PROGRESS REPORT

UPDATED CONSTRUCTION STATUS OF " BANALATA" , CLUSTER OF TEEN KANYA


As on 08/05/23
SL % OF COMPLITION Remarks
PARTICULARS
NO TOWER- 1 TOWER-2 TOWER-3

1 Pilling work 100% 100% 100%


2 Foundation 100% 100% 100%
3 Ground Floor slab 100% 100% 100%
4 RCC 1st Floor Slab 100% 100% 100%
5 RCC 2nd Floor Slab 100% 100% 100%
6 RCC 3rd Floor slab 100% 100% 100%
7 RCC 4th Floor Slab 100% 100% 100%
8 RCC 5th Floor slab 100% 100% 100%
9 RCC 6th Floor Slab 100% 100% 100%
10 RCC 7th Floor slab 100% 100% 100%
11 RCC 8th Floor Slab 100% 100% 100%
12 RCC 9th Floor Slab 100% 100% 100%
13 RCC 10th Floor Slab 100% 100% 100%
14 RCC 11th Floor Slab 100% 100% 100%
15 RCC 12th Floor slab 100% 100% 100%
16 RCC 13th Floor Slab 100% 100% 100%
17 Roof Slab 100% 100% 100%
18 Above Roof Slab 100% 100% 100%
19 Brick Work 95% 98% 98%
20 Inside Plaster 92% 97% 97%
21 Flooring (only Internal Flats) 95% (Except Toilet and Kitchen)
22 Door Frame Fixing 100% 100% 100%
Plumbing works (internal and
except cp fittings and sanitery
23 external works of flats upto ground 80% 85% 95%
floor ceiling level) wares

Electrical work- Chase Cutting, DB


24 fixing etc 95% 95% 95%

26 Supply & Erection of Lift


27 Outside Plaster 90% 97% 95%
28 Outside Painting/ Primer
29 Ready to Handover
Water Proofing of sunken area and
98% 88%
30 sunken PCC (only flats)

Progress Report
Updated Report of Internal Road and Sweage System at Teen kanya
As on 08/05/2023
SL NO Particulars % of Remarks
1 Internal Compliti
85%
Road

Progress Report
Updated Report of Internal Road and Sweage System at Teen kanya
As on 08/05/2023
SL NO Particulars % of Remarks
1 Swearage Compliti
85%
2 weage 95%
As on 06/05/22 Syste

95%
92% 97%

60% 70%

As on 06/05/2022

Internal Road