Boeing India

Start Date 25-12-2018 %complete 28%


Finish Date 07-03-2020 Delay 30 Days
Office Block (1 basement)
Footing RCC 82 Nos Done out of 136
Grade Slab RCC 1540sqm done out of 7875sqm
Column RCC 70Nos done out of 149
Ground Floor lvl
Pour 1 Column Concrete 40% completed. Shuttering & Scaffolding Going on
Pour 2 Column Concrete 40% completed. Shuttering & Scaffolding Going on
Pour 3 Column Concrete 15% completed. Shuttering & Scaffolding Going on
Pour 4 Column Concrete 10% completed. Shuttering & Scaffolding Going on
Pour 5 Column Concrete 10% completed. Shuttering & Scaffolding Going on
Pour 6 Column Concrete 5% completed. Shuttering & Scaffolding Going on

Manufacturing Lab (No basement)


Excavation 100% done
Footing RCC 256 Nos completed out of 269, 13 hold by client
Column RCC 28 Nos completed out of 179 Nos
Grade Slab RCC 2900Sqm Completed out of 7875sqm

first floor
Portion 1 Pour 1 Column 30%
Pour 2 Column 20%
Pour 3 Column 20%
Pour 4 Column 10%
Portion 2 Pour 1 Column 5%
Pour 2 Column 5%
Portion 3 Pour 1 Column 5%
Pour 2 Column 0%

DG House
Earthwork 91% completed
PCC footing 75 Nos completed out of 82 Nos
RCC footing 25 Nos completed out of 82 Nos

CSO Building
Grade Slab RCC - Completed
Fly Ash blockwork 99 % completed
Plastering 9% completed
Decksheet eraction 555sqm completed out of 555sqm.

HSD Yard
Excavation 100% completed

Cannie House
Top soil removal 100% completed
Foundation excavation 204Cum completed out of 2040Cum

STP
Excavation 100% completed
ATT & PCC 100% completed
Rebar for Raft 30% completed