first floor
Portion 1 Pour 1 Column 30%
Pour 2 Column 20%
Pour 3 Column 20%
Pour 4 Column 10%
Portion 2 Pour 1 Column 5%
Pour 2 Column 5%
Portion 3 Pour 1 Column 5%
Pour 2 Column 0%
DG House
Earthwork 91% completed
PCC footing 75 Nos completed out of 82 Nos
RCC footing 25 Nos completed out of 82 Nos
CSO Building
Grade Slab RCC - Completed
Fly Ash blockwork 99 % completed
Plastering 9% completed
Decksheet eraction 555sqm completed out of 555sqm.
HSD Yard
Excavation 100% completed
Cannie House
Top soil removal 100% completed
Foundation excavation 204Cum completed out of 2040Cum
STP
Excavation 100% completed
ATT & PCC 100% completed
Rebar for Raft 30% completed