1) JJM Construction Co. provides a summary of accomplishment report for work done as of April 15, 2021 on a construction project.
2) Several areas of the project are nearly complete, such as perimeter fencing, retaining walls, and some road and parking areas.
3) Other areas like grilles installation, wheel stoppers, street lights, and sidewalks are still ongoing and waiting for delivery of materials.
4) Overall progress is at various stages across different aspects of the project, with some nearing completion while others are still in initial phases.
1) JJM Construction Co. provides a summary of accomplishment report for work done as of April 15, 2021 on a construction project.
2) Several areas of the project are nearly complete, such as perimeter fencing, retaining walls, and some road and parking areas.
3) Other areas like grilles installation, wheel stoppers, street lights, and sidewalks are still ongoing and waiting for delivery of materials.
4) Overall progress is at various stages across different aspects of the project, with some nearing completion while others are still in initial phases.
1) JJM Construction Co. provides a summary of accomplishment report for work done as of April 15, 2021 on a construction project.
2) Several areas of the project are nearly complete, such as perimeter fencing, retaining walls, and some road and parking areas.
3) Other areas like grilles installation, wheel stoppers, street lights, and sidewalks are still ongoing and waiting for delivery of materials.
4) Overall progress is at various stages across different aspects of the project, with some nearing completion while others are still in initial phases.
1) JJM Construction Co. provides a summary of accomplishment report for work done as of April 15, 2021 on a construction project.
2) Several areas of the project are nearly complete, such as perimeter fencing, retaining walls, and some road and parking areas.
3) Other areas like grilles installation, wheel stoppers, street lights, and sidewalks are still ongoing and waiting for delivery of materials.
4) Overall progress is at various stages across different aspects of the project, with some nearing completion while others are still in initial phases.
Download as DOCX, PDF, TXT or read online from Scribd
Download as docx, pdf, or txt
You are on page 1/ 3
JJM CONSTRUCTION CO., INC.
General Contractor . Engineers . Designers
De Quiroz Compound, 3626 Buhay na Tubig, Imus, Cavite Cell. Nos. 09189256281, 09089574920, Tel No. (046) 683-2838
SUMMARY OF ACCOMPLISHMENT REPORT
DATE COVERED: As of April 15, 2021
WORK TOTAL QUANTITY COMPLETED BALANCE/S Remarks
DESCRIPTION PERIMETER FENCE Fabrication of Grilles 48pcs. 45pcs. 3pcs. On going fabrication Cornering Interior 48spans 21spans 27spans Cornering Exterior 48spans 17spans 31spans Groove Interior 48span 21spans 27spans On going but as of april 13 up to now no manpower c/o Johnny Miscala Groove Exterior 48spans 8spans 40spans Wall Finishing Interior 48spans 23spans 25spans Wall Finishing 48spans 23spans 28spans Exterior Concreting of column 49pcs. 40pcs. 9pcs. Waiting for the delivery of phenolic for formworks. CHB Laying and 47spans 47spans 0 Completed Plastering RETAINING WALL CHB Laying 217lm 214lm 3lm Due to abandoned Meralco post Plastering Exterior 217lm 211lm 6lm On going Plastering Interior 217lm 202lm 15lm On going Finishing 217lm 179m 48lm On going INSTALLATION OF GRILLES (Justice Hall) Fabrication 71pcs. 5pcs. 66pcs. Waiting for the delivery of materials. Installation 71pcs. 0 71pcs. Waiting for approval of connection detail. Painting 71pcs. 0 71pcs. Waiting for the delivery of materials for painting. WHEEL STOPPER Fabrication 207pcs. 180pcs. 27pcs. On going Installation 207pcs. 0 207pcs. Waiting for the delivery of concrete epoxy. STREET LIGHT Pedestal 27pcs. 15pcs. 12pcs. The balances proceed together the roadway and parkings. Installation of street 27pcs. 14pcs. 13pcs. Installation will proceed if Light post the balance pedestals are already done. Installation of Bulb 27pcs. 12pcs. 15pcs. MANHOLE Installation of 44pcs. 7pcs. 37pcs. Waiting for the delivery of Manhole Cover materials. Installation of Ladder 44pcs. 4pcs. 40pcs. On going rung ROADS Area A and 20% There’s a lot of obstruction Commercial like stock file of Preparation of Sub 30% 20% scaffolding,materials, etc. Base Course of other contractor. Preparation of Base 20% 0% Course Formworks 10% 0% Concrete Pouring 40% 0% Area B 100% Preparation of Sub 30% 30% Base Course Preparation of Base 20% 20% completed Course Formworks 10% 10% Concrete Pouring 40% 40% Area C 94% Preparation of Sub 30% 28% Base Course Preparation of Base 20% 19% On going Course Formworks 10% 9% Concrete Pouring 40% 38% Area D 100% Preparation of Sub 30% 30% Base Course Completed Preparation of Base 20% 20% Course Formworks 10% 10% Concreting 40% 40% PARKINGS Area A 18% Preparation of Sub 30% 5% Base Course Preparation of Base 20% 3% Course Formworks 10% 2% Concrete Pouring 40% 8% Area B 50% Preparation of Sub 30% 15% Base Course Preparation of Base 20% 10% Course Formworks 10% 5% Concrete Pouring 40% 20% Area C 97% Preparation of Sub 30% 30% Base Course Preparation of Base 20% 19% Course Formworks 10% 9% Concrete Pouring 40% 39% Area D 100% Preparation of Sub 30% 30% Base Course Preparation of Base 20% 20% Completed Course Formworks 10% 10% Concreting 40% 40% SIDEWALK Area A 20% Waiting for the delivery of Preparation of Sub 30% 20% rebars Base Course Spreading of gravel 20% beeding Formworks 10% Concrete Pouring 40% Area B 42% Preparation of Sub 30% 25% Base Course Spreading of gravel 20% 10% beeding Formworks 10% 7% Concrete Pouring 40% Area C Preparation of Sub 30% Base Course Preparation of Base 20% Course Formworks 10% Concrete Pouring 40% Area D Preparation of Sub 30% Base Course Preparation of Base 20% Course Formworks 10% Concreting 40% DRAINAGE Installation of 95% 5% Waiting for the delivery of Concrete Pipe RCP