102,205.31
1" dia ,, 375.00 295.26 110,723.61
1-1/4" dia ,, 250.00 413.02 103,255.45
1-1/2" dia ,, 150.00 631.22 94,683.30
2" dia ,,
CPVC Ball Valve (CTS Sockets) 250.00 412.93 103,232.25
1/2" Nos 125.00 549.15 68,644.13
3/4" Nos 100.00 664.09 66,409.20
12
Prepared Design By: Approved By:
Checked By:
Detail Project Report (DPR) of Godavari Municipality Building Bajarbarahi, Lalitpur

ABSTRACT OF COST

Project :- Construction of Godavari Municipality Building Bajarbarahi, Lalitpur

S.N. DESCRIPTION OF WORKS UNIT QUANTITY RATE AMOUNT REMARKS


1" Nos 75.00 1,549.55 116,216.10
1-1/4" Nos 50.00 1,856.05 92,802.60
1-1/2" Nos 25.00 2,392.43 59,810.85
2" Nos - - -
CPVC Reducer Brass Coupling 250.00 155.86 38,964.32
3/4" X 1/2" Nos 230.00 204.35 46,999.63
1" X 1/2" Nos - - -
CPVC Tee 180.00 40.70 7,325.29
1/2" Nos 150.00 86.59 12,988.11
3/4" Nos 120.00 132.48 15,897.44
1" Nos 100.00 248.51 24,850.58
1-1/4" Nos 75.00 361.94 27,145.14
1-1/2" Nos 50.00 775.82 38,791.15
2" Nos - - -
CPVC Reducer Tee 150.00 79.66 11,949.06
1/2" x 1/2" x 3/4" Nos 150.00 121.22 18,183.35
3/4" x 3/4" x1/2" Nos 150.00 151.53 22,729.19
3/4" x 1/2" x 3/4" Nos 150.00 173.17 25,976.21
3/4" x 1/2" x 1/2" Nos 75.00 181.83 13,637.51
1" x 1" x 3/4" Nos 75.00 283.14 21,235.55
1-1/2" x 1-1/2" x 1" Nos 75.00 492.68 36,951.16
2" x 2" x 1" Nos 75.00 160.19 12,014.00
1-1/4" x 1-1/4" x 1/2" Nos 50.00 173.17 8,658.74
1-1/4" x 1-1/4" x 1" Nos 50.00 484.02 24,201.17
2" x 2" x 1/2" Nos 50.00 112.56 5,628.18
1" x 1" x 1/2" Nos - - -
CPVC Brass FPT Tee 75.00 135.94 10,195.66
1/2" x 1/2" x 1/2" Nos 70.00 141.14 9,879.62
3/4" x 3/4" x 1/2" Nos 65.00 156.72 10,187.01
1" x 1" x 1/2" Nos 50.00 566.28 28,314.07
1-1/4" x 1-1/4" x 1-1/4" Nos 45.00 307.39 13,832.33
1-1/4" x 1-1/4" x 1/2" Nos - - -
CPVC Elbow 90º 75.00 28.57 2,143.04
1/2" Nos 70.00 58.88 4,121.56
3/4" Nos 60.00 107.37 6,442.10
1" Nos 55.00 202.61 11,143.80
1-1/4" Nos 50.00 302.19 15,109.50
1-1/2" Nos 45.00 646.81 29,106.35
2" Nos - - -
CPVC Reducer Elbow 90º 150.00 59.75 8,961.79
3/4" X 1/2" Nos - - -
CPVC Brass FPT Elbow 90º 250.00 94.38 23,595.06
1/2" x 1/2" Nos 230.00 109.97 25,292.17
3/4" x 1/2" Nos 130.00 125.55 16,321.72
3/4" x 3/4" Nos 100.00 242.44 24,244.47
1" X 1/2" Nos 50.00 673.65 33,682.49
1" X 1" Nos 60.00 874.53 52,471.95
1-1/4" x 1-1/4" Nos - - -
CPVC Elbow 45º 250.00 33.77 8,442.27
1/2" Nos 125.00 61.48 7,684.63
3/4" Nos 100.00 87.45 8,745.33
1" Nos 75.00 154.13 11,559.42
1-1/4" Nos 25.00 222.53 5,563.24
District
1-1/2" Nos 20.00 482.29 9,645.83 Rate
2" Nos - - -
CPVC Male Adapter (CPVC Threads) 280.00 25.11 7,030.90
1/2" Nos 250.00 44.16 11,039.89
3/4" Nos 230.00 66.67 15,334.62
1" Nos 65.00 119.49 7,766.89
13
Prepared Design By: Approved By:
Checked By:
Detail Project Report (DPR) of Godavari Municipality Building Bajarbarahi, Lalitpur
District
ABSTRACT OF COST Rate

Project :- Construction of Godavari Municipality Building Bajarbarahi, Lalitpur

S.N. DESCRIPTION OF WORKS UNIT QUANTITY RATE AMOUNT REMARKS


1-1/4" Nos 75.00 167.98 12,598.46
1-1/2" Nos 50.00 328.17 16,408.31
2" Nos - - -
CPVC Reducing Male Adapter (CPVC
Threads) 85.00 45.89 3,900.76
3/4" x 1/2" Nos - - -
CPVC Male Adapters (Brass Threads) 130.00 232.92 30,279.61
1/2" Nos 100.00 301.32 30,132.41
3/4" Nos 75.00 476.23 35,717.29
1" Nos 60.00 1,045.98 62,758.53
1-1/4" Nos 55.00 1,220.88 67,148.51
1-1/2" Nos 25.00 2,512.77 62,819.14
2" Nos - - -
CPVC Reducing Male Adapter (Brass
Threads) 244.00 258.90 63,170.69
3/4" x 1/2" Nos - - -
CPVC Female Adapter (CPVC Threads) 335.00 34.63 11,602.71
1/2" Nos 125.00 58.01 7,251.69
3/4" Nos 100.00 86.59 8,658.74
1" Nos - - -
CPVC Female Adapters Brass Threads 150.00 223.40 33,509.32
1/2" Nos 120.00 303.92 36,470.60
3/4" Nos 100.00 394.84 39,483.85
1" Nos 75.00 1,036.45 77,733.82
1-1/4" Nos 50.00 1,152.48 57,623.90
1-1/2" Nos 25.00 2,253.00 56,325.09
2" Nos - - -
CPVC Caps 250.00 14.72 3,679.96
1/2" Nos 220.00 27.71 6,095.75
3/4" Nos 150.00 41.56 6,234.29
1" Nos 75.00 81.39 6,104.41
1-1/4" Nos 70.00 119.49 8,364.34
1-1/2" Nos 65.00 254.57 16,546.85
2" Nos - - -
CPVC Union 250.00 305.65 76,413.36
1/2" Nos 105.00 449.39 47,185.79
3/4" Nos 100.00 532.51 53,251.24
1" Nos 75.00 974.11 73,058.10
1-1/4" Nos 65.00 1,065.02 69,226.61
1-1/2" Nos 55.00 1,528.27 84,054.70
2" Nos - - -
CPVC Cross Tee 250.00 55.42 13,853.98
1/2" Nos 300.00 119.49 35,847.18
3/4" Nos - - -
CPVC Step Over Bend 250.00 71.00 17,750.41
1/2" Nos 150.00 117.76 17,663.83
3/4" Nos - - -
CPVC Ball Valve (CTS Sockets) 125.00 747.25 93,406.14
1/2" Nos 120.00 910.03 109,204.00
3/4" Nos 110.00 1,040.78 114,485.83
1" Nos 50.00 2,123.12 106,156.13
1-1/4" Nos 40.00 2,701.53 108,061.05
1-1/2" Nos 25.00 3,474.75 86,868.79
2" Nos - - -
CPVC Flow Guard Adhesive Solution 50.00 1,662.48 83,123.88
946ML Nos - - -
Plastic Strap 61.00 5.20 316.91
1/2" Nos 65.00 6.06 393.97
3/4" Nos 55.00 8.66 476.23
14
Prepared Design By: Approved By:
Checked By:
Detail Project Report (DPR) of Godavari Municipality Building Bajarbarahi, Lalitpur

ABSTRACT OF COST

Project :- Construction of Godavari Municipality Building Bajarbarahi, Lalitpur

S.N. DESCRIPTION OF WORKS UNIT QUANTITY RATE AMOUNT REMARKS


1" Nos 15.00 12.99 194.82
1-1/4" Nos 60.00 16.45 987.10
1-1/2" Nos 20.00 20.78 415.62
2" Nos - - -
Tee Holder 180.00 6.06 1,091.00
1/2" X 1/2" X 1/2" Nos 180.00 8.66 1,558.57
3/4" X 3/4" X 1/2" Nos - - -
Elbow Holder 180.00 6.06 1,091.00
1/2" X 1/2" Nos 180.00 7.79 1,402.72
1/2" X 3/4" Nos - - -
Snap Fix Repair Coupling 10.00 258.90 2,588.96
1/2" Nos 150.00 280.54 42,081.47
3/4" Nos 1,500.00 12.99 19,482.16
End plug threaded 1/2" Nos 75.00 6,100.00 457,500.00
c
Providing and installation UVC Pipe-4 Kg/sq.
cm Rain water pipes with necessary all fittings
as per detail drawings I) OD - 100 Pic
d Soil and waste pipes 75.00 269.00 20,175.00
I) OD-75 r.m 50.00 3,017.00 150,850.00
ii) 4 inch valve bend Kg 4.00 6,792.09 27,168.37
e Providing & installation of water pump (1.5 Sets 4,000.00 14.00 56,000.00
f HP)
Providing and Installation of 1000 Lt. PVC Liter 6,250,068.76
Water Tank all complete as per instructed by
engineers. Total Sanitary Works
29 ELECTRICAL WORKS
(A) Wiring of light/fan & power points:
Following Light /Power /fan Points shall cover
all necessary conduit, PVC duct, Bottom, HDP
pipe 3/22 sliver wire. as per site condition with
furniture layout and As instructed by Project
Manager or Site engineers..( make: NS
stander)
District Rate
pointswith 2 no 3/22 cable & junction
Light Point 450.00 1,328.25 597,712.50
boxes. Points 480.00 3,307.50 1,587,600.00
Power Points 10A 3 pin socket Light point with
7/22 cable &junction Boxes Points 200.00 252.00 50,400.00
Light fixture of Approved Brand of
(B) Wipro,Havells with CFL bulb or Philips Points 50.00 1,401.75 70,087.50
(C) equivalent brand
Ex-Fan Points Points
(D) Switches, Light &Power and plug in
sockets (North-West or equivalent)
Supply of materials (Modular type light
switches, light and power sockets, weather
proof plug-in-power sockets as mentioned
below, 18 SWG GI metal boxes, Screw and
other necessary materials) installation, 267,750.00
interconnection and commissioning. As per
instructed by Project Manager or Site
engineers.
150.00 1,785.00
a 6 A 6 gang 1 way switch Sets 150.00 1,785.00 267,750.00
b 6 A 3 gang 1 way switch Sets 150.00 1,785.00 267,750.00
c 6 A 2 gang 1 way switch Sets
( E) Power Cable: 4,500.00 27.00 121,500.00

15
Prepared Design By: Approved By:
Checked By:
Detail Project Report (DPR) of Godavari Municipality Building Bajarbarahi, Lalitpur

ABSTRACT OF COST

Project :- Construction of Godavari Municipality Building Bajarbarahi, Lalitpur

S.N. DESCRIPTION OF WORKS UNIT QUANTITY RATE AMOUNT REMARKS


Supply of materials (cables,pipe,cable shoes)
& laying , interconnection & testing of
following size of pvc insulated Cu. cable
including digging,refilling, compction & cable
termination with cable shoes of suitable size RM
using crimping device. As per instructed by
Project Manager or Site engineers.

( F) Earthing and Lighting protection system 2.00 5,579.00 11,158.00


Supply of materials necessary for earthing
system loke copper plate (600X600X6 mm),
salt, charcoal dust 25mm wide copper strip &
copper nut, bolts, spring washer, bolts
watering 30mm dia PVC pipe & its installation
in a whole of 90X90X150 cm with layers of
materials (as per site condition contractor can
sets
installed the 2235mm long 25mm dia copper
Grounding Rod and make the Bonding for
Grid) As per instructed by Project Manager or
Site engineers.

Electrical Main Panel & Distribution Boards District Rate


(G) Circuit Breakers: Merlin
Gerlin/Legrand/ABB/Simens/Havels
Supply, delivery, Testing, installation and
Commissioning of the following floor/ Pad/
Wall Mounted Panel/ Distribution Board
(440/400/230 V, 50 Hz) with transparent
acrylic and separate chamber for Bus bar
enclosure made from 16 SWG HRCA Sheet
metal including necessary cable. As per
instructed by Project Manager or Site
engineers.

Main PB
Incoming
40 A, 25KA, MCCB TP Moulded-1 set.
60A TPNE Copper bus bat with hardware and
1100 volt insulating -1 set.
0-500 Volt meter Digital Static unit with
selecting device-1 set.
Outgoing 14.00 5,590.00 78,260.00
6/16/20/60 A MCB Sets 14.00 225.00 3,150.00
Distribution Box Sets
Wiring of Telephone points
Following points shall cover all necessary
conduit, PVC duct, Bottom, HD pipe etc as per
site condition with furniture layout and As
instructed by Project Manager or Site
engineers.
Supply and materials and wiring in suitable
size medium presser PVC conduit concealed/
false ceiling without any joint in middle of the
span. As per instructed by Project Manager or
Site engineers.
150.00 320.00 48,000.00
Telephone points with CAT-5 Cable. Points 75.00 4,484.00 336,300.00
56''Celling Fans Sets 150.00 234.00 35,100.00
15 watt CFL Bulbs Sets 150.00 339.00 50,850.00
25 watt CFL Bulbs Sets 100.00 489.00 48,900.00

16
Prepared Design By: Approved By:
Checked By:
Detail Project Report (DPR) of Godavari Municipality Building Bajarbarahi, Lalitpur

ABSTRACT OF COST

Project :- Construction of Godavari Municipality Building Bajarbarahi, Lalitpur

S.N. DESCRIPTION OF WORKS UNIT QUANTITY RATE AMOUNT REMARKS


Weather proof light Sets 3,842,268.00
Total Electrical Works
1.00 1,000,000.00 1,000,000.00
30 Rain Water Harvesting no. 1.00 1,500,000.00 1,500,000.00
31 Emergency Exit no. 2,500,000.00
Total Other Works #REF!
Grand Total #REF!
Add vat 13% #REF!
Total with VAT #REF!
Contingencies (3 % of total estimated cost) #REF!
Physical contingencies 10% #REF!
Price escalation contengency 10% #REF!
Total Project Cost

17
Prepared Design By: Approved By:
Checked By:
Project :- Construction of Godavari Municipality Building Bajarbarahi, Lalitpur
Quantity Estimate
Length Area (Sq
S.N Description No Breadth (m) Height (m) Quantity Remarks
(m) m)

1 SITE CLEARANCE WORKS


Site clearance work including cutting herbs,
shrubs and removal
Building Area 1 8465.00 1 8465.00
Other Parts 1 26496.41 26496.41
Total 34961.41 Sqm

2 EXCAVATION WORKS
Raft Footing @ 3.6m depth 1.00 3142.00 1.00 3.60 11311.20
Raft Footing @ 2m depth 1.00 5323.00 1.00 2.00 10646.00
other area except building 1 511058 511058.00
Total 533015.20 Cum

3 Solling Works
At Footing
Raft Footing @ 3.6m depth 1.00 3142.00 1.00 0.07 204.23
Raft Footing @ 2m depth 1.00 5323.00 1.00 0.07 346.00
Total 550.23 Sqm

4 Back Filling

Providing and laying to Back fill the foundation


area below plinth level in perfect line & level as
per the design, drawing, specification &
instructions of engineer(periphery area) 101910.00 101910.00

Providing and laying to Back fill the foundation


area below plinth level in perfect line & level as
per the design, drawing, specification &
instructions of engineer(building area) 30% of E/W Excavation 6587.16
Total 108497.16 Cum

5 Transporting and disposing the surplus earth and debris

Transporting and disposing the surplus earth


and debris from the site including re-excavating
the deposited soil excavated earlier if any,
transporting, loading, laying at all depths and
heights, stacking, leveling, and dressing both
the areas for leads as per the design, drawing,
specification & instructions of engineer on safe
place. 70% of E/W Excavation 7917.84
Total 7917.84 Cum

7 P.C.C WORKS
At Footing (1:3:6)
Raft Footing @ 3.6m depth 1.00 3142.00 0.10 314.20
Raft Footing @ 2m depth 1.00 5323.00 0.10 532.30
Total 846.50 Cum

8 RCC WORK (1:1.5:3)


Footing
Raft Footing @ 3.6m depth 1.00 3142.00 1.00 1.00 3142.00
Raft Footing @ 2m depth 1.00 5323.00 1.00 1.00 5323.00
3142.00 Cum
Total RCC for footing
Shear Wall
Basement
basement wall 1.00 452.20 0.30 3.60 488.38
Water tank 1.00 60.00 0.75 15.00 675.00
1.00 20.00 20.00 0.75 300.00
Septic tank 1.00 45.00 0.75 15.00 506.25
1.00 15.00 20.00 0.75 225.00
2194.63 Cu m

18
Prepared /Design By: Approved By
Checked By:
Project :- Construction of Godavari Municipality Building Bajarbarahi, Lalitpur
Quantity Estimate
Length Area (Sq
S.N Description No Breadth (m) Height (m) Quantity Remarks
(m) m)

Total RCC for Shear Wall


Column
Grid A 22.00 0.60 0.60 2.00 15.84
Grid B 22.00 0.60 0.60 5.60 44.35
Grid C 22.00 0.60 0.60 9.20 72.86
Grid D 22.00 0.60 0.60 9.20 72.86
Grid E 16.00 0.60 0.60 5.60 32.26
Grid F(36-84) 39.00 0.60 0.60 3.60 50.54
Grid F(23-35,85-98) 26.00 0.60 0.60 2.00 18.72
Grid G(36-84) 39.00 0.60 0.60 7.20 101.09
Grid G(23-35,85-98) 26.00 0.60 0.60 5.6 52.416
Grid H(36-84) 39.00 0.60 0.60 10.80 151.63
Grid H(23-35,85-98) 26.00 0.60 0.60 9.20 86.11
Total RCC for Column 698.69 Cum

Main Beam
Ground Floor
Grid along F 1.00 330.00 0.30 0.60 59.40
Grid along G 1.00 361.20 0.30 0.60 65.02
Grid along H 1.00 395.60 0.30 0.60 71.21
Grid along 23-98 65.00 15.00 0.30 0.60 175.50

Cicumferential Secondary Beam between grid F


&G 1.00 205.00 0.23 0.50 23.58
Cicumferential Secondary Beam between grid G
&H 1.00 214.20 0.23 0.50 24.63

Radial Secondary Beam between grid F, G &H 35.00 13.50 0.23 0.50 54.34
Grid along A 1.00 121.00 0.30 0.60 21.78
Grid along B 1.00 121.00 0.30 0.30 10.89
Grid along C 1.00 121.00 0.30 0.30 10.89
Grid along D 1.00 121.00 0.30 0.30 10.89
Grid along E 1.00 93.00 0.30 0.30 8.37
Grid along 1,2,3,20,21,22 6.00 23.00 0.30 0.30 12.42
Grid along 4-19 16.00 26.60 0.30 0.30 38.30
First Floor
Grid along G 1.00 361.20 0.50 0.70 126.42
Grid along H 1.00 395.60 0.50 0.70 138.46
Grid along 23-98 65.00 6.30 0.50 0.70 143.33

Cicumferential Secondary Beam between grid G


&H 1.00 361.20 0.23 0.50 41.54

Radial Secondary Beam between grid G &H 60.00 6.30 0.23 0.50 43.47
Grid along B 1.00 121.00 0.30 0.60 21.78
Grid along C 1.00 121.00 0.30 0.60 21.78
Grid along D 1.00 121.00 0.30 0.60 21.78
Grid along E 1.00 93.00 0.30 0.60 16.74
Grid along 1,2,3,20,21,22 6.00 15.10 0.30 0.60 16.31
Grid along 4-19 16.00 18.70 0.30 0.60 53.86

Secondary Beam along East-West between grid


1,2,3,20,21,22 4.00 15.10 0.23 0.50 6.95

Secondary Beam along East-West between grid


4-19 10.00 18.70 0.23 0.50 21.51

Secondary Beam along North south between


grid 1 -22 1.00 456.00 0.23 0.50 52.44
Second Floor
Grid along H 1.00 395.60 0.50 0.70 138.46
Grid along C 1.00 121.00 0.50 0.70 42.35
Grid along D 1.00 121.00 0.30 0.60 21.78
Grid along E 1.00 93.00 0.30 0.60 16.74

19
Prepared /Design By: Approved By
Checked By:
Project :- Construction of Godavari Municipality Building Bajarbarahi, Lalitpur
Quantity Estimate
Length Area (Sq
S.N Description No Breadth (m) Height (m) Quantity Remarks
(m) m)

Grid along 1,2,3,20,21,22 6.00 7.10 0.30 0.60 7.67


Grid along 4-19 16.00 10.70 0.30 0.60 30.82

Secondary Beam along East-West between grid


1,2,3,20,21,22 4.00 7.10 0.23 0.50 3.27

Secondary Beam along East-West between grid


4-19 10.00 10.70 0.23 0.50 12.31

Secondary Beam along North south between


grid 1 -22 1.00 335.00 0.23 0.50 38.53
Third Floor
Grid along C 1.00 121.00 0.50 0.70 42.35
Grid along D 1.00 121.00 0.30 0.60 21.78
Grid along 1,2,3,20,21,22 6.00 7.10 0.30 0.60 7.67
Grid along 4-19 16.00 10.70 0.30 0.60 30.82

Secondary Beam along East-West between grid


1,2,3,20,21,22 4.00 6.90 0.23 0.50 3.17

Secondary Beam along East-West between grid


4-19 10.00 6.90 0.23 0.50 7.94

Secondary Beam along North south between


grid 1 -22 1.00 121.00 0.23 0.50 13.92

Inclined beams along grids 1-98 88.00 15.80 0.30 0.60 250.27

Inclined beams along grids 1-98 in between 87.00 15.80 0.23 0.50 158.08
Total Beam Work 1753.11 Cum
Lintel and sill band
Ground Floor
Wall along grid G 1.00 361.20 0.23 0.15 24.92
Wall along grid H 1.00 395.60 0.23 0.15 27.30

Wall along grid


23,24,25,27,28,30,31,32,35,36,38,39,40,41,43,4
4,47-52,55-57,59,60,70-73,76,77,79-82,84-
85,88,89,92-95,96-98 39.00 5.40 0.12 0.15 7.27
Wall along grid B 1.00 126.50 0.23 0.15 8.73
Wall along grid C 1.00 92.40 0.23 0.15 6.38
Wall along grid D 1.00 80.00 0.23 0.15 5.52
Wall along grid E 1.00 93.00 0.23 0.15 6.42
Wall along gridS 1-22 1.00 215.00 0.12 0.15 7.42
First Floor 0.00
Wall along grid H 1.00 18.70 0.23 0.15 1.29
Wall along grid C 1.00 92.40 0.23 0.15 6.38
Wall along grid D 1.00 80.00 0.23 0.15 5.52
Wall along grid E 1.00 93.00 0.23 0.15 6.42
Wall along gridS 1-22 1.00 102.00 0.12 0.15 3.52
Second Floor 0.15 0.00
Wall along grid C 1.00 92.40 0.23 0.15 6.38
Wall along grid D 1.00 80.00 0.23 0.15 5.52
Wall along grid E 1.00 93.00 0.23 0.15 6.42
Wall along gridS 1-22 1.00 95.00 0.12 0.15 3.28
Third Floor
Wall along grid C 1.00 92.40 0.12 0.15 3.19
Wall along grid D 1.00 80.00 0.12 0.15 2.76

walls between blocks 1.00 32.00 0.23 0.15 2.21


Total Lintel and sill
band 146.81 Cum

Slab
Ground Floor
Slab 1.00 6708.00 1.00 0.13 838.50

20
Prepared /Design By: Approved By
Checked By:
Project :- Construction of Godavari Municipality Building Bajarbarahi, Lalitpur
Quantity Estimate
Length Area (Sq
S.N Description No Breadth (m) Height (m) Quantity Remarks
(m) m)

First Floor
Slab 1.00 4703.00 1.00 0.13 587.88
Deduction of void -1.00 73.00 1.00 0.13 -9.13
Deduction of Staircase -1.00 32.00 1.00 0.13 -4.00
Second Floor
Slab 1.00 1266.00 1.00 0.13 158.25
Deduction of Staircase -1.00 32.00 1.00 0.13 -4.00
Third Floor
Slab 1.00 1266.00 1.00 0.13 158.25
Total Slab Work 1725.75 Cum

Staircase
Basement Floor
Dog -legged stair 2.00 23.76 1.00 0.20 9.50
Straight stair 0.00 1.00 1.00 0.20 0.00
Ground Floor
Dog -legged stair 4.00 23.76 1.00 0.20 19.01
Straight stair 23.00 16.00 1.00 0.20 73.60
First Floor
Dog -legged stair 2.00 23.76 1.00 0.20 9.50
Straight stair 0.00 1.00 1.00 0.20 0.00
Second Floor
Dog -legged stair 2.00 23.76 1.00 0.20 9.50
Straight stair 0.00 1.00 1.00 0.20 0.00

East block steps


steps 1.00 150.00 1.00 0.20 30.00
Parapet seatings
Stepped Slab 1.00 482.00 1.00 7.53 3629.46
Total Staircase Work 3780.58 Cum

Slab of Ramp
Ramp slab 2.00 120.00 1.00 0.30 72.00
Grand Total RCC Work 13513.56 Cum

9 REINFORCEMENT WORK

Supplying, cutting, bending, placing in position


as shown in drawing and binding by plain wire
of reinforcement steel bars for R.C.C. works all
complete
For Footing = 3142 M3 @ 0.85% X 7850 kg/M3 = 209649.95
For Shear wall = 2194.63 M3 @ 1.25 % X 7850 kg/M3 = 215347.68
For Column = 776.45 M3 @ 3 % X 7850 kg/M3 = 164541.02
For beam = 1973.6 M3 @ 2.0% x 7850 kg/M3 = 298287.57
For slab = 1797.75M3 @ 1.0% x 7850 kg/M3 = 141123.38
For stair case steps =3780.58 M3 @ 1.7% x 7850 kg/M3 = 504518.40
Total reinforcement work for concreting = 1533467.99 Kg
1533.47 M.T.
10 FORM WORK
For Footing
Raft Foundation 1 1.00 1052.00 1.00 1052.00
Total Form Work for footing 1052.00 Sqm

For Column
Grid A 22.00 0.60 0.60 2.00 105.60
Grid B 22.00 0.60 0.60 5.60 295.68
Grid C 22.00 0.60 0.60 9.20 485.76
Grid D 22.00 0.60 0.60 9.20 485.76
Grid E 16.00 0.60 0.60 5.60 215.04
Grid F(36-84) 39.00 0.60 0.60 3.60 336.96
Grid F(23-35,85-98) 26.00 0.60 0.60 2.00 124.80
Grid G(36-84) 39.00 0.60 0.60 7.20 673.92
Grid G(23-35,85-98) 26.00 0.60 0.60 5.6 349.44

21
Prepared /Design By: Approved By
Checked By:
Project :- Construction of Godavari Municipality Building Bajarbarahi, Lalitpur
Quantity Estimate
Length Area (Sq
S.N Description No Breadth (m) Height (m) Quantity Remarks
(m) m)

Grid H(36-84) 39.00 0.60 0.60 10.80 1010.88


Grid H(23-35,85-98) 26.00 0.60 0.60 9.20 574.08
4657.92 Sqm
Total Form Work for Column
Shear Wall
Basement
basement wall 1.00 452.20 3.60 3255.84
3255.84 Sqm
Total Form Work for Shear Wall

Beam
Grid along F 1.00 330.00 0.30 0.60 495.00
Grid along G 1.00 361.20 0.30 0.60 541.80
Grid along H 1.00 395.60 0.30 0.60 593.40
Grid along Beam
Cicumferential Secondary 23-98 between grid F 65.00 15.00 0.30 0.60 22.50
Cicumferential Secondary &G Beam between grid G 1.00 205.00 0.23 0.50 252.15
&H 1.00 214.20 0.23 0.50 263.47
Radial Secondary Beam between grid F, G &H 35.00 13.50 0.23 0.50 16.61
Grid along A 1.00 121.00 0.30 0.60 181.50
Grid along B 1.00 121.00 0.30 0.30 108.90
Grid along C 1.00 121.00 0.30 0.30 108.90
Grid along D 1.00 121.00 0.30 0.30 108.90
Grid along E 1.00 93.00 0.30 0.30 83.70
Grid along 1,2,3,20,21,22 6.00 23.00 0.30 0.30 20.70
Grid along 4-19 16.00 26.60 0.30 0.30 23.94
First Floor 0.00
Grid along G 1.00 361.20 0.50 0.70 686.28
Grid along H 1.00 395.60 0.50 0.70 751.64
Grid alongBeam
Cicumferential Secondary 23-98 between grid G 65.00 6.30 0.50 0.70 11.97
&H 1.00 361.20 0.23 0.50 444.28
Radial Secondary Beam between grid G &H 60.00 6.30 0.23 0.50 7.75
Grid along B 1.00 121.00 0.30 0.60 181.50
Grid along C 1.00 121.00 0.30 0.60 181.50
Grid along D 1.00 121.00 0.30 0.60 181.50
Grid along E 1.00 93.00 0.30 0.60 139.50
Grid along 1,2,3,20,21,22 6.00 15.10 0.30 0.60 22.65
Secondary BeamGrid alongalong 4-19 between grid
East-West 16.00 18.70 0.30 0.60 28.05
Secondary Beam 1,2,3,20,21,22
along East-West between grid 4.00 15.10 0.23 0.50 18.57
Secondary Beam along 4-19North south between 10.00 18.70 0.23 0.50 23.00
grid 1 -22 1.00 456.00 0.23 0.50 560.88
Second Floor 0.00
Grid along H 1.00 395.60 0.50 0.70 751.64
Grid along C 1.00 121.00 0.50 0.70 229.90
Grid along D 1.00 121.00 0.30 0.60 181.50
Grid along E 1.00 93.00 0.30 0.60 139.50
Grid along 1,2,3,20,21,22 6.00 7.10 0.30 0.60 10.65
Secondary BeamGrid alongalong 4-19 between grid
East-West 16.00 10.70 0.30 0.60 16.05
Secondary Beam 1,2,3,20,21,22
along East-West between grid 4.00 7.10 0.23 0.50 8.73
Secondary Beam along 4-19North south between 10.00 10.70 0.23 0.50 13.16
grid 1 -22 1.00 335.00 0.23 0.50 412.05
Third Floor 0.00
Grid along C 1.00 121.00 0.50 0.70 229.90
Grid along D 1.00 121.00 0.30 0.60 181.50
Grid along 1,2,3,20,21,22 6.00 7.10 0.30 0.60 10.65
Secondary BeamGrid alongalong 4-19 between grid
East-West 16.00 10.70 0.30 0.60 16.05
Secondary Beam 1,2,3,20,21,22
along East-West between grid 4.00 6.90 0.23 0.50 8.49
Secondary Beam along 4-19North south between 10.00 6.90 0.23 0.50 8.49
grid 1 -22 1.00 121.00 0.23 0.50 148.83
Inclined beams along grids 1-98 88.00 15.80 0.30 0.60 23.70
Inclined beams along grids 1-98 in between 87.00 15.80 0.23 0.50 19.43
7975.752 Sq m
Total Form Work for Beam

Lintel and sill band


Ground Floor
Wall along grid G 1.00 395.60 0.23 0.15 118.68
Wall along grid H 1.00 6.30 0.23 0.15 1.89

22
Prepared /Design By: Approved By
Checked By:
Project :- Construction of Godavari Municipality Building Bajarbarahi, Lalitpur
Quantity Estimate
Length Area (Sq
S.N Description No Breadth (m) Height (m) Quantity Remarks
(m) m)

Wall along grid


23,24,25,27,28,30,31,32,35,36,38,39,40,41,43,4
4,47-52,55-57,59,60,70-73,76,77,79-82,84-
85,88,89,92-95,96-98 49.00 5.40 0.12 0.15 79.38
Wall along grid B 1.00 126.50 0.23 0.15 37.95

Wall along grid C 1.00 92.40 0.23 0.15 27.72


Wall along grid D 1.00 80.00 0.23 0.15 24.00
Wall along grid E 1.00 93.00 0.23 0.15 27.90
Wall along gridS 1-22 1.00 215.00 0.12 0.15 64.50
First Floor 0.00
Wall along grid H 1.00 15.10 0.23 0.15 4.53
Wall along grid C 1.00 92.40 0.23 0.15 27.72
Wall along grid D 1.00 80.00 0.23 0.15 24.00
Wall along grid E 1.00 93.00 0.23 0.15 27.90
Wall along gridS 1-22 1.00 102.00 0.12 0.15 30.60
Second Floor
Wall along grid C 1.00 92.40 0.23 0.15 27.72
Wall along grid D 1.00 80.00 0.23 0.15 24.00
Wall along grid E 1.00 93.00 0.23 0.15 27.90
Wall along gridS 1-22 1.00 95.00 0.12 0.15 28.50
Third Floor
Wall along grid C 1.00 92.40 0.12 0.15 27.72
Wall along grid D 1.00 80.00 0.12 0.15 24.00

walls between blocks 1.00 32.00 0.23 0.15 9.60


666.21 Sq m
Total Form Work for Lintel and Sil Band

Slab
Ground Floor
Slab 1.00 6708.00 1.00 1.00 6708.00
First Floor
Slab 1.00 4703.00 1.00 1.00 4703.00
Deduction of void -1.00 73.00 1.00 1.00 -73.00
Deduction of Staircase -1.00 32.00 1.00 1.00 -32.00
Second Floor
Slab 1.00 1266.00 1.00 1.00 1266.00
Deduction of Staircase -1.00 32.00 1.00 1.00 -32.00
Third Floor
Slab 1.00 1266.00 1.00 0.13 158.25
12698.25 Sq m
Total Form Work for Slab

Staircase
Basement Floor
Dog -legged stair 2.00 23.76 1.00 1.00 47.52
Straight stair 0.00 1.00 1.00 1.00 0.00
Ground Floor
Dog -legged stair 4.00 23.76 1.00 1.00 95.04
Straight stair 23.00 16.00 1.00 1.00 368.00
First Floor
Dog -legged stair 2.00 23.76 1.00 1.00 47.52
Straight stair 0.00 1.00 1.00 1.00 0.00
Second Floor
Dog -legged stair 2.00 23.76 1.00 1.00 47.52
Straight stair 0.00 1.00 1.00 1.00 0.00

East block steps


steps 1.00 150.00 1.00 1.00 150.00
Parapet seatings
Stepped Slab 1.00 482.00 1.00 29.00 13978.00
14733.60 Sqm
Total Form Work for Staircase

Grand total for Form Work 45039.57 Sq m

23
Prepared /Design By: Approved By
Checked By:
Project :- Construction of Godavari Municipality Building Bajarbarahi, Lalitpur
Quantity Estimate
Length Area (Sq
S.N Description No Breadth (m) Height (m) Quantity Remarks
(m) m)

11 BRICK WORK
11.1 Ground Floor
Wall along grid G 1.00 361.20 0.23 3.00 249.23
Wall along grid H 1.00 395.60 0.23 3.00 272.96

Wall along grid


23,24,25,27,28,30,31,32,35,36,38,39,40,41,43,4
4,47-52,55-57,59,60,70-73,76,77,79-82,84-
85,88,89,92-95,96-98 49.00 5.40 0.12 3.00 91.29
Wall along grid B 1.00 126.50 0.23 3.00 87.29
Wall along grid C 1.00 92.40 0.23 3.00 63.76
Wall along grid D 1.00 80.00 0.23 3.00 55.20
Wall along grid E 1.00 93.00 0.23 3.00 64.17
Wall along gridS 1-22 1.00 215.00 0.12 3.00 74.18
First Floor
Wall along grid H 1.00 18.70 0.23 3.00 12.90
Wall along grid C 1.00 92.40 0.23 3.00 63.76
Wall along grid D 1.00 80.00 0.23 3.00 55.20
Wall along grid E 1.00 93.00 0.23 3.00 64.17
Wall along gridS 1-22 1.00 102.00 0.12 3.00 35.19
Second Floor
Wall along grid C 1.00 92.40 0.23 3.00 63.76
Wall along grid D 1.00 80.00 0.23 3.00 55.20
Wall along grid E 1.00 93.00 0.23 1.20 25.67
Wall along gridS 1-22 1.00 95.00 0.12 3.00 32.78
Third Floor
Wall along grid C 1.00 92.40 0.12 1.20 12.75
Wall along grid D 1.00 80.00 0.12 1.20 11.04

walls between blocks 1.00 32.00 0.23 3.00 22.08

Deduction of Doors and windows


Ground floor
V1(window) -22.00 1.20 0.23 0.50 -3.04
V2(window) -47.00 3.60 0.23 0.50 -19.46
W1(window) -4.00 2.40 0.23 1.00 -2.21
Door (D2) -12.00 2.40 0.23 1.00 -6.62
Door (D3) -4.00 2.40 0.23 1.00 -2.21
First Floor
Deduction of Doors and windows
W1(window) -4.00 2.40 0.23 1.00 -2.21
W2(window) -16.00 1.80 0.23 1.00 -6.62
Door (D3) -4.00 2.40 0.23 1.00 -2.21
Second Floor
Deduction of Doors and windows
W1(window) -8.00 2.40 0.23 1.00 -4.42
W2(window) -38.00 1.80 0.23 1.00 -15.73
Door (D3) -2.00 2.40 0.23 1.00 -1.10
Total Brickwork = 1346.73 cum

12.00 PLASTERING WORKS


12.5 mm th.Plaster on 9'' wall surface with
12.2
( 1:4) cement mortar
Ground Floor
Wall along grid G 1.00 361.20 0.23 3.00 2167.20
Wall along grid H 1.00 395.60 0.23 3.00 2373.60

Wall along grid


23,24,25,27,28,30,31,32,35,36,38,39,40,41,43,4
4,47-52,55-57,59,60,70-73,76,77,79-82,84-
85,88,89,92-95,96-98 49.00 5.40 0.12 3.50 1852.20
Wall along grid B 1.00 126.50 0.23 3.00 759.00
Wall along grid C 1.00 92.40 0.23 3.00 554.40
Wall along grid D 1.00 80.00 0.23 3.00 480.00
Wall along grid E 1.00 93.00 0.23 3.00 558.00
Wall along gridS 1-22 1.00 215.00 0.12 3.50 1505.00
First Floor
24
Prepared /Design By: Approved By
Checked By:
Project :- Construction of Godavari Municipality Building Bajarbarahi, Lalitpur
Quantity Estimate
Length Area (Sq
S.N Description No Breadth (m) Height (m) Quantity Remarks
(m) m)

Wall along grid H 1.00 95.00 0.23 3.00 570.00


Wall along grid C 1.00 92.40 0.23 3.00 554.40
Wall along grid D 1.00 80.00 0.23 3.00 480.00
Wall along grid E 1.00 93.00 0.23 3.00 558.00
Wall along gridS 1-22 1.00 102.00 0.12 3.50 714.00
Second Floor
Wall along grid C 1.00 92.40 0.23 3.00 554.40
Wall along grid D 1.00 80.00 0.23 3.00 480.00
Wall along grid E 1.00 93.00 0.23 1.20 223.20
Wall along gridS 1-22 1.00 95.00 0.12 3.50 665.00
Third Floor
Wall along grid C 1.00 92.40 0.12 1.20 221.76
Wall along grid D 1.00 80.00 0.12 1.20 192.00

walls between blocks 1.00 32.00 0.23 3.00 192.00

Ground floor
Deduction of Doors and windows
V1(window) -22.00 1.20 0.23 0.50 -26.40
V2(window) -47.00 3.60 0.23 0.50 -169.20
W1(window) -4.00 2.40 0.23 1.00 -19.20
Door (D2) -12.00 2.40 0.23 1.00 -57.60
Door (D3) -4.00 2.40 0.23 1.00 -19.20
First Floor
Deduction of Doors and windows
W1(window) -4.00 2.40 0.23 1.00 -19.20
W2(window) -16.00 1.80 0.23 1.00 -57.60
Door (D3) -4.00 2.40 0.23 1.00 -19.20
Second Floor
Deduction of Doors and windows
W1(window) -8.00 2.40 0.23 1.00 -38.40
W2(window) -38.00 1.80 0.23 1.00 -136.80
Door (D3) -2.00 2.40 0.23 1.00 -9.60
15081.76 sqm
Total Wall Plaster
Column
Column
Grid A 22.00 0.60 0.60 2.00 81.84
Grid B 22.00 0.60 0.60 5.60 229.15
Grid C 22.00 0.60 0.60 9.20 376.46
Grid D 22.00 0.60 0.60 9.20 376.46
Grid E 16.00 0.60 0.60 5.60 166.66
Grid F(36-84) 39.00 0.60 0.60 3.60 261.14
Grid F(23-35,85-98) 26.00 0.60 0.60 2.00 96.72
Grid G(36-84) 39.00 0.60 0.60 7.20 522.29
Grid G(23-35,85-98) 26.00 0.60 0.60 5.6 270.82
Grid H(36-84) 39.00 0.60 0.60 10.80 783.43
Grid H(23-35,85-98) 26.00 0.60 0.60 9.20 444.91
Total plaster for Column 3609.89 sqm

Main Beam (only sides)


Ground Floor
Grid along F 1.00 330.00 0.30 0.60 313.50
Grid along G 1.00 361.20 0.30 0.60 343.14
Grid along H 1.00 395.60 0.30 0.60 375.82
Grid along Beam
Cicumferential Secondary 23-98 between grid F 65.00 15.00 0.30 0.60 926.25
&G
Cicumferential Secondary Beam between grid G 1.00 205.00 0.23 0.50 153.75
&H 1.00 214.20 0.23 0.50 160.65
Radial Secondary Beam between grid F, G &H 35.00 13.50 0.23 0.50 354.38
Grid along A 1.00 121.00 0.30 0.60 114.95
Grid along B 1.00 121.00 0.30 0.30 42.35
Grid along C 1.00 121.00 0.30 0.30 42.35
Grid along D 1.00 121.00 0.30 0.30 42.35

25
Prepared /Design By: Approved By
Checked By:
Project :- Construction of Godavari Municipality Building Bajarbarahi, Lalitpur
Quantity Estimate
Length Area (Sq
S.N Description No Breadth (m) Height (m) Quantity Remarks
(m) m)

Grid along E 1.00 93.00 0.30 0.30 32.55


Grid along 1,2,3,20,21,22 6.00 23.00 0.30 0.30 48.30
Grid along 4-19 16.00 26.60 0.30 0.30 148.96
First Floor
Grid along G 1.00 361.20 0.50 0.70 415.38
Grid along H 1.00 395.60 0.50 0.70 454.94
Grid alongBeam
Cicumferential Secondary 23-98 between grid G 65.00 6.30 0.50 0.70 470.93
&H 1.00 361.20 0.23 0.50 270.90
Radial Secondary Beam between grid G &H 60.00 6.30 0.23 0.50 283.50
Grid along B 1.00 121.00 0.30 0.60 114.95
Grid along C 1.00 121.00 0.30 0.60 114.95
Grid along D 1.00 121.00 0.30 0.60 114.95
Grid along E 1.00 93.00 0.30 0.60 88.35
Grid along 1,2,3,20,21,22 6.00 15.10 0.30 0.60 86.07
Secondary BeamGridalongalong 4-19 between grid
East-West 16.00 18.70 0.30 0.60 284.24
Secondary Beam 1,2,3,20,21,22
along East-West between grid 4.00 15.10 0.23 0.50 45.30
Secondary Beam along 4-19North south between 10.00 18.70 0.23 0.50 140.25
grid 1 -22 1.00 456.00 0.23 0.50 342.00
Second Floor
Grid along H 1.00 395.60 0.50 0.70 454.94
Grid along C 1.00 121.00 0.50 0.70 139.15
Grid along D 1.00 121.00 0.30 0.60 114.95
Grid along E 1.00 93.00 0.30 0.60 88.35
Grid along 1,2,3,20,21,22 6.00 7.10 0.30 0.60 40.47
Secondary BeamGridalongalong 4-19 between grid
East-West 16.00 10.70 0.30 0.60 162.64
Secondary Beam 1,2,3,20,21,22
along East-West between grid 4.00 7.10 0.23 0.50 21.30
Secondary Beam along 4-19North south between 10.00 10.70 0.23 0.50 80.25
grid 1 -22 1.00 335.00 0.23 0.50 251.25
Third Floor
Grid along C 1.00 121.00 0.50 0.70 139.15
Grid along D 1.00 121.00 0.30 0.60 114.95
Grid along 1,2,3,20,21,22 6.00 7.10 0.30 0.60 40.47
Secondary BeamGridalongalong 4-19 between grid
East-West 16.00 10.70 0.30 0.60 162.64
1,2,3,20,21,22
Secondary Beam along East-West between grid 4.00 6.90 0.23 0.50 20.70
Secondary Beam along 4-19North south between 10.00 6.90 0.23 0.50 51.75
grid 1 -22 1.00 121.00 0.23 0.50 90.75
Inclined beams along grids 1-98 88.00 15.80 0.30 0.60 834.24

Inclined beams along grids 1-98 in between 87.00 15.80 0.23 0.50 549.84
Total plaster in beam sides 9683.79 sqm
Slab
Ground Floor
Slab 1.00 6708.00 1.00 0.13 6708.00
First Floor
Slab 1.00 4703.00 1.00 0.13 4703.00
Deduction of void 1.00 73.00 1.00 0.13 73.00
Deduction of Staircase 1.00 32.00 1.00 0.13 32.00
Second Floor
Slab 1.00 1266.00 1.00 0.13 1266.00
Deduction of Staircase 1.00 32.00 1.00 0.13 32.00
Third Floor
Slab 1.00 1266.00 1.00 0.13 1266.00
Total Plaster Work in slab 14080.00 sqm

Staircase
Basement Floor
Dog -legged stair 2.00 23.76 1.00 0.20 95.04
Straight stair 0.00 1.00 1.00 0.20
Ground Floor
Dog -legged stair 4.00 23.76 1.00 0.20 190.08
Straight stair 23.00 16.00 1.00 0.20 736.00

26
Prepared /Design By: Approved By
Checked By:
Project :- Construction of Godavari Municipality Building Bajarbarahi, Lalitpur
Quantity Estimate
Length Area (Sq
S.N Description No Breadth (m) Height (m) Quantity Remarks
(m) m)

First Floor
Dog -legged stair 2.00 23.76 1.00 0.20 95.04
Straight stair 0.00 1.00 1.00 0.20 0.00
Second Floor
Dog -legged stair 2.00 23.76 1.00 0.20 95.04
Straight stair 0.00 1.00 1.00 0.20 0.00

East block steps


steps 1.00 150.00 1.00 0.20 300.00
Parapet seatings
Stepped Slab 1.00 482.00 1.00 46.00 22172.00
Total Plaster Work in staircase 23683.20 sqm

Slab of Ramp
Ramp slab 1.00 120.00 1.00 0.30 120.00 sqm

Lift Shear Wall


Shear Wall
Basement
basement wall 2.00 452.20 1.00 3.50 3165.40 sqm
Total Inside Beam, Column, Stair case and others
Total Plaster 69424.04 Sqm

13 STONE WORK
Rubble stone masonryworks in 1:6 c/s mortar &
including 10m trasportation
Site wall 2.00 75.00 2.00 5.00 1500.00
Compound wall 2.00 210.00 2.00 5.00 4200.00
Total 5700.00 Cuft
161.56 Cu m
14 C.G.I SHEETS WORKS
Roof Top 1.00 470.00 13.00 6110.00
Total 6110.00 Sqm

15 TRUSS WORKS
25.00 482.20 12055.00 m
ISNB 65M purlin
Medium Black pipe per m wt 6.42 kg /m 77393.10 Kg

88.00 13 1144.00 m
ISNB 80M bottom chord
Medium Black pipe per m wt 8.36 kg /m 9563.84 Kg

88.00 13 1144.00 m
ISNB 65M top chord
Medium Black pipe per m wt 6.42 kg /m 7344.48 Kg

88.00 51 4488.00 m
ISNB 65M struts
Medium Black pipe per m wt 6.42 kg /m 28812.96 Kg

88.00 6.6 580.80 m


ISNB 65M supports near coumn
Medium Black pipe per m wt 6.42 kg /m 3728.74 Kg

88.00 13 1131.68 m
ISMC 200 columns
channel per m wt 44.6 kg /m 50472.93 Kg

Connections 15% of total steel 26597.41 Kg


Total Wt 203913.45 kg
203.91 Mt
16 WOOD WORK

16.1 Making and fitting sal wood door frame having


(3"x 4") wood size with good finish from
approved wood including necessary hardware
Ground floor

27
Prepared /Design By: Approved By
Checked By:
Project :- Construction of Godavari Municipality Building Bajarbarahi, Lalitpur
Quantity Estimate
Length Area (Sq
S.N Description No Breadth (m) Height (m) Quantity Remarks
(m) m)

V1(window) 22.00 3.40 0.08 0.10 0.56


V2(window) 47.00 8.20 0.08 0.10 2.89
W1(window) 4.00 6.80 0.08 0.10 0.20
Door (D2) 12.00 5.80 0.08 0.10 0.52
Door (D3) 4.00 5.80 0.08 0.10 0.17
First Floor
W1(window) 4.00 6.80 0.08 0.10 0.20
W2(window) 16.00 9.00 0.08 0.10 1.08
Door (D3) 4.00 5.80 0.08 0.10 0.17
Second Floor
W1(window) 8.00 6.80 0.08 0.10 0.41
W2(window) 38.00 9.00 0.08 0.10 2.57
Door (D3) 2.00 5.80 0.08 0.10 0.09
Door type (D2) 16 5.80 0.08 0.10 0.70
Total Sal wood work for door frame = 9.57 cum

Making and fitting 38 mm thick sal wood


panelled door shutter including necessary brass
16.2 fittings all complete
Door (D2) 28.00 2.400 1.000 67.20
Door (D3) 10.00 2.40 1.00 24.00
Total 38mm thick pannelled door shutter = 91.20 sqm

Fixing glass of various thickness in frame using


16.3 glass thickness 4 mm.
V1(window) 22.00 1.20 0.50 13.20
V2(window) 47.00 3.60 0.50 84.60
W1(window) 16.00 2.40 1.00 38.40
W2(window) 54.00 3.50 1.00 189.00
Total fix glass = Total 325.20 sqm

17 FLOORING WORK

75mm P.C.C. (1:2:4) in floor with proper mixing


17.1 by mixer machine and compaction by vibrator
machine including proper curing all complete

Ground Floor
Ground Floor
Slab 1.00 6708.00 1.00 0.08 503.10
First Floor
Slab 1.00 4703.00 1.00 0.08 352.73
Deduction of void 1.00 73.00 1.00 0.08 5.48
Deduction of Staircase 1.00 32.00 1.00 0.08 2.40
Second Floor
Slab 1.00 1266.00 1.00 0.08 94.95
Deduction of Staircase 1.00 32.00 1.00 0.08 2.40
Third Floor
Slab 1.00 1266.00 1.00 0.08 94.95
Total Flooring Work 1056.00 cum
17.2 6'' Sand Fiiling
Ground Floor
all 1.00 6708.00 1.00 0.15 1006.20
Total Sand Filling 1006.20 Cu m

18 PAINTING WORKS
Two coat plastic emulsion paint over one coat
18.1 primer (Astar) on new surface
wall 15081.76
column 3609.89
beam 9683.79
ceiling 14080.00
staicase 23683.20

28
Prepared /Design By: Approved By
Checked By:
Project :- Construction of Godavari Municipality Building Bajarbarahi, Lalitpur
Quantity Estimate
Length Area (Sq
S.N Description No Breadth (m) Height (m) Quantity Remarks
(m) m)

shear wall 3165.40


Total painiting works 69304.04 Sqm

18.2 Supplying and applying of two coats of


Door (D2) 28.00 2.400 1.000 134.40
Door (D3) 10.00 2.40 1.00 48.00
Total enamel paints = 182.40 Sqm
Total Painting Work

19 HANDRAIL WORKS

Making and fitting 1" x 1" size square pipe


railing having height 2'-6" to 3'-0" including 3" x
4" size seasoned sissau wood handrail on top of Sq ft
railing and brass caping on bottom of each
square pipe of railing with 1 coat primer and
two coats enamel paint on railing and 3 coats
chapra polish on handrail as per instruction all
complete 5 30.000 3.000 450.00
Total handrail = 41.86 Sqm
22 TILE WORKS
22.1 8''x12'' Tile on wall surface
Ground Floor
Gents toilet-1 6 7 5.8 3.6 552.96
Ladies toilet-1 6 7 4.2 3.6 483.84
Gents toilet-1 2 5.1 7.8 3.6 185.76
Ladies toilet-1 2 5.1 3.6 3.6 125.28
Disable toilet 1 5.1 8.6 3.6 98.64
Team changing toilet 2 5 8 3.6 187.20
Refree room, Delegates, Coach room toilet 3 5 2 3.6 151.20

First Floor
Gents toilet 1.00 5.10 7.80 3.60 92.88
Total 1877.76 sqm

22.2 12"x12" Tile on floor surface


Ground Floor
Gents toilet-1 6 7 5.8 3.6 243.60
Ladies toilet-1 6 7 4.2 3.6 176.40
Gents toilet-1 2 5.1 7.8 3.6 79.56
Ladies toilet-1 2 5.1 3.6 3.6 36.72
Disable toilet 1 5.1 8.6 3.6 43.86
Team changing toilet 2 5 8 3.6 80.00
Refree room, Delegates, Coach room toilet 3 5 2 3.6 30.00
First Floor
Gents toilet 1.00 5.10 7.80 3.60 39.78
Total 729.92 Sqm

23 Marbal Laying And Placing

15 mm thick marble (450 x450 mm) over 20


mm1:2 surki with rubbing & polish to finish
also
Ground Floor
total area 2230 1 1 2230.00
deduction from toilets 690.14 -1 1 -690.14
deduction from stairs 120 -1 1 -120.00
First Floor
total area 1264 1 1 1264.00
deduction from toilets 40.00 -1 1 -40.00
deduction from stairs 50 -1 1 -50.00
deduction from voids 73 -1 1 -73.00
Second Floor
total area 1264 1 1 1264.00
deduction from toilets 40.00 -1 1 -40.00
deduction from stairs 50 -1 1 -50.00
29
Prepared /Design By: Approved By
Checked By:
Project :- Construction of Godavari Municipality Building Bajarbarahi, Lalitpur
Quantity Estimate
Length Area (Sq
S.N Description No Breadth (m) Height (m) Quantity Remarks
(m) m)

Total Marbal Laying & Placing 3694.86 sqm

26 Expansion joint 8.00 15.00 120.00


8.00 9.20 73.60
3.00 26.60 79.80
3.00 18.90 56.70
3.00 11.30 33.90
3.00 7.85 23.55
Total 387.55 Run m

27 SANITARY WORK
a
Providing and installation of gun metal gate
valve
I) NB 40mm 12.00 12.00 Sets
ii) NB 25mm 18.00 18.00 Sets
b
CPVC Pipes & Fittings for hot and cold water
distribution system CPVC means Chlorinated
Poly Vinyl Chloride as per ASTM are as per
ASTM F 442, CPVC SOLVENT are as per ASTM F-
493 2846 (Flowguard : astral, ashivad, ajay,
marvel or eqv. - 0.00 -
CPVC Pipe SDR 13.5 (22.5 Kg/cm2) - 0.00 -
1/2" dia 717.38 717.38 Rm
3/4" dia 467.99 467.99 ,,
1" dia 430.79 430.79 ,,
1-1/4" dia 375.00 375.00 ,,
1-1/2" dia 250.00 250.00 ,,
2" dia 150.00 150.00 ,,
CPVC Ball Valve (CTS Sockets) - 0.00 -
1/2" 250.00 250.00 Nos
3/4" 125.00 125.00 Nos
1" 100.00 100.00 Nos
1-1/4" 75.00 75.00 Nos
1-1/2" 50.00 50.00 Nos
2" 25.00 25.00 Nos
CPVC Reducer Brass Coupling - 0.00 -
3/4" X 1/2" 250.00 250.00 Nos
1" X 1/2" 230.00 230.00 Nos
CPVC Tee - 0.00 -
1/2" 180.00 180.00 Nos
3/4" 150.00 150.00 Nos
1" 120.00 120.00 Nos
1-1/4" 100.00 100.00 Nos
1-1/2" 75.00 75.00 Nos
2" 50.00 50.00 Nos
CPVC Reducer Tee - 0.00 -
1/2" x 1/2" x 3/4" 150.00 150.00 Nos
3/4" x 3/4" x1/2" 150.00 150.00 Nos
3/4" x 1/2" x 3/4" 150.00 150.00 Nos
3/4" x 1/2" x 1/2" 150.00 150.00 Nos
1" x 1" x 3/4" 75.00 75.00 Nos
1-1/2" x 1-1/2" x 1" 75.00 75.00 Nos
2" x 2" x 1" 75.00 75.00 Nos
1-1/4" x 1-1/4" x 1/2" 75.00 75.00 Nos

30
Prepared /Design By: Approved By
Checked By:
Project :- Construction of Godavari Municipality Building Bajarbarahi, Lalitpur
Quantity Estimate
Length Area (Sq
S.N Description No Breadth (m) Height (m) Quantity Remarks
(m) m)

1-1/4" x 1-1/4" x 1" 50.00 50.00 Nos


2" x 2" x 1/2" 50.00 50.00 Nos
1" x 1" x 1/2" 50.00 50.00 Nos
CPVC Brass FPT Tee - 0.00 -
1/2" x 1/2" x 1/2" 75.00 75.00 Nos
3/4" x 3/4" x 1/2" 70.00 70.00 Nos
1" x 1" x 1/2" 65.00 65.00 Nos
1-1/4" x 1-1/4" x 1-1/4" 50.00 50.00 Nos
1-1/4" x 1-1/4" x 1/2" 45.00 45.00 Nos
CPVC Elbow 90º - 0.00 -
1/2" 75.00 75.00 Nos
3/4" 70.00 70.00 Nos
1" 60.00 60.00 Nos
1-1/4" 55.00 55.00 Nos
1-1/2" 50.00 50.00 Nos
2" 45.00 45.00 Nos
CPVC Reducer Elbow 90º - 0.00 -
3/4" X 1/2" 150.00 150.00 Nos
CPVC Brass FPT Elbow 90º - 0.00 -
1/2" x 1/2" 250.00 250.00 Nos
3/4" x 1/2" 230.00 230.00 Nos
3/4" x 3/4" 130.00 130.00 Nos
1" X 1/2" 100.00 100.00 Nos
1" X 1" 50.00 50.00 Nos
1-1/4" x 1-1/4" 60.00 60.00 Nos
CPVC Elbow 45º - 0.00 -
1/2" 250.00 250.00 Nos
3/4" 125.00 125.00 Nos
1" 100.00 100.00 Nos
1-1/4" 75.00 75.00 Nos
1-1/2" 25.00 25.00 Nos
2" 20.00 20.00 Nos
CPVC Male Adapter (CPVC Threads) - 0.00 -
1/2" 280.00 280.00 Nos
3/4" 250.00 250.00 Nos
1" 230.00 230.00 Nos
1-1/4" 65.00 65.00 Nos
1-1/2" 75.00 75.00 Nos
2" 50.00 50.00 Nos

CPVC Reducing Male Adapter (CPVC Threads) - 0.00 -


3/4" x 1/2" 85.00 85.00 Nos
CPVC Male Adapters (Brass Threads) - 0.00 -
1/2" 130.00 130.00 Nos
3/4" 100.00 100.00 Nos
1" 75.00 75.00 Nos
1-1/4" 60.00 60.00 Nos
1-1/2" 55.00 55.00 Nos
2" 25.00 25.00 Nos

CPVC Reducing Male Adapter (Brass Threads) - 0.00 -


3/4" x 1/2" 244.00 244.00 Nos
CPVC Female Adapter (CPVC Threads) - 0.00 -
1/2" 335.00 335.00 Nos
3/4" 125.00 125.00 Nos
1" 100.00 100.00 Nos
CPVC Female Adapters Brass Threads - 0.00 -
1/2" 150.00 150.00 Nos
3/4" 120.00 120.00 Nos
1" 100.00 100.00 Nos
1-1/4" 75.00 75.00 Nos
1-1/2" 50.00 50.00 Nos
2" 25.00 25.00 Nos
CPVC Caps - 0.00 -
1/2" 250.00 250.00 Nos
3/4" 220.00 220.00 Nos
1" 150.00 150.00 Nos
31
Prepared /Design By: Approved By
Checked By:
Project :- Construction of Godavari Municipality Building Bajarbarahi, Lalitpur
Quantity Estimate
Length Area (Sq
S.N Description No Breadth (m) Height (m) Quantity Remarks
(m) m)

1-1/4" 75.00 75.00 Nos


1-1/2" 70.00 70.00 Nos
2" 65.00 65.00 Nos
CPVC Union - 0.00 -
1/2" 250.00 250.00 Nos
3/4" 105.00 105.00 Nos
1" 100.00 100.00 Nos
1-1/4" 75.00 75.00 Nos
1-1/2" 65.00 65.00 Nos
2" 55.00 55.00 Nos
CPVC Cross Tee - 0.00 -
1/2" 250.00 250.00 Nos
3/4" 300.00 300.00 Nos
CPVC Step Over Bend - 0.00 -
1/2" 250.00 250.00 Nos
3/4" 150.00 150.00 Nos
CPVC Ball Valve (CTS Sockets) - 0.00 -
1/2" 125.00 125.00 Nos
3/4" 120.00 120.00 Nos
1" 110.00 110.00 Nos
1-1/4" 50.00 50.00 Nos
1-1/2" 40.00 40.00 Nos
2" 25.00 25.00 Nos
CPVC Flow Guard Adhesive Solution - 0.00 -
946ML 50.00 50.00 Nos
Plastic Strap - 0.00 -
1/2" 61.00 61.00 Nos
3/4" 65.00 65.00 Nos
1" 55.00 55.00 Nos
1-1/4" 15.00 15.00 Nos
1-1/2" 60.00 60.00 Nos
2" 20.00 20.00 Nos
Tee Holder - 0.00 -
1/2" X 1/2" X 1/2" 180.00 180.00 Nos
3/4" X 3/4" X 1/2" 180.00 180.00 Nos
Elbow Holder - 0.00 -
1/2" X 1/2" 180.00 180.00 Nos
1/2" X 3/4" 180.00 180.00 Nos
Snap Fix Repair Coupling - 0.00 -
1/2" 10.00 10.00 Nos
3/4" 150.00 150.00 Nos
End plug threaded 1/2" 1,500.00 1500.00 Nos

Providing and installation UVC Pipe-4 Kg/sq. cm


Rain water pipes with necessary all fittings as
per detail drawings I) OD - 100 75.00 75.00 Pic
Soil and waste pipes - 0.00 -
I) OD-75 75.00 75.00 r.m
ii) 4 inch valve bend 50.00 50.00 Kg

Providing & installation of water pump (1.5 HP) 4.00 4.00 Sets
Overhead Water Tank (1000 lit ) with Valve and
necessary fitting
4 4.00 nos
29 ELECTRICAL WORKS
Wiring of light/fan & power points:
Light points 200 200.00 Points
Power Points 240 240.00 Points
Light fixture of Approved Brand of
Wipro,Havells with CFL bulb or Philips
equivalent brand
115 115.00 Points
1X11 Watt Down lights with CFL bulb 86 86.00 Points
Ex-Fan fixtures: (Crompton or equivalent)
1500 RPM Heavy duty Auto Louver type 300
mm Exhaust fan with Housing complete set.
15 15.00 Points
Switches, Light &Power and plug in sockets
(North-West or equivalent)

32
Prepared /Design By: Approved By
Checked By:
Project :- Construction of Godavari Municipality Building Bajarbarahi, Lalitpur
Quantity Estimate
Length Area (Sq
S.N Description No Breadth (m) Height (m) Quantity Remarks
(m) m)
Modular type light switches, light and power
socket
6 A 6 gang 1 way switch 35 35.00 Points
6 A 3 gang 1 way switch 25 25.00 Points
6 A 2 gang 1 way switch 20 20.00 Points
Fan 25 25.00 Points
Earthing and Lighting protection system 2 2.00 Points
Electrical Main Panel 2 2.00 Points
Distribution Boards 4 4.00 Points
Wiring of Telephone points 18 18.00 Points
15 A power socket 60 60.00 Points
30 Insurance for the damage and loss of works,
plants and vehicles; personal injury, death of Job
labour, Employee & third party insurance 1 1
31 Provide and maintain Engineer's Office and
logistic facilities(SP6) & Provision for Expert
Services for monitoring construction process and PS
providing training (SP4) As per instructed by
Project Manager or Site engineers. 1 1
32
Photography of construction activities. As per
Job
instructed by Project Manager or Site engineers.
1 1
33
Supplying and placing of Project Sign Board As
per instructed by Project Manager or Site no
engineers. 1 1
34 Rain Water Harvesting 1 1 no
35 Emergency Exit 1 1
36 Passenger Elevator

Providing and fixing lift set for 8 person capacity


with all setting,installation, joint properly 1 1 no
welded, buffed, polished and finished in perfect
line, level along with all necessary accessories
all complete as per design, drawing,
specification and instruction of engineer.
Contractor site facilities (LabourCamp and Site
37 Office) 1 1 LS

Carry out tests for material and works as


required and instructed by the Project Manager. 1 1 PS
Relocation of the utilities and services as
instructed by the Project Manager 1 1 PS

Supply Motorbikes ( Four stroke Engine & 150


CC or more ) including fuel, lubricants
,maintenance and insurance all complete, for
the site supervision team of Technical Team of
Muncipalty 2 2 Nos

Engineers Faciliies Type A: Supply of labtop and


computers with printer accessories as per
Specification 2 2 Nos
Contract information board 1 1 Nos

33
Prepared /Design By: Approved By
Checked By:
R.A. Bldg. 072/73

Summary of Rate Analysis


CIVIL WORKS :

District: Lalitpur F/Y : 2073/74

Rate(NRs) Without Rate(NRs) Without contract


Item No Description of works O/H &Vat O/H &Vat rate Remarks
1 2 3 4 5 6 7
1. Tree Lawn ,Branch seperation etc. with 15m Lead. 86.71 Per no
2. Excavation of roots of trees, with disposal within 15m Lead. 266.80 Per no
Per sqm.
A. Site 3. Surface dressing, Pit filling, mud cutting works etc,
6.67 0.62 Per sft. 7.671 Per sqm.
clearanc
e Works 4. Removal of grasses, small trees, levelling of undulated ground,
landscaping all complete work, and disposal existing earth materials Per sqm.
away from construction site (thickness 15- 20 cm.) 15.34 1.43 Per sft. 17.642 Per sqm.
5. Earth work in excavation in soft clay/silt including 10m hauling,
disposing & 1.5m lifting 480.91 Per cum. 13.63 Per cft. 553.043 Per cum.
6. Earth work in excavation in hard soil soft rocks including 10m
hauling, disposing & 1.5m lifting 549.61 Per cum. 15.58 Per cft. 632.049 Per cum.
B. Earth 7. Earth back filling with compaction in 6" layer with sprinkling water
work in , transporting from 10m distance 333.50 Per cum. 9.45 Per cft. 383.525 Per cum.
excavati
on and 8. Earth filling with compaction in 6" layer without sprinkling water,
filling transporting from 10m distance 166.75 Per cum. 4.73 Per cft. 191.763 Per cum.
9. Pumping out water from trench -Put Qty according to capacity of Per
pumpset 100.00 5000L 0.02 Per Lit. 115.000 Per 5000L
10. Sand filling with compaction in 6" layer, watering etc.
transporting from 10m distance 3532.73 Per cum. 100.13 Per cft. 4062.642 Per cum.
11. Brick work in 1:3 cement mortar in Ground Floor using machine
made brick & including 30m trasportation 13900.52 Per cum. 394.01 Per cft. 15985.603 Per cum.
12. Brick work in 1:3 c/s mortar above Ground Floor using machine
made brick & including 30m trasportation 14244.03 Per cum. 403.74 Per cft. 16380.634 Per cum.
13. Brick work in 1:4 cem mortar in Ground Floor using machine
made brick & including 30m trasportation 13422.32 Per cum. 380.45 Per cft. 15435.673 Per cum.
14. Brick work in 1:4 cem mortar above Ground Floor using machine
made brick & including 30m trasportation 13765.83 Per cum. 390.19 Per cft. 15830.704 Per cum.
15. B/W in 1:5 cement mortar on Ground Floor using machine
made brick & including 30m trasportation 13374.41 Per cum. 379.09 Per cft. 15380.571 Per cum.
16. B/W in 1:5 cement mortar above Ground Floor using machine
made brick & including 30m trasportation 13717.91 Per cum. 388.83 Per cft. 15775.601 Per cum.
17. B/W in 1:6 cement mortar in Ground Floor using machine made
brick & including 30m trasportation 13027.74 Per cum. 369.27 Per cft. 14981.899 Per cum.
18. B/W in 1:6 cement mortar above Ground Floor using machine
made brick & including 30m trasportation 13371.24 Per cum. 379.00 Per cft. 15376.929 Per cum.
19. Brick work in 1:3 cement mortar in ground floor using chimney
made brick & including 30m trasportation 13631.52 Per cum. 386.38 Per cft. 15676.253 Per cum.
20. Brick work in 1:3 cement mortar above ground floor using
chimney made brick & including 30m trasportation 13975.03 Per cum. 396.12 Per cft. 16071.284 Per cum.
C. Brick 21. Brick work in 1:4 cement mortar in ground floor using chimney
& stone made brick & including 30m trasportation 13181.20 Per cum. 373.62 Per cft. 15158.375 Per cum.
works
22. Brick work in 1:4 cement mortar above ground floor using
chimney made brick & including 30m trasportation 13524.70 Per cum. 383.35 Per cft. 15553.406 Per cum.
23 . Half brick thick brick work in 1:4 cement mortar in all height
using chimney made brick & including 30m trasportation 2061.46 Per sqm. 191.59 Per sft. 2370.683 Per sqm.
24. Brick work in 1:6 cement mortar in ground floor using chimney
made brick & including 30m trasportation 12758.74 Per cum. 361.64 Per cft. 14672.549 Per cum.
25. Brick work in 1:6 cement mortar in above ground floor using
chimney made brick & including 30m trasportation 13102.24 Per cum. 371.38 Per cft. 15067.579 Per cum.
26. Brick work in 1:1:1 Lime Sand Surki in ground floor using
chimney made brick & including 30m trasportation 13764.74 Per cum. 390.16 Per cft. 15829.454 Per cum.
27. B/W in 1:1:1 Lime Sand Surki above Gnd Floor using chimney
made brick & including 30m trasportation 14108.25 Per cum. 399.89 Per cft. 16224.485 Per cum.
28. Brick work in 1:2 Lime Surki in ground floor using chimney
made brick & including 30m trasportation 13590.29 Per cum. 385.21 Per cft. 15628.834 Per cum.
29. B/W in 1:2 Lime Surki above ground floor using chimney made
brick & including 30m trasportation 13933.80 Per cum. 394.95 Per cft. 16023.865 Per cum.
30. Brick work in mud mortar in ground floor using chimney made
brick & including 30m trasportation 10128.50 Per cum. 287.09 Per cft. 11647.777 Per cum.
31. Brick work in mud mortar above ground floor using chimney
made brick & including 30m trasportation 10472.01 Per cum. 296.83 Per cft. 12042.808 Per cum.
32. Rubble stone masonryworks in 1:3 c/s mortar & including 10m
trasportation 11288.43 Per cum. 319.97 Per cft. 12981.695 Per cum.
33. Rubble stone masonryworks in 1:4 c/s mortar & including 10m
trasportation 10786.27 Per cum. 305.73 Per cft. 12404.214 Per cum.
34. Rubble stone masonryworks in 1:6 c/s mortar & including 10m
trasportation 10025.07 Per cum. 284.16 Per cft. 11528.826 Per cum.
35. Dry stone Rubble masonryworks & including 30m trasportation
4570.48 Per cum. 129.55 Per cft. 5256.052 Per cum.
D. Stone
Works

_________ _________ __________


Prepared By Checked By Approved By
R.A. Bldg. 072/73

D. Stone 36. Rubble stone masonry works in mud mortar & including 30m
Works trasportation 4846.43 Per cum. 137.37 Per cft. 5573.395 Per cum.
37. Rubble stone masonry works in 1:3 cement mortar on arch
and lintels & including 30m trasportation 12009.23 Per cum. 340.40 Per cft. 13810.615 Per cum.
38. Rubble stone masonry works in 1:4 cement mortar on arch
and lintels & including 30m trasportation 11534.94 Per cum. 326.95 Per cft. 13265.186 Per cum.
39. Rubble stone masonry works in 1:6 cement mortar on arch
and lintels & including 30m trasportation 10745.87 Per cum. 304.59 Per cft. 12357.746 Per cum.
40. Dressed stone masonry works in 1:6 cement mortar 7887.75 Per cum. 223.58 Per cft. 9070.913 Per cum.
41. Stone filling on trench and levelling transporting upto 30m 3540.66 Per cum. 100.36 Per cft. 4071.759 Per cum.
42. 1:4:8 P.C.C. work in foundation, walls and floor,etc. including
material collection and transportation upto 30m 9967.62 Per cum. 282.53 Per cft. 11462.764 Per cum.
43. 1:3:6 P.C.C. work in foundation, and floor, including material
collection and transportation upto 30m 10764.62 Per cum. 305.12 Per cft. 12379.314 Per cum.
44. 1:2:4 P.C.C. work in foundation and floor including material
collection & transportation upto 30m 12170.05 Per cum. 344.96 Per cft. 13995.557 Per cum.
E. 45. 1:2:4 P.C.C. work in superstructure slab, beams, columns,
Cement lintels etc. with transportation up to 30m 13989.45 Per cum. 396.53 Per cft. 16087.867 Per cum.
Concret 46. 1:1.5:3 P.C.C. work in superstructure slab, beams, columns,
e Works lintels etc. with transportation up to 30m 15241.01 Per cum. 432.00 Per cft. 17527.163 Per cum.
47. 1:1:2 P.C.C. work in superstructure slab, beams, columns,
lintels etc. with transportation up to 30m 18575.36 Per cum. 526.51 Per cft. 21361.662 Per cum.
48. Curtail, bent up, binding of MS bars according to the drawing for
RCC and its transportation up to 30m 98522.20 Per mt 98.52 Per kg 113300.530 Per mt
49. 6.35cm thick Reinforced Brick work in 1:3 cement mortar in
superstructure slab, lintels etc. with transportation 1047.46 Per sqm. 97.37 Per sft 1204.582 Per sqm.
50. Form work for beams, slab in structure including, screening, Per sqm.
fitting, oiling, dismantling, removing and transportation up to 30m 666.01 61.91 Per sft. 765.917 Per sqm.
51. Column post fitting and dismantling, removing with supplying Per sqm.
wood and transporting upto 30m 1053.73 97.95 Per sft. 1211.784 Per sqm.
52. Form work for structural beams installlation and dismantling, Per sqm.
F. Form removing and transporting upto 30m & up to 0.3m Ht of beams 1101.82 102.42 Per sft. 1267.093 Per sqm.
Work 53. Form work for structural beams installlation and dismantling, Per sqm.
removing and transporting upto 30m 847.66 78.79 Per sft. 974.804 Per sqm.
54. Form work for trench shuttering upto 1.5 to 3.0m depth and Per sqm.
transporting upto 30m 148.06 13.76 Per sft. 170.274 Per sqm.
55. Form work for open trench protection depth over 3.0m and Per sqm.
transporting upto 30m 157.61 14.65 Per sft. 181.247 Per sqm.
56. CGI Sheet Roofing with supplying all materials (26 Gauge Per sqm.
medium CGI) 765.59 71.16 Per sft. 880.423 Per sqm.
57.Fixing GI plain Sheet (0.28mm) Ridge cover with supplying all Per Rm.
materials 750.06 228.68 Per rft. 862.564 Per Rm.
G. Roof 58. Coloured CGI Sheet (26 Gauge medium) Roofing with supplying
Coverin all materials Per sqm.
g 868.93 80.77 Per sft. 999.268 Per sqm.
59.Fixing Coloured GI plain Sheet (0.35mm) Ridge cover with Per Rm.
supplying all materials 911.43 277.88 Per rft. 1048.147 Per Rm.
60.1:1:3 (Lime surki brk agg)10cm thick Lime concrete terracing Per sqm.
work with supplying all materials 3662.71 340.46 Per sft. 4212.119 Per sqm.
61. 20 cm thick wood Ceiling work, plankings with 40x20mm Biding Per sqm.
Joint with supplying all materials 5336.15 496.02 Per sft. 6136.577 Per sqm.
62. Sal wood work for choukosh[0.9x2.1m size &0.1x0.075m
section] 248358.09 Per cum. 7039.63 Per cft. 285611.799 Per cum.
63. 38 mm thick Salwood solid pannel shutter (size 1.07m x 1.982m Per sqm.
= 2.114 sq.m.) 12649.18 1175.79 Per sft. 14546.553 Per sqm.
64 . Openable glazed shutter with 38 x 75mm sal wood frame & 3 Per sqm.
mm thick glass 8632.94 802.47 Per sft. 9927.877 Per sqm.
65 . Openable glazed shutter with 38 x 75mm sal wood frame & 4 Per sqm.
mm thick glass 8706.16 809.27 Per sft. 10012.086 Per sqm.
66. Openable glazed shutter with 38 x 75mm sal wood frame &5 Per sqm.
mm thick glass 8821.23 819.97 Per sft. 10144.414 Per sqm.
67 . Openable glazed shutter with 38 x 75mm sal wood frame & 6 Per sqm.
mm thick glass 8894.46 826.78 Per sft. 10228.623 Per sqm.

H. Wood
Work

_________ _________ __________


Prepared By Checked By Approved By
R.A. Bldg. 072/73

68. Flush shutter 38mm thick sal wood frame with 4mm thick Per sqm.
commercial plywood on both side of shutter 6824.68 634.38 Per sft. 7848.377 Per sqm.
69.3. Flush shutter 38mm thick sal wood frame with 3mm thick teak Per sqm.
plywood on both side of shutter 7559.46 702.68 Per sft. 8693.377 Per sqm.
70. a.38mm thick sal wood shutter with 28 Gauge GI Plain Sheet on Per sqm.
both side of shutter 6467.87 601.21 Per sft. 7438.047 Per sqm.
71. G.I. mosquito proof wire mess (24gauge) shutter works with Per sqm.
H. Wood 38mm thick sal wood frame 4746.82 441.24 Per sft. 5458.848 Per sqm.
Work
72 . Fixed glazed shutter with 3 mm thick glass 724.38 Per sqm. 67.32 Per sft. 833.039 Per sqm.
73. Fixed glazed shutter with 4 mm thick glass 874.88 Per sqm. 81.31 Per sft. 1006.114 Per sqm.
74. Fixed glazed shutter with 5 mm thick glass 1111.38 Per sqm. 103.29 Per sft. 1278.089 Per sqm.
75. Fixed glazed shutter with 6 mm thick glass 1261.88 Per sqm. 117.28 Per sft. 1451.164 Per sqm.
76 . Wooden partition with frames of 38x75 mm sections on
0.61x0.915m rooms fixed with commercial ply both side fixing with
listy 1673.37 Per sqm. 155.52 Per sft. 1924.370 Per sqm.
77 . Wooden partition with frames of 38x75 mm sections on
0.61x0.915m rooms fixed with 12mm thick hard board both side
2091.42 Per sqm. 194.37 Per sft. 2405.127 Per sqm.
fixing with listypartition with frames of 38x75 mm sections on
78. Wooden
0.61x0.915m rooms fixed with 19mm thick planks both side in lap
3114.31 Per sqm. 289.43 Per sft. 3581.455 Per sqm.
joint
79 . False ceiling with 50x75 mm sections sisau wood with
600x900mm openings fixed with 4mm thick Commercial plywood 2137.66 Per sqm. 198.67 Per sft. 2458.314 Per sqm.
80. False ceiling with 50x75 mm sections sal wood with
600x900mm openings fixed with 3mm thick Asbetos plain sheets
2224.10 Per sqm. 206.70 Per sft. 2557.714 Per sqm.
81. False ceiling with 50x75 mm sections sisau wood with
600x900mm openings fixed with 12mm thick Hard board 2352.94 Per sqm. 218.67 Per sft. 2705.876 Per sqm.
82 . Wooden rafter/purlins/beams making and fixing of saal wood
221269.12 Per cum. 6271.80 Per cft. 254459.488 Per cum.
83 . Wooden trussmaking and fixing of saal wood. 237837.20 Per cum. 6741.42 Per cft. 273512.780 Per cum.
84 . 25mm x150mm salwood eaves board making and fixing 5486.38 Per sqm. 509.89 Per sft. 6309.339 Per sqm.
85. 16-20 mm dia ms rod fixing on windows 110250.00 Per MT 110.25 Per kg. 126787.500 Per MT
86. 38mm(11/2") thick 1:2:4 Cement Concrete FLooring and Per sqm.
finishing with neat cement coat 602.08 55.97 Per sft. 692.397 Per sqm.
87. 50mm(2") thick 1:2:4 Cement Concrete FLooring and finishing Per sqm.
with neat cement coat 740.30 68.81 Per sft. 851.340 Per sqm.
88. 75mm(3") thick 1:2:4 Cement Concrete FLooring and finishing Per sqm.
with neat cement coat 1007.53 93.65 Per sft. 1158.657 Per sqm.
89. 25mm thick mosaic flooring with 20mm thick cement plaster
1:2:4 cement sand ratio & 5mm thick 1:1 white cement & marble Per sqm.
chipping surface course including by rubbing & polish to finish 1748.65 162.54 Per sft. 2010.952 Per sqm.
90. 25mm thick mosaic flooring with 6mm thick 1:1 white cement &
marble chipping over 19mm c/s plaster surface with rubbing & Per sqm.
polish to finish 3236.93 300.89 Per sft. 3722.470 Per sqm.
91. 20mm thick mosaic flooring with 6mm thick 1:1 white cement &
marble chipping over 12.5mm1:2 c/s plaster surface with rubbing Per sqm.
I. & polish to finish 3247.22 301.84 Per sft. 3734.309 Per sqm.
Flooring
Works 92. 20mm terrazo tile over 20mm1:4 c/s plaster surface with Per sqm.
rubbing & polish to finish
2714.38 252.31 Per sft. 3121.535 Per sqm.
93. 15mm thick marble (450x450mm) over 20mm1:2 surki with Per sqm.
rubbing & polish to finish also 3639.89 338.34 Per sft. 4185.875 Per sqm.
Per sqm.
94. Porcelain glazed tile over 20mm1:4 c/s mortar 2401.14 Per sqm. 223.20 Per sft. 2761.313 Per sqm.
95. 50 mm Flagstone paving on 1:4 c/s mortar 1930.58 Per sqm. 179.46 Per sft. 2220.169 Per sqm.
96. 50 mm down Flagstone paving on filled sand 1618.07 Per sqm. 150.41 Per sft. 1860.784 Per sqm.
97. 37.5 mm Flagstone paving on 1:4 cement mortar 1651.11 Per sqm. 153.48 Per sft. 1898.779 Per sqm.
98. 25 mm Flagstone paving on 1:4 cement mortar 1436.54 133.53 Per sft. 1652.020 Per sqm.
99. 25 mm Telia brick paving in 1:2 surki masala & tipkar in 1:2 Per sqm.
cement mortar 1579.47 146.82 Per sft. 1816.394 Per sqm.
100. Brick flat soling on 1:6 cement mortar and pointing in 1:2 Per sqm.
cement mortar on joints 1211.23 112.59 Per sft. 1392.917 Per sqm.
101. Brick edge soling on 1:6 cement mortar and pointing in 1:2 Per sqm.
cement mortar on joints works 1582.94 147.14 Per sft. 1820.380 Per sqm.
Per sqm.
102. Parketting with polishing after rubbing with sand paper works
2210.95 Per sqm. 205.52 Per sft. 2542.593 Per sqm.
103. Dry flat brick soling works 897.99 Per sqm. 83.47 Per sft. 1032.683 Per sqm.
104. Dry edge brick soling works 1555.46 144.59 Per sft. 1788.780 Per sqm.
105. Dry stone soling works 7549.84 Per Cum 214.00 Per cft. 8682.310 Per Cum
106. 125mm Edge Brick soling and pointing works in 1:3cement Per sqm.
mortar on joints after sand filling 1728.17 160.64 Per sft. 1987.390 Per sqm.
107. Pointing in 1:1cement mortar on joints works on paved stone Per sqm.
46cm X46cm 86.28 Per sqm. 8.02 Per sft. 99.223 Per sqm.
108. Filling with sand works 3499.38 Per cum. 325.28 Per sft. 4024.289 Per sqm.
109. 15-150 mm brick bat Filling works 1062.95 30.13 Per cft. 1222.387 Per cum.
Per sqm.
110. 3mm thick thin layer cement Punning (chipping )works 242.30 22.52 Per sft. 278.646 Per sqm.
Per sqm.
111. 12.5mm 1:3 cement sand plaster on ceiling 404.90 Per sqm. 37.64 Per sft. 465.635 Per sqm.
112. 12.5mm 1:4cement sand plaster works on ceiling 396.05 Per sqm. 36.81 Per sft. 455.457 Per sqm.
113. 12.5mm 1:4 cement sand plaster works except in ceiling 342.13 Per sqm. 31.80 Per sft. 393.449 Per sqm.
J. 114. 12.5mm 1:6 cement sand plaster works 320.33 29.78 Per sft. 368.378 Per sqm.
Per sqm.
Plasters 115. 12.5mm 1:2 Lime surki plaster works 336.96 31.32 Per sft. 387.505 Per sqm.
&
116. 20mm 1:3 cement sand plaster works 461.22 Per sqm. 42.87 Per sft. 530.406 Per sqm.
Pointing Per sqm.
Work : 117. 20mm 1:4cement sand plaster works except in ceiling 444.28 Per sqm. 41.30 Per sft. 510.923 Per sqm.
118. 20mm 1:6 cement sand plaster works except in ceiling 410.21 38.13 Per sft. 471.736 Per sqm.
_________ _________ __________
Prepared By Checked By Approved By
J.
Plasters
&
Pointing
Work :
R.A. Bldg. 072/73

119. 25mm mud plaster works with preparation of mud and surface Per sqm.
etc. 30m lead 362.41 Per sqm. 33.69 Per sft. 416.772 Per sqm.
120. 12 mm mud plaster works with preparation of mud and surface
278.88 Per sqm. 25.92 Per sft. 320.712 Per sqm.
etc. 30m lead
121. 2 coat white washing works in ceiling on new surface 32.73 Per sqm. 3.04 Per sft. 37.635 Per sqm.
122. 2 coat white washing works on other new surface 27.49 Per sqm. 2.55 Per sft. 31.610 Per sqm.
123. 3 coat white washing works in ceiling on new surface 66.06 Per sqm. 6.14 Per sft. 75.968 Per sqm.
124. 3 coat white washing works on other new surface 54.75 Per sqm. 5.09 Per sft. 62.959 Per sqm.
125. One White washing works on old surface 14.90 Per sqm. 1.39 Per sft. 17.136 Per sqm.
126. One coat distempering works over one coat astar 101.35 Per sqm. 9.42 Per sft. 116.553 Per sqm.
127. Two coat distemper works over one coat astar 141.60 13.16 Per sft. 162.840 Per sqm.

128 One coat water proof cement paint works over one coat astar Per sqm.
50.48 4.69 Per sft. 58.046 Per sqm.
Per sqm.
129. Two coat water proof cement paint works over one coat astar
117.07 10.88 Per sft. 134.625 Per sqm.
130. One coat readymade enamel paint over one coat primer Per sqm.
(Astar) on new surface 188.95 17.56 Per sft. 217.295 Per sqm.
K. 131. Two coat readymade enamel paint over one coat primer Per sqm.
Painting (Astar) on new surface 284.48 26.44 Per sft. 327.154 Per sqm.
Work 132. One coat plastic emulsion paint over one coat primer (Astar)
Per sqm.
on new surface 179.74 16.71 Per sft. 206.696 Per sqm.
133. Two coat plastic emulsion paint over one coat primer (Astar) Per sqm.
on new surface 275.41 25.60 Per sft. 316.717 Per sqm.
134. Two coat aluminium paint over one coat primer (Astar) on Per sqm.
new surface 264.85 24.62 Per sft. 304.572 Per sqm.
135. One coat double boiled linseed oiling work on new surface Per sqm.
44.10 4.10 Per sft. 50.715 Per sqm.

136. Two coat double boiled linseed oiling work on new surface Per sqm.
86.10 8.00 Per sft. 99.015 Per sqm.
Per sqm.
137. One coat varnishing work on new surface 68.78 Per sqm. 6.39 Per sft. 79.097 Per sqm.
138. Two coat varnishing work on new surface 132.86 12.35 Per sft. 152.789 Per sqm.
Per sqm.
139. One coat bitumen paint work on new surface 25.29 2.35 Per sft. 29.084 Per sqm.
Per sqm.
140. Two coat bitumen paint work on new surface 44.44 Per sqm. 4.13 Per sft. 51.106 Per sqm.
141. Three coat french(chapra) polish work on new surface 156.31 14.53 Per sft. 179.757 Per sqm.
142. One coat snowcem work after cement paint on new Per sqm.
plastered surface 78.83 7.33 Per sft. 90.649 Per sqm.
143. Two coat snowcem work after cement paint on new Per sqm.
plastered surface 141.88 13.19 Per sft. 163.156 Per sqm.
144. Flush pointing works in 1:1 cement sand mortar on brick Per sqm.
masonry work 231.88 21.55 Per sft. 266.664 Per sqm.
145. Ruled pointing works in 1:1 cement sand mortar on brick Per sqm.
masonry work 271.90 25.27 Per sft. 312.687 Per sqm.
146. Flush pointin g works in 1:2 cement sand mortar on Brick Per sqm.
masonry work 216.94 20.17 Per sft. 249.477 Per sqm.
147. Ruled pointing works in 1:2 cement sand mortar on Brick Per sqm.
masonry work 256.96 23.89 Per sft. 295.500 Per sqm.
148. Flush pointing works in 1:3 cement sand mortar on Brick Per sqm.
masonry work 209.01 19.43 Per sft. 240.357 Per sqm.
149. ruled pointing works in 1:3 cement sand mortar on Brick Per sqm.
masonry work 249.03 23.15 Per sft. 286.380 Per sqm.
150. Flush pointing works in 1:1:3 cement Lime sand mortar on Per sqm.
Brick masonry work 216.69 20.14 Per sft. 249.196 Per sqm.
151. Ruled pointing works in 1:1:3 cement Lime sand mortar on Per sqm.
Brick masonry work 239.87 22.30 Per sft. 275.855 Per sqm.
152. Flush pointing works in 1:1 Lime Surki mortar on Brick Per sqm.
L. masonry work 215.73 20.05 Per sft. 248.090 Per sqm.
Pointing 153. Ruled pointing works in 1:1 Lime Surki mortar on Brick Per sqm.
Works masonry work 255.75 23.77 Per sft. 294.113 Per sqm.
154. Flush pointing works in 1:2 Lime Surki mortar on Brick Per sqm.
masonry work 205.05 19.06 Per sft. 235.806 Per sqm.

_________ _________ __________


Prepared By Checked By Approved By
L.
Pointing
Works
R.A. Bldg. 072/73

155. Ruled pointing works in 1:2 Lime Surki mortar on Brick Per sqm.
masonry work 245.07 22.78 Per sft. 281.829 Per sqm.
156. Flush ruled pointing works in 1:1 c/s mortar on random rubble Per sqm.
masonry work 293.72 27.30 Per sft. 337.775 Per sqm.
157. Flush ruled pointing works in 1:2 c/s mortar on random rubble Per sqm.
masonry work 265.10 24.64 Per sft. 304.867 Per sqm.
157. Flush ruled pointing works in 1:3 c/s mortar on random rubble Per sqm.
masonry work 250.52 23.29 Per sft. 288.093 Per sqm.
158. Flush ruled pointing works in 1:3cement sand mortar on ashlar Per sqm.
masonry work 162.45 15.10 Per sft. 186.815 Per sqm.
164. Pointing works in 1:3cement sand mortar on 45x45cm Per sqm.
flagstone paving 86.28 Per sqm. 8.02 Per sft. 99.223 Per sqm.
165. Pointing works in 1:1cement sand mortar on telia bricks 184.20 Per sqm. 17.12 Per sft. 211.827 Per sqm.
166. 3mm Lime flushing plaster works 184.38 Per sqm. 17.14 Per sft. 212.037 Per sqm.
167. 3mm cement flushing plaster works 240.07 Per sqm. 22.32 Per sft. 276.080 Per sqm.
168. 2 cm thick DPC in 1:2 C/S with Water Proofing Compound
464.85 Per sqm. 43.21 Per sft. 534.575 Per sqm.
(WPC)
169. 2.5 cm thick DPC in 1:1.5:3 concrete with Water Proofing
517.93 Per sqm. 48.14 Per sft. 595.623 Per sqm.
Compound (WPC)
170. One coat Bitumenous paint on DPC and sand covering 173.59 Per sqm. 16.14 Per sft. 199.633 Per sqm.
171. One Layer 500 Gauge polythene sheet for DPC 127.50 Per sqm. 11.85 Per sft. 146.625 Per sqm.
0 172. One coat tar felt works with sand 773.73 Per sqm. 71.92 Per sft. 889.790 Per sqm.
173. Two coat tar felt works with sand 1196.06 Per sqm. 111.18 Per sft. 1375.470 Per sqm.
174. One coat damp Proof grade tar felt works with sand 974.20 Per sqm. 90.56 Per sft. 1120.331 Per sqm.
175. Two coat damp Proof grade tar felt works with sand 1792.19 Per sqm. 166.59 Per sft. 2061.019 Per sqm.
176. One coat rain seal or equivalent painting works 672.16 62.48 Per sft. 772.985 Per sqm.
177. Maintenance of wall in 1:6 C/S at corners with removal of old Per Cum. Per Cum.
bricks 18096.58 512.94 Per Cu ft. 20811.071
178. Maintenance of wall in 1:2 lime surki with removal of old bricks Per Cum. Per Cum.
at wall corners 18533.26 Per Sqm. 525.32 Per Cu ft. 21313.254 Per Sqm.
179. One coat Enamel paintings works after linseed oil flushing 186.42 17.33 Per Sq ft. 214.380
180. Dismantling of Cement Plaster and Disposing with Per Cum. Per Cum.
transportation of 10m. 72.04 2.04 Per Cu ft. 82.841
N. 181. Dismantling of Tile Roof and Disposing tile/Woods with Per Cum. Per Cum.
Mainten transportation of 10m. 103.06 Per Sqm. 2.92 Per Cu ft. 118.518 Per Sqm.
ance 182. Antitermite paint on wood 326.24 30.33 Per Sqft. 375.176
Work 183. Dismantling of Mud mortared wall and Disposing with
Per Cum. Per Cum.
transportation of 10m. 707.02 20.04 Per Cu ft. 813.073
184. Dismantling of Cement mortared wall and Disposing with Per Cum. Per Cum.
transportation of 10m. 1414.04 40.08 Per Cu ft. 1626.146
185. Dismantling of R.C.C./R.B.C. and Disposing with Per Cum. Per Cum.
transportation of 10m. 7337.00 207.96 Per Cu ft. 8437.550
186. Dismantling of P.C.C. and Disposing with transportation of Per Cum. Per Cum.
10m. 2668.00 75.62 Per Cu ft. 3068.200
187. 3 x 20mm Metal Grill including manufacturing, fitting, painting Per sqm.
with Aluminium paint, sand papering all complete 1790.95 166.48 Per sft. 2059.593 Per sqm.
188. 216. 4.5 x 20mm Metal Grill including manufacturing, fitting, Per sqm.
painting with Aluminium paint, sand papering all complete 3220.70 299.38 Per sft. 3703.805 Per sqm.
O. (Iron)
Steel 189. Iron tubular Truss including manufacturing, welding, supply of
Work material, painting and fixing all complete 139.44 Per
Per Rm.
kg 139.44 Per kg 160.355 Per kg
190. GI Barbed wire fencingworks 62.08 18.93 Per rft. 71.396 Per Rm.
191. Barbed wire fencing in 75x100x2100 Saal wood posts with Per Rm.
5rows & two cross bracings all complete 1374.18 418.96 Per rft. 1580.308 Per Rm.
192. M1 . Rain Water Pipe 90 mm dia. HDPE 296.49 Per Rmt. 90.39 Per Rft 340.964 Per Rmt.
P. 193. M11.Concrete Hollow Block Masonry works in 1:4 cement
2108.63 Per Sq.m. 196.15 Per Sq.ft. 2424.930 Per Sq.m.
Miscelan mortar
194. M12. 50mm thick inter locking concrete block work on 50mm
eous 195. 1420.41 Per sqm.. 132.13 Per sqft. 1633.474 Per sqm..
thick M13.
dust 60mm thick inter locking concrete block work on 50mm
1445.95 Per sqm. 134.38 Per sqft. 1662.848 Per sqm.
thick dust

_________ _________ __________


Prepared By Checked By Approved By
COST ESTIMATE:
Official Rate

District: Lalitpur
Fiscal Year: 074/075
Labour,Equipments & Material Rates for Official Use.

Rates
Total
S.N. Description of Resources Units Basic Rate(NRs) Rates(NRs) Remarks
A: Labours
1 Sk MD 908.00 908.00
2 Unsk MD 667.00 667.00
3 Coolies MD 667.00 667.00
B: Equipments 0.00
1 Water Pump Hrs 200.00 200.00
2 Truck Hrs 450.00 450.00
3 Road Roller Hrs 700.00 700.00
4 Machine to rub sandpaper hrs 150.00 150.00
C: Materials
1 Cement (Nepal made gen.) MT 15940.00 15940.00
2 Sand (Khani) cum 2787.12 2787.12
3 Aggregate 20- 40mm cum 2646.00 2646.00
10-20mm cum 2716.56 2716.56
6-10mm cum 2540.16 2540.16
4 Gravel (River/Quarry Local) cum 1587.60 1587.60

5 Screening (20-40mm river pebbles) cum 1658.16 1658.16


6 Stone dust Binding materials cum 1058.40 1058.40
7 Mix soling base course cum 0.00 0.00
8 Bricks Local(chimnee made) Nos 14.00 14.00
Machine made Nos 15.30 15.30
25mm Telia Bricks Nos 13.00 13.00
9 Block/Bund stone Cum 2116.80 2116.80
Chisel Dressed Stone cum 2469.60 2469.60
Soil from borrow pits cum 260.00 260.00
10 Paints Snowcem(cement) Kg 79.00 79.00
Primer on plaster Ltr 286.00 286.00
Red Oxide Paint Ltr 280.00 280.00
Enamel Ltr 560.00 560.00
Wood Primer Ltr 402.00 402.00
Distemper Kg 238.00 238.00
Emulsion Paint Ltr 562.00 562.00
Aluminium Paint Ltr 583.00 583.00
Linseed Oil Ltr 210.00 210.00
Cement Paint Kg 79.00 79.00

Wood Preservative paint Ltr 244.00 244.00

Rain seal paint (Equivalent to


Weather coat) Ltr 673.00 673.00
Plastic Emulsion paint Ltr 562.00 562.00
Varnish Ltr 470.00 470.00
Chapra(French Polish) Kg 978.00 978.00
Spirit Ltr 126.00 126.00
Geru(nepal Red) Kg 146.00 146.00
Bituminous paint Ltr 68.00 68.00
11 WP Compound (silica flum) kg 289.00 289.00
12 White Lime Kg 21.00 21.00 800Kg/m3
White Lime Cum 16800.00 16800.00
13 Surki Cum 1541.03 1541.03

14 Steel reinforcements TMT MT 75000.00 75000.00

Binding/Wire Kg 87.22 87.22 ToR Steel


15 Wood Saal Cum 194040.00 194040.00
Sisau Cum 92010.24 92010.24

Normal (Local for Formwork) Cum 44452.80 44452.80


Planks normal uttis Sqm 578.78 578.78
Wooden Listy 1.5" Rm 28.00 28.00
Hard Board Sqm 451.50 451.50
16 3mm Commercial Plywood Sqm 204.25 204.25
4mm Commercial Plywood Sqm 247.25 247.25
3mm Asbetos Sheet Sqm 329.26 329.26
17 3mm Teak Ply Sqm 602.00 602.00
18 24gauge GI Wire Mesh for Mosquito proofing Sqm 116.00 116.00
19 Nails(steel) Ordinary Kg 109.00 109.00
20mm Screws Nos 1.00 1.00
35mm Screws Nos 2.00 2.00
50mm Screws Nos 7.00 7.00
50mm Nails Nos 7.00 7.00
20 Mud Cum 260.00 260.00
21 J-Hook 8 mm(1kg=7nos) Nos 19.00 19.00
Bitumen washer Nos 3.00 3.00
8mm Nut-Bolt Nos 28.00 28.00
22 CGI Sheet 26 Gauge 0.38mm Sqm 369.44 369.44
GI Plain sheet 26G (0.38 mm thick) Meter 94.76 94.76
GI Plain sheet 28G (0.28 mm thick) Meter 74.98 74.98
GI Plain sheet 28G 4 feet wide Meter 304.63 304.63

23 Coloured CGI(0.38mm) medium Sq M 455.56 455.56


Coloured GI plain sheet -.35mm Meter 439.11 439.11
24 Slates Sqm 301.86 301.86
25 Clay Tiles (machine made) Nos 18.00 18.00
Clay Ridge Tiles ( " " ) Nos 31.00 31.00
200mm terrazo Tiles Sq M 516.00 516.00
Glazed Ceramic Tiles Sq M 516.00 516.00
26 Brick Agg cum 1155.77 1155.77
27 Colouring pigments kg 39.00 39.00
28 Khar Bdle 10.00 10.00
Bamboo Nos 198.00 198.00
Rope (nariyal) Kg 120.00 120.00
Chatai Sq M 20.00 20.00
29 Hold fast Nos 17.29 17.29
30 Hinges100mm Nos 27.00 27.00
Hinges 75 mm Nos 15.00 15.00
Tower Bolts 300mm Nos 103.00 103.00
Tower Bolts150mm Nos 65.00 65.00
Tower Bolts100mm Nos 39.00 39.00
Locking sets300mm Nos 252.00 252.00
Locking sets225mm Nos 221.00 221.00
Mortish lock Nos 404.00 404.00
Handles(Good Quality) Nos 46.00 46.00
Spring (Normal) Nos 173.00 173.00
32 Iron Strips/Angles kg 85.00 85.00
33 Glass (3 - 6 mm thick)3mm sqm 537.50 537.50
4mm sqm 688.00 688.00
5mm sqm 924.50 924.50
6mm sqm 1075.00 1075.00
34 Barbed wire Rm 13.57 13.57
U-Hook nos 0.74 0.74
35 GIWire 12 SWG Commercial kg 83.00 83.00
10SWG Commercial kg 83.00 83.00
8SWG Commercial kg 83.00 83.00
36 Collapsible gate sqm 5375.00 5375.00
37 Rolling shutter sqm 3762.50 3762.50
38 Iron Tubular Truss sqm 2150.00 2150.00
39 Iron Gate sqm 6987.50 6987.50
40 Metal gril 3x20mm sqm 1790.95 1790.95
4.5x20mm sqm 3220.70 3220.70
41 Bitumen kg 68.00 68.00
42 Tar felt sqm 120.00 120.00
43 Miscellaneous
sand Paper Nos 6.00 6.00
Gum(white washing) kg 217.00 217.00
Fire Wood kg 20.00 20.00
White Cement Mt 26375.00 26375.00
Marble chips Cum 13728.00 13728.00
Axalic acid kg 115.00 115.00
Wax Polish kg 200.00 200.00
Turpentine Oil lit. 229.00 229.00
13mm thick marbles sqm 1644.75 1644.75
Porcelain glaged tile(12"*12" and above) Sq M 709.50 709.50
50 mm thick flagstone Sq M 1182.50 1182.50
50 mm down thick flagstone Sq M 1026.63 1026.63
37.5 mm thick flagstone Sq M 1021.25 1021.25
25 mm thick flagstone Sq M 870.75 870.75
Parkette wooden Sq M 1870.50 1870.50
Batten Bricks cum 359.95 359.95
HDPE 2.5Kgf 90mm Dia rain waterpipe Rm 200.00 200.00
PVC 90mm 2.5 kgf Rm 141.00 141.00
Rice Straw Kg 5.00 5.00
Cow Dung Kg 4.80 4.80
500 gauge polythene sheet sq m 30.00 30.00
Interlocking cc block 50mm sq m 534.06 534.06
Interlocking cc block 60mm sq m 557.28 557.28
Concrete Hollow Block 16"*8"*6" nos 76 76
Black Iron Pipe Kg 79 79

Note: The above rates are excluding VAT


Rate Analysis

RATE ANALYSIS

District : Lalitpur
F/Y : 2073/2074

CIVIL WORKS :

Contents
CATEGO
RIES WORKS
A: Site clearance Works
B: Earth cutting and Filling Works
C: Brick Works
D: Stone Works
E: Cement Concrete Works
F: Form Works
G: Roofing Works
H: Wood Works
I: Flooring Works
J: Plastering Works
K: Painting Works
L: Pointing Works
M: Water Proofing Works
N: Maintenance works
O: Iron (Steel) Works
P: Miscellaneous Works

2073 Bhadra

_______________
____________ _______________
Approved By
Prepared By Checked By
Rate Analysis

A. Site clearance Works


1. Tree Lawn ,Branch seperation etc. with 15m Lead. (1nos)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: Unskilled 0.130 Nos. 667.00 86.71 86.71
Actual rate 86.71
Rate 15% contractor's overhead 13.01
Per no Total 99.72
86.71

2. Excavation of roots of trees, with disposal within 15m Lead. (1nos)


Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: Unskilled 0.400 Nos. 667.00 266.80 266.80
Actual rate 266.80
Rate 15% contractor's overhead 40.02
Per no Total 306.82
266.80

3. Surface dressing, Pit filling, mud cutting works etc, (1sqm/10.76 sft)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: Unskilled 0.010 Nos. 667.00 6.67 6.67
Actual rate 6.67
Rate 15% contractor's overhead 1.00
Per sqm. Per sft. Total 7.67
6.67 0.62

4. Removal of grasses, small trees, levelling of undulated ground, landscaping all complete work, and disposal existing earth materials
away from construction site (thickness 15- 20 cm.)
(10sqm)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: Unskilled 0.230 Nos. 667.00 153.41 153.41
Actual rate 153.41
Rate 15% contractor's overhead 23.01
Per sqm. Per sft. Total 176.42
15.34 1.43

B. Earth work in excavation and filling


5. Earth work in excavation in soft clay/silt including 10m hauling, disposing & 1.5m lifting (1cu.m./35.28 cft)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: Coolies 0.700 Nos. 667.00 466.90 466.90
Tools & Equipments 3% of total labour cost 14.01 14.01
Actual rate 480.91
Rate 15% contractor's overhead 72.14
Per cum. Per cft. Total 553.04
480.91 13.63

6. Earth work in excavation in hard soil soft rocks including 10m hauling, disposing & 1.5m lifting (1cu.m./35.28 cft)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: Coolies 0.800 Nos. 667.00 533.60 533.60
Tools & Equipments 3% of total labour cost 16.01 16.01
Actual rate 549.61
Rate 15% contractor's overhead 82.44
Per cum. Per cft. Total 632.05
549.61 15.58

_______________
____________ _______________
Approved By
Prepared By Checked By
Rate Analysis

7. Earth back filling with compaction in 6" layer with sprinkling water , transporting from 10m distance ( 1cu.m/35.28 cft )
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
a) Coolies 0.500 Nos. 667.00 333.50 333.50
Actual rate 333.50
Rate 15% contractor's overhead 50.03
Per cum. Per cft. Total 383.53
333.50 9.45

8. Earth filling with compaction in 6" layer without sprinkling water, transporting from 10m distance ( 1cu.m/35.28 cft )
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
a) Coolies 0.250 Nos. 667.00 166.75 166.75
Actual rate 166.75
Rate 15% contractor's overhead 25.01
Per cum. Per cft. Total 191.76
166.75 4.73

9. Pumping out water from trench -Put Qty according to capacity of pumpset ( 5000L/0.5 cum)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
a) pump Hours 0.500 Hours 200.00 100.000 100.000
Actual rate 100.000
Rate 15% contractor's overhead 15.000
Per 5000L Per Lit. Total 115.000
100.00 0.02

10. Sand filling with compaction in 6" layer, watering etc. transporting from 10m distance ( 1cu.m/35.28 cft )
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Coolies 0.700 Nos. 667.00 466.90 466.90
Materials Sand 1.100 cu.m. 2787.12 3065.83 3065.83
Actual rate 3532.73
Rate 15% contractor's overhead 529.91
Per cum. Per cft. Total 4062.64
3532.73 100.13

C. Brick & stone works


11. Brick work in 1:3 cement mortar in Ground Floor using machine made brick & including 30m trasportation
( 1 cu.m./35.28 cft)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.50 Nos. 908.00 1362.00
b) Unskilled 2.20 Nos. 667.00 1467.40
c) Unskilled(for scafolding) 0.20 Nos. 667.00 133.40 2962.80
Bricks 530.000 Nos. 15.30 8109.00
Materials Cement 0.130 MT 15940.00 2072.20
Sand 0.270 Cub.M. 2787.12 752.52 10933.72
Sundries 3% of (c) 4.00 4.00
Actual rate 13900.52
Rate 15% contractor's overhead 2085.08
Per cum. Per cft. Total 15985.60
13900.52 394.01

12. Brick work in 1:3 c/s mortar above Ground Floor using machine made brick & including 30m trasportation
( 1 cu.m./35.28 cft)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.50 Nos. 908.00 1362.00
b) Unskilled 2.20 Nos. 667.00 1467.40
c) Unskilled(for scafolding) 0.70 Nos. 667.00 466.90 3296.30
Bricks 530.000 Nos. 15.30 8109.00
Materials Cement 0.130 MT 15940.00 2072.20
Sand 0.270 Cub.M. 2787.12 752.52 10933.72
Sundries 3% of (c) 14.01 14.01
Actual rate 14244.03
Rate 15% contractor's overhead 2136.60
Per cum. Per cft. Total 16380.63
14244.03 403.74

_______________
____________ _______________
Approved By
Prepared By Checked By
Rate Analysis

13. Brick work in 1:4 cem mortar in Ground Floor using machine made brick & including 30m trasportation
( 1 cu.m./35.28 cft)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.50 Nos. 908.00 1362.00
b) Unskilled 2.20 Nos. 667.00 1467.40
c) Unskilled(for scafolding) 0.20 Nos. 667.00 133.40 2962.80
Bricks 530.000 Nos. 15.30 8109.00
Materials Cement 0.100 MT 15940.00 1594.00
Sand 0.270 Cub.M. 2787.12 752.52 10455.52
Sundries 3% of (c) 4.00 4.00
Actual rate 13422.32
Rate 15% contractor's overhead 2013.35
Per cum. Per cft. Total 15435.67
13422.32 380.45

14. Brick work in 1:4 cem mortar above Ground Floor using machine made brick & including 30m trasportation
( 1 cu.m./35.28 cft)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.50 Nos. 908.00 1362.00
b) Unskilled 2.20 Nos. 667.00 1467.40
c) Unskilled(for scafolding) 0.70 Nos. 667.00 466.90 3296.30
Bricks 530.000 Nos. 15.30 8109.00
Materials Cement 0.100 MT 15940.00 1594.00
Sand 0.270 Cub.M. 2787.12 752.52 10455.52
Sundries 3% of (c) 14.01 14.01
Actual rate 13765.83
Rate 15% contractor's overhead 2064.87
Per cum. Per cft. Total 15830.70
13765.83 390.19

15. B/W in 1:5 cement mortar on Ground Floor using machine made brick & including 30m trasportation
( 1 cu.m./35.28 cft)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.50 Nos. 908.00 1362.00
b) Unskilled 2.20 Nos. 667.00 1467.40
c) Unskilled(for scafolding) 0.20 Nos. 667.00 133.40 2962.80
Bricks 530.000 Nos. 15.30 8109.00
Materials Cement 0.090 MT 15940.00 1434.60
Sand 0.310 Cub.M. 2787.12 864.01 10407.61
Sundries 3% of (c) 4.00 4.00
Actual rate 13374.41
Rate 15% contractor's overhead 2006.16
Per cum. Per cft. Total 15380.57
13374.41 379.09

16. B/W in 1:5 cement mortar above Ground Floor using machine made brick & including 30m trasportation
( 1 cu.m./35.28 cft)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.50 Nos. 908.00 1362.00
b) Unskilled 2.20 Nos. 667.00 1467.40
c) Unskilled(for scafolding) 0.70 Nos. 667.00 466.90 3296.30
Bricks 530.000 Nos. 15.30 8109.00
Materials Cement 0.090 MT 15940.00 1434.60
Sand 0.310 Cub.M. 2787.12 864.01 10407.61
Sundries 3% of (c) 14.01 14.01
Actual rate 13717.91
Rate 15% contractor's overhead 2057.69
Per cum. Per cft. Total 15775.60
13717.91 388.83

17. B/W in 1:6 cement mortar in Ground Floor using machine made brick & including 30m trasportation
( 1 cu.m./35.28 cft)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.50 Nos. 908.00 1362.00
b) Unskilled 2.20 Nos. 667.00 1467.40
c) Unskilled(for scafolding) 0.20 Nos. 667.00 133.40 2962.80
Bricks 530.000 Nos. 15.30 8109.00
Materials Cement 0.070 MT 15940.00 1115.80
Sand 0.300 Cub.M. 2787.12 836.14 10060.94
Sundries 3% of (c) 4.00 4.00
Actual rate 13027.74
Rate 15% contractor's overhead 1954.16
Per cum. Per cft. Total 14981.90
13027.74 369.27

_______________
____________ _______________
Approved By
Prepared By Checked By
Rate Analysis

18. B/W in 1:6 cement mortar above Ground Floor using machine made brick & including 30m trasportation
( 1 cu.m./35.28 cft)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.500 Nos. 908.00 1362.00
b) Unskilled 2.200 Nos. 667.00 1467.40
c) Unskilled(for scafolding) 0.700 Nos. 667.00 466.90 3296.30
Bricks 530.000 Nos. 15.30 8109.00
Materials Cement 0.070 MT 15940.00 1115.80
Sand 0.300 Cub.M. 2787.12 836.14 10060.94
Sundries 3% of (c) 14.01 14.01
Actual rate 13371.24
Rate 15% contractor's overhead 2005.69
Per cum. Per cft. Total 15376.93
13371.24 379.00

19. Brick work in 1:3 cement mortar in ground floor using chimney made brick & including 30m trasportation
( 1 cu.m./35.28 cft)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.500 Nos. 908.00 1362.00
b) Unskilled 2.200 Nos. 667.00 1467.40
c) Unskilled(for scafolding) 0.200 Nos. 667.00 133.40 2962.80
Bricks 560.000 Nos. 14.00 7840.00
Materials Cement 0.130 MT 15940.00 2072.20
Sand 0.270 Cub.M. 2787.12 752.52 10664.72
Sundries 3% of (c) 4.00 4.00
Actual rate 13631.52
Rate 15% contractor's overhead 2044.73
Per cum. Per cft. Total 15676.25
13631.52 386.38

20. Brick work in 1:3 cement mortar above ground floor using chimney made brick & including 30m trasportation
( 1 cu.m./35.28 cft)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.500 Nos. 908.00 1362.00
b) Unskilled 2.200 Nos. 667.00 1467.40
c) Unskilled(for scafolding) 0.700 Nos. 667.00 466.90 3296.30
Bricks 560.000 Nos. 14.00 7840.00
Materials Cement 0.130 MT 15940.00 2072.20
Sand 0.270 Cub.M. 2787.12 752.52 10664.72
Sundries 3% of (c) 14.01 14.01
Actual rate 13975.03
Rate 15% contractor's overhead 2096.25
Per cum. Per cft. Total 16071.28
13975.03 396.12

21. Brick work in 1:4 cement mortar in ground floor using chimney made brick & including 30m trasportation
( 1 cu.m./35.28 cft)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.500 Nos. 908.00 1362.00
b) Unskilled 2.200 Nos. 667.00 1467.40
c) Unskilled(for scafolding) 0.200 Nos. 667.00 133.40 2962.80
Bricks 560.000 Nos. 14.00 7840.00
Materials Cement 0.100 MT 15940.00 1594.00
Sand 0.280 Cub.M. 2787.12 780.39 10214.39
Sundries 3% of (c) 4.00 4.00
Actual rate 13181.20
Rate 15% contractor's overhead 1977.18
Per cum. Per cft. Total 15158.37
13181.20 373.62

22. Brick work in 1:4 cement mortar above ground floor using chimney made brick & including 30m trasportation
( 1 cu.m./35.28 cft)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.500 Nos. 908.00 1362.00
b) Unskilled 2.200 Nos. 667.00 1467.40
c) Unskilled(for scafolding) 0.700 Nos. 667.00 466.90 3296.30
Bricks 560.000 Nos. 14.00 7840.00
Materials Cement 0.100 MT 15940.00 1594.00
Sand 0.280 Cub.M. 2787.12 780.39 10214.39
Sundries 3% of (c) 14.01 14.01
Actual rate 13524.70
Rate 15% contractor's overhead 2028.71
Per cum. Per cft. Total 15553.41
13524.70 383.35

_______________
____________ _______________
Approved By
Prepared By Checked By
Rate Analysis

23 . Half brick thick brick work in 1:4 cement mortar in all height using chimney made brick & including 30m trasportation
( 1 sqm/10.76 sft)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 0.350 Nos. 908.00 317.80
b) Unskilled 0.510 Nos. 667.00 340.17
c) Unskilled(for scafolding) 0.161 Nos. 667.00 107.39 765.36
Bricks 73.000 Nos. 14.00 1022.00
Materials Cement 0.010 MT 15940.00 159.40
Sand 0.040 Cub.M. 2787.12 111.48 1292.88
Sundries 3% of (c) 3.22 3.22
Actual rate 2061.46
Rate 15% contractor's overhead 309.22
Per sqm. Per sft. Total 2370.68
2061.46 191.59

24. Brick work in 1:6 cement mortar in ground floor using chimney made brick & including 30m trasportation
( 1 cu.m./35.28 cft)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.500 Nos. 908.00 1362.00
b) Unskilled 2.200 Nos. 667.00 1467.40
c) Unskilled(for scafolding) 0.200 Nos. 667.00 133.40 2962.80
Bricks 560.000 Nos. 14.00 7840.00
Materials Cement 0.070 MT 15940.00 1115.80
Sand 0.300 Cub.M. 2787.12 836.14 9791.94
Sundries 3% of (c) 4.00 4.00
Actual rate 12758.74
Rate 15% contractor's overhead 1913.81
Per cum. Per cft. Total 14672.55
12758.74 361.64

25. Brick work in 1:6 cement mortar in above ground floor using chimney made brick & including 30m trasportation
( 1 cu.m./35.28 cft)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.500 Nos. 908.00 1362.00
b) Unskilled 2.200 Nos. 667.00 1467.40
c) Unskilled(for scafolding) 0.700 Nos. 667.00 466.90 3296.30
Bricks 560.000 Nos. 14.00 7840.00
Materials Cement 0.070 MT 15940.00 1115.80
Sand 0.300 Cub.M. 2787.12 836.14 9791.94
Sundries 3% of (c) 14.01 14.01
Actual rate 13102.24
Rate 15% contractor's overhead 1965.34
Per cum. Per cft. Total 15067.58
13102.24 371.38

26. Brick work in 1:1:1 Lime Sand Surki in ground floor using chimney made brick & including 30m trasportation
( 1 cu.m./35.28 cft)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.500 Nos. 908.00 1362.00
b) Unskilled 2.200 Nos. 667.00 1467.40
c) Unskilled(for scafolding) 0.200 Nos. 667.00 133.40 2962.80
Bricks 560.000 Nos. 14.00 7840.00
Materials Lime 0.140 Cub.M. 16800.00 2352.00
Sand 0.140 Cub.M. 2787.12 390.20
Surki 0.140 Cub.M. 1541.03 215.74 10797.94
Sundries 3% of (c) 4.00 4.00
Actual rate 13764.74
Rate 15% contractor's overhead 2064.71
Per cum. Per cft. Total 15829.45
13764.74 390.16

_______________
____________ _______________
Approved By
Prepared By Checked By
Rate Analysis

27. B/W in 1:1:1 Lime Sand Surki above Gnd Floor using chimney made brick & including 30m trasportation
( 1 cu.m./35.28 cft)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.500 Nos. 908.00 1362.00
b) Unskilled 2.200 Nos. 667.00 1467.40
c) Unskilled(for scafolding) 0.700 Nos. 667.00 466.90 3296.30
Bricks 560.000 Nos. 14.00 7840.00
Materials Lime 0.140 Cub.M. 16800.00 2352.00
Sand 0.140 Cub.M. 2787.12 390.20
Surki 0.140 Cub.M. 1541.03 215.74 10797.94
Sundries 3% of (c) 14.01 14.01
Actual rate 14108.25
Rate 15% contractor's overhead 2116.24
Per cum. Per cft. Total 16224.49
14108.25 399.89

28. Brick work in 1:2 Lime Surki in ground floor using chimney made brick & including 30m trasportation
( 1 cu.m./35.28 cft)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.500 Nos. 908.00 1362.00
b) Unskilled 2.200 Nos. 667.00 1467.40
c) Unskilled(for scafolding) 0.200 Nos. 667.00 133.40 2962.80
Bricks 560.000 Nos. 14.00 7840.00
Materials Lime 0.140 Cub.M. 16800.00 2352.00
Surki 0.280 Cub.M. 1541.03 431.49 10623.49
Sundries 3% of (c) 4.00 4.00
Actual rate 13590.29
Rate 15% contractor's overhead 2038.54
Per cum. Per cft. Total 15628.83
13590.29 385.21

29. B/W in 1:2 Lime Surki above ground floor using chimney made brick & including 30m trasportation
( 1 cu.m./35.28 cft)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.500 Nos. 908.00 1362.00
b) Unskilled 2.200 Nos. 667.00 1467.40
c) Unskilled(for scafolding) 0.700 Nos. 667.00 466.90 3296.30
Bricks 560.000 Nos. 14.00 7840.00
Materials Lime 0.140 MT 16800.00 2352.00
Surki 0.280 Cub.M. 1541.03 431.49 10623.49
Sundries 3% of (c) 14.01 14.01
Actual rate 13933.80
Rate 15% contractor's overhead 2090.07
Per cum. Per cft. Total 16023.86
13933.80 394.95

30. Brick work in mud mortar in ground floor using chimney made brick & including 30m trasportation
( 1 cu.m./35.28 cft)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.000 Nos. 908.00 908.00
b) Unskilled 1.700 Nos. 667.00 1133.90
c)Unskilled(for scafolding) 0.200 Nos. 667.00 133.40 2175.30
Bricks 560.000 Nos. 14.00 7840.00
Materials Mud 0.420 Cub.M. 260.00 109.20 7949.20
Sundries 3% of (c) 4.00 4.00
Actual rate 10128.50
Rate 15% contractor's overhead 1519.28
Per cum. Per cft. Total 11647.78
10128.50 287.09

31. Brick work in mud mortar above ground floor using chimney made brick & including 30m trasportation
( 1 cu.m./35.28 cft)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.000 Nos. 908.00 908.00
b) Unskilled 1.700 Nos. 667.00 1133.90
c)Unskilled(for scafolding) 0.700 Nos. 667.00 466.90 2508.80
Bricks 560.000 Nos. 14.00 7840.00
Materials Mud 0.420 Cub.M. 260.00 109.20 7949.20
Sundries 3% of (c) 14.01 14.01
Actual rate 10472.01
Rate 15% contractor's overhead 1570.80
Per cum. Per cft. Total 12042.81
10472.01 296.83

_______________
____________ _______________
Approved By
Prepared By Checked By
Rate Analysis

D. Stone Works
32. Rubble stone masonryworks in 1:3 c/s mortar & including 10m trasportation ( 1 cu.m./35.28 cft)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.500 Nos. 908.00 1362.00
b) Unskilled 5.000 Nos. 667.00 3335.00 4697.00
Cement 0.194 MT 15940.00 3092.36
Materials Sand 0.420 Cub.M. 2787.12 1170.59
Blockstone 1.000 Cub.M. 2116.80 2116.80
Bundstone 0.100 Cub.M. 2116.80 211.68 6591.43
Actual rate 11288.43
Rate 15% contractor's overhead 1693.26
Per cum. Per cft. Total 12981.69
11288.43 319.97

33. Rubble stone masonryworks in 1:4 c/s mortar & including 10m trasportation ( 1 cu.m./35.28 cft)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.500 Nos. 908.00 1362.00
b) Unskilled 5.000 Nos. 667.00 3335.00 4697.00
Cement 0.159 MT 15940.00 2534.46
Materials Sand 0.440 Cub.M. 2787.12 1226.33
Blockstone 1.000 Cub.M. 2116.80 2116.80
Bundstone 0.100 Cub.M. 2116.80 211.68 6089.27
Actual rate 10786.27
Rate 15% contractor's overhead 1617.94
Per cum. Per cft. Total 12404.21
10786.27 305.73

34. Rubble stone masonryworks in 1:6 c/s mortar & including 10m trasportation ( 1 cu.m./35.28 cft)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.500 Nos. 908.00 1362.00
b) Unskilled 5.000 Nos. 667.00 3335.00 4697.00
Cement 0.106 MT 15940.00 1689.64
Materials Sand 0.470 Cub.M. 2787.12 1309.95
Blockstone 1.000 Cub.M. 2116.80 2116.80
Bundstone 0.100 Cub.M. 2116.80 211.68 5328.07
Actual rate 10025.07
Rate 15% contractor's overhead 1503.76
Per cum. Per cft. Total 11528.83
10025.07 284.16

35. Dry stone Rubble masonryworks & including 30m trasportation ( 1 cu.m./35.28 cft)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.000 Nos. 908.00 908.00
b) Unskilled 2.000 Nos. 667.00 1334.00 2242.00
Materials Blockstone 1.000 Cub.M. 2116.80 2116.80
Bundstone 0.100 Cub.M. 2116.80 211.68 2328.48
Actual rate 4570.48
Rate 15% contractor's overhead 685.57
Per cum. Per cft. Total 5256.05
4570.48 129.55

36. Rubble stone masonry works in mud mortar & including 30m trasportation ( 1 cu.m./35.28 cft)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.000 Nos. 908.00 908.00
b) Unskilled 2.250 Nos. 667.00 1500.75 2408.75
Materials Blockstone 1 Cub.M. 2116.80 2116.8
Bundstone 0.1 Cub.M. 2116.80 211.68
Mud 0.42 Cub.M. 260.00 109.2 2437.68
Actual rate 4846.43
Rate 15% contractor's overhead 726.96
Per cum. Per cft. Total 5573.39
4846.43 137.37

_______________
____________ _______________
Approved By
Prepared By Checked By
Rate Analysis

37. Rubble stone masonry works in 1:3 cement mortar on arch and lintels & including 30m trasportation ( 1 cu.m./35.28 cft)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 2.000 Nos. 908.00 1816.00
b) Unskilled 5.400 Nos. 667.00 3601.80 5417.80
Cement 0.194 MT 15940.00 3092.36
Materials Sand 0.420 Cub.M. 2787.12 1170.59
Blockstone 1.000 Cub.M. 2116.80 2116.80
Bundstone 0.100 Cub.M. 2116.80 211.68 6591.43
Actual rate 12009.23
Rate 15% contractor's overhead 1801.38
Per cum. Per cft. Total 13810.61
12009.23 340.40

38. Rubble stone masonry works in 1:4 cement mortar on arch and lintels & including 30m trasportation
( 1 cu.m./35.28 cft)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 2.000 Nos. 908.00 1816.00
b) Unskilled 5.400 Nos. 667.00 3601.80 5417.80
Cement 0.159 MT 15940.00 2534.46
Materials Sand 0.450 Cub.M. 2787.12 1254.20
Blockstone 1.000 Cub.M. 2116.80 2116.80
Bundstone 0.100 Cub.M. 2116.80 211.68 6117.14
Actual rate 11534.94
Rate 15% contractor's overhead 1730.24
Per cum. Per cft. Total 13265.19
11534.94 326.95

39. Rubble stone masonry works in 1:6 cement mortar on arch and lintels & including 30m trasportation
( 1 cu.m./35.28 cft)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 2.000 Nos. 908.00 1816.00
b) Unskilled 5.400 Nos. 667.00 3601.80 5417.80
Cement 0.106 MT 15940.00 1689.64
Materials Sand 0.470 Cub.M. 2787.12 1309.95
Blockstone 1.000 Cub.M. 2116.80 2116.80
Bundstone 0.100 Cub.M. 2116.80 211.68 5328.07
Actual rate 10745.87
Rate 15% contractor's overhead 1611.88
Per cum. Per cft. Total 12357.75
10745.87 304.59

40. Dressed stone masonry works in 1:6 cement mortar ( 10 cu.m./352.8 cft)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 15.000 Nos. 908.00 13620.00
b) Unskilled 30.000 Nos. 667.00 20010.00 33630.00
Cement 0.400 MT 15940.00 6376.00
Materials Sand 4.200 Cub.M. 2787.12 11705.90
Dressed stone 11.000 Cub.M. 2469.60 27165.60 45247.50
Actual rate 78877.50
Rate 15% contractor's overhead 11831.63
Per cum. Per cft. Total 90709.13
7887.75 223.58

41. Stone filling on trench and levelling transporting upto 30m ( 1 cu.m./35.28 cft)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 0.000 Nos. 908.00 0.00
b) Unskilled 1.500 Nos. 667.00 1000.50 1000.50
Materials Blockstone 1.000 Cub.M. 2116.80 2116.80
Bundstone 0.200 Cub.M. 2116.80 423.36 2540.16
Actual rate 3540.66
Rate 15% contractor's overhead 531.10
Per cum. Per cft. Total 4071.76
3540.66 100.36

_______________
____________ _______________
Approved By
Prepared By Checked By
Rate Analysis

E. Cement Concrete Work

42. 1:4:8 P.C.C. work in foundation, walls and floor,etc. including material collection and transportation upto 30m
( 1 cu.m./ 35.28 cft )
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.000 Nos. 908.00 908.00
b) Coolies 4.000 Nos. 667.00 2668.00 3576.00
Materials Cement 0.170 MT 15940.00 2709.80
Sand 0.470 Cub M 2787.12 1309.95
40 mm aggregate 0.650 Cub M 2646.00 1719.90
20 mm aggregate 0.240 Cub M 2716.56 651.97 6391.62
Actual rate 9967.62
Rate 15% contractor's overhead 1495.14
Per cum. Per cft. Total 11462.76
9967.62 282.53

43. 1:3:6 P.C.C. work in foundation, and floor, including material collection and transportation upto 30m
( 1 cu.m./ 35.28 cft )
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.000 Nos. 908.00 908.00
b) Coolies 4.000 Nos. 667.00 2668.00 3576.00
Materials Cement 0.220 MT 15940.00 3506.80
Sand 0.470 Cub M 2787.12 1309.95
40 mm aggregate 0.650 Cub M 2646.00 1719.90
20 mm aggregate 0.240 Cub M 2716.56 651.97 7188.62
Actual rate 10764.62
Rate 15% contractor's overhead 1614.69
Per cum. Per cft. Total 12379.31
10764.62 305.12

44. 1:2:4 P.C.C. work in foundation and floor including material collection & transportation upto 30m
( 1 cu.m./ 35.28 cft )
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.000 Nos. 908.00 908.00
b) Coolies 4.000 Nos. 667.00 2668.00 3576.00
Materials Cement 0.320 MT 15940.00 5100.80
Sand 0.445 Cu.m. 2787.12 1240.27
40 mm aggregate 0.520 Cu.m. 2646.00 1375.92
20 mm aggregate 0.220 Cu.m. 2716.56 597.64
10 mm aggregate 0.110 Cu.m. 2540.16 279.42 8594.05
Actual rate 12170.05
Rate 15% contractor's overhead 1825.51
Per cum. Per cft. Total 13995.56
12170.05 344.96

45. 1:2:4 P.C.C. work in superstructure slab, beams, columns, lintels etc. with transportation up to 30m
( 1 cu.m./ 35.28 cft )
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 0.800 Nos. 908.00 726.40
b) Coolies 7.000 Nos. 667.00 4669.00 5395.40
Materials Cement 0.320 MT 15940.00 5100.80
Sand 0.445 Cub M 2787.12 1240.27
40 mm aggregate 0.520 Cub M 2646.00 1375.92
20 mm aggregate 0.220 Cub M 2716.56 597.64
10 mm aggregate 0.110 Cub M 2540.16 279.42 8594.05
Actual rate 13989.45
Rate 15% contractor's overhead 2098.42
Per cum. Per cft. Total 16087.87
13989.45 396.53

_______________
____________ _______________
Approved By
Prepared By Checked By
Rate Analysis

46. 1:1.5:3 P.C.C. work in superstructure slab, beams, columns, lintels etc. with transportation up to 30m
( 1 cu.m./ 35.28 cft )
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 0.800 Nos. 908.00 726.40
b) Coolies 7.000 Nos. 667.00 4669.00 5395.40
Materials Cement 0.400 MT 15940.00 6376.00
Sand 0.425 Cub M 2787.12 1184.53
20 mm aggregate 0.570 Cub M 2716.56 1548.44
10 mm aggregate 0.290 Cub M 2540.16 736.65 9845.61
Actual rate 15241.01
Rate 15% contractor's overhead 2286.15
Per cum. Per cft. Total 17527.16
15241.01 432.00

47. 1:1:2 P.C.C. work in superstructure slab, beams, columns, lintels etc. with transportation up to 30m
(1 cu.m./ 35.28 cft )
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 0.800 Nos. 908.00 726.40
b) Coolies 7.000 Nos. 667.00 4669.00 5395.40
Materials Cement 0.610 MT 15940.00 9723.40
Sand 0.425 Cub M 2787.12 1184.53
20 mm aggregate 0.640 Cub M 2716.56 1738.60
10 mm aggregate 0.210 Cub M 2540.16 533.43 13179.96
Actual rate 18575.36
Rate 15% contractor's overhead 2786.30
Per cum. Per cft. Total 21361.66
18575.36 526.51

48. Curtail, bent up, binding of MS bars according to the drawing for RCC and its transportation up to 30m
( 1 MT =1000 kg )
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 12.000 Nos. 908.00 10896.00
b) Coolies 12.000 Nos. 667.00 8004.00 18900.00
Materials Tor steel/MS bar 1.050 MT 75000.00 78750.00
Binding Wires 10.000 Kg 87.22 872.20 79622.20
Actual rate 98522.20
Rate 15% contractor's overhead 14778.33
Per mt Per kg Total 113300.53
98522.20 98.52

49. 6.35cm thick Reinforced Brick work in 1:3 cement mortar in superstructure slab, lintels etc. with transportation
upto 30m(for 10 sq.m./ 107.58sft )
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.150 Nos. 908.00 1044.20
b) Coolies 3.000 Nos. 667.00 2001.00 3045.20
Materials Cement 0.100 MT 15940.00 1594.00
Sand 0.200 Cub M 2787.12 557.42
Local Bricks 377.000 Nos. 14.00 5278.00 7429.42
Actual rate 10474.62
Rate 15% contractor's overhead 1571.19
Per sqm. Per sft Total 12045.82
1047.46 97.37

_______________
____________ _______________
Approved By
Prepared By Checked By
Rate Analysis

F. Form Work
50. Form work for beams, slab in structure including, screening, fitting, oiling, dismantling, removing and transportation up to 30m
( 10 sq.m./ 107.58 sft )
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.720 Nos. 908.00 1561.76
b) Coolies 2.570 Nos. 667.00 1714.19 3275.95
Materials Wood (Local/Normal)* 0.070 Cub M 44452.80 3111.70
Nails 2.500 Kg 109.00 272.50 3384.20
Actual rate 6660.15
Rate 15% contractor's overhead 999.02
Per sqm. Per sft. Total 7659.17
666.01 61.91
* Asume that timber and ballies will become unserviceable after being used for 6 Times
\ Qty. of material = 0.526/8 = 0.07 Cu. m.

51. Column post fitting and dismantling, removing with supplying wood and transporting upto 30m ( 10 sq.m./ 107.58 sft )
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 3.748 Nos. 908.00 3403.18
b) Coolies 5.622 Nos. 667.00 3749.87 7153.06
Materials Wood (Ordinary) 0.070 Cub M 44452.80 3111.70
Nails 2.500 Kg 109.00 272.50 3384.20
Actual rate 10537.25
Rate 15% contractor's overhead 1580.59
Per sqm. Per sft. Total 12117.84
1053.73 97.95

52. Form work for structural beams installlation and dismantling, removing and transporting upto 30m & up to 0.3m Ht of beams
( 10 sq.m./ 107.58 sft )
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 4.000 Nos. 908.00 3632.00
b) Coolies 6.000 Nos. 667.00 4002.00 7634.00
Materials Wood (Local/Normal)* 0.070 Cub M 44452.80 3111.70
Nails 2.500 Kg 109.00 272.50 3384.20
Actual rate 11018.20
Rate 15% contractor's overhead 1652.73
Per sqm. Per sft. Total 12670.93
1101.82 102.42

53. Form work for structural beams installlation and dismantling, removing and transporting upto 30m
(0.3m to 0.8m Ht of beams) ( 10 sq.m./ 107.58 sft )
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 2.670 Nos. 908.00 2424.36
b) Coolies 4.000 Nos. 667.00 2668.00 5092.36
Materials Wood (Local/Normal)* 0.070 Cub M 44452.80 3111.70
Nails 2.500 Kg 109.00 272.50 3384.20
Actual rate 8476.56
Rate 15% contractor's overhead 1271.48
Per sqm. Per sft. Total 9748.04
847.66 78.79

54. Form work for trench shuttering upto 1.5 to 3.0m depth and transporting upto 30m (100 sq.m./ 1075.8 sft )
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 0.500 Nos. 908.00 454.00
b) Coolies 1.000 Nos. 667.00 667.00 1121.00
Materials Planks 4.160 Sq M 578.78 2407.72

Walling Strut Wood (Normal)* 0.254 Cub M 44452.80 11277.68 13685.40


Actual rate 14806.40
Rate 15% contractor's overhead 2220.96
Per sqm. Per sft. Total 17027.36
148.06 13.76

55. Form work for open trench protection depth over 3.0m and transporting upto 30m ( 100 sq.m./ 1075.8 sft )
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.000 Nos. 908.00 908.00
b) Coolies 1.750 Nos. 667.00 1167.25 2075.25
Materials Planks 4.160 Sq M 578.78 2407.72
Walling Strut Wood
(Local/Normal) 0.254 Cub M 44452.80 11277.68 13685.40
Actual rate 15760.65
Rate 15% contractor's overhead 2364.10
Per sqm. Per sft. Total 18124.75
157.61 14.65

_______________
____________ _______________
Approved By
Prepared By Checked By
Rate Analysis

G. Roof Covering
56. CGI Sheet Roofing with supplying all materials (26 Gauge medium CGI) (10sq.m / 107.58 sq. ft)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.100 Nos. 908.00 998.80
b) Unskilled 1.250 Nos. 667.00 833.75 1832.55
CGI Sheet (26 Gauge) 12.000 Sq M 369.44 4433.30
Materials 8mm Nut Bolt 30.000 Nos. 28.00 840.00
J-Hook 25.000 Nos. 19.00 475.00
Bitumin washer 25.000 Nos. 3.00 75.00 5823.30
Actual rate 7655.85
Rate 15% contractor's overhead 1148.38
Per sqm. Per sft. Total 8804.23
765.59 71.16

57.Fixing GI plain Sheet (0.28mm) Ridge cover with supplying all materials (10Rm / 3.28 ft)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 2.000 Nos. 908.00 1816.00
b) Unskilled 3.000 Nos. 667.00 2001.00 3817.00
GI Sheet (28Gauge) 12.000 R M 304.63 3655.56
Materials 8mm Nut Bolt L.S. 28.00 28.00 3683.56
Actual rate 7500.56
Rate 15% contractor's overhead 1125.08
Per Rm. Per rft. Total 8625.64
750.06 228.68

58. Coloured CGI Sheet (26 Gauge medium) Roofing with supplying all materials (10sq.m / 107.58 sq. ft)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.100 Nos. 908.00 998.80
b) Unskilled 1.250 Nos. 667.00 833.75 1832.55
* CGI Sheet(0.35mm th total) 12.000 Sq M 455.56 5466.73
Materials 8mm Nut Bolt 30.000 Nos. 28.00 840.00
J-Hook 25.000 Nos. 19.00 475.00
Bitumin washer 25.000 Nos. 3.00 75.00 6856.73
Actual rate 8689.28
Rate 15% contractor's overhead 1303.39
Per sqm. Per sft. Total 9992.68
868.93 80.77
* 0.37mm base metal thickness(i.e.add 2mm for total thickness)

59.Fixing Coloured GI plain Sheet (0.35mm) Ridge cover with supplying all materials (10Rm / 3.28 ft)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 2.000 Nos. 908.00 1816.00
b) Unskilled 3.000 Nos. 667.00 2001.00 3817.00
GI Sheet(0.43mm) 12.000 R M 439.11 5269.32
Materials 8mm Nut Bolt L.S. 28.00 28.00 5297.32
Actual rate 9114.32
Rate 15% contractor's overhead 1367.15
Per Rm. Per rft. Total 10481.47
911.43 277.88

60.1:1:3 (Lime surki brk agg)10cm thick Lime concrete terracing work with supplying all materials (10sq.m / 107.58 sq. ft)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.500 Nos. 908.00 1362.00
b) Unskilled 12.000 Nos. 667.00 8004.00 9366.00
Brick Agg. 1.250 Cub M 1155.77 1444.71
Materials Lime 1.500 Cub M 16800.00 25200.00
Surki 0.400 Cub M 1541.03 616.41 27261.12
Actual rate 36627.12
Rate 15% contractor's overhead 5494.07
Per sqm. Per sft. Total 42121.19
3662.71 340.46

H. Wood Work
61. 20 cm thick wood Ceiling work, plankings with 40x20mm Biding Joint with supplying all materials (10sq.m / 107.58 sq. ft)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.880 Nos. 908.00 1707.04
b) Unskilled 1.500 Nos. 667.00 1000.50 2707.54
Wood Saal 0.260 Cub M 194040.00 50450.40
Materials Nails 0.400 Kg. 109.00 43.60
40mm screw 160.000 Nos. 1.00 160.00 50654.00
Actual rate 53361.54
Rate 15% contractor's overhead 8004.23
Per sqm. Per sft. Total 61365.77
5336.15 496.02

_______________
____________ _______________
Approved By
Prepared By Checked By
Rate Analysis

62. Sal wood work for choukosh[0.9x2.1m size &0.1x0.075m section] ( 1cu.m./ 35.28 cft )
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 34.000 Nos. 908.00 30872.00
b) Coolies 3.400 Nos. 667.00 2267.80 33139.80
Materials Sal wood 1.100 Cub M 194040.00 213444.00
Hold fast 92.000 Nos. 17.29 1590.29
Screw 184.000 Nos. 1.00 184.00 215218.29
Actual rate 248358.09
Rate 15% contractor's overhead 37253.71
Per cum. Per cft. Total 285611.80
248358.09 7039.63

63. 38 mm thick Salwood solid pannel shutter (size 1.07m x 1.982m = 2.114 sq.m.) Rate analysis for 2.114 sq.m. / 22.7255 sft.
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 10.000 Nos. 908.00 9080.00
b) Coolies 1.000 Nos. 667.00 667.00 9747.00
Materials Sal wood 0.084 Cub M 194040.00 16299.36
100mm hinges 6.000 Nos. 27.00 162.00
150mm tower bolt 1.000 No 65.00 65.00
300mm tower bolt 1.000 No 103.00 103.00
300mm locking set 1.000 No 252.00 252.00
Handles (Good Quality) 2.000 Nos. 46.00 92.00
Screw nails 1.000 LS 20.00 20.00 16993.36
Actual rate 26740.36
Rate 15% contractor's overhead 4011.05
Per sqm. Per sft. Total 30751.41
12649.18 1175.79

64 . Openable glazed shutter with 38 x 75mm sal wood frame & 3 mm thick glass
(for rate analysis 1.829 x 1.22 = 2.23 sq m / 23.97 sft. )
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 9.000 Nos. 908.00 8172.00
b) Coolies 0.900 Nos. 667.00 600.30 8772.30
Materials Sal wood 0.049 Cub M 194040.00 9507.96
3 mm glass 1.085 sq.m. 537.50 583.19
75mm hinges 8.000 Nos. 15.00 120.00
100mm tower bolt 4.000 Nos. 39.00 156.00
Handles (Good Quality) 2.000 Nos. 46.00 92.00
Screw nails 1.000 LS 20.00 20.00 10479.15
Actual rate 19251.45
Rate 15% contractor's overhead 2887.72
Per sqm. Per sft. Total 22139.16
8632.94 802.47

65 . Openable glazed shutter with 38 x 75mm sal wood frame & 4 mm thick glass
(for rate analysis 1.829 x 1.22 = 2.23 sq m / 23.97 sft. )
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 9.000 Nos. 908.00 8172.00
b) Coolies 0.900 Nos. 667.00 600.30 8772.30
Materials Sal wood 0.049 Cub M 194040.00 9507.96
4 mm glass 1.085 sq.m. 688.00 746.48
75mm hinges 8.000 Nos. 15.00 120.00
100mm tower bolt 4.000 Nos. 39.00 156.00
Handles (Good Quality) 2.000 Nos. 46.00 92.00
Screw nails 1.000 LS 20.00 20.00 10642.44
Actual rate 19414.74
Rate 15% contractor's overhead 2912.21
Per sqm. Per sft. Total 22326.95
8706.16 809.27

_______________
____________ _______________
Approved By
Prepared By Checked By
Rate Analysis

66. Openable glazed shutter with 38 x 75mm sal wood frame &5 mm thick glass
(for rate analysis 1.829 x 1.22 = 2.23 sq m / 23.97 sft. )
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 9.000 Nos. 908.00 8172.00
b) Coolies 0.900 Nos. 667.00 600.30 8772.30
Materials Sal wood 0.049 Cub M 194040.00 9507.96
5 mm glass 1.085 sq.m. 924.50 1003.08
75mm hinges 8.000 Nos. 15.00 120.00
100mm tower bolt 4.000 Nos. 39.00 156.00
Handles (Good Quality) 2.000 Nos. 46.00 92.00
Screw nails 1.000 LS 20.00 20.00 10899.04
Actual rate 19671.34
Rate 15% contractor's overhead 2950.70
Per sqm. Per sft. Total 22622.04
8821.23 819.97

67 . Openable glazed shutter with 38 x 75mm sal wood frame & 6 mm thick glass
(for rate analysis 1.829 x 1.22 = 2.23 sq m / 23.97 sft. )
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 9.000 Nos. 908.00 8172.00
b) Coolies 0.900 Nos. 667.00 600.30 8772.30
Materials Sal wood 0.049 Cub M 194040.00 9507.96
6 mm glass 1.085 sq.m. 1075.00 1166.38
75mm hinges 8.000 Nos. 15.00 120.00
100mm tower bolt 4.000 Nos. 39.00 156.00
Handles (Good Quality) 2.000 Nos. 46.00 92.00
Screw nails 1.000 LS 20.00 20.00 11062.34
Actual rate 19834.64
Rate 15% contractor's overhead 2975.20
Per sqm. Per sft. Total 22809.83
8894.46 826.78

68. Flush shutter 38mm thick sal wood frame with 4mm thick commercial plywood on both side of shutter
(for rate analysis 1.092 x 2.058 = 2.245sq m/24.13 sft)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 7.000 Nos. 908.00 6356.00
b) Coolies 0.700 Nos. 667.00 466.90 6822.90
Materials Sal wood 0.0346 Cub M 194040.00 6713.78
4mm com.plywood 4.650 sq.m. 247.25 1149.71
100mm hinges 3.000 Nos. 27.00 81.00
150mm tower bolt 2.000 Nos. 65.00 130.00
Mortish lock 1.000 Nos. 404.00 404.00
Screw nails 1.000 LS 20.00 20.00 8498.50
Actual rate 15321.40
Rate Rate 15% contractor's overhead 2298.21
Per sqm. Per sft. Total 17619.61
6824.68 634.38

69.3. Flush shutter 38mm thick sal wood frame with 3mm thick teak plywood on both side of shutter
(for rate analysis 1.092 x 2.058 = 2.245sq m/24.13 sft)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 7.000 Nos. 908.00 6356.00
b) Coolies 0.700 Nos. 667.00 466.90 6822.90
Materials Sal wood 0.0346 Cub M 194040.00 6713.78
3mm teak ply 4.650 sq.m. 602.00 2799.30
100mm hinges 3.000 Nos. 27.00 81.00
150mm tower bolt 2.000 Nos. 65.00 130.00
Mortish lock 1.000 Nos. 404.00 404.00
Screw nails 1.000 LS 20.00 20.00 10148.08
Actual rate 16970.98
Rate Rate 15% contractor's overhead 2545.65
Per sqm. Per sft. Total 19516.63
7559.46 702.68

70. a.38mm thick sal wood shutter with 28 Gauge GI Plain Sheet on both side of shutter
(for rate analysis 1.092 x 2.058 = 2.245sq m/24.13 sft)

_______________
____________ _______________
Approved By
Prepared By Checked By
Rate Analysis

Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 7.000 Nos. 908.00 6356.00
b) Coolies 0.700 Nos. 667.00 466.90 6822.90
Materials Sal wood 0.0346 Cub M 194040.00 6713.78
28 Gauge GI Sheet 4.650 sq.m. 74.98 348.68
100mm hinges 3.000 Nos. 27.00 81.00
150mm tower bolt 2.000 Nos. 65.00 130.00
Mortish lock 1.000 Nos. 404.00 404.00
Screw nails 1.000 LS 20.00 20.00 7697.46
Actual rate 14520.36
Rate Rate 15% contractor's overhead 2178.05
Per sqm. Per sft. Total 16698.42
6467.87 601.21

71. G.I. mosquito proof wire mess (24gauge) shutter works with 38mm thick sal wood frame
(for rate analysis 1.092 x 2.058 = 2.245sq m/24.13 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 5.000 Nos. 908.00 4540.00
b) Coolies 0.500 Nos. 667.00 333.50 4873.50
Materials Sal wood 0.026 Cub M 194040.00 5045.04
24 gau.GI wiremess 2.130 sq.m. 116.00 247.08
100mm hinges 3.000 Nos 27.00 81.00
150mm tower bolt 2.000 Nos 65.00 130.00
Handles (Good Quality) 2.000 Nos 46.00 92.00
Spring (simple) 1.000 No 173.00 173.00
Screw nails 1.000 LS 15.00 15.00 5783.12
Actual rate 10656.62
Rate 15% contractor's overhead 1598.49
Per sqm. Per sft. Total 12255.11
4746.82 441.24

72 . Fixed glazed shutter with 3 mm thick glass (for 1 sq.m 10.76 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 0.060 Nos. 908.00 54.48
b) Coolies 0.006 Nos. 667.00 4.00 58.48
Materials 3 mm thick glass 1.000 S.m. 537.50 537.50
wooden listy 4.050 m 28.00 113.40
Screw nails 1.000 LS 15.00 15.00 665.90
Actual rate 724.38
Rate Rate 15% contractor's overhead 108.66
Per sqm. Per sft. Total 833.04
724.38 67.32

73. Fixed glazed shutter with 4 mm thick glass (for 1 sq.m 10.76 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 0.060 Nos. 908.00 54.48
b) Coolies 0.006 Nos. 667.00 4.00 58.48
Materials 4 mm thick glass 1.000 S.m. 688.00 688.00
wooden listy 4.050 m 28.00 113.40
Screw nails 1.000 LS 15.00 15.00 816.40
Actual rate 874.88
Rate Rate 15% contractor's overhead 131.23
Per sqm. Per sft. Total 1006.11
874.88 81.31

74. Fixed glazed shutter with 5 mm thick glass ( for 1 sq.m 10.76 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 0.060 Nos. 908.00 54.48
b) Coolies 0.006 Nos. 667.00 4.00 58.48
Materials 5 mm thick glass 1.000 S.m. 924.50 924.50
wooden listy 4.050 m 28.00 113.40
Screw nails 1.000 LS 15.00 15.00 1052.90
Actual rate 1111.38
Rate Rate 15% contractor's overhead 166.71
Per sqm. Per sft. Total 1278.09
1111.38 103.29

_______________
____________ _______________
Approved By
Prepared By Checked By
Rate Analysis

75. Fixed glazed shutter with 6 mm thick glass (for 1 sq.m 10.76 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 0.060 Nos. 908.00 54.48
b) Coolies 0.006 Nos. 667.00 4.00 58.48
Materials 6 mm thick glass 1.000 S.m. 1075.00 1075.00
wooden listy 4.050 m 28.00 113.40
Screw nails 1.000 LS 15.00 15.00 1203.40
Actual rate 1261.88
Rate Rate 15% contractor's overhead 189.28
Per sqm. Per sft. Total 1451.16
1261.88 117.28

76 . Wooden partition with frames of 38x75 mm sections on 0.61x0.915m rooms fixed with commercial ply both side fixing with listy
9.75mx3.65m=35.58sqm (382.84sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 23.000 Nos. 908.00 20884.00
b) Coolies 2.300 Nos. 667.00 1534.10 22418.10
Materials Wood Local 0.350 Cum 44452.80 15558.48
4mm ply 75.000 sqm 247.25 18543.75
wooden listy 100.000 Rm 28.00 2800.00
Ordinary nails 2.000 Kg 109.00 218.00 37120.23
Actual rate 59538.33
Rate Rate 15% contractor's overhead 8930.75
Per sqm. Per sft. Total 68469.08
1673.37 155.52

_______________
____________ _______________
Approved By
Prepared By Checked By
Rate Analysis

77 . Wooden partition with frames of 38x75 mm sections on 0.61x0.915m rooms fixed with 12mm thick hard board both side fixing
with listy
9.75mx3.65m=35.58sqm (382.84sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 23.000 Nos. 908.00 20884.00
b) Coolies 2.300 Nos. 667.00 1534.10 22418.10
Materials Wood 0.340 Cum 44452.80 15113.95
Hard board 75.000 sqm 451.50 33862.50
wooden listy 100.000 Rm 28.00 2800.00
Ordinary nails 2.000 Kg 109.00 218.00 51994.45
Actual rate 74412.55
Rate Rate 15% contractor's overhead 11161.88
Per sqm. Per sft. Total 85574.43
2091.42 194.37

78. Wooden partition with frames of 38x75 mm sections on 0.61x0.915m rooms fixed with 19mm thick planks both side in lap joint

Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 30.000 Nos. 908.00 27240.00
b) Coolies 3.000 Nos. 667.00 2001.00 29241.00
Materials Wood Local 1.767 Cum 44452.80 78548.10
wooden listy 100.000 Rm 28.00 2800.00
Ordinary nails 2.000 Kg 109.00 218.00 81566.10
Actual rate 110807.10
Rate Rate 15% contractor's overhead 16621.06
Per sqm. Per sft. Total 127428.16
3114.31 289.43

79 . False ceiling with 50x75 mm sections sisau wood with 600x900mm openings fixed with 4mm thick Commercial plywood
9.75mx3.65m=35.58sqm (382.84sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 23.000 Nos. 908.00 20884.00
b) Coolies 2.300 Nos. 667.00 1534.10 22418.10
Materials Sisau Wood 0.450 Cum 92010.24 41404.61
4mm Ply 37.500 sqm 247.25 9271.88
wooden listy 100.000 Rm 28.00 2800.00
Ordinary nails 1.500 Kg 109.00 163.50 53639.98
Actual rate 76058.08
Rate Rate 15% contractor's overhead 11408.71
Per sqm. Per sft. Total 87466.80
2137.66 198.67

80. False ceiling with 50x75 mm sections sal wood with 600x900mm openings fixed with 3mm thick Asbetos plain sheets
9.75mx3.65m=35.58sqm (382.84sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 23.000 Nos. 908.00 20884.00
b) Coolies 2.300 Nos. 667.00 1534.10 22418.10
Materials Sisau Wood 0.450 Cum 92010.24 41404.61
3mm asbetos sheet 37.500 sqm 329.26 12347.25
wooden listy 100.000 Rm 28.00 2800.00
Ordinary nails 1.500 Kg 109.00 163.50 56715.36
Actual rate 79133.46
Rate Rate 15% contractor's overhead 11870.02
Per sqm. Per sft. Total 91003.48
2224.10 206.70

81. False ceiling with 50x75 mm sections sisau wood with 600x900mm openings fixed with 12mm thick Hard board
9.75mx3.65m=35.58sqm (382.84sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 23.000 Nos. 908.00 20884.00
b) Coolies 2.300 Nos. 667.00 1534.10 22418.10
Materials Sisau Wood 0.450 Cum 92010.24 41404.61
Hard board 12 mm 37.500 sqm 451.50 16931.25
wooden listy 100.000 Rm 28.00 2800.00
Ordinary nails 1.500 Kg 109.00 163.50 61299.36
Actual rate 83717.46
Rate Rate 15% contractor's overhead 12557.62
Per sqm. Per sft. Total 96275.08
2352.94 218.67

_______________
____________ _______________
Approved By
Prepared By Checked By
Rate Analysis

82 . Wooden rafter/purlins/beams making and fixing of saal wood (1cum=35.28cft)


Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 17.650 Nos. 908.00 16026.20
b) Coolies 1.760 Nos. 667.00 1173.92 17200.12
Materials Wood saal 1.050 Cum 194040.00 203742.00
Ordinary nails 3.000 Kg 109.00 327.00 204069.00
Actual rate 221269.12
Rate Rate 15% contractor's overhead 33190.37
Per cum. Per cft. Total 254459.49
221269.12 6271.80

83 . Wooden trussmaking and fixing of saal wood. (1cum=35.28cft)


Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 17.650 Nos. 908.00 16026.20
b) Coolies 26.000 Nos. 667.00 17342.00 33368.20
Materials Wood Saal 1.050 Cum 194040.00 203742.00
Steel plates 1.000 LS 200.00 200.00
Nut bolts 1.000 LS 200.00 200.00
Ordinary nails 3.000 Kg 109.00 327.00 204469.00
Actual rate 237837.20
Rate Rate 15% contractor's overhead 35675.58
Per cum. Per cft. Total 273512.78
237837.20 6741.42

84 . 25mm x150mm salwood eaves board making and fixing (10sqm=107.6sft)


Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.430 Nos. 908.00 1298.44
b) Coolies 0.143 Nos. 667.00 95.38 1393.82
Materials Wood saal 0.275 Cum 194040.00 53361.00
Ordinary nails 1.000 Kg 109.00 109.00 53470.00
Actual rate 54863.82
Rate Rate 15% contractor's overhead 8229.57
Per sqm. Per sft. Total 63093.39
5486.38 509.89

85. 16-20 mm dia ms rod fixing on windows (1MT)


Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 20.000 Nos. 908.00 18160.00
b) Coolies 20.000 Nos. 667.00 13340.00 31500.00
Materials MS rod 1.050 MT 75000.00 78750.00 78750.00
Actual rate 110250.00
Rate Rate 15% contractor's overhead 16537.50
Per MT Per kg. Total 126787.50
110250.00 110.25

I. Flooring works

86. 38mm(11/2") thick 1:2:4 Cement Concrete FLooring and finishing with neat cement coat (for 10 sqm /107.58 sft)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.250 Nos. 908.00 1135.00
b) Coolies 2.000 Nos. 667.00 1334.00 2469.00
Materials Cement 0.130 MT 15940.00 2072.20
Sand 0.180 Cub M 2787.12 501.68
12 mm aggregate 0.360 Cub M 2716.56 977.96 3551.84
Actual rate 6020.84
Rate 15% contractor's overhead 903.13
Per sqm. Per sft. Total 6923.97
602.08 55.97

_______________
____________ _______________
Approved By
Prepared By Checked By
Rate Analysis

87. 50mm(2") thick 1:2:4 Cement Concrete FLooring and finishing with neat cement coat (for 10 sqm/ 107.58 sft)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.250 Nos. 908.00 1135.00
b) Coolies 2.500 Nos. 667.00 1667.50 2802.50
Materials Cement 0.170 MT 15940.00 2709.80
Sand 0.230 Cub M 2787.12 641.04
12 mm aggregate 0.460 Cub M 2716.56 1249.62 4600.46
Actual rate 7402.96
Rate 15% contractor's overhead 1110.44
Per sqm. Per sft. Total 8513.40
740.30 68.81

88. 75mm(3") thick 1:2:4 Cement Concrete FLooring and finishing with neat cement coat (for 10 sqm /107.58 sft)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.250 Nos. 908.00 1135.00
b) Coolies 3.000 Nos. 667.00 2001.00 3136.00
Materials Cement 0.260 MT 15940.00 4144.40
Sand 0.340 Cub M 2787.12 947.62
20 mm aggregate 0.680 Cub M 2716.56 1847.26 6939.28
Actual rate 10075.28
Rate 15% contractor's overhead 1511.29
Per sqm. Per sft. Total 11586.57
1007.53 93.65

89. 25mm thick mosaic flooring with 20mm thick cement plaster 1:2:4 cement sand ratio & 5mm thick 1:1 white cement & marble
chipping surface course including by rubbing & polish to finish
(10 sqm/ 107.58 sft )
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 2.500 Nos. 908.00 2270.00
b) Coolies 16.000 Nos. 667.00 10672.00 12942.00
Materials Cement 0.065 mt 15940.00 1036.10
Sand 0.088 cub m 2787.12 245.27
12.5mm aggregate 0.176 cub m 2716.56 478.11
White cement 0.061 Mt 26375.00 1608.88
Marble chips 0.061 Mt 13728.00 837.41
Axalic acid 0.365 kg 115.00 41.98
Wax polish 0.118 kg 200.00 23.60
Turpentine 0.538 lit. 229.00 123.20
Carborendom stone 1.000 LS 150.00 150.00 4544.54
Actual rate 17486.54
Rate 15% contractor's overhead 2622.98
Per sqm. Per sft. Total 20109.52
1748.65 162.54

90. 25mm thick mosaic flooring with 6mm thick 1:1 white cement & marble chipping over 19mm c/s plaster surface with rubbing &
polish to finish
(10 sqm/ 107.58 sft )
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 3.500 Nos. 908.00 3178.00
b) Coolies 36.000 Nos. 667.00 24012.00 27190.00
Materials Cement 0.121 mt 15940.00 1928.74
Sand 0.165 cub m 2787.12 459.87
White cement 0.069 Mt 26375.00 1819.88
Marble chips 3mm 0.047 Mt 13728.00 645.22
Axalic acid 0.340 kg 115.00 39.10
Wax polish 0.110 kg 200.00 22.00
turpentine 0.500 lit. 229.00 114.50
Carborendom stone 1.000 LS 150.00 150.00 5179.31
Actual rate 32369.31
Rate 15% contractor's overhead 4855.40
Per sqm. Per sft. Total 37224.70
3236.93 300.89

_______________
____________ _______________
Approved By
Prepared By Checked By
Rate Analysis

91. 20mm thick mosaic flooring with 6mm thick 1:1 white cement & marble chipping over 12.5mm1:2 c/s plaster surface with
rubbing & polish to finish
(10 sqm/ 107.58 sft )
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 3.500 Nos. 908.00 3178.00
b) Coolies 36.000 Nos. 667.00 24012.00 27190.00
Materials Cement 0.089 mt 15940.00 1418.66
Sand 0.122 cub m 2787.12 340.03
White cement 0.089 Mt 26375.00 2347.38
Marble chips 3mm 0.061 Mt 13728.00 837.41
Axalic acid 0.365 kg 115.00 41.98
Wax polish 0.118 kg 200.00 23.60
turpentine 0.538 lit. 229.00 123.20
Carborendom stone 1.000 LS 150.00 150.00 5282.25
Actual rate 32472.25
Rate 15% contractor's overhead 4870.84
Per sqm. Per sft. Total 37343.09
3247.22 301.84

92. 20mm terrazo tile over 20mm1:4 c/s plaster surface with rubbing & polish to finish (10 sqm/ 107.58 sft )
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 2.000 Nos. 908.00 1816.00
b) Coolies 12.600 Nos. 667.00 8404.20 10220.20
Materials Cement 0.081 mt 15940.00 1291.14
Sand 0.220 cub m 2787.12 613.17
20mm terrazotile 11.000 Sq M 516.00 5676.00
Axalic acid 0.365 kg 115.00 41.98
Wax polish 0.118 kg 200.00 23.60
turpentine 0.538 lit. 229.00 123.20
Carborendom stone 1.000 LS 150.00 150.00
Rubbing unskilled labour 13.500 Nos. 667.00 9004.50 16923.58
Actual rate 27143.78
Rate 15% contractor's overhead 4071.57
Per sqm. Per sft. Total 31215.35
2714.38 252.31

93. 15mm thick marble (450x450mm) over 20mm1:2 surki with rubbing & polish to finish also (10 sqm/ 107.58 sft )
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 2.000 Nos. 908.00 1816.00
b) Coolies 8.000 Nos. 667.00 5336.00 7152.00
Materials Lime 0.091 Cub M 16800.00 1528.80
25mm marble 11.000 Sq M 1644.75 18092.25
Surki 0.183 Cub M 1541.03 282.01
Axalic acid 0.370 kg 115.00 42.55
Wax polish 0.118 kg 200.00 23.60
turpentine 0.538 lit. 229.00 123.20
Carborendom stone 1.000 LS 150.00 150.00
Rubbing unskilled labour 13.500 Nos. 667.00 9004.50 29246.91
Actual rate 36398.91
Rate 15% contractor's overhead 5459.84
Per sqm. Per sft. Total 41858.75
3639.89 338.34

94. Porcelain glazed tile over 20mm1:4 c/s mortar (10 sqm/ 107.58 sft )
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 13.000 Nos. 908.00 11804.00
b) Coolies 4.500 Nos. 667.00 3001.50 14805.50
Materials Cement 0.056 mt 15940.00 892.64
Sand 0.152 cub m 2787.12 423.64
White cement 3.228 kg 26.38 85.14
Porcelain glaged tile 11.000 Sq M 709.50 7804.50 9205.92
Actual rate 24011.42
Rate 15% contractor's overhead 3601.71
Per sqm. Per sft. Total 27613.13
2401.14 223.20

95. 50 mm Flagstone paving on 1:4 c/s mortar (10 sqm/ 107.58 sft )
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 2.000 Nos. 908.00 1816.00
b) Coolies 4.500 Nos. 667.00 3001.50 4817.50
Materials Cement 0.063 mt 15940.00 1004.22
Sand 0.171 cub m 2787.12 476.60
50 mm thick flagstone 11.000 Sq M 1182.50 13007.50 14488.32
Actual rate 19305.82
Rate 15% contractor's overhead 2895.87
Per sqm. Per sft. Total 22201.69
1930.58 179.46

_______________
____________ _______________
Approved By
Prepared By Checked By
Rate Analysis

96. 50 mm down Flagstone paving on filled sand (10 sqm/ 107.58 sft )
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.000 Nos. 908.00 908.00
b) Coolies 3.000 Nos. 667.00 2001.00 2909.00
Materials Sand 0.710 cub m 2787.12 1978.86
50 mm down Flagstone 11.000 Sq M 1026.63 11292.88 13271.73
Actual rate 16180.73
Rate 15% contractor's overhead 2427.11
Per sqm. Per sft. Total 18607.84
1618.07 150.41

97. 37.5 mm Flagstone paving on 1:4 cement mortar (10 sqm/ 107.58 sft )
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 2.000 Nos. 908.00 1816.00
b) Coolies 4.500 Nos. 667.00 3001.50 4817.50
Cement 0.060 mt 15940.00 956.40
Materials Sand 0.165 cub m 2787.12 459.87
37.5mm Flagstone 11.000 Sq M 1021.25 11233.75 11693.62
Actual rate 16511.12
Rate 15% contractor's overhead 2476.67
Per sqm. Per sft. Total 18987.79
1651.11 153.48

98. 25 mm Flagstone paving on 1:4 cement mortar (10 sqm/ 107.58 sft )
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.500 Nos. 908.00 1362.00
b) Coolies 4.500 Nos. 667.00 3001.50 4363.50
Cement 0.056 mt 15940.00 892.64
Materials Sand 0.152 cub m 2787.12 423.64
25mm Flagstone 11.000 Sq M 870.75 9578.25 10001.89
Actual rate 14365.39
Rate 15% contractor's overhead 2154.81
Per sqm. Per sft. Total 16520.20
1436.54 133.53

99. 25 mm Telia brick paving in 1:2 surki masala & tipkar in 1:2 cement mortar (10 sqm/ 107.58 sft )
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 4.500 Nos. 908.00 4086.00
b) Coolies 4.500 Nos. 667.00 3001.50 7087.50
Materials Cement 0.016 mt 15940.00 255.04
Sand 0.110 cub m 2787.12 306.58
Lime 0.122 cub m 16800.00 2049.60
Surki 0.244 cub m 1541.03 376.01
Telia Bricks 25mm thick 440.000 Nos. 13.00 5720.00 8707.23
Actual rate 15794.73
Rate 15% contractor's overhead 2369.21
Per sqm. Per sft. Total 18163.94
1579.47 146.82

100. Brick flat soling on 1:6 cement mortar and pointing in 1:2 cement mortar on joints (10 sqm/ 107.58 sft )
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 2.250 Nos. 908.00 2043.00
b) Coolies 3.250 Nos. 667.00 2167.75 4210.75
Cement 0.078 mt 15940.00 1243.32
Materials Sand 0.229 cub m 2787.12 638.25
Local Bricks 430.000 Nos. 14.00 6020.00 7901.57
Actual rate 12112.32
Rate 15% contractor's overhead 1816.85
Per sqm. Per sft. Total 13929.17
1211.23 112.59

101. Brick edge soling on 1:6 cement mortar and pointing in 1:2 cement mortar on joints works (10 sqm/ 107.58 sft )
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.100 Nos. 908.00 998.80
b) Coolies 1.800 Nos. 667.00 1200.60 2199.40
Cement 0.121 mt 15940.00 1928.74
Materials Sand 0.431 cub m 2787.12 1201.25
Local Bricks 750.000 Nos. 14.00 10500.00 13629.99
Actual rate 15829.39
Rate 15% contractor's overhead 2374.41
Per sqm. Per sft. Total 18203.80
1582.94 147.14

_______________
____________ _______________
Approved By
Prepared By Checked By
Rate Analysis

102. Parketting with polishing after rubbing with sand paper works (10 sqm/ 107.58 sft )
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.750 Nos. 908.00 1589.00
b) Coolies 0.750 Nos. 667.00 500.25 2089.25
Parkette 10.500 Sq M 1870.50 19640.25
Materials Sand paper 1.000 LS 30.00 30.00
Wax polish 1.000 LS 50.00 50.00 19720.25
Machine to rub machine to sand paper 2.000 Hrs 150.00 300.00 300.00
Actual rate 22109.50
Rate 15% contractor's overhead 3316.43
Per sqm. Per sft. Total 25425.93
2210.95 205.52

103. Dry flat brick soling works (10 sqm/ 107.58 sft )
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 0.500 Nos. 908.00 454.00
b) Coolies 1.000 Nos. 667.00 667.00 1121.00
Local Bricks 420.000 Sq M 14.00 5880.00
Materials Sand 0.710 Cum 2787.12 1978.86 7858.86
Actual rate 8979.86
Rate 15% contractor's overhead 1346.98
Per sqm. Per sft. Total 10326.83
897.99 83.47

104. Dry edge brick soling works (10 sqm/ 107.58 sft )
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.000 Nos. 908.00 908.00
b) Coolies 3.250 Nos. 667.00 2167.75 3075.75
Bricks 750.000 Sq M 14.00 10500.00
Materials Sand 0.710 Cum 2787.12 1978.86 12478.86
Actual rate 15554.61
Rate 15% contractor's overhead 2333.19
Per sqm. Per sft. Total 17887.80
1555.46 144.59

105. Dry stone soling works (1Cum/35.28 Cft )


Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.000 Nos. 908.00 908.00
b) Coolies 3.500 Nos. 667.00 2334.50 3242.50
Stone 1.100 Sq M 2116.80 2328.48
Materials Sand 0.710 Cum 2787.12 1978.86 4307.34
Actual rate 7549.84
Rate 15% contractor's overhead 1132.48
Per Cum Per cft. Total 8682.31
7549.84 214.00

106. 125mm Edge Brick soling and pointing works in 1:3cement mortar on joints after sand filling (10 sqm/ 107.58 sft )
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 2.000 Nos. 908.00 1816.00
b) Coolies 4.000 Nos. 667.00 2668.00 4484.00
Materials Cement 0.020 Mt 15940.00 318.80
Sand 0.710 Cum 2787.12 1978.86
Bricks 750.000 Nos. 14.00 10500.00 12797.66
Actual rate 17281.66
Rate 15% contractor's overhead 2592.25
Per sqm. Per sft. Total 19873.90
1728.17 160.64

_______________
____________ _______________
Approved By
Prepared By Checked By
Rate Analysis

107. Pointing in 1:1cement mortar on joints works on paved stone 46cm X46cm (10 sqm/ 107.58 sft )
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 0.500 Nos. 908.00 454.00
b) Coolies 0.500 Nos. 667.00 333.50 787.50
Materials Cement 4.200 Kg 15.94 66.95
Sand 0.003 Cum 2787.12 8.36 75.31
Actual rate 862.81
Rate 15% contractor's overhead 129.42
Per sqm. Per sft. Total 992.23
86.28 8.02

108. Filling with sand works (10 cum/ 352.8cft )


Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 0.000 Nos. 908.00 0.00
b) Coolies 6.500 Nos. 667.00 4335.50 4335.50
Materials Sand 11.000 Cum 2787.12 30658.32 30658.32
Actual rate 34993.82
Rate 15% contractor's overhead 5249.07
Per sqm. Per sft. Total 40242.89
3499.38 325.28

109. 15-150 mm brick bat Filling works (10 cum/ 352.8cft )


Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 0.000 Nos. 908.00 0.00
b) Coolies 10.000 Nos. 667.00 6670.00 6670.00
Materials Batten Bricks 11.000 Cum 359.95 3959.45 3959.45
Actual rate 10629.45
Rate 15% contractor's overhead 1594.42
Per cum. Per cft. Total 12223.87
1062.95 30.13

110. 3mm thick thin layer cement Punning (chipping )works (10 sqm/ 107.58 sft )
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.000 Nos. 908.00 908.00
b) Coolies 1.000 Nos. 667.00 667.00 1575.00
Materials Cement 53.200 Kg 15.94 848.01 848.01
Actual rate 2423.01
Rate 15% contractor's overhead 363.45
Per sqm. Per sft. Total 2786.46
242.30 22.52

J. Plasters & Pointing Work :


111. 12.5mm 1:3 cement sand plaster on ceiling (for 100 sq.m/1075.8 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 15.000 Nos. 908.00 13620.00
b) Coolies 20.000 Nos. 667.00 13340.00 26960.00
Materials Cement 0.625 MT 15940.00 9962.50
Sand 1.280 Cub M 2787.12 3567.51 13530.01
Actual rate 40490.01
Rate 15% contractor's overhead 6073.50
Per sqm. Per sft. Total 46563.52
404.90 37.64

_______________
____________ _______________
Approved By
Prepared By Checked By
Rate Analysis

112. 12.5mm 1:4cement sand plaster works on ceiling (for 100 sq.m/1075.8 sft.)
Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 15.000 Nos. 908.00 13620.00
b) Coolies 20.000 Nos. 667.00 13340.00 26960.00
Materials Cement 0.538 MT 15940.00 8575.72
Sand 1.460 Cub M 2787.12 4069.20 12644.92
Actual rate 39604.92
Rate 15% contractor's overhead 5940.74
Per sqm. Per sft. Total 45545.65
396.05 36.81

113. 12.5mm 1:4 cement sand plaster works except in ceiling (for 100 sq.m/1075.8 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 12.000 Nos. 908.00 10896.00
b) Coolies 16.000 Nos. 667.00 10672.00 21568.00
Materials Cement 0.538 Mt 15940.00 8575.72
Sand 1.460 Cub M 2787.12 4069.20 12644.92
Actual rate 34212.92
Rate 15% contractor's overhead 5131.94
Per sqm. Per sft. Total 39344.85
342.13 31.80

114. 12.5mm 1:6 cement sand plaster works (for 100 sq.m/1075.8 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 12.000 Nos. 908.00 10896.00
b) Coolies 16.000 Nos. 667.00 10672.00 21568.00
Materials Cement 0.382 Mt 15940.00 6089.08
Sand 1.570 Cub M 2787.12 4375.78 10464.86
Actual rate 32032.86
Rate 15% contractor's overhead 4804.93
Per sqm. Per sft. Total 36837.79
320.33 29.78

115. 12.5mm 1:2 Lime surki plaster works (for 100 sq.m/1075.8 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 12.000 Nos. 908.00 10896.00
b) Coolies 16.000 Nos. 667.00 10672.00 21568.00
Materials Lime 0.610 Cub M 16800.00 10248.00
Surki 1.220 Cub M 1541.03 1880.06 12128.06
Actual rate 33696.06
Rate 15% contractor's overhead 5054.41
Per sqm. Per sft. Total 38750.47
336.96 31.32

116. 20mm 1:3 cement sand plaster works (for 100 sq.m/1075.8 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 14.000 Nos. 908.00 12712.00
b) Coolies 19.000 Nos. 667.00 12673.00 25385.00
Materials Cement 0.960 Mt 15940.00 15302.40
Sand 1.950 Cub M 2787.12 5434.88 20737.28
Actual rate 46122.28
Rate 15% contractor's overhead 6918.34
Per sqm. Per sft. Total 53040.63
461.22 42.87

117. 20mm 1:4cement sand plaster works except in ceiling (for 100 sq.m/1075.8 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 14.000 Nos. 908.00 12712.00
b) Coolies 19.000 Nos. 667.00 12673.00 25385.00
Materials Cement 0.810 mt 15940.00 12911.40
Sand 2.200 Cub M 2787.12 6131.66 19043.06
Actual rate 44428.06
Rate 15% contractor's overhead 6664.21
Per sqm. Per sft. Total 51092.27
444.28 41.30

_______________
____________ _______________
Approved By
Prepared By Checked By
Rate Analysis

118. 20mm 1:6 cement sand plaster works except in ceiling (for 100 sq.m/1075.8 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 14.000 Nos. 908.00 12712.00
b) Coolies 19.000 Nos. 667.00 12673.00 25385.00
Materials Cement 0.570 mt 15940.00 9085.80
Sand 2.350 Cub M 2787.12 6549.73 15635.53
Actual rate 41020.53
Rate 15% contractor's overhead 6153.08
Per sqm. Per sft. Total 47173.61
410.21 38.13

119. 25mm mud plaster works with preparation of mud and surface etc. 30m lead (for 100 sq.m/1075.8 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 20.000 Nos. 908.00 18160.00
b) Coolies 25.000 Nos. 667.00 16675.00 34835.00
Materials Mud 3.000 Cub M 260.00 780.00
Rice straw 10.000 Kg. 5.00 50.00
Cow Dung 120.000 Kg. 4.80 576.00 1406.00
Actual rate 36241.00
Rate 15% contractor's overhead 5436.15
Per sqm. Per sft. Total 41677.15
362.41 33.69

120. 12 mm mud plaster works with preparation of mud and surface etc. 30m lead (for 100 sq.m/1075.8 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 15.000 Nos. 908.00 13620.00
b) Coolies 20.000 Nos. 667.00 13340.00 26960.00
Materials Mud 1.500 Cub M 260.00 390.00
Rice straw 50.000 Kg. 5.00 250.00
Cow Dung 60.000 Kg. 4.80 288.00 928.00
Actual rate 27888.00
Rate 15% contractor's overhead 4183.20
Per sqm. Per sft. Total 32071.20
278.88 25.92

K. Painting Work
121. 2 coat white washing works in ceiling on new surface (for 100 sq.m/1075.8 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.875 Nos. 908.00 1702.50
b) Coolies 1.375 Nos. 667.00 917.13 2619.63
Materials Gum 0.880 Kg. 217.00 190.96
White Lime 22.000 Kg. 21.00 462.00 652.96
Actual rate 3272.59
Rate 15% contractor's overhead 490.89
Per sqm. Per sft. Total 3763.47
32.73 3.04

122. 2 coat white washing works on other new surface (for 100 sq.m/1075.8 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.500 Nos. 908.00 1362.00
b) Coolies 1.100 Nos. 667.00 733.70 2095.70
Materials Gum 0.880 Kg. 217.00 190.96
White Lime 22.000 Kg. 21.00 462.00 652.96
Actual rate 2748.66
Rate 15% contractor's overhead 412.30
Per sqm. Per sft. Total 3160.96
27.49 2.55

123. 3 coat white washing works in ceiling on new surface (for 100 sq.m/1075.8 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 3.750 Nos. 908.00 3405.00
b) Coolies 3.375 Nos. 667.00 2251.13 5656.13
Materials Gum 1.280 Kg. 217.00 277.76
White Lime 32.000 Kg. 21.00 672.00 949.76
Actual rate 6605.89
Rate 15% contractor's overhead 990.88
Per sqm. Per sft. Total 7596.77
66.06 6.14

_______________
____________ _______________
Approved By
Prepared By Checked By
Rate Analysis

124. 3 coat white washing works on other new surface (for 100 sq.m/1075.8 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 3.000 Nos. 908.00 2724.00
b) Coolies 2.700 Nos. 667.00 1800.90 4524.90
Materials Gum 1.280 Kg. 217.00 277.76
White Lime 32.000 Kg. 21.00 672.00 949.76
Actual rate 5474.66
Rate 15% contractor's overhead 821.20
Per sqm. Per sft. Total 6295.86
54.75 5.09

125. One White washing works on old surface (for 100 sq.m/1075.8 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 0.800 Nos. 908.00 726.40
b) Coolies 0.700 Nos. 667.00 466.90 1193.30
Materials Gum 0.400 Kg. 217.00 86.80
White Lime 10.000 Kg. 21.00 210.00 296.80
Actual rate 1490.10
Rate 15% contractor's overhead 223.52
Per sqm. Per sft. Total 1713.62
14.90 1.39

126. One coat distempering works over one coat astar (for 100 sq.m/1075.8 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 4.000 Nos. 908.00 3632.00
b) Coolies 4.000 Nos. 667.00 2668.00 6300.00
Materials Astar 8.000 Ltr. 286.00 2288.00
Distamper Powder 6.500 Kg. 238.00 1547.00 3835.00
Actual rate 10135.00
Rate 15% contractor's overhead 1520.25
Per sqm. Per sft. Total 11655.25
101.35 9.42

127. Two coat distemper works over one coat astar (for 100 sq.m/1075.8 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 5.800 Nos. 908.00 5266.40
b) Coolies 5.800 Nos. 667.00 3868.60 9135.00
Materials Astar 8.000 Ltr. 286.00 2288.00
Distamper Powder 11.500 Kg. 238.00 2737.00 5025.00
Actual rate 14160.00
Rate 15% contractor's overhead 2124.00
Per sqm. Per sft. Total 16284.00
141.60 13.16

128 One coat water proof cement paint works over one coat astar
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.700 Nos. 908.00 1543.60
b) Coolies 1.700 Nos. 667.00 1133.90 2677.50
Materials Cement Paint 30.000 Ltr. 79.00 2370.00 2370.00
Actual rate 5047.50
Rate 15% contractor's overhead 757.13
Per sqm. Per sft. Total 5804.63
50.48 4.69

129. Two coat water proof cement paint works over one coat astar (for 100 sq.m/1075.8 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 5.000 Nos. 908.00 4540.00
b) Coolies 5.000 Nos. 667.00 3335.00 7875.00
Materials Cement Paint 48.500 Ltr. 79.00 3831.50 3831.50
Actual rate 11706.50
Rate 15% contractor's overhead 1755.98
Per sqm. Per sft. Total 13462.48
117.07 10.88

130. One coat readymade enamel paint over one coat primer (Astar) on new surface (for 100 sq.m/1075.8 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 8.000 Nos. 908.00 7264.00
b) Coolies 5.000 Nos. 667.00 3335.00 10599.00
Materials Primer 8.100 lit. 402.00 3256.20
Enamel 9.000 lit. 560.00 5040.00 8296.20
Actual rate 18895.20
Rate 15% contractor's overhead 2834.28
Per sqm. Per sft. Total 21729.48
188.95 17.56

_______________
____________ _______________
Approved By
Prepared By Checked By
Rate Analysis

131. Two coat readymade enamel paint over one coat primer (Astar) on new surface (for 100 sq.m/1075.8 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 12.000 Nos. 908.00 10896.00
b) Coolies 8.000 Nos. 667.00 5336.00 16232.00
Materials Primer 8.100 lit. 402.00 3256.20
Enamel 16.000 lit. 560.00 8960.00 12216.20
Actual rate 28448.20
Rate 15% contractor's overhead 4267.23
Per sqm. Per sft. Total 32715.43
284.48 26.44

132. One coat plastic emulsion paint over one coat primer (Astar) on new surface (for 100 sq.m/1075.8 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 8.000 Nos. 908.00 7264.00
b) Coolies 5.000 Nos. 667.00 3335.00 10599.00
Materials Primer 8.100 lit. 286.00 2316.60
Readymade Plastic Emulsion
paint 9.000 lit. 562.00 5058.00 7374.60
Actual rate 17973.60
Rate 15% contractor's overhead 2696.04
Per sqm. Per sft. Total 20669.64
179.74 16.71

133. Two coat plastic emulsion paint over one coat primer (Astar) on new surface (for 100 sq.m/1075.8 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 12.000 Nos. 908.00 10896.00
b) Coolies 8.000 Nos. 667.00 5336.00 16232.00
Materials Primer 8.100 lit. 286.00 2316.60
Readymade paint 16.000 lit. 562.00 8992.00 11308.60
Actual rate 27540.60
Rate 15% contractor's overhead 4131.09
Per sqm. Per sft. Total 31671.69
275.41 25.60

134. Two coat aluminium paint over one coat primer (Astar) on new surface (for 100 sq.m/1075.8 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 10.750 Nos. 908.00 9761.00
b) Coolies 10.750 Nos. 667.00 7170.25 16931.25
Materials Primer 8.100 lit. 402.00 3256.20
Aluminium paint 10.760 lit. 583.00 6273.08
Sand paper 4.000 Nos. 6.00 24.00 9553.28
Actual rate 26484.53
Rate 15% contractor's overhead 3972.68
Per sqm. Per sft. Total 30457.21
264.85 24.62

135. One coat double boiled linseed oiling work on new surface (for 100 sq.m/1075.8 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 2.000 Nos. 908.00 1816.00
b) Coolies 2.000 Nos. 667.00 1334.00 3150.00
Materials Linseed oil 6.000 lit. 210.00 1260.00 1260.00
Actual rate 4410.00
Rate 15% contractor's overhead 661.50
Per sqm. Per sft. Total 5071.50
44.10 4.10

_______________
____________ _______________
Approved By
Prepared By Checked By
Rate Analysis

136. Two coat double boiled linseed oiling work on new surface (for 100 sq.m/1075.8 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 4.000 Nos. 908.00 3632.00
b) Coolies 4.000 Nos. 667.00 2668.00 6300.00
Materials Linseed oil 11.000 lit. 210.00 2310.00 2310.00
Actual rate 8610.00
Rate 15% contractor's overhead 1291.50
Per sqm. Per sft. Total 9901.50
86.10 8.00

137. One coat varnishing work on new surface (for 100 sq.m/1075.8 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 3.000 Nos. 908.00 2724.00
b) Coolies 2.000 Nos. 667.00 1334.00 4058.00
Materials Varnish 6.000 lit. 470.00 2820.00 2820.00
Actual rate 6878.00
Rate 15% contractor's overhead 1031.70
Per sqm. Per sft. Total 7909.70
68.78 6.39

138. Two coat varnishing work on new surface (for 100 sq.m/1075.8 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 6.000 Nos. 908.00 5448.00
b) Coolies 4.000 Nos. 667.00 2668.00 8116.00
Materials Varnish 11.000 lit. 470.00 5170.00 5170.00
Actual rate 13286.00
Rate 15% contractor's overhead 1992.90
Per sqm. Per sft. Total 15278.90
132.86 12.35

139. One coat bitumen paint work on new surface (for 100 sq.m/1075.8 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.500 Nos. 908.00 1362.00
b) Coolies 1.000 Nos. 667.00 667.00 2029.00
Materials Bitumen Paint 7.000 lit. 68.00 476.00
Sand paper 4.000 Nos. 6.00 24.00 500.00
Actual rate 2529.00
Rate 15% contractor's overhead 379.35
Per sqm. Per sft. Total 2908.35
25.29 2.35

140. Two coat bitumen paint work on new surface (for 100 sq.m/1075.8 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 2.500 Nos. 908.00 2270.00
b) Coolies 2.000 Nos. 667.00 1334.00 3604.00
Materials Bitumen Paint 12.000 lit. 68.00 816.00
Sand paper 4.000 Nos. 6.00 24.00 840.00
Actual rate 4444.00
Rate 15% contractor's overhead 666.60
Per sqm. Per sft. Total 5110.60
44.44 4.13

141. Three coat french(chapra) polish work on new surface (for 100 sq.m/1075.8 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 10.000 Nos. 908.00 9080.00
b) Coolies 5.000 Nos. 667.00 3335.00 12415.00
Materials Chapra 2.000 kg 978.00 1956.00
Spirit 10.000 lit. 126.00 1260.00 3216.00
Actual rate 15631.00
Rate 15% contractor's overhead 2344.65
Per sqm. Per sft. Total 17975.65
156.31 14.53

_______________
____________ _______________
Approved By
Prepared By Checked By
Rate Analysis

142. One coat snowcem work after cement paint on new plastered surface (for 100 sq.m/1075.8 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 3.500 Nos. 908.00 3178.00
b) Coolies 3.500 Nos. 667.00 2334.50 5512.50
Materials Snowcem 30.000 lit. 79.00 2370.00 2370.00
Actual rate 7882.50
Rate 15% contractor's overhead 1182.38
Per sqm. Per sft. Total 9064.88
78.83 7.33

143. Two coat snowcem work after cement paint on new plastered surface (for 100 sq.m/1075.8 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 6.500 Nos. 908.00 5902.00
b) Coolies 6.500 Nos. 667.00 4335.50 10237.50
Materials Snowcem 50.000 lit. 79.00 3950.00 3950.00
Actual rate 14187.50
Rate 15% contractor's overhead 2128.13
Per sqm. Per sft. Total 16315.63
141.88 13.19

L. Pointing Works
144. Flush pointing works in 1:1 cement sand mortar on brick masonry work (for 100 sq.m/1075.8 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 10.500 Nos. 908.00 9534.00
b) Coolies 12.000 Nos. 667.00 8004.00 17538.00
Materials Cement 0.316 mt 15940.00 5037.04
Sand 0.220 Cub M 2787.12 613.17 5650.21
Actual rate 23188.21
Rate 15% contractor's overhead 3478.23
Per sqm. Per sft. Total 26666.44
231.88 21.55

145. Ruled pointing works in 1:1 cement sand mortar on brick masonry work (for 100 sq.m/1075.8 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 10.500 Nos. 908.00 9534.00
b) Coolies 18.000 Nos. 667.00 12006.00 21540.00
Materials Cement 0.316 mt 15940.00 5037.04
Sand 0.220 Cub M 2787.12 613.17 5650.21
Actual rate 27190.21
Rate 15% contractor's overhead 4078.53
Per sqm. Per sft. Total 31268.74
271.90 25.27

146. Flush pointin g works in 1:2 cement sand mortar on Brick masonry work (for 100 sq.m/1075.8 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 10.500 Nos. 908.00 9534.00
b) Coolies 12.000 Nos. 667.00 8004.00 17538.00
Materials Cement 0.210 mt 15940.00 3347.40
Sand 0.290 Cub M 2787.12 808.26 4155.66
Actual rate 21693.66
Rate 15% contractor's overhead 3254.05
Per sqm. Per sft. Total 24947.71
216.94 20.17

147. Ruled pointing works in 1:2 cement sand mortar on Brick masonry work (for 100 sq.m/1075.8 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 10.500 Nos. 908.00 9534.00
b) Coolies 18.000 Nos. 667.00 12006.00 21540.00
Materials Cement 0.210 mt 15940.00 3347.40
Sand 0.290 Cub M 2787.12 808.26 4155.66
Actual rate 25695.66
Rate 15% contractor's overhead 3854.35
Per sqm. Per sft. Total 29550.01
256.96 23.89

_______________
____________ _______________
Approved By
Prepared By Checked By
Rate Analysis

148. Flush pointing works in 1:3 cement sand mortar on Brick masonry work (for 100 sq.m/1075.8 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 10.500 Nos. 908.00 9534.00
b) Coolies 12.000 Nos. 667.00 8004.00 17538.00
Materials Cement 0.155 mt 15940.00 2470.70
Sand 0.320 Cub M 2787.12 891.88 3362.58
Actual rate 20900.58
Rate 15% contractor's overhead 3135.09
Per sqm. Per sft. Total 24035.67
209.01 19.43

149. ruled pointing works in 1:3 cement sand mortar on Brick masonry work (for 100 sq.m/1075.8 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 10.500 Nos. 908.00 9534.00
b) Coolies 18.000 Nos. 667.00 12006.00 21540.00
Materials Cement 0.155 mt 15940.00 2470.70
Sand 0.320 Cub M 2787.12 891.88 3362.58
Actual rate 24902.58
Rate 15% contractor's overhead 3735.39
Per sqm. Per sft. Total 28637.97
249.03 23.15

150. Flush pointing works in 1:1:3 cement Lime sand mortar on Brick masonry work (for 100 sq.m/1075.8 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 10.500 Nos. 908.00 9534.00
b) Coolies 12.000 Nos. 667.00 8004.00 17538.00
Materials Cement 0.125 mt 15940.00 1992.50
Lime 0.085 Cub M 16800.00 1428.00
Sand 0.255 Cub M 2787.12 710.72 4131.22
Actual rate 21669.22
Rate 15% contractor's overhead 3250.38
Per sqm. Per sft. Total 24919.60
216.69 20.14

151. Ruled pointing works in 1:1:3 cement Lime sand mortar on Brick masonry work (for 100 sq.m/1075.8 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 10.500 Nos. 908.00 9534.00
b) Coolies 18.000 Nos. 667.00 12006.00 21540.00
Materials Cement 0.125 mt 2469.60 308.70
Lime 0.085 Cub M 16800.00 1428.00
Sand 0.255 Cub M 2787.12 710.72 2447.42
Actual rate 23987.42
Rate 15% contractor's overhead 3598.11
Per sqm. Per sft. Total 27585.53
239.87 22.30

152. Flush pointing works in 1:1 Lime Surki mortar on Brick masonry work (for 100 sq.m/1075.8 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 10.500 Nos. 908.00 9534.00
b) Coolies 12.000 Nos. 667.00 8004.00 17538.00
Materials Lime 0.220 Cub M 16800.00 3696.00
Surki 0.220 Cub M 1541.03 339.03 4035.03
Actual rate 21573.03
Rate 15% contractor's overhead 3235.95
Per sqm. Per sft. Total 24808.98
215.73 20.05

153. Ruled pointing works in 1:1 Lime Surki mortar on Brick masonry work (for 100 sq.m/1075.8 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 10.500 Nos. 908.00 9534.00
b) Coolies 18.000 Nos. 667.00 12006.00 21540.00
Materials Lime 0.220 Cub M 16800.00 3696.00
Surki 0.220 Cub M 1541.03 339.03 4035.03
Actual rate 25575.03
Rate 15% contractor's overhead 3836.25
Per sqm. Per sft. Total 29411.28
255.75 23.77

_______________
____________ _______________
Approved By
Prepared By Checked By
Rate Analysis

154. Flush pointing works in 1:2 Lime Surki mortar on Brick masonry work (for 100 sq.m/1075.8 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 10.500 Nos. 908.00 9534.00
b) Coolies 12.000 Nos. 667.00 8004.00 17538.00
Materials Lime 0.150 Cub M 16800.00 2520.00
Surki 0.290 Cub M 1541.03 446.90 2966.90
Actual rate 20504.90
Rate 15% contractor's overhead 3075.73
Per sqm. Per sft. Total 23580.63
205.05 19.06

155. Ruled pointing works in 1:2 Lime Surki mortar on Brick masonry work (for 100 sq.m/1075.8 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 10.500 Nos. 908.00 9534.00
b) Coolies 18.000 Nos. 667.00 12006.00 21540.00
Materials Lime 0.150 Cub M 16800.00 2520.00
Surki 0.290 Cub M 1541.03 446.90 2966.90
Actual rate 24506.90
Rate 15% contractor's overhead 3676.03
Per sqm. Per sft. Total 28182.93
245.07 22.78

156. Flush ruled pointing works in 1:1 c/s mortar on random rubble masonry work (for 100 sq.m/1075.8 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 10.000 Nos. 908.00 9080.00
b) Coolies 14.000 Nos. 667.00 9338.00 18418.00
Materials Cement 0.612 mt 15940.00 9755.28
Sand 0.430 Cub M 2787.12 1198.46 10953.74
Actual rate 29371.74
Rate 15% contractor's overhead 4405.76
Per sqm. Per sft. Total 33777.50
293.72 27.30

157. Flush ruled pointing works in 1:2 c/s mortar on random rubble masonry work (for 100 sq.m/1075.8 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 10.000 Nos. 908.00 9080.00
b) Coolies 14.000 Nos. 667.00 9338.00 18418.00
Materials Cement 0.408 mt 15940.00 6503.52
Sand 0.570 Cub M 2787.12 1588.66 8092.18
Actual rate 26510.18
Rate 15% contractor's overhead 3976.53
Per sqm. Per sft. Total 30486.71
265.10 24.64

157. Flush ruled pointing works in 1:3 c/s mortar on random rubble masonry work (for 100 sq.m/1075.8 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 10.000 Nos. 908.00 9080.00
b) Coolies 14.000 Nos. 667.00 9338.00 18418.00
Materials Cement 0.306 mt 15940.00 4877.64
Sand 0.630 Cub M 2787.12 1755.89 6633.53
Actual rate 25051.53
Rate 15% contractor's overhead 3757.73
Per sqm. Per sft. Total 28809.25
250.52 23.29

158. Flush ruled pointing works in 1:3cement sand mortar on ashlar masonry work (for 100 sq.m/1075.8 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 8.000 Nos. 908.00 7264.00
b) Coolies 10.000 Nos. 667.00 6670.00 13934.00
Materials Cement 0.110 mt 15940.00 1753.40
Sand 0.200 Cub M 2787.12 557.42 2310.82
Actual rate 16244.82
Rate 15% contractor's overhead 2436.72
Per sqm. Per sft. Total 18681.55
162.45 15.10

164. Pointing works in 1:3cement sand mortar on 45x45cm flagstone paving (for 100 sq.m/1075.8 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 5.000 Nos. 908.00 4540.00
b) Coolies 5.000 Nos. 667.00 3335.00 7875.00
Materials Cement 0.042 mt 15940.00 669.48
Sand 0.030 Cub M 2787.12 83.61 753.09
Actual rate 8628.09
Rate 15% contractor's overhead 1294.21
Per sqm. Per sft. Total 9922.31
86.28 8.02

_______________
____________ _______________
Approved By
Prepared By Checked By
Rate Analysis

165. Pointing works in 1:1cement sand mortar on telia bricks (for 100 sq.m/1075.8 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 10.000 Nos. 908.00 9080.00
b) Coolies 10.000 Nos. 667.00 6670.00 15750.00
Materials Cement 0.150 mt 15940.00 2391.00
Sand 0.100 Cub M 2787.12 278.71 2669.71
Actual rate 18419.71
Rate 15% contractor's overhead 2762.96
Per sqm. Per sft. Total 21182.67
184.20 17.12

166. 3mm Lime flushing plaster works (for 100 sq.m/1075.8 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 10.000 Nos. 908.00 9080.00
b) Coolies 10.000 Nos. 667.00 6670.00 15750.00
Materials Lime 0.160 cum 16800.00 2688.00 2688.00
Actual rate 18438.00
Rate 15% contractor's overhead 2765.70
Per sqm. Per sft. Total 21203.70
184.38 17.14

167. 3mm cement flushing plaster works (for 100 sq.m/1075.8 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 10.000 Nos. 908.00 9080.00
b) Coolies 10.000 Nos. 667.00 6670.00 15750.00
Materials Cement 0.518 mt 15940.00 8256.92 8256.92
Actual rate 24006.92
Rate 15% contractor's overhead 3601.04
Per sqm. Per sft. Total 27607.96
240.07 22.32

_______________
____________ _______________
Approved By
Prepared By Checked By
Rate Analysis

M. Water Proofing Works

168. 2 cm thick DPC in 1:2 C/S with Water Proofing Compound (WPC) (for rate analysis 10sq.m/ 107.58 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 0.750 Nos. 908.00 681.00
b) Coolies 0.800 Nos. 667.00 533.60 1214.60
Cement 0.135 MT 15940.00 2151.90
Materials Sand 0.180 cum 2787.12 501.68
WPC 2.700 Kg 289.00 780.30 3433.88
Actual rate 4648.48
Rate 15% contractor's overhead 697.27
Per sqm. Per sft. Total 5345.75
464.85 43.21

169. 2.5 cm thick DPC in 1:1.5:3 concrete with Water Proofing Compound (WPC) (for rate analysis 10sq.m/ 107.58 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.000 Nos. 908.00 908.00
b) Coolies 1.250 Nos. 667.00 833.75 1741.75
Cement ### MT 15940.00 1793.25
Materials Sand 0.113 cum 2787.12 314.94
12 mm aggregate 0.250 cum 2716.56 679.14
WPC 2.250 Kg 289.00 650.25 3437.58
Actual rate 5179.33
Rate 15% contractor's overhead 776.90
Per sqm. Per sft. Total 5956.23
517.93 48.14

_______________
____________ _______________
Approved By
Prepared By Checked By
Rate Analysis

170. One coat Bitumenous paint on DPC and sand covering (for rate analysis 10sq.m/ 107.58 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 0.000 Nos. 908.00 0.00
b) Coolies 0.600 Nos. 667.00 400.20 400.20
Bitumen 10.000 Kg 68.00 680.00
Materials Sand 0.020 cum 2787.12 55.74
Fire wood 30.000 Kg 20.00 600.00 1335.74
Actual rate 1735.94
Rate 15% contractor's overhead 260.39
Per sqm. Per sft. Total 1996.33
173.59 16.14

171. One Layer 500 Gauge polythene sheet for DPC (for rate analysis 10sq.m/ 107.58 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 0.600 Nos. 908.00 544.80
b) Coolies 0.600 Nos. 667.00 400.20 945.00
Materials Polythene sheet 11.000 Sqm 30.00 330.00 330.00
Actual rate 1275.00
Rate 15% contractor's overhead 191.25
Per sqm. Per sft. Total 1466.25
127.50 11.85

172. One coat tar felt works with sand (for rate analysis 10sq.m/ 107.58 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.100 Nos. 908.00 998.80
b) Coolies 3.500 Nos. 667.00 2334.50 3333.30
Bitumen 15.000 Kg 68.00 1020.00
Materials Sand 0.310 cum 2787.12 864.01
Tar Felt 11.000 sqm 120.00 1320.00
Fire wood 60.000 Kg 20.00 1200.00 4404.01
Actual rate 7737.31
Rate 15% contractor's overhead 1160.60
Per sqm. Per sft. Total 8897.90
773.73 71.92

173. Two coat tar felt works with sand (for rate analysis 10sq.m/ 107.58 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 2.300 Nos. 908.00 2088.40
b) Coolies 4.600 Nos. 667.00 3068.20 5156.60
Bitumen 25.000 Kg 68.00 1700.00
Materials Sand 0.310 cum 2787.12 864.01
Tar Felt 22.000 sqm 120.00 2640.00
Fire wood 80.000 Kg 20.00 1600.00 6804.01
Actual rate 11960.61
Rate 15% contractor's overhead 1794.09
Per sqm. Per sft. Total 13754.70
1196.06 111.18

_______________
____________ _______________
Approved By
Prepared By Checked By
Rate Analysis

174. One coat damp Proof grade tar felt works with sand (for rate analysis 10sq.m/ 107.58 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 2.350 Nos. 908.00 2133.80
b) Coolies 4.600 Nos. 667.00 3068.20 5202.00
Bitumen 17.000 Kg 68.00 1156.00
Materials Sand 0.310 cum 2787.12 864.01
Tar Felt 11.000 sqm 120.00 1320.00
Fire wood 60.000 Kg 20.00 1200.00 4540.01
Actual rate 9742.01
Rate 15% contractor's overhead 1461.30
Per sqm. Per sft. Total 11203.31
974.20 90.56

175. Two coat damp Proof grade tar felt works with sand (for rate analysis 10sq.m/ 107.58 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 3.500 Nos. 908.00 3178.00
b) Coolies 11.700 Nos. 667.00 7803.90 10981.90
Bitumen 27.000 Kg 68.00 1836.00
Materials Sand 0.310 cum 2787.12 864.01
Tar Felt 22.000 sqm 120.00 2640.00
Fire wood 80.000 Kg 20.00 1600.00 6940.01
Actual rate 17921.91
Rate 15% contractor's overhead 2688.29
Per sqm. Per sft. Total 20610.19
1792.19 166.59

176. One coat rain seal or equivalent painting works (for rate analysis 1sq.m/ 10.758 sft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 0.162 Nos. 908.00 147.10
b) Coolies 0.540 Nos. 667.00 360.18 507.28
Materials Rain seal paint 0.245 Ltr 673.00 164.89 164.89
Actual rate 672.16
Rate 15% contractor's overhead 100.82
Per sqm. Per sft. Total 772.99
672.16 62.48

N. Maintenance Work
177. Maintenance of wall in 1:6 C/S at corners with removal of old bricks (1Cum./35.28Cu ft)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 3.530 Nos. 908.00 3205.24
b) Unskilled 7.060 Nos. 667.00 4709.02 7914.26
a) Cement 0.084 M.Ton 15940.00 1338.96
b) Sand 0.360 Cub M. 2787.12 1003.36
Materials c) Bricks 560.000 Nos. 14.00 7840.00 10182.32
Actual rate 18096.58
Rate 15% contractor's overhead 2714.49
Per Cum. Per Cu ft. Total 20811.07
18096.58 512.94

178. Maintenance of wall in 1:2 lime surki with removal of old bricks at wall corners (10Cum./352.8Cu ft)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 35.280 Nos. 908.00 32034.24
b) Unskilled 70.560 Nos. 667.00 47063.52 79097.76
a) Lime 1.400 Cub M. 16800.00 23520.00
Materials b) Surki 2.800 Cub M. 1541.03 4314.88
c) Bricks 5600.000 Nos. 14.00 78400.00 106234.88
Actual rate 185332.64
Rate 15% contractor's overhead 27799.90
Per Cum. Per Cu ft. Total 213132.54
18533.26 525.32

179. One coat Enamel paintings works after linseed oil flushing (10Sqm./107.58 Sq ft)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 0.538 Nos. 908.00 488.50
b) Unskilled 0.538 Nos. 667.00 358.85 847.35
a) Linseed oil 0.538 Ltr 210.00 112.98
Materials b) Enamel 1.614 Ltr 560.00 903.84 1016.82
Actual rate 1864.17
Rate 15% contractor's overhead 279.63
Per Sqm. Per Sq ft. Total 2143.80
186.42 17.33

_______________
____________ _______________
Approved By
Prepared By Checked By
Rate Analysis

180. Dismantling of Cement Plaster and Disposing with transportation of 10m. ( 1cu.m/35.28 cft )
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: b) Unskilled 0.108 Nos. 667.00 72.04 72.04
Actual rate 72.04
Rate 15% contractor's overhead 10.81
Per Cum. Per Cu ft. Total 82.84
72.04 2.04

181. Dismantling of Tile Roof and Disposing tile/Woods with transportation of 10m. ( 1cu.m/35.28 cft )
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
a) Skilled 0.054 Nos. 908.00 49.03
Labours: b) Unskilled 0.081 Nos. 667.00 54.03 103.06
Actual rate 103.06
Rate 15% contractor's overhead 15.46
Per Cum. Per Cu ft. Total 118.52
103.06 2.92

182. Antitermite paint on wood ( 1Sqm/10.758Sqft )


Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
a) Skilled 0.220 Nos. 908.00 199.76
Labours: b) Unskilled 0.100 Nos. 667.00 66.70 266.46
Materials a)Wood preservative paint 0.245 Ltr. 244.00 59.78 59.78
Actual rate 326.24
Rate 15% contractor's overhead 48.94
Per Sqm. Per Sqft. Total 375.18
326.24 30.33

183. Dismantling of Mud mortared wall and Disposing with transportation of 10m. ( 1cu.m/35.28 cft )
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: b) Unskilled 1.060 Nos. 667.00 707.02 707.02
Actual rate 707.02
Rate 15% contractor's overhead 106.05
Per Cum. Per Cu ft. Total 813.07
707.02 20.04

184. Dismantling of Cement mortared wall and Disposing with transportation of 10m. ( 1cu.m/35.28 cft )
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: b) Unskilled 2.120 Nos. 667.00 1414.04 1414.04
Actual rate 1414.04
Rate 15% contractor's overhead 212.11
Per Cum. Per Cu ft. Total 1626.15
1414.04 40.08

_______________
____________ _______________
Approved By
Prepared By Checked By
Rate Analysis

185. Dismantling of R.C.C./R.B.C. and Disposing with transportation of 10m. ( 1cu.m/35.28 cft )
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: b) Unskilled 11.000 Nos. 667.00 7337.00 7337.00
Actual rate 7337.00
Rate 15% contractor's overhead 1100.55
Per Cum. Per Cu ft. Total 8437.55
7337.00 207.96

186. Dismantling of P.C.C. and Disposing with transportation of 10m. ( 1cu.m/35.28 cft )
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: b) Unskilled 4.000 Nos. 667.00 2668.00 2668.00
Actual rate 2668.00
Rate 15% contractor's overhead 400.20
Per Cum. Per Cu ft. Total 3068.20
2668.00 75.62

O. (Iron) Steel Work


187. 3 x 20mm Metal Grill including manufacturing, fitting, painting with Aluminium paint, sand papering all complete
for 10 sq.m/107.58 sft.
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Materials Metal grill
3 x 20mm size 10.000 sq.m 1790.95 17909.50 17909.50
Actual rate 17909.50
Rate 15% contractor's overhead 2686.43
Per sqm. Per sft. Total 20595.93
1790.95 166.48

188. 216. 4.5 x 20mm Metal Grill including manufacturing, fitting, painting with Aluminium paint, sand papering all complete
for 10 sq.m/107.58 sft.
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Materials Metal grill
4.5 x 20mm size 10.000 sq.m 3220.70 32207.00 32207.00
Actual rate 32207.00
Rate 15% contractor's overhead 4831.05
Per sqm. Per sft. Total 37038.05
3220.70 299.38

189. Iron tubular Truss including manufacturing, welding, supply of material, painting and fixing all complete
for 18.94 kg
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: Skilled 0.687 No. 908.00 623.80 1144.72
Unskilled 0.781 No. 667.00 520.93
Materials Black Pipe 18.940 Kg. 79.00 1496.26 1496.26
Actual rate 2640.98
Rate 15% contractor's overhead 396.15
Per kg Per kg Total 3037.13
139.44 139.44
Combined 50mmf &37.5mmf Black pipe(medium Class) with necessary nutbolts & Plates.

_______________
____________ _______________
Approved By
Prepared By Checked By
Rate Analysis

190. GI Barbed wire fencingworks (for 100 R m/328Rft.)


Labours: a) Skilled 1.076 Nos. 908.00 977.01
b) Unskilled 5.380 Nos. 667.00 3588.46 4565.47
Materials GI Barbed wire 110.000 Rm 13.57 1492.86
U-Hook 1.000 L.S. 150.00 150.00 1642.86
Actual rate 6208.33
Rate 15% contractor's overhead 931.25
Per Rm. Per rft. Total 7139.57
62.08 18.93

191. Barbed wire fencing in 75x100x2100 Saal wood posts with 5rows & two cross bracings all complete
(for 30 R m/98.4 Rft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.000 Nos. 908.00 908.00 908.00
Salwood 0.190 Cub M. 194040.00 36867.60
Materials Barbed wire 250.000 Rm 13.57 3392.86
U-Hook 77.000 Nos. 0.74 56.98 40317.44
Actual rate 41225.44
Rate 15% contractor's overhead 6183.82
Per Rm. Per rft. Total 47409.25
1374.18 418.96

P. Miscelaneous
192. M1 . Rain Water Pipe 90 mm dia. HDPE (100 RM/ 328 R Ft.)
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 4.000 Nos. 908.00 3632.00
b) Coolies 6.000 Nos. 667.00 4002.00 7634.00
Materials 90 mm dia. HDPE Pipe 110.000 R M 200.00 22000.00
Bed Fitting 1.000 L S 5.00 5.00
Clamps 1.000 L S 10.00 10.00 22015.00
Actual rate 29649.00
15% contractor's overhead 4447.35
Rate Total 34096.35
Per Rmt. Per Rft
296.49 90.39

193. M11.Concrete Hollow Block Masonry works in 1:4 cement mortar Per sq.m
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 0.250 Nos. 908.00 227.00
b) Unskilled 0.250 Nos. 667.00 166.75 393.75
16"*8"*6" hollow block 19.000 Nos. 76.00 1444.00
Cement 0.010 MT 15940.00 159.40
Materials Sand 0.040 Cub.M. 2787.12 111.48
1714.88
Actual rate 2108.63
Rate 15% contractor's overhead 316.30
Per Sq.m. Per Sq.ft. Total 2424.93
2108.63 196.15

194. M12. 50mm thick inter locking concrete block work on 50mm thick dust per 10 sq.m
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.000 Nos. 908.00 908.00
b) Unskilled 10.000 Nos. 667.00 6670.00 7578.00
Interloking block 11.000 Sq.m 534.06 5874.66
Materials Stone dust 0.710 Cub.M. 1058.40 751.46
6626.12
Actual rate 14204.12
Rate 15% contractor's overhead 2130.62
Per sqm.. Per sqft. Total 16334.74
1420.41 132.13

195. M13. 60mm thick inter locking concrete block work on 50mm thick dust per 10 sq.m
Resources Level/Type Quantity Unit Rate per Amount Total from each
Unit Resources
Labours: a) Skilled 1.000 Nos. 908.00 908.00
b) Unskilled 10.000 Nos. 667.00 6670.00 7578.00
Interloking block 11.000 Sq.m 557.28 6130.08
Materials Stone dust 0.710 Cub.M. 1058.40 751.46
6881.54
Actual rate 14459.54
Rate 15% contractor's overhead 2168.93
Per sqm. Per sqft. Total 16628.48
1445.95 134.38

_______________
____________ _______________
Approved By
Prepared By Checked By
17 !%X!% ;]=dL= ;fOhsf] ;fn sf7sf] kf]i6 tyf #ÆX#Æ ;fO{hsf] an':6/ /fvL #ÆX$Æ ;fO{hsf] ;fnsf] Xof08/]n
agfO{ h8fg ug]{ sfd .
b/ ljZn]if0fsf] nflu ( j=dL= lnOPsf]
b/ k|lt
;|f]t ;fwg tx÷lsl;d kl/df0f PsfO{ /sd k|To]s ;|f]t ;fwgsf] hDdf
PsfO{
l;kfn' 5.27 hjfg 908.00 4785.16
>lds
HofdL 0.52 hjfg 667.00 346.84 5132.00
lgdf{0f ;fdu|L ;fnsf] sf7 0.329 3=dL= 194040.00 63839.16 63839.16
jf:tljs b//]6 68971.16
b/ k|lt j=dL=sf] !%Ü 7]s]bf/ cf]e/x]8 10345.67
79316.83 Ö ?= 8812.98 k}= hDdf b/ /]6 79316.83
9

7 Water-proof and damp resistant. PREFAB WORKS


Sound insulation and absorption.

Rate for 1.5 m x 0.61 m 0.915 sq. m 9.849 sq. ft.

S.n Description Unit Quantity Rate Amount Remarks


1 Material

75 mm wallboard internal/
1.1 external layer with insulation sq. ft. 9.849 293.55 2891.17395
1.2 1.5" x 1.5" square pipe kg 12.08 100.00 1208.47
Transportation charge from
2 Kathmandu to site

75 mm wallboard internal/
external layer with insulation kg 44.60625 1.15 51.2971875

3 Installation charge for board sq. ft. 9.849 20 196.98


Pointing of wall with suitable
4 White Cement Sq m 1.83 30.00 54.9
Sub Total 4402.82
2 % power
Charge 88.06
Total 4490.88
15 % over Head 673.6320869
Grand Total 5164.51
Rate for Per Sq m 5644.28

Description of work :- Providing and installing expansion joint including all Unit:- RM
Labour necessary
Unit axilliary and incidental
Quantity works etc.Amount
rate all Remarks
A
For labour 10% of material cost 450.00
Sub total (in Rs.) 450.00
Materials
B
Expansion joint Rm 1.00 4500.00 4500.00
Sub total (in Rs.) 4500.00
Equipments
C
For T & P 3% of material cost 135.00
Sub total (in Rs.) 135.00
Total of A+B+C (in Rs.) 5085.00
Overhead 15% 762.75
Grand Total (in Rs.) 5847.75
Unit rate (in Rs.) 5847.75

1 !^ dL=dL= afSnf] /fh:yfgL dfj{n @) dL=dL= afSnf]


!!–^ !M@ efusf] l;d]G6 d;nfdf 5fkL 3f]6\g] / kflnz ;d]t ug]{ .
b/ ljZn]if0fsf] nflu !) j=dL= lnOPsf]
b/ k|lt
;|f]t ;fwg tx÷lsl;d kl/df0f PsfO{ /sd k|To]s ;|f]t ;fwgsf] hDdf
PsfO{
s_ l;kfn' 2 hjfg 908.00 1816.00
>lds
v_ HofdL 8 hjfg 667.00 5336.00 7152.00
l;d]G6 0.130 d]=6= 15940.00 2072.20
afn'jf vf]nfsf] 0.183 3=dL= 2787.12 510.04
!# dL=dL= dfj{n 11.00 j=dL= 1644.75 18092.25
lgdf{0f ;fdu|L cShflns Pl;8 0.37 s]=hL= 69.34 25.65
d}g kflnz 0.118 s]=hL= 626.17 73.88
tf/k]G6fOg 0.538 nL= 82.80 44.54
sfaf]{/08d 9'+uf cGbfhL – 120.00 20938.56
oflGqs pks/0f 3f]6\g] HofdL 13.50 hjfg 667.00 9004.50 9004.50
jf:tljs b//]6 37095.06
b/ k|lt j=dL=sf] !%Ü 7]s]bf/ cf]e/x]8 5564.25
42659.31 ?= 4265.93 k}= hDdf b/ /]6 42659.31
10
gf]6 M d]lzg k|of]u gu/L HofdL ;+Vof !#½ j9fpg] x'g] hDdf b/ ?= ==========÷========= k}= jf:tljs b//]6 ?= ===========÷===========k}=

Rate Analysis(Transportation)
Travel Time (T) for truck to be used for this activity shall be determined as follows:
T = 2 * { d1/v1 + d2/v2 + d3/v3 + …………. Dn/vn}, where d1, d2, d3 … dn and v1, v2, v3……vn are the
streches of distances to be travelled and corresponding average speeds on these streches.
Activity Nos 8.04.03 Using 8 tonne Capacity Trunk
1 . Transportation of Excavation Soil by Truck
Unit 1 m3
MOPPW : Norms for rate analysis as per standard specifications for Road and Bridge Works
Activity No. - 8.04.03, SPEC. Clause No. - 800(2)
Source Name Khola/River/ F/Y: 072/73
Lead Distance 4 Km
Description Unit Gravel Road Metallic Road Total Length
Distance from source to site KM 1 3 4
Average speed of truck KM/Hr 25 40
0.23 Hrs.

Description of Works Type Unit Quantity Remarks


A. Equipment Truck hr 0.13*(T+0.75) T= Travel Time
for Truck
0.1274
B. Labours Unskilled md 0.3

C. Materials Fuel ltr. 1.7*T T= Travel Time


for Truck
0.391
D. Cost
Description Unit Quantity Rate Amount
Truck : Travel Time hr 0.13 0.00 0.00
Labour md 0.3 667.00 200.10
Fuel ltr. 0.391 95.00 37.15
Actual cost per m³ 237.25
Grand Total per m³ 237.25

You might also like