Award - JMC Projects v. SDMC - 30.06.2021
Award - JMC Projects v. SDMC - 30.06.2021
Award - JMC Projects v. SDMC - 30.06.2021
1.1 The Hon’ble High Court of Delhi, in Arbitration Petition being Arb.
P. No. 632 of 2017, passed an order dated 13.08.2020 vide which it
appointed the undersigned as the Sole Arbitrator to adjudicate upon
the dispute between the Parties herein.
1.2 It would be relevant to mention here itself that when the disputes
arose between the parties, the Claimant made a request dated
06.03.2016 to the Respondent to consider its various claims raised
vide its letter dated 15.01.2016 and refer the same for adjudication
by the Disputes Resolution Committee (DRC). Such a request was
made having regard to Clause 46 of the Special Conditions of
Contract (SCC), which provides for settlement of disputes by the
DRC comprising of representatives of the Claimant and the Chief
Engineer, MCD. DRC was constituted which held the proceedings
on several dates. It gave its decision on 29.05.2017 directing the
Respondent to pay an amount of INR 69,13,247 and INR 11,15,841
along with interest @ 7.5% p.a. with effect from 24.09.2015 to the
Claimant. This order was, however, signed only by the Chief
Engineer of the Respondent as the representative of the Claimant
refused to accept the aforesaid decision and sign the same.
According to the Claimant, the disputes remained unresolved and
therefore, it sent the notice dated 03.06.2017 to the Respondent
invoking the Arbitration Agreement. The Respondent, however, did
not appoint an Arbitrator because of which the Claimant filed the
Petition under section 11(6) of the Act before the High Court. It is
in this petition, as mentioned above, the matter was referred to the
Page 2 of 133
present Arbitrator. It may be mentioned that one of the issues
raised by the Respondent in contesting the said petition was that
Clause 46 of SCC on which reliance was placed by the Claimant for
invoking arbitration, could not be construed as an Arbitration
clause. In nutshell, it was argued that there was no Arbitration
Agreement and therefore, the petition was not maintainable. This
objection was repelled by the Hon’ble High Court in its order dated
13.08.2020 while allowing the petition and constituting the present
Arbitral Tribunal.
2. ARBITRATION PROCEEDINGS
2.1 After receiving a copy of the order dated 13.08.2020 passed by the
Hon’ble High Court of Delhi, the Arbitral Tribunal issued notice
dated 25.08.2020 to the parties notifying them that the first
procedural hearing shall be conducted on 07.09.2020 at 4 p.m. It
was decided to conduct the hearing via video conferencing as
physical hearing was not possible due to Covid -19 pandemic. It may
be stated that all the hearings thereafter were also conducted in
virtual mode upto the stage of final arguments, with the consent of
the parties.
Page 3 of 133
2.2 In the procedural hearing held on 07.09.2020, the time table for
completion of pleadings was fixed. The procedure for conduct of the
arbitral proceedings was also laid down in consultation with the
learned Counsel for the parties. The Arbitrator also gave
declaration under Section 12 of the Arbitration and Conciliation Act
1996 (the Act). On the completion of pleadings, second procedural
hearing was conducted on 23.11.2020.
2.4 The Counsel for the parties had requested for three weeks time to
file their written submissions as well which opportunity was
granted. The Respondent submitted its written arguments vide e-
mail dated 07.04.2021 and the Claimant filed its written
submissions on 08.04.2021. Here it may be mentioned that while
Page 4 of 133
reserving the Award, the Arbitral Tribunal directed the parties to
deposit the balance arbitral fee within three weeks. However, this
fee was not deposited for substantial time. Vide communication
dated 14.05.2021, the Arbitral Tribunal communicated to the parties
that the Award is likely to be pronounced within May 2021 and
directed both the parties to deposit the balance fee immediately.
Without going into the details, it may be mentioned that the
Claimant, thereafter, deposited the balance fee on 21.05.2021 and
the Respondent has remitted its share of fee on 26.06.2021,
intimation whereof was given by the counsel for the Respondent on
29.06.2021. Accordingly, this Award is being pronounced.
3.1 In the Statement of Claim filed by the Claimant, it has given its own
version of factual matrix in detail. However, those facts which are
necessary for adjudication of the claims are noted while stating the
case of the Claimant.
Nature of Work
Page 5 of 133
for the work shall be made available at the time of issuance of work
order.
3.3 The Claimant submits that it had taken all the necessary steps to
mobilize the resources at site with the intention to complete the
work and achieve the desired progress as per the milestones
mentioned in the Contract. However, the work could not be executed
at the desired speed pursuant to various reasons beyond the control
of the Claimant which, inter- alia, include unavailability of full site
pursuant to Clause 13 of the ITB, which led to underutilization of
Plant and Machinery and manpower and other deployed resources
until 15.10.2015.
Page 6 of 133
3.5 When the project was underway, vide letter dated 21.10.2013 of the
Respondent, the Claimant was informed not to execute any further
work at the site as the National Green Tribunal (NGT) had passed
restraint order dated 21.10.2013 in this behalf. On various
occasions, the Claimant expressed the difficulties in commencement
of works and underutilization of resources at site, the particulars of
which may not be necessary. Suffice is to mention that upon
exchange of various correspondence between the Parties, extension
was granted until 06.07.2014. The contract was further extended
till 30.09.2014 vide letters of the Respondent dated 14.02.2014 and
30.06.2014.
3.6 The NGT by its Final Order dated 13.01.2015 held that no
construction is permissible on the drain, subject matter of the
present Contract which led the Respondent to close the Contract
under Clause 13 vide letter dated 23.09.2015. The Claimant objected
and submitted that the Respondent had failed to mitigate the losses.
Page 7 of 133
4.1 Claim No. 1: Compensation towards idling of Plants and
Machinery.
4.1.1 Claim No. 1A: Unrecovered Plant & Machinery cost due to
underutilization from 08.09.2012 to 21.10.2013.
i) The Claimant claims an amount of INR 6,56,69,160/- as dry hire
charges and underutilization of the Plant & Machinery.
ii) The Claimant submits that despite the mobilisation of Plant &
Machinery on the site, there was slow progress of works due to
the reasons attributed to the Respondent. The number of Plant
& Machinery deployed was arrived on basis of Monthly Progress
Reports. The deployed Plant & Machinery has resulted in
productivity of 22.21% and 77.79% has been stated to be the
underutilization percentage.
iii) To compute the abovementioned amount, the underutilization
percentage is multiplied with the total cost of Plant &
Machinery and is further quantified along with an interest of
12% p.a.
4.1.2 Claim No. 1B: Unrecovered cost of Plant & Machinery due to
idling in suspended period from 21.10.2013 to 15.10.2015
i) According to the Claimant, the Respondent has failed to
mitigate the losses for resources and material lying idle at the
site, hence claims an amount of INR 20,23,41,835/- as
Page 8 of 133
compensation for the period of suspension i.e., from 21.10.2013
to 15.10.2015.
ii) The quantum of compensation has been calculated on basis on
available Plant & Machinery on the Project site. It is further
quantified along with an interest of 12% p.a.
Page 9 of 133
4.3.1 Claim No.3A: Unrecovered Site Overheads during the period
from 08.09.2012 to 21.10.2013
1) The Claimant claims the unrecovered portion of Site Overheads
amounting to INR 7,77,18,414/- for this period.
2) The Claimant has computed the claim using the Emden
Formula. The average yearly Site Overhead cost of
Infrastructure division for Financial years 2012-13 and 2013-14
constituted 6.69% of the turnover achieved by Infrastructure
division. An additional time of 8.18 months was taken to
complete the work. The quantum is noted to be the difference of
total site overheads and Site overheads recovered through
actual work done along with 12% interest.
Page 10 of 133
10,59,95,234/-. The basis of Turnover and Site Overhead
expenses are the certificates issued by an Independent
Chartered Accountant.
ii) According to the Claimant, the average yearly Site Overhead
cost of Infrastructure division for Financial years 2014-15 and
2015-16 constituted 16.89% of the turnover achieved by
Infrastructure division. The computation of the claim was using
the Emden Formula, considered to be 50% of 16.89%,
amounting to 8.45%. It is further quantified along with an
interest of 12%.
The Claimant claims the costs incurred by the Regional Office and
the Head Office of the Claimant which, according to the Claimant
were to be recovered by generating revenue received upon the
execution of the work.
Page 11 of 133
Financial years 2012-13 and 2013-14 constituted 4.59% of the
turnover achieved [Head Office percentage: 3.29% and Regional
Office percentage: 1.29%]
iii) The compensation has been claimed for an additional time of
8.18 months, which, according to the Complainant was not a
time attributable to itself. The computation of the claim was
using the Emden Formula and was further quantified along
with an interest of 12%.
4.4.2 Claim No. 4B: Unrecovered Regional Office & Head Office
Overheads due to under-utilization during the period from
21.10.2013 to 19.01.2015:
i) The Claimant claims compensation under this head amounting
to INR 8,31,68,566/-. The basis of the turnover and the claimed
costs is the certificate issued by an independent Chartered
Accountant.
ii) According to the Claimant, the average yearly Regional and
Head Office Overhead cost of Infrastructure division for
Financial years 2013-14 and 2014-15 constituted 5.22% of the
turnover achieved [Head Office percentage: 3.76% and Regional
Office percentage: 1.46%]
iii) The compensation has been claimed for the suspension period
of 14.96 months, which, according to the Complainant was not
a time attributable to the itself. The computation of the claim
was using the Emden Formula, considered as 75% of 5.22%,
amounting to 3.92% and was further quantified along with an
interest of 12%.
Page 12 of 133
4.4.3 Claim No. 4C: Unrecovered Regional Office & Head Office
Overheads due to under-utilization during the period from
19.01.2015 to 15.10.2015:
i) The Claimant claims compensation under this head amounting
to INR 4,51,71,895/-. The basis of the turnover and the claimed
costs is the certificate issued by an independent Chartered
Accountant.
ii) According to the Claimant, the average yearly Regional and
Head Office Overhead cost of Infrastructure division for
Financial years 2014-15 and 2015-16 constituted 7.20% of the
turnover achieved [Head Office percentage: 4.71% and Regional
Office percentage: 2.49%]
iii) The compensation has been claimed for the suspension period
of 8.84 months, which, according to the Complainant was not a
time attributable to itself. The computation of the claim was
using the Emden Formula, considered as 50% of 7.20%,
amounting to 3.60% and was further quantified along with an
interest of 12%.
Page 13 of 133
considered as average of the profit percentage earned during the
period from FY 2009-10 to FY 2011-12 as certified by
Independent Chartered Accountant.
In totality, the Claimant has sought and prayed before the Sole
Arbitrator to pass an award in the sum of INR 91,91,23,626/-, as
revealed from an addition of the above-mentioned Claims, along
with an interest of 15% for delay in making the timely payments, as
payable from the due dates of the aforementioned amounts to the
actual date of payment.
Page 14 of 133
5. CASE OF THE RESPONDENT
5.1.2 The Respondent has also challenged the veracity of the claims filed
by the Claimant, contending the same to be not maintainable being:
unsubstantiated and uncertified. It has been submitted that the
Claimant has merely estimated the claims without any basis by
placing reliance on one chartered accountant’s certificate and
balance sheets, for which, no evidence, proof of actual payment has
been shown. The Claimant fails to follow the procedure provided in
the Contract for certification. Apart from contending the above, the
Respondent also submits that almost all men and machinery was
removed by the Claimant after the order dated 21.10.2013 of the
NGT.
5.1.3 The Respondent submits that the Claimant has itself failed to meet
the prescribed milestones and the uncompleted work cannot be
attributed to the Respondent. In this behalf, the Respondent has
referred to Schedule F of the Tender which prescribed the Table of
Page 15 of 133
Milestones that were to be achieved by the specific dates and the
same reads as under :
Sl. Financial Time allowed Amount to be withheld in case of non-
No. Progress (from date of achievement of Milestone
start
1. 1/8th (of 1/4th (of whole In the event of not achieving the
whole work) work) necessary progress as assessed from the
2. 3/8th (of 1/2nd (of whole running payment, 1% of the tendered
whole work) work) value of work will be withheld for failure
3. 3/4th (of 3/4th (of whole of each mile stone. The withheld amount
whole work) work) may be released against bank guarantee/
4. Full Full FDR of the equal amount.
The Respondent also contends that in light of the stay order passed
by the NGT, according to the Respondent when no work was carried
out and there was no labour or staff deployed on sites and that the
Claimant has failed to mitigate the losses and unrequired expenses.
5.1.4 Apart from submissions challenging the merits and the jurisdiction,
the Respondent also challenges the permissibility of some claims as
being barred by limitation, by effect of not mentioning in the notice
of arbitration dated 03.06.2017, and by being blown out of proportion
in their quantification.
5.1.5 The Respondent also brings to the Tribunal’s notice that time is of
essence of the Contract as per Clause 40 of ITB and Clause 5 of GCC.
The Respondent further highlights that the Claimant has failed to
substantiate the reasons for delay.
Page 16 of 133
5.1.7 The Respondent has also given its detailed version/reply to each of
the claims. As those aspects were pointed out at the time of
arguments, the same would be taken note of while analysing the
claims.
Page 17 of 133
Interest at the rate of 10% p.a. from 69,26,027/-
01.12.2012 to 15.10.2013 on 1st
Mobilisation Advance [C]
Interest at the rate of 10% p.a from 50,75,342/-
04.01.2013 to 15.10.2013 on 2nd
Mobilisation Advance [C]
d) 20.03.2017 4th RA Bill Net amount of 4th RA Bill [1] 4,21,37,206/-
Balance amount of mobilisation advance 11,33,73,326/-
upto 3rd RA Bill [2]
Amount Recovered on respect of the 1,51,06,827/-
Mobilisation Advance [3]
Interest at the rate of 10% p.a. from 1,86,367/-
16.10.2013 to 21.10.2013 on 1st
Mobilisation Advance [4]
Net amount 1-3-4 [5] 2,68,44,012/-
Balance mobilisation advance to be 9,82,66,499/-
recovered from the contractor as on
20.03.2017 (11,33,73,326-1,51,06,827) [6]
Balance amount to be recovered from 7,14,22,487/-
contractor after considering 4th RA Bill
INR 9,82,66,499-2,68,44,012 [7]
Interest for the period 21.10.2013 to 2,44,02,683/-
20.03.2017 ie 41 months on 1st Mobilisation
Advance [8]
Total amount due towards the contractor 9,58,25,170/-
as on 20.03.17 [9]
e) Principal Amount of outstanding Mobilisation Advance 7,14,22,487/-
f) Interest at the rate of 10% p.a. from 21.10.2013 to 20.10.2020 on 4,99,95,741/-
Outstanding Mobilisation Advance [H]
CUMULATIVE AMOUNT OUTSTANDING [G+H] 12,14,18,228/-
Page 18 of 133
7. RELEVANT CONTRACTUAL PROVISONS
Page 19 of 133
10.03.2014, which means that the contract period was 18 months
when counted from the date of LOA i.e., 14.08.2012.
Clauses of Contract:
General Conditions of Contract (GCC):
ii. The Performance Guarantee shall be initially valid upto the stipulated
date of completion plus 60 days beyond that. In case the time for
completion of work gets enlarged, the contractor shall get the validity of
Performance Guarantee extended to cover such enlarged time for
completion of work. After recording of the completion certificates for the
work by the competent authority, the Performance Guarantee shall be
returned to the contractor, without any interest.
Page 20 of 133
iii. The Engineer-in-Charge shall not make a claim under the Performance
Guarantee except for amounts to which the Commissioner, MCD is
entitled under the contract (notwithstanding and/or without prejudice to
any other provisions in the contract agreement) in the event of :
a) Failure by the contractor to extend the validity of the Performance
Guarantee as described hereinabove, in which event the Engineer-
in-Charge may claim the full amount of the Performance Guarantee;
b) Failure by the contractor to pay Commissioner, MCD any amount
due, either as agreed by the contractor or determined under any of
the Clause/conditions of the agreement, within 30 days of the service
of notice of this effect by Engineer-in-Charge.
This will also apply to items or group of items for which a separate period of
completion has been specified:
Provided always that the total amount of compensation for delay to be paid
under this Condition shall not exceed 10% of the Tendered Value of work or
of the Tendered Value of the item or group of items of work for which a
separate period of completion is originally given.
Page 21 of 133
milestone missed subsequently also shall be withheld. However, no interest,
whatsoever, shall be payable on such withheld amount.
The time allowed for execution of the works as specified in Schedule-F or the
extended time in accordance with these conditions shall be the essence of the
Contract. The execution of the works shall commence from such time period
as mentioned in Schedule-F or from the date of handing over of the site,
whichever is later. If the Contractor commits default in commencing the
execution of the work as aforesaid, MCD shall without prejudice to any other
right or remedy available in law, be at liberty to forfeit the earnest money
absolutely.
5.1 As soon as possible, after the Contract is concluded, the Contractor shall
submit a Time and Progress Chart for each milestone and get it
approved by the Department. The chart shall be prepared in direct
relation to the time stated in the Contract documents for completion of
items of the works. It shall indicate the forecast of the dates of
commencement and completion of various trades of sections of the work
and may be amended as necessary by agreement between the Engineer-
in-Charge and the Contractor within the limitations of time imposed in
the Contract documents, and further to ensure good progress during the
execution of the work, the contractor shall in all cases in which the time
allowed for any work, exceeds one month (save for special jobs for which
a separate programme has been agreed upon) complete the work as per
milestones given in Schedule-F.
Page 22 of 133
v. Delay on the part of other contractors or tradesmen engaged by
Engineer-in-Charge in executing work not forming part of the
Contract; or
vi. Non-availability of stores, which are the responsibility of MCD
to supply; or
vii. Non-availability or breakdown of tools and Plant to be supplied
or supplied by MCD; or
viii. Any other cause, which, in the absolute discretion of the
Engineer-in-Charge is beyond the Contractor’s control.
Then, upon the happening of any such event causing delay, the
contractor shall immediately give notice thereof in writing to the
Engineer-in-Charge but shall nevertheless use constantly his best
endeavours to prevent or make good the delay and shall do all that
may be reasonably required to the satisfaction of the Engineer-in-
Charge to proceed with the works.
5.4 In any such case, the Engineer-in-Charge may give a fair and
reasonable extension of time and re-schedule the milestones for
completion of work. Such extension shall be communicated to the
Contractor by the Engineer-in-Charge in writing, within three months
of the date of receipt of such request. Non-application by the contractor
for extension of time shall not be a bar for giving a fair and reasonable
extension by the Engineer-in-Charge and this shall be binding on the
contractor.”
Page 23 of 133
Plant machinery and Shuttering Material Advance
(iv) The mobilization advance and Plant and Machinery Advance in (ii) and
(iii) above bear simple interest at the rate of 10 per cent per annum and
shall be calculated from the date of payment to the date of recovery,
both days inclusive on the outstanding amount of advance. Recovery of
such sums advanced shall be made by the deduction from the
Contractor’s bills commencing after first ten per cent of the gross value
of the work is executed and paid, on pro rate percentage basis to the
gross value of the work bills beyond 10% in such a way that the entire
advance is recovered by the time eight percent of the gross value of the
Contract is executed and paid, together with interest due on the entire
outstanding amount upto the date of recovery of the authorized.
“The Contractor shall execute the whole and every part of the work in
the most substantial and workmanlike manner both as regards
materials and otherwise in every respects in strict accordance with the
specifications. The Contractor shall also conform exactly, fully and
faithfully to the design, drawings and instructions in writing in respect
of the work signed by the Engineer-in-Charge and the Contractor shall
be furnished free of charge one copy of the contract documents together
with specifications, design, drawings and instructions as are not
included in the standard specifications of Central Public Works
Department specified in Schedule-F or in any Bureau of Indian
Standards or any other, published standard or code or schedule of rates
or any other printed publications referred to elsewhere in the contract.”
If, at any time, after acceptance of the tender, Government shall decide
to abandon or reduce the scope of the work for any reason whatsoever
and hence not require the whole or any part of the works to be carried
out, the Engineer-in-Charge shall give notice in writing to that effect to
the Contractor and the Contractor shall act accordingly in the matter.
The Contractor shall have no claim to any payment of compensation or
otherwise whatsoever, on account of any profit or advantage which he
might have derived from the execution of the works in full but which he
did not derive in consequences of the foreclosure of the whole or part of
the works. The Contractor shall be paid at contract rates, full amount
for works executed at site and, in addition a reasonable amount as
certified by the Engineer-in-Charge for the items hereunder mentioned
which could not be utilized on the work to the full extent in view of the
foreclosure:
Page 24 of 133
i) Any expenditure incurred on preliminary site work, e.g., temporary
access roads, temporary labour huts, staff quarters and site office;
storage accommodation and water storage tanks;
ii) Government shall have the option to take over Contractor’s materials
or any part thereof either brought to site or of which the Contractor is
legally bound to accept delivery from suppliers (for incorporation in or
incidental to the work) provided, however, Government shall be
bound to take over the materials or such portions thereof as the
Contractor does not desire to retain. For materials taken over or to
be taken over by Government, cost of such materials as detailed by
Engineer-in-Charge shall be paid. The cost shall, however, take into
account purchase price, cost of transportation and deterioration or
damage which may have been caused to materials whilst in the
custody of the Contractor.
iii) If any material supplied by MCD are rendered surplus, the same
except normal wastage shall be returned by the contractor to MCD at
rates not exceeding those at which these were originally issued, less
allowance for any deterioration or damage which may have been
caused whilst the materials were in the custody of the contractor. In
addition, cost of transporting such materials from site to MCD stores,
if so required by MCD, shall be paid.
The reasonable amount of items on (i), (iv) and (v) above shall not be
in excess of 2% of the cost of the work remaining incomplete on the
date of closure i.e., total stipulated cost of the work as per accepted
tender less the cost of work actually executed under the Contract and
less the cost of Contractor’s materials at site taken over by the MCD
as per item (ii) above. Provided always that against any payments
due to the Contractor on this account or otherwise, the Engineer-in-
Charge shall be entitled to recover or be credited with any
outstanding balances due from the contractor for advance paid in
respect of any tool, plants and materials and any other sums which at
the date of termination were recoverable by the MCD from the
Contractor under the terms of the contract.
Page 25 of 133
Clause 15: Suspension of work
ii) If the suspension is ordered for reasons (b) and (c) in sub-para(i)
above:
Page 26 of 133
shall within ten days of expiry of such period of 15 days give notice in
writing of his intention to the Engineer-in-Charge. If the event of the
contractor treating the suspension as an abandonment of the contract
by MCD, he shall have no claim to payment of any compensation on
account of any profit or advantage which he might have derived from
the execution of the work in full but which he could not derive in
consequence of the abandonment. He shall, however, be entitled to
such compensation as the Engineer-in-Charge may consider
reasonable, in respect of salaries and/or wages paid by him to his
employees and labour at site, remaining idle in consequences adding
to the total thereof 2% to cover indirect expenses of the contractor
provided the contractor submits his claim supported by details to the
Engineer-in-Charge within 30 days of the expiry of the period of three
months.
Page 27 of 133
“14. The Contractor will not have any claim in case of any delay by
the Engineer-in-Charge in removal of trees or shifting, raising,
removing of telegraph,m telephone or electric lines (over head or
underground), water and sewer lines and other structures etc., if any,
which may come in the way of the work. However, suitable extension
of time will be granted to cover such delays.”
Equipment capabilities
Undertaking
I, the undersigned, do hereby undertake that our firm M/s.............
shall deploy all plants and machinery/equipment required for
implementation of the project as per technical specifications. I also
undertake to either own or have assured access through hire or
lease all the plant and machinery/equipment.
................................................
Signed by an Authorised Officer of the Firm
................................................
Title of Officer
................................................
Name of Firm
................................................
Date
Personnel capabilities
Undertaking
I, the undersigned, do hereby undertake that our firm M/s.............
shall make provision for suitably qualified personnel to carry out
the work, namely........................... as required during contract
implementation.
................................................
Signed by an Authorised Officer of the Firm
Page 28 of 133
................................................
Title of Officer
................................................
Name of Firm
................................................
Date
8. TRIBUNAL’S ANALYSIS
8.1 Before coming to the discussion on each of the Claims and Counter-
Claims preferred by the parties, it would be necessary to deal with
some of the preliminary aspects which have been raised by the
Respondent.
Preliminary submissions
8.2 As already noticed while mentioning the case of the Respondent, the
Respondent argues that there is no valid arbitration clause in the
contract. Therefore, the Tribunal has not been constituted
appropriately.
8.3 Though detailed submissions are made by the parties in this behalf,
and the Respondent has referred to a judgment of the Supreme
Court as well [Jagdish Chander v. Ramesh Chander (2007) 5 SCC
719], it may not be necessary to go into this aspect in detail because
of the simple reason that this issue in the present case, inter-parties,
stands settled by the highest court. It is reiterated that this very
contention was taken by the Respondent before the Hon’ble High
Page 29 of 133
Court while contesting the application of the Claimant under
Section 11 of the Act i.e., appointment of an Arbitrator. The
contention was specifically turned down by the High Court giving
detailed reasons which can be found in paragraphs 27 to 40 of the
High Court’s order dated 13.08.2020. The Respondent challenged
the said decision by filing a Special Leave Petition before the Hon’ble
Supreme Court, which was also dismissed vide order dated
05.01.2021. The operative part of the order reads as under:
“In view of the above, we see no reason to interfere with the impugned
order passed by the High Court.
Page 30 of 133
2. Onus to prove breach of contract by the Respondent on
Claimant: Aspects of Delay
8.6 As can be seen from the above, the proposition is predicated on the
submission that there is no fault on the part of the Respondent and
the Respondent has not committed any breach of contract. Further,
the Claimant has not been able to show such a breach on the part of
the Respondent. The argument is in two parts. In the first place, it
is mentioned that before awarding the contract to the Claimant, all
necessary permissions were taken from the concerned authorities
and on that basis, it is submitted that there is no failure on the part
of the Respondent in discharging its obligations under the contract.
The submission is that the work was halted at the direction of the
NGT for which the Respondent cannot be faulted with. Second limb
of the argument is that during the period when there was no stay,
the Claimant is to be blamed for slow progress of work.
Page 31 of 133
8.7 The case set up by the Claimant, on the other hand, is that breaches
of the Respondent are two-fold. In the first phase i.e., before the
order of the NGT, delay occurred because of various reasons which
are attributed to the Respondent, which amounts to breach of the
contract. Secondly, the NGT order clearly shows that the
Respondent had failed to comply with various legal formalities
which led to stoppage of the work.
8.8 Mr. Datta, Learned Senior counsel appearing for the Claimant
structured his submissions with the statement that having regard
to the event that took place during the execution of the contract, the
entire period could be bifurcated in two parts as under :
• First Period – From the commencement date till Interim
order dated 21.10.2013 passed by the National Green
Tribunal (NGT);
8.9 Mr. Datta pointed out that during the First period, which consists of
thirteen and a half months (approx.) [as against 18 months of
contractual period], only 16% of the work could be completed.
According to him, the delay in the completion of work was entirely
attributed to the Respondent, which failed to fulfil its obligations
under the contract. In this behalf, it was argued that the following
were the fundamental breaches attributable to the Respondent:
a) Delay in supplying the drawings by the Respondent to the
Claimant to enable the Claimant to execute the work;
b) Encroachments at Site;
c) Delay in seeking permissions from other Authorities which
were required for execution of the work.
Page 32 of 133
encroachments at site were concerned, attention of the Tribunal was
drawn to letters at pages 322, 323 and 324. It was argued that the
Respondent accepted the delay on its part as extension of time was
sought vide letter dated 06.03.2013 stating as many as eleven
reasons which were all attributed to the Respondent. It was
specifically mentioned therein that all these reasons for delay had
been recorded by the concerned officers from time to time. In this
letter, it was also mentioned that though there is a provision of
deducting/withholding 1% from the Running Bill on account of non-
achieving of the financial progress, request was made not to resort
to that provision as delays were not attributable to the Claimant.
Along with that letter, the Claimant had enclosed copy of
communication dated 02.03.2013 addressed by Deputy Director
(Horti.) Horticulture Division VI to Executive Engineer (Project-I)
wherein attention was drawn to the letter dated 31.01.2013 of the
Executive Engineer seeking temporary permission to access the site
for four months for undertaking the aforesaid work and by this
letter, the permission was granted on certain conditions. It was thus
pointed out that this permission came only in March 2013.
8.11 He also argued that while taking decision on the extension of time,
it was recorded by the concerned officials of the Respondent that the
delay in execution of the work leading to slippage of milestone may
not be completely attributed to the Contractor, which is clear from
its text as under:
“Municipal Corporation of Delhi
Page 33 of 133
The subject work was awarded to M/s. JMC Projects (India) Limited by
South Delhi Municipal Corporation (SDMC) vide Letter of Acceptance
(LOA) No. D/EE(Pr)-I/CNZ/12-13/383 dated 18.08.2012 and
subsequently, the contract agreement for the said project was executed
on 24.09.2012 with time of completion of project as 18 months. As per
contract, the date of start and date of completion of the project are
08.09.12 and 07.03.14 respectively.
Page 34 of 133
Submitted please.
Sd/- 8.3.2013
AE(Pr)-II Div Pr-I/CNZ”
Page 35 of 133
4) Delay and financial loss due to obstruction created by DDA in the major
part of the scope;
5) Non-availability of site for batching plant/yard for steel, cement and other
material;
6) Delay due to non-availability of clear site-other contractor work;
7) Delay in deployment of third party/inspecting agency;
8) Non-availability of drawing for parallel work-Road/Drain,etc.
9) Delay in shifting of utilities;
10) Clearance and handing over of piecemeal front;
11) Unpredicted heavy pre-monsoon rain and extended monsoon period.
8.13 This letter was replied to by the Respondent vide its communication
dated 23.12.2013, inter-alia, stating that in general, the so called
hindrances mentioned prior to 14.06.2013 did not appear to be
hindrances on a particular stretch and that could not be a reason to
stop the work on the entire stretch of drain which was about 4.5 km
long and there were sufficient work fronts where work could be
taken up. As per the Respondent, the Claimant had not executed
the work even on the work fronts which were available, which
showed that the Claimant was not having either sufficient resources
or manpower. With regard to the hindrances pointed out by the
Claimant, some of these were refuted in the following manner:
“As per terms and conditions of the contract, the arrangement of site for
batching plant was to be arranged in the vicinity of the site by yourself.
SDMC was only to facilitate in this regard in case any site is available
with the SDMC. However, sole responsibility was yours to install the
batching plant. However, SDMC, keeping in view the progress of work
is not hindered, has allowed to procure the cement concrete from other
plants.
Page 36 of 133
The rain is very common environmental phenomena and it is expected
in the period of rainy weather. From the available record, it has been
seen that the work was not hindered in any abnormal manner due to
rains and the work has also been executed June-13 to October-12 except
few days.
Regarding slow progress of work, this office vide letter No. D/EE(Pr.)-
II/CNZ/13-14/314 dt. 02.09.13 has also informed you to expedite teh
work but no fruitful result was achieved. In spite of completion of 11
months time, the progress of work is about 15%; however, upto this
period, proportionate physical progress of the work should be 60%
approximately.”
8.14 Mr. Datta attempted to meet the averment in the aforesaid letter of
the Respondent by relying upon the Hindrance Register which is
signed by representatives of both the parties and inter-alia records
as under. He pointed out that the Hindrance Register clearly records
hindrances of following nature at certain areas/chainages and
mentioned the period during which the hindrances remained. He
stated that for certain period, work could not be executed as it was
stopped by DDA. Hindrance was also caused due to existence of
trees on a particular chainage.
• Chainage 1772 to 3055 – DDA had stopped the work on
25.07.2013 which position remained till 14.08.2013 and
because of this, no work could be executed during this
period.
On that basis, it was argued that actual site available for the work
was negligible.
8.15 The Ld. Senior Counsel also pointed out the extensions which were
granted from time to time were without the levy of Liquidated
Damages and submitted that this shows that the Respondent
accepted the delays were not on account of alleged slow progress of
Page 37 of 133
work on the part of the Claimant. Vide letter dated 14.02.2014,
extension was granted upto 06.07.2014, vide letter dated 30.06.2014,
extension was granted upto 30.09.2014.
8.17 Insofar as the Second period from 21.10.2013 i.e., from the date
when the stay order by NGT came to be passed till the closure of the
contract on 23.09.2015 is concerned, there is hardly any dispute on
facts. After the said stay order was passed, it was communicated by
the Respondent to the Claimant on the same day, and the Claimant
was directed not to execute any further work at site. The Claimant,
vide letter dated 29.10.2013, requested the Respondent to throw
light on the type and nature of the order issued by NGT so as to aid
the Claimant in assessing its effects on the project. It was also
stated that there was no clarity in respect of direction not to carry
out further work at site viz., whether it was time bound and/or
subject to official procedure of the Tribunal. The Claimant also
requested that it be conveyed the expected outcome of the case in
terms of timelines. This letter concluded with the following
assertion:
Page 38 of 133
is a crucial factor of any Contract. Also, we cannot suffer unwarranted
costs as well as loss of time for no fault of ours and reasons which are
beyond our control.
8.18 The position about the case is mentioned in the letter dated
20.11.2013 addressed by Respondent in which the Respondent
informed its officers that a petition had been filed titled as Manoj
Kumar Mishra and Anr v. Union of India and Anr, before National
Green Tribunal in which Status Quo order had been passed by the
Tribunal. It was also informed that the matter was listed on
19.11.2015 when NGT desired a comprehensive report dealing with
Peak Storm Drainage, modified catchment area, percentage of open
area, land-use and channel design parameters and treatment, if any,
being provided to discharge made from these drains to River
Yamuna. NGT had also asked the Respondent as to whether it had
taken approval from the State Environmental Impact Assessment
Authority or Delhi Pollution Control Committee for carrying out this
work. The officials were asked to hand over the record so that the
Tribunal is informed accordingly.
Page 39 of 133
complete the work beyond the originally stipulated date of
completion. Vide another letter dated 28.11.2013, the Claimant
submitted complete list of the resources in the form of Plant and
Machinery as well as manpower which were lying idle. It also made
a specific request to the Respondent to respond as to whether
Claimant should demobilise these resources. This requested was
repeated by another letter dated 13.12.2013, inter-alia, stated as
under :
We also state that we shall continue to notify and claim the accruing
damages on account of the stoppage of works, without prejudice to our
entitlements under the Contract.
Page 40 of 133
mobilization advances and as such, second instalment of
mobilization advance was to be recovered as per the order of the
Chief Engineer already conveyed to the Claimant. It also mentioned
that the Claimant had not deployed proper machinery inputs which
had resulted in slow progress of work from 14.06.2013 to 21.10.2013.
It categorically stated that the deployment of machinery and
manpower which was allegedly shown was wrong and had not been
deployed. Insofar as resumption of work is concerned, it was pointed
out that the same could be done only after vacation of the stay order
by NGT.
8.22 The Claimant by another letter dated 31.12.2013, reiterated that the
suspension of work was causing substantial financial burden on the
Claimant due to idling of manpower and machinery deployed at the
site. This position was reiterated by the Claimant in subsequent
letter dated 01.12.2014, reiterating the plea that the Claimant
would be entitled to the damages on account of delay that was being
caused. Thereafter, by letter dated 05.06.2014, the Claimant even
requested the Respondent to foreclose the contract as the Status Quo
order of NGT was continuing for a long period. This request was
reiterated vide letters dated 21.07.2014, 13.08.2014 and 19.09.2014.
However, the Respondent did not take any action on these requests
as, perhaps, it wanted to wait for the outcome of the NGT
proceedings. NGT passed final order dated 19.01.2015 banning the
execution of the said project permanently. It is only thereafter, the
Respondent processed the matter and more than eight months from
the passing of the final order of the NGT, it decided to foreclose the
contract which decision was conveyed by the Respondent to the
Claimant vide letter dated 23.09.2015.
Page 41 of 133
8.23 From the aforesaid events mentioned in respect of the two periods,
it can be discerned that the parties are at variance on the following
two aspects :
Page 42 of 133
total period of the contract i.e., 18 months, the Claimant had worked
for a period of 13.40 months. But, it could only get completed
16.48% of the work, which shows slow progress of the work at the
instance of the Claimant.
8.26 The Respondent argued that the Claimant’s entire arguments for
failing in completion of work within the milestones prescribed under
the Contract are based upon the hindrance register reported to the
Respondent. However, the Claimant ignored that as per the tender
conditions, the Claimant was supposed to inspect the site and thus,
was fully aware about the hindrances existing on the ground, even
before submitting the bid for the work/project (Clause 15 of
Instructions to Bidder). On this premise, it is argued that the claims
of the Claimant in respect of losses suffered due to hindrances are
not acceptable. Commenting upon the Hindrance Register, the
learned counsel for the respondent argued that none of the
hindrances referred in the Hindrance Register could be attributed
solely to the Respondent. Further, as per Clause 28 of the Contract,
the Respondent cannot be held liable for any damages/ compensation
in case of delay caused in handing over the site because several
agencies were involved in the project. Thus, being aware about the
nature of work and these ground realities, the Claimant cannot later
in time seek to be compensated for the loss it suffered as a result of
the said risk. Further, so far as the alleged hindrances caused in
removing of trees is concerned, the same also cannot be used as a
reason to hold the Respondent liable in light of the express terms of
Clause 14 of the Contract Agreement. It is also submitted that the
Respondent had specifically raised the issue of delay in progress of
work in its various letters. The said letters are as following:
Page 43 of 133
a) The Respondent vide its letter dated 02.09.2013 apprised
the Claimant that 11 months had been passed and the
Claimant was only able to complete approximate 10-12 %
work, however in terms of the Contract the Claimant
should have been completed more than 50% of the work.
Page 44 of 133
Tribunal’s findings qua First Period:
Page 45 of 133
Page 46 of 133
Page 47 of 133
8.28 The period for which the work could not be executed at a particular
chainage due to one or the other reason mentioned in the Hindrance
Register, is demonstrated by the Claimant in the following manner :
8.30 Chainage 203 -504 – [Pg. 157 of the Rejoinder to SoD, Annexure –
B and Chart – I, Annexure – C] there was a delay in providing
structural drawings by the SDMC, which were received by the
Contractor / Claimant only on 15.10.2012.
Cost of the stretch (approx. in crores) – Rs. 10.14 Cr. [length of the
stretch 301m]
Page 48 of 133
8.31 It is stated that as against 548 days provided in the Contract to
complete the work of Rs. 10.14 Cr. in this particular stretch, work of
worth Rs. 4.84 Cr. could only be done as only 261 days [242 days +
19 days] were available with the Contractor.
Cost of the stretch (approx. in crores) – Rs. 23.29 Cr. [length of the stretch
691m]
Period during which work could not be executed – 08-09-2012 till 21-10-
2013
Cost of the stretch (approx. in crores) – Rs. 4.65 Cr. [length of the stretch
138m]
Page 49 of 133
8.34 Chainage 1333-1772 [Pg. 157 of the Rejoinder to SoD, Annexure –
B and Chart – I, Annexure – C] were affected due to trees falling in
the alignment of the drain and all the items of work were affected.
Cost of the stretch (approx. in crores) – Rs. 14.79 Cr. [length of the
stretch 439m]
Period during which work could not be executed – 08-09-2012 till 21-10-
2013
8.35 Vide one such letter dated 26.09.2012 [Vol. C-2, Pg. 323], the
Claimant requested the Respondent to arrange the necessary
permission for tree cutting and also requested for removal of
encroachment i.e. hutments etc. For this reason, the Claimant was
forced to select site where there were no trees, due to which, the
Claimant was unable to commence the work for 2.257 km of area:
CH 0 to CH 191
CH 527 to CH 1343
CH 3005 to CH 3747
CH 3747 to CH 3895
CH 5175 to CH 5535
Page 50 of 133
8.37 Chainage 1772-3055 [Pg. 158 of the Rejoinder to SoD, Annexure –
B and Chart – I, Annexure – C] - (Press Enclave Road to Outer Ring
road, Chirag Delhi) the DDA stopped the work on the plea that land
pertained to DDA and it was a green land and also due to rain. In
Chainage 1772-3055 the work at site was again stopped by DDA
from 25.7.2013 to 14.8.2013.
Cost of the stretch (approx. in crores) – Rs. 23.32 Cr. [length of the stretch
692m]
Period during which work could not be executed – 08-09-2012 till 21-10-
2013
Period when the work could be executed – Nil
Amount of work that could be executed – Nil
8.39 The Claimant was deprived of any access to the site from Ch. 1742
to Ch. 3005 (Chirag Dilli) and Ch. 3005 to Ch. 3747 (behind
Panchsheel Enclave) due to the restrictions imposed by DDA since
December 2012. The Respondent was requested by the Claimant
vide letter dated 12.12.2012 [Vol. C-2, Pg. 325] to intervene in the
matter and resolve the issue with DDA, so that the Claimant be
allowed the access to site without any disruption and hindrance.
Page 51 of 133
8.40 The Claimant started the work in the area (CH 1742 – CH 3005) and
continued the work for 47 days. During this period, the following
works were carried out:
i. Hutment
ii. Office set up
iii. Cement store
iv. Foundation for batching plant and weigh bridge
v. Diversion / embankment of drain
vi. Drain excavation up to bed level for PCC / RCC (2 Boxes
10M width)
8.41 The said activity was stopped by the DDA suddenly and the
Claimant was asked to remove the construction and the access was
also closed by constructing a boundary wall. Again, vide letter dated
11.02.2013 [Vol. C-2, Pg. 328], the Claimant informed the
Respondent that the non-resolution of the dispute between MCD &
DDA over the land issue was causing severe distress to the
Claimant’s project as a whole. Referring to Respondent’s
communication dated 11.03.2013 [Vol. C-2, Pg. 333], whereby the
Respondent accepted that the delay cannot be attributed to the
Claimant / Contractor, the Claimant wrote to the Respondent on
24.05.2013 [Vol. C-2, Pg. 339] stating that the delay in handing over
the site / site –clearance shall be considered suitably under Clause 5
of the Contract Agreement since around 2/3 of the alignment was
under the hold of DDA and work could not be taken up as desired in
the contract. Further, the Respondent also asked the Claimant /
Contractor to submit a security deposit of Rs. 1 Lakh for according
permission for access to the construction site through the DDA land.
The same was provided by the Claimant vide demand draft (refer
SDMC’s letter dated 02.09.2013 [Vol. C-2, Pg. 341], JMC letter dated
Page 52 of 133
06.09.2013 [Vol. C-2, Pg. 342] and SDMC’s letter dated 06.09.2013
[Vol. C-2, Pg. 343].
Cost of the stretch (approx. in crores) – Rs. 4.99 Cr. [length of the stretch
148m]
Period during which work could not be executed – 08-09-2012 till 21-10-
2013
8.43 Chainage 3895 – 4806 – 911 m in length, not in scope of work of the
present Contract.
8.45 Chainage 5299 – 5754 [Pg. 158 of the Rejoinder to SoD, Annexure
– B and Chart – I, Annexure – C] - (BRT to Ring Road) there was
Page 53 of 133
hindrances in the nature of encroachment by Jhuggis on both sides
of drain, DJB waterline falling in the alignment of Drain, and
electric lines passing through the drain due to which no work could
be possible nor any excavation could be executed.
Total Cost of the stretch (approx. in crores) – Rs. 15.33 Cr. [total length
of the stretch 455m]
Page 54 of 133
• Delay in removal of encroachment and other things so as to provide
the Claimant with an encumbrance free site by the Respondent –
The Claimant was made to face the problem of encroachment since
the beginning of the work near Andrews Ganj due to the existence
of the kutcha hutments in both banks of the drain. Due to the said
hindrance the work progress got reduced from CH.5549 to CH
5754. In Greater Kailash – 1, there were obstructions as the
several house owners had encroached the nallah by extending their
rear courtyard and objected to excavate the nallah. The Claimant,
vide separate letter dated 26.09.2012 [Vol. C-2, Pg. 324] had
requested the Respondent to allocate the suitable land nearby the
construction site for store yard and for setting up the RMC plant.
Vide letter dated 26.09.2012 [Vol. C-2, Pg. 323], the Claimant
requested the Respondent to arrange the necessary permission for
tree cutting and also requested for removal of encroachment i.e.
hutments etc. Also, vide letter dated 26.09.2012 [Vol. C-2, Pg. 322],
the Claimant requested the Respondent for allocation of dumping
yard. Despite such requests, an encumbrance free site was not
provided to the Claimant / Contractor. The progress of the work
was adversely affected due to such hindrances.
Page 55 of 133
covered with piling work for pipe line pedestals and equipment
deployed by the other contractor.
Page 56 of 133
like to observe that whereas the Claimant has given in detail its
version about the position at various chainages, no such exercise is
conducted by the Respondent in rebuttal.
8.50 So far as the Second Period, which is from the date of passing of the
Interim Order by the NGT, the submission of the Respondent is two-
fold, which is recapitulated below:
Page 57 of 133
On this premise, it is contended that the Claimant cannot take
defence that the Claimant could not foreclose contract because
the Claimant was not aware of the proceedings.
(b) The second submission is that in any case, because of the said
stay for a long period, it is inconceivable that the Claimant kept
the site mobilized. It also not acceptable to the Respondent, by
standards of a reasonable man, that a company having its
annual average turnover for the year 2014-2015 around INR
2000 crore would keep the site deployed to 100% capacity, when
no work was going on. It is not the case of the Claimant this was
their only site in Delhi and hence the site had to be deployed
and there was no alternative use for the items deployed. In such
a scenario, as per settled principles of law, it is the duty of a
party suffering a lost to mitigate the same and it cannot
luxuriously claim losses without taking any steps to control the
ripple effect.
8.51 Insofar as the second limb of the submission at para (b) above is
concerned, that would be considered while discussing the claim of
the Claimant on merits. As far as the submission of the Respondent
that it had taken all permissions necessary before starting of the
work, such a wholesome argument may not be acceptable. May be,
the clearance for going ahead with the project was taken by the
Respondent from the authorities at the highest level of the
Government of India or Government of Delhi. The harsh truth,
however, is that NGT found that such a Project was impermissible
in law and stopped the execution thereof. The project belonged to
the Respondent and therefore, it was for the Respondent to take all
necessary precautions and ensure that it meets all the requirements
Page 58 of 133
of environmental laws before awarding the work. Once NGT has
found the Project to be lacking in this behalf, it is the Respondent or
the Government authorities which have to bear the responsibility
thereof. By no stretch of imagination, the Claimant can be faulted
for the same. More over, after the passing order of the final order
by NGT on 13.01.2015, the Respondent took more than eight months
to take the decision for the closure of the contract. The Respondent,
therefore, cannot shut the Claimant for raising the claims by taking
such a plea. The claims for this period, therefore, will need
adjudication on merits.
Page 59 of 133
8.53 It is submitted by Mr. Sachin Datta, Ld. Senior Counsel for the
Claimant that there are numerous judicial pronouncements which
hold that right of the Claimant to claim damages is not constricted
by mere insertion of such clauses.
Page 60 of 133
artificial curtailment of the compensation that is otherwise legally
due and payable to the Contractor as the same is contrary to law. It
is also argued that the said clause clearly applies only in the event
of “abandonment” or “reduction in scope” necessitated due to site
conditions and cannot possibly apply to a situation where the entire
work is brought to an unceremonious grinding halt.
8.55 It is argued that the delay was not on account of any default or
breach of contract on the part of the Claimant, and therefore, a rigid
interpretation of the terms of contract is not warranted. In support
of this proposition, the Ld. Senior Counsel has relied upon the
judgment in the case of KN Sathyapalan v. State of Kerala & Ors.
[(2007) 13 SCC 43], it has been held as under:
“32. Ordinarily, the parties would be bound by the terms agreed upon
in the contract, but in the event one of the parties to the contract is
unable to fulfil its obligations under the contract which has a direct
bearing on the work to be executed by the other party, the arbitrator
is vested with the authority to compensate the second party for
the extra costs incurred by him as a result of the failure of the
first party to live up to its obligations. That is the distinguishing
feature of cases of this nature and Alopi Parshad case [(1960) 2 SCR
793 : AIR 1960 SC 588] and also Patel Engg. case [(2004) 10 SCC 566].
As was pointed out by Mr Dave, the said principle was recognised by
this Court in P.M. Paul [1989 Supp (1) SCC 368] where a reference was
made to a retired Judge of this Court to fix responsibility for the delay
in construction of the building and the repercussions of such delay.
Based on the findings of the learned Judge, this Court gave its approval
to the excess amount awarded by the arbitrator on account of increase
in price of materials and costs of labour and transport during the
extended period of the contract, even in the absence of any escalation
clause. The said principle was reiterated by this Court in T.P.George
case [(2001) 2 SCC 758].
Page 61 of 133
at the departmental quarry at Mannady, had to be obtained from
quarries which were situated at double the distance, and even more,
resulting in doubling of the transportation charges. Even the space for
dumping of excess earth was not provided by the respondents which
compelled the appellant to dump the excess earth at a place which was
far away from the worksite entailing extra costs for the same.
8.56 Also, in the case of M/s Mohan Lal Harbanslal Bhayana & Company
v. Union of India [2012 SCC Online Del 1957], it has been held as
under:
“7. A conjoint and harmonious reading of the judgments cited by both the
parties would lead us to cull out the legal proposition to the effect that
whenever there is a provision in the contract within the parameters
whereof a particular claim falls, said claim has to be adjudicated upon
within the four corners of the said contractual provision. It is for the reason
that the arbitrator has to take into consideration the provision of the
contract and he cannot travel beyond the parameters of the contract. If the
award is given outside the said contractual provision, it would amount to
exceeding the jurisdiction by the arbitrator which is not permitted. A
distinction has to be maintained between an error within the jurisdiction
and an error in excess of jurisdiction. On the other hand, if the claim does
not fall within the stipulated contractual provision but is a claim for loss
suffered which can be granted under the provisions of Sections 73 and 74 of
the Indian Contract Act, it would be permissible for the Arbitrator to award
such a claim. Keeping in view the aforesaid position in law, we have to
examine as to whether clause 10(CC) of the GCC apply to the claim as
preferred by the claimant or such a claim could be entertained under the
provisions of Section 73 of the Indian Contract Act notwithstanding
existence of clause 10(CC) of the GCC. In order to appreciate this, we may
first reproduce clause 10(CC). It reads as under:…
8. This clause clearly takes into account escalation in the prices of material
as well as compensation for escalation for labour and provides the formula
on the basis of which escalation in the prices of material and/or labour is to
be worked out. Therefore, if the claim for escalation preferred by the
contractor relates to material or labour, it would be covered by Clause
10(CC) of the GCC and the Contractor is entitled to get the claim as per the
said provision. In the present case, the claim was admittedly on account of
escalation in the prices of material and, therefore, would be covered by
Clause 10(CC) of the GCC. Identical situation arose in the case of Pt.
Munshi Ram & Associates (P) Ltd. (supra) and the learned Single Judge
held that the claim awarded as per the provisions of Clause 10(CC) of the
Page 62 of 133
GCC was justified. That was also a case where the contract prolonged
beyond the stipulated date and the contractor had given a notice to the
department to charge 40% extra over and above the quoted rates. However,
the Court held that such a claim would be permissible only in accordance
with Clause 10(CC) of the GCC. The judgments cited by learned counsel for
the appellant have no applicability. In Narain Das R. Israni (supra), claim
No. 22 was for compensation on account of factors other than covered by
Clause 10(CC) of the GCC and it was for this reason that the Court held
that award given did not suffer from any infirmity. Likewise in K.N.
Sathyapalan (supra), there was no provision at all in the contract, for any
price escalation in the original agreement and by supplemental agreement,
it was provided that no claim for escalation would be permissible. The
question was examined from that angle and it was held that such a
provision prohibiting grant of compensation would not apply in the event
when one of the parties to the contract is unable to fulfill its obligation
under the contract and the compensation was permissible under the law,
i.e., the Indian Contract Act.”
8.57 It would also be useful to take note of the judgment of the High Court
of Delhi in Rawla Construction v. Union of India ILR 1982 Delhi 44,
following discussion in the said judgment needs to be reproduced:
“(4) Now I turn to the first two claims. Counsel for the Union of India
says that under clauses 9, 11, and 63 of the Conditions of the Contract,
the contractor is not entitled to any compensation even if the delay in
the execution of the contract is caused by reason of default on the part
of the government. I cannot accept this argument. If there is delay in
the execution of the contract by reason of default on the part of the
government, none of the three clauses referred to by counsel will stand
in the way of the contractor in making a claim before the arbitrator
regarding the increase in the cost of material or expenses on account of
overheads and establishment charges. Hudson in his Building and
Engineering Contracts (9th ed. p. 492) states the principle governing
damages in these words: “WHERE the cause of delay is due to the
breach of contract by the employer, and there is also an applicable power
to extend the time, the exercise of that power will not, in the absence of
clearest possible language, deprive the contractor of his right to
damages for the breach.” Such provision as attempt to deprive the
contractor of the right to claim damages will be strictly construed
against the employer (Hudson p. 493). Because such a clause will have
calamitous consequences for the Contractor. He will have no remedy
anywhere, however outrageous the conduct or behavior of the employer
may be, however interminable the delay. (See Metro Electric Co. v.
Delhi Development Authority, AIR 1980 Delhi 266 (1) at p. 270).
(5) “THE most usual circumstances which give rise to claims are delay
in giving the contractor possession of the site, or in the supply of
drawings, or suspension of the work caused by some act or omission of
the employer, and a consequent increase of expense in the performance
of the works. The contractor will be entitled to recover damages for
delay caused by the employer notwithstanding that an extension of time
Page 63 of 133
for completion has been granted in respect of such delay.” (Emden and
Gill’s Building Contracts and Practice, 7th ed. p. 272; Halsbury Laws of
England, 4th ed. Vol. 4 para 1281 p. 653).
(6) The fact that the engineer has under the building contract, a power
to extend for any reason the date for completion of the contract, and has
so extended it, does not operate to free the employer from damages for
breach of contract (i.e. for delay by the employer) unless the contractor,
on his side also, has accepted this extension as full satisfaction in
respect of the delay. In Trollope and Sons and Colls and Sons Ltd. v.
Singar. (1913), H.B.C. (4th ed.) 849 (2), during a contract for carrying out
alterations and additions, to a dwelling-house, the contractor was
delayed by (inter alia) the non-supply of drawings and details and
essential information, and he claimed damages on these counts. The
employer denied liability and counter-claimed for damages for delay in
completion. The time for completion had been extended by the architect,
and was further extended by the arbitrator, in an arbitration which
ensued, to the date when the work was in fact completed. It was held
that this extension of time did not affect the damages claimed by the
contractor against the employer for breach of contract, by not affording
possession of the site, and by interference with the execution of the
work.
(7) The contractor’s claim was that due to prolongation of the period of
contract he had to buy construction material at higher rates because the
prices had increased and also had, incur extra expenditure on overheads
and establishment. The arbitrator found these claims partly justified.
He awarded INR 2,45,217.03 on the first claim on account of increase in
the cost of construction material. On account of expenditure on
overheads and establishment he awarded to the contractor a sum of INR
3,11,958. Both the claims were founded on the primary plea of
“prolongation of the period of contract.” This prolongation can well be
due to the default of the government. And if the arbitrator finds that
the government is to be blamed for the delay and that the contractor
could not complete the work in time because of the delay on their part,
the arbitrator, I think, is entitled to award damages on account of
increase in the cost of construction material or extra expenditure on
overheads and establishment. These are damages which the contractor
suffers because of the breach of contract by the government. The period
of performance is lengthened. It is extended beyond the time originally
fixed in the contract.
(8) If the duration of the work is prolonged, the expenses will increase.
The question then will be: Who is responsible for delay? Who is in
breach? Who is the prolonger? Neither clause 9 nor clause 11 nor clause
64 take away the arbitrator’s jurisdiction to adjudicate upon the claim
of the contractor, and award him damages for the loss sustained by the
breach. If the contractor himself is guilty of delay, the arbitrator will
dismiss the claim because no party can take advantage of his own
wrong. But if he is not at fault and the other party to the contract is in
default, the arbitrator can award damages.”
Page 64 of 133
8.58 I have given due consideration to this seminal issue. Such clauses
have come up for discussion before the judicial for a umpteen
number of times. There are few judgments which are indicative of
the proposition that in case there is a limitation of liability in the
contract, then no time related claims are maintainable and the
Learned Counsel for the Respondent referred to some of them. Let
me list some at this stage.
i) Syed Israr Masood (1981) 4 SCC 289;
ii) Associated Engineering Co. (1991) 4 SCC 93
iii) T.A. Choudhary 2004 (3) ALD 357
iv) Ramnath International (2007) 2 SCC 453
11. We do not, therefore, find it possible to agree with the reasons stated by the
High Court for refusing the plaintiff’s prayer for refund of the amount paid by
him by way of the first instalment of the sale price. The conclusion recorded by
the Trial Court on this issue was perfectly correct and the High Court was in
error in interfering with the said finding.”
Page 65 of 133
8.60 The Apex Court, in Associated Engineering Company v. Government
of Andhra Pradesh and Another (1991) 4 SCC 93, upheld the High
Court judgment setting aside claims, which were not supported by
the agreement between parties and that the Arbitrator travelled
outside the contract in awarding those claims. The Court held that
the High Court was right in stating that the Arbitrator acted outside
the contract in awarding those claims, while making following
observations :
“On facts, these (four) claims are not payable under the contract. The
contract does not postulate – in fact, it prohibits payment of any
escalation otherwise than in terms of the formula prescribed by the
contract. The conclusion is reached not by construction of the contract
but by merely looking at the contract.
It held that the aforesaid clause prohibits claims on the above account.
It further held that the Arbitrator has travelled beyond the
jurisdiction in awarding those claims. The Division Bench held that it
Page 66 of 133
was of the view that the Arbitrator had exceeded his jurisdiction in
awarding the amount. In that basis, it held that it did not find any
illegality in the judgment of the lower Court rejecting the claim as
awarded by the Arbitrator.
8.62 The similar judicial position was followed by the Supreme Court in
Ramnath International Construction (P) Ltd v. Union of India,
(2007) 2 SCC 453, where Section 11 of the General Conditions of
Contract relating to time, delay and extension, inter-alia, provided:
The Court found that Clause (C) provides that where extensions
have been granted by reason of the delays enumerated in Clause (A),
which were beyond the control of the contractor, or on account of the
delays on the part of the employer specified in Clause (B), the
contractor is not entitled to make any claim either for compensation
or otherwise, arising in whatsoever manner, as a result of such
extensions. After enumerating certain delays, sub-clause (viii) of
Clause (A) specifically mentions delay on account of any other cause
beyond the control of the contractor. The cause for delays specified
in Clause A; thus, encompass all delays over which the contractor
has no control. This will necessarily include any delays attributable
to the employer or any delay for which both the employer and the
contractor are responsible. The contract thus provides that if there
is any delay, attributable either to the contractor or the employer or
to both, and the contractor seeks and obtains extension of time for
execution on that account, he will not be entitled to claim
compensation of any nature, on the ground of such delay, in addition
to extension of time obtained by him. Thus, the Court held that the
Page 67 of 133
claims for compensation as a consequence of delays, i.e., Claim 24
and Claims 13 to 16 was barred by Clause 11(C).
8.63 It may be pointed out at this stage that on the other hand, in M/s.
Asian Techs Ltd v. Union of India & Others (2009) 10 SCC 354, the
Court, while interpreting a similar provision in the contract came to
the conclusion that notwithstanding such a clause, the Contractor
was eligible to make a claim for further amount and the Arbitrator
was within his jurisdiction to award the same. It can be argued that
this judgment did not consider either the case of Ramnath
International or other judgments referred to above. It can also be
argued that as against above, the Apex Court, in Wig Brothers
(2010) 13 SCC 377 chose to base its decision on Ramnath
International which view is reiterated by the Supreme Court in M/s.
Kss Kssipl Consortium (2015) 4 SCC 210, holding that in view of the
exclusionary clause in the said agreement, the claim for ‘extended
stay compensation’ was not an arbitrable dispute.
8.64 In Asian Techs Ltd., the Apex Court, while interpreting such a
clause took the view:
“(B) If the works be delayed:
Page 68 of 133
(C) No claim in respect of compensation or otherwise, howsoever arising,
as a result of extensions granted under Conditions (A) and B) above
shall be admitted.
The letter dated 24.11.1988 makes it clear that the appellant was
not ready to carry out the work beyond the contracted period
otherwise than on separate work orders, and the subsequent
correspondence like the letter dated 11.10.1989 makes it clear that
it was on the specific assurance given by the respondent to the
appellant to continue the work and that the rates would be decided
across the table that the appellant went ahead with the work.
Hence, in our opinion, it is now not open to the respondent to contend
that no claim for further amount can be made due to clause 11(C)
and that the arbitrator would have no jurisdiction to award the
same.
8.65 However, apart from M/s Asian Techs Ltd. (supra), there are various
judgments wherein the courts have held that when the delays are
attributable to the employer, the cost escalates, and in addition, it
increases burden on overhead expenses. If the contractor is not
compensated for such escalation, it would result not only in wiping
off the margin, but losses to the contractor as well. On this
reasoning, the courts have granted compensation and/or damages
notwithstanding such clauses. In this behalf, another judgment in
State of West Bengal v. Pam Developments (P) Ltd. 2017 SCC
Online CAL 13272 may be referred to wherein the Calcutta High
Court has conducted indepth analysis of prevailing caselaw and
culled out the legal position in the following manner:
“46. A Supreme Court judgment reported at (2008) 16 SCC 128
(Associated Construction v. Pawanhans Helicopters Limited) has been
carried by the contractor for the proposition that prohibitory clauses
may operate during the stipulated period of the contract, but they may
not govern the period of extension. On similar lines, the judgments
reported at (2009) 10 SCC 354 (Asian Techs Limited v. Union of India)
and (2009) 16 SCC 705 (Bharat Drilling and Foundation Treatment
Page 69 of 133
Private Limited v. State of Jharkhand) delivered by the same bench
have been relied upon by the contractor qua the applicability of the
prohibitory or no-damage clauses during the extended period of the
contract when the delay was held by the arbitral tribunal to be on
account of the employer. In the first of such judgments, the Supreme
Court found that the award of damages in respect of the claims
prohibited under the contract was justified as “it is apparent that the
delay in the execution of the contract was solely due to the default of the
respondents.” However, the no-damage clauses in the relevant
agreement covering the “excepted matters” were equated with clauses
in some contracts prohibiting any payment on account of interest in the
court referring to the judgment reported at (1996) 1 SCC 516 (Port of
Calcutta v. Engineers-De-Space-Age). The other judgment of the same
bench covered an arbitral award that awarded substantial amounts in
respect of the claims for idle labour, business loss and delay in
communicating drawings and specifications despite prohibitory clauses
in the contract governing such heads of damages. The argument on
behalf of the award-holder in that case was that such prohibitory
clauses amount to “only a bar on the Department and not a bar on the
arbitrator in respect of the matters mentioned therein.” In support of
such contention, the judgment in Engineers-De-Space-Age was also
cited on behalf of the award-holder in such case. The employer in that
case, on the other hand, referred to a judgment reported at (2009) 12
SCC 26 (Sayeed Ahmed and Co. v. State of Uttar Pradesh). The court
held that the decision in Sayeed Ahmed and Co. was “distinguishable
because it relates to interest under the Arbitration and Conciliation Act,
1996 and was not in respect of a claim for the principal amount.” The
court then noticed Section 31(7) of the 1996 Act that permits the parties
to an arbitration agreement to “agree otherwise to the awarding of
interest by the Arbitral Tribunal”.
Page 70 of 133
the Act has undergone a change pursuant to the 2016 Amendment
which has been given retrospective operation from October 23, 2015.
The amended provision is not applicable in this case. Under the original
Section 31(7) of the Act the statute conferred specific authority on the
arbitral tribunal to award interest at such rate as it deems reasonable,
but such authority of the arbitrator was subject to an agreement to the
contrary between the parties. It is, thus, that the judgments in Ambica
Construction read the authority of the arbitral tribunal to be unfettered
unless there was an express agreement to the contrary curbing the
power of the arbitrator to award interest. Thus, a clause simpliciter in
the agreement prohibiting the payment of interest without expressly
referring to the authority of the arbitrator in such regard may not be
regarded as impeding the statutory authority of the arbitrator to award
interest. Such is not the case in respect of any other prohibitory or no-
damage clause covering heads of damages other than interest. As a
consequence, the legal reasoning pertaining to the arbitrator’s authority
to award interest notwithstanding a general prohibition in such regard
in the agreement between the parties cannot guide the treatment or
interpretation of a prohibitory clause pertaining to other heads of
damages than interest. Accordingly, whether or not the dictum in
Engineers-De-Space-Age has been misread in some of the later
judgments without noticing the peculiar clause in that case, is
irrelevant in the present context.
Page 71 of 133
75. However, in the present case the amounts awarded under the four
principal heads of claim despite the prohibitory clauses in respect of
such heads, do not appear to be unconscionable, far less shocking.
Cogent and acceptable reasons were furnished by the arbitrator in
respect of every head of claim awarded in favour of the contractor and
it did not call for any interference under any permissible ground in
Section 34 of the 1996 Act read with Section 28 thereof. In particular,
the tinkering with the costs awarded by the arbitrator and the rate of
interest appear to be the unkindest cuts of all. Much more than a sum
of INR 5 lakh must have been expended by the contractor in course of
the 134 sittings and no “realistic assessment” on the same lines as the
condemned “rough and ready justice” methodology could have prompted
even a paisa to be knocked off from the costs. The award of interest was,
again, within the exclusive domain of the arbitrator and subject to his
discretion as recognised in original Section 31(7) of the 1996 Act and
could not have been interfered with, without an express finding of
perversity in the exercise of the discretion by the arbitrator.”
Page 72 of 133
contractor is not entitled to make any claim either for
compensation or otherwise, arising in whatsoever manner, as a
result of such extensions. After enumerating certain delays, sub-
clause (viii) of clause (A) specifically mentions delay on account
of any other cause beyond the control of the contractor. The
causes for delays specified in clause (A), thus, encompass all
delays over which the contractor has no control. This will
necessarily include any delays attributable to the employer or
any delay for which both the employer and the contractor are
responsible. The contract thus provides that if there is any delay,
attributable either to the contractor or the employer or to both,
and the contractor seeks and obtains extension of time for
execution on that account, he will not be entitled to claim
compensation of any nature, on the ground of such delay, in
addition to the extension of time obtained by him. Therefore, the
claims for compensation as a consequence of delays, that is
Claim 24 of the Hangar Contract and Claims 13 to 16 of the Road
Contract are barred by Clause 11(C). (Underlining is mine).”
“6. What should a High Court do when faced with two judgments of the
Supreme Court which apparently cannot be reconciled with respect to
its ratio ? The Full Bench of the Patna High Court in the judgment
reported as Amar Singh Yadav v. Shanti Devi and Ors ., AIR 1987 Pat
191 has held that when there are two different judgments of the
Supreme Court, then, the High Court should follow that judgment
which lays down the correct law.”
8.67 The Delhi High Court reproduced detailed discussion from the
aforesaid judgment of the Patna High Court which noticed various
judgments laying down the course of action needs to be followed by
subordinate courts/High Courts when they are confronted with two
conflicting judgments of the Supreme Court. It is not necessary to
into that discussion in detail. Suffice it to state that Delhi High
Court accepted that more popular view was that the courts must
follow the judgment which appears to them to state the law
accurately and elaborately and particularly so when the latter
decisions of the Supreme Court did not notice the earlier decision.
Page 73 of 133
8.68 It would be interesting to note that the Delhi High Court also
discussed the validity of such a clause which bars the Contractor
from claiming damages on the touchstone of Section 23 of the
Contract Act and came to the conclusion that such a clause would be
void, being violative of Section 23 of the Contract Act. Ultimately, it
concluded as under :
“19. In my opinion, if I look at the issue from both the micro and macro
positions, keeping in focus the intendment of legislation called the
Contract Act, then, the judgment in the case of Asian Techs Ltd, can be
said to laying down a law which would further the object and purpose
of the Contract Act. I must hasten to add that I am still doubtful
whether I am entitled to decide the aspect that out of two decisions of
Supreme Court, which one is to prevail, therefore, my observations are
strictly in terms of the limited parameters of the facts of the present
case required to decide the aspect of the entitlement or the
disentitlement to damages in view of the provisions of Section 55 and
73 of the Contract Act. I would, with all due respect to the learned senior
counsel for the petitioner, would not venture further and would leave it
finally for a larger Bench of this court or the Supreme Court itself to
consider whether at all there is any conflict between the judgments of
Ramnath International and Asian Techs Ltd and if there is a conflict,
the ratio of which of the two judgments ought to prevail. I am therefore,
deciding this case, to make things very clear, only on the basis of the
decision that contractual clauses which prohibit the entitlement of
rightful damages of a person is clearly hit and are void by virtue of
Section 23 of the Contract Act.”
8.69 For our purposes, it is not necessary to examine the issue from the
prism of Section 23 of the Contract Act. It is rightly contended by Ms
Arora that Asian Techs refers to the earlier judgment of the
Supreme Court in Board of Trustees, Port of Calcutta which has
categorically laid down that such clauses only prohibit the
department from entertaining the claim but do not prohibit the
Arbitrator from entertaining. Moreover, in the present case, Clause
49.5 itself talks of ‘reasonable delay’ and not when the delay in
‘unreasonable’. The judgments, which, on the basis of such clauses,
are held as not maintainable were the cases involving normal delays
and not delays to this magnitude. Whenever the court found the
Page 74 of 133
delay to be abnormal, the courts have taken the view that claim for
compensation would be maintainable notwithstanding such clauses.
8.70 As already noted above, when the delay is on the part of the
Contractor, the Engineer may allow the extension of time for
completion of the work, but at the same time, for the delay caused,
the Contractor is to pay the Liquidated Damages. On the other hand,
in case the delay in completion of the work occurs due to the fault of
the employer, the extension is to be granted, but in that event,
contractual provisions stipulate that such delay would neither affect
nor vitiate the contract or alter the character thereof nor the
Contractor shall be entitled to any damages or compensation. From
the aforesaid, it is clear that whereas the Contractor will be
punished in the form of payment of Liquidated Damages in case
Contractor is responsible for a delay, no such obligation or liability
comes on the Employer in case delay is due to the fault of the
Employer. It is apparent, therefore, the clauses relied upon by the
Respondent are tilted in favour of the employer. It is a Standard
Form Contract and all these provisions are unilaterally incorporated
by the Respondent. How such clauses are to be construed is
described in Rawla Construction Company v. Union of India 1981
SCC Online DEL 315 and Fertilizers and Chemicals Travancore Ltd.
v. Vellapally Bros Constructions (P) Ltd. 1982 SCC Online KER 281.
Page 75 of 133
and machinery as well as rise in the cost of raw material.
Therefore, depriving altogether the Contractor of compensation
on account of the aforesaid factors, it has to be limited to those
circumstances where delay is negligible in nature. Thus, it is
necessary to give pragmatic and practical approach while
construing such a clause, keeping in mind the letter and spirit
of Section 73 of the Contract Act.
Page 76 of 133
We may also quote Chrisomar Corporation v. MJR Steels Pvt.
Ltd. and Anr. (2018) 16 SCC 117, in which the Supreme Court
referred to the case of Satya Jain thr. LRs and Ors v. Anis
Ahmed Rushdie thr. LRs and Ors (2013) 8 SCC 131, wherein
the principle of business efficacy has been dealt with as under :
“The principle of business efficacy is normally invoked to read a
term in an agreement or contract so as to achieve the result or
the consequence intended by the parties acting as prudent
businessmen. Business efficacy means the power to produce
intended results. The classic test of business efficacy was
proposed by Lord Justice Bowen in the Moorcock. The test
requires that a term can only be implied if it is necessary to give
business efficacy to the contract to avoid such a failure of
consideration that the parties cannot as reasonable businessmen
have intended. But only the most limited term should then be
implied – the bare minimum to achieve this goal. If the contract
makes business sense without the term, the courts will not imply
the same.”
Page 77 of 133
would be justified on the basis that such a term was always and
obviously intended by and between the parties thereto. An
unexpressed term can be implied if and only if the court finds
that the parties must have intended that term to form part of
their contract. It is not enough for the court to find that such a
term would have been adopted by the parties as reasonable men
if it had been suggested to them. It must have been a term that
went without saying, a term necessary to give business efficacy
to the contract, a term which, although tacit, forms part of the
contract.”
8.72 The Courts have found following ways to salvage the situation and
solve the problem:
a) When the contract is not completed within the stipulated
time, and fault is attributed to the Employer, the Contractor
can refuse to perform the work beyond the initial contract
period. In Asian Techs Ltd. v. Union of India (2009) 10 SCC
354, the Court found that delay in the execution of the
contract was solely due to the default of the Respondent. The
appellant was not ready to carry out the work beyond the
contracted period, otherwise that on separate work orders,
and that it was on the specific assurances given by the
Respondent to the appellant to continue the work and that
the rates would be decided across the table that the appellant
Page 78 of 133
went ahead with the work. Hence, it was not open to the
Respondent to contend that no claim for further amount
could be made due to the stipulation in the contract that no
claim for compensation consequent to grant of extension of
time would be admissible and that the Arbitrator would have
no jurisdiction to award the same. The Court found that in
the case before it, notices for claiming compensation for delay
were given by the Claimants to the Respondent from time to
time. However, the Respondent did not give any reply and
never asserted that the claim was not payable due to the
aforesaid exclusionary clause. Had it been denied by the
Respondent, the Claimants could have taken a call as to
whether it is to continue the contract or not.
b) In Bharat Drilling and Foundation Treatment Pvt Ltd v.
State of Jharkhand (2009) 16 SCC 705, the Court held that
such a clause puts a bar on the department but cannot be
treated as restrain on the Arbitrator to award compensation
as can be seen from the following discussion. Para 5 from the
judgment is extracted below:
“5. Shri Dwivedi submitted that the bar in Clause 1.21 is only a
bar on the Department and not a bar on the arbitrator in respect
of the matters mentioned therein. He further submitted that
admittedly the Department was not possessed of the land in
question nor had funds for the contract while the appellant was
asked to work and it placed the machinery, labour, etc. on the
spot which was lying idle and because of that reason he suffered
heavy losses. On the facts of the case, he submitted that the bar
under Clause 1.21 will not apply. In support of his contentions,
learned counsel for the appellant has invited our attention to a
decision of this Court in Port of Calcutta v. Engineers-De-Space-
Age [(1996) 1 SCC 516] in which it has been held that a similar
clause prohibited the Department from entertaining a claim for
interest but it did not prohibit the arbitrator from awarding the
interest.” [See also PM Pal v. UOI 1989 Supp 1 SCC 368].
Page 79 of 133
c) In some cases, the courts have held that exclusionary clause
is not applicable on the extended period but only on account
of delay in discharging particular obligation which happens
within the period of contract itself (See 2017 SCC Online
DEL 6470), TA Choudhary v. State of Andhra Pradesh (2004)
3 ALD 357 (DB).
Page 80 of 133
proof has been placed on record by the Claimant in the present
arbitral proceedings. The Respondent has dialated this submission
by arguing that claims can be proved by two methods: either through
the medium of leading oral evidence or by relying on the documents
of record. The Claimant in the instant case has chosen not to lead
any oral evidence during the arbitration proceedings. As for as
documents submitted by the Claimant are concerned, it is contended
that from a bare perusal of the documents placed on record, it
becomes clear that the Claimant has failed to prove any of the
grounds of compensation which have been claimed in its Statement
of Claim. The documents placed on record by the Claimant showcase
that the Claimant has failed to fulfill its contractual obligations as
provided under the Contract and by initiating the present
arbitration proceedings Claimant is only trying to put pressure upon
the Respondent so that Respondent waives off its claim for Mobilized
advance. Otherwise, the Claimant did not have any evidence to
prove its claim and accordingly, the choice of not leading any oral
evidence was made.
Page 81 of 133
8.77 It is also pointed out that the Claimant has sought to rely on alleged
contemporaneous documents. However the first communication
with respect to the hindrances/ delays at project was ever issued the
Claimant vide its letter dated 18.10.2013, which was only received
by the Respondent on 23.10.2013. The time was convenient as the
NGT had passed its interim order on 21.10.2013 which was
intimated to the Claimant on 21.10.2013 by the Respondent. It is
contended that Claimant has approached this Arbitral Tribunal in
order to make profit out of the situation, as the claims have been
belatedly submitted. If there was any bonafide in the said claims of
the Claimant, it would have duly been submitted and raised at the
actual time of having incurred such an expenses.
Page 82 of 133
the circumstances, the arbitral award to the extent that it allows the claim
for loss of profits is based on pure conjecture and in the absence of any
evidence whatsoever was correctly set aside. Similarly, in regard to the claim
for underutilized plant and equipment and for reimbursement of expenses of
infrastructure, it is evident that the Arbitrator has merely awarded a sum
which he considered to be reasonable. No evidence whatsoever was led before
the Arbitral Tribunal. “
Page 83 of 133
Overhead
Expenses
21.10.2013 to 19.01.2015 16,03,73,042/-
19.01.2015 to 15.10.2015 10,59,95,234/- Interest 6,22,34,728/-
(Interest @ 18% Page
no. 420
TOTAL 34,40,86,690/- TOTAL 7,47,30,549/-
Compensation for 08.09.2012 to 5,32,60,097/- N/A
d) Head Office and 21.10.2013
Regional Office
Overhead Expenses
(as per Emden
Formula)
21.10.2013 to 19.01.2015 8,31,68,566/-
19.01.2015 to 15.10.2015 4,51,71,895/-
TOTAL 18,16,00,558/-
Loss of Profit - 7,74,39,924/- - 20,40,00,000/-
e) (as per (Page No. 419
Hudson’s (10))
Formula)
Interest 5,94,55,800/-
(Page No. 419 (11))
TOTAL 26,34,55,800/-
Compensation N/A 1,08,22,546/- N/A 1,44,60,000
f) for Unrecovered
Cost due to fall
in market price
of
Reinforcement
Steel
Project Staff Not Claimed Not Claimed 08.09.2012 to 2,89,03,516/-
g) Idling 21.10.2013
Page 84 of 133
Loss on account Not Claimed Not Claimed 63,50,000/-
l) of theft during (Page No. 425(I)
idle period
Page 85 of 133
8.84 Claim No. 1A: Compensation towards idling of plant and
machinery for the period 08.09.2012 to 21.10.2013 – INR
6,56,69,160/-
8.85 The number of plant and machinery deployed is arrived on the basis
of Monthly Progress Reports (Vol. C-4) and contemporaneous
correspondence submitted by the Claimant to the Employer. It is
stated that few machineries like Water Tanker, JCB, TATA Ace,
Trolley for shifting of reinforcement etc. were available throughout
the duration, however, were not recorded in MPR, as they were at
Yard and used to be deployed for different stretches of Site as per
requirement.
Page 86 of 133
the basis of the bid itself. The cost is calculated in terms of machine-
months.
8.87 At Volume C-2, Page 579, Column No. 1 to 13, the number of the
respective machinery deployed has been taken from the Monthly
Progress Report of each month [Vol. C-4]. It is pointed out that the
pleading in para 7.3 of the SoC mentions the MPR showing the
utilization, which has not been specifically denied by the SDMC in
the SoD. The number of machinery deployed also corresponds with
the letters showing the utilization of mobilization advance dated
27.12.2012 [Vol. C-2, Pg 326] and 20.04.2013 [Vol. C-2 Pg 336]. The
mobilization advance was released in two tranches. Only after the
Claimant showed the proper utilization of the 1st mobilization
advance, the second tranche of the mobilization advance was
released to the Contractor. Prima facie, the Respondent was
satisfied about the utilization of the 1st mobilization advance and
that is why they proceeded to release the second mobilization
advance.
Page 87 of 133
of Pockelein (L&T) 25 FT Book is 2. Likewise, for November
2012, refer Vol. C-4, Pg 791; the number of Pocklein (L&T) 25 FT
Book is 1. The Respondent has denied the MPRs filed by the
Claimant as C-4 documents, even though these MPRs were
submitted during the course of execution of the work as per
Clause 8 of the Special Conditions of Contract [Vol. C-1, Pg 215].
Further, no penalty or compensation has been recovered for delay
in submitting the MPRs. However, the Respondent in paragraph
no. 6 of its Affidavit filed on 18.02.2021, has admitted that, “two
MPRs dated 03.08.2013 (pertaining to July 2013) and 05.11.2013
(pertaining to October 2013) [affirmed by the Diary No. 5550
dated 04.11.2013 as available in the original Diary Register are
available on record....”
Page 88 of 133
cost. Therefore, dry hire usage rate per month is computed as Rs.
1,45,600 i.e., Rs. 2,08,000 minus (-) 30% (rebate towards fuel).
8.92 The table dealing with the calculation for the unrecovered cost of
plant and machinery is given in Vol. C-2, page 578. It is submitted
that the work of Rs. 163.20 crore was to be completed in 18 months
whereas, work of the value of only Rs. 27.00 crore could be completed
in 13.41months. As per the Milestone, work of the value of Rs.
121.58 crore should have been completed in 13.41 months. Hence,
only 22.21% productivity has been achieved from the deployed
resources and balance 77.79% capacity of the deployed plant and
machinery remained unutilized and cost thereof is, therefore,
claimed. The under-utilization percentage of 77.79% is considered
for evaluating the unrecovered cost of plant and machinery deployed
Page 89 of 133
at site. By multiplying this percentage with the total Plant and
Machinery cost arrived [Vol. C-2, Page 579], the claim for
unremunerated cost is quantified along with interest of 12% p.a.
which comes to the tune of INR 6,56,69,160 [Vol. C-2, Pg 578].
iii) Furthermore, the records make it clear that the plant and
machinery was claimed to have been purchased on buy
back basis and furthermore, the claims in respect of
payment for such purchase is also not supported by any
independent documents. Only an invoice and cheque have
been placed on record. The Claimant has not even placed
on record the final document/bill in respect of the buy
Page 90 of 133
back as to whether the plant and machinery was bought
back or not. It is accordingly clear that no evidence has
been led by the Claimant due to the said defective case
being presented by the Claimant. As per the Respondent,
the Claimant intentionally did not lead any evidence as
then it farce would have been called out by the
Respondent.
Page 91 of 133
Claimant. This is in addition to the fact that the Claimant
has not furnished any records/documents/bills to prove
that the Claimant had either hired the machines as
mentioned in the list at Page No. 579 of C-3 or purchased
the same.
Page 92 of 133
very clear that Claimant is hiding the truth and making
false allegation. Furthermore, the Claimant has also
made wrong submissions with respect to the working
hours of Plant and Machinery, failed to comply with the
Clause 8 (at page No. 215 of C-1) which deals with
monthly progress reports. Most of the Monthly Progress
Reports were belatedly produced before this Tribunal,
when most of them were never not even received by the
Respondent. It is pointed out that the Respondent had
received only two Monthly Progress Reports, however
contents of the same have been denied.
vii) It is also pointed out that Claimant vide its letter dated
15.01.2016 provided the list of machines and manpower.
In the said list at S.No (E) losses incurred due to
underutilization of establishment was claimed as an
amount of 1.24 Crore, the same amount has been now
become 7.77 crore. It is, thus, argued that the Claimant
has failed to prove its case and accordingly, Claim No. 1
on the basis of the above.
Page 93 of 133
period. According to the Claimant, full plant and machinery was
deployed at the site which remained under-utilized.
Page 94 of 133
bearing on the question of repayment of mobilization advance which
is discussed while considering the counter-claim of the Respondent.
8.96 The Claimant has arrived at the details of deployment of plant and
machinery on the basis of monthly progress reports. These reports
are filed by the Claimant which are admitted documents. On the
basis therefore, the Claimant has calculated the cost of unutilized
plant and machinery.
8.97 Once the Claimant is able to demonstrate that there was a proper
utilization of Mobilization Advance to the satisfaction of the
Respondent, it can be concluded that the required plant and
machinery for undertaking the work of this magnitude in order to
complete it within the period prescribed in the contract, was brought
on the site. A finding is already recorded that there was slow pace
of work because of the hindrances caused by the Respondent.
Therefore, it can safely be inferred that the plant and machinery has
not been fully utilized during this period. It may also be relevant to
mention that in respect of utilization of second instalment of the
Mobilization Advance, details were provided by the Claimant vide
letter dated 20.04.2013. After this, certain queries were raised by
the Respondent vide letter dated 20.06.2013 which were replied to
by the Claimant vide its communication of the same date. The
correspondence also reveals that Respondent had given notices
dated 25.06.2013 and 10.07.2013. In its reply dated 17.07.2013, the
Claimant had explained that the machinery was taken on hire basis.
The Respondent thereafter passed speaking order dated 26.07.2013
acknowledging that the machinery was “brought” from advance
given to the Claimant. Thus, the Respondent questioned the
Claimant as to why the machinery was not purchased but taken on
Page 95 of 133
hire. There cannot be a dispute that machinery was brought at the
site. It would also be pertinent to mention that vide letters dated
29.10.2013, the Claimant mentioned about the details of the
machinery deployed at the site and reserved its rights to claim
damages on account of under-utilization of the said machinery. This
was followed by another letter dated 28.11.2013 to which the
Respondent did not give any reply thereto.
Page 96 of 133
altogether, more so when the Claimant has given its own basis of
calculating the same. Taking into consideration the entire
perspective, the Tribunal is of the view that granting 50% of the
amount claimed for this period i.e., INR 2,09,50,000 would be
reasonable and meet the ends of justice. The Claimant will not be
entitled to interest for the past period in view of Clause 29 of the
Contract [See:]. Moreover, it is a claim in the nature of
compensation/damages. Thus, the Tribunal is of the view that
interest should be paid from the date of the Award and payment of
interest @ 7% p.a. would be reasonable.
This claim is towards idling of plant and machinery for the second
period i.e., 21.10.2013 to 15.10.2015. A sum of INR20,23,41,835 is
claimed in this behalf. For calculating the cost (Dry Hire Charges of
the plant and machinery) the Claimant has resorted to trade usage
by relying upon CPWD Delhi Schedule of Rates (DSR-2013). It is
submitted that the Claimant could rely upon the same as DSR is
expressly referred to and made part of the contract itself. The
Respondent has refuted the claim by arguing that the NGT passed
the status quo order dated 21.10.2013 and the Respondent duly
conveyed to the Claimant on the very same day about the said
occurrence. Furthermore, the status quo continued till the final
order was passed. The NGT passed the final order on 13.01.2015
whereby NGT directed authorities not to proceed with any work at
the site on the basis of recommendation given by the expert
committee. Therefore, there was no reason to keep the plant and
machinery or the workforce at the site for periods 2 and 3.
Page 97 of 133
8.102 No valid proof is furnished by the Claimant to substantiate this
claim. In this behalf, it is argued that no proof has been placed on
record to confirm that the P&M and manpower were actually
deployed at the site or that the overhead expenses/ site expenses
were not duly recovered or that the Head Office and Regional Office
were being put to use for the Period 2 and 3, to the extent claimed.
It is contended that if Claimant had incurred cost in respect of any
of the above aspects, the Claimant could have submitted the service
bills of machines and wages receipts of workmen, proof of files
occupying space in the Head Office and Regional Office, in order to
prove its claim. However, Claimant has not submitted any evidence
which prove any of its claims during the Period 2 and 3 after the
NGT status quo order was passed.
8.103 The Respondent points out that the Claimant has written four
letters to Respondent asking for the foreclosure of the contract
(05.06.2014 at Page No. 397 of C-2, 21.07. 2014 at Page No. 401 of
C-2, 13 .07.2014 at Page No. Pg. 403 of C-2, 19.09.2014 at Page No.
405 of C-2.). It is submitted by the Respondent that Claimant could
have foreclosed the Contract if Claimant was expending on deployed
Plant and Machinery and manpower and the other alleged expenses
without there being any revenue arising from such deployment, in
terms of Clause 15 of the Contract. Hence, the fact that the Claimant
never exercised this right substantiates the case of the Respondent
that there was no such cost being incurred by the Claimant and that
the same as presented in the Statement of Claim are mere after
thoughts and based on the whims and fancies of the Claimant.
Page 98 of 133
8.104 It is also argued that video submitted by the Claimant shows that
Plant and Machinery was brought at the site to make fake evidence.
In this behalf, following aspects are sought to be highlighted.
(i) The same should not be taken on record as it was
filed belatedly and the Claimant has not even
bothered to comply with section 65-B of the Indian
Evidence Act, 1872 while filing the pendrive which
contain the said video.
8.105 Furthermore, if the Plant and Machinery were idling at the site for
2 (two) years then the claimant must have filed for damages which
would have caused to the idling Plant and Machinery. However
Claimant has not filed such claim in the present case. In the light
of aforesaid, it is submitted that Claimant has failed to prove that
Page 99 of 133
the Plant and Machinery was kept idle at site and video is not
reliable for any purpose.
8.107 Here, I find adequate force in the submission of the Ld. Counsel for
the Respondent. NGT had passed stay order on 21.10.2013 which
was communicated to the Claimant on the same day and it was
asked to stop the work. No doubt, contract was not foreclosed at that
time as it was only an interim order and nobody knew as to what
would be the final outcome. At the same time, the Claimant had
come to know that it would not be able to proceed with the work so
long as the interim order continues. As a prudent and experienced
contractor, the Claimant also knew that stay order passed on
21.10.2013 would continue at least till the next date which was a
couple of months thereafter. In these circumstances, there was no
purpose in continuing to deploy the plant and machinery at the site
during this period. During arguments, the Ld. Senior Counsel for
the Claimant accepted that the Claimant was executing other
projects as well at the time. In all probability, the Claimant either
would have diverted the plant and machinery to other site or
returned the same to the agency from which it was hired. That was
also a legal obligation of the Claimant as its duty in law to mitigate
the losses. When the Claimant came to know that stay was being
extended time and again by NGT, it would not have brought the
plant and machinery to site till the fate of the NGT proceedings was
known.
8.112 The aforesaid calculations are made on the premise that minimum
number of labour was deployed at site as per the requirement; the
number was gradually reduced owing to the NGT Status Quo order,
which is reflected in letter dated 28.11.2013 as well. It is pointed
out that the number of skilled, semi-skilled and unskilled workers
is tallying completely with the claimant’s contemporaneous letter
dated 28.11.2013. The manpower is also seen to be reducing
drastically.
8.113 The Respondent has contested the said claim primarily on the
ground that no evidence is led to prove that the Claimant had
8.117 These uncovered Site Overheads for the period from 08.09.2012 to
21.10.2013 are the costs incurred for running the Project including
the costs for Employee/Staff salary and allowances, insurance
charges, Bank Guarantee charges, office maintenance, Guest House
rents, Site expenses, security expenses, vehicle running expenses
(car hire for staff) etc. The cost claimed under this head are time
related and the un-remunerated portions of these costs have been
claimed. This claim has been calculated using the universally
8.118 It is argued that the average yearly Site Overhead costs of the
Infrastructure Division for the FY 2012-13 to 2013-14 constituted
6.69% of the turnover achieved by Infrastructure Division. This
percentage is arrived by dividing the Total expenses incurred on Site
Overheads for Infra Division (excluding HO and RO Overheads)
from FY 2012-13 to 2013-14 with Cumulative Turnover of Infra
8.123 While analysing Claim No.1, the Tribunal has already stated the
manner in which period 1 and period 2 are to be dealt with. To avoid
any repetition, the same is not expressed again. It is suffice to say
the Tribunal shall proceed on that basis.
8.126 It has been held in the case of McDermott International Inc v. Burn
Standard Co Ltd and Others [(2006) 11 SCC 181] that, claim for
Overhead costs / additional Management costs which resulted in
decrease in profits are in the nature of a claim for damages. It has
also been held that quantification of such a claim is merely a matter
of proof. The Arbitrator can use different formulae depending on the
facts and circumstances of each case. Also, it has been held that :
“106. We do not intend to delve deep into the matter as it is an accepted
position that different formulate can be applied in different
circumstances and the question as to whether damages should be
computed by taking recourse to one or the other formula, having regard
to the facts and circumstances of a particular case, would eminently fall
within the domain of the Arbitrator.
8.133 This claim has been calculated using the Emden Formula. The
computation is at pages 675-676 of Volume C-3, which is reproduced
hereunder :
Computation of unrecovered HO and RO overhead expenses as per Emden Formula:
8.134 The average yearly Regional and Head Office overhead costs for the
FY 2012-13 to 2013-14 constituted 4.59% of the turnover achieved.
This percentage is arrived at by summing up the percentages i.e.,
3.29% (HO percentage) + 1.29% (Regional Office percentage).
8.135 The data has been taken from the Chartered Accountant Certificate
and also from the Annual Report (Pages 684-769, Volume C-3) of the
Claimant Company as the Claimant is a listed company. The
Revenue from operations in 2013-14 was to the tune of about INR
2658.83 crore. Notes on Financial Statements given at page 733,
Expenses accounted for in the Financial Statements and a
percentage of this is 4.59%. The CA certificate is based on the
Annual Report.
8.136 This claim has also been calculated using Emden Formula. The
computation has been explained at pages 678-679 of Volume C-3 and
certificate of an Independent Chartered Accountant is also filed.
8.139 It is clear from the aforesaid defence of the Respondent that insofar
as periods Second and Third are concerned, the opposition is on the
8.140 So far as Claim No. 4A relating to the first period is concerned, the
Claimant has applied Emden formula and attributed 4.59% of
Regional Office and Head Office overhead expenses towards this
project. This seems to be reasonable having regard to the discussion
above while dealing with Claim No. 3A.
“8. …One of the heads of damages under which claim is made is “loss of
expected profit in the work”. The claim under this head as canvassed
before the High Court was in the amount of Rs 4,30,314.
9. It was not disputed before us that where in a works contract, the party
entrusting the work commits breach of the contract, the contractor would
be entitled to claim damages for loss of profit which he expected to earn
by undertaking the works contract. What must be the measure of profit
and what proof should be tendered to sustain the claim are different
matters. But the claim under this head is certainly admissible…
ii. Dwaraka Das v. State of M.P. and Another [(1999) 3 SCC 500]
“It is not his case that for due compliance of the contract he had
advanced money to the labourers or that he had purchased
materials or that he had incurred any obligations and on account
of breach of contract by the defendants he had to suffer loss on
the above and other heads. Even in regard to the percentage of
profit he did not place any material on record but relied upon
assessment of the profits by the Income Tax Officer while
assessing the income of the contractors from building contracts.”
***
iii. MSK Projects India (JV) Limited v. State of Rajasthan & Anr.
[(2011) 10 SCC 573]
“39. In A.T. Brij Paul Singh v. State of Gujarat [(1984) 4 SCC 59 : AIR
1984 SC 1703] , while interpreting the provisions of Section 73 of the
In the present case, it was held that there is no infirmity in the award,
since there was rationality in the award and percentage picked up from
Standard Data Book of MoRTH. Further, the claim for loss of earning
capacity and profit means that manpower, plant and machinery used
at site by contractor during extended period of contract disabled
contractor to use the same for another contract and it is loss of profit of
that contract which has to be recompensed.
“41. …But a claim for loss of earning capacity and profit is entirely
different. It means that the manpower, plant and machinery used
at the site by the contractor during extended period of contract
disabled the contractor to use the same for another contract and
it is loss of profit of that contract which has to be recompensed.
The majority award has extracted a quote from Hudson's
Building and Engineering Contracts as under:-
43. The view taken by the learned Single Judge to overrule the
majority award pertaining to claim No. 8 under dispute 8A is
accordingly overruled.”
8.144 It is argued that in the light of the above judgements, the Contractor
/ Claimant is entitled to the claim for loss of profit.
8.145 Per contra, it is argued by Mr. Sandeep Bajaj, Standing Counsel for
the Respondent, that the Claimant is not entitled for loss of profits
as no damages had been caused to the Claimant or established by
the Claimant by placing on record oral or documentary evidence. It
is submitted that reliance upon Hudson’s Formula is misconceived
as that cannot be applied in vacuum. In support of this proposition,
Mr. Bajaj has referred to the judgment in the case of “Shah
JagshiJethabhaiv. J.N. Construction” (2012 SCC Online Bom 154),
wherein it has been held by the High Court of Bombay that:
(a) Edifice Developers and Project Engineers Ltd v. M/s Essar Projects
(India) Ltd. (2012 SCC Online Bom 154),
8.150 On the contrary, in the present case, the Claimant has produced
cogent evidence as discussed above.
8.153 It is pointed out that the said claim was also raised before the DRC
and the same was accepted by the DRC letter dated 29.05.2017
(Pages 432-435). A sum of INR 69,13,247 was recommended by DRC
to be paid by the Respondent to the Claimant. At page 434, the DRC
recommended that “.....Concerned Division has reported that at the
time of the closure of the Contract i.e., 05.08.2015 that there was
831,9919 MT of the steel reinforcement lying at the site and the same
was returned to the contractor. The steel reinforcement was procured
by the contractor at higher rates and the market rate at the time of
submission of tenders was INR 47,500 per MT and at the time of
closure of contract, rate was INR 39,190 per MT as reported by the
concerned Division. The difference amount due to fall in market price
is to the tune of INR 69,13,247 and the contractor suffered this loss
due to stoppage of work midway on 21.10.2013 in compliance of order
of Hon’ble NGT.” It is thus argued that the Respondent has never
denied the factum of 831.9919 MT of the steel reinforcement lying
at the site and that they were procured by the Contractor at higher
rates and the market rate at the time of submission of tenders was
INR 47,500 per MT and at the time of closure of contract, rate was
INR 39,190 per MT. The Claimant has thus claimed the aforesaid
amount of INR 69,13,247 plus interest thereupon @ 12% from
8.154 As per the Respondent, the Claimant is not entitled to this claim. It
is submitted that the entire basis of the claim is DRC decision dated
29.05.2017. However, in the present case, the Claimant is
challenging rest of the recommendations of DRC. On that basis, it
is submitted that the Claimant cannot pick and choose to rely on the
contents of a document. On the one hand, Claimant is seeking to rely
on the DRC decision by raising the claim on the basis of the
recommendation of the DRC in the said decision and on the other
hand it is not accepting all the other findings. As per the
Respondent, in the said DRC decision it has been clearly mentioned
that the Claimant had procured the steel at higher rates. Thus by
virtue of Clause 6 of Instruction to Bidder Respondent is not liable
to pay any extra charges for reinforcement steel.
This will also apply to items or group of items for which a separate
period of completion has been specified.
8.158 The claim is not sustainable on two grounds. In the first instance,
it has already been held that no delay can be attributed to the
Claimant. Secondly, it was for the Superintending Engineer who
had to take a decision for imposing Liquidated Damages as per
Clause 2 of GCC, which was never done. Presumably, no Liquidated
Damages were imposed as the Respondent was convinced that there
was no fault of the Claimant. Be as it may, having failed to take any
such decision by following procedure contained in Clause 2 of GCC,
such a claim cannot be preferred before the Arbitral Tribunal. This
Counter Claim No. 1 is, therefore, rejected.
8.161 It may be remarked at the outset that the Mobilisation Advance was
given as a loan by the Respondent to the Claimants to help the
Claimants in mobilising certain resources for taking up the
execution of the Contract. Such a mobilisation of these resources was
necessary for the start of the work. It is also obvious that the
contractual term which provides for such an advance to be given by
the Employer to the Contractor is to financially help the Contractor
inasmuch as it is the obligation of the Contractor to mobilise these
resources for proper execution of the Contract. It is also a matter of
record that in the normal course the Contractor is obliged to refund
the said advances by getting it adjusted against the running bills.
The Mobilisation Advance also carries interest, and the Contractor
is liable to pay that interest as well.
8.162 The Claimant has contested the Counter-claim on the ground that
mobilization advance given to it by the Respondent was utilized was
utilized to the satisfaction of the Respondent. However, this
argument need not detain us inasmuch as the terms of the
contractual provisions, the Claimant was supposed to return this
amount with interest. No doubt, after utilization of the mobilization
advance, the Claimant is prevented from executing the entire work
and had the project been completed, the Claimant would have
earned enough money to easily refund the mobilization advance.
8.163 The Claimant has also disputed this claim on the ground that the
claim is time barred. It is submitted that this claim should have
been preferred within a period of three years from the date on which
the cause of action first arose, in view of Section 43 of the Arbitration
and Conciliation Act 1996 as per which the Limitation Act applies to
arbitrations as well. This Section also clarifies that an arbitration
shall be deemed to have commenced on the date referred to in
Section 21 of the Act. It is submitted that these counter claims are
raised for the first time in the Statement of Defence filed on
12.11.2020. Before that, this claim was not preferred. It was not
even raised before the DRC. There is a force in the submission of
the Claimant. As per the Respondent, the amount became payable
on 21.10.2013 as the interest is claimed from that date. In any case,
it can be said that when the contract was foreclosed on 15.10.2015,
the claim is preferred more than five years thereafter whereas, as
per Articles 55 and 137 of the Limitation Act, this claim should have
been raised within three years from the date on which cause of
action arose. The Counter Claim No.2 is, therefore, rejected as
time barred.
Since certain claims are awarded in favour of the Claimant and counter-
claims of the Respondent are rejected, there is no need for the Claimant to
keep the Bank Guarantee alive. The Bank Guarantee, which is valid till
30.06.2021, need not be extended further, the same stands discharged.