Pre-Startup Safety Review (PSSR)
Pre-Startup Safety Review (PSSR)
Pre-Startup Safety Review (PSSR)
-2018
http://iraj.in
PRE-STARTUP SAFETY REVIEW (PSSR) PROCEDURE AT KUWAIT
OIL COMPANY
AHMAD ANWAR AL-FUZAIE
Abstract - this procedure provides the minimum requirements for preparation and conducting of Pre-Startup Safety Reviews
(PSSRs) of operating, new or modified facilities. PSSR shall be performed after mechanical completion, prior to
commissioning or the introduction of hazardous substances in the process.
54
International Journal of Management and Applied Science, ISSN: 2394-7926 Volume-4, Issue-11, Nov.-2018
http://iraj.in
Civil civil and general items. These checklists are classified
PSM (Asset/ Directorates). as “short form” and “long form”, and are depicted in
HSE (Asset/ Directorates). appendices 1 and 2, respectively.
Fire (Support Services) Team. The PSSR team will perform a physical review of the
facility just before startup to confirm that all related
Conducting the PSSR (projects and MOC) requirements have been met before the hazardous
The PSSR Coordinator schedules the team meetings substances are introduced in the process and/ or
and assigns roles for the team members. equipment.
The review will consist of two parts: All members of the PSSR team shall review and sign
A review of the changes and the PSSR checklist in the PSSR form to confirm the facility is safe for
an effort to discuss the status of the checklist startup.
items not requiring a field visit (e.g. training,
procedures, etc.) and to generate a list of items for Tracking of Corrective Actions (projects and
review in the field. MOC)
A field visit by the PSSR team to verify the status If, during the PSSR process, incorrect or incomplete
of items requiring a field visit, as well as to verify items are found by the PSSR Team, they may be
the status of issues identified during the review divided into two groups:
mentioned above. Actions that shall be corrected before startup, i.e.
items that must be completed or corrected before
The PSSR coordinator shall lead the team in the process can safely startup.
completing the PSSR checklist. For each portion of the Actions that shall be corrected after startup, i.e. an
checklist, the team must determine if the status of the issue that does not impact safe startup or
item is adequate to allow the unit to start safely. operation but, if corrected, enhances process
If the team determines that there are substandard safety.
conditions, they must identify the corrective action Note: The completion dates for both pre and post
and the individual who is responsible for ensuring that startup cases must be included in the action tracker.
the issues are resolved, as well as the appropriate due Priority on resolution of these corrective actions
date for the resolution of the issue. The team must also should be based on the residual risk associated with
determine whether the issues must be resolved prior to the items, with highest priority given to those items
starting the equipment, or they can be postponed until that must be completed prior to startup of the
after the startup. Safety critical shall not be started equipment.
until all corrective actions that require resolution prior
to startup are verified as completed. Authorization for Startup (projects and MOC)
The Team conducts physical examination of the new Startup. Upon completion of all pre-startup action
or modified plant, process or equipment, or that has items, the PSSR report and corresponding form are
been shut down for any reason. This physical forwarded to the Operations Manager/Team Leader of
examination is necessary to verify that the plant or the area for approval to implement and startup the
process was built according to design and that all project or modification.
necessary safety features have been incorporated and After Startup. The Project Manager or MOC Change
are functioning. Coordinator as appropriate shall ensure that the “after
This examination includes interviews with key startup” action items are completed by the target date,
personnel and reviews of documentation such as and that the new or modified equipment is safe to
specifications and drawings to verify that the design operate.
criteria are met The PSSR team members shall
confirm that: Closure of PSSR (projects and MOC)
All Construction and equipment have been The PSSR Coordinator will verify that all
verified and tested in accordance with original recommendations and issues have been satisfactory
design specification. resolved and proceeded to signature and closure of the
Operating, Maintenance, HSE and Emergency PSSR process. The PSSR shall be closed only when all
procedures are in place and adequate. before and after start-up items are completed. The
All PHA and required process safety closure of a PSSR shall be communicated to all
concerned persons, including the PSSR team
documentation have been performed, are updated
members.
and on file.
The PSSR Coordinator should seek out all appropriate
Training of each employee involved in the
approvals prior to reviewing the PSSR with the
operating process is complete.
Operations Manager/Team Leader.
Completing the PSSR Form (projects and MOC)
Completing the PSSR Form (Operational PSSR)
PSSR is carried out with the help of checklists for
The Operations responsible person (Operator 1 on
mechanical, instrumentation, electrical, fire, HSE,
duty or the employee assigned by the facility
55
International Journal of Management and Applied Science, ISSN: 2394-7926 Volume-4, Issue-11, Nov.-2018
http://iraj.in
custodian) will confirm by the application of the safety features shall be available to recommence
Operational PSSR Checklist if there are substandard production.
conditions on the process equipment after a partial or The operations on duty will confirm through the
total shutdown. This person shall monitor the physical examination of the plant processes or
implementation of corrective actions until those equipment that the safe operating conditions for
substandard conditions are eliminated. Then he will startup exist completing the Operational Checklist (it
authorize starting the equipment or plant to normal shall be filled totally but whenever some items are to
operations. Equipment shall not be started until be omitted simply tick them as NA).
identified deviations are corrected. All necessary
56
International Journal of Management and Applied Science, ISSN: 2394-7926 Volume-4, Issue-11, Nov.-2018
http://iraj.in
have been resolved or implemented before startup, and REFERENCES
modified facilities meet the management of change
requirements; and training of each employee involved [1] KOC.PS.014 - Pre-Startup Safety Review (PSSR) Procedure
in operating a process has been completed.
57