Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                

EIA Projected Power Plant Costs

Download as pdf or txt
Download as pdf or txt
You are on page 1of 189

Updated Capital Cost Estimates for Electricity

Generation Plants

November 2010
U. S. Energy Information Administration
Office of Energy Analysis

U.S. Department of Energy


Washington, DC 20585

This report was prepared by the U.S. Energy Information Administration (EIA), the statistical and analytical agency
within the U.S. Department of Energy. By law, EIA’s data, analyses, and forecasts are independent of approval by
any other officer or employee of the United States Government. The views in this report therefore should not be
construed as representing those of the Department of Energy or other Federal agencies.
The current and future projected cost of new electricity generation capacity is a critical input into
the development of energy projections and analyses. The cost of new generating plants plays an
important role in determining the mix of capacity additions that will serve growing loads in the
future. New plant costs also help to determine how new capacity competes against existing
capacity, and the response of the electricity generators to the imposition of environmental
controls on conventional pollutants or any limitations on greenhouse gas emissions.

The current and projected future costs of energy-related capital projects, including but not
limited to new electric generating plants, have been subject to considerable change in recent
years. EIA updates its cost and performance assumptions annually, as part of the development
cycle for the Annual Energy Outlook (AEO). For the AEO2011 cycle, EIA commissioned an
external consultant to develop current cost estimates for utility-scale electric generating plants.1
This paper briefly summarizes the design of the project and provides a summary of its main
findings, including a comparison of the new estimates to those used in AEO2010. The final
section discusses how EIA uses information on cost and other factors in modeling technology
choice in the electric power sector.

Developing Updated Estimates: Key Design Considerations

In order to maximize its value to EIA and external energy analysts, the project focused on
gathering current information regarding the “overnight”2 cost for a wide range of generation
technologies, while taking care to use a common boundary in the costing exercise across those
technologies. The cost estimates for each technology were developed for a generic facility of a
specific size and configuration, and assuming a location without unusual constraints or
infrastructure needs.

Current information is particularly important during a period when actual and estimated costs
have been evolving rapidly, since the use of up-to-date cost estimates for some technologies in
conjunction with estimates that are two, three, or even five years old for others can significantly
skew the results of modeling and analysis. Where possible, costs estimates were based on
information regarding actual or planned projects available to the consultant. When this
information was not available, project costs were estimated by using costing models that account
for current labor and material rates that would be necessary to complete the construction of a
generic facility.

The use of a common boundary for costing is also very important. From experience in reviewing
many costing studies for individual technologies, EIA is well aware that differences in practices
regarding the inclusion or exclusion of various components of costs can have a large impact on
overall cost estimates. This includes the categories of civil and structural costs (e.g., allowance

1
EIA’s electricity modeling includes both combined heat and power (CHP) technologies as well as a variety of
distributed generation technologies, but those technologies were not addressed in the study, which focused on
technologies within the electric power sector.
2
“Overnight cost” is an estimate of the cost at which a plant could be constructed assuming that the entire process
from planning through completion could be accomplished in a single day. This concept is useful to avoid any
impact of financing issues and assumptions on estimated costs. Starting from overnight cost estimates, EIA’s
electricity modeling explicitly takes account of the time required to bring each generation technology online and the
costs of financing construction in the period before a plant becomes operational.

2
for site preparation, drainage, underground utilities, and buildings), project indirect costs (e.g., a
construction contingency), and owners costs (e.g., development costs, preliminary feasibility and
engineering studies, environmental studies and permitting, legal fees, insurance costs, property
taxes during construction, and the electrical interconnection costs, including a plant switchyard
and tie-in to nearby transmission).

Summary of updated overnight capital costs estimates and comparison to information used in
AEO2010

Table 1 summarizes the updated cost estimates for the generic utility-scale generation plants
represented in EIA’s model, including 7 powered by coal, 6 by natural gas, 3 by solar energy, 2
each by wind, hydro, biomass, and geothermal power, and 1 each by uranium and municipal
solid waste. For some plant types there are several options shown to better represent the range of
plants that might be built and their costs. For example, both single unit and dual unit advanced
pulverized coal plants are shown, because many plants include multiple units and the costs
associated with the dual unit configuration might better reflect the costs of most plants built.
Similarly, solar photovoltaic technologies include a relatively small 7 MW system and a much
larger 150 MW system, because there is such variance in the sizes of the facilities being
considered. The nominal capacity of the generic plants ranges from a 7 megawatt (MW) solar
plant to a 2,236 MW advanced dual-unit nuclear plant, reflecting the significant variation in the
scale of utility applications. Each technology is characterized by its overnight capital costs, heat
rate (where applicable), non-fuel operations and maintenance costs, and, though not shown in
Table 1, its environmental characteristics.

Table 2 compares the updated overnight cost estimates to those used as inputs to the AEO2010.
To facilitate comparisons, both are shown in real year 2010 dollars. Notable changes between
the updated estimates and the AEO2010 values include:

� Coal & Nuclear: The updated overnight capital cost estimates for coal and nuclear
power plants are 25 to 37 percent above those in AEO2010. The higher cost estimates
reflect many factors including the overall trend of rising costs of capital intensive
technology in the power sector, higher global commodity prices, and the fact that there
are relatively few construction firms with the ability to complete complex engineering
projects such as a new nuclear or advanced coal power plant. The study assumes cost-
sharing agreements between the project owner and the project construction contractors
are reflective of those recently observed in the marketplace. As shown in Table 1, dual
unit coal and nuclear plants generally have lower overnight costs per kilowatt than single-
unit plants, reflecting their ability to take advantage of redundancies and scale economies
in onsite infrastructure such as wastewater management and environmental controls to
reduce the estimated total per-kilowatt cost of the project.
� Natural Gas: The updated cost estimates for natural gas combined cycle and combustion
turbines generally remained similar to those of AEO2010.
� Solar: The overnight capital costs for solar thermal and photovoltaic technologies
dropped by 10 percent and 25 percent, respectively. The decrease in the cost of
photovoltaics was due to the assumption of larger plant capacity and falling component
costs.

3
� Onshore Wind: Overnight costs for onshore wind increased by about 21 percent relative
to AEO 2010 assumptions. This is based on a specification for a new, stand-alone wind
plant including all owners’ costs and may differ from other reported costs in the literature,
which are not fully characterized and may include sites that are built along side existing
plants (and are thus able to avoid some amount of infrastructure costs).
� Offshore Wind: While offshore wind plants have been built in Europe, there have only
been proposals in the United States, with final permitting only recently issued on the first
of these proposals. The updated costs, some 50 percent higher than AEO 2010 estimates,
are consistent with substantial first-of-a-kind costs that would likely be encountered when
building projects in the United States, which largely lacks the unique infrastructure,
needed to support this type of construction.
� Geothermal: Geothermal costs are highly site-specific, and are represented as such in the
AEO estimates. The updated cost estimate is over 50 percent higher than the same site in
AEO 2010.
� Biomass: Biomass capital costs are largely unchanged from AEO2010. However, the
technology represented by the costs has changed significantly. Prior estimates were for a
highly efficient plant employing gasification and a combined cycle generator; the new
estimate is for a significantly less efficient direct combustion boiler. The lower operating
efficiency (and therefore higher operating cost) for the biomass plant considered in the
updated cost estimate implies a reduced attractiveness of investment in new biomass
generation at an overnight cost similar to that for the more efficient biomass plant
characterized in AEO2010.

While estimates of the current cost of generic electric generation capacity of various types are
one key input to EIA’s analysis of electricity markets, the evolution of the electricity mix in each
of the 22 regions to be modeled in AEO20113 is also sensitive to many other factors, including
the projected evolution of capital costs over the modeling horizon, projected fuel costs, whether
wholesale power markets are regulated or competitive, the existing generation mix, additional
costs associated with environmental control requirements, load growth, and the load shape.
Almost all of these factors can vary by region, as do capacity factors for renewable generation,
operations and maintenance costs associated with individual plants, and cost multipliers applied
to the generic estimates of overnight capital costs outlined in Tables 1 and 2. The next section
provides a brief overview of some of the relevant issues, which are described in more detail in
the description of the Electric Market Module included in the 2010 edition of the documentation
for EIA’s National Energy Modeling System.

EIA’s Analysis of Technology Choice in the Electric Power Sector

Estimates of the overnight capital cost of generic generating technologies are only the starting
point for consideration of the cost of new generating capacity in EIA modeling analyses. EIA
also considers regional variation in construction costs, the structure of wholesale power markets
that affect financing costs, the length of time required to bring each type of plant into service,
and the capacity availability factors for solar and wind generation plants. EIA also accounts for

3
In AEO2010 and prior editions, the continental U.S., excluding Alaska, was divided in 13 regions for purposes of
electricity modeling. The 22 region model that will be used starting with AEO2011 will allow for better
representation of policy boundaries and market structure at the State level.

4
three distinct dynamic forces that drive changes in plant cost over time. One is the projected
relationship between rate of inflation for key drivers of plant costs, such as materials and
construction costs, and the overall economy-wide rate of inflation. A projected economy–wide
inflation rate that exceeds projected inflation for key plant cost drivers results in a projected
decline in real (inflation-adjusted) capital costs. Projected capital costs also reflect projected
technology progress over time. Learning-by-doing, which allows for additional reductions in
projected capital costs as a function of cumulative additions new technologies, has a further
effect on technology costs. See the AEO2010 assumptions and model documentation for more
details.4

Levelized cost is often cited as a convenient summary measure of the overall competiveness of
different generating technologies. Levelized cost represents the present value of the total cost of
building and operating a generating plant over an assumed economic life, converted to equal
annual payments and expressed in terms of real dollars to remove the impact of inflation.
Levelized costs, which reflect overnight capital cost, fuel cost, fixed and variable O&M cost, are
a useful indicator of the competitiveness of different generation technologies. For technologies
such as solar and wind generation that have no fuel costs and relatively small O&M costs,
levelized cost changes in rough proportion to the estimated overnight capital cost of generation
capacity. For technologies with significant fuel cost, both fuel cost and overnight cost estimates
significantly affect levelized cost. Thus, while Table 2 shows little change between the updated
capital cost estimates for natural gas combined cycle plants and those used in AEO2010,
improved supply prospects for natural gas that will be incorporated in AEO2011 result in lower
projected prices that in turn lower the levelized cost of gas-fired generation and improve the
attractiveness of operating and adding gas-fired generation technologies.

It is important to note, however, that actual investment decisions are affected by numerous
factors other than levelized costs. The projected utilization rate, which depends on the load
shape and the existing resource mix in an area where additional capacity is needed, is one such
factor. The existing resource mix in a region can directly affect the economic viability of a new
investment through its effect on the economics surrounding the displacement of existing
resources. For example, a wind resource that would primarily back out existing natural gas
generation will generally have a higher value than one that would back out existing coal
generation under fuel price conditions where the variable cost of operating existing gas-fired
plants exceeds that of operating existing coal-fired plants.

A related factor is the capacity value, which depends on both the existing capacity mix and load
characteristics in a region. Since load must be balanced on a continuous basis, units whose
output can be varied to follow demand generally have more value to a system than less flexible
units or those whose operation is tied to the availability of an intermittent resource. Policy-
related factors, such as investment or production tax credits for specified generation sources, can
also impact investment decisions. Finally, although levelized cost calculations are generally
made using an assumed set of capital and operating costs, the inherent uncertainty about future
fuel prices and future policies, may cause plant owners or investors who finance plants to place a

4
Assumptions and model documentation for the 2010 Annual Energy Outlook are available at
http://www.eia.doe.gov/oiaf/aeo/index.html.

5
value on portfolio diversification. EIA considers all of these factors in its analyses of
technology choice in the electricity sector.

In sum, while overnight cost estimates are important inputs for EIA modelers and other analysts,
they are not the sole driver of the choice among electric generation technologies. Users
interested in additional details regarding these updated cost estimates should review the
consultant study prepared by R.W. Beck for EIA in Appendix A.

6
Table 1. Updated Estimates of Power Plant Capital and Operating Costs

Plant Characteristics Plant Costs


Variable
Overnight O&M
Nominal Capital Fixed O&M Cost
Capacity Heat Rate Cost (2010 Cost (2010
(kilowatts) (Btu/kWh) $/kW) (2010$/kW) $/MWh)
Coal
Single Unit
Advanced PC 650,000 8,800 $3,167 $35.97 $4.25
Dual Unit
Advanced PC 1,300,000 8,800 $2,844 $29.67 $4.25
Single Unit Advanced PC with CCS 650,000 12,000 $5,099 $76.62 $9.05
Dual Unit Advanced PC with CCS 1,300,000 12,000 $4,579 $63.21 $9.05
Single Unit IGCC 600,000 8,700 $3,565 $59.23 $6.87
Dual Unit IGCC 1,200,000 8,700 $3,221 $48.90 $6.87
Single Unit IGCC with CCS 520,000 10,700 $5,348 $69.30 $8.04
Natural Gas
Conventional NGCC 540,000 7,050 $978 $14.39 $3.43
Advanced NGCC 400,000 6,430 $1,003 $14.62 $3.11
Advanced NGCC with CCS 340,000 7,525 $2,060 $30.25 $6.45
Conventional CT 85,000 10,850 $974 $6.98 $14.70
Advanced CT 210,000 9,750 $665 $6.70 $9.87
Fuel Cells 10,000 9,500 $6,835 $350 $0.00
Uranium
Dual Unit Nuclear 2,236,000 N/A $5,335 $88.75 $2.04
Biomass
Biomass CC 20,000 12,350 $7,894 $338.79 $16.64
Biomass BFB 50,000 13,500 $3,860 $100.50 $5.00
Wind
Onshore Wind 100,000 N/A $2,438 $28.07 $0.00
Offshore Wind 400,000 N/A $5,975 $53.33 $0.00
Solar
Solar Thermal 100,000 N/A $4,692 $64.00 $0.00
Small Photovoltaic 7,000 N/A $6,050 $26.04 $0.00
Large Photovoltaic 150,000 N/A $4,755 $16.7 $0.00
Geothermal
Geothermal – Dual Flash 50,000 N/A $5,578 $84.27 $9.64
Geothermal – Binary 50,000 NA $4,141 $84.27 $9.64
MSW
MSW 50,000 18,000 $8,232 $373.76 $8.33
Hydro
Hydro-electric 500,000 N/A $3,076 $13.44 $0.00
Pumped Storage 250,000 N/A $5,595 $13.03 $0.00

7
Table 2. Comparison of Updated Plant Costs to AEO2010 Plant Costs

Table II
Overnight Capital Cost ($/kW) Nominal Capacity KW's1
AEO AEO % AEO
AEO 2010
2011 2010 Change 2011
Coal
Advanced PC w/o CCS $2,844 $2,271 25% 1,300,000 600,000
IGCC w/o CCS $3,221 $2,624 23% 1,200,000 550,000
IGCC CCS $5,348 $3,857 39% 600,000 380,000
Natural Gas
Conventional NGCC $978 $1,005 -3% 540,000 250,000
Advanced NGCC $1,003 $989 1% 400,000 400,000
Advanced NGCC with
$2,060 $1,973 4% 340,000 400,000
CCS
Conventional CT $974 $700 39% 85,000 160,000
Advanced CT $665 $662 0% 210,000 230,000
Fuel Cells $6,835 $5,595 22% 10,000 10,000
Nuclear
Nuclear $5,339 $3,902 37% 2,236,000 1,350,000
Renewables
Biomass $3,860 $3,931 -2% 50,000 80,000
Geothermal $4,141 $1,786 132% 50,000 50,000
MSW - Landfill Gas $8,232 $2,655 210% 50,000 30,000
Conventional
$3,078 $2,340 53% 500,000 500,000
Hydropower
Wind $2,438 $2,007 21% 100,000 50,000
Wind Offshore $5,975 $4,021 49% 400,000 100,000
Solar Thermal $4,692 $5,242 -10% 100,000 100,000
Photovoltaic $4,755 $6,303 -25% 150,000 5,000
1
Higher plant capacity reflects the assumption that plants would install multiple units per
site and that savings could could be gained by eliminating redundancies and combining
services.

8
Appendix A

9
EOP III TASK 1606, SUBTASK 3 – REVIEW OF
POWER PLANT COST AND PERFORMANCE
ASSUMPTIONS FOR NEMS
Technology Documentation Report
R. W. Beck, Inc.
Science Applications International Corporation (SAIC)

Prepared by:
Vincent Hahn, R. W. Beck
John Fix, R. W. Beck
John Schmalz, R. W. Beck
Michael Wennen, R. W. Beck
Evis Couppis, Ph.D., R. W. Beck

Prepared in Coordination with:


Jay Ratafia-Brown, SAIC

Prepared For:
Energy Information Administration
Office of Integrated Analysis and Forecasting
Alan Beamon
Michael Leff

October 2010
Disclaimer

Certain statements included in this report constitute forward-looking statements. The achievement of certain results
or other expectations contained in such forward-looking statements involve known and unknown risks, uncertainties
and other factors which may cause actual results, performance or achievements described in the report to be
materially different from any future results, performance or achievements expressed or implied by such
forward-looking statements. We do not plan to issue any updates or revisions to the forward-looking statements if
or when our expectations or events, conditions, or circumstances on which such statements are based occur.
TABLE OF CONTENTS
1. Introduction ................................................................................................................. 1-1
1.1 Technologies Assessed .......................................................................................... 1-1

2. General Basis for Technology Evaluation Basis ...................................................... 2-1


2.1 R. W. Beck Background ........................................................................................ 2-1
2.2 Base Fuel Characteristics ...................................................................................... 2-1
2.3 Environmental Compliance Basis ......................................................................... 2-4
2.4 Local Capacity Adjustments ................................................................................. 2-4
2.5 Technology Specifications .................................................................................... 2-6
2.6 Cost Estimation Methodology ............................................................................... 2-6
2.6.1 Capital Cost ............................................................................................................ 2-6
2.6.1.1 Costing Scope .................................................................................................. 2-6
2.6.2 Operation and Maintenance (O&M) Expenses ...................................................... 2-7
2.6.2.1 Fixed O&M (FOM).......................................................................................... 2-8
2.6.2.2 Variable O&M (VOM) .................................................................................... 2-8
2.6.2.3 Major Maintenance .......................................................................................... 2-8

3. Advanced Pulverized Coal (APC) ............................................................................. 3-1


3.1 Mechanical Equipment and Systems..................................................................... 3-1
3.2 Electrical and Control Systems ............................................................................. 3-2
3.3 Off-Site Requirements ........................................................................................... 3-2
3.4 Capital Cost Estimate ............................................................................................ 3-3
3.5 O&M Estimate ...................................................................................................... 3-8
3.6 Environmental Compliance Information ............................................................... 3-8

4. Advanced Pulverized Coal With CCS (APC/CCS).................................................. 4-1


4.1 Mechanical Equipment and Systems..................................................................... 4-1
4.2 Electrical and Control Systems ............................................................................. 4-2
4.3 Off-Site Requirements ........................................................................................... 4-2
4.4 Capital Cost Estimate ............................................................................................ 4-2
4.5 O&M Estimate ...................................................................................................... 4-7
4.6 Environmental Compliance Information ............................................................... 4-8

i
5. Conventional Natural Gas Combined Cycle (NGCC) ............................................. 5-1
5.1 Mechanical Equipment and Systems..................................................................... 5-1
5.2 Electrical and Control Systems ............................................................................. 5-2
5.3 Off-Site Requirements ........................................................................................... 5-2
5.4 Capital Cost Estimate ............................................................................................ 5-3
5.5 O&M Estimate ...................................................................................................... 5-6
5.6 Environmental Compliance Information ............................................................... 5-7

6. Advanced Generation Natural Gas Combined Cycle (AG-NGCC) ....................... 6-1


6.1 Mechanical Equipment and Systems..................................................................... 6-1
6.2 Electrical and Control Systems ............................................................................. 6-1
6.3 Off-Site Requirements ........................................................................................... 6-1
6.4 Capital Cost Estimate ............................................................................................ 6-1
6.5 O&M Estimate ...................................................................................................... 6-4
6.6 Environmental Compliance Information ............................................................... 6-4

7. Advanced Generation Natural Gas Combined Cycle With CCS


(AG-NGCC/CCS)........................................................................................................ 7-1
7.1 Mechanical Equipment and Systems..................................................................... 7-1
7.2 Electrical and Control Systems ............................................................................. 7-1
7.3 Off-Site Requirements ........................................................................................... 7-1
7.4 Capital Cost Estimate ............................................................................................ 7-1
7.5 O&M Estimate ...................................................................................................... 7-4
7.6 Environmental Compliance Information ............................................................... 7-4

8. Conventional Combustion Turbine (CT).................................................................. 8-1


8.1 Mechanical Equipment and Systems..................................................................... 8-1
8.2 Electrical and Control Systems ............................................................................. 8-1
8.3 Off-Site Requirements ........................................................................................... 8-1
8.4 Capital Cost Estimate ............................................................................................ 8-2
8.5 O&M Estimate ...................................................................................................... 8-5
8.6 Environmental Compliance Information ............................................................... 8-6

9. Advanced Combustion Turbine (ACT) .................................................................... 9-1


9.1 Mechanical Equipment and Systems..................................................................... 9-1
9.2 Electrical and Control Systems ............................................................................. 9-1

ii
9.3 Off-Site Requirements ........................................................................................... 9-1
9.4 Capital Cost Estimate ............................................................................................ 9-1
9.5 O&M Estimate ...................................................................................................... 9-4
9.6 Environmental Compliance Information ............................................................... 9-4

10. Integrated Gasification Combined Cycle (IGCC) ................................................. 10-1


10.1 Mechanical Equipment and Systems................................................................... 10-1
10.2 Electrical and Control Systems ........................................................................... 10-3
10.3 Off-Site Requirements ......................................................................................... 10-3
10.4 Capital Cost Estimate .......................................................................................... 10-4
10.5 O&M Estimate .................................................................................................. 10-10
10.6 Environmental Compliance Information ........................................................... 10-11

11. Integrated Gasification Combined Cycle With CCS (IGCC/CCS) ...................... 11-1
11.1 Mechanical Equipment and Systems................................................................... 11-1
11.2 Electrical and Control Systems ........................................................................... 11-1
11.3 Off-Site Requirements ......................................................................................... 11-1
11.4 Capital Cost Estimate .......................................................................................... 11-1
11.5 O&M Estimate .................................................................................................... 11-4
11.6 Environmental Compliance Information ............................................................. 11-4

12. Advanced Nuclear (AN) ........................................................................................... 12-1


12.1 Mechanical Equipment and Systems................................................................... 12-1
12.2 Electrical and Control Systems ........................................................................... 12-2
12.3 Off-Site Requirements ......................................................................................... 12-3
12.4 Capital Cost Estimate .......................................................................................... 12-3
12.5 O&M Estimate .................................................................................................... 12-7
12.6 Environmental Compliance Information ............................................................. 12-7

13. Biomass Combined Cycle (BCC) ............................................................................. 13-1


13.1 Mechanical Equipment and Systems................................................................... 13-1
13.2 Electrical and Control Systems ........................................................................... 13-2
13.3 Off-Site Requirements ......................................................................................... 13-3

iii
13.4 Capital Cost Estimate .......................................................................................... 13-3
13.5 O&M Estimate .................................................................................................... 13-7
13.6 Environmental Compliance Information ............................................................. 13-8

14. Biomass Bubbling Fluized Bed (BBFB) .................................................................. 14-1


14.1 Mechanical Equipment and Systems................................................................... 14-1
14.2 Electrical and Control Systems ........................................................................... 14-2
14.3 Off-Site Requirements ......................................................................................... 14-2
14.4 Capital Cost Estimate .......................................................................................... 14-2
14.5 O&M Estimate .................................................................................................... 14-6
14.6 Environmental Compliance Information ............................................................. 14-7

15. Fuel Cell (FC) Mechanical Equipment and Systems ............................................. 15-1
15.1 Electrical and Control Systems ........................................................................... 15-1
15.2 Off-Site Requirements ......................................................................................... 15-1
15.3 Capital Cost Estimate .......................................................................................... 15-2
15.4 O&M Estimate .................................................................................................... 15-5
15.5 Environmental Compliance Information ............................................................. 15-6

16. Geothermal Dual Flash (GT) ................................................................................... 16-1


16.1 Mechanical Equipment and Systems................................................................... 16-1
16.2 Electrical and Control Systems ........................................................................... 16-2
16.3 Off-Site Requirements ......................................................................................... 16-2
16.4 Capital Cost Estimate .......................................................................................... 16-3
16.5 O&M Estimate .................................................................................................... 16-6
16.6 Environmental Compliance Information ............................................................. 16-6

17. Geothermal Binary (Binary) .................................................................................... 17-1


17.1 Mechanical Equipment and Systems................................................................... 17-1
17.2 Electrical and Control Systems ........................................................................... 17-1
17.3 Off-Site Requirements ......................................................................................... 17-2
17.4 Capital Cost Estimate .......................................................................................... 17-2
17.5 O&M Estimate .................................................................................................... 17-5
17.6 Environmental Compliance Information ............................................................. 17-6

iv
18. Municipal Solid Waste (MSW) ................................................................................ 18-1
18.1 Mechanical Equipment and Systems................................................................... 18-1
18.2 Electrical and Control Systems ........................................................................... 18-2
18.3 Off-Site Requirements ......................................................................................... 18-2
18.4 Capital Cost Estimate .......................................................................................... 18-2
18.5 O&M Estimate .................................................................................................... 18-5
18.6 Environmental Compliance Information ............................................................. 18-6

19. Hydroelectric (HY) ................................................................................................... 19-1


19.1 Mechanical Equipment and Systems................................................................... 19-1
19.2 Electrical and Control Systems ........................................................................... 19-1
19.3 Off-Site Requirements ......................................................................................... 19-1
19.4 Capital Cost Estimate .......................................................................................... 19-2
19.5 O&M Estimate .................................................................................................... 19-5
19.6 Environmental Compliance Information ............................................................. 19-5

20. Pumped Storage (PS) ................................................................................................ 20-1


20.1 Mechanical Equipment and Systems................................................................... 20-1
20.2 Electrical and Control Systems ........................................................................... 20-1
20.3 Off-Site Requirements ......................................................................................... 20-1
20.4 Capital Cost Estimate .......................................................................................... 20-2
20.5 O&M Estimate .................................................................................................... 20-5
20.6 Environmental Compliance Information ............................................................. 20-5

21. Onshore Wind (WN) ................................................................................................. 21-1


21.1 Mechanical Equipment and Systems................................................................... 21-1
21.2 Electrical and Control Systems ........................................................................... 21-2
21.3 Off-Site Requirements ......................................................................................... 21-2
21.4 Capital Cost Estimate .......................................................................................... 21-2
21.5 O&M Estimate .................................................................................................... 21-5
21.6 Environmental Compliance Information ............................................................. 21-6

22. Offshore Wind (WF) ................................................................................................. 22-1


22.1 Mechanical Equipment and Systems................................................................... 22-1
22.2 Electrical and Control Systems ........................................................................... 22-2

v
22.3 Off-Site Requirements ......................................................................................... 22-2
22.4 Capital Cost Estimate .......................................................................................... 22-3
22.5 O&M Estimate .................................................................................................... 22-6
22.6 Environmental Compliance Information ............................................................. 22-6

23. Solar Thermal - Central Station (SO) ..................................................................... 23-1


23.1 Mechanical Equipment and Systems................................................................... 23-1
23.2 Electrical and Control Systems ........................................................................... 23-2
23.3 Off-Site Requirements ......................................................................................... 23-3
23.4 Capital Cost Estimate .......................................................................................... 23-3
23.5 O&M Estimate .................................................................................................... 23-7
23.6 Environmental Compliance Information ............................................................. 23-7

24. Photovoltaic (Central Station) Facility (PV) .......................................................... 24-1


24.1 Mechanical Equipment and Systems................................................................... 24-1
24.2 Electrical and Control Systems ........................................................................... 24-1
24.3 Off-Site Requirements ......................................................................................... 24-2
24.4 Capital Cost Estimate .......................................................................................... 24-2
24.5 O&M Estimate .................................................................................................... 24-9
24.6 Environmental Compliance Information ........................................................... 24-10

vi
LIST OF FIGURES

Figure 3-1 – Advanced Pulverized Coal Design Configuration .................................................. 3-2


Figure 4-1 – APC Facility Diagram ............................................................................................. 4-1
Figure 5-1 – Conventional NGCC Design Configuration ........................................................... 5-2
Figure 6-1 – AG-NGCC Design Configuration ........................................................................... 6-1
Figure 7-1 – AG-NGCC With CCS Design Configuration ......................................................... 7-1
Figure 8-1 – Conventional CT Design Configuration ................................................................. 8-1
Figure 9-1 – Advanced CT Design Configuration ....................................................................... 9-1
Figure 10-1 – IGCC Design Configuration ............................................................................... 10-3
Figure 11-1 – IGCC/CCS Design Configuration ....................................................................... 11-1
Figure 12-1 – AN Design Configuration ................................................................................... 12-2
Figure 13-1 – BCC Design Configuration ................................................................................. 13-2
Figure 14-1 – BCC Design Configuration ................................................................................. 14-1
Figure 15-1 – FC Design Configuration .................................................................................... 15-1
Figure 16-1 – GT Design Configuration .................................................................................... 16-2
Figure 17-1 – GT Design Configuration .................................................................................... 17-1
Figure 19-1 – HY Design Configuration ................................................................................... 19-1
Figure 20-1 – PS Design Configuration..................................................................................... 20-1
Figure 21-1 – WN Design Configuration .................................................................................. 21-1
Figure 22-1 – WF Design Configuration ................................................................................... 22-2
Figure 23-1 – SO Design Configuration .................................................................................... 23-2
Figure 24-1 – PV Design Configuration .................................................................................... 24-1

vii
LIST OF TABLES

Table 1-1 – List of Technologies For Review ............................................................................. 1-2


Table 2-1 – Reference Coal Specification ................................................................................... 2-2
Table 2-2 – Natural Gas Specification ......................................................................................... 2-3
Table 2-3 – Wood-Biomass Specification ................................................................................... 2-3
Table 2-4 – CT Capacity Adjustments......................................................................................... 2-5
Table 2-5 – Technology Performance Specifications ................................................................ 2-10
Table 3-1 – Base Plant Site Capital Cost Estimate for APC........................................................ 3-3
Table 3-2 – Base Plant Site Capital Cost Estimate for APC........................................................ 3-4
Table 3-3 – Location-Based Costs for APC (650,000 kW) ......................................................... 3-5
Table 3-4 – Location-Based Costs for APC (1,300,000 kW) ...................................................... 3-7
Table 3-5 – O&M Expenses for APC (650,000 kW)................................................................... 3-8
Table 3-6 – O&M Expenses for APC (1,300,000 kW)................................................................ 3-8
Table 3-7 – Environmental Emissions for APC .......................................................................... 3-9
Table 4-1 – Base Plant Site Capital Cost Estimate for APC/CCS ............................................... 4-3
Table 4-2 – Base Plant Site Capital Cost Estimate for APC/CCS ............................................... 4-3
Table 4-3– Location-Based Costs for APC/CCS Facility (650,000 kW) .................................... 4-4
Table 4-4 – Location-Based Costs for APC/CCS Facility (1,300,000 kW) ................................ 4-6
Table 4-5 – O&M Expenses for APC/CCS (650,000 kW) .......................................................... 4-7
Table 4-6 – O&M Expenses for APC/CCS (1,300,000 kW) ....................................................... 4-8
Table 4-7 – Environmental Emissions for APC/CCS .................................................................. 4-8
Table 5-1 – Base Plant Site Capital Cost Estimate for Conventional NGCC .............................. 5-3
Table 5-2 – Location-Based Costs for Conventional NGCC....................................................... 5-5
Table 5-3 – O&M Expenses for Conventional NGCC ................................................................ 5-7
Table 5-4 – Environmental Emissions for Conventional NGCC................................................. 5-7
Table 6-1 – Base Plant Site Capital Cost Estimate for AG-NGCC ............................................. 6-2
Table 6-2 – Location-Based Costs for AG-NGCC ...................................................................... 6-3
Table 6-3 – O&M Expenses for AG-NGCC................................................................................ 6-4
Table 6-4 – Environmental Emissions for AG-NGCC ................................................................ 6-5
Table 7-1 – Base Plant Site Capital Cost Estimate for AG-NGCC/CCS Cost ............................ 7-2
Table 7-2 – Location-Based Costs for AG-NGCC/CCS ............................................................. 7-3

viii
Table 7-3 – O&M Expenses for AG-NGCC With CCS .............................................................. 7-4
Table 7-4 – Environmental Emissions for AG-NGCC/CCS ....................................................... 7-5
Table 8-1 – Base Plant Site Capital Cost Estimate for Conventional CT.................................... 8-2
Table 8-2 – Location-Based Costs for Conventional CT............................................................. 8-4
Table 8-3 – O&M Expenses for Conventional CT ...................................................................... 8-6
Table 8-4 – Environmental Emissions for Conventional CT....................................................... 8-6
Table 9-1 – Base Plant Site Capital Cost Estimate for Advanced CT ......................................... 9-2
Table 9-2 – Location-Based Costs for Advanced CT .................................................................. 9-3
Table 9-3 – O&M Expenses for Advanced CT ........................................................................... 9-4
Table 9-4 – Environmental Emissions for Advanced CT ............................................................ 9-5
Table 10-1 – Base Plant Site Capital Cost Estimate for IGCC .................................................. 10-4
Table 10-2 – Base Plant Site Capital Cost Estimate for IGCC .................................................. 10-5
Table 10-3 – Location-Based Costs for IGCC (600,000 kW) ................................................... 10-7
Table 10-4 – Location-Based Costs for IGCC (1,200,000 kW) ................................................ 10-9
Table 10-5 – O&M Expenses for IGCC (600,000 kW) ........................................................... 10-10
Table 10-6 – O&M Expenses for IGCC (1,200,000 kW) ........................................................ 10-11
Table 10-7 – Environmental Emissions for IGCC ................................................................... 10-11
Table 11-1 – Base Plant Site Capital Cost Estimate for IGCC/CCS ......................................... 11-2
Table 11-2 – Location-Based Costs for IGCC/CCS .................................................................. 11-3
Table 11-3 – O&M Expenses for IGCC/CCS............................................................................ 11-4
Table 11-4 – Environmental Emissions for IGCC/CCS ............................................................ 11-5
Table 12-1 – Base Plant Site Capital Cost Estimate for AN...................................................... 12-4
Table 12-2 – Location-Based Costs for AN .............................................................................. 12-5
Table 12-3 – O&M Expenses for AN ........................................................................................ 12-7
Table 12-4 – Environmental Emissions for AN ........................................................................ 12-7
Table 13-1 – Base Plant Site Capital Cost Estimate for BCC ................................................... 13-4
Table 13-2 – Location-Based Costs for BCC ............................................................................ 13-6
Table 13-3 – O&M Expenses for BCC ...................................................................................... 13-7
Table 13-4 – Environmental Emissions for BCC ...................................................................... 13-8
Table 14-1 – Base Plant Site Capital Cost Estimate for BBFB ................................................. 14-3
Table 14-2– Location-Based Costs for BBFB ........................................................................... 14-5
Table 14-3 – O&M Expenses for BCC ...................................................................................... 14-6
Table 14-4 – Environmental Emissions for BBFB .................................................................... 14-7

ix
Table 15-1 – Base Plant Site Capital Cost Estimate for FC ...................................................... 15-2
Table 15-2 – Location-Based Costs for FC ............................................................................... 15-4
Table 15-3 – O&M Expenses for FC ......................................................................................... 15-5
Table 15-4 – Environmental Emissions for FC ......................................................................... 15-6
Table 16-1 – Base Plant Site Capital Cost Estimate for GT ...................................................... 16-3
Table 16-2 – Location-Based Costs for GT ............................................................................... 16-5
Table 16-3 – O&M Expenses for GT ........................................................................................ 16-6
Table 16-4 – Environmental Emissions for GT ......................................................................... 16-7
Table 17-1 – Base Plant Site Capital Cost Estimate for GT ...................................................... 17-2
Table 17-2 – Location-Based Costs for GT ............................................................................... 17-4
Table 17-3 – O&M Expenses for Binary ................................................................................... 17-5
Table 17-4 – Environmental Emissions for Binary ................................................................... 17-6
Table 18-1 – Base Plant Site Capital Cost Estimate for MSW .................................................. 18-3
Table 18-2 – Location-Based Costs for MSW ........................................................................... 18-4
Table 18-3 – O&M Expenses for MSW .................................................................................... 18-6
Table 18-4 – Environmental Emissions for MSW ..................................................................... 18-6
Table 19-1 – Base Plant Site Capital Cost Estimate for HY...................................................... 19-2
Table 19-2 – Location-Based Costs for HY .............................................................................. 19-4
Table 19-3 – O&M Expenses for HY ........................................................................................ 19-5
Table 19-4 – Environmental Emissions for HY ........................................................................ 19-6
Table 20-1 – Base Plant Site Capital Cost Estimate for PS ....................................................... 20-2
Table 20-2 – Location-Based Costs for PS ................................................................................ 20-4
Table 20-3 – O&M Expenses for PS ......................................................................................... 20-5
Table 20-4 – Environmental Emissions for PS .......................................................................... 20-6
Table 21-1 – Location-Based Costs for WN.............................................................................. 21-3
Table 21-2 – Location-Based Costs for WN.............................................................................. 21-4
Table 21-3 – O&M Expenses for WN ....................................................................................... 21-6
Table 21-4 – Environmental Emissions for WN........................................................................ 21-6
Table 22-1 – Base Plant Site Capital Cost Estimate for WF ..................................................... 22-3
Table 22-2 – Location-Based Costs for WF .............................................................................. 22-5
Table 23-1 – Base Plant Site Capital Cost Estimate for SO ...................................................... 23-4
Table 23-2 – Location-Based Costs for SO ............................................................................... 23-6
Table 23-3 – O&M Expenses for SO......................................................................................... 23-7

x
Table 23-4 – Environmental Emissions for SO ......................................................................... 23-8
Table 24-1 – Base Plant Site Capital Cost Estimate for PV ...................................................... 24-3
Table 24-2 – Base Plant Site Capital Cost Estimate for PV ...................................................... 24-4
Table 24-3 – Location-Based Costs for PV (7 MW) ................................................................. 24-6
Table 24-4 – Location-Based Costs for PV (150 MW) ............................................................. 24-8
Table 24-5 – O&M Expenses for PV Facility (7 MW) ............................................................. 24-9
Table 24-6 – O&M Expenses for PV Facility (150 MW) ......................................................... 24-9
Table 24-7 – Environmental Emissions for PV ....................................................................... 24-10

xi
LIST OF ACRONYMS AND ABBREVIATIONS

AC Alternating Current
AG Advanced Generation
AG Advanced Generation
AG-NGCC Advanced Generation Natural Gas Combined Cycle
AG-NGCC/CCS Advanced Generation Natural Gas Combined Cycle with CCS
AGR Acid Gas Removal
AN Advanced Nuclear
APC Advanced Pulverized Coal Facility
APC/CCS Advanced Pulverized Coal with CCS
ASU Air Separation Unit
BACT Best Available Control Technology
BCC Biomass Combined Cycle
BBFB Biomass Bubbling Fluidized Bed
BFB Bubbling Fluidized Bed
BOP Balance-of-Plant
BPF Brine Processing Facility
Btu British Thermal Unit
C Carbon
CCS Carbon Capture and Sequestration
CFB Circulating Fluidized Bed
C2H6 Ethane
C3H8 Propane
C4H10 n-Butane
CH4 Methane
CO Carbon Monoxide
CO2 Carbon Dioxide
COS Carbonyl Sulfide
CT Combustion Turbine
DC Direct Current
DCS Distributed Control System
DLN Dry Low-NOX Combustion
EIA Energy Information Administration
EMM Electricity Market Module of NEMS
EPC Engineering, Procurement and Construction
�F Degrees Fahrenheit
FC Fuel Cell
FGD Flue Gas Desulfurization
FOM Fixed O&M
Geothermal GT
GHG Greenhouse Gas
GSU Generator Step-up Transformer
GT Geothermal
H2S Hydrogen Sulfide

xii
HHV High(er) Heating Value
HP High Pressure
HRSG Heat Recovery Steam Generator
HY Hydroelectric
Hz Hertz
I&C Instrumentation and Controls
IGCC Integrated Gasification Combined Cycle
IGCC/CCS Integrated Gasification Combined Cycle Carbon Capture and Sequestration
IP Intermediate Pressure
kg Kilograms
KJ Kilojoules
kW Kilowatt
kWh Kilowatt-hour
kV Kilovolt
kVA kilovolt-amperes
lb Pound
LHV Low(er) Heating Value
CLP Low Pressure
MEA Monoethanolamine
MJ Mega joules
MMBtu Million Btu
MSW Municipal Solid Waste
MW Megawatt
MWe Megawatts Electric
MWh Megawatt-hour
MVA Mega-volt-amperes
N2 Nitrogen
NEMS National Energy Modeling System
NGCC Natural Gas Combined Cycle
NH3 Ammonia
NOX Oxides of Nitrogen
O2 Oxygen
O&M Operating and Maintenance
NOx Nitrogen Oxides
ppmvd Parts per Million Volume Dry
PS Pumped Storage
psia Pounds per Square Inch Absolute
PV Photovoltaic
PWR Pressurized Water Reactor
RCS Reactor Coolant System
S Sulfur
SCADA Supervisory Control and Data Acquisition
scf Standard Cubic Feet
scm Standard Cubic Meters
SCR Selective Catalytic Reduction
SNCR Selective Non-catalytic Reduction

xiii
SO Solar Thermal
SO2 Sulfur Dioxide
SRU Sulfur Recovery Unit
ST Steam Turbine
TGF Turbine Generating Facility
U.S. United States
V Volt
VOM Variable Operating and Maintenance
WF Offshore Wind
WFGD Wet Flue Gas Desulfurization
WN Onshore Wind
WTG Wind Turbine Generator
ZLD Zero Liquid Discharge

xiv
1. INTRODUCTION
This report presents R. W. Beck, Inc.’s (“R. W. Beck”) performance and cost assessment of
power generation technologies utilized by the Energy Information Administration (“EIA”) in the
Electricity Market Module (“EMM”) of the National Energy Modeling System (“NEMS”). The
assessment for each of the technologies considered includes the following:
� Overnight construction costs, construction lead times, first year of commercial
application, typical unit size, contingencies, fixed and variable operating costs, and
efficiency (heat rate). The analysis was conducted to ensure that the overnight cost
estimates developed for use in the EMM for electric generating technologies are
consistent in scope, accounting for all costs in the planning and development of a power
plant including the basic interconnection to the grid at the plant site, but excluding
financing costs.
� For emission control technologies, the removal rates for pollutants and other assumptions
were examined.
� Review of the regional multipliers that are used to represent local conditions, such as
labor rates that are included in EMM.
� Review of assumptions regarding how construction costs decline over time due to
technological advancement and “learning by doing.”
� Review of the appropriateness of technology-specific project and process contingency
assumptions (capturing differences between engineering estimates and realized costs for
new technologies).
� Where possible, compare the values used by EIA with those for recently built facilities in
the United States (“U.S.”) or abroad. Where such actual cost estimates do not exist, an
assessment was made between values used by EIA and other analyst estimates, as well as
vendor estimates.
� The key factors expected to drive each technology’s costs.
� Document the source and basis for final recommendations for altering or retaining the
various assumptions.

1.1 TECHNOLOGIES ASSESSED


The following table lists all technologies to be assessed in this project.

1-1
TABLE 1-1 – LIST OF TECHNOLOGIES FOR REVIEW
TECHNOLOGY DESCRIPTION COMMENTS
Advanced Pulverized Coal 650 megawatt-electrical (“MWe”) Greenfield Installation
and 1,300 MWe; supercritical; all
advanced pollution control
technologies
Advanced Pulverized Coal with 650 MWe and 1,300 MWe; Greenfield Installation
Carbon Capture and supercritical; all advanced
Sequestration (“CCS”) pollution control technologies,
including CCS technologies
Conventional Natural Gas 540 MWe; F-Class system
Combined Cycle (“NGCC”)
Advanced NGCC 400 MWe; H-Class system
Advanced NGCC with CCS 340 MWe; H-Class system
Conventional Combustion 85 MWe; E-Class turbine
Turbine (“CT”)
Advanced CT 210 MWe; F-Class turbine
Integrated Gasification 600 MWe and 1,200 MWe; F-
Combined Cycle (“IGCC”) Class-syngas system

IGCC with CCS 520 MWe; F-Class-syngas system


Advanced Nuclear 2,236 megawatt (“MW”); AP1000 Brownfield Installation
PWR Basis
Biomass Combined Cycle 20 MWe Wood Fuel
Biomass Bubbling Fluidized 50 MWe Wood Fuel
Bed (“BFB”)
Fuel Cells 10 MWe
Geothermal 50 MWe Dual Flash and Binary
Municipal Solid Waste 50 MWe
(“MSW”)
Hydroelectric 500 MWe
Pumped Storage 250 MWe
Wind Farm – Onshore 100 MWe
Wind Farm – Offshore 400 MWe
Solar Thermal – Central Station 100 MWe
Photovoltaic – Central Station 7 MWe and 150 MWe

1-2
2. GENERAL BASIS FOR TECHNOLOGY EVALUATION BASIS
This section specifies the general evaluation basis used for all technologies reviewed herein.

2.1 R. W. BECK BACKGROUND


R. W. Beck is an infrastructure consulting firm that has been providing technical and business
consulting in the energy industry since 1942. Particularly, R. W. Beck has supported the
purchase, sale, financing and Owner’s advisory consulting for tens-of-billions of dollars of
power plants across the world in all commercial power generating technologies as well as many
emerging technologies. This background has supported R. W. Beck’s acumen with respect to
construction costs, operating costs, technology development and evolution, as well as trends in
environmental regulation and compliance.

2.2 BASE FUEL CHARACTERISTICS


This section provides a general fuel basis for each of the fuel types utilized by the technologies
considered in this report and listed in Table 1-1. Each of the technologies that combust a fuel
has the ability to operate over a range of fuels; thus Table 2-1, Table 2-2 and Table 2-3 show a
typical fuel specification for coal, natural gas, and wood-biomass, respectively. MSW has such a
wide range of constituents; a typical analysis is not included here.

2-1
TABLE 2-1 – REFERENCE COAL SPECIFICATION
Rank Bituminous
Seam Illinois No. 6 (Herrin)
Source Old Ben Mine
Proximate Analysis (weight %) (Note A)
As Received Dry
Moisture 11.12 0.00
Ash 9.70 10.91
Volatile Matter 34.99 39.37
Fixed Carbon 44.19 49.72
Total 100.00 100.00
Sulfur 2.51 2.82
HHV (1), KJ/kg (2) 27,113 30,506
HHV, Btu/lb (3) 11,666 13,126
(4)
LHV , KJ/kg 26,151 29,544
LHV, Btu/lb 11,252 12,712
Ultimate Analysis (weight %)
As Received Dry
Moisture 11.12 0.00
Carbon 63.75 71.72
Hydrogen 4.50 5.06
Nitrogen 1.25 1.41
Chlorine 0.29 0.33
Sulfur 2.51 2.82
Ash 9.70 10.91
Oxygen 6.88 7.75
Total 100.00 100.00
(1) High(er) heating value (“HHV”).
(2) Kilojoules per kilogram (“KJ/kg”).
(3) British thermal units per pound (“Btu/lb”).
(4) Low(er) heating value (“LHV”).

2-2
TABLE 2-2 – NATURAL GAS SPECIFICATION
Component Volume Percentage
Methane CH4 93.9
Ethane C2H6 3.2
Propane C3H8 0.7
n-Butane C4H10 0.4
Carbon Dioxide CO2 1.0
Nitrogen N2 0.8
Total 100.0
LHV HHV
kJ/kg 47.764 52,970
MJ/scm (1) 35 39
Btu/lb 20,552 22,792
Btu/scf (2) 939 1,040
(1) Mega joules per standard cubic meter (“MJ/scm”).
(2) Standard cubic feet (“scf”).

TABLE 2-3 – WOOD-BIOMASS SPECIFICATION (1)


Component Volume Percentage
Moisture 17.27
Carbon C 41.55
Hydrogen H2 4.77
Nitrogen N2 0.37
Sulfur S <0.01
Ash 2.35
Oxygen (2) O2 33.75
Total 100.0
HHV
Btu/lb 6,853
(1) As received.
(2) Oxygen by Difference.

2-3
2.3 ENVIRONMENTAL COMPLIANCE BASIS
The technology assessments considered the emissions rates after implementation of best
available control technology (“BACT”), including sulfur dioxide (“SO2”), oxides of nitrogen
(“NOX”), particulate matter, mercury, and carbon dioxide (“CO2”). With respect to CCS
technologies, which are not currently considered “proven” or BACT by regulating bodies,
R. W. Beck assumed capture and sequestration technologies that are currently in development
for large-scale deployment, as discussed herein, and at industry expected rates of CO2 removal
(i.e., 90 percent).

2.4 LOCAL CAPACITY ADJUSTMENTS


For power plants that use CT technologies, adjustments were made for regional ambient
conditions. The adjustments took into consideration that CTs are machines that produce power
proportional to mass flow. Since air density is inversely proportional to temperature, ambient
temperature has a strong influence on the capacity of a given technology utilizing a CT
(e.g., peaking power plant, combined-cycle power plant, and some gasification power plants).
Additionally, relative humidity impacts the available capacity of a CT and consequently a
CT-based power plant, primarily driven by the base assumption that the CT-based technologies
incorporate inlet evaporative cooling. By circulating water across a porous media in the CT
compressor inlet (across which the air flows), the inlet evaporative cooling reduces the difference
between the ambient dry-bulb temperature (the temperature that is typically reported to the
public as a measure of “local temperature”) and the wet-bulb temperature (a measure of relative
humidity). Since inlet evaporative cooling is limited by the wet-bulb temperature, the
effectiveness of these devices increases in areas of high dry-bulb temperature and low relative
humidity. The final adjustment for ambient conditions made for the CT-based plants is ambient
pressure, which on average (notwithstanding high or low pressure weather fronts that pass
through a region) takes into consideration elevation (average number of feet above sea level).
Air density is proportional to ambient pressure.
Table 2-4 provides the aggregate capacity adjustment for each location, which provides regional
differences related to capital costs against the ISO net capacity for the CT-based power plant
technologies.

2-4
TABLE 2-4 – CT CAPACITY ADJUSTMENTS
Conventional CT Advanced CT Conventional NGCC Advanced�� NGCC Advanced�� NGCC With CCS IGCC IGCC With CCS
ISO Capacity Adjusted ISO Capacity Adjusted ISO Capacity Adjusted ISO Capacity Adjusted ISO Capacity Adjusted ISO Capacity Adjusted ISO Capacity Adjusted
Capacity Adjustment Capacity Capacity Adjustment Capacity Capacity Adjustment Capacity Capacity Adjustment Capacity Capacity Adjustment Capacity Capacity Adjustment Capacity Capacity Adjustment Capacity
State City (MW) (MW) (MW) (MW) (MW) (MW) (MW) (MW) (MW) (MW) (MW) (MW) (MW) (MW) (MW) (MW) (MW) (MW) (MW) (MW) (MW)
Alaska Anchorage 85 7.58 92.58 210 18.73 229 540 32.27 572 400 35.67 436 340 30.32 370 600 35.85 636 520 46.38 566
Alaska Fairbanks 85 9.97 94.97 210 24.63 235 540 42.43 582 400 46.91 447 340 39.87 380 600 47.14 647 520 60.98 581
Alabama Huntsville 85 �2.12 82.88 210 �5.23 205 540 �9.01 531 400 �9.96 390 340 �8.46 332 600 �10.01 590 520 �12.94 507
Arizona Phoenix 85 �8.33 76.67 210 �20.59 189 540 �35.47 505 400 �39.22 361 340 �33.34 307 600 �39.41 561 520 �50.98 469
Arkansas Little Rock 85 �1.77 83.23 210 �4.37 206 540 �7.53 532 400 �8.32 392 340 �7.07 333 600 �8.36 592 520 �10.82 509
California Los Angeles 85 �1.77 83.23 210 �4.37 206 540 �7.52 532 400 �8.32 392 340 �7.07 333 600 �8.36 592 520 �10.81 509
California Redding 85 �2.52 82.48 210 �6.21 204 540 �10.71 529 400 �11.84 388 340 �10.06 330 600 �11.90 588 520 �15.39 505
California Bakersfield 85 �3.77 81.23 210 �9.30 201 540 �16.03 524 400 �17.72 382 340 �15.06 325 600 �17.81 582 520 �23.03 497
California Sacramento 85 �0.69 84.31 210 �1.71 208 540 �2.95 537 400 �3.26 397 340 �2.78 337 600 �3.28 597 520 �4.24 516
California San Francisco 85 0.83 85.83 210 2.06 212 540 3.54 544 400 3.92 404 340 3.33 343 600 3.94 604 520 5.09 525
Colorado Denver 85 �12.30 72.70 210 �30.40 180 540 �52.37 488 400 �57.90 342 340 �49.22 291 600 �58.19 542 520 �75.27 445
Connecticut Hartford 85 2.97 87.97 210 7.33 217 540 12.63 553 400 13.96 414 340 11.87 352 600 14.03 614 520 18.15 538
Delaware Dover 85 1.22 86.22 210 3.00 213 540 5.17 545 400 5.72 406 340 4.86 345 600 5.75 606 520 7.43 527
District of Columbia Washington 85 2.01 87.01 210 4.96 215 540 8.55 549 400 9.46 409 340 8.04 348 600 9.50 610 520 12.29 532
Florida Tallahassee 85 �3.00 82.00 210 �7.42 203 540 �12.79 527 400 �14.14 386 340 �12.01 328 600 �14.21 586 520 �18.38 502
Florida Tampa 85 �4.78 80.22 210 �11.80 198 540 �20.34 520 400 �22.49 378 340 �19.11 321 600 �22.60 577 520 �29.23 491
Georgia Atlanta 85 �3.66 81.34 210 �9.05 201 540 �15.59 524 400 �17.24 383 340 �14.65 325 600 �17.32 583 520 �22.41 498
Hawaii Honolulu 85 �6.75 78.25 210 �16.66 193 540 �28.71 511 400 �31.74 368 340 �26.98 313 600 �31.90 568 520 �41.26 479
Idaho Boise 85 �5.52 79.48 210 �13.64 196 540 �23.50 517 400 �25.98 374 340 �22.08 318 600 �26.11 574 520 �33.77 486
Illinois Chicago 85 1.76 86.76 210 4.35 214 540 7.49 547 400 8.28 408 340 7.04 347 600 8.33 608 520 10.77 531
Indiana Indianapolis 85 0.20 85.20 210 0.50 211 540 0.87 541 400 0.96 401 340 0.81 341 600 0.96 601 520 1.24 521
Iowa Davenport 85 1.81 86.81 210 4.47 214 540 7.70 548 400 8.51 409 340 7.23 347 600 8.55 609 520 11.06 531
Iowa Waterloo 85 2.02 87.02 210 4.98 215 540 8.58 549 400 9.48 409 340 8.06 348 600 9.53 610 520 12.33 532
Kansas Wichita 85 �2.91 82.09 210 �7.19 203 540 �12.39 528 400 �13.70 386 340 �11.65 328 600 �13.77 586 520 �17.81 502
Kentucky Louisville 85 �0.20 84.80 210 �0.50 210 540 �0.86 539 400 �0.95 399 340 �0.81 339 600 �0.96 599 520 �1.24 519
Louisiana New Orleans 85 �3.26 81.74 210 �8.05 202 540 �13.87 526 400 �15.34 385 340 �13.03 327 600 �15.41 585 520 �19.94 500
Maine Portland 85 4.72 89.72 210 11.66 222 540 20.08 560 400 22.20 422 340 18.87 359 600 22.31 622 520 28.86 549
Maryland Baltimore 85 1.21 86.21 210 2.98 213 540 5.13 545 400 5.67 406 340 4.82 345 600 5.70 606 520 7.38 527
Massachusetts Boston 85 2.92 87.92 210 7.20 217 540 12.41 552 400 13.72 414 340 11.66 352 600 13.79 614 520 17.84 538
Michigan Detroit 85 2.03 87.03 210 5.00 215 540 8.62 549 400 9.53 410 340 8.10 348 600 9.58 610 520 12.39 532
Michigan Grand Rapids 85 1.97 86.97 210 4.87 215 540 8.39 548 400 9.27 409 340 7.88 348 600 9.32 609 520 12.05 532
Minnesota Saint Paul 85 2.00 87.00 210 4.95 215 540 8.52 549 400 9.42 409 340 8.01 348 600 9.47 609 520 12.25 532
Mississippi Jackson 85 �2.95 82.05 210 �7.30 203 540 �12.58 527 400 �13.90 386 340 �11.82 328 600 �13.97 586 520 �18.08 502
Missouri St. Louis 85 �0.40 84.60 210 �0.98 209 540 �1.68 538 400 �1.86 398 340 �1.58 338 600 �1.87 598 520 �2.42 518
Missouri Kansas City 85 �1.23 83.77 210 �3.04 207 540 �5.23 535 400 �5.78 394 340 �4.92 335 600 �5.81 594 520 �7.52 512
Montana Great Falls 85 �6.00 79.00 210 �14.81 195 540 �25.52 514 400 �28.21 372 340 �23.98 316 600 �28.35 572 520 �36.68 483
Nebraska Omaha 85 0.15 85.15 210 0.36 210 540 0.62 541 400 0.68 401 340 0.58 341 600 0.69 601 520 0.89 521
New Hampshire Concord 85 4.18 89.18 210 10.33 220 540 17.79 558 400 19.67 420 340 16.72 357 600 19.77 620 520 25.57 546
New Jersey Newark 85 1.69 86.69 210 4.18 214 540 7.21 547 400 7.97 408 340 6.77 347 600 8.01 608 520 10.36 530
New Mexico Albuquerque 85 �13.95 71.05 210 �34.46 176 540 �59.37 481 400 �65.64 334 340 �55.79 284 600 �65.97 534 520 �85.33 435
New York New York 85 1.69 86.69 210 4.18 214 540 7.21 547 400 7.97 408 340 6.77 347 600 8.01 608 520 10.36 530
New York Syracuse 85 3.06 88.06 210 7.56 218 540 13.03 553 400 14.41 414 340 12.25 352 600 14.48 614 520 18.73 539
Nevada Las Vegas 85 �9.24 75.76 210 �22.82 187 540 �39.31 501 400 �43.46 357 340 �36.95 303 600 �43.68 556 520 �56.50 463
North Carolina Charlotte 85 �2.41 82.59 210 �5.95 204 540 �10.26 530 400 �11.34 389 340 �9.64 330 600 �11.40 589 520 �14.74 505
North Dakota Bismarck 85 1.02 86.02 210 2.53 213 540 4.36 544 400 4.82 405 340 4.09 344 600 4.84 605 520 6.26 526
Ohio Cincinnati 85 1.45 86.45 210 3.58 214 540 6.16 546 400 6.81 407 340 5.79 346 600 6.85 607 520 8.85 529
Oregon Portland 85 2.02 87.02 210 5.00 215 540 8.61 549 400 9.51 410 340 8.09 348 600 9.56 610 520 12.37 532
Pennsylvania Philadelphia 85 1.88 86.88 210 4.65 215 540 8.00 548 400 8.85 409 340 7.52 348 600 8.89 609 520 11.50 532
Pennsylvania Wilkes�Barre 85 1.07 86.07 210 2.64 213 540 4.55 545 400 5.03 405 340 4.27 344 600 5.05 605 520 6.54 527
Rhode Island Providence 85 3.16 88.16 210 7.82 218 540 13.47 553 400 14.89 415 340 12.66 353 600 14.96 615 520 19.36 539
South Carolina Spartanburg 85 �2.32 82.68 210 �5.73 204 540 �9.88 530 400 �10.92 389 340 �9.28 331 600 �10.98 589 520 �14.20 506
South Dakota Rapid City 85 �5.15 79.85 210 �12.72 197 540 �21.91 518 400 �24.22 376 340 �20.59 319 600 �24.34 576 520 �31.49 489
Tennessee Knoxville 85 �2.15 82.85 210 �5.32 205 540 �9.17 531 400 �10.14 390 340 �8.62 331 600 �10.19 590 520 �13.18 507
Texas Houston 85 �3.46 81.54 210 �8.54 201 540 �14.71 525 400 �16.27 384 340 �13.83 326 600 �16.35 584 520 �21.15 499
Utah Salt Lake City 85 �9.73 75.27 210 �24.03 186 540 �41.40 499 400 �45.77 354 340 �38.90 301 600 �46.00 554 520 �59.50 461
Vermont Burlington 85 4.40 89.40 210 10.86 221 540 18.71 559 400 20.68 421 340 17.58 358 600 20.79 621 520 26.89 547
Virginia Alexandria 85 0.27 85.27 210 0.66 211 540 1.14 541 400 1.26 401 340 1.07 341 600 1.26 601 520 1.63 522
Virginia Lynchburg 85 �1.05 83.95 210 �2.59 207 540 �4.47 536 400 �4.94 395 340 �4.20 336 600 �4.96 595 520 �6.42 514
Washington Seattle 85 1.10 86.10 210 2.72 213 540 4.68 545 400 5.18 405 340 4.40 344 600 5.20 605 520 6.73 527
Washington Spokane 85 �2.90 82.10 210 �7.17 203 540 �12.35 528 400 �13.66 386 340 �11.61 328 600 �13.73 586 520 �17.75 502
West Virginia Charleston 85 �1.21 83.79 210 �3.00 207 540 �5.16 535 400 �5.71 394 340 �4.85 335 600 �5.74 594 520 �7.42 513
Wisconsin Green Bay 85 3.51 88.51 210 8.67 219 540 14.94 555 400 16.52 417 340 14.04 354 600 16.60 617 520 21.47 541
Wyoming Cheyenne 85 �13.05 71.95 210 �32.24 178 540 �55.55 484 400 �61.42 339 340 �52.21 288 600 �61.7 538 520 �79.84 440
Puerto Rico Cayey 85 �6.00 79.00 210 �14.83 195 540 �25.56 514 400 �28.25 372 340 �24.02 316 600 �28.40 572 520 �36.73 483

2-5
2.5 TECHNOLOGY SPECIFICATIONS
This section provides the base performance specifications for each technology. Table 2-5
provides the current technology specifications.

2.6 COST ESTIMATION METHODOLOGY


2.6.1 Capital Cost
A summary base capital cost estimate (“Cost Estimate”) was developed for each power plant
technology, based on a generic facility of a certain size (capacity) and configuration, and
assuming a non-specific U.S. location with no unusual location impacts (e.g., urban construction
constraints) or infrastructure needs (e.g., a project-dedicated interconnection upgrade cost).
Each Cost Estimate was developed assuming costs in fourth quarter 2010 dollars on an
“overnight” capital cost basis. In each Cost Estimate, the total project engineering, procurement
and construction (“EPC”) cost was organized into the following categories:
� Civil/structural material and installation,
� Mechanical equipment supply and installation,
� Electrical instrumentation and controls (“I&C”) supply and installation,
� Project indirect costs, fees and contingency, and
� Owner’s costs (excluding project financing costs).
It should be noted that an EPC (turnkey) or equipment supply/balance of plant, as applicable to a
given technology, contracting approach was assumed for each of the technologies, which
included a risk sharing between the project owner and project construction contractor that, based
on our experience, would be required in typical financing markets. This approach does not
always result in the lowest cost of construction; however, on average, we believe this approach
to result in an achievable cost of construction, given the other considerations discussed herein.
In addition to the base Cost Estimate provided for the given technology, specific regional cost
differences were determined. Regional costs for 64 unique locations in the U.S. were analyzed.
Eleven subcategories were used (depending on the specific technology under review) to estimate
the differences in various regions of the U.S. for the each power plant technology. The regional
analyses include but are not limited to assessing the cost differences for outdoor installation
considerations, air-cooled condensers versus cooling tower issues, seismic design differences,
zero-water discharge issues, local enhancements, remote location issues, urban high-density
population issues, labor wage and productivity differences, location adjustments, owner cost
differences, and the increase in overheads associated with these 10 locations. More detail with
respect to regional differences for each given technology is provided in the following sections.
2.6.1.1 Costing Scope
The civil and structural costs include allowance for site preparation, such as clearing, roads,
drainage, underground utilities installation, concrete for foundations, piling material, structural
steel supply and installation, and buildings.
The mechanical equipment supply and installation includes major equipment , including but not
limited to, boilers, scrubbers, cooling tower, steam turbine (“ST”) generators, solar panels, CTs,

2-6
as well as auxiliary equipment such as material handling, fly and bottom ash handling, pumps,
condensers, and balance of plant (“BOP”) equipment such as fire protection, as applicable to a
given technology.
The electrical and I&C supply and installation includes electrical transformers, switchgear,
motor control centers, switchyards, distributed control systems (“DCS”) and instrumentation,
and electrical commodities, such as wire, cable tray, and lighting.
While commodities, project equipment, and site assumptions can vary widely from project-to-
project for a given technology, the Cost Estimates are based upon a cross section of projects.
The project indirect costs include engineering, distributable labor and materials, craft labor
overtime and incentives, scaffolding costs, construction management, and start-up and
commissioning. The fees and contingency include contractor overhead costs, fees and profit, and
construction contingency. Contingency in this category is considered “contractor” contingency,
which would be held by a given contractor to mitigate its risk in the construction of a project.
The owner’s costs include development costs, preliminary feasibility and engineering studies,
environmental studies and permitting, legal fees, project management (including third-party
management), insurance costs, infrastructure interconnection costs (e.g., gas, electricity),
Owner’s Contingency, and property taxes during construction. The electrical interconnection
cost includes an allowance for the plant switchyard and a subsequent interconnection to an
“adjacent” (e.g. within a mile) of the plant, but does not include significant transmission system
upgrades.
2.6.2 Operation and Maintenance (O&M) Expenses
O&M expenses consist of non-fuel O&M costs, owner’s expenses, and fuel-related expenses. In
evaluating the non-fuel O&M expenses for use in the EMM of NEMS, we focused on non-fuel
O&M costs associated with the direct operation of the given power plant technology, referred to
here as the “Production Related Non-Fuel O&M Expenses,” to allow for comparison of O&M
costs on the same basis.
Production Related Non-Fuel O&M Expenses include the following categories:
� Fixed O&M (“FOM”)
� Variable O&M (“VOM”)
� Major Maintenance
Presented below is a brief summary below of the expense categories included within the
categories of Fixed O&M, Variable O&M, and Major Maintenance. Further, Sections 3 through
22 provide more specific information related to Production-Related Non-Fuel O&M Expenses
for each technology.
Owner’s expenses, which are not addressed in this report, include expenses paid by plant owners
that are plant specific and can vary significantly between two virtually identical plants in the
same geographic region. For example, the owner’s expenses include, but are not limited to,
property taxes, asset management fees, energy marketing fees, and insurance.

2-7
2.6.2.1 Fixed O&M (FOM)
FOM expenses are those expenses incurred at a power plant that do not vary significantly with
generation and include the following categories:
� Staffing and monthly fees under pertinent operating agreements
� Typical bonuses paid to the given plant operator
� Plant support equipment which consists of equipment rentals and temporary labor
� Plant-related general and administrative expenses (postage, telephone, etc.)
� Routine preventive and predictive maintenance performed during operations
� Maintenance of structures and grounds
� Other fees required for a project to participate in the relevant National Electric Reliability
Council region and be in good standing with the regulatory bodies.
Routine preventive and predictive maintenance expenses do not require an extended plant
shutdown and include the following categories:
� Maintenance of equipment such as water circuits, feed pumps, main steam piping, and
demineralizer systems
� Maintenance of electric plant equipment, which includes service water, DCS, condensate
system, air filters, and plant electrical
� Maintenance of miscellaneous plant equipment such as communication equipment,
instrument and service air, and water supply system
� Plant support equipment which consists of tools, shop supplies and equipment rental, and
safety supplies.
2.6.2.2 Variable O&M (VOM)
VOM expenses are production-related costs which vary with electrical generation and include
the following categories, as applicable to the given power plant technology:
� Raw water
� Waste and wastewater disposal expenses
� Purchase power (which is incurred inversely to operating hours), demand charges and
related utilities
� Chemicals, catalysts and gases
� Ammonia (“NH3”) for selective catalytic reduction (“SCR”), as applicable
� Lubricants
� Consumable materials and supplies.
2.6.2.3 Major Maintenance
Major maintenance expenses generally require an extended outage, are typically undertaken no
more than once per year; and are assumed to vary with electrical generation or the number of

2-8
plant starts based on the given technology and specific original equipment manufacturer
recommendations and requirements. These major maintenance expenses include the following
expense categories:
� Scheduled major overhaul expenses for maintaining the prime mover equipment at a
power plant
� Major maintenance labor
� Major maintenance spares parts costs
� BOP major maintenance, which is major maintenance on the equipment at the given plant
that cannot be accomplished as part of routine maintenance or while the unit is in
commercial operation.

2-9
TABLE 2-5 – TECHNOLOGY PERFORMANCE SPECIFICATIONS

Nominal Nominal Capital Variable


Capacity Heat Rate Cost Fixed O&M O&M SO2 (lb/ NOX CO2
Technology Fuel (kW) (1) (Btu/kWh) (2) ($/kW) (3) ($/kW-yr) (4) ($/MWh) (5) MMBtu (6) (lb/MMBtu) (lb/MMBtu)
Advanced Pulverized Coal Coal 650,000 8,800 3,167 35.97 4.25 0.1 (6) 0.06 206 (7)
Advanced Pulverized Coal Coal 1,300,000 8,800 2,844 29.67 4.25 0.1 (6) 0.06 206 (7)
Advanced Pulverized Coal with
0.02 (8) 0.06 20.6 (9)
CCS Coal 650,000 12,000 5,099 76.62 9.05
Advanced Pulverized Coal with
0.02 (8) 0.06 20.6 (9)
CCS Coal 1,300,000 12,000 4,579 63.21 9.05
NGCC Gas 540,000 7,050 978 14.39 3.43 0.001 0.0075 (13) 117 (14)
AG-NGCC Gas 400,000 6,430 1,003 14.62 3.11 0.001 0.0075 (13) 117 (14)
Advanced NGCC with CCS Gas 340,000 7,525 2,060 30.25 6.45 0.001 0.0075 (13) 12 (15)
Conventional CT Gas 85,000 10,850 974 6.98 14.70 0.001 0.03 (12) 117 (14)
Advanced CT Gas 210,000 9,750 665 6.70 9.87 0.001 0.03 (13) 117 (14)
IGCC Coal 600,000 8,700 3,565 59.23 6.87 0.025 (10) 0.0075 (12) 206 (14)
IGCC Coal 1,200,000 8,700 3,221 48.90 6.87 0.025 (10) 0.0075 (12) 206 (14)
IGCC with CCS Coal 520,000 10,700 5,348 69.30 8.04 0.015 (11) 0.0075 (12) 20.6 (14)
Advanced Nuclear Uranium 2,236,000 N/A 5,339 88.75 2.04 0 0 0
Biomass Combined Cycle Biomass 20,000 12,350 7,894 338.79 16.64 0 0.054 195 (14)
Biomass BFB Biomass 50,000 13,500 3,860 100.50 5.00 0 0.08 195 (14)
Fuel Cells Gas 10,000 9,500 6,835 350 0 0.00013 0.013 130
Geothermal – Dual Flash Geothermal 50,000 N/A 5,578 84.27 9.64 0.2 (16) 0 120 (17)
Geothermal – Binary Geothermal 50,000 N/A 4,141 84.27 9.64 0.2 (16) 0 120 (17)
MSW MSW 50,000 18,000 8,232 373.76 8.33 0.07 (18) 0.27 (19) 200
Hydroelectric Hydro 500,000 N/A 3,076 13.44 0 0 0 0
Pumped Storage Hydro 250,000 N/A 5,595 13.03 0 0 0 0
Onshore Wind Wind 100,000 N/A 2,438 28.07 0 0 0 0
Offshore Wind Wind 400,000 N/A 5,975 53.33 0 0 0 0
Solar Thermal Solar 100,000 N/A 4,692 64.00 0 0 0 0
Photovoltaic Solar 7,000 N/A 6,050 26.04 0 0 0 0
Photovoltaic Solar 150,000 N/A 4,755 16.70 0 0 0 0

Footnotes are listed on the next page.

2-10
(1) Capacity is net of auxiliary loads.
(2) Heat Rate is on a HHV basis for British thermal units per kilowatt-hour (“Btu/kWh”).
(3) Capital Cost excludes financing-related costs (e.g., fees, interest during construction).
(4) FOM expenses exclude owner's costs (e.g., insurance, property taxes, and asset management fees).
(5) VOM expenses include major maintenance.
(6) Million Btu (“MMBtu”).
(7) Based on high sulfur bituminous fuel. Emission rate could be lower for sub-bituminous fuel.
(8) From greenhouse gas (“GHG”) Reporting Rule for Bituminous Coal.
(9) SO2 emission rates are lower than in the non-capture case to avoid reagent contamination.
(10) Assuming 90 percent capture.
(11) Assuming 3 percent sulfur coal at 12,000 British thermal units per pound (“Btu/lb”) and a 99.5 percent sulfur removal rate.
(12) Assuming 3 percent sulfur coal at 12,000 Btu/lb and a 99.7 percent sulfur removal rate.
(13) Assuming 9 parts per million volume dry (“ppmvd”) corrected to 15 percent O2; simple-cycle E-Class or F-Class engine.
(14) Assuming 2 ppmvd corrected to 15 percent O2 for F-Class engine. Assumes development of SCR for IGCC with CCS.
(15) From GHG Reporting Rule for Pipeline Natural Gas.
(16) Assuming 90 percent capture.
(17) Reported as pounds per MWh and as H2S – actual will vary with resource.
(18) Reported as pounds per MWh – actual will vary with resource.
(19) Based on 30 ppmvd at 7 percent O2 – 5,000 Btu/lb HHV of MSW.
(20) Based on 150 ppmvd at 7 percent O2 - 5,000 Btu/lb HHV of MSW.

2-11
3. ADVANCED PULVERIZED COAL (APC)

3.1 MECHANICAL EQUIPMENT AND SYSTEMS


The following describes the Advanced Pulverized Coal Facility, which is a nominal 650 MW
coal-fired supercritical steam-electric generating unit built in a Greenfield location. An analysis
is also provided for a nominally 1,300 MW coal-fired supercritical steam-electric generating unit
built in a Greenfield location, which is essentially a dual-unit configuration, based on doubling
the single-unit description provided below; however, a detailed technical description (due to the
similarities/duplication with the single unit) is not provided herein. This unit employs a
supercritical Rankine power cycle in which coal is burned to produce steam in a boiler, which is
expanded through a ST to produce electric power. The steam is then condensed to water and
pumped back to the boiler to be converted to steam once again to complete the cycle.
The unit will operate at steam conditions of up to 3,700 pounds per square inch-absolute (“psia”)
and 1,050 degrees Fahrenheit (“ºF”) at the ST inlet. The superheated steam produced in the
boiler is supplied to the ST, which drives an electric generator. After leaving the high-pressure
(“HP”) ST, the steam is reheated and fed to the intermediate-pressure (“IP”) ST. In the
low-pressure (“LP”) ST, the steam admitted directly from the IP ST expands to condenser
pressure and is condensed in the condenser. Cooling tower water is used for the condensing
process. Condensate collected in the condenser hotwell is discharged by the main condensate
pumps and returned to the deaerator/feedwater storage tank via the LP feedwater heaters. The
feedwater pumps discharge feedwater from the feedwater storage tank to the boiler via the HP
feedwater heaters. In the boiler, the supercritical fluid is heated for return to the ST.
The combustion air and flue gas systems are designed for balanced draft and starts with the
ambient air drawn in by the forced draft fans. This air is heated by steam preheaters and the
regenerative air heaters. Some of the air is passed through the primary air fans for use in drying
and conveying the pulverized coal to the boiler. The air and coal combust in the boiler furnace
and the flue gas passes through the furnace and back passes of the boiler, giving up heat to the
supercritical fluid in the boiler tubes. The flue gas exiting the boiler economizer enters the SCR
equipment for NOX reduction and into the regenerative air heaters where it transfers heat to the
incoming air. From the regenerative air heaters, the flue gas is treated with an injection of
hydrated lime, enters a pulse-jet fabric filter (baghouse) for the collection of particulate material,
and then flows to the induced draft fans. From the fans, gas enters the Wet Flue Gas
Desulfurization (“WFGD”) absorber. From the absorber, the flue gas discharges into the stack.
Figure 3-1 presents the Advanced Pulverized Coal process flow diagram.

3-1
FIGURE 3-1 – ADVANCED PULVERIZED COAL DESIGN CONFIGURATION

3.2 ELECTRICAL AND CONTROL SYSTEMS


The Advanced Pulverized Coal Facility has one ST electric generator. The generator is a
60 Hertz (“Hz”) machine rated at approximately 800 mega-volt-amperes (“MVA”) with an
output voltage of 24 kilovolts (“kV”). The ST electric generator is directly connected to
generator step-up transformer (“GSU”), which in turn is connected between two circuit breakers
in the high-voltage bus in the Advanced Pulverized Coal Facility switchyard through a
disconnect switch. The GSU increases the voltage from the electric generator from 24 kV to
interconnected transmission system high voltage.
The Advanced Pulverized Coal Facility is controlled using a DCS. The DCS provides
centralized control of the plant by integrating the control systems provided with the boiler, ST
and associated electric generator and the control of BOP systems and equipment.

3.3 OFF-SITE REQUIREMENTS


Coal is delivered to the facility via rail, truck or barge. Water for all processes at the Advanced
Pulverized Coal Facility can be obtained from one of a variety of sources; however, water is
typically sourced from an adjacent river, when possible. The Advanced Pulverized Coal Facility
uses a water treatment system and a high-efficiency reverse osmosis system to reduce the
dissolved solids from the cooling water and to provide distilled water for boiler makeup.
Wastewater is sent to an adjacent river or other approved alternative. Further, the electrical
interconnection from the Advanced Pulverized Coal on-site switchyard is effectuated by a
connection to an adjacent utility substation, assumed to be no more than 1 mile from the
Advanced Pulverized Coal Facility.

3-2
3.4 CAPITAL COST ESTIMATE
The base Cost Estimate for the Advanced Pulverized Coal Facility (“APC”) with a nominal
capacity of 650 MW is $3,167/kilowatt (“kW”) and with a nominal capacity of 1,300 MW is
$2,844/kW. Table 3-1 and Table 3-2 summarize the Cost Estimate categories for the APC
Facility.
TABLE 3-1 – BASE PLANT SITE CAPITAL COST ESTIMATE FOR APC
Technology: APC
Nominal Capacity (ISO): 650,000 kW
Nominal Heat Rate (ISO): 8,800 Btu/kWh-HHV

Capital Cost Category (000s) (October 1, 2010$)

Civil Structural Material and Installation 224,000

Mechanical Equipment Supply and


Installation 838,500

Electrical / I&C Supply and Installation 123,000

Project Indirects (1) 350,000

EPC Cost before Contingency and Fee 1,535,500

Fee and Contingency 180,000

Total Project EPC 1,715,500

Owner's Costs (excluding project finance) 343,100

Total Project Cost (excluding finance) 2,058,600

Total Project EPC $ / kW 2,639

Owner Costs 20% (excluding project finance) $ / kW 528

Total Project Cost (excluding project finance) $ / kW 3,167

(1) Includes engineering, distributable costs, scaffolding, construction management, and start-up.

3-3
TABLE 3-2 – BASE PLANT SITE CAPITAL COST ESTIMATE FOR APC
Technology: APC
Nominal Capacity (ISO): 1,300,000 kW
Nominal Heat Rate (ISO): 8,800 Btu/kWh-HHV

Capital Cost Category (000s) (October 1, 2010$)

Civil Structural Material and Installation 397,250

Mechanical Equipment Supply and


Installation 1,596,100

Electrical / I&C Supply and Installation 235,000

Project Indirects (1) 584,750

EPC Cost before Contingency and Fee 2,813,100

Fee and Contingency 320,000

Total Project EPC 3,133,100

Owner Costs (excluding project finance) 563,958

Total Project Cost (excluding finance) 3,697,058

Total Project EPC $ / kW 2,410

Owner Costs 18% (excluding project finance) $ / kW 434

Total Project Cost (excluding project finance) $ / kW 2,844

(1) Includes engineering, distributable costs, scaffolding, construction management, and start-up.

For this type of technology and power plant configuration, our regional adjustments took into
consideration the following: outdoor installation considerations, seismic design differences,
remote location issues, labor wage and productivity differences, location adjustments, owner cost
differences, and the increase in overheads associated with these six adjustment criteria.
Outdoor installation locations are considered in geographic areas where enclosed structures for
the boilers would not be required due to the low probability of freezing. The locations that were
included in outdoor installation are Alabama, Arizona, Arkansas, Florida, Georgia, Hawaii,
Louisiana, Mississippi, New Mexico, South Carolina, and Puerto Rico.
Seismic design differences among the various locations were based on U.S. seismic map
information that detailed the various seismic zones throughout the U.S. No cost increases were
associated with seismic Zone 0 and cost step increases were considered for Zones 1, 2, 3 and 4.

3-4
Remote location issues are related to geographic areas that typically require installation of man
camps, higher craft incentives, and higher per diems are generally required with respect to
construction, due to the fact that such areas are long distances from urban areas, where labor is
generally abundant. Remote location designations were also considered in locations where
higher equipment freight costs are typically incurred, which for example are regions not near
established rail or highway access. Remote locations related to the APC Facility include
Fairbanks, Alaska; Honolulu, Hawaii; Albuquerque, New Mexico; Cheyenne, Wyoming; and
Cayey, Puerto Rico.
Labor wage and productivity differences were handled as discussed in Section 1.5.1, taking into
consideration the amount of labor we estimated for the APC Facility.
Location adjustments were made to locations where higher cost of living levels are incurred
and/or where population density generally correlates to higher construction costs for power and
other infrastructure projects. These locations include Alaska, California, Connecticut, Delaware,
District of Columbia, Hawaii, Illinois, Maine, Maryland, Massachusetts, Michigan, Minnesota,
New York, Ohio; and Wisconsin.
Owner costs were reviewed based on the need for utility upgrades and/or infrastructure costs
such as new facility transmission lines to tie to existing utility transmission substations or
existing transmission lines.
Table 3-3 and Table 3-4 show the APC capital cost variations for alternative U.S. plant locations,
including the difference between the given location and the average location specified for the
Cost Estimate.
TABLE 3-3 – LOCATION-BASED COSTS FOR APC (650,000 KW)
(OCTOBER 1, 2010 DOLLARS)
Base
Project Location Delta Cost Total Location
Cost Percent Difference Project Cost
State City ($/kW) Variation ($/kW) ($/kW)
Alaska Anchorage 3,200 33.1% 1,058 4,258
Alaska Fairbanks 3,200 32.0% 1,026 4,226
Alabama Huntsville 3,200 -7.5% (239) 2,961
Arizona Phoenix 3,200 -5.2% (166) 3,034
Arkansas Little Rock 3,200 -6.2% (200) 3,000
California Los Angeles 3,200 20.3% 649 3,849
California Redding 3,200 9.8% 314 3,514
California Bakersfield 3,200 9.4% 300 3,500
California Sacramento 3,200 14.4% 462 3,662
California San Francisco 3,200 42.4% 1,356 4,556
Colorado Denver 3,200 -6.1% (194) 3,006
Connecticut Hartford 3,200 26.6% 851 4,051
Delaware Dover 3,200 23.0% 736 3,936
District of Columbia Washington 3,200 39.6% 1,267 4,467
Florida Tallahassee 3,200 -10.9% (349) 2,851
Florida Tampa 3,200 -4.9% (156) 3,044
Georgia Atlanta 3,200 -8.1% (260) 2,940
Hawaii Honolulu 3,200 69.0% 2,210 5,410
Idaho Boise 3,200 -3.7% (118) 3,082
Illinois Chicago 3,200 19.8% 635 3,835
Indiana Indianapolis 3,200 3.2% 102 3,302

3-5
Base
Project Location Delta Cost Total Location
Cost Percent Difference Project Cost
State City ($/kW) Variation ($/kW) ($/kW)
Iowa Davenport 3,200 -1.6% (50) 3,150
Iowa Waterloo 3,200 -9.0% (288) 2,912
Kansas Wichita 3,200 -7.5% (241) 2,959
Kentucky Louisville 3,200 -5.6% (178) 3,022
Louisiana New Orleans 3,200 -11.2% (359) 2,841
Maine Portland 3,200 -1.5% (47) 3,153
Maryland Baltimore 3,200 4.6% 148 3,348
Massachusetts Boston 3,200 35.3% 1,128 4,328
Michigan Detroit 3,200 3.8% 123 3,323
Michigan Grand Rapids 3,200 -7.9% (251) 2,949
Minnesota St. Paul 3,200 3.9% 125 3,325
Mississippi Jackson 3,200 -7.4% (238) 2,962
Missouri St. Louis 3,200 7.2% 231 3,431
Missouri Kansas City 3,200 3.4% 109 3,309
Montana Great Falls 3,200 -4.3% (137) 3,063
Nebraska Omaha 3,200 -3.5% (113) 3,087
New Hampshire Concord 3,200 -1.6% (52) 3,148
New Jersey Newark 3,200 15.5% 495 3,695
New Mexico Albuquerque 3,200 -3.9% (125) 3,075
New York New York 3,200 32.6% 1,044 4,244
New York Syracuse 3,200 10.7% 342 3,542
Nevada Las Vegas 3,200 9.2% 295 3,495
North Carolina Charlotte 3,200 -11.2% (360) 2,840
North Dakota Bismarck 3,200 -8.0% (255) 2,945
Ohio Cincinnati 3,200 0.3% 11 3,211
Oregon Portland 3,200 9.5% 305 3,505
Pennsylvania Philadelphia 3,200 12.1% 387 3,587
Pennsylvania Wilkes-Barre 3,200 -3.5% (112) 3,088
Rhode Island Providence 3,200 4.1% 132 3,332
South Carolina Spartanburg 3,200 -11.8% (377) 2,823
South Dakota Rapid City 3,200 -10.7% (342) 2,858
Tennessee Knoxville 3,200 -8.9% (286) 2,914
Texas Houston 3,200 -9.5% (304) 2,896
Utah Salt Lake City 3,200 -3.1% (98) 3,102
Vermont Burlington 3,200 -5.3% (169) 3,031
Virginia Alexandria 3,200 9.7% 310 3,510
Virginia Lynchburg 3,200 -2.0% (62) 3,138
Washington Seattle 3,200 12.8% 409 3,609
Washington Spokane 3,200 -2.3% (74) 3,126
West Virginia Charleston 3,200 -1.8% (58) 3,142
Wisconsin Green Bay 3,200 0.5% 16 3,216
Wyoming Cheyenne 3,200 3.9% 125 3,325
Puerto Rico Cayey 0 0 0 0

3-6
TABLE 3-4 – LOCATION-BASED COSTS FOR APC (1,300,000 KW)
(OCTOBER 1, 2010 DOLLARS)
Base
Project Location Delta Cost Total Location
Cost Percent Difference Project Cost
State City ($/kW) Variation ($/kW) ($/kW)
Alaska Anchorage 2,850 36.5% 1,040 3,890
Alaska Fairbanks 2,850 35.3% 1,006 3,856
Alabama Huntsville 2,850 -8.2% (233) 2,617
Arizona Phoenix 2,850 -5.7% (161) 2,689
Arkansas Little Rock 2,850 -5.9% (169) 2,681
California Los Angeles 2,850 22.4% 638 3,488
California Redding 2,850 10.7% 306 3,156
California Bakersfield 2,850 10.3% 293 3,143
California Sacramento 2,850 15.7% 447 3,297
California San Francisco 2,850 46.7% 1,330 4,180
Colorado Denver 2,850 -6.6% (188) 2,662
Connecticut Hartford 2,850 29.4% 838 3,688
Delaware Dover 2,850 25.5% 728 3,578
District of Columbia Washington 2,850 44.4% 1,265 4,115
Florida Tallahassee 2,850 -11.9% (339) 2,511
Florida Tampa 2,850 -5.4% (154) 2,696
Georgia Atlanta 2,850 -8.9% (253) 2,597
Hawaii Honolulu 0 0 0 0
Idaho Boise 2,850 -4.0% (115) 2,735
Illinois Chicago 2,850 21.3% 606 3,456
Indiana Indianapolis 2,850 3.5% 99 2,949
Iowa Davenport 2,850 -1.8% (53) 2,797
Iowa Waterloo 2,850 -9.8% (280) 2,570
Kansas Wichita 2,850 -7.3% (209) 2,641
Kentucky Louisville 2,850 -6.1% (173) 2,677
Louisiana New Orleans 2,850 -12.2% (348) 2,502
Maine Portland 2,850 -0.6% (16) 2,834
Maryland Baltimore 2,850 5.3% 150 3,000
Massachusetts Boston 2,850 38.7% 1,103 3,953
Michigan Detroit 2,850 4.0% 114 2,964
Michigan Grand Rapids 2,850 -8.6% (244) 2,606
Minnesota St. Paul 2,850 4.1% 116 2,966
Mississippi Jackson 2,850 -8.1% (231) 2,619
Missouri St. Louis 2,850 7.7% 221 3,071
Missouri Kansas City 2,850 3.5% 101 2,951
Montana Great Falls 2,850 -4.7% (133) 2,717
Nebraska Omaha 2,850 -3.9% (111) 2,739
New Hampshire Concord 2,850 -1.8% (52) 2,798
New Jersey Newark 2,850 16.4% 467 3,317
New Mexico Albuquerque 2,850 -4.3% (122) 2,728
New York New York 2,850 34.8% 992 3,842
New York Syracuse 2,850 12.0% 341 3,191
Nevada Las Vegas 2,850 9.9% 282 3,132
North Carolina Charlotte 2,850 -10.4% (296) 2,554
North Dakota Bismarck 2,850 -8.7% (248) 2,602
Ohio Cincinnati 2,850 0.5% 13 2,863
Oregon Portland 2,850 10.4% 297 3,147
Pennsylvania Philadelphia 2,850 12.9% 366 3,216
Pennsylvania Wilkes-Barre 2,850 -3.8% (109) 2,741

3-7
Base
Project Location Delta Cost Total Location
Cost Percent Difference Project Cost
State City ($/kW) Variation ($/kW) ($/kW)
Rhode Island Providence 2,850 4.3% 123 2,973
South Carolina Spartanburg 2,850 -12.7% (363) 2,487
South Dakota Rapid City 2,850 -11.6% (331) 2,519
Tennessee Knoxville 2,850 -9.7% (276) 2,574
Texas Houston 2,850 -10.3% (295) 2,555
Utah Salt Lake City 2,850 -3.3% (93) 2,757
Vermont Burlington 2,850 -5.8% (164) 2,686
Virginia Alexandria 2,850 10.9% 310 3,160
Virginia Lynchburg 2,850 -2.0% (57) 2,793
Washington Seattle 2,850 13.9% 397 3,247
Washington Spokane 2,850 -2.6% (73) 2,777
West Virginia Charleston 2,850 -2.1% (59) 2,791
Wisconsin Green Bay 2,850 0.6% 16 2,866
Wyoming Cheyenne 2,850 4.6% 131 2,981
Puerto Rico Cayey 0 0 0 0

3.5 O&M ESTIMATE


In addition to the general O&M items discussed in Section 2.5.2., the APC Facility includes the
major maintenance for boiler, ST, associated generator, BOP, and emissions reduction catalysts.
These major maintenance expenses are included with the VOM expense for this technology and
are given on an average basis across the megawatt-hours (“MWh”) incurred. Typically,
significant overhauls on an APC Facility occur no less frequently than six or seven years.
Table 3-5 presents the FOM and VOM expenses for the APC Facility. Table 3-5 and Table 3-6
present the O&M expenses for the APC Facility.
TABLE 3-5 – O&M EXPENSES FOR APC (650,000 KW)
Technology: APC
Fixed O&M Expense $35.97/kW-year
Variable O&M Expense $4.25/MWh
TABLE 3-6 – O&M EXPENSES FOR APC (1,300,000 KW)
Technology: APC
Fixed O&M Expense $29.67/kW-year
Variable O&M Expense $4.25/MWh

3.6 ENVIRONMENTAL COMPLIANCE INFORMATION


As mentioned in Section 3.1, the APC Facility is assumed to include low NOX combustion
burners in the boiler, SCR, and a flue gas desulfurization (“FGD”) to further control the
emissions of NOX and SO2, respectively. Table 3-7 presents the environmental emissions for the
APC Facility.

3-8
TABLE 3-7 – ENVIRONMENTAL EMISSIONS FOR APC
Technology: APC
NOX 0.06 lb/MMBtu
SO2 0.1 lb/MMBtu
CO2 206 lb/MMBtu

3-9
4. ADVANCED PULVERIZED COAL WITH CCS (APC/CCS)

4.1 MECHANICAL EQUIPMENT AND SYSTEMS


The plant configuration for the APC with CCS Facility (“APC/CCS”) is the same as the APC
case with two exceptions: (1) an amine scrubbing system, utilizing monoethanolamine (“MEA”)
as a solvent, to capture CO2 from the flue gas, and (2) the scaling of the boiler to a larger size, as
described below. The captured CO2 is compressed to approximately 2,000 psia for injection into
a pipeline at the plant fence line as a supercritical fluid. The net output of the APC/CCS Facility
case is 650 MW (and 1,300 MW for the two unit configuration), and since the CCS system
requires about one-third of the given facility’s gross capacity in auxiliary load, the APC/CCS
Facility assumes that the boiler is increased by approximately one-third (i.e., it is approximately
133 percent the size of the boiler in the APC Facility), which provides the necessary steam to
facilitate the capture process and to run a steam-driven compressor for compressing the CO2 for
sequestration. Figure 4-1 presents a diagram of the APC and Figure 4-2 presents a diagram of
the APC/CCS Facility.
FIGURE 4-1 – APC FACILITY DIAGRAM

4-1
FIGURE 4-2 – APC/CCS FACILITY DIAGRAM

4.2 ELECTRICAL AND CONTROL SYSTEMS


The electrical and control systems for the APC/CCS Facility are materially similar to the APC
Facility.

4.3 OFF-SITE REQUIREMENTS


The off-site requirements for the APC/CCS Facility are materially similar to the APC Facility,
except that the CO2 needs sequestering in one of the following geologic formations:
(1) exhausted gas storage location, (2) unminable coal seam, (3) enhanced oil recovery, or
(4) saline aquifer. To the extent that a sequestration site is not near the given facility being
analyzed, transportation for a viable sequestration site has the potential to materially affect the
capital cost estimates discussed below.

4.4 CAPITAL COST ESTIMATE


The base Cost Estimate for the APC/CCS Facility with a nominal capacity of 650 MW is
$5,099/kW and with a nominal capacity of 1,300,000 MW is $4,579/kW. The capital cost
estimate was based on the advanced pulverized APC Facility (without CCS) and the base Cost
Estimate was increased to include the expected costs of CCS. Since there are currently no full-
scale pulverized coal facilities operating with CCS in the world, our estimate is based on industry
research. Our team tested the veracity of this research against assumptions for implementing the
additional equipment necessary to effectuate CCS on an advanced coal facility. Table 4-1 and
Table 4-2 summarize the Cost Estimate categories for the APC/CCS Facility.

4-2
TABLE 4-1 – BASE PLANT SITE CAPITAL COST ESTIMATE FOR APC/CCS
Technology: APC/CCS
Nominal Capacity (ISO): 650,000 kW
Nominal Heat Rate (ISO): 12,000 Btu/kWh-HHV

Capital Cost Category (000s) (October 1, 2010$)

Total Project EPC 2,761,958

Owner Costs (excluding project finance) 552,391

Total Project Cost (excluding finance) 3,314,350

Total Project EPC / kW 4,249

Owner Costs 20% (excluding project finance) / kW 850

Total Project Cost (excluding project finance) / kW 5,099

(1) Includes engineering, distributable costs, scaffolding, construction management, and start-up.

TABLE 4-2 – BASE PLANT SITE CAPITAL COST ESTIMATE FOR APC/CCS
Technology: APC/CCS
Nominal Capacity (ISO): 1,300,000 kW
Nominal Heat Rate (ISO): 12,000 Btu/kWh-HHV

Capital Cost Category (000s) (October 1, 2010$)

Total Project EPC 5,045,763

Owner Costs (excluding project finance) 908,237

Total Project Cost (excluding finance) 5,954,000

Total Project EPC / kW 3,881

Owner Costs 18% (excluding project finance) / kW 699

Total Project Cost (excluding project finance) / kW 4,579

(1) Includes engineering, distributable costs, scaffolding, construction management, and start-up.

For this type of technology and power plant configuration, our regional adjustments took into
consideration the following: outdoor installation considerations, seismic design differences,
remote location issues, labor wage and productivity differences, location adjustments, owner cost
differences, and the increase in overheads associated with these six adjustment criteria. The

4-3
methodology used for the APC/CCS Facility is the same as that discussed in Section 3.4 for the
APC Facility (without CCS).
Table 4-3 and Table 4-4 show the APC capital cost variations for alternative U.S. plant locations,
including the difference between the given location and the average location specified for the
Cost Estimate.
TABLE 4-3– LOCATION-BASED COSTS FOR APC/CCS FACILITY (650,000 KW)
(OCTOBER 1, 2010 DOLLARS)
Base
Project Location Delta Cost Total Location
Cost Percent Difference Project Cost
State City ($/kW) Variation ($/kW) ($/kW)
Alaska Anchorage 5,100 32.2% 1,643 6,743
Alaska Fairbanks 5,100 31.4% 1,602 6,702
Alabama Huntsville 5,100 -8.0% (409) 4,691
Arizona Phoenix 5,100 -5.7% (289) 4,811
Arkansas Little Rock 5,100 -6.7% (342) 4,797
California Los Angeles 5,100 19.6% 1,000 6,100
California Redding 5,100 9.4% 481 5,581
California Bakersfield 5,100 9.0% 458 5,558
California Sacramento 5,100 14.4% 734 5,834
California San Francisco 5,100 41.6% 2,124 7,224
Colorado Denver 5,100 -6.6% (335) 4,765
Connecticut Hartford 5,100 25.6% 1,306 6,406
Delaware Dover 5,100 21.9% 1,116 6,216
District of Columbia Washington 5,100 37.0% 1,888 6,988
Florida Tallahassee 5,100 -11.6% (591) 4,509
Florida Tampa 5,100 -5.1% (262) 4,838
Georgia Atlanta 5,100 -8.7% (445) 4,655
Hawaii Honolulu 5,100 65.6% 3,347 8,447
Idaho Boise 5,100 -4.1% (211) 4,889
Illinois Chicago 5,100 20.7% 1,055 6,155
Indiana Indianapolis 5,100 2.8% 141 5,241
Iowa Davenport 5,100 -1.7% (85) 5,015
Iowa Waterloo 5,100 -9.6% (491) 4,609
Kansas Wichita 5,100 -8.1% (411) 4,728
Kentucky Louisville 5,100 -6.1% (309) 4,791
Louisiana New Orleans 5,100 -11.9% (608) 4,492
Maine Portland 5,100 -2.2% (111) 5,028
Maryland Baltimore 5,100 3.8% 195 5,295
Massachusetts Boston 5,100 34.9% 1,779 6,879
Michigan Detroit 5,100 4.0% 204 5,304
Michigan Grand Rapids 5,100 -8.4% (428) 4,672
Minnesota St. Paul 5,100 4.0% 206 5,306
Mississippi Jackson 5,100 -8.0% (406) 4,694
Missouri St. Louis 5,100 7.2% 366 5,466

4-4
Base
Project Location Delta Cost Total Location
Cost Percent Difference Project Cost
State City ($/kW) Variation ($/kW) ($/kW)
Missouri Kansas City 5,100 3.4% 174 5,274
Montana Great Falls 5,100 -4.8% (244) 4,856
Nebraska Omaha 5,100 -3.9% (197) 4,903
New Hampshire Concord 5,100 -2.0% (100) 5,000
New Jersey Newark 5,100 16.4% 837 5,937
New Mexico Albuquerque 5,100 -4.4% (222) 4,878
New York New York 5,100 34.7% 1,768 6,868
New York Syracuse 5,100 8.5% 433 5,533
Nevada Las Vegas 5,100 7.5% 382 5,482
North Carolina Charlotte 5,100 -12.0% (612) 4,566
North Dakota Bismarck 5,100 -8.5% (434) 4,666
Ohio Cincinnati 5,100 -0.3% (13) 5,087
Oregon Portland 5,100 9.1% 466 5,566
Pennsylvania Philadelphia 5,100 12.7% 649 5,749
Pennsylvania Wilkes-Barre 5,100 -3.9% (201) 4,899
Rhode Island Providence 5,100 4.2% 214 5,314
South Carolina Spartanburg 5,100 -12.7% (649) 4,451
South Dakota Rapid City 5,100 -11.4% (583) 4,517
Tennessee Knoxville 5,100 -9.6% (492) 4,608
Texas Houston 5,100 -10.2% (518) 4,582
Utah Salt Lake City 5,100 -3.8% (194) 4,906
Vermont Burlington 5,100 -5.9% (299) 4,801
Virginia Alexandria 5,100 8.7% 443 5,543
Virginia Lynchburg 5,100 -2.7% (138) 4,962
Washington Seattle 5,100 12.6% 644 5,744
Washington Spokane 5,100 -2.7% (136) 4,964
West Virginia Charleston 5,100 -2.0% (103) 4,997
Wisconsin Green Bay 5,100 0.0% 0 5,100
Wyoming Cheyenne 5,100 1.4% 74 5,174
Puerto Rico Cayey 0 0 0 0

4-5
TABLE 4-4 – LOCATION-BASED COSTS FOR APC/CCS FACILITY (1,300,000 KW)
(OCTOBER 1, 2010 DOLLARS)
Base
Project Location Delta Cost Total Location
Cost Percent Difference Project Cost
State City ($/kW) Variation ($/kW) ($/kW)
Alaska Anchorage 4,580 35.2% 1,610 6,190
Alaska Fairbanks 4,580 34.2% 1,565 6,145
Alabama Huntsville 4,580 -8.3% (380) 4,200
Arizona Phoenix 4,580 -5.8% (266) 4,314
Arkansas Little Rock 4,580 -6.1% (278) 4,302
California Los Angeles 4,580 21.5% 985 5,565
California Redding 4,580 10.4% 475 5,055
California Bakersfield 4,580 9.9% 453 5,033
California Sacramento 4,580 15.5% 710 5,290
California San Francisco 4,580 45.2% 2,071 6,651
Colorado Denver 4,580 -6.7% (309) 4,271
Connecticut Hartford 4,580 28.1% 1,288 5,868
Delaware Dover 4,580 24.2% 1,109 5,689
District of Columbia Washington 4,580 41.4% 1,895 6,475
Florida Tallahassee 4,580 -12.1% (552) 4,028
Florida Tampa 4,580 -5.4% (245) 4,335
Georgia Atlanta 4,580 -9.0% (413) 4,167
Hawaii Honolulu 0 0 0 0
Idaho Boise 4,580 -4.2% (191) 4,389
Illinois Chicago 4,580 21.7% 995 5,575
Indiana Indianapolis 4,580 3.2% 148 4,728
Iowa Davenport 4,580 -1.7% (79) 4,501
Iowa Waterloo 4,580 -10.0% (457) 4,123
Kansas Wichita 4,580 -7.5% (343) 4,237
Kentucky Louisville 4,580 -6.2% (284) 4,296
Louisiana New Orleans 4,580 -12.4% (567) 4,013
Maine Portland 4,580 -1.1% (48) 4,532
Maryland Baltimore 4,580 4.6% 211 4,791
Massachusetts Boston 4,580 37.7% 1,728 6,308
Michigan Detroit 4,580 4.2% 193 4,773
Michigan Grand Rapids 4,580 -8.7% (398) 4,182
Minnesota St. Paul 4,580 4.3% 195 4,775
Mississippi Jackson 4,580 -8.2% (377) 4,203
Missouri St. Louis 4,580 7.7% 354 4,934
Missouri Kansas City 4,580 3.7% 168 4,748
Montana Great Falls 4,580 -4.8% (222) 4,358
Nebraska Omaha 4,580 -3.9% (180) 4,400
New Hampshire Concord 4,580 -1.9% (87) 4,493
New Jersey Newark 4,580 17.1% 781 5,361

4-6
Base
Project Location Delta Cost Total Location
Cost Percent Difference Project Cost
State City ($/kW) Variation ($/kW) ($/kW)
New Mexico Albuquerque 4,580 -4.4% (202) 4,378
New York New York 4,580 36.0% 1,650 6,230
New York Syracuse 4,580 9.7% 442 5,022
Nevada Las Vegas 4,580 7.9% 361 4,941
North Carolina Charlotte 4,580 -10.7% (492) 4,088
North Dakota Bismarck 4,580 -8.8% (404) 4,176
Ohio Cincinnati 4,580 0.1% 4 4,584
Oregon Portland 4,580 10.1% 461 5,041
Pennsylvania Philadelphia 4,580 13.3% 609 5,189
Pennsylvania Wilkes-Barre 4,580 -4.0% (182) 4,398
Rhode Island Providence 4,580 4.5% 205 4,785
South Carolina Spartanburg 4,580 -13.1% (600) 3,980
South Dakota Rapid City 4,580 -11.8% (542) 4,038
Tennessee Knoxville 4,580 -9.9% (455) 4,125
Texas Houston 4,580 -10.5% (482) 4,098
Utah Salt Lake City 4,580 -3.6% (167) 4,413
Vermont Burlington 4,580 -6.0% (273) 4,307
Virginia Alexandria 4,580 9.9% 455 5,035
Virginia Lynchburg 4,580 -2.4% (112) 4,468
Washington Seattle 4,580 13.7% 626 5,206
Washington Spokane 4,580 -2.6% (121) 4,459
West Virginia Charleston 4,580 -2.0% (93) 4,487
Wisconsin Green Bay 4,580 0.3% 14 4,594
Wyoming Cheyenne 4,580 2.2% 102 4,682
Puerto Rico Cayey 0 0 0 0

4.5 O&M ESTIMATE


The O&M items for the APC/CCS Facility are the same as those discussed in Section 3.5 for the
APC Facility (without CCS), except that adders are included to both FOM and VOM to
accommodate the expenses associated with compressor maintenance, sequestration maintenance,
and the associated additional labor required to manage, operate, and maintain the additional
equipment. Table 4-5 and Table 4-6 present the FOM and VOM expenses for the APC/CCS
Facility.
TABLE 4-5 – O&M EXPENSES FOR APC/CCS (650,000 KW)
Technology: APC/CCS
Fixed O&M Expense $76.62/kW-year
Variable O&M Expense $9.05/MWh

4-7
TABLE 4-6 – O&M EXPENSES FOR APC/CCS (1,300,000 KW)
Technology: APC/CCS
Fixed O&M Expense $63.21/kW-year
Variable O&M Expense $9.05/MWh

4.6 ENVIRONMENTAL COMPLIANCE INFORMATION


In addition to the equipment utilized for environmental compliance in the APC Facility, the
APC/CCS Facility includes an amine scrubber that is intended to remove 90 percent of the CO2
produced in the combustion process, wherein the captured CO2 is later compressed to HP and
sequestered, as discussed above. Table 4-7 presents the environmental emissions for the
APC/CCS Facility.
TABLE 4-7 – ENVIRONMENTAL EMISSIONS FOR APC/CCS
Technology: APC/CCS
NOX 0.06 lb/MMBtu
SO2 0.02 lb/MMBtu
CO2 20.6 lb/MMBtu

4-8
5. CONVENTIONAL NATURAL GAS COMBINED CYCLE (NGCC)
5.1 MECHANICAL EQUIPMENT AND SYSTEMS
The Conventional NGCC produces 540 MW of net electricity. The facility utilizes two natural
gas-fueled F-class CTs and associated electric generators, two supplemental-fired heat recovery
steam generators (“HRSG”), and one condensing ST and associated electric generator operating
in combined-cycle mode. Each CT is designed to produce nominally 172 MW and includes a
dry-low NOX (“DLN”) combustion system and a hydrogen-cooled electric generator. The two
triple-pressure HRSGs include integrated deaerators, SCRs, oxidation catalyst for the control of
carbon monoxide (“CO”), and supplemental duct firing with associated combustion
management. The ST is a single-reheat condensing ST designed for variable pressure operation,
designed to produce an additional 210 MW. The ST exhaust is cooled in a closed-loop
condenser system with a mechanical draft cooling tower. The CTs are equipped with inlet
evaporative coolers to reduce the temperature of the turbine inlet air to increase summer output.
The Conventional NGCC plant also includes a raw water treatment system consisting of
clarifiers and filters and a turbine hall, in which the CTs, ST, and HRSGs are enclosed to avoid
freezing during periods of cold ambient temperatures. Figure 5-1 presents the Conventional
NGCC process flow diagram.

5-1
FIGURE 5-1 – CONVENTIONAL NGCC DESIGN CONFIGURATION

5.2 ELECTRICAL AND CONTROL SYSTEMS


The Conventional NGCC has two CT electric generators and one ST electric generator. The
generators for the CTs are 60 Hz and rated at approximately 215 MVA with an output voltage of
18 kV. The ST electric generator is 60 Hz and rated at approximately 310 MVA with an output
voltage of 18 kV. Each CT and ST electric generator is connected to a high-voltage bus in the
Conventional NGCC via a dedicated generator circuit breaker, generator GSU, and a disconnect
switch. The GSUs increase the voltage from the electric generators from 18 kV to
interconnected high voltage.
The Conventional NGCC is controlled using a DCS. The DCS provides centralized control of
the facility by integrating the control systems provided with each individual CT and associated
electric generator, ST and associated electric generator, and the control of BOP systems and
equipment.

5.3 OFF-SITE REQUIREMENTS


Natural gas is delivered to the facility through a lateral connected to the local natural gas trunk
line. Water for all processes at the Conventional NGCC Facility is obtained from a one of
several available water sources (e.g., municipal water supply). The Conventional NGCC Facility

5-2
uses a water treatment system and a high-efficiency reverse osmosis system to reduce the
dissolved solids from the cooling water and to provide distilled water for HRSG makeup.
Wastewater is sent to a municipal wastewater system. Further, the electrical interconnection
from the Conventional NGCC on-site switchyard is effectuated by a connection to an adjacent
utility substation.

5.4 CAPITAL COST ESTIMATE


The base Cost Estimate for the Conventional NGCC Facility with a nominal capacity of
540 MW is $980/kW. Table 5-1 summarizes the Cost Estimate categories for the Conventional
NGCC Facility.
TABLE 5-1 – BASE PLANT SITE CAPITAL COST ESTIMATE FOR CONVENTIONAL
NGCC
Technology: Conventional NGCC
Nominal Capacity (ISO): 540,000 kW
Nominal Heat Rate (ISO): 7,050 Btu/kWh-HHV

Capital Cost Category (000s) (October 1, 2010$)

Civil Structural Material and Installation 40,100

Mechanical Equipment Supply and


Installation 221,500

Electrical / I&C Supply and Installation 35,000

Project Indirects (1) 88,400

EPC Cost before Contingency and Fee 385,000

Fee and Contingency 55,000

Total Project EPC 440,000

Owner Costs (excluding project finance) 88,000

Total Project Cost (excluding finance) 528,000

Total Project EPC / kW 815

Owner Costs 20% (excluding project finance) / kW 163

Total Project Cost (excluding project finance) / kW 978

(1) Includes engineering, distributable costs, scaffolding, construction management, and start-up.

5-3
For this type of technology and power plant configuration, our regional adjustments took into
consideration the following: outdoor installation considerations, air-cooled condensers
compared to cooling towers, seismic design differences, zero-water discharge issues, local
technical enhancements (e.g., additional noise remediation that is generally required in urban
siting), remote location issues, urban – high density population issues, labor wage and
productivity differences, location adjustments, owner cost differences, and the increase in
overheads associated with these 10 adjustments.
Outdoor installation locations are considered in geographic areas where enclosed structures for
the boilers would not be required due to the low probability of freezing. The locations that were
included in outdoor installation are Alabama, Arizona, Arkansas, Florida, Georgia, Hawaii,
Louisiana, Mississippi, New Mexico, South Carolina, and Puerto Rico.
The potential locations relating to the use of air-cooled condensers in place of mechanical draft
wet cooling towers were identified as Arizona, California, Connecticut, Delaware, District of
Columbia, Maryland, Massachusetts, New Hampshire, New York, Oregon, Pennsylvania, Rhode
Island, Virginia, and Puerto Rico. These locations are identified as those where conservation of
water, notwithstanding supply, has been and/or is becoming a significant issue in plant
permitting/siting.
Seismic design differences among the various locations were based on U.S. seismic map
information that detailed the various seismic zones throughout the U.S. No cost increases were
associated with seismic Zone 0 and cost step increases were considered for Zones 1, 2, 3 and 4.
The potential locations relating to the need of zero-water discharge were identified as Arizona,
California, Colorado, Connecticut, Delaware, District of Columbia, Maryland, Massachusetts,
New Hampshire, New York, Rhode Island, Virginia, and Puerto Rico. Similar to water usage
discussed above in this section on Conventional NGCC, wastewater treatment and disposal is
considered a critical permitting/siting issue in these areas.
The locations with local technical enhancements include California, Colorado, Connecticut,
Delaware, District of Columbia, Louisiana, Maryland, Massachusetts, New Jersey, New York,
Rhode Island, Vermont, and Virginia. These areas are places where noise, visual impacts, and
other technical enhancements generally need to be made by a project developer or utility to
comply with the applicable permitting/siting requirements.
Remote location issues are related to geographic areas that typically require installation of man
camps, higher craft incentives, and higher per diems are generally required with respect to
construction, due to the fact that such areas are long distances from urban areas, where labor is
generally abundant. Remote location designations were also considered in locations where
higher equipment freight costs are typically incurred, which for example are regions not near
established rail or highway access. Remote locations related to the Conventional NGCC include
Fairbanks, Alaska; Honolulu, Hawaii; Albuquerque, New Mexico; Cheyenne, Wyoming; and
Cayey, Puerto Rico.
Labor wage and productivity differences were handled as discussed in Section 2.5.1., taking into
consideration the amount of labor we estimated for the Conventional NGCC Facility.
Location adjustments were made to locations where higher cost of living levels are incurred
and/or where population density generally correlates to higher construction costs for power and
other infrastructure projects. These locations include Alaska, California, Connecticut, Delaware,

5-4
District of Columbia, Hawaii, Illinois, Maine, Maryland, Massachusetts, Michigan, Minnesota,
New York, Ohio, and Wisconsin.
Owner costs were reviewed based on the need for utility upgrades and/or infrastructure costs
such as new facility transmission lines to tie to existing utility transmission substations or
existing transmission lines.
Table 5-2 presents the Conventional NGCC capital cost variations for alternative U.S. plant
locations, including the difference between the given location and the average location specified
for the Cost Estimate.
TABLE 5-2 – LOCATION-BASED COSTS FOR CONVENTIONAL NGCC
(OCTOBER 1, 2010 DOLLARS)
Base
Project Location Delta Cost Total Location
Cost Percent Difference Project Cost
State City ($/kW) Variation ($/kW) ($/kW)
Alaska Anchorage 980 33.3% 326 1,306
Alaska Fairbanks 980 38.2% 374 1,354
Alabama Huntsville 980 -8.6% (84) 896
Arizona Phoenix 980 2.6% 25 1,005
Arkansas Little Rock 980 -7.5% (73) 912
California Los Angeles 980 29.0% 284 1,264
California Redding 980 13.5% 132 1,112
California Bakersfield 980 15.8% 154 1,134
California Sacramento 980 20.5% 200 1,180
California San Francisco 980 46.1% 452 1,432
Colorado Denver 980 2.1% 21 1,001
Connecticut Hartford 980 27.9% 274 1,254
Delaware Dover 980 26.2% 256 1,236
District of Columbia Washington 980 33.3% 326 1,306
Florida Tallahassee 980 -11.6% (113) 867
Florida Tampa 980 -6.0% (58) 922
Georgia Atlanta 980 -6.6% (64) 916
Hawaii Honolulu 980 50.2% 492 1,472
Idaho Boise 980 -3.9% (38) 942
Illinois Chicago 980 16.7% 163 1,143
Indiana Indianapolis 980 0.9% 9 989
Iowa Davenport 980 0.5% 5 985
Iowa Waterloo 980 -6.4% (63) 917
Kansas Wichita 980 -5.0% (49) 936
Kentucky Louisville 980 -5.4% (53) 927
Louisiana New Orleans 980 -5.2% (51) 929
Maine Portland 980 -3.4% (33) 952
Maryland Baltimore 980 20.4% 200 1,180
Massachusetts Boston 980 40.0% 392 1,372
Michigan Detroit 980 5.3% 52 1,032

5-5
Base
Project Location Delta Cost Total Location
Cost Percent Difference Project Cost
State City ($/kW) Variation ($/kW) ($/kW)
Michigan Grand Rapids 980 -5.3% (52) 928
Minnesota St. Paul 980 4.5% 44 1,024
Mississippi Jackson 980 -8.6% (84) 896
Missouri St. Louis 980 5.6% 55 1,035
Missouri Kansas City 980 2.7% 27 1,007
Montana Great Falls 980 -2.4% (24) 956
Nebraska Omaha 980 -1.5% (15) 965
New Hampshire Concord 980 7.3% 72 1,052
New Jersey Newark 980 22.1% 217 1,197
New Mexico Albuquerque 980 -2.4% (24) 956
New York New York 980 68.4% 670 1,650
New York Syracuse 980 16.3% 160 1,140
Nevada Las Vegas 980 6.2% 61 1,041
North Carolina Charlotte 980 -10.5% (102) 888
North Dakota Bismarck 980 -5.4% (53) 927
Ohio Cincinnati 980 -1.7% (17) 963
Oregon Portland 980 13.2% 130 1,110
Pennsylvania Philadelphia 980 26.1% 255 1,235
Pennsylvania Wilkes-Barre 980 -1.7% (17) 963
Rhode Island Providence 980 22.0% 215 1,195
South Carolina Spartanburg 980 -12.8% (126) 854
South Dakota Rapid City 980 -8.0% (78) 902
Tennessee Knoxville 980 -8.5% (84) 896
Texas Houston 980 -8.8% (87) 893
Utah Salt Lake City 980 -4.0% (39) 941
Vermont Burlington 980 -0.1% (1) 979
Virginia Alexandria 980 16.0% 157 1,137
Virginia Lynchburg 980 -5.8% (57) 923
Washington Seattle 980 7.0% 68 1,048
Washington Spokane 980 -2.6% (25) 955
West Virginia Charleston 980 0.1% 1 981
Wisconsin Green Bay 980 -1.3% (13) 967
Wyoming Cheyenne 980 -0.5% (4) 976
Puerto Rico Cayey 980 10.9% 106 1,086

5.5 O&M ESTIMATE


In addition to the general O&M items discussed in Section 2.5.2., the Conventional NGCC
Facility includes the major maintenance for the CTs, as well as the BOP, including the ST,
associated electric generators, HRSGs, and emissions reduction catalysts. These major
maintenance expenses are included with the VOM expense for this technology and are given on
an average basis across the MWhs incurred. Typically, significant overhauls on a Conventional

5-6
NGCC Facility occur no less frequently than 24,000 operating hour intervals. Table 5-3 presents
the O&M expenses for the Conventional NGCC Facility.
TABLE 5-3 – O&M EXPENSES FOR CONVENTIONAL NGCC
Technology: Conventional NGCC
Fixed O&M Expense $14.39/kW-year
Variable O&M Expense $3.43/MWh

5.6 ENVIRONMENTAL COMPLIANCE INFORMATION


The Conventional NGCC utilizes DLN combustion systems in the primary combustion zone of
the CT and best available burner technology with respect to the duct burners in the HRSGs to
manage the production of NOX and CO. Additional control of NOX and CO is accomplished
through an SCR and an oxidization catalyst, respectively. Oxides of sulfur in the Conventional
NGCC are managed through the natural gas fuel quality, which is generally very low in sulfur
U.S. domestic pipeline quality natural gas, and consequently the low sulfur content translates
into SO2 after combustion. The Conventional NGCC does not include any control devices for
CO2, which is proportional the heat rate (inversely proportional to the efficiency) of the
technology. Water, wastewater, and solid waste compliance are achieved through traditional on-
site and off-site methods, and the costs for such compliance are included in the O&M estimate
for the Conventional NGCC Facility. Table 5-4 presents environmental emissions for the
Conventional NGCC Facility.
TABLE 5-4 – ENVIRONMENTAL EMISSIONS FOR CONVENTIONAL NGCC
Technology: Conventional NGCC
NOX 0.0075 lb/MMBtu
SO2 0.001 lb/MMBtu
CO2 117 lb/MMBtu

5-7
6. ADVANCED GENERATION NATURAL GAS COMBINED CYCLE (AG-NGCC)
6.1 MECHANICAL EQUIPMENT AND SYSTEMS
The Advanced Generation (“AG”)-NGCC design is the same as the Conventional NGCC, except
an H-class CT is utilized in lieu of F-class, and there is only one CT/HRSG supporting the ST
included. Since the H-class CT design employees steam cooling of both stationary and rotational
hot parts, the HRSG systems and the ST are both considered “advanced” designs, as compared to
the Conventional NGCC. The net output of the AG-NGCC is 400 MW. Figure 6-1 presents the
AG-NGCC process flow diagram.
FIGURE 6-1 – AG-NGCC DESIGN CONFIGURATION

6.2 ELECTRICAL AND CONTROL SYSTEMS


The AG-NGCC electrical and control systems are similar to the Conventional NGCC Facility,
except that the sizing of the generators and transformers are larger to support the larger CT and
ST equipment utilized in the AG-NGCC.

6.3 OFF-SITE REQUIREMENTS


The off-site requirements for the AG-NGCC Facility are the same as the Conventional NGCC.
Refer to Section 5.3 for the description of the Conventional NGCC off-site requirements.

6.4 CAPITAL COST ESTIMATE


The base Cost Estimate for the AG-NGCC Facility with a nominal capacity of 400 MW is
$1,003/kW. Table 6-1 summarizes the Cost Estimate categories for the Conventional NGCC
Facility.

6-1
TABLE 6-1 – BASE PLANT SITE CAPITAL COST ESTIMATE FOR AG-NGCC
Technology: AG-NGCC
Nominal Capacity (ISO): 400,000 kW
Nominal Heat Rate (ISO): 6,430 Btu/kWh-HHV

Capital Cost Category (000s) (October 1, 2010$)

Civil Structural Material and Installation 20,610

Mechanical Equipment Supply and


Installation 178,650

Electrical / I&C Supply and Installation 24,800

Project Indirects (1) 68,300

EPC Cost before Contingency and Fee 292,360

Fee and Contingency 42,000

Total Project EPC 334,360

Owner Costs (excluding project finance) 66,872

Total Project Cost (excluding finance) 401,232

Total Project EPC / kW 836

Owner Costs 20% (excluding project finance) / kW 167

Total Project Cost (excluding project finance) / kW 1,003

(1) Includes engineering, distributable costs, scaffolding, construction management, and start-up.

The locational adjustments for the AG-NGCC Facility similar to those made for the
Conventional NGCC Facility.
Table 6-2 presents the AG-NGCC Facility capital cost variations for alternative U.S. plant
locations, including the difference between the given location and the average location specified
for the Cost Estimate.

6-2
TABLE 6-2 – LOCATION-BASED COSTS FOR AG-NGCC
(OCTOBER 1, 2010 DOLLARS)
Base
Project Location Delta Cost Total Location
Cost Percent Difference Project Cost
State City ($/kW) Variation ($/kW) ($/kW)
Alaska Anchorage 1,005 32.4% 325 1,330
Alaska Fairbanks 1,005 37.2% 374 1,379
Alabama Huntsville 1,005 -8.3% (84) 921
Arizona Phoenix 1,005 2.6% 26 1,031
Arkansas Little Rock 1,005 -6.7% (67) 938
California Los Angeles 1,005 28.2% 283 1,288
California Redding 1,005 13.1% 132 1,137
California Bakersfield 1,005 15.4% 154 1,159
California Sacramento 1,005 19.9% 200 1,205
California San Francisco 1,005 44.9% 451 1,456
Colorado Denver 1,005 2.1% 21 1,026
Connecticut Hartford 1,005 27.2% 273 1,278
Delaware Dover 1,005 25.5% 256 1,261
District of Columbia Washington 1,005 32.5% 326 1,331
Florida Tallahassee 1,005 -11.2% (113) 892
Florida Tampa 1,005 -5.8% (58) 947
Georgia Atlanta 1,005 -6.3% (64) 941
Hawaii Honolulu 1,005 48.9% 492 1,497
Idaho Boise 1,005 -3.7% (38) 967
Illinois Chicago 1,005 16.1% 162 1,167
Indiana Indianapolis 1,005 0.9% 9 1,014
Iowa Davenport 1,005 0.5% 5 1,010
Iowa Waterloo 1,005 -6.2% (62) 943
Kansas Wichita 1,005 -4.3% (43) 962
Kentucky Louisville 1,005 -5.2% (52) 953
Louisiana New Orleans 1,005 -5.0% (50) 955
Maine Portland 1,005 -2.7% (27) 978
Maryland Baltimore 1,005 19.9% 200 1,205
Massachusetts Boston 1,005 38.9% 391 1,396
Michigan Detroit 1,005 5.2% 52 1,057
Michigan Grand Rapids 1,005 -5.1% (51) 954
Minnesota St. Paul 1,005 4.4% 44 1,049
Mississippi Jackson 1,005 -8.3% (83) 922
Missouri St. Louis 1,005 5.4% 54 1,059
Missouri Kansas City 1,005 2.6% 26 1,031
Montana Great Falls 1,005 -2.3% (24) 981
Nebraska Omaha 1,005 -1.4% (14) 991
New Hampshire Concord 1,005 7.2% 72 1,077
New Jersey Newark 1,005 21.4% 215 1,220
New Mexico Albuquerque 1,005 -2.3% (23) 982

6-3
Base
Project Location Delta Cost Total Location
Cost Percent Difference Project Cost
State City ($/kW) Variation ($/kW) ($/kW)
New York New York 1,005 66.4% 667 1,672
New York Syracuse 1,005 15.9% 160 1,165
Nevada Las Vegas 1,005 6.0% 61 1,066
North Carolina Charlotte 1,005 -9.1% (91) 914
North Dakota Bismarck 1,005 -5.2% (52) 953
Ohio Cincinnati 1,005 -1.6% (16) 989
Oregon Portland 1,005 12.9% 130 1,135
Pennsylvania Philadelphia 1,005 25.3% 254 1,259
Pennsylvania Wilkes-Barre 1,005 -1.6% (16) 989
Rhode Island Providence 1,005 21.4% 215 1,220
South Carolina Spartanburg 1,005 -12.4% (125) 880
South Dakota Rapid City 1,005 -7.7% (77) 928
Tennessee Knoxville 1,005 -8.2% (83) 922
Texas Houston 1,005 -8.5% (86) 919
Utah Salt Lake City 1,005 -3.8% (38) 967
Vermont Burlington 1,005 0.0% (0) 1,005
Virginia Alexandria 1,005 15.6% 157 1,162
Virginia Lynchburg 1,005 -5.6% (56) 949
Washington Seattle 1,005 6.8% 68 1,073
Washington Spokane 1,005 -2.5% (25) 980
West Virginia Charleston 1,005 0.1% 1 1,006
Wisconsin Green Bay 1,005 -1.3% (13) 992
Wyoming Cheyenne 1,005 -0.4% (4) 1,001
Puerto Rico Cayey 1,005 10.6% 107 1,112

6.5 O&M ESTIMATE


The O&M items for the AG-NGCC Facility are the same as those described in Section 5.5 for
the Conventional NGCC Facility. Table 6-3 presents the O&M expenses for the AG-NGCC
Facility.
TABLE 6-3 – O&M EXPENSES FOR AG-NGCC
Technology: AG-NGCC
Fixed O&M Expense $14.62/kW-year
Variable O&M Expense $3.11/MWh

6.6 ENVIRONMENTAL COMPLIANCE INFORMATION


The environmental compliance strategy and equipment for the AG-NGCC Facility is the same as
those described in Section 5.6 for the Conventional NGCC Facility. Table 6-4 presents
environmental emissions for the AG-NGCC Facility.

6-4
TABLE 6-4 – ENVIRONMENTAL EMISSIONS FOR AG-NGCC
Technology: AG-NGCC
NOX 0.0075 lb/MMBtu
SO2 0.001 lb/MMBtu
CO2 117 lb/MMBtu

6-5
7. ADVANCED GENERATION NATURAL GAS COMBINED CYCLE WITH CCS
(AG-NGCC/CCS)
7.1 MECHANICAL EQUIPMENT AND SYSTEMS
The plant configuration for the AG-NGCC/CCS Facility is the same as the AG-NGCC Facility
with the exception that an amine system based on MEA as the solvent is included for CO2
capture from the flue gas. The captured CO2 is compressed to approximately 2,000 psia for
injection into a pipeline at the plant fence line. Figure 7-1 presents the AG-NGCC with CCS
process flow diagram.
FIGURE 7-1 – AG-NGCC WITH CCS DESIGN CONFIGURATION

7.2 ELECTRICAL AND CONTROL SYSTEMS


The electrical and control systems for the AG-NGCC/CCS Facility are materially similar to the
AG-NGCC Facility described in Section 6.2.

7.3 OFF-SITE REQUIREMENTS


The off-site requirements for the AG-NGCC/CCS Facility are materially similar to the
AG-NGCC Facility, except that the CO2 needs sequestering in one of the following geologic
formations: (1) exhausted gas storage location, (2) unminable coal seam, (3) enhanced oil
recovery, or (4) saline aquifer. To the extent that a sequestration site is not near the given facility
being analyzed, transportation for a viable sequestration site has the potential to materially affect
the capital cost estimates discussed below.

7.4 CAPITAL COST ESTIMATE


The base Cost Estimate for the AG-NGCC/CCS Facility with a nominal capacity of 340 MW is
$2,060/kW. The capital cost estimate was based on the AG-NGCC (without CCS) and the base
cost estimate was increased to include the expected costs of CCS. Table 7-1 summarizes the
Cost Estimate categories for the AG-NGCC/CCS Facility.

7-1
TABLE 7-1 – BASE PLANT SITE CAPITAL COST ESTIMATE FOR AG-NGCC/CCS
COST
Technology: AG-NGCC/CCS
Nominal Capacity (ISO): 340,000 kW
Nominal Heat Rate (ISO): 7,525 Btu/kWh-HHV

Total Project EPC 583,667

Owner Costs (excluding project finance) 116,733

Total Project Cost (excluding finance) 700,400

Total Project EPC / kW 1,717

Owner Costs 20% (excluding project finance) / kW 343

Total Project Cost (excluding project finance) / kW 2,060

(1) Includes engineering, distributable costs, scaffolding, construction management, and start-up.

The locational adjustments for the AG-NGCC/CCS Facility are similar to those made for the
Conventional NGCC Facility, described in Section 5.4.
Table 7-2 presents the AG-NGCC/CCS Facility capital cost variations for alternative U.S. plant
locations, including the difference between the given location and the average location specified
for the Cost Estimate.

7-2
TABLE 7-2 – LOCATION-BASED COSTS FOR AG-NGCC/CCS
(OCTOBER 1, 2010 DOLLARS)
Base
Project Location Delta Cost Total Location
Cost Percent Difference Project Cost
State City ($/kW) Variation ($/kW) ($/kW)
Alaska Anchorage 2,060 20.8% 428 2,488
Alaska Fairbanks 2,060 23.7% 488 2,548
Alabama Huntsville 2,060 -8.5% (174) 1,886
Arizona Phoenix 2,060 -2.3% (47) 2,013
Arkansas Little Rock 2,060 -7.0% (143) 1,917
California Los Angeles 2,060 16.1% 331 2,391
California Redding 2,060 7.4% 152 2,212
California Bakersfield 2,060 8.2% 169 2,229
California Sacramento 2,060 13.3% 274 2,334
California San Francisco 2,060 29.8% 615 2,675
Colorado Denver 2,060 -2.9% (60) 2,000
Connecticut Hartford 2,060 15.9% 328 2,388
Delaware Dover 2,060 13.5% 278 2,338
District of Columbia Washington 2,060 14.8% 305 2,365
Florida Tallahassee 2,060 -11.4% (234) 1,826
Florida Tampa 2,060 -5.3% (108) 1,952
Georgia Atlanta 2,060 -7.9% (162) 1,898
Hawaii Honolulu 2,060 26.8% 551 2,611
Idaho Boise 2,060 -4.9% (100) 1,960
Illinois Chicago 2,060 16.9% 348 2,408
Indiana Indianapolis 2,060 -0.5% (11) 2,049
Iowa Davenport 2,060 -0.6% (13) 2,047
Iowa Waterloo 2,060 -8.2% (168) 1,892
Kansas Wichita 2,060 -6.4% (132) 1,928
Kentucky Louisville 2,060 -6.2% (127) 1,933
Louisiana New Orleans 2,060 -8.5% (175) 1,885
Maine Portland 2,060 -4.9% (102) 1,958
Maryland Baltimore 2,060 7.3% 150 2,210
Massachusetts Boston 2,060 26.6% 547 2,607
Michigan Detroit 2,060 4.3% 88 2,148
Michigan Grand Rapids 2,060 -7.0% (144) 1,916
Minnesota St. Paul 2,060 3.7% 76 2,136
Mississippi Jackson 2,060 -8.4% (173) 1,887
Missouri St. Louis 2,060 4.4% 91 2,151
Missouri Kansas City 2,060 2.3% 47 2,107
Montana Great Falls 2,060 -4.5% (93) 1,967
Nebraska Omaha 2,060 -3.2% (65) 1,995
New Hampshire Concord 2,060 1.6% 34 2,094
New Jersey Newark 2,060 18.8% 388 2,448
New Mexico Albuquerque 2,060 -4.2% (86) 1,974

7-3
Base
Project Location Delta Cost Total Location
Cost Percent Difference Project Cost
State City ($/kW) Variation ($/kW) ($/kW)
New York New York 2,060 50.1% 1,032 3,092
New York Syracuse 2,060 6.4% 133 2,193
Nevada Las Vegas 2,060 6.1% 126 2,186
North Carolina Charlotte 2,060 -10.8% (223) 1,837
North Dakota Bismarck 2,060 -7.1% (146) 1,914
Ohio Cincinnati 2,060 -3.4% (70) 1,990
Oregon Portland 2,060 7.1% 146 2,206
Pennsylvania Philadelphia 2,060 18.3% 378 2,438
Pennsylvania Wilkes-Barre 2,060 -3.7% (77) 1,983
Rhode Island Providence 2,060 11.9% 244 2,304
South Carolina Spartanburg 2,060 -13.4% (275) 1,785
South Dakota Rapid City 2,060 -9.8% (203) 1,857
Tennessee Knoxville 2,060 -9.6% (197) 1,863
Texas Houston 2,060 -9.6% (198) 1,862
Utah Salt Lake City 2,060 -5.9% (123) 1,937
Vermont Burlington 2,060 -4.0% (81) 1,979
Virginia Alexandria 2,060 5.7% 118 2,178
Virginia Lynchburg 2,060 -6.6% (137) 1,923
Washington Seattle 2,060 6.0% 123 2,183
Washington Spokane 2,060 -3.5% (71) 1,989
West Virginia Charleston 2,060 -1.4% (30) 2,030
Wisconsin Green Bay 2,060 -2.7% (55) 2,005
Wyoming Cheyenne 2,060 -4.5% (92) 1,968
Puerto Rico Cayey 2,060 1.7% 34 2,094

7.5 O&M ESTIMATE


The O&M items for the AG-NGCC/CCS Facility are the same as those set forth in Section 6.5
for the AG-NGCC Facility, except that adders are included to both FOM and VOM to
accommodate the expenses associated with compressor maintenance, sequestration maintenance,
and the associated additional labor required to manage, operate, and maintain the additional
equipment. Table 7-3 presents the O&M expenses for the AG-NGCC/CCS Facility.
TABLE 7-3 – O&M EXPENSES FOR AG-NGCC WITH CCS
Technology: AG-NGCC/CCS
Fixed O&M Expense $30.25/kW-year
Variable O&M Expense $6.45/MWh

7.6 ENVIRONMENTAL COMPLIANCE INFORMATION


The environmental compliance strategy and equipment for the AG-NGCC Facility are the same
as those described in Section 5.6 for the Conventional NGCC Facility, with the exception that
the AG-NGCC with CCS Facility includes an amine scrubber control device for CO2. Table 7-4
presents environmental emissions for the AG-NGCC/CCS Facility.

7-4
TABLE 7-4 – ENVIRONMENTAL EMISSIONS FOR AG-NGCC/CCS
Technology: AG-NGCC/CCS
NOX 0.0075 lb/MMBtu
SO2 0.001 lb/MMBtu
CO2 12 lb/MMBtu

7-5
8. CONVENTIONAL COMBUSTION TURBINE (CT)

8.1 MECHANICAL EQUIPMENT AND SYSTEMS


The Conventional CT Facility produces 85 MW of electricity using a single natural gas-fueled
E-class CT and associated electric generator in simple-cycle mode. The CT is equipped with an
inlet evaporative cooler to reduce the temperature of the turbine inlet air to increase summer
output. Figure 8-1 presents the Conventional CT Facility process flow diagram.
FIGURE 8-1 – CONVENTIONAL CT DESIGN CONFIGURATION

8.2 ELECTRICAL AND CONTROL SYSTEMS


The Conventional CT Facility has one CT electric generator. The generator is a 60 Hz machine
rated at approximately 101 MVA with an output voltage of 13.8 kV. The CT electric generator
is connected to a high-voltage bus in the Conventional CT Facility switchyard via a dedicated
generator circuit breaker, GSU, and a disconnect switch. The GSU increases the voltage from
the electric generator from 13.8 kV to interconnected transmission system high voltage.
The Conventional CT Facility is controlled using a DCS. The DCS provides centralized control
of the facility by integrating the control systems provided with the individual CT and associated
electric generator and the control of BOP systems and equipment.

8.3 OFF-SITE REQUIREMENTS


Natural gas is delivered to the facility through an approximately lateral connected to the local
natural gas trunk line. Water for the limited processes that utilize water at the Conventional CT
Facility is obtained from a one of several available water sources (e.g., municipal water supply).
The Conventional CT Facility uses a water treatment system and a high-efficiency reverse
osmosis system to reduce the dissolved solids for compressor cleaning. Wastewater is sent to a
municipal wastewater system. Further, the electrical interconnection from the Conventional CT
on-site switchyard is effectuated by a connection to an adjacent utility substation.

8-1
8.4 CAPITAL COST ESTIMATE
The base Cost Estimate for the Conventional CT Facility with a nominal capacity of 85 MW is
$975/kW. Table 8-1 summarizes the Cost Estimate categories for the Conventional CT Facility.
TABLE 8-1 – BASE PLANT SITE
CAPITAL COST ESTIMATE FOR CONVENTIONAL CT
Technology: Conventional CT
Nominal Capacity (ISO): 85,000 kW
Nominal Heat Rate (ISO): 10,850 Btu/kWh-HHV

Capital Cost Category (000s) (October 1, 2010$)

Civil Structural Material and Installation 5,570

Mechanical Equipment Supply and


Installation 34,709

Electrical / I&C Supply and Installation 10,700

Project Indirects (1) 12,248

EPC Cost before Contingency and Fee 63,227

Fee and Contingency 5,757

Total Project EPC 68,994

Owner Costs (excluding project finance) 13,799

Total Project Cost (excluding finance) 82,793

Total Project EPC / kW 812

Owner Costs 20% (excluding project finance) / kW 162

Total Project Cost (excluding project finance) / kW 974

(1) Includes engineering, distributable costs, scaffolding, construction management, and start-up.

For this type of technology and power plant configuration, our regional adjustments took into
consideration the following: outdoor installation considerations, seismic design differences,
local technical enhancements (e.g., additional noise remediation that is generally required in
urban siting), remote location issues, urban – high density population issues, labor wage and
productivity differences, location adjustments, owner cost differences, and the increase in
overheads associated with these previous eight location adjustments.
Outdoor installation locations are considered in geographic areas where enclosed structures for
the boilers would not be required due to the low probability of freezing. The locations that were

8-2
included in outdoor installation are Alabama, Arizona, Arkansas, Florida, Georgia, Hawaii,
Louisiana, Mississippi, New Mexico, South Carolina, and Puerto Rico.
Seismic design differences among the various locations were based on U.S. seismic map
information that detailed the various seismic zones throughout the U.S. No cost increases were
associated with seismic Zone 0 and cost step increases were considered for Zones 1, 2, 3 and 4.
The locations with local technical enhancements include California, Colorado, Connecticut,
Delaware, District of Columbia, Louisiana, Maryland, Massachusetts, New Jersey, New York,
Rhode Island, Vermont, and Virginia. These are areas where noise, visual impacts, and other
technical enhancements generally need to be made by a project developer or utility to comply
with the applicable permitting/siting requirements.
Remote location issues are related to geographic areas that typically require installation of man
camps, higher craft incentives, and higher per diems are generally required with respect to
construction, due to the fact that such areas are long distances from urban areas, where labor is
generally abundant. Remote location designations were also considered in locations where
higher equipment freight costs are typically incurred, which for example are regions not near
established rail or highway access. Remote locations related to the Conventional CT Facility
include Fairbanks, Alaska; Honolulu, Hawaii; Albuquerque, New Mexico; Cheyenne, Wyoming;
and Cayey, Puerto Rico.
Labor wage and productivity differences were handled as discussed in Section 2.5.1, taking into
consideration the amount of labor we estimated for the Conventional CT Facility.
Location adjustments were made to locations where higher cost of living levels are incurred
and/or where population density generally correlates to higher construction costs for power and
other infrastructure projects. These locations include Alaska, California, Connecticut, Delaware,
District of Columbia, Hawaii, Illinois, Maine, Maryland, Massachusetts, Michigan, Minnesota,
New York, Ohio, and Wisconsin.
Owner costs were reviewed based on the need for utility upgrades and/or infrastructure costs
such as new facility transmission lines to tie to existing utility transmission substations or
existing transmission lines.
Table 8-2 presents the Conventional CT Facility capital cost variations for alternative U.S. plant
locations.

8-3
TABLE 8-2 – LOCATION-BASED COSTS FOR CONVENTIONAL CT
(OCTOBER 1, 2010 DOLLARS)
Base
Project Location Delta Cost Total Location
Cost Percent Difference Project Cost
State City ($/kW) Variation ($/kW) ($/kW)
Alaska Anchorage 975 31.7% 309 1,284
Alaska Fairbanks 975 36.5% 355 1,330
Alabama Huntsville 975 -7.1% (69) 906
Arizona Phoenix 975 3.8% 38 1,013
Arkansas Little Rock 975 -5.7% (55) 920
California Los Angeles 975 28.3% 276 1,251
California Redding 975 13.2% 129 1,104
California Bakersfield 975 15.6% 152 1,127
California Sacramento 975 19.3% 188 1,163
California San Francisco 975 43.6% 425 1,400
Colorado Denver 975 3.5% 34 1,009
Connecticut Hartford 975 27.1% 265 1,240
Delaware Dover 975 25.9% 253 1,228
District of Columbia Washington 975 33.8% 330 1,305
Florida Tallahassee 975 -9.6% (93) 882
Florida Tampa 975 -5.1% (50) 925
Georgia Atlanta 975 -4.9% (48) 927
Hawaii Honolulu 975 49.5% 482 1,457
Idaho Boise 975 -2.8% (28) 947
Illinois Chicago 975 13.6% 132 1,107
Indiana Indianapolis 975 1.3% 13 988
Iowa Davenport 975 0.9% 8 983
Iowa Waterloo 975 -4.6% (45) 930
Kansas Wichita 975 -3.0% (29) 946
Kentucky Louisville 975 -4.1% (40) 935
Louisiana New Orleans 975 -3.1% (30) 945
Maine Portland 975 -1.6% (15) 960
Maryland Baltimore 975 21.4% 208 1,183
Massachusetts Boston 975 37.5% 366 1,341
Michigan Detroit 975 4.8% 46 1,021
Michigan Grand Rapids 975 -3.8% (37) 938
Minnesota St. Paul 975 4.0% 39 1,014
Mississippi Jackson 975 -7.1% (69) 906
Missouri St. Louis 975 5.0% 48 1,023
Missouri Kansas City 975 2.4% 23 998
Montana Great Falls 975 -1.3% (12) 963
Nebraska Omaha 975 -0.6% (6) 969
New Hampshire Concord 975 8.0% 78 1,053
New Jersey Newark 975 19.3% 188 1,163

8-4
Base
Project Location Delta Cost Total Location
Cost Percent Difference Project Cost
State City ($/kW) Variation ($/kW) ($/kW)
New Mexico Albuquerque 975 -1.4% (13) 962
New York New York 975 62.5% 609 1,584
New York Syracuse 975 16.8% 164 1,139
Nevada Las Vegas 975 5.2% 50 1,025
North Carolina Charlotte 975 -7.2% (70) 905
North Dakota Bismarck 975 -3.8% (38) 937
Ohio Cincinnati 975 -0.8% (8) 967
Oregon Portland 975 13.0% 127 1,102
Pennsylvania Philadelphia 975 24.1% 235 1,210
Pennsylvania Wilkes-Barre 975 -0.7% (7) 968
Rhode Island Providence 975 21.6% 210 1,185
South Carolina Spartanburg 975 -10.3% (101) 874
South Dakota Rapid City 975 -5.8% (57) 918
Tennessee Knoxville 975 -6.6% (65) 910
Texas Houston 975 -7.0% (68) 907
Utah Salt Lake City 975 -2.6% (25) 950
Vermont Burlington 975 1.3% 13 988
Virginia Alexandria 975 16.8% 163 1,138
Virginia Lynchburg 975 -4.5% (44) 931
Washington Seattle 975 6.1% 59 1,034
Washington Spokane 975 -1.8% (18) 957
West Virginia Charleston 975 0.6% 6 981
Wisconsin Green Bay 975 -0.6% (6) 969
Wyoming Cheyenne 975 1.0% 10 985
Puerto Rico Cayey 975 12.1% 118 1,093

8.5 O&M ESTIMATE


In addition to the general O&M items discussed in Section 2.5.2, the Conventional CT Facility
includes the major maintenance for the CT and associated electric generator. These major
maintenance expenses are included with the VOM expense for this technology, based upon an
assumed 10 percent annual capacity factor and an operating profile of approximately 8 hours of
operation per CT start. Typically, significant overhauls on a Conventional CT Facility occur no
less frequently than 8,000 operating hour intervals; with more significant major maintenance
outages occurring at 24,000 operating hour intervals; however, often times the major
maintenance for a CT at a peaking facility is driven off of CT hours (depending on the
equipment manufacturer and the operating hours per start incurred on the equipment). Table 8-3
presents the O&M expenses for the Conventional CT Facility.

8-5
TABLE 8-3 – O&M EXPENSES FOR CONVENTIONAL CT
Technology: Conventional CT
Fixed O&M Expense $6.98/kW-year
Variable O&M Expense $14.70/MWh

8.6 ENVIRONMENTAL COMPLIANCE INFORMATION


Typically, a Conventional CT Facility would be equipped with only the DLN combustion
hardware to mitigate emissions. There are some states in the U.S. that do require a “hot” SCR
that can operate at the higher exhaust temperatures of a simple-cycle plant, though that
equipment was not contemplated herein.
TABLE 8-4 – ENVIRONMENTAL EMISSIONS FOR CONVENTIONAL CT
Technology: Conventional CT
NOX 0.03 lb/MMBtu
SO2 0.001 lb/MMBtu
CO2 117 lb/MMBtu

8-6
9. ADVANCED COMBUSTION TURBINE (ACT)

9.1 MECHANICAL EQUIPMENT AND SYSTEMS


The Advanced CT Facility produces 210 MW of electricity using a single natural gas-fueled,
state of the art (as of 2010) F-class CT and associated electric generator. The CT is equipped
with an inlet evaporative cooler to reduce the temperature of the turbine inlet air to increase
summer output. Figure 9-1 presents the Advanced CT process flow diagram.
FIGURE 9-1 – ADVANCED CT DESIGN CONFIGURATION

9.2 ELECTRICAL AND CONTROL SYSTEMS


The Advanced CT Facility has the same general electrical and control systems as the
Conventional CT Facility, except that the electric generator is rated at approximately 234 MVA
and the corresponding GSU is larger in the Advanced CT Facility.

9.3 OFF-SITE REQUIREMENTS


The off-site requirements for the Advanced CT Facility are materially similar to the
Conventional CT Facility.

9.4 CAPITAL COST ESTIMATE


The base Cost Estimate for the Advanced CT Facility with a nominal capacity of 210 MW is
$665/kW. Table 9-1 summarizes the Cost Estimate categories for the Advanced CT Facility.

9-1
TABLE 9-1 – BASE PLANT SITE CAPITAL COST ESTIMATE FOR ADVANCED CT
Technology: Advanced CT
Nominal Capacity (ISO): 210,000 kW
Nominal Heat Rate (ISO): 9,750 Btu/kWh-HHV

Capital Cost Category (000s) (October 1, 2010$)

Civil Structural Material and Installation 11,800

Mechanical Equipment Supply and


Installation 58,700

Electrical / I&C Supply and Installation 15,300

Project Indirects (1) 16,460

EPC Cost before Contingency and Fee 102,260

Fee and Contingency 14,196

Total Project EPC 116,456

Owner Costs (excluding project finance) 23,291

Total Project Cost (excluding finance) 139,747

Total Project EPC / kW 554

Owner Costs 20% (excluding project finance) / kW 111

Total Project Cost (excluding project finance) / kW 665

(1) Includes engineering, distributable costs, scaffolding, construction management, and start-up.

The locational considerations for the Advanced CT Facility are the same as those set forth in the
section on the Conventional CT Facility.
Table 9-2 presents the Advanced CT Facility capital cost variations for alternative U.S. plant
locations.

9-2
TABLE 9-2 – LOCATION-BASED COSTS FOR ADVANCED CT
(OCTOBER 1, 2010 DOLLARS)
Base
Project Location Delta Cost Total Location
Cost Percent Difference Project Cost
State City ($/kW) Variation ($/kW) ($/kW)
Alaska Anchorage 665 34.3% 228 893
Alaska Fairbanks 665 5.4% 36 701
Alabama Huntsville 665 -1.4% (9) 656
Arizona Phoenix 665 4.4% 29 694
Arkansas Little Rock 665 -3.4% (23) 642
California Los Angeles 665 5.6% 38 703
California Redding 665 2.5% 17 682
California Bakersfield 665 1.2% 8 673
California Sacramento 665 1.3% 9 674
California San Francisco 665 -0.2% (2) 663
Colorado Denver 665 20.6% 137 802
Connecticut Hartford 665 3.7% 25 690
Delaware Dover 665 61.7% 410 1,075
District of Columbia Washington 665 12.2% 81 746
Florida Tallahassee 665 4.6% 31 696
Florida Tampa 665 -4.6% (31) 634
Georgia Atlanta 665 -1.5% (10) 655
Hawaii Honolulu 665 1.2% 8 673
Idaho Boise 665 4.7% 31 696
Illinois Chicago 665 16.1% 107 772
Indiana Indianapolis 665 1.7% 11 676
Iowa Davenport 665 16.6% 111 776
Iowa Waterloo 665 -5.5% (37) 628
Kansas Wichita 665 -3.0% (20) 645
Kentucky Louisville 665 -4.6% (31) 634
Louisiana New Orleans 665 -5.2% (35) 630
Maine Portland 665 0.0% (0) 665
Maryland Baltimore 665 5.6% 37 702
Massachusetts Boston 665 12.6% 84 749
Michigan Detroit 665 -3.0% (20) 645
Michigan Grand Rapids 665 6.5% 43 708
Minnesota St. Paul 665 -0.6% (4) 661
Mississippi Jackson 665 2.3% 15 680
Missouri St. Louis 665 1.0% 6 671
Missouri Kansas City 665 5.5% 36 701
Montana Great Falls 665 10.3% 68 733
Nebraska Omaha 665 34.3% 228 893
New Hampshire Concord 665 5.4% 36 701
New Jersey Newark 665 -1.4% (9) 656

9-3
Base
Project Location Delta Cost Total Location
Cost Percent Difference Project Cost
State City ($/kW) Variation ($/kW) ($/kW)
New Mexico Albuquerque 665 4.4% 29 694
New York New York 665 -3.4% (23) 642
New York Syracuse 665 5.6% 38 703
Nevada Las Vegas 665 2.5% 17 682
North Carolina Charlotte 665 1.2% 8 673
North Dakota Bismarck 665 1.3% 9 674
Ohio Cincinnati 665 -0.2% (2) 663
Oregon Portland 665 20.6% 137 802
Pennsylvania Philadelphia 665 3.7% 25 690
Pennsylvania Wilkes-Barre 665 61.7% 410 1,075
Rhode Island Providence 665 12.2% 81 746
South Carolina Spartanburg 665 4.6% 31 696
South Dakota Rapid City 665 -4.6% (31) 634
Tennessee Knoxville 665 -1.5% (10) 655
Texas Houston 665 1.2% 8 673
Utah Salt Lake City 665 4.7% 31 696
Vermont Burlington 665 16.1% 107 772
Virginia Alexandria 665 1.7% 11 676
Virginia Lynchburg 665 16.6% 111 776
Washington Seattle 665 -5.5% (37) 628
Washington Spokane 665 -3.0% (20) 645
West Virginia Charleston 665 -4.6% (31) 634
Wisconsin Green Bay 665 -5.2% (35) 630
Wyoming Cheyenne 665 0.0% (0) 665
Puerto Rico Cayey 665 5.6% 37 702

9.5 O&M ESTIMATE


The O&M items for the Advanced CT Facility are the same as those set forth in Section 8.5 for
the Conventional CT Facility. Table 9-3 presents the O&M expenses for the Advanced CT
Facility.
TABLE 9-3 – O&M EXPENSES FOR ADVANCED CT
Technology: Advanced CT
Fixed O&M Expense $6.70/kW-year
Variable O&M Expense $9.87/MWh

9.6 ENVIRONMENTAL COMPLIANCE INFORMATION


The environmental compliance strategy and equipment for the Advanced CT Facility are the
same as those used for the Conventional CT Facility (see Section 8.6). Table 9-4 presents
environmental emissions for the Advanced CT Facility.

9-4
TABLE 9-4 – ENVIRONMENTAL EMISSIONS FOR ADVANCED CT
Technology: Advanced CT
NOX 0.03 lb/MMBtu
SO2 0.001 lb/MMBtu
CO2 117 lb/MMBtu

9-5
10. INTEGRATED GASIFICATION COMBINED CYCLE (IGCC)

10.1MECHANICAL EQUIPMENT AND SYSTEMS


The following describes the IGCC Facility, which is a nominal 600 MW net coal-fired
gasification-to-power facility. An analysis is also provided for a nominally 1,200 MW coal-fired
gasification-to-power facility, which is essentially a dual-unit configuration, based on doubling
the single-unit description provided below; however, a detailed technical description (due to the
similarities/duplication with the single unit) is not provided herein. The feed for the gasification
system is a slurry of water and ground coal and/or petroleum coke. The raw feedstock is ground
in rod mills along with recycled water and slag fines to form the slurry. A fluxing agent is also
added, if necessary, depending on the properties of the feedstock, to facilitate slagging at
appropriate temperatures in the gasifier.
Air separation units (“ASU”) provide a 95 percent-pure oxygen (“O2”) stream for gasification,
and nitrogen for use as a diluent in the CTs, and for purging the gasifiers.
The IGCC Facility is based on two trains of ConocoPhillips (E-Gas�) gasifier, which is a
two-stage, refractory lined vessel that converts the slurry feed into syngas consisting of
hydrogen, CO, CO2, methane, nitrogen, argon and water along with sulfur compounds in the
form of hydrogen sulfide (“H2S”) and carbonyl sulfide (“COS”) and a small amount of NH3.
The first stage is the slagging section in which the feedstock is partially combusted with O2 at
elevated temperature and pressure (2,500 degrees ºF and 540 psia). O2 and preheated slurry are
fed to each of two opposing mixing nozzles at opposite ends of the horizontal section. The
gasification temperature is maintained above the ash fusion point to allow for slag formation and
carbon conversion.
The raw syngas from the first stage flows into the vertical second stage where additional feed
slurry is introduced to take advantage of the sensible heat in the gas. This fuel undergoes
devolatization and pyrolysis generating additional syngas. The endothermic nature of the
reactions and the introduction of a quench fluid reduce the temperature of the gas exiting to the
gasifier to approximately 1,900ºF. At these temperatures (2,500ºF to 1,900ºF), two additional
reactions occur, which change the character of the syngas as follows: (1) carbon-steam to
produce CO; and (2) water gas shift (steam and CO) to produce hydrogen and CO2. In addition,
the lower reaction temperature in the second stage allows the formation of methane. Unreacted
char is carried overhead and exits the reactor with the syngas. This char is recycled to the first
stage of gasification.
The mineral matter in the feedstock and any fluxing agent form a molten slag that flows out of
the horizontal section into water quench bath. The cooled slag exits the bottom of the quench, is
crushed and exits the unit through a continuous slag removal system as a slurry.
The hot raw syngas is cooled in a vertical fire tube boiler from 1,900ºF to 700ºF. The hot gas is
on the tube side with pressurized water on the shell side. This unit generates HP saturated steam.
The saturated steam is sent to the HRSGs in the power block.
After cooling, the syngas is cleaned of entrained particles in a filter vessel containing numerous
candlestick-type filter elements. The particles collect on the filter elements producing an
essentially particulate matter free syngas that proceeds through the system.

10-1
Captured particulate matter is cleaned from the filter elements using cleaned syngas (in a
back-pulse mode) and the carbon-rich material is pneumatically conveyed back to the first stage
of the gasifier for conversion.
Following particulate matter removal, the syngas is scrubbed with water to remove chlorine and
trace metals. The scrubbing medium is condensed sour water from the low-temperature heat
recovery system.
After the chlorine scrubber, the raw syngas is treated in COS hydrolysis units, which convert the
COS in the syngas to H2S. The syngas is then cooled to approximately 100°F in a series of shell
and tube heat exchangers in a step known as low-temperature heat recovery. This cooling
removes most of the water in the syngas. In addition, most of the NH3 and a small portion of
CO2 and H2S are absorbed in the water. A portion of the condensed water is used in the chlorine
scrubber with the remainder sent to sour water treatment. The low temperature heat removed
prior to acid gas removal (“AGR”) is used within the process.
After low-temperature heat recovery, the H2S is then removed in the AGR units. The AGR units
use the Selexol solvent in a single absorption stage to remove much of the sulfur from the
syngas. The syngas passes through a mercury removal system consisting of sulfated activated
carbon beds. Finally, the treated syngas is moisturized and sent to the power block.
The acid gas streams containing H2S and COS with some CO2 from AGR and sour water
treatment are fed to the sulfur recovery units (“SRUs”). The SRUs are based on a standard Claus
process to convert the acid gas to pure molten sulfur. The tail gas from the SRUs, composed of
CO2, nitrogen, and small amounts of sulfur, is catalytically hydrogenated to convert all of the
sulfur to H2S. This converted tail gas is compressed and recycled to the gasifiers.
Process water blowdown and water condensed during cooling of the sour syngas contains small
amounts of dissolved gases (H2S, CO2 and NH3). This water is treated in sour water stripping
units and either recycled to slurry preparation or further treated in a zero-liquid discharge
(“ZLD”) system to recover and reuse water. Solid waste from the ZLD is landfilled.
The power block for the IGCC Facility case is based on a two-on-one combined-cycle
configuration using F-class CTs. The combined cycle is similar to the Conventional NGCC
Facility except the CTs are designed to combust natural gas and/or syngas, and the combustors
are not DLN. Figure 10-1 presents the IGCC process flow diagram.

10-2
FIGURE 10-1 – IGCC DESIGN CONFIGURATION

10.2ELECTRICAL AND CONTROL SYSTEMS


The IGCC Facility has two CT electric generators and one ST electric generator. The generators
for the CTs are 60 Hz machines rated at approximately 255 MVA with an output voltage of
18 kV. The ST electric generator is a 60 Hz machine rated at approximately 333 MVA with an
output voltage of 18 kV. Each CT electric generator is connected to a high-voltage bus in the
IGCC Facility switchyard via a dedicated generator circuit breaker, GSU, and a disconnect
switch. The ST electric generator is connected directly to its GSU and connected through a
disconnect switch between two breakers on the high-voltage bus. The GSUs increase the
voltage from the electric generators from 18 kV to interconnected transmission system high
voltage.
The IGCC Facility is controlled using a DCS. The DCS provides centralized control of the
facility by integrating the control systems provided with each individual CT and associated
electric generator, ST and associated electric generator, and the control of BOP systems and
equipment.

10.3OFF-SITE REQUIREMENTS
Coal is delivered to the IGCC Facility by rail, truck or barge. Water for all processes at the
IGCC is obtained from one of several available water sources; however, water is typically
sourced from an adjacent river, when possible. The IGCC uses a water treatment system and a
high-efficiency reverse osmosis system to reduce the dissolved solids from the cooling water and
to provide distilled water for HRSG makeup. Wastewater is sent to an adjacent river or other
approved wastewater delivery point. Further, the electrical interconnection from the IGCC on-
site switchyard is effectuated by a connection to an adjacent utility substation.

10-3
10.4CAPITAL COST ESTIMATE
The base Cost Estimate for the IGCC Facility with a nominal capacity of 600 MW is $3,565/kW
and with a nominal capacity of 1,200 MW is $3,221/kW. Table 10-1 and Table 10-2 summarize
the Cost Estimate categories for the IGCC Facility.
TABLE 10-1 – BASE PLANT SITE CAPITAL COST ESTIMATE FOR IGCC
Technology: IGCC
Nominal Capacity (ISO): 600,000 kW
Nominal Heat Rate (ISO): 8,700 Btu/kWh-HHV

Capital Cost Category (000s) (October 1, 2010$)

Civil Structural Material and Installation 102,121

Mechanical Equipment Supply and


Installation 975,212

Electrical / I&C Supply and Installation 200,708

Project Indirects (1) 313,558

EPC Cost before Contingency and Fee 1,591,599

Fee and Contingency 190,992

Total Project EPC 1,782,591

Owner Costs (excluding project finance) 356,518

Total Project Cost (excluding finance) 2,139,109

Total Project EPC / kW 2,971

Owner Costs 20% (excluding project finance) / kW 594

Total Project Cost (excluding project finance) / kW 3,565

(1) Includes engineering, distributable costs, scaffolding, construction management, and start-up.

10-4
TABLE 10-2 – BASE PLANT SITE CAPITAL COST ESTIMATE FOR IGCC
Technology: IGCC
Nominal Capacity (ISO): 1,200,000 kW
Nominal Heat Rate (ISO): 8,700 Btu/kWh-HHV

Capital Cost Category (000s) (October 1, 2010$)

Civil Structural Material and Installation 178,606

Mechanical Equipment Supply and


Installation 1,859,974

Electrical / I&C Supply and Installation 364,745

Project Indirects (1) 521,600

EPC Cost before Contingency and Fee 2,924,925

Fee and Contingency 350,991

Total Project EPC 3,275,916

Owner Costs (excluding project finance) 589,665

Total Project Cost (excluding finance) 3,865,581

Total Project EPC / kW 2730

Owner Costs 18% (excluding project finance) / kW 491

Total Project Cost (excluding project finance) / kW 3,221

(1) Includes engineering, distributable costs, scaffolding, construction management, and start-up.

For this type of technology and power plant configuration, our regional adjustments took into
consideration the following: outdoor installation considerations, seismic design differences,
remote location issues, labor wage and productivity differences, location adjustments, owner cost
differences, and the increase in overheads associated with these six adjustments.

Outdoor installation locations are considered in geographic areas where enclosed structures for
the boilers would not be required due to the low probability of freezing. The locations that
included outdoor installation are Alabama, Arizona, Arkansas, Florida, Georgia, Hawaii,
Louisiana, Mississippi, New Mexico, South Carolina, and Puerto Rico.
Seismic design differences among the various locations were based on U.S. seismic map
information that detailed the various seismic zones throughout the U.S. No cost increases were
associated with seismic Zone 0 and cost step increases were considered for Zones 1, 2, 3 and 4.

10-5
Remote locations issues are related to geographic areas that typically require installation of man
camps, higher craft incentives, and higher per diems for construction, because such areas are
long distances from urban areas, where labor is generally abundant. Remote location
designations were also considered in locations where higher equipment freight costs are typically
incurred, which for example are regions not near established rail or highway access. Remote
locations related to the IGCC Facility include Fairbanks, Alaska; Honolulu, Hawaii;
Albuquerque, New Mexico; Cheyenne, Wyoming; and Cayey, Puerto Rico.
Labor wage and productivity differences were handled as discussed in Section 2.5.1, taking into
consideration the amount of labor we estimated for the IGCC Facility.
Location adjustments were made to locations where higher cost of living levels are incurred
and/or where population density generally correlates to higher construction costs for power and
other infrastructure projects. These locations include Alaska, California, Connecticut, Delaware,
District of Columbia, Hawaii, Illinois, Maine, Maryland, Massachusetts, Michigan, Minnesota,
New York, Ohio, and Wisconsin.
Owner costs were reviewed based on the need for utility upgrades and/or infrastructure costs
such as new facility transmission lines to tie to existing utility transmission substations or
existing transmission lines.
Table 10-3 and Table 10-4 present the IGCC Facility capital cost variations for alternative U.S.
plant locations.

10-6
TABLE 10-3 – LOCATION-BASED COSTS FOR IGCC (600,000 KW)
(OCTOBER 1, 2010 DOLLARS)
Base
Project Location Delta Cost Total Location
Cost Percent Difference Project Cost
State City ($/kW) Variation ($/kW) ($/kW)
Alaska Anchorage 3,565 29.4% 1,049 4,614
Alaska Fairbanks 3,565 28.5% 1,016 4,581
Alabama Huntsville 3,565 -6.5% (232) 3,333
Arizona Phoenix 3,565 -4.5% (160) 3,405
Arkansas Little Rock 3,565 -4.7% (167) 3,398
California Los Angeles 3,565 18.1% 645 4,210
California Redding 3,565 8.7% 312 3,877
California Bakersfield 3,565 8.4% 299 3,864
California Sacramento 3,565 12.8% 455 4,020
California San Francisco 3,565 37.6% 1,342 4,907
Colorado Denver 3,565 -5.2% (187) 3,378
Connecticut Hartford 3,565 23.7% 846 4,411
Delaware Dover 3,565 20.6% 734 4,299
District of Columbia Washington 3,565 35.6% 1,269 4,834
Florida Tallahassee 3,565 -9.5% (339) 3,226
Florida Tampa 3,565 -4.3% (152) 3,413
Georgia Atlanta 3,565 -7.1% (252) 3,313
Hawaii Honolulu 0 0
Idaho Boise 3,565 -3.2% (113) 3,452
Illinois Chicago 3,565 17.4% 619 4,184
Indiana Indianapolis 3,565 2.9% 103 3,668
Iowa Davenport 3,565 -1.4% (48) 3,517
Iowa Waterloo 3,565 -7.8% (279) 3,286
Kansas Wichita 3,565 -5.8% (208) 3,357
Kentucky Louisville 3,565 -4.8% (172) 3,393
Louisiana New Orleans 3,565 -9.8% (348) 3,217
Maine Portland 3,565 -0.4% (14) 3,551
Maryland Baltimore 3,565 4.3% 153 3,718
Massachusetts Boston 3,565 31.3% 1,115 4,680
Michigan Detroit 3,565 3.4% 120 3,685
Michigan Grand Rapids 3,565 -6.8% (243) 3,322
Minnesota St. Paul 3,565 3.4% 123 3,688
Mississippi Jackson 3,565 -6.5% (230) 3,335
Missouri St. Louis 3,565 6.4% 227 3,792
Missouri Kansas City 3,565 3.0% 107 3,672
Montana Great Falls 3,565 -3.7% (131) 3,434
Nebraska Omaha 3,565 -3.0% (108) 3,457
New Hampshire Concord 3,565 -1.4% (49) 3,516
New Jersey Newark 3,565 13.5% 480 4,045

10-7
Base
Project Location Delta Cost Total Location
Cost Percent Difference Project Cost
State City ($/kW) Variation ($/kW) ($/kW)
New Mexico Albuquerque 3,565 -3.4% (120) 3,445
New York New York 3,565 28.4% 1,013 4,578
New York Syracuse 3,565 9.7% 345 3,910
Nevada Las Vegas 3,565 8.1% 290 3,855
North Carolina Charlotte 3,565 -8.3% (296) 3,269
North Dakota Bismarck 3,565 -6.9% (247) 3,318
Ohio Cincinnati 3,565 0.4% 16 3,581
Oregon Portland 3,565 8.5% 303 3,868
Pennsylvania Philadelphia 3,565 10.6% 377 3,942
Pennsylvania Wilkes-Barre 3,565 -3.0% (107) 3,458
Rhode Island Providence 3,565 3.6% 129 3,694
South Carolina Spartanburg 3,565 -10.2% (364) 3,201
South Dakota Rapid City 3,565 -9.3% (331) 3,234
Tennessee Knoxville 3,565 -7.7% (276) 3,289
Texas Houston 3,565 -8.3% (294) 3,271
Utah Salt Lake City 3,565 -2.6% (91) 3,474
Vermont Burlington 3,565 -4.6% (162) 3,403
Virginia Alexandria 3,565 8.8% 313 3,878
Virginia Lynchburg 3,565 -1.6% (56) 3,509
Washington Seattle 3,565 11.3% 404 3,969
Washington Spokane 3,565 -2.0% (70) 3,495
West Virginia Charleston 3,565 -1.5% (55) 3,510
Wisconsin Green Bay 3,565 0.5% 19 3,584
Wyoming Cheyenne 3,565 3.7% 132 3,697
Puerto Rico Cayey 0 0 0

10-8
TABLE 10-4 – LOCATION-BASED COSTS FOR IGCC (1,200,000 KW)
(OCTOBER 1, 2010 DOLLARS)
Base
Project Location Delta Cost Total Location
Cost Percent Difference Project Cost
State City ($/kW) Variation ($/kW) ($/kW)
Alaska Anchorage 3,221 32.0% 1,031 4,252
Alaska Fairbanks 3,221 30.9% 996 4,217
Alabama Huntsville 3,221 -6.7% (216) 3,005
Arizona Phoenix 3,221 -4.6% (147) 3,074
Arkansas Little Rock 3,221 -4.8% (154) 3,067
California Los Angeles 3,221 19.8% 637 3,858
California Redding 3,221 9.6% 308 3,529
California Bakersfield 3,221 9.2% 296 3,517
California Sacramento 3,221 13.7% 442 3,663
California San Francisco 3,221 40.8% 1,313 4,534
Colorado Denver 3,221 -5.4% (173) 3,048
Connecticut Hartford 3,221 26.0% 836 4,057
Delaware Dover 3,221 22.7% 730 3,951
District of Columbia Washington 3,221 39.5% 1,272 4,493
Florida Tallahassee 3,221 -9.9% (318) 2,903
Florida Tampa 3,221 -4.4% (143) 3,078
Georgia Atlanta 3,221 -7.3% (235) 2,986
Hawaii Honolulu - -
Idaho Boise 3,221 -3.2% (102) 3,119
Illinois Chicago 3,221 18.2% 586 3,807
Indiana Indianapolis 3,221 3.3% 107 3,328
Iowa Davenport 3,221 -1.4% (45) 3,176
Iowa Waterloo 3,221 -8.1% (261) 2,960
Kansas Wichita 3,221 -6.0% (192) 3,029
Kentucky Louisville 3,221 -4.9% (158) 3,063
Louisiana New Orleans 3,221 -10.1% (326) 2,895
Maine Portland 3,221 0.0% (1) 3,220
Maryland Baltimore 3,221 5.0% 162 3,383
Massachusetts Boston 3,221 33.8% 1,087 4,308
Michigan Detroit 3,221 3.5% 114 3,335
Michigan Grand Rapids 3,221 -7.1% (227) 2,994
Minnesota St. Paul 3,221 3.6% 117 3,338
Mississippi Jackson 3,221 -6.6% (214) 3,007
Missouri St. Louis 3,221 6.9% 221 3,442
Missouri Kansas City 3,221 3.2% 103 3,324
Montana Great Falls 3,221 -3.7% (119) 3,102
Nebraska Omaha 3,221 -3.1% (99) 3,122
New Hampshire Concord 3,221 -1.3% (42) 3,179
New Jersey Newark 3,221 14.0% 449 3,670

10-9
Base
Project Location Delta Cost Total Location
Cost Percent Difference Project Cost
State City ($/kW) Variation ($/kW) ($/kW)
New Mexico Albuquerque 3,221 -3.4% (109) 3,112
New York New York 3,221 29.5% 949 4,170
New York Syracuse 3,221 10.8% 349 3,570
Nevada Las Vegas 3,221 8.6% 278 3,499
North Carolina Charlotte 3,221 -8.5% (273) 2,948
North Dakota Bismarck 3,221 -7.2% (230) 2,991
Ohio Cincinnati 3,221 0.8% 25 3,246
Oregon Portland 3,221 9.3% 300 3,521
Pennsylvania Philadelphia 3,221 11.0% 355 3,576
Pennsylvania Wilkes-Barre 3,221 -3.0% (96) 3,125
Rhode Island Providence 3,221 3.9% 124 3,345
South Carolina Spartanburg 3,221 -10.5% (337) 2,884
South Dakota Rapid City 3,221 -9.6% (309) 2,912
Tennessee Knoxville 3,221 -7.9% (256) 2,965
Texas Houston 3,221 -8.5% (275) 2,946
Utah Salt Lake City 3,221 -2.4% (76) 3,145
Vermont Burlington 3,221 -4.6% (148) 3,073
Virginia Alexandria 3,221 9.9% 320 3,541
Virginia Lynchburg 3,221 -1.3% (41) 3,180
Washington Seattle 3,221 12.3% 395 3,616
Washington Spokane 3,221 -1.9% (62) 3,159
West Virginia Charleston 3,221 -1.5% (49) 3,172
Wisconsin Green Bay 3,221 0.8% 27 3,248
Wyoming Cheyenne 3,221 4.6% 148 3,369
Puerto Rico Cayey 0 0 0 0

10.5O&M ESTIMATE
In addition to the general O&M items discussed in Section 2.5.2, IGCC Facility includes the
major maintenance for the CTs, as well as the BOP, including the ST, associated electric
generators, HRSGs, and emissions reduction catalysts. Additionally, provisions need to be made
for routine and major maintenance for the gasification systems, the ASU, and associated
gasification auxiliary equipment needs to be made. For example, major maintenance for the
gasifier includes repair and replacement of the refractory. Typically, significant overhauls on an
IGCC Facility occur no less frequently than 18 months and the cycle for the power generation
equipment is similar to the to the Advanced NGCC discussed above. Table 10-5 and Table 10-6
present the O&M expenses for the IGCC Facility.
TABLE 10-5 – O&M EXPENSES FOR IGCC (600,000 KW)
Technology: IGCC
Fixed O&M Expense $59.23/kW-year
Variable O&M Expense $6.87/MWh

10-10
TABLE 10-6 – O&M EXPENSES FOR IGCC (1,200,000 KW)
Technology: IGCC
Fixed O&M Expense $48.90/kW-year
Variable O&M Expense $6.87/MWh

10.6ENVIRONMENTAL COMPLIANCE INFORMATION


The IGCC uses syngas combustors (which do not have DLN) in the CT and best available burner
technology with respect to the duct burners in the HRSGs to manage the production of NOX and
CO. Additional control of NOX and CO is accomplished through an SCR and an oxidization
catalyst, respectively. SO2 in the IGCC is managed through the removal of sulfur in the syngas
via the AGR system prior to combustion. The IGCC does not include any control devices for
CO2, which is proportional to the heat rate (inversely proportional to the efficiency) of the
technology. Water, wastewater, and solid waste compliance are achieved through traditional
on-site and off-site methods, and the costs for such compliance are included in the O&M
Estimate for the IGCC. Table 10-7 presents environmental emissions for the IGCC Facility.
TABLE 10-7 – ENVIRONMENTAL EMISSIONS FOR IGCC
Technology: IGCC
NOX 0.0075 lb/MMBtu
SO2 0.025 lb/MMBtu
CO2 206 lb/MMBtu

10-11
11. INTEGRATED GASIFICATION COMBINED CYCLE WITH CCS (IGCC/CCS)

11.1MECHANICAL EQUIPMENT AND SYSTEMS


The plant configuration for the IGCC/CCS Facility case is the same as the IGCC Facility case
with the exceptions that: (1) a water gas shift reactor system is substituted instead of the COS
hydrolysis system upstream of the AGR; and (2) a two-stage Selexol AGR system is utilized
instead of a single stage to allow the capture of CO2 from the syngas prior to combustion. The
captured CO2 is compressed to approximately 2,000 psia for injection into a pipeline at the plant
fence line. The IGCC/CCS Facility produces 690 MW of gross power and 520 MW of net
power. Figure 11-1 presents the IGCC/CCS process flow diagram.
FIGURE 11-1 – IGCC/CCS DESIGN CONFIGURATION

11.2ELECTRICAL AND CONTROL SYSTEMS


The electrical and control systems for the IGCC/CCS Facility are materially similar to the IGCC
Facility (without CCS) discussed in Section 10.2.

11.3OFF-SITE REQUIREMENTS
The off-site requirements for the IGCC/CCS Facility are materially similar to the IGCC Facility
(without CCS) discussed in Section 10.3, except that an interconnection needs to be made with
respect to the sequestration of CO2.

11.4CAPITAL COST ESTIMATE


The base Cost Estimate for the IGCC/CCS Facility with a nominal capacity of 520 MW is
$5,348/kW. Table 11-1 summarizes the Cost Estimate categories for the IGCC/CCS Facility.

11-1
TABLE 11-1 – BASE PLANT SITE CAPITAL COST ESTIMATE FOR IGCC/CCS
Technology: IGCC/CCS
Nominal Capacity (ISO): 520,000 kW
Nominal Heat Rate (ISO): 10,700 Btu/kWh-HHV

Capital Cost Category (000s) (October 1, 2010$)

Total Project EPC 2,317,500

Owner Costs (excluding project finance) 463,500

Total Project Cost (excluding finance) 2,781,000

Total Project EPC / kW 4,458

Owner Costs 20% (excluding project finance) / kW 892

Total Project Cost (excluding project finance) / kW 5,348

(1) Includes engineering, distributable costs, scaffolding, construction management, and start-up.

The locational considerations for the IGCC/CCS Facility are the same as those set forth in
Section 10.4 for the IGCC Facility.
Table 11-2 presents the IGCC/CCS Facility capital cost variations for alternative U.S. plant
locations.

11-2
TABLE 11-2 – LOCATION-BASED COSTS FOR IGCC/CCS
(OCTOBER 1, 2010 DOLLARS)
Base
Project Location Delta Cost Total Location
Cost Percent Difference Project Cost
State City ($/kW) Variation ($/kW) ($/kW)
Alaska Anchorage 5,350 23.1% 1,236 6,586
Alaska Fairbanks 5,350 22.9% 1,225 6,575
Alabama Huntsville 5,350 -7.4% (397) 4,953
Arizona Phoenix 5,350 -5.5% (293) 5,057
Arkansas Little Rock 5,350 -5.7% (306) 5,044
California Los Angeles 5,350 13.7% 732 6,082
California Redding 5,350 6.5% 348 5,698
California Bakersfield 5,350 6.1% 326 5,676
California Sacramento 5,350 11.1% 591 5,941
California San Francisco 5,350 30.7% 1,642 6,992
Colorado Denver 5,350 -6.3% (335) 5,015
Connecticut Hartford 5,350 17.7% 946 6,296
Delaware Dover 5,350 14.5% 774 6,124
District of Columbia Washington 5,350 23.0% 1,229 6,579
Florida Tallahassee 5,350 -10.5% (561) 4,789
Florida Tampa 5,350 -4.5% (243) 5,107
Georgia Atlanta 5,350 -8.1% (432) 4,918
Hawaii Honolulu 0 0 0 0
Idaho Boise 5,350 -4.2% (227) 5,123
Illinois Chicago 5,350 17.9% 959 6,309
Indiana Indianapolis 5,350 1.2% 67 5,417
Iowa Davenport 5,350 -1.5% (82) 5,268
Iowa Waterloo 5,350 -8.9% (474) 4,876
Kansas Wichita 5,350 -6.9% (370) 4,980
Kentucky Louisville 5,350 -5.8% (309) 5,041
Louisiana New Orleans 5,350 -10.8% (577) 4,773
Maine Portland 5,350 -2.8% (151) 5,199
Maryland Baltimore 5,350 1.1% 60 5,410
Massachusetts Boston 5,350 26.2% 1,402 6,752
Michigan Detroit 5,350 3.5% 185 5,535
Michigan Grand Rapids 5,350 -7.7% (413) 4,937
Minnesota St. Paul 5,350 3.4% 181 5,531
Mississippi Jackson 5,350 -7.4% (394) 4,956
Missouri St. Louis 5,350 5.5% 295 5,645
Missouri Kansas City 5,350 2.7% 145 5,495
Montana Great Falls 5,350 -4.8% (259) 5,091
Nebraska Omaha 5,350 -3.8% (201) 5,149
New Hampshire Concord 5,350 -2.2% (119) 5,231
New Jersey Newark 5,350 14.9% 795 6,145

11-3
Base
Project Location Delta Cost Total Location
Cost Percent Difference Project Cost
State City ($/kW) Variation ($/kW) ($/kW)
New Mexico Albuquerque 5,350 -4.4% (235) 5,115
New York New York 5,350 31.4% 1,681 7,031
New York Syracuse 5,350 5.5% 295 5,645
Nevada Las Vegas 5,350 7.7% 410 5,760
North Carolina Charlotte 5,350 -10.1% (538) 4,812
North Dakota Bismarck 5,350 -7.8% (419) 4,931
Ohio Cincinnati 5,350 -1.5% (82) 5,268
Oregon Portland 5,350 6.2% 333 5,683
Pennsylvania Philadelphia 5,350 11.3% 602 5,952
Pennsylvania Wilkes-Barre 5,350 -4.1% (217) 5,133
Rhode Island Providence 5,350 3.4% 183 5,533
South Carolina Spartanburg 5,350 -12.0% (640) 4,710
South Dakota Rapid City 5,350 -10.5% (562) 4,788
Tennessee Knoxville 5,350 -9.1% (486) 4,864
Texas Houston 5,350 -9.3% (499) 4,851
Utah Salt Lake City 5,350 -4.6% (245) 5,105
Vermont Burlington 5,350 -5.8% (311) 5,039
Virginia Alexandria 5,350 4.5% 241 5,591
Virginia Lynchburg 5,350 -3.8% (203) 5,147
Washington Seattle 5,350 9.4% 505 5,855
Washington Spokane 5,350 -2.9% (154) 5,196
West Virginia Charleston 5,350 -2.1% (111) 5,239
Wisconsin Green Bay 5,350 -1.1% (58) 5,292
Wyoming Cheyenne 5,350 -0.5% (29) 5,321
Puerto Rico Cayey 0 0 0 0

11.5O&M ESTIMATE
The O&M methodology for the IGCC/CCS Facility is the same as that set forth in the section on
the IGCC Facility, except that consideration needs to be made for the additional maintenance
resulting from the CCS equipment.
Table 11-3 presents the O&M expenses for the IGCC/CCS Facility.
TABLE 11-3 – O&M EXPENSES FOR IGCC/CCS
Technology: IGCC/CCS
Fixed O&M Expense $69.30/kW-year
Variable O&M Expense $8.04/MWh

11.6ENVIRONMENTAL COMPLIANCE INFORMATION


The environmental compliance strategy for the IGCC/CCS Facility is the same as that set forth in
the section on the IGCC Facility, except for CCS including a two-stage Selexol AGR for capture
of CO2. Table 11-4 presents environmental emissions for the IGCC/CCS Facility.

11-4
TABLE 11-4 – ENVIRONMENTAL EMISSIONS FOR IGCC/CCS
Technology: IGCC/CCS
NOX 0.0075 lb/MMBtu
SO2 0.015 lb/MMBtu
CO2 20.6 lb/MMBtu

11-5
12. ADVANCED NUCLEAR (AN)

12.1MECHANICAL EQUIPMENT AND SYSTEMS


The Advanced Nuclear (“AN”) Facility consists of two 1,117 MW Westinghouse AP1000
nuclear power units built in a brownfield (existing nuclear facility site).
The steam cycle of a nuclear powered electric generation facility is similar to other
steam-powered generating facilities. The difference is with the source of heat used to generate
steam. In units that use fossil fuels, hydrocarbons are burned to heat water, producing steam. In
the AP1000, splitting the nucleus (fission) of uranium atoms provides the energy to heat the
water.
Nuclear fuel is a uranium dioxide ceramic pellet encased in a zirconium alloy tube. The uranium
atoms in the pellet absorb neutrons and split, or fission. When the uranium atom splits, a large
amount of energy, as well as additional neutrons and fission fragments are released. The
neutrons can be absorbed by other uranium atoms which fission, producing more neutrons. The
chain reaction is controlled by controlling the number of neutrons available for fission. The
number of neutrons available is controlled by the water in the nuclear reactor core, the
arrangement of neutron absorbing control rods inserted into the core, the design of the core, and
by controlling the void fraction and temperature of the coolant water (which both affect the
density of water which affects the neutrons available for the fission process).
The uranium fuel is contained inside a pressurized water reactor (“PWR”). The AP1000 is a
two-loop PWR. The fission of the uranium fuel releases heat to the surrounding water (reactor
cooling water), which under pressure does not boil, but through a heat exchanger (typically
referred to as a steam generator) results in a lower pressure water (that in the “secondary loop”)
to boil.
The cooling water inside the PWR is circulated through the nuclear core by internal pumps. This
cooling water system is termed the Reactor Coolant System (“RCS”). The RCS consists of two
heat transfer circuits, with each circuit containing one Delta-125 steam generator, two reactor
coolant pumps, and a single hot leg and two cold legs for circulating coolant between the reactor
and the steam generators. The system also includes a pressurizer, interconnecting piping, and the
valves and instrumentation necessary for operational control and the actuation of safeguards.
Each AP1000 unit has a 130-foot diameter freestanding containment vessel with four ring
sections and an upper and lower head.
The passive core cooling system provides protection for the facility against RCS leaks and
ruptures. The passive containment cooling system is the ultimate safety-related ultimate heat
sink for the facility. The passive containment cooling system cools the containment following an
accident to rapidly reduce the pressure via the natural circulation of air supplemented by water
evaporation to transfer heat through the steel containment vessel.
Main steam from the steam generator is routed to the HP section of the ST. The ST consists of a
double-flow HP ST section and three double-flow LP ST sections in a tandem-compound
configuration. As the steam exits the HP section it passes through a moisture separator and
reheater. The moisture separator and reheater dries and reheats the steam before it enters the LP
ST section, which improves the cycle efficiency and reduces moisture related erosion of the LP
ST blades. A portion of the steam is extracted from the HP and LP sections of the ST and with

12-1
ST exhaust heats the condensate and feedwater before it is sent back to the reactor. The HP and
LP STs are connected via a common shaft that drives the generator which produces the electrical
power output of approximately 1,100 MW per unit.
The steam that exits the LP section of the ST, as well as the drains from the feedwater heaters,
are directed to the condenser. The condenser is a surface condensing (tube type) heat exchanger
that is maintained under vacuum to increase the turbine efficiency. The steam condenses on the
outside of the tubes and condenser cooling water is circulated through the inside of the tubes.
Numerous other systems are needed to support and provide redundancy for the cycle process
described herein. These include the residual heat removal system, the HP core flooder system,
and the LP core flooder system which are redundant systems and are designed to remove heat
from the reactor core in the event the normal core cooling system fails. Other support systems
include the liquid and solid radioactive waste systems which handle, control, and process
radioactive waste from the plant. The reactor containment ventilation system controls and filters
airborne radiation. Figure 12-1 presents a simplified process flow diagram for a PWR AN plant.
FIGURE 12-1 – AN DESIGN CONFIGURATION

12.2ELECTRICAL AND CONTROL SYSTEMS


The AN Facility has one ST electric generator for each reactor. Each generator is a 60 Hz
machine rated at approximately 1,250 MVA with an output voltage of 24 kV. The ST electric
generator is connected through a generator circuit breaker to a GSU that is in turn connected
between two circuit breakers in the high-voltage bus in the facility switchyard through a
disconnect switch. The GSU increases the voltage from the electric generator from 24 kV to
interconnected transmission system high voltage.

12-2
The AN Facility is controlled using a DCS. The DCS provides centralized control of the facility
by integrating the control systems provided with the reactor, ST and associated electric generator
and the control of BOP systems and equipment.

12.3OFF-SITE REQUIREMENTS
Water for all processes at the AN Facility is obtained from one of several available water supply
options; however, water is typically sourced from an adjacent river, when possible. The
AN Facility uses a water treatment system and a high-efficiency reverse osmosis system to
reduce the dissolved solids from the cooling water and to provide distilled water. Wastewater is
sent to an adjacent river or other approved wastewater delivery point. Further, the electrical
interconnection from the AN on-site switchyard is effectuated by a connection to an adjacent
utility substation.

12.4CAPITAL COST ESTIMATE


The base Cost Estimate for the AN Facility with a nominal capacity of 2,236 MW is $5,339/kW.
Table 12-1 summarizes the Cost Estimate categories for the AN Facility.

12-3
TABLE 12-1 – BASE PLANT SITE CAPITAL COST ESTIMATE FOR AN
Technology: AN
Nominal Capacity (ISO): 2,236,000 kW
Nominal Heat Rate (ISO): N/A Btu/kWh-HHV

Capital Cost Category (000s) (October 1, 2010$)

Civil Structural Material and Installation 1,732,000

Mechanical Equipment Supply and


Installation 3,400,000

Electrical / I&C Supply and Installation 630,000

Project Indirects (1) 2,722,500

EPC Cost before Contingency and Fee 8,484,500

Fee and Contingency 1,300,000

Total Project EPC 9,784,500

Owner Costs (excluding project finance) 2,152,590

Total Project Cost (excluding finance) 11,937,090

Total Project EPC / kW 4,376

Owner Costs 22% (excluding project finance) / kW 963

Total Project Cost (excluding project finance) / kW 5,339


(1) Includes engineering, distributable costs, scaffolding, construction management, and start-up.

For this type of technology and power plant configuration, our regional adjustments took into
consideration the following: seismic design differences, remote location issues, labor wage and
productivity differences, location adjustments, owner cost differences, and the increase in
overheads associated with these five adjustments.
Seismic design differences among the various locations were based on U.S. seismic map
information that detailed the various seismic zones throughout the U.S. No cost increases were
associated with seismic Zone 0 and cost step increases were considered for Zones 1, 2, 3 and 4.
Remote location issues are related to geographic areas that typically require installation of man
camps, higher craft incentives, and higher per diems are generally required with respect to
construction, due to the fact that such areas are long distances from urban areas, where labor is
generally abundant. Remote location designations were also considered in locations where
higher equipment freight costs are typically incurred, which for example are regions not near
established rail or highway access. Remote locations related to the Advanced Nuclear Facility

12-4
include Fairbanks, Alaska; Honolulu, Hawaii; Albuquerque, New Mexico; Cheyenne, Wyoming;
and Cayey, Puerto Rico.
Labor wage and productivity differences were handled as discussed in Section 2.5.1, taking into
consideration the amount of labor we estimated for the AN Facility.
Location adjustments were made to locations where higher cost of living levels are incurred
and/or where population density generally correlates to higher construction costs for power and
other infrastructure projects. These locations include Alaska, California, Connecticut, Delaware,
District of Columbia, Hawaii, Illinois, Maine, Maryland, Massachusetts, Michigan, Minnesota,
New York, Ohio, and Wisconsin.
Owner costs were reviewed based on the need for utility upgrades and/or infrastructure costs
such as new facility transmission lines to tie to existing utility transmission substations or
existing transmission lines.
Table 12-2 presents the AN Facility capital cost variations for alternative U.S. plant locations.
TABLE 12-2 – LOCATION-BASED COSTS FOR AN
(OCTOBER 1, 2010 DOLLARS)
Base
Project Location Delta Cost Total Location
Cost Percent Difference Project Cost
State City ($/kW) Variation ($/kW) ($/kW)
Alaska Anchorage 5,340 16.3% 868 6,208
Alaska Fairbanks 5,340 16.4% 878 6,218
Alabama Huntsville 5,340 -3.3% (174) 5,166
Arizona Phoenix 5,340 -2.4% (126) 5,214
Arkansas Little Rock 5,340 -2.5% (131) 5,209
California Los Angeles 5,340 9.5% 505 5,845
California Redding 5,340 4.6% 245 5,585
California Bakersfield 5,340 4.4% 236 5,576
California Sacramento 5,340 6.5% 348 5,688
California San Francisco 5,340 20.9% 1,114 6,454
Colorado Denver 5,340 -2.6% (136) 5,204
Connecticut Hartford 5,340 14.7% 784 6,124
Delaware Dover 5,340 13.2% 707 6,047
District of Columbia Washington 5,340 23.9% 1,275 6,615
Florida Tallahassee 5,340 -4.6% (248) 5,092
Florida Tampa 5,340 -2.1% (114) 5,226
Georgia Atlanta 5,340 -3.5% (189) 5,151
Hawaii Honolulu 0 0 0 0
Idaho Boise 5,340 -1.6% (86) 5,254
Illinois Chicago 5,340 9.0% 479 5,819
Indiana Indianapolis 5,340 2.0% 108 5,448
Iowa Davenport 5,340 -0.6% (35) 5,305
Iowa Waterloo 5,340 -3.7% (200) 5,140
Kansas Wichita 5,340 -2.8% (151) 5,189
Kentucky Louisville 5,340 -2.4% (126) 5,214

12-5
Base
Project Location Delta Cost Total Location
Cost Percent Difference Project Cost
State City ($/kW) Variation ($/kW) ($/kW)
Louisiana New Orleans 5,340 -4.8% (254) 5,086
Maine Portland 5,340 0.4% 21 5,361
Maryland Baltimore 5,340 3.4% 180 5,520
Massachusetts Boston 5,340 18.3% 976 6,316
Michigan Detroit 5,340 1.6% 83 5,423
Michigan Grand Rapids 5,340 -3.3% (174) 5,166
Minnesota St. Paul 5,340 1.9% 99 5,439
Mississippi Jackson 5,340 -3.2% (173) 5,167
Missouri St. Louis 5,340 2.8% 148 5,488
Missouri Kansas City 5,340 1.3% 70 5,410
Montana Great Falls 5,340 -1.9% (100) 5,240
Nebraska Omaha 5,340 -1.5% (80) 5,260
New Hampshire Concord 5,340 -0.8% (41) 5,299
New Jersey Newark 5,340 6.4% 340 5,680
New Mexico Albuquerque 5,340 -1.6% (83) 5,257
New York New York 5,340 13.4% 718 6,058
New York Syracuse 5,340 6.6% 355 5,695
Nevada Las Vegas 5,340 4.1% 220 5,560
North Carolina Charlotte 5,340 -4.1% (218) 5,122
North Dakota Bismarck 5,340 -3.3% (176) 5,164
Ohio Cincinnati 5,340 0.8% 45 5,385
Oregon Portland 5,340 4.5% 239 5,579
Pennsylvania Philadelphia 5,340 4.9% 263 5,603
Pennsylvania Wilkes-Barre 5,340 -1.5% (82) 5,258
Rhode Island Providence 5,340 1.6% 87 5,427
South Carolina Spartanburg 5,340 -5.1% (272) 5,068
South Dakota Rapid City 5,340 -4.4% (237) 5,103
Tennessee Knoxville 5,340 -3.7% (200) 5,140
Texas Houston 5,340 -3.9% (210) 5,130
Utah Salt Lake City 5,340 -1.5% (80) 5,260
Vermont Burlington 5,340 -2.3% (122) 5,218
Virginia Alexandria 5,340 6.2% 332 5,672
Virginia Lynchburg 5,340 -0.1% (6) 5,334
Washington Seattle 5,340 5.8% 311 5,651
Washington Spokane 5,340 -1.0% (56) 5,284
West Virginia Charleston 5,340 -0.8% (42) 5,298
Wisconsin Green Bay 5,340 1.0% 51 5,391
Wyoming Cheyenne 5,340 3.5% 188 5,528
Puerto Rico Cayey 0 0 0 0

12-6
12.5O&M ESTIMATE
In addition to the general items discussed in the section of this report entitled O&M Estimate, the
AN Facility includes provisions for major maintenance on the steam generators, STs, electric
generators, BOP systems, and the reactor (beyond refueling). Table 12-3 presents the O&M
expenses for the AN Facility.
TABLE 12-3 – O&M EXPENSES FOR AN
Technology: AN
Fixed O&M Expense $88.75/kW-year
Variable O&M Expense $2.04/MWh

12.6ENVIRONMENTAL COMPLIANCE INFORMATION


Environmental compliance with respect to air emissions is effectively not necessary for the AN
Facility, as this technology does not combust a fuel as is the case for other non-renewable power
technologies. While there are environmental compliance considerations for a given nuclear
facility (e.g., spent nuclear fuel), only air emissions were considered in this report. Table 12-4
presents environmental emissions for the AN Facility.
TABLE 12-4 – ENVIRONMENTAL EMISSIONS FOR AN
Technology: AN
NOX 0 lb/MMBtu
SO2 0 lb/MMBtu
CO2 0 lb/MMBtu

12-7
13. BIOMASS COMBINED CYCLE (BCC)

13.1MECHANICAL EQUIPMENT AND SYSTEMS


The Biomass Combined-Cycle (“BCC”) Facility utilizes approximately 500 tons per day of
wood (at 25 percent moisture), or 370 dry tons per day for the production of 20 MW net of
electricity. The facility consists of a biomass gasification system for the conversion of the wood
to syngas, a clean-up system for the syngas, and a combined-cycle plant using the syngas as fuel.
The gasification system consists of dual circulating fluid bed (“CFB”) units (one gasifier and one
combustor) connected by a sand circulation system. Related equipment includes the wood feed
system, the product gas quench, ash handling, steam supply and typical BOP equipment.
The wood is fed to the circulating fluid bed gasifier through a standard system of lock hoppers,
live bottom bins and feed screws. The lock hoppers are purged with nitrogen to keep the
produced fuel gas from escaping.
The gasifier is a refractory-lined vessel with a sand-type carrier and requires a LP steam source.
The primary purpose of the steam is to maintain a reducing environment in the gasifier to enable
pure gasification and not partial oxidation conditions. The gasification CFB is essentially an
entrained flow reactor, which operates between 1,400�F and 1,500�F. The two products of the
gasifier are a medium-heating value gas (approximately 450 Btu/scf dry) and non-converted
char. A small amount of condensable “tars” are also produced. The gases are directed to a
clean-up system to remove the entrained tars.
The CFB combustor unit burns the char produced in the gasifier. The char combustor operates at
approximately 1,800�F. The flue gas from the char combustor goes to a boiler to recover the
excess sensible energy.
The two CFBs are connected by the sand circulation system. The purpose of this system is to
transfer the char and circulating sand from the gasifier to the combustor, where the char is
burned to reheat the sand. This hotter sand is then returned to the gasifier to provide the energy
to convert the solid wood to a gas. The sand transfer system consists of mechanical cyclones
(two in series for each CFB) and a sand inventory pot for each leg of the configuration. An
overflow system, with some fluidizing steam in the pot, is used to regulate the flow from the
gasifier to the combustor.
The syngas clean-up system consists of a reformer to convert the tars and other hydrocarbons to
CO and hydrogen in an isothermal fluidized bed reactor. The hot syngas is cooled by producing
steam to be used in the combined cycle. A wet scrubber removes particulates, NH3 and residual
tars. The excess scrubber water is sent off-site to a wastewater treatment facility.
The syngas is then compressed to the required pressure for use in the CT. The BCC Facility is
based on a single CT, which produces approximately 15 MW of electricity. The CT exhaust is
sent to an HRSG. The HRSG is equipped with an SCR to reduce NOX emissions. Both the
steam generated in the HRSG and the steam generated the cooling of the combustion flue gas
and the syngas are superheated and sent to the ST. The ST output is approximately 9 MW. The
total gross output is approximately 24 MW. The internal power load is approximately 4 MW for
a net power output of about 20 MW.

13-1
Nitrogen is required for start-up and shutdown. A separate steam system is required for start-up.
NH3 is required for operation of the two SCRs for reducing NOX emissions. A flare system is
required for normal operation to eliminate volatile organics from the scrubbing system, and for
start-up and shutdown of the process. Figure 13-1 presents the BCC process flow diagram,
where the “Power Block” is based on a traditional combined-cycle configuration, as is often the
case for gasification derivative plants.
FIGURE 13-1 – BCC DESIGN CONFIGURATION

13.2ELECTRICAL AND CONTROL SYSTEMS


The BCC Facility has one CT electric generator and one ST electric generator. The generator for
the CT is a 60 Hz machine rated at approximately 17 MVA with an output voltage of 13.8 kV.
The ST electric generator is a 60 Hz machine rated at approximately 10 MVA with an output
voltage of 13.8 kV. The generator breakers for the CT and ST electric generators are bussed
together in 15 kV class switchgear that is connected to a high-voltage transmission system at the
facility switchyard via a circuit breaker, GSU, and a disconnect switch. The GSU increases the
voltage from the electric generators from 13.8 kV to interconnected transmission system high
voltage.
The BCC Facility is controlled using a DCS. The DCS provides centralized control of the
facility by integrating the control systems provided with each individual CT and associated

13-2
electric generator, ST and associated electric generator, and the control of BOP systems and
equipment.

13.3OFF-SITE REQUIREMENTS
Biomass is delivered to the BCC Facility by rail, truck or barge. Water for all processes at the
BCC Facility is obtained from one of several available water sources. The BCC Facility uses a
water treatment system and a high-efficiency reverse osmosis system to reduce the dissolved
solids from the cooling water and to provide distilled water for HRSG makeup. Wastewater is
sent to a municipal wastewater system or other available wastewater delivery point. Further, the
electrical interconnection from the BCC Facility on-site switchyard is effectuated by a
connection to an adjacent utility substation.

13.4CAPITAL COST ESTIMATE


The base Cost Estimate for the BCC Facility with a nominal capacity of 20 MW is $7,573/kW.
Table 13-1 summarizes the Cost Estimate categories for the BCC Facility.

13-3
TABLE 13-1 – BASE PLANT SITE CAPITAL COST ESTIMATE FOR BCC
Technology: BCC
Nominal Capacity (ISO): 20,000 kW
Nominal Heat Rate (ISO): 12,350 Btu/kWh-HHV

Capital Cost Category (000s) (October 1, 2010$)

Civil Structural Material and Installation 16,459

Mechanical Equipment Supply and


Installation 70,137

Electrical / I&C Supply and Installation 11,267

Project Indirects (1) 21,207

EPC Cost before Contingency and Fee 119,070

Fee and Contingency 12,500

Total Project EPC 131,570

Owner Costs (excluding project finance) 26,314

Total Project Cost (excluding finance) 157,884

Total Project EPC / kW 6,578

Owner Costs 20% (excluding project finance) / kW 1,316

Total Project Cost (excluding project finance) / kW 7,894

(1) Includes engineering, distributable costs, scaffolding, construction management, and start-up.

For this type of technology and power plant configuration, our regional adjustments took into
consideration the following: outdoor installation considerations, seismic design differences,
remote location issues, labor wage and productivity differences, location adjustments, owner cost
differences, and the increase in overheads associated with these six adjustments.

Outdoor installation locations are considered in geographic areas where enclosed structures for
the boilers would not be required due to the low probability of freezing. The locations that
included outdoor installation are Alabama, Arizona, Arkansas, Florida, Georgia, Hawaii,
Louisiana, Mississippi, New Mexico, South Carolina, and Puerto Rico.
Seismic design differences among the various locations were based on U.S. seismic map
information that detailed the various seismic zones throughout the U.S. No cost increases were
associated with seismic Zone 0 and cost step increases were considered for Zones 1, 2, 3 and 4.

13-4
Remote location issues are related to geographic areas that typically require installation of man
camps, higher craft incentives, and higher per diems are generally required with respect to
construction, due to the fact that such areas are long distances from urban areas, where labor is
generally abundant. Remote location designations were also considered in locations where
higher equipment freight costs are typically incurred, which for example are regions not near
established rail or highway access. Remote locations related to the BCC include Fairbanks,
Alaska; Honolulu, Hawaii; Albuquerque, New Mexico; Cheyenne, Wyoming; and Cayey, Puerto
Rico.
Labor wage and productivity differences were handled as discussed in Section 2.5.1, taking into
consideration the amount of labor we estimated for the BCC Facility.
Location adjustments were made to locations where higher cost of living levels are incurred
and/or where population density generally correlates to higher construction costs for power and
other infrastructure projects. These locations include Alaska, California, Connecticut, Delaware,
District of Columbia, Hawaii, Illinois, Maine, Maryland, Massachusetts, Michigan, Minnesota,
New York, Ohio, and Wisconsin.
Owner costs were reviewed based on the need for utility upgrades and/or infrastructure costs
such as new facility transmission lines to tie to existing utility transmission substations or
existing transmission lines.
Table 13-2 presents the BCC Facility capital cost variations for alternative U.S. plant locations.

13-5
TABLE 13-2 – LOCATION-BASED COSTS FOR BCC
(OCTOBER 1, 2010 DOLLARS)
Base
Project Location Delta Cost Total Location
Cost Percent Difference Project Cost
State City ($/kW) Variation ($/kW) ($/kW)
Alaska Anchorage 7,900 14.0% 1,104 9,004
Alaska Fairbanks 7,900 15.2% 1,197 9,097
Alabama Huntsville 7,900 -6.0% (472) 7,428
Arizona Phoenix 0 0.0% 0 0
Arkansas Little Rock 7,900 -5.0% (392) 7,508
California Los Angeles 7,900 7.2% 566 8,466
California Redding 7,900 3.3% 262 8,162
California Bakersfield 7,900 3.0% 237 8,137
California Sacramento 7,900 6.8% 539 8,439
California San Francisco 7,900 19.6% 1,547 9,447
Colorado Denver 7,900 -9.2% (724) 7,176
Connecticut Hartford 7,900 11.9% 940 8,840
Delaware Dover 7,900 9.7% 768 8,668
District of Columbia Washington 7,900 15.1% 1,196 9,096
Florida Tallahassee 7,900 -8.0% (635) 7,265
Florida Tampa 7,900 -3.5% (274) 7,626
Georgia Atlanta 7,900 -6.5% (511) 7,389
Hawaii Honolulu 7,900 29.3% 2,311 10,211
Idaho Boise 7,900 -3.9% (304) 7,596
Illinois Chicago 7,900 13.6% 1,073 8,973
Indiana Indianapolis 7,900 0.4% 35 7,935
Iowa Davenport 7,900 -1.2% (93) 7,807
Iowa Waterloo 7,900 -6.8% (539) 7,361
Kansas Wichita 7,900 -5.6% (444) 7,456
Kentucky Louisville 7,900 -4.7% (375) 7,525
Louisiana New Orleans 7,900 -8.3% (653) 7,247
Maine Portland 7,900 -3.0% (236) 7,664
Maryland Baltimore 7,900 0.1% 10 7,910
Massachusetts Boston 7,900 18.5% 1,459 9,359
Michigan Detroit 7,900 2.4% 188 8,088
Michigan Grand Rapids 7,900 -5.9% (469) 7,431
Minnesota St. Paul 7,900 2.5% 200 8,100
Mississippi Jackson 7,900 -5.9% (469) 7,431
Missouri St. Louis 7,900 2.8% 220 8,120
Missouri Kansas City 7,900 1.5% 119 8,019
Montana Great Falls 7,900 -4.8% (379) 7,521
Nebraska Omaha 7,900 -3.2% (252) 7,648
New Hampshire Concord 7,900 -2.3% (182) 7,718
New Jersey Newark 7,900 11.2% 882 8,782

13-6
Base
Project Location Delta Cost Total Location
Cost Percent Difference Project Cost
State City ($/kW) Variation ($/kW) ($/kW)
New Mexico Albuquerque 0 0.0% 0 0
New York New York 7,900 23.6% 1,866 9,766
New York Syracuse 7,900 3.3% 259 8,159
Nevada Las Vegas 0 0.0% 0 0
North Carolina Charlotte 7,900 -8.3% (658) 7,242
North Dakota Bismarck 7,900 -6.0% (476) 7,424
Ohio Cincinnati 7,900 -1.7% (134) 7,766
Oregon Portland 7,900 3.1% 246 8,146
Pennsylvania Philadelphia 7,900 8.1% 639 8,539
Pennsylvania Wilkes-Barre 7,900 -3.7% (293) 7,607
Rhode Island Providence 7,900 2.1% 162 8,062
South Carolina Spartanburg 7,900 -9.8% (771) 7,129
South Dakota Rapid City 7,900 -8.1% (639) 7,261
Tennessee Knoxville 7,900 -7.3% (575) 7,325
Texas Houston 7,900 -7.2% (568) 7,332
Utah Salt Lake City 0 0.0% 0 0
Vermont Burlington 7,900 -5.1% (400) 7,500
Virginia Alexandria 7,900 2.5% 198 8,098
Virginia Lynchburg 7,900 -3.4% (271) 7,629
Washington Seattle 7,900 5.6% 441 8,341
Washington Spokane 7,900 -2.8% (222) 7,678
West Virginia Charleston 7,900 -1.9% (149) 7,751
Wisconsin Green Bay 7,900 -1.1% (83) 7,817
Wyoming Cheyenne 0 0.0% 0 0
Puerto Rico Cayey 7,900 -3.7% (290) 7,610

13.5O&M ESTIMATE
In addition to the general items discussed in the section of this report entitled O&M Estimate, the
BCC Facility include the major maintenance for the CT, as well as the BOP, including the ST,
associated electric generator, HRSG, and emissions reduction catalysts. These major
maintenance expenses are included with the VOM expense for this technology and are given on
an average basis across the MWhs incurred. Typically, significant overhauls on a BCC Facility
occur no less frequently than 8,000 operating hour intervals, with more significant major outages
occurring on 24,000 hour intervals. Additionally, major maintenance needs to be completed on
the gasifier, including the refractory, which due to the lower operating temperature (as compared
to the IGCC Facility discussed above) only needs replacing approximately every 10 years.
Table 13-3 presents the O&M expenses for the BCC Facility.
TABLE 13-3 – O&M EXPENSES FOR BCC
Technology: BCC
Fixed O&M Expense $338.79/kW-year
Variable O&M Expense $16.64/MWh

13-7
13.6ENVIRONMENTAL COMPLIANCE INFORMATION
The BCC Facility utilizes syngas combustors (which do not have DLN) in the CT and best
available burner technology with respect to the duct burners in the HRSGs to manage the
production of NOX and CO. Additional control of NOX and CO is accomplished through an SCR
and an oxidization catalyst, respectively. SO2 in the IGCC is managed through the use of low-
sulfur biomass feedstocks. The BCC does not include any control devices for CO2, which is
proportional to the heat rate (inversely proportional to the efficiency) of the technology. Water,
wastewater, and solid waste compliance are achieved through traditional on-site and off-site
methods, and the costs for such compliance are included in the O&M Estimate for the BCC
Facility. Table 13-4 presents environmental emissions for the BCC Facility.
TABLE 13-4 – ENVIRONMENTAL EMISSIONS FOR BCC
Technology: BCC
NOX 0.054 lb/MMBtu
SO2 0 lb/MMBtu
CO2 195 lb/MMBtu

13-8
14. BIOMASS BUBBLING FLUIZED BED (BBFB)

14.1MECHANICAL EQUIPMENT AND SYSTEMS


The Biomass BFB (“BBFB”) Facility utilizes approximately 2,000 tons per day of wood (at
50 percent maximum moisture) for the production of 50 MW net of electricity. The BBFB
Facility consists of a BFB boiler, which will flow to the ST. Steam leaving the ST will be
condensed to water in a shell and tube surface condenser. The water will be pumped from the
“hotwell” of the condenser through a series of feedwater heaters for purposes of pre-heating the
water with ST extraction steam. The combination of feedwater heating and waste heat flowing
through the economizer is included to improve cycle efficiency. The water will enter the first
feedwater heater where it will be heated using extraction steam from the ST. The water will then
flow to the deaerating feedwater heater and into an electric-driven boiler feed pump where the
pressure of the water will be increased to approximately 1,800 psia. After leaving the boiler feed
pump, the water will flow through two more feedwater heaters. After exiting the last feedwater
heater, the water will flow to the economizer section of the BFB boiler for delivery to the
combustion section where it will be converted back to steam and the cycle will be repeated. The
cooling tower is to be used to cool the circulating water that is used to condense the steam inside
the condenser.
In a BFB boiler, a portion of air is introduced through the bottom of the combustor. The bottom
of the bed is supported by refractory walls or water-cooled membrane with specially designed air
nozzles which distribute the air uniformly. The fuel and limestone are fed into the lower bed. In
the presence of fluidizing air, the fuel and limestone quickly and uniformly mix under the
turbulent environment and behave like a fluid. Carbon particles in the fuel are exposed to the
combustion air. The balance of combustion air is introduced at the top of the lower, dense bed.
This staged combustion limits the formation of NOX. The advantages of BFB boiler technology
include fuel flexibility, low SO2 emissions, low NOX emissions, and high combustion efficiency.
FIGURE 14-1 – BCC DESIGN CONFIGURATION

14-1
14.2ELECTRICAL AND CONTROL SYSTEMS
The BBFB Facility has one ST electric generator. The generator for the ST is a 60 Hz machine
rated at approximately 65 MVA with an output voltage of 13.8 kV. The generator breakers for
the ST electric generator are bussed together in 15 kV class switchgear that is connected to a
high-voltage transmission system at the facility switchyard via a circuit breaker, GSU, and a
disconnect switch. The GSU increases the voltage from the electric generators from 13.8 kV to
interconnected transmission system high voltage.
The BBFB Facility is controlled using a DCS. The DCS provides centralized control of the
facility by integrating the control systems provided with the ST and associated electric generator
and the control of BOP systems and equipment.

14.3OFF-SITE REQUIREMENTS
Biomass is delivered to the BBFBFacility by rail, truck or barge. Water for all processes at the
BBFB Facility is obtained from one of several available water sources. The BBFB Facility uses
a water treatment system and a high-efficiency reverse osmosis system to reduce the dissolved
solids from the cooling water and to provide distilled water for HRSG makeup. Wastewater is
sent to a municipal wastewater system or other available wastewater delivery point. Further, the
electrical interconnection from the BBFB Facility on-site switchyard is effectuated by a
connection to an adjacent utility substation.

14.4CAPITAL COST ESTIMATE


The base Cost Estimate for the BBFB Facility with a nominal capacity of 50 MW is $3,860/kW.
Table 14-1 summarizes the Cost Estimate categories for the BBFB Facility.

14-2
TABLE 14-1 – BASE PLANT SITE CAPITAL COST ESTIMATE FOR BBFB
Technology: BBFB
Nominal Capacity (ISO): 50,000 kW
Nominal Heat Rate (ISO): 13,500 Btu/kWh-HHV

Capital Cost Category (000s) (October 1, 2010$)

Civil Structural Material and Installation 13,650

Mechanical Equipment Supply and


Installation 67,200

Electrical / I&C Supply and Installation 20,000

Project Indirects (1) 40,250

EPC Cost before Contingency and Fee 141,100

Fee and Contingency 19,754

Total Project EPC 160,854

Owner Costs (excluding project finance) 32,171

Total Project Cost (excluding finance) 193,025

Total Project EPC / kW 3,217

Owner Costs 20% (excluding project finance) / kW 643

Total Project Cost (excluding project finance) / kW 3,860

(1) Includes engineering, distributable costs, scaffolding, construction management, and start-up.

For this type of technology and power plant configuration, our regional adjustments took into
consideration the following: outdoor installation considerations, seismic design differences,
remote location issues, labor wage and productivity differences, location adjustments, owner cost
differences, and the increase in overheads associated with these six adjustments.

Outdoor installation locations are considered in geographic areas where enclosed structures for
the boilers would not be required due to the low probability of freezing. The locations that
included outdoor installation are Alabama, Arizona, Arkansas, Florida, Georgia, Hawaii,
Louisiana, Mississippi, New Mexico, South Carolina, and Puerto Rico.
Seismic design differences among the various locations were based on U.S. seismic map
information that detailed the various seismic zones throughout the U.S. No cost increases were
associated with seismic Zone 0 and cost step increases were considered for Zones 1, 2, 3 and 4.

14-3
Remote location issues are related to geographic areas that typically require installation of man
camps, higher craft incentives, and higher per diems are generally required with respect to
construction, due to the fact that such areas are long distances from urban areas, where labor is
generally abundant. Remote location designations were also considered in locations where
higher equipment freight costs are typically incurred, which for example are regions not near
established rail or highway access. Remote locations related to the BCC include Fairbanks,
Alaska; Honolulu, Hawaii; Albuquerque, New Mexico; Cheyenne, Wyoming; and Cayey, Puerto
Rico.
Labor wage and productivity differences were handled as discussed in Section 2.5.1, taking into
consideration the amount of labor we estimated for the BCC Facility.
Location adjustments were made to locations where higher cost of living levels are incurred
and/or where population density generally correlates to higher construction costs for power and
other infrastructure projects. These locations include Alaska, California, Connecticut, Delaware,
District of Columbia, Hawaii, Illinois, Maine, Maryland, Massachusetts, Michigan, Minnesota,
New York, Ohio, and Wisconsin.
Owner costs were reviewed based on the need for utility upgrades and/or infrastructure costs
such as new facility transmission lines to tie to existing utility transmission substations or
existing transmission lines.
Table 14-2 presents the BBFB Facility capital cost variations for alternative U.S. plant locations.

14-4
TABLE 14-2– LOCATION-BASED COSTS FOR BBFB
(OCTOBER 1, 2010 DOLLARS)
Base
Project Location Delta Cost Total Location
Cost Percent Difference Project Cost
State City ($/kW) Variation ($/kW) ($/kW)
Alaska Anchorage 3,860 25.8% 995 4,855
Alaska Fairbanks 3,860 27.9% 1,076 4,936
Alabama Huntsville 3,860 -9.7% (376) 3,484
Arizona Phoenix 0 0.0% 0 0
Arkansas Little Rock 3,860 -8.1% (311) 3,549
California Los Angeles 3,860 13.4% 516 4,376
California Redding 3,860 6.3% 242 4,102
California Bakersfield 3,860 5.7% 221 4,081
California Sacramento 3,860 11.9% 460 4,320
California San Francisco 3,860 35.6% 1,373 5,233
Colorado Denver 3,860 -8.2% (318) 3,542
Connecticut Hartford 3,860 22.9% 882 4,742
Delaware Dover 3,860 19.3% 745 4,605
District of Columbia Washington 3,860 31.6% 1,219 5,079
Florida Tallahassee 3,860 -13.1% (506) 3,354
Florida Tampa 3,860 -5.7% (221) 3,639
Georgia Atlanta 3,860 -10.5% (407) 3,453
Hawaii Honolulu 3,860 58.2% 2,248 6,108
Idaho Boise 3,860 -6.2% (238) 3,622
Illinois Chicago 3,860 22.7% 875 4,735
Indiana Indianapolis 3,860 1.5% 56 3,916
Iowa Davenport 3,860 -1.9% (74) 3,786
Iowa Waterloo 3,860 -11.0% (426) 3,434
Kansas Wichita 3,860 -9.1% (350) 3,510
Kentucky Louisville 3,860 -7.6% (295) 3,565
Louisiana New Orleans 3,860 -13.5% (520) 3,340
Maine Portland 3,860 -4.0% (156) 3,704
Maryland Baltimore 3,860 1.6% 63 3,923
Massachusetts Boston 3,860 33.5% 1,292 5,152
Michigan Detroit 3,860 3.9% 150 4,010
Michigan Grand Rapids 3,860 -9.6% (371) 3,489
Minnesota St. Paul 3,860 4.3% 166 4,026
Mississippi Jackson 3,860 -9.7% (373) 3,487
Missouri St. Louis 3,860 4.7% 181 4,041
Missouri Kansas City 3,860 2.5% 96 3,956
Montana Great Falls 3,860 -4.8% (185) 3,675
Nebraska Omaha 3,860 -5.1% (198) 3,662
New Hampshire Concord 3,860 -3.6% (141) 3,719
New Jersey Newark 3,860 18.1% 698 4,558

14-5
Base
Project Location Delta Cost Total Location
Cost Percent Difference Project Cost
State City ($/kW) Variation ($/kW) ($/kW)
New Mexico Albuquerque 3,860 0.0% (3,860) -
New York New York 3,860 38.3% 1,477 5,337
New York Syracuse 3,860 7.5% 288 4,148
Nevada Las Vegas 0 0.0% 0 0
North Carolina Charlotte 3,860 -13.4% (517) 3,343
North Dakota Bismarck 3,860 -9.7% (376) 3,484
Ohio Cincinnati 3,860 -2.0% (77) 3,783
Oregon Portland 3,860 5.9% 228 4,088
Pennsylvania Philadelphia 3,860 13.1% 507 4,367
Pennsylvania Wilkes-Barre 3,860 -5.9% (229) 3,631
Rhode Island Providence 3,860 3.4% 131 3,991
South Carolina Spartanburg 3,860 -15.8% (611) 3,249
South Dakota Rapid City 3,860 -13.1% (505) 3,355
Tennessee Knoxville 3,860 -11.7% (453) 3,407
Texas Houston 3,860 -11.6% (449) 3,411
Utah Salt Lake City 0 0.0% 0 0
Vermont Burlington 3,860 -8.1% (314) 3,546
Virginia Alexandria 3,860 6.2% 240 4,100
Virginia Lynchburg 3,860 -4.8% (186) 3,674
Washington Seattle 3,860 9.9% 382 4,242
Washington Spokane 3,860 -4.5% (172) 3,688
West Virginia Charleston 3,860 -3.0% (117) 3,743
Wisconsin Green Bay 3,860 -1.0% (39) 3,821
Wyoming Cheyenne 0 0.0% 0 0
Puerto Rico Cayey 3,860 -5.5% (213) 3,647

14.5O&M ESTIMATE
In addition to the general items discussed in the section of this report entitled O&M Estimate, the
BBFB Facility includes the major maintenance for the ST and associated electric generator, as
well as the BOP. These major maintenance expenses are included with the VOM expense for
this technology and are given on an average basis across the MWhs incurred. Typically,
significant overhauls on a BBFB Facility occur no less frequently than 6 to 8 years. Table 14-3
presents the O&M expenses for the BBFB Facility.
TABLE 14-3 – O&M EXPENSES FOR BCC
Technology: BCC
Fixed O&M Expense $100.50/kW-year
Variable O&M Expense $5.0/MWh

14-6
14.6ENVIRONMENTAL COMPLIANCE INFORMATION
The BBFB Facility utilizes BFB combustion to control NOX and CO. SO2 in the BFB is
managed through the use of low-sulfur biomass feedstocks. The BBFB Facility does not include
any control devices for CO2, which is proportional to the heat rate (inversely proportional to the
efficiency) of the technology. Water, wastewater, and solid waste compliance are achieved
through traditional on-site and off-site methods, and the costs for such compliance are included
in the O&M Estimate for the BBFB Facility. Table 14-4 presents environmental emissions for
the BBFB Facility.
TABLE 14-4 – ENVIRONMENTAL EMISSIONS FOR BBFB
Technology: BBFB
NOX 0.08 lb/MMBtu
SO2 0 lb/MMBtu
CO2 195 lb/MMBtu

14-7
15. FUEL CELL (FC) MECHANICAL EQUIPMENT AND SYSTEMS
The Fuel Cell (“FC”) Facility utilizes multiple phosphoric acid fuel cell units, each with a power
output of 400 kW, for a total output of 10 MW. The fuel cells convert chemical energy directly
into electricity from natural gas and air vapor and produce heat and water vapor as byproducts.
The fuel (the reactant) is introduced continuously to the anode side of the unit cell while air (the
oxidant) is introduced continuously into the cathode side via a blower. In a fuel cell, electricity
is produced by ionic transfer across an electrolyte that separates the fuel from the air. A high
temperature fuel cell produces electricity by splitting a molecule of the oxidant into its ionic
components at the cathode, passing ions through the electrolyte (e.g. in the case of the
FC Facility, a phosphoric acid ion) and then reacting the ions with the fuel at the anode to
produce heat to allow the reaction to occur. During this ionic transfer process, two electrons are
stripped from each ion to which develops a voltage and current. Since each fuel cell develops a
relatively low voltage, the cells are stacked to produce a higher, more useful voltage. Depending
on the type of fuel cell, high temperature waste heat from the process may be available for
cogeneration applications. Figure 15-1 presents the fuel cell process flow diagram.
FIGURE 15-1 – FC DESIGN CONFIGURATION

15.1ELECTRICAL AND CONTROL SYSTEMS


Each fuel cell stack generates DC electric power. These stacks are connected to DC-to-AC
inverters that produce an output of 60 Hz, three-phase 480 volt (“V”) AC electric power voltage.
The inverters also provide power quality control and protection when designed to IEEE
Standards. The fuel cell units are connected through circuit breakers to a switchgear bus that
combines the output of the fuel cell units for a total output of 10 MW. The switchgear is
connected through a circuit breaker to the local utility distribution system.
Each individual fuel cell module has its own autonomous control system with an overall data
acquisition system for the combined FC Facility.

15.2OFF-SITE REQUIREMENTS
Natural gas is delivered to the FC Facility through a lateral or in an urban environment,
potentially through the local distribution company infrastructure. Water for all processes at the

15-1
FC Facility is obtained from one of several available water sources, but given that the water
needs are low, a municipal (potable) water source would be preferable. Wastewater is sent to a
municipal wastewater system. Further, the electrical interconnection from the FC Facility is into
the local grid distribution infrastructure.

15.3CAPITAL COST ESTIMATE


The base Cost Estimate for the FC Facility with a nominal capacity of 10 MW is $9,960/kW.
Table 15-1 summarizes the Cost Estimate categories for the FC Facility.
TABLE 15-1 – BASE PLANT SITE CAPITAL COST ESTIMATE FOR FC
Technology: FC
Nominal Capacity (ISO): 10,000 kW
Nominal Heat Rate (ISO): 9,500 Btu/kWh-HHV

Capital Cost Category (000s) (October 1, 2010$)

Civil Structural Material and Installation 3,148

Mechanical Equipment Supply and


Installation 49,925

Electrical / I&C Supply and Installation 2,050

Project Indirects (1) 3,473

EPC Cost before Contingency and Fee 58,596

Fee and Contingency 4,688

Total Project EPC 63,284

Owner Costs (excluding project finance) 5,063

Total Project Cost (excluding finance) 68,347

Total Project EPC / kW 6,328

Owner Costs 8% (excluding project finance) / kW 500

Total Project Cost (excluding project finance) / kW 6,835

(1) Includes engineering, distributable costs, scaffolding, construction management, and start-up.

For this type of technology and power plant configuration, our regional adjustments took into
consideration the following: seismic design differences, remote location issues, labor wage and
productivity differences, location adjustments, owner cost differences, and the increase in
overheads associated with these five adjustments.

15-2
Seismic design differences among the various locations were based on U.S. seismic map
information that detailed the various seismic zones throughout the U.S. No cost increases were
associated with seismic Zone 0 and cost step increases were considered for Zones 1, 2, 3 and 4.
Remote location issues are related to geographic areas that typically require installation of man
camps, higher craft incentives, and higher per diems are generally required with respect to
construction, due to the fact that such areas are long distances from urban areas, where labor is
generally abundant. Remote location designations were also considered in locations where
higher equipment freight costs are typically incurred, which for example are regions not near
established rail or highway access. Remote locations related to the FC Facility include
Fairbanks, Alaska; Honolulu, Hawaii; Albuquerque, New Mexico; Cheyenne, Wyoming; and
Cayey, Puerto Rico.
Labor wage and productivity differences were handled as discussed in Section 2.5.1, taking into
consideration the amount of labor we estimated for the FC Facility.
Location adjustments were made to locations where higher cost of living levels are incurred
and/or where population density generally correlates to higher construction costs for power and
other infrastructure projects. These locations include Alaska, California, Connecticut, Delaware,
District of Columbia, Hawaii, Illinois, Maine, Maryland, Massachusetts, Michigan, Minnesota,
New York, Ohio, and Wisconsin.
Owner costs were reviewed based on the need for utility upgrades and/or infrastructure costs
such as new facility transmission lines to tie to existing utility transmission substations or
existing transmission lines.
Table 15-2 presents the FC Facility capital cost variations for alternative U.S. plant locations.

15-3
TABLE 15-2 – LOCATION-BASED COSTS FOR FC
(OCTOBER 1, 2010 DOLLARS)
Base
Project Location Delta Cost Total Location
Cost Percent Difference Project Cost
State City ($/kW) Variation ($/kW) ($/kW)
Alaska Anchorage 6,835 12.7% 871 7,706
Alaska Fairbanks 6,835 18.4% 1,255 8,090
Alabama Huntsville 6,835 -4.6% (312) 6,523
Arizona Phoenix 6,835 -3.5% (240) 6,595
Arkansas Little Rock 6,835 -3.7% (251) 6,584
California Los Angeles 6,835 4.3% 293 7,128
California Redding 6,835 1.7% 119 6,954
California Bakersfield 6,835 2.2% 150 6,985
California Sacramento 6,835 4.6% 313 7,148
California San Francisco 6,835 10.7% 733 7,568
Colorado Denver 6,835 -4.1% (278) 6,557
Connecticut Hartford 6,835 4.4% 299 7,134
Delaware Dover 6,835 2.4% 166 7,001
District of Columbia Washington 6,835 1.9% 127 6,962
Florida Tallahassee 6,835 -6.3% (432) 6,403
Florida Tampa 6,835 -2.6% (179) 6,656
Georgia Atlanta 6,835 -5.0% (340) 6,495
Hawaii Honolulu 6,835 12.0% 817 7,652
Idaho Boise 6,835 -3.0% (203) 6,632
Illinois Chicago 6,835 10.0% 681 7,516
Indiana Indianapolis 6,835 -0.6% (42) 6,793
Iowa Davenport 6,835 -1.0% (65) 6,770
Iowa Waterloo 6,835 -5.5% (378) 6,457
Kansas Wichita 6,835 -4.5% (306) 6,529
Kentucky Louisville 6,835 -3.8% (258) 6,577
Louisiana New Orleans 6,835 -6.5% (445) 6,390
Maine Portland 6,835 -2.4% (162) 6,673
Maryland Baltimore 6,835 -1.3% (86) 6,749
Massachusetts Boston 6,835 9.7% 662 7,497
Michigan Detroit 6,835 2.3% 156 6,991
Michigan Grand Rapids 6,835 -4.5% (310) 6,525
Minnesota St. Paul 6,835 1.9% 133 6,968
Mississippi Jackson 6,835 -4.5% (310) 6,525
Missouri St. Louis 6,835 2.6% 180 7,015
Missouri Kansas City 6,835 1.4% 94 6,929
Montana Great Falls 6,835 -3.1% (209) 6,626
Nebraska Omaha 6,835 -2.5% (172) 6,663
New Hampshire Concord 6,835 -1.4% (98) 6,737
New Jersey Newark 6,835 10.1% 689 7,524

15-4
Base
Project Location Delta Cost Total Location
Cost Percent Difference Project Cost
State City ($/kW) Variation ($/kW) ($/kW)
New Mexico Albuquerque 6,835 -2.8% (194) 6,641
New York New York 6,835 22.2% 1,514 8,349
New York Syracuse 6,835 -0.7% (48) 6,787
Nevada Las Vegas 6,835 3.7% 253 7,088
North Carolina Charlotte 6,835 -6.6% (451) 6,384
North Dakota Bismarck 6,835 -4.6% (314) 6,521
Ohio Cincinnati 6,835 -2.6% (180) 6,655
Oregon Portland 6,835 1.6% 107 6,942
Pennsylvania Philadelphia 6,835 6.7% 459 7,294
Pennsylvania Wilkes-Barre 6,835 -2.9% (195) 6,640
Rhode Island Providence 6,835 1.8% 124 6,959
South Carolina Spartanburg 6,835 -7.6% (517) 6,318
South Dakota Rapid City 6,835 -6.3% (429) 6,406
Tennessee Knoxville 6,835 -5.8% (398) 6,437
Texas Houston 6,835 -5.8% (398) 6,437
Utah Salt Lake City 6,835 -3.7% (251) 6,584
Vermont Burlington 6,835 -3.7% (251) 6,584
Virginia Alexandria 6,835 -0.8% (52) 6,783
Virginia Lynchburg 6,835 -4.0% (276) 6,559
Washington Seattle 6,835 3.6% 244 7,079
Washington Spokane 6,835 -1.8% (126) 6,709
West Virginia Charleston 6,835 -1.2% (80) 6,755
Wisconsin Green Bay 6,835 -1.9% (130) 6,705
Wyoming Cheyenne 6,835 -3.6% (245) 6,590
Puerto Rico Cayey 6,835 -0.2% (14) 6,821

15.4O&M ESTIMATE
In addition to the general items discussed in the section of this report entitled O&M Estimate,
since a FC is a direct energy conversion device, the specific O&M related to the FC Facility that
differs from other facilities discussed in this report is the stack replacement, currently anticipated
to be every five years by the various vendors and developers. Table 15-3 presents the O&M
expenses for the FC Facility.
TABLE 15-3 – O&M EXPENSES FOR FC
Technology: FC
Fixed O&M Expense $350/kW-year
Variable O&M Expense $0/MWh

15-5
15.5ENVIRONMENTAL COMPLIANCE INFORMATION
Table 15-4 presents environmental emissions for the FC Facility. It should be noted that the CO2
production from the FC Facility occurs as a result of reforming natural gas to the feedstock for
the fuel cell module.
TABLE 15-4 – ENVIRONMENTAL EMISSIONS FOR FC
Technology: FC
NOX <0.013 lb/MMBtu
SO2 <0.00013 lb/MMBtu
CO2 <130 lb/MMBtu

15-6
16. GEOTHERMAL DUAL FLASH (GT)

16.1MECHANICAL EQUIPMENT AND SYSTEMS


The Geothermal (“GT”) Facility produces 50 MW net of electricity. The facility uses a
dual-flash GT cycle, which includes one ST with the capability to generate 55 gross MW based
on a high-temperature, high-salinity brine. The GT Facility consists of production wells, a
Turbine Generating Facility (“TGF”), a Brine Processing Facility (“BPF”), injection wells, and a
plant injection well. GT fluid in mixed phase (steam and brine) from the production wells is
piped to the BPF where the fluid is flashed at successively lower pressures to produce three
separate pressure levels of steam to be delivered to the TGF. Additionally, the BPF will produce
a concentrated brine to be further processed to remove solids.
The GT production wells deliver the GT brine to the BPF where it is initially flashed in a
separator drum to produce HP steam. The remaining brine is subject to two additional pressure
reduction stages, in closed pressure vessels called crystallizers, which are operated in a manner
to prevent the rapid scaling of the vessel walls and internal parts by the precipitation of solids
from the brine. The medium-pressure crystallizer is supplied with a small quantity of seed flow,
concentrated brine from the primary clarifier, to provide a nucleus to which the solids in the
crystallizer brine can attach themselves and be carried out with the brine leaving the crystallizer.
The separated brine from the crystallizers is sent through an atmospheric flash tank to reduce
pressure, and then further processed via a primary and secondary clarifier system where the
solids produced are formed into a solid cake after being passed through a filter press, treated with
acid and neutralizing washes, and steam and hot-air dried to produce a silica rich filter cake
Steam at the three pressure levels from the BPF is delivered to the TGF and directed through
steam scrubbers (one for each pressure level), which are designed to produce 99.95 percent
quality steam, by removing free liquids and a proportion of the entrained liquids within the
steam. The scrubbed steam is delivered to the ST. The ST is a condensing ST equipped with
dual HP, IP, and LP inlets. Steam from the ST is condensed in a two-pass shell and tube
condenser constructed of stainless steel, with part of the condensate used for cooling tower
make-up, and the remainder pumped to the re-injection wells. Condensate pumps direct
condensate to the circulating water system, the purge system, or the condensate injection system.
The non-condensable gases are evacuated by a non-condensable gas removal system and vent
products delivered to an H2S abatement system. Cooling water for the ST condenser is supplied
by an induced-draft cooling tower. Circulating water pumps direct water from the cooling tower
to the ST condenser. Make-up water for the cycle is supplied from the condensate from the ST
condenser. Additional make-up water may be needed during the summer months. Figure 16-1
presents a simplified process flow diagram for a GT power plant configuration.

16-1
FIGURE 16-1 – GT DESIGN CONFIGURATION

16.2ELECTRICAL AND CONTROL SYSTEMS


The GT Facility has one ST electric generator. The generator is a 60 Hz machine rated at
approximately 70 MVA with an output voltage of 13.8 kV. The ST electric generator is
connected to a high-voltage bus in the facility switchyard via a dedicated generator circuit
breaker, GSU, high-voltage circuit breaker and a disconnect switch. The GSU increases the
voltage from the electric generator from 13.8 kV to interconnected transmission system high
voltage.
The GT Facility is controlled using a DCS. The DCS provides centralized control of the facility
by integrating the control systems provided with the BPF, ST and associated electric generator,
and the control of BOP systems and equipment.

16.3OFF-SITE REQUIREMENTS
Since the GT Facility is fueled by a renewable, underground fuel source, an off-site fuel source,
other than incidental plant heating, is not required. Water for all processes at the GT Facility is
obtained from one of several available water sources; however, due to the geography of most
geothermal power plants, water is sourced from on-site wells. Processed wastewater is generally
re-injected, if wells are the source of water, though many GT facilities utilize ZLD. Further, the

16-2
electrical interconnection from the GT Facility is accomplished by interconnecting via the plant
switchyard into the utility high-voltage transmission system.

16.4CAPITAL COST ESTIMATE


The base Cost Estimate for the GT Facility with a nominal capacity of 50 MW is $6,163/kW.
Table 16-1 summarizes the Cost Estimate categories for the GT Facility.
TABLE 16-1 – BASE PLANT SITE CAPITAL COST ESTIMATE FOR GT
Technology: GT
Nominal Capacity (ISO): 50,000 kW
Nominal Heat Rate (ISO): N/A Btu/kWh-HHV

Capital Cost Category (000s) (October 1, 2010$)

Civil Structural Material and Installation 9,450

Mechanical Equipment Supply and


Installation (and well costs) 152,000

Electrical / I&C Supply and Installation 12,062

Project Indirects (1) 32,000

EPC Cost before Contingency and Fee 205,512

Fee and Contingency 30,827

Total Project EPC 236,339

Owner Costs (excluding project finance) 42,541

Total Project Cost (excluding finance) 278,879

Total Project EPC / kW 4,726

Owner Costs 18% (excluding project finance) / kW 852

Total Project Cost (excluding project finance) / kW 5,578

(1) Includes engineering, distributable costs, scaffolding, construction management, and start-up.

For this type of technology and power plant configuration, our regional adjustments took into
consideration the following: seismic design differences, local technical enhancements
(e.g., additional noise remediation that is generally required in urban siting), remote location
issues, labor wage and productivity differences, location adjustments, and the increase in
overheads associated with these five adjustments. It was assumed that geothermal facilities
would only be considered in 13 states: Alaska, Arizona, California, Colorado, Florida, Hawaii,
Idaho, Nevada, New Mexico, Oregon, Utah, Washington, and Wyoming.

16-3
Seismic design differences among the various locations were based on U.S. seismic map
information that detailed the various seismic zones throughout the U.S. No cost increases were
associated with seismic Zone 0 and cost step increases were considered for Zones 1, 2, 3 and 4.
Remote location issues are related to geographic areas that typically require installation of man
camps, higher craft incentives, and higher per diems are generally required with respect to
construction, due to the fact that such areas are long distances from urban areas, where labor is
generally abundant. Remote location designations were also considered in locations where
higher equipment freight costs are typically incurred, which for example are regions not near
established rail or highway access. Remote locations related to the Geothermal Facility include
Fairbanks, Alaska; Honolulu, Hawaii; Albuquerque, New Mexico; and Cheyenne, Wyoming.
Labor wage and productivity differences were handled as discussed in Section 2.5.1, taking into
consideration the amount of labor we estimated for the GT Facility.
Location adjustments were made to locations where higher cost of living levels are incurred
and/or where population density generally correlates to higher construction costs for power and
other infrastructure projects. These locations include Alaska, California, Hawaii, and Wyoming.
Table 16-2 presents the GT Facility capital cost variations for alternative U.S. plant locations.

16-4
TABLE 16-2 – LOCATION-BASED COSTS FOR GT
(OCTOBER 1, 2010 DOLLARS)
Base
Project Location Delta Cost Total Location
Cost Percent Difference Project Cost
State City ($/kW) Variation ($/kW) ($/kW)
Alaska Anchorage 5,580 13.9% 777 6,357
Alaska Fairbanks 5,580 20.6% 1,150 6,730
Alabama Huntsville 0 0.0% 0 0
Arizona Phoenix 5,580 -3.1% (173) 5,407
Arkansas Little Rock 0 0.0% 0 0
California Los Angeles 5,580 5.4% 301 5,881
California Redding 5,580 1.8% 101 5,681
California Bakersfield 5,580 2.4% 136 5,716
California Sacramento 5,580 4.9% 271 5,851
California San Francisco 5,580 11.8% 661 6,241
Colorado Denver 5,580 -3.0% (165) 5,415
Connecticut Hartford 0 0.0% 0 0
Delaware Dover 0 0.0% 0 0
District of Columbia Washington 0 0.0% 0 0
Florida Tallahassee 0 0.0% 0 0
Florida Tampa 0 0.0% 0 0
Georgia Atlanta 0 0.0% 0 0
Hawaii Honolulu 5,580 21.8% 1,217 6,797
Idaho Boise 5,580 -2.6% (146) 5,434
Illinois Chicago 0 0.0% 0 0
Indiana Indianapolis 0 0.0% 0 0
Iowa Davenport 0 0.0% 0 0
Iowa Waterloo 0 0.0% 0 0
Kansas Wichita 0 0.0% 0 0
Kentucky Louisville 0 0.0% 0 0
Louisiana New Orleans 0 0.0% 0 0
Maine Portland 0 0.0% 0 0
Maryland Baltimore 0 0.0% 0 0
Massachusetts Boston 0 0.0% 0 0
Michigan Detroit 0 0.0% 0 0
Michigan Grand Rapids 0 0.0% 0 0
Minnesota St. Paul 0 0.0% 0 0
Mississippi Jackson 0 0.0% 0 0
Missouri St. Louis 0 0.0% 0 0
Missouri Kansas City 0 0.0% 0 0
Montana Great Falls 0 0.0% 0 0
Nebraska Omaha 0 0.0% 0 0
New Hampshire Concord 0 0.0% 0 0
New Jersey Newark 0 0.0% 0 0

16-5
Base
Project Location Delta Cost Total Location
Cost Percent Difference Project Cost
State City ($/kW) Variation ($/kW) ($/kW)
New Mexico Albuquerque 5,580 -2.1% (117) 5,463
New York New York 0 0.0% 0 0
New York Syracuse 0 0.0% 0 0
Nevada Las Vegas 5,580 3.5% 193 5,773
North Carolina Charlotte 0 0.0% 0 0
North Dakota Bismarck 0 0.0% 0 0
Ohio Cincinnati 0 0.0% 0 0
Oregon Portland 5,580 1.7% 92 5,672
Pennsylvania Philadelphia 0 0.0% 0 0
Pennsylvania Wilkes-Barre 0 0.0% 0 0
Rhode Island Providence 0 0.0% 0 0
South Carolina Spartanburg 0 0.0% 0 0
South Dakota Rapid City 0 0.0% 0 0
Tennessee Knoxville 0 0.0% 0 0
Texas Houston 0 0.0% 0 0
Utah Salt Lake City 5,580 -3.1% (173) 5,407
Vermont Burlington 0 0.0% 0 0
Virginia Alexandria 0 0.0% 0 0
Virginia Lynchburg 0 0.0% 0 0
Washington Seattle 5,580 3.5% 194 5,774
Washington Spokane 5,580 -1.8% (103) 5,477
West Virginia Charleston 0 0.0% 0 0
Wisconsin Green Bay 0 0.0% 0 0
Wyoming Cheyenne 5,580 -2.9% (164) 5,416
Puerto Rico Cayey 0 0.0% 0 0

16.5O&M ESTIMATE
In addition to the general items discussed in the section of this report entitled O&M Estimate, the
GT Facility includes major maintenance on the ST, electric generator (each approximately every
six years) and well field maintenance, which can vary depending on the GT resource. Table 16-3
presents the FOM and VOM expenses for the GT Facility.
TABLE 16-3 – O&M EXPENSES FOR GT
Technology: GT
Fixed O&M Expense $84.27/kW-year
Variable O&M Expense $9.46/MWh

16.6ENVIRONMENTAL COMPLIANCE INFORMATION


Table 16-4 presents environmental emissions for the GT Facility.

16-6
TABLE 16-4 – ENVIRONMENTAL EMISSIONS FOR GT
Technology: GT
NOX 0 per MWh
SO2 0.2 per MWh
CO2 120 per MWh

16-7
17. GEOTHERMAL BINARY (BINARY)

17.1MECHANICAL EQUIPMENT AND SYSTEMS


The Geothermal Binary (“Binary”) Facility produces 50 MW net of electricity. The Binary
Facility consists primarily of three heat recovery systems. These heat recovery systems operate
on a closed looped organic supercritical Rankine cycle using geothermal brine as a heat source,
with a brine temperature approximately 275°F. Cycle heat rejection will be provided through
three cooling towers. After supplying the three heat recovery systems with hot water, the
geothermal brine will be re-injected into the resource at approximately 140°F through injection
wells.
The heat recovery systems are equipped with a multistage, radial inflow turbo-expander
generator unit. The turbo-expander is designed for a supercritical refrigerant inlet pressure and
temperature. Each turbo-expander unit has a design output (gross) of approximately 10,000 kW.
Refrigerant is pumped from the condenser to the evaporators in each heat recovery system by
means of a single high pressure vertical turbine pump.
FIGURE 17-1 – GT DESIGN CONFIGURATION

17.2ELECTRICAL AND CONTROL SYSTEMS


There are to be three turbine generators at the Binary Facility. Each turbine generator is to be an
air cooled unit with static excitation designed for operation at 60 Hz, three-phase and 12.5 kV.
Each turbine generator is to be rated for 18 MW with a power factor range of 0.85 lagging.
The three turbine generators are to be connected to a single GSU connected through a generator
circuit breaker and a switchgear main circuit breaker and underground cable to a switch on a
common open air bus in the Binary Facility substation.

17-1
17.3OFF-SITE REQUIREMENTS
Since the Binary Facility is fueled by a renewable, underground fuel source, an off-site fuel
source, other than incidental plant heating is not required. Water for all processes at the Binary
Facility is obtained from one of several available water sources; however, due to the geography
of most geothermal power plants, water is sourced from on-site wells. Processed wastewater is
generally re-injected, if wells are the source of water, though many Binary facilities utilize ZLD.
Further, the electrical interconnection from the Binary Facility is accomplished by
interconnecting via the plant switchyard into the utility high-voltage transmission system.

17.4CAPITAL COST ESTIMATE


The base Cost Estimate for the Binary Facility with a nominal capacity of 50 MW is $4,141/kW.
Table 17-1 summarizes the Cost Estimate categories for the Binary Facility.
TABLE 17-1 – BASE PLANT SITE CAPITAL COST ESTIMATE FOR GT
Technology: GT
Nominal Capacity (ISO): 50,000 kW
Nominal Heat Rate (ISO): N/A Btu/kWh-HHV

Capital Cost Category (000s) (October 1, 2010$)

Civil Structural Material and Installation 6,760

Mechanical Equipment Supply and


Installation (and well costs) 107,545

Electrical / I&C Supply and Installation 13,345

Project Indirects (1) 29,000

EPC Cost before Contingency and Fee 156,650

Fee and Contingency 18,798

Total Project EPC 175,448

Owner Costs (excluding project finance) 31,598

Total Project Cost (excluding finance) 207,046

Total Project EPC / kW 3,509

Owner Costs 18% (excluding project finance) / kW 632

Total Project Cost (excluding project finance) / kW 4,141

(1) Includes engineering, distributable costs, scaffolding, construction management, and start-up.

17-2
For this type of technology and power plant configuration, our regional adjustments took into
consideration the following: seismic design differences, local technical enhancements
(e.g., additional noise remediation that is generally required in urban siting), remote location
issues, labor wage and productivity differences, location adjustments, and the increase in
overheads associated with these five adjustments. It was assumed that geothermal facilities
would only be considered in 13 states: Alaska, Arizona, California, Colorado, Florida, Hawaii,
Idaho, Nevada, New Mexico, Oregon, Utah, Washington, and Wyoming.
Seismic design differences among the various locations were based on U.S. seismic map
information that detailed the various seismic zones throughout the U.S. No cost increases were
associated with seismic Zone 0 and cost step increases were considered for Zones 1, 2, 3 and 4.
Remote location issues are related to geographic areas that typically require installation of man
camps, higher craft incentives, and higher per diems are generally required with respect to
construction, due to the fact that such areas are long distances from urban areas, where labor is
generally abundant. Remote location designations were also considered in locations where
higher equipment freight costs are typically incurred, which for example are regions not near
established rail or highway access. Remote locations related to the Geothermal Facility include
Fairbanks, Alaska; Honolulu, Hawaii; Albuquerque, New Mexico; and Cheyenne, Wyoming.
Labor wage and productivity differences were handled as discussed in Section 2.5.1, taking into
consideration the amount of labor we estimated for the GT Facility.
Location adjustments were made to locations where higher cost of living levels are incurred
and/or where population density generally correlates to higher construction costs for power and
other infrastructure projects. These locations include Alaska, California, Hawaii, and Wyoming.
Table 17-2 presents the GT Facility capital cost variations for alternative U.S. plant locations.

17-3
TABLE 17-2 – LOCATION-BASED COSTS FOR GT
(OCTOBER 1, 2010 DOLLARS)
Base
Project Location Delta Cost Total Location
Cost Percent Difference Project Cost
State City ($/kW) Variation ($/kW) ($/kW)
Alaska Anchorage 4,140 17.1% 710 4,850
Alaska Fairbanks 4,140 26.0% 1,075 5,215
Alabama Huntsville 0 0.0% 0 0
Arizona Phoenix 4,140 -3.0% (125) 4,015
Arkansas Little Rock 0 0.0% 0 0
California Los Angeles 4,140 6.5% 270 4,410
California Redding 4,140 2.1% 88 4,228
California Bakersfield 4,140 3.1% 127 4,267
California Sacramento 4,140 5.4% 222 4,362
California San Francisco 4,140 13.4% 553 4,693
Colorado Denver 4,140 -2.7% (112) 4,028
Connecticut Hartford 0 0.0% 0 0
Delaware Dover 0 0.0% 0 0
District of Columbia Washington 0 0.0% 0 0
Florida Tallahassee 0 0.0% 0 0
Florida Tampa 0 0.0% 0 0
Georgia Atlanta 0 0.0% 0 0
Hawaii Honolulu 4,140 28.5% 1,178 5,318
Idaho Boise 4,140 -2.5% (105) 4,035
Illinois Chicago 0 0.0% 0 0
Indiana Indianapolis 0 0.0% 0 0
Iowa Davenport 0 0.0% 0 0
Iowa Waterloo 0 0.0% 0 0
Kansas Wichita 0 0.0% 0 0
Kentucky Louisville 0 0.0% 0 0
Louisiana New Orleans 0 0.0% 0 0
Maine Portland 0 0.0% 0 0
Maryland Baltimore 0 0.0% 0 0
Massachusetts Boston 0 0.0% 0 0
Michigan Detroit 0 0.0% 0 0
Michigan Grand Rapids 0 0.0% 0 0
Minnesota St. Paul 0 0.0% 0 0
Mississippi Jackson 0 0.0% 0 0
Missouri St. Louis 0 0.0% 0 0
Missouri Kansas City 0 0.0% 0 0
Montana Great Falls 0 0.0% 0 0
Nebraska Omaha 0 0.0% 0 0
New Hampshire Concord 0 0.0% 0 0
New Jersey Newark 0 0.0% 0 0

17-4
Base
Project Location Delta Cost Total Location
Cost Percent Difference Project Cost
State City ($/kW) Variation ($/kW) ($/kW)
New Mexico Albuquerque 4,140 -1.8% (76) 4,064
New York New York 0 0.0% 0 0
New York Syracuse 0 0.0% 0 0
Nevada Las Vegas 4,140 3.6% 150 4,290
North Carolina Charlotte 0 0.0% 0 0
North Dakota Bismarck 0 0.0% 0 0
Ohio Cincinnati 0 0.0% 0 0
Oregon Portland 4,140 2.0% 81 4,221
Pennsylvania Philadelphia 0 0.0% 0 0
Pennsylvania Wilkes-Barre 0 0.0% 0 0
Rhode Island Providence 0 0.0% 0 0
South Carolina Spartanburg 0 0.0% 0 0
South Dakota Rapid City 0 0.0% 0 0
Tennessee Knoxville 0 0.0% 0 0
Texas Houston 0 0.0% 0 0
Utah Salt Lake City 4,140 -2.9% (118) 4,022
Vermont Burlington 0 0.0% 0 0
Virginia Alexandria 0 0.0% 0 0
Virginia Lynchburg 0 0.0% 0 0
Washington Seattle 4,140 3.8% 158 4,298
Washington Spokane 4,140 -1.7% (72) 4,068
West Virginia Charleston 0 0.0% 0 0
Wisconsin Green Bay 0 0.0% 0 0
Wyoming Cheyenne 4,140 -2.6% (106) 4,034
Puerto Rico Cayey 0 0.0% 0 0

17.5O&M ESTIMATE
In addition to the general items discussed in the section of this report entitled O&M Estimate, the
Binary Facility includes major maintenance on the turbines, electric generator (each
approximately every six years) and well field maintenance, which can vary depending on the
Binary Facility resource. Table 17-3 presents the FOM and VOM expenses for the Binary
Facility.
TABLE 17-3 – O&M EXPENSES FOR BINARY
Technology: GT
Fixed O&M Expense $43.82/kW-year
Variable O&M Expense $5.15/MWh

17-5
17.6ENVIRONMENTAL COMPLIANCE INFORMATION
Table 17-4 presents environmental emissions for the Binary Facility.
TABLE 17-4 – ENVIRONMENTAL EMISSIONS FOR BINARY
Technology: Binary
NOX 0 per MWh
SO2 0.2 per MWh
CO2 120 per MWh

17-6
18. MUNICIPAL SOLID WASTE (MSW)

18.1MECHANICAL EQUIPMENT AND SYSTEMS


The MSW Facility processes approximately 2,000 tons per day of MSW and produces
approximately 50 MW. Three refuse-fired boilers are installed, which incorporate the Marin
mass-burning technology and grates specifically designed for combusting waste having an HHV
between 4,000 and 6,500 Btu/lb. The three boilers together produce approximately 450,000 lb/hr
of 900 psia steam.
Grapple cranes are used to transfer solid waste from a storage pit to loading chutes, where
hydraulically operated feeds push the MSW onto the grates at a rate determined by the
combustion control system. The Martin grates are constructed as assemblies of modular grate
units. The units are driven by hydraulic systems to provide a reverse reciprocating motion of the
grates, which move the burning refuse along the length of the downward sloped grate. At the
end of its travel along the grate, the MSW is completely combusted, and the remaining ash
residue falls into a proprietary Martin ash residue discharger, which receives the combustion
residue and cools it in a quench chamber. The fly ash from the dry flue gas scrubber and fabric
filter baghouse is conveyed to the ash discharger where it is combined with the bottom ash and
quenched. After being quenched, the combined ash residue is pushed up an inclined
draining/drying chute. Excess water from the residue drains back into the quench bath. The
residue, containing sufficient moisture to prevent dusting, is transferred by a conveyor to a
residue storage pit. Clamshell grapple cranes transport the residue to a scalper screen. The
scalper screen extracts pieces of the residue larger than a certain size in order to protect the
downstream equipment. The smaller material which passes through the scalper screen is fed
onto a conveyer belt which discharges onto a vibrating feeder. The vibrating feeder passes the
residue beneath a magnetic drum to separate ferrous material from the ash. Non-magnetic
residue falls onto a distribution conveyor for distribution to a transport vehicle. Ferrous material
is conveyed to a rotating trommel screen for cleaning, after which it is conveyed to a roll-off
container.
Each boiler is equipped with a dry flue gas scrubber in combination with a reverse air fabric
filter baghouse. The dry scrubbers remove the acid gases (mainly SO2, hydrochloric acid and
hydrofluoric acid) from the flue gas. A hydrated lime injection system prior to the dry scrubber
augments the AGR capability of the system. The reverse air baghouse reduces dioxin/furan and
particulate emissions. The facility also uses selective non-catalytic reduction (“SNCR”) for NOX
control, and activated carbon injection for mercury control.
Steam from the boilers is used to drive a single condensing ST for the production of
approximately 50 MW of net electricity. The ST exhausts to a water-cooled condenser which
receives circulating cooling water from an evaporative-type cooling tower. The ST includes
extraction taps to provide steam for feedwater heating, air preheating and other miscellaneous
steam requirements. The MSW process flow diagram at a high level is similar to the pulverized
coal flow diagram, except that the fuel source is MSW, rather than coal (see Figure 3-1).
The MSW process flow diagram at a high level is similar to the pulverized coal flow diagram,
except that the fuel source is MSW, rather than coal.

18-1
18.2ELECTRICAL AND CONTROL SYSTEMS
The MSW Facility has one ST electric generator. The generator is a 60 Hz machine rated at
approximately 70 MVA with an output voltage of 13.8 kV. The ST electric generator is
connected to a high-voltage bus in the facility switchyard via a dedicated generator circuit
breaker, GSU, high-voltage circuit breaker and a disconnect switch. The GSU increases the
voltage from the electric generator from 13.8 kV to interconnected transmission system high
voltage.
The MSW Facility is controlled using a DCS. The DCS provides centralized control of the
facility by integrating the control systems provided with the boiler, ST and associated electric
generator, and the control of BOP systems and equipment.

18.3OFF-SITE REQUIREMENTS
MSW is delivered to the facility via rail, truck or barge. Water for all processes at the
MSW Facility can be obtained from one of a variety of sources. The MSW Facility uses a water
treatment system and a high-efficiency reverse osmosis system to reduce the dissolved solids
from the cooling water and to provide distilled water for boiler make-up. Wastewater is sent to a
municipal wastewater system or other approved alternative. Further, the electrical
interconnection from the MSW Facility on-site switchyard is effectuated by a connection to an
adjacent utility substation.

18.4CAPITAL COST ESTIMATE


The base Cost Estimate for the MSW Facility with a nominal capacity of 50 MW is $8,232/kW.
Table 18-1 summarizes the Cost Estimate categories for the GT Facility.

18-2
TABLE 18-1 – BASE PLANT SITE CAPITAL COST ESTIMATE FOR MSW
Technology: MSW
Nominal Capacity (ISO): 50,000 kW
Nominal Heat Rate (ISO): 18,000 Btu/kWh-HHV

Capital Cost Category (000s) (October 1, 2010$)

Civil Structural Material and Installation 33,875

Mechanical Equipment Supply and


Installation 183,000

Electrical / I&C Supply and Installation 25,300

Project Indirects (1) 56,080

EPC Cost before Contingency and Fee 298,255

Fee and Contingency 44,738

Total Project EPC 342,993

Owner Costs (excluding project finance) 68,599

Total Project Cost (excluding finance) 411,592

Total Project EPC / kW 6,860

Owner Costs 20% (excluding project finance) / kW 1,372

Total Project Cost (excluding project finance) / kW 8,232

(1) Includes engineering, distributable costs, scaffolding, construction management, and start-up.

For this type of technology and power plant configuration, our regional adjustments took into
consideration the following: seismic design differences, local enhancements, remote location
issues, labor wage and productivity differences, location adjustments, and the increase in
overheads associated with these five adjustments.
Seismic design differences among the various locations were based on U.S. seismic map
information that detailed the various seismic zones throughout the U.S. No cost increases were
associated with seismic Zone 0 and cost step increases were considered for Zones 1, 2, 3 and 4.
Remote location issues are related to geographic areas that typically require installation of man
camps, higher craft incentives, and higher per diems are generally required with respect to
construction, due to the fact that such areas are long distances from urban areas, where labor is
generally abundant. Remote location designations were also considered in locations where
higher equipment freight costs are typically incurred, which for example are regions not near
established rail or highway access. Remote locations related to the MSW Facility include

18-3
Fairbanks, Alaska; Honolulu, Hawaii; Albuquerque, New Mexico; Cheyenne, Wyoming; and
Cayey, Puerto Rico.
Labor wage and productivity differences were handled as discussed in Section 2.5.1, taking into
consideration the amount of labor we estimated for the MSW Facility.
Location adjustments were made to locations where higher cost of living levels are incurred
and/or where population density generally correlates to higher construction costs for power and
other infrastructure projects. These locations include Alaska, California, Connecticut, Delaware,
District of Columbia, Hawaii, Illinois, Maine, Maryland, Massachusetts, Michigan, Minnesota,
New York, Ohio, and Wisconsin.
Table 18-2 presents the MSW Facility capital cost variations for alternative U.S. plant locations.
TABLE 18-2 – LOCATION-BASED COSTS FOR MSW
(OCTOBER 1, 2010 DOLLARS)
Base
Project Location Delta Cost Total Location
Cost Percent Difference Project Cost
State City ($/kW) Variation ($/kW) ($/kW)
Alaska Anchorage 8,240 12.8% 1,054 9,294
Alaska Fairbanks 8,240 17.7% 1,459 9,699
Alabama Huntsville 8,240 -5.8% (474) 7,766
Arizona Phoenix 8,240 -4.5% (371) 7,869
Arkansas Little Rock 8,240 -4.7% (387) 7,853
California Los Angeles 8,240 5.2% 430 8,670
California Redding 8,240 1.9% 154 8,394
California Bakersfield 8,240 2.1% 176 8,416
California Sacramento 8,240 5.7% 472 8,712
California San Francisco 8,240 13.4% 1,104 9,344
Colorado Denver 8,240 -4.7% (384) 7,856
Connecticut Hartford 8,240 5.2% 429 8,669
Delaware Dover 8,240 3.1% 258 8,498
District of Columbia Washington 8,240 1.7% 140 8,380
Florida Tallahassee 8,240 -7.9% (649) 7,591
Florida Tampa 8,240 -3.3% (268) 7,972
Georgia Atlanta 8,240 -6.3% (515) 7,725
Hawaii Honolulu 8,240 19.9% 1,638 9,878
Idaho Boise 8,240 -3.8% (315) 7,925
Illinois Chicago 8,240 12.5% 1,033 9,273
Indiana Indianapolis 8,240 -0.9% (78) 8,162
Iowa Davenport 8,240 -1.0% (79) 8,161
Iowa Waterloo 8,240 -6.7% (548) 7,692
Kansas Wichita 8,240 -5.4% (446) 7,794
Kentucky Louisville 8,240 -4.8% (392) 7,848
Louisiana New Orleans 8,240 -7.3% (603) 7,637
Maine Portland 8,240 -4.1% (341) 7,899
Maryland Baltimore 8,240 -1.7% (144) 8,096

18-4
Base
Project Location Delta Cost Total Location
Cost Percent Difference Project Cost
State City ($/kW) Variation ($/kW) ($/kW)
Massachusetts Boston 8,240 11.8% 975 9,215
Michigan Detroit 8,240 2.7% 220 8,460
Michigan Grand Rapids 8,240 -5.8% (475) 7,765
Minnesota St. Paul 8,240 2.3% 190 8,430
Mississippi Jackson 8,240 -5.7% (471) 7,769
Missouri St. Louis 8,240 3.0% 247 8,487
Missouri Kansas City 8,240 1.8% 150 8,390
Montana Great Falls 8,240 -4.0% (333) 7,907
Nebraska Omaha 8,240 -3.0% (243) 7,997
New Hampshire Concord 8,240 -2.0% (166) 8,074
New Jersey Newark 8,240 11.9% 984 9,224
New Mexico Albuquerque 8,240 -3.5% (287) 7,953
New York New York 8,240 26.3% 2,167 10,407
New York Syracuse 8,240 -0.4% (31) 8,209
Nevada Las Vegas 8,240 4.5% 370 8,610
North Carolina Charlotte 8,240 -8.3% (688) 7,552
North Dakota Bismarck 8,240 -5.6% (463) 7,777
Ohio Cincinnati 8,240 -3.1% (256) 7,984
Oregon Portland 8,240 1.7% 136 8,376
Pennsylvania Philadelphia 8,240 8.5% 698 8,938
Pennsylvania Wilkes-Barre 8,240 -3.4% (283) 7,957
Rhode Island Providence 8,240 2.8% 229 8,469
South Carolina Spartanburg 8,240 -9.5% (786) 7,454
South Dakota Rapid City 8,240 -7.9% (654) 7,586
Tennessee Knoxville 8,240 -7.3% (603) 7,637
Texas Houston 8,240 -7.3% (598) 7,642
Utah Salt Lake City 8,240 -4.9% (401) 7,839
Vermont Burlington 8,240 -4.4% (364) 7,876
Virginia Alexandria 8,240 -1.8% (148) 8,092
Virginia Lynchburg 8,240 -5.1% (420) 7,820
Washington Seattle 8,240 4.1% 342 8,582
Washington Spokane 8,240 -2.8% (228) 8,012
West Virginia Charleston 8,240 -1.6% (135) 8,105
Wisconsin Green Bay 8,240 -2.3% (186) 8,054
Wyoming Cheyenne 8,240 -4.6% (383) 7,857
Puerto Rico Cayey 8,240 -1.7% (144) 8,096

18.5O&M ESTIMATE
In addition to the general items discussed in the section of this report entitled O&M Estimate, the
MSW Facility includes major maintenance for the feedstock handling, ST, electric generator,
boiler, and BOP systems. Table 18-3 presents the O&M expenses for the MSW Facility.

18-5
TABLE 18-3 – O&M EXPENSES FOR MSW
Technology: MSW
Fixed O&M Expense $373.76/kW-year
Variable O&M Expense $8.33/MWh

18.6ENVIRONMENTAL COMPLIANCE INFORMATION


As mentioned above in the section on mechanical systems, each boiler is equipped with a dry
flue gas scrubber in combination with a reverse air fabric filter baghouse. A hydrated lime
injection system prior to the dry scrubber augments the AGR capability of the system. The
reverse air baghouse reduces dioxin/furan and particulate emissions, an SNCR is used for NOX
control, and activated carbon injection is used for mercury control. Table 18-4 presents
environmental emissions for the MSW Facility.
TABLE 18-4 – ENVIRONMENTAL EMISSIONS FOR MSW
Technology: MSW
NOX 0.27 lb/MMBtu
SO2 0.07 lb/MMBtu
CO2 200 lb/MMBtu

18-6
19. HYDROELECTRIC (HY)

19.1MECHANICAL EQUIPMENT AND SYSTEMS


The 500 MW Hydroelectric (“HY”) Facility is composed of two 250 MW vertical shaft Francis
turbine generator units with a minimum of 650 feet (200 meters) of head. Figure 19-1 presents
the HY process flow diagram.
FIGURE 19-1 – HY DESIGN CONFIGURATION

19.2ELECTRICAL AND CONTROL SYSTEMS


The HY Facility has two synchronous electric generators. Each generator is a 60 Hz machine
rated at approximately 300 MVA with an output voltage of approximately 23 kV. Each electric
generator is connected to a high-voltage bus in the facility switchyard via a dedicated generator
circuit breaker, GSU, high-voltage circuit breaker and a disconnect switch. In some instances,
the generator is connected directly to its GSU and connected through a disconnect switch
between two breakers on the high-voltage bus. The GSU increases the voltage from the electric
generator from 23 kV to interconnected transmission system high voltage.
The HY Facility is controlled using a DCS. The DCS provides centralized control of the facility
by integrating the control systems provided hydro-turbine and associated electric generator and
the control of BOP systems and equipment.

19.3OFF-SITE REQUIREMENTS
Since the fuel source for the HY Facility is renewable, the most important off-site requirement is
the electrical interconnection to the high-voltage transmission system of the utility, which can be
effectuated through the HY Facility switchyard.

19-1
19.4CAPITAL COST ESTIMATE
The base Cost Estimate for the HY Facility with a nominal capacity of 500 MW is $3,076/kW.
Table 19-1 summarizes the Cost Estimate categories for the HY Facility.
TABLE 19-1 – BASE PLANT SITE CAPITAL COST ESTIMATE FOR HY
Technology: HY
Nominal Capacity (ISO): 500,000 kW
Nominal Heat Rate (ISO): Not Applicable

Capital Cost Category (000s) (October 1, 2010$)

Civil Structural Material and Installation 634,250

Mechanical Equipment Supply and


Installation 253,000

Electrical / I&C Supply and Installation 77,600

Project Indirects (1) 174,500

EPC Cost before Contingency and Fee 1,139,350

Fee and Contingency 142,419

Total Project EPC 1,281,769

Owner Costs (excluding project finance) 256,354

Total Project Cost (excluding finance) 1,538,123

Total Project EPC / kW 2,564

Owner Costs 20% (excluding project finance) / kW 513

Total Project Cost (excluding project finance) / kW 3,076

(1) Includes engineering, distributable costs, scaffolding, construction management, and start-up.

For this type of technology and power plant configuration, our regional adjustments took into
consideration the following: seismic design differences, local technical enhancements
(e.g., additional noise remediation that is generally required in urban siting), remote location
issues, labor wage and productivity differences, location adjustments, and the increase in
overheads associated with these five adjustments. The assumption was made that hydroelectric
facilities would only be considered for construction in the states of Alaska, California, Colorado,
Connecticut, Idaho, Maine, Missouri, Montana, North Carolina, Ohio, Oregon, South Dakota,
and Washington.

19-2
Seismic design differences among the various locations were based on U.S. seismic map
information that detailed the various seismic zones throughout the U.S. No cost increases were
associated with seismic Zone 0 and cost step increases were considered for Zones 1, 2, 3 and 4.
The locations with local technical enhancements include California, Colorado, Connecticut, and
Delaware. These are areas where technical enhancements generally need to be made by a project
developer or utility to comply with the applicable permitting/siting requirements.
Remote location issues are related to geographic areas that typically require installation of man
camps, higher craft incentives, and higher per diems are generally required with respect to
construction, due to the fact that such areas are long distances from urban areas, where labor is
generally abundant. Remote location designations were also considered in locations where
higher equipment freight costs are typically incurred, which for example are regions not near
established rail or highway access. The remote location related to the Hydroelectric Facility is
Fairbanks, Alaska.
Labor wage and productivity differences were handled as discussed in Section 2.5.1, taking into
consideration the amount of labor we estimated for the HY Facility.
Location adjustments were made to locations where higher cost of living levels are incurred
and/or where population density generally correlates to higher construction costs for power and
other infrastructure projects. These locations include Alaska, California, Connecticut, Maine,
Ohio, and South Dakota.
Table 19-2 presents the HY Facility capital cost variations for alternative U.S. plant locations.

19-3
TABLE 19-2 – LOCATION-BASED COSTS FOR HY
(OCTOBER 1, 2010 DOLLARS)
Base
Project Location Delta Cost Total Location
Cost Percent Difference Project Cost
State City ($/kW) Variation ($/kW) ($/kW)
Alaska Anchorage 3,080 20.1% 619 3,699
Alaska Fairbanks 3,080 31.6% 974 4,054
Alabama Huntsville 0 0.0% 0 0
Arizona Phoenix 0 0.0% 0 0
Arkansas Little Rock 0 0.0% 0 0
California Los Angeles 3,080 7.4% 228 3,308
California Redding 3,080 2.8% 88 3,168
California Bakersfield 3,080 2.4% 75 3,155
California Sacramento 3,080 3.7% 113 3,193
California San Francisco 3,080 13.2% 408 3,488
Colorado Denver 3,080 -1.3% (40) 3,040
Connecticut Hartford 3,080 6.4% 197 3,277
Delaware Dover 0 0.0% 0 0
District of Columbia Washington 0 0.0% 0 0
Florida Tallahassee 0 0.0% 0 0
Florida Tampa 0 0.0% 0 0
Georgia Atlanta 0 0.0% 0 0
Hawaii Honolulu 0 0.0% 0 0
Idaho Boise 3,080 -1.6% (49) 3,031
Illinois Chicago 0 0.0% 0 0
Indiana Indianapolis 0 0.0% 0 0
Iowa Davenport 0 0.0% 0 0
Iowa Waterloo 0 0.0% 0 0
Kansas Wichita 0 0.0% 0 0
Kentucky Louisville 0 0.0% 0 0
Louisiana New Orleans 0 0.0% 0 0
Maine Portland 3,080 -0.8% (23) 3,057
Maryland Baltimore 0 0.0% 0 0
Massachusetts Boston 0 0.0% 0 0
Michigan Detroit 0 0.0% 0 0
Michigan Grand Rapids 0 0.0% 0 0
Minnesota St. Paul 0 0.0% 0 0
Mississippi Jackson 0 0.0% 0 0
Missouri St. Louis 3,080 1.3% 41 3,121
Missouri Kansas City 3,080 1.4% 42 3,122
Montana Great Falls 3,080 -1.2% (37) 3,043
Nebraska Omaha 0 0.0% 0 0
New Hampshire Concord 0 0.0% 0 0
New Jersey Newark 0 0.0% 0 0
New Mexico Albuquerque 0 0.0% 0 0

19-4
Base
Project Location Delta Cost Total Location
Cost Percent Difference Project Cost
State City ($/kW) Variation ($/kW) ($/kW)
New York New York 0 0.0% 0 0
New York Syracuse 0 0.0% 0 0
Nevada Las Vegas 0 0.0% 0 0
North Carolina Charlotte 0 0.0% 20 3,100
North Dakota Bismarck 0 0.0% 0 0
Ohio Cincinnati 3,080 -1.6% (49) 3,031
Oregon Portland 3,080 4.7% 145 3,225
Pennsylvania Philadelphia 0 0.0% 0 0
Pennsylvania Wilkes-Barre 0 0.0% 0 0
Rhode Island Providence 0 0.0% 0 0
South Carolina Spartanburg 0 0.0% 0 0
South Dakota Rapid City 3,080 -3.9% (119) 2,961
Tennessee Knoxville 0 0.0% 0 0
Texas Houston 0 0.0% 0 0
Utah Salt Lake City 0 0.0% 0 0
Vermont Burlington 0 0.0% 0 0
Virginia Alexandria 0 0.0% 0 0
Virginia Lynchburg 0 0.0% 0 0
Washington Seattle 3,080 3.5% 109 3,189
Washington Spokane 3,080 -1.0% (31) 3,049
West Virginia Charleston 0 0.0% 0 0
Wisconsin Green Bay 0 0.0% 0 0
Wyoming Cheyenne 0 0.0% 0 0
Puerto Rico Cayey 0 0.0% 0 0

19.5O&M ESTIMATE
In addition to the general items discussed in the section of the report entitled O&M Estimate, the
most significant differentiating O&M expenses for the HY Facility include dam and associated
civil major maintenance and hydro-turbine major maintenance, which are generally conducted
approximately every ten years. Because HY power plants are typically operated when available,
most operators consider a majority of O&M expenses for this technology to be fixed. Table 19-3
presents the O&M expenses for the HY Facility.
TABLE 19-3 – O&M EXPENSES FOR HY
Technology: HY
Fixed O&M Expense $13.44/kW-year
Variable O&M Expense $0/MWh

19.6ENVIRONMENTAL COMPLIANCE INFORMATION


The HY Facility does not burn a fuel and consequently there are no air emissions from this type
of plant. Table 19-4 presents environmental emissions for the HY Facility.

19-5
TABLE 19-4 – ENVIRONMENTAL EMISSIONS FOR HY
Technology: HY
NOX 0 lb/MMBtu
SO2 0 lb/MMBtu
CO2 0 lb/MMBtu

19-6
20. PUMPED STORAGE (PS)

20.1MECHANICAL EQUIPMENT AND SYSTEMS


The 250 MW Pumped Storage (“PS”) Facility is composed of two 125 MW Francis turbine
generator units. During off-peak hours, water is pumped from a lower reservoir to an upper
reservoir using electricity from the grid. During the generating cycle, water is discharged
through the reversible turbine generators to produce power. Figure 20-1 presents the PS process
flow diagram.
FIGURE 20-1 – PS DESIGN CONFIGURATION

20.2ELECTRICAL AND CONTROL SYSTEMS


The PS Facility has two synchronous electric generators that are also capable of being operated
as motors powered from the grid to provide the pumping function by driving the Francis
hydro-turbines in reverse. The generators are 60 Hz machines rated at approximately 150 MVA
with an output voltage of 13.8 kV to 24 kV. Each electric generator is connected to a high-
voltage bus in the facility switchyard via a dedicated generator circuit breaker, GSU,
high-voltage circuit breaker and a disconnect switch. The GSU increases the voltage from the
electric generator voltage to the interconnected transmission system high voltage.
The PS Facility is controlled using a DCS. The DCS provides centralized control of the facility
by integrating the control systems provided with the hydro-turbine and associated electric
generator and the control of BOP systems and equipment.

20.3OFF-SITE REQUIREMENTS
Similar to the HY Facility, since the fuel source for the PS Facility is renewable, the most
important off-site requirement is the electrical interconnection to the high-voltage transmission
system of the utility, which can be effectuated through the PS switchyard. Unlike the HY
Facility, which uses the backfeed from the utility transmission system only to run required plant

20-1
loads when the hydro-turbines are not operating, significant volumes of electricity are consumed
in off-peak hours at the PS Facility.

20.4CAPITAL COST ESTIMATE


The base Cost Estimate for the PS Facility with a nominal capacity of 250 MW is $5,595/kW.
Table 20-1 summarizes the Cost Estimate categories for the PS Facility. However, it should be
noted that the construction costs for future pumped storage power plants are strongly impacted
by the size (e.g., larger plants are most generally lower cost on a $/kW basis) and by the existing
infrastructure that may be leveraged in the development, design, and construction.
TABLE 20-1 – BASE PLANT SITE CAPITAL COST ESTIMATE FOR PS
Technology: PS
Nominal Capacity (ISO): 250,000 kW
Nominal Heat Rate (ISO): N/A Btu/kWh-HHV

Capital Cost Category (000s) (October 1, 2010$)

Civil Structural Material and Installation 653,000

Mechanical Equipment Supply and


Installation 152,400

Electrical / I&C Supply and Installation 73,700

Project Indirects (1) 171,100

EPC Cost before Contingency and Fee 1,050,200

Fee and Contingency 115,522

Total Project EPC 1,165,722

Owner Costs (excluding project finance) 233,144

Total Project Cost (excluding finance) 1,398,866

Total Project EPC / kW 4,663

Owner Costs 20% (excluding project finance) / kW 933

Total Project Cost (excluding project finance) / kW 5,595

(1) Includes engineering, distributable costs, scaffolding, construction management, and start-up.

For this type of technology and power plant configuration, our regional adjustments took into
consideration the following: seismic design differences, local technical enhancements, remote
location issues, labor wage and productivity differences, location adjustments, and the increase
in overheads associated with these five adjustments listed. While the analysis shown below

20-2
contemplates cost adjustment factors for each area considered, realistically, there are certain
areas that do not have enough elevation difference to cost effectively produce a pumped storage
plant.
Seismic design differences among the various locations were based on U.S. seismic map
information that detailed the various seismic zones throughout the U.S. No cost increases were
associated with seismic Zone 0 and cost step increases were considered for Zones 1, 2, 3 and 4.
The locations with local technical enhancements include California, Colorado, Connecticut,
Delaware, District of Columbia, Louisiana, Maryland, Massachusetts, New Jersey, New York,
Rhode Island, Vermont, and Virginia. These are areas where noise, visual impacts, and other
technical enhancements generally need to be made by a project developer or utility to comply
with the applicable permitting/siting requirements.
Remote location issues are related to geographic areas that typically require installation of man
camps, higher craft incentives, and higher per diems are generally required with respect to
construction, due to the fact that such areas are long distances from urban areas, where labor is
generally abundant. Remote location designations were also considered in locations where
higher equipment freight costs are typically incurred, which for example are regions not near
established rail or highway access. Remote locations related to the Pumped Storage Facility
include Fairbanks, Alaska; Honolulu, Hawaii; Albuquerque, New Mexico; Cheyenne, Wyoming;
and Cayey, Puerto Rico.
Labor wage and productivity differences were handled as discussed in Section 2.5.1., taking into
consideration the amount of labor we estimated for the PS Facility.
Location adjustments were made to locations where higher cost of living levels are incurred
and/or where population density generally correlates to higher construction costs for power and
other infrastructure projects. These locations include Alaska, California, Connecticut, Delaware,
District of Columbia, Hawaii, Illinois, Maine, Maryland, Massachusetts, Michigan, Minnesota,
New York, Ohio; and Wisconsin.
Table 20-2 presents the PS Facility capital cost variations for alternative U.S. plant locations.

20-3
TABLE 20-2 – LOCATION-BASED COSTS FOR PS
(OCTOBER 1, 2010 DOLLARS)
Base
Project Location Delta Cost Total Location
Cost Percent Difference Project Cost
State City ($/kW) Variation ($/kW) ($/kW)
Alaska Anchorage 5,595 17.6% 985 6,580
Alaska Fairbanks 5,595 24.7% 1,382 6,977
Alabama Huntsville 5,595 -7.4% (413) 5,182
Arizona Phoenix 5,595 -5.7% (322) 5,273
Arkansas Little Rock 5,595 -6.0% (335) 5,260
California Los Angeles 5,595 7.1% 398 5,993
California Redding 5,595 2.5% 141 5,736
California Bakersfield 5,595 3.0% 166 5,761
California Sacramento 5,595 7.5% 422 6,017
California San Francisco 5,595 17.8% 994 6,589
Colorado Denver 5,595 -5.9% (329) 5,266
Connecticut Hartford 5,595 7.0% 392 5,987
Delaware Dover 5,595 4.3% 243 5,838
District of Columbia Washington 5,595 2.8% 155 5,750
Florida Tallahassee 0 0 0 0
Florida Tampa 0 0 0 0
Georgia Atlanta 5,595 -8.0% (449) 5,146
Hawaii Honolulu 5,595 15.8% 883 6,478
Idaho Boise 5,595 -4.9% (273) 5,322
Illinois Chicago 5,595 16.2% 907 6,502
Indiana Indianapolis 5,595 -1.1% (64) 5,531
Iowa Davenport 5,595 -1.2% (66) 5,529
Iowa Waterloo 5,595 -8.5% (476) 5,119
Kansas Wichita 0 0 0 0
Kentucky Louisville 5,595 -6.1% (341) 5,254
Louisiana New Orleans 5,595 -9.3% (519) 5,076
Maine Portland 5,595 -5.2% (290) 5,305
Maryland Baltimore 5,595 -2.0% (110) 5,485
Massachusetts Boston 5,595 15.5% 869 6,464
Michigan Detroit 5,595 3.5% 196 5,791
Michigan Grand Rapids 5,595 -7.4% (413) 5,182
Minnesota St. Paul 5,595 3.0% 168 5,763
Mississippi Jackson 5,595 -7.3% (410) 5,185
Missouri St. Louis 5,595 4.0% 222 5,817
Missouri Kansas City 5,595 2.4% 136 5,731
Montana Great Falls 5,595 -5.1% (286) 5,309
Nebraska Omaha 5,595 -3.7% (209) 5,386
New Hampshire Concord 5,595 -2.5% (140) 5,455
New Jersey Newark 5,595 15.5% 867 6,462
New Mexico Albuquerque 5,595 -4.4% (245) 5,350

20-4
Base
Project Location Delta Cost Total Location
Cost Percent Difference Project Cost
State City ($/kW) Variation ($/kW) ($/kW)
New York New York 5,595 34.3% 1,921 7,516
New York Syracuse 5,595 -0.2% (13) 5,582
Nevada Las Vegas 5,595 5.8% 326 5,921
North Carolina Charlotte 5,595 -10.7% (599) 4,996
North Dakota Bismarck 5,595 -7.1% (399) 5,196
Ohio Cincinnati 5,595 -3.9% (220) 5,375
Oregon Portland 5,595 3.1% 171 5,766
Pennsylvania Philadelphia 5,595 11.0% 615 6,210
Pennsylvania Wilkes-Barre 5,595 -4.3% (243) 5,352
Rhode Island Providence 5,595 3.7% 209 5,804
South Carolina Spartanburg 5,595 -12.2% (684) 4,911
South Dakota Rapid City 5,595 -10.2% (569) 5,026
Tennessee Knoxville 5,595 -9.4% (526) 5,069
Texas Houston 5,595 -9.3% (523) 5,072
Utah Salt Lake City 5,595 -6.2% (344) 5,251
Vermont Burlington 5,595 -5.5% (309) 5,286
Virginia Alexandria 5,595 -2.2% (121) 5,474
Virginia Lynchburg 5,595 -6.5% (366) 5,229
Washington Seattle 5,595 5.4% 305 5,900
Washington Spokane 5,595 -3.5% (197) 5,398
West Virginia Charleston 5,595 -2.0% (114) 5,481
Wisconsin Green Bay 5,595 -2.8% (157) 5,438
Wyoming Cheyenne 5,595 -5.8% (324) 5,271
Puerto Rico Cayey 5,595 -1.7% (95) 5,500

20.5O&M ESTIMATE
The O&M discussion in Section 17.5, related to the HY Facility at a high-level is applicable to
the PS Facility, including the fact that most operators budget for a given PS facility on a FOM
expense basis only. The additional areas of O&M that are applicable to the PS Facility that are
not applicable to the HY Facility are pump and associated motor maintenance. Table 20-3
presents the O&M expenses for the PS Facility.
TABLE 20-3 – O&M EXPENSES FOR PS
Technology: PS
Fixed O&M Expense $13.03/kW-year
Variable O&M Expense $0/MWh

20.6ENVIRONMENTAL COMPLIANCE INFORMATION


The PS Facility does not directly burn a fuel and consequently there are no air emissions from
this type of plant. Note that the fuel used to power the off-peak energy market, allowing
off-peak pumping to the reservoir, is not considered in this report. Table 20-4 presents
environmental emissions for the PS Facility.

20-5
TABLE 20-4 – ENVIRONMENTAL EMISSIONS FOR PS
Technology: PS
NOX 0 lb/MMBtu
SO2 0 lb/MMBtu
CO2 0 lb/MMBtu

20-6
21. ONSHORE WIND (WN)

21.1MECHANICAL EQUIPMENT AND SYSTEMS


The Onshore Wind (“WN”) Facility is based on 67 wind turbine generators (“WTGs”), each with
a rated capacity of 1.5 MW. The total design capacity is 100 MW.

The turbines are each supported by a conical steel tower, which is widest at the base and tapers
in diameter just below the nacelle. A foundation provides the tower with a firm anchor to the
ground. The nacelle is attached to the top of the tower and contains the main mechanical
components of the wind turbine, which include a variable-speed generator, transmission, and
yaw drive. The rotor hub connects to the transmission through one end of the nacelle, and the
rotor is then connected to the hub. The WTG has a three-bladed rotor with a diameter of
77 meters. The WTG has an active yaw system in the nacelle to keep the rotor facing into the
wind.
Power is generated by the wind turbines, then converted using an onboard transformer to
34.5 kV AC. It is then delivered to a collection system at the base of each turbine. Power from
all turbines will be collected by the underground collection circuit.
The collection system supplies power to a new substation designed to step up the voltage to
115 kV for interconnection with the transmission system. Other facility components include
access roads, an O&M building and electrical interconnection facilities. Figure 21-1 presents a
picture of a typical WN Facility.
FIGURE 21-1 – WN DESIGN CONFIGURATION

21-1
21.2ELECTRICAL AND CONTROL SYSTEMS
The WN Facility has 67 wind turbine-driven electric generators. Each generator is a doubly-fed
induction generator that feeds an AC/DC/AC power converter that provides an output of
three-phase, 60 Hz electrical power. The power output available is approximately 1.75 MVA
with an output voltage of 575 V stepped up to 34.5 kV using a pad-mounted transformer at the
base of the wind turbine. The wind turbine transformers are interconnected on one or more
underground collector circuits that are connected to a collector bus through a circuit breaker for
each circuit. The collector bus is connected to a high-voltage transmission system through the
facility substation, which includes a 34.5 kV switch or circuit breaker, GSU, high-voltage circuit
breaker, and a disconnect switch. The GSU increases the voltage from the electric generator
from 34.5 kV to interconnected transmission system high voltage.
The WN Facility is controlled using a control system generally referred to as the wind farm
supervisory control and data acquisition (“SCADA”) system. The SCADA system provides
centralized control of the facility by integrating the control systems provided with each of the
wind turbines and the control of BOP systems and equipment.

21.3OFF-SITE REQUIREMENTS
Since wind uses a renewable fuel, the most significant off-site requirements are the construction
of and interconnection to roads and the electrical interconnection to the utility high-voltage
transmission system, as discussed in Section 19.2.

21.4CAPITAL COST ESTIMATE


The base Cost Estimate for the WN Facility with a nominal capacity of 100 MW is $2,400/kW.
Table 21-1 summarizes the Cost Estimate categories for the WN Facility.

21-2
TABLE 21-1 – LOCATION-BASED COSTS FOR WN
Technology: WN
Nominal Capacity (ISO): 100,000 kW
Nominal Heat Rate (ISO): N/A Btu/kWh-HHV

Capital Cost Category (000s) (October 1, 2010$)

Civil Structural Material and Installation 25,625

Mechanical Equipment Supply and


Installation 158,585

Electrical / I&C Supply and Installation 27,753

Project Indirects (1) 8,070

EPC Cost before Contingency and Fee 220,033

Fee and Contingency 10,000

Total Project EPC 230,033

Owner Costs (excluding project finance) 13,802

Total Project Cost (excluding finance) 243,835

Total Project EPC / kW 2,300

Owner Costs 6% (excluding project finance) / kW 138

Total Project Cost (excluding project finance) / kW 2,438

(1) Includes engineering, distributable costs, scaffolding, construction management, and start-up.

For this type of technology and power plant configuration, our regional adjustments took into
consideration the following: seismic design differences, remote location issues, labor wage and
productivity differences, location adjustments, and owner cost differences and the increase in
overheads associated with these five adjustments.
Seismic design differences among the various locations were based on U.S. seismic map
information that detailed the various seismic zones throughout the U.S. No cost increases were
associated with seismic Zone 0 and cost step increases were considered for Zones 1, 2, 3 and 4.
Remote location issues are related to geographic areas that typically require installation of man
camps, higher craft incentives, and higher per diems are generally required with respect to
construction, due to the fact that such areas are long distances from urban areas, where labor is
generally abundant. Remote location designations were also considered in locations where
higher equipment freight costs are typically incurred, which for example are regions not near
established rail or highway access. Remote locations related to the WN Facility include

21-3
Fairbanks, Alaska; Honolulu, Hawaii; Albuquerque, New Mexico; Cheyenne, Wyoming; and
Cayey, Puerto Rico.
Labor wage and productivity differences were handled as discussed in Section 2.5.1, taking into
consideration the amount of labor we estimated for the WN Facility.
Location adjustments were made to locations where higher cost of living levels are incurred
and/or where population density generally correlates to higher construction costs for power and
other infrastructure projects. These locations include Alaska, California, Connecticut, Delaware,
District of Columbia, Hawaii, Illinois, Maine, Maryland, Massachusetts, Michigan, Minnesota,
New York, Ohio, and Wisconsin.
Owner costs were reviewed based on the need for utility upgrades and/or infrastructure costs
such as new facility transmission lines to tie to existing utility transmission substations or
existing transmission lines.
Table 21-2 presents the WN Facility capital cost variations for alternative U.S. plant locations.
TABLE 21-2 – LOCATION-BASED COSTS FOR WN
(OCTOBER 1, 2010 DOLLARS)
Base
Project Location Delta Cost Total Location
Cost Percent Difference Project Cost
State City ($/kW) Variation ($/kW) ($/kW)
Alaska Anchorage 2,440 25.2% 615 3,055
Alaska Fairbanks 2,440 45.0% 1,099 3,539
Alabama Huntsville 2,440 -3.5% (86) 2,354
Arizona Phoenix 2,440 -2.4% (58) 2,382
Arkansas Little Rock 2,440 -2.5% (61) 2,379
California Los Angeles 2,440 12.4% 304 2,744
California Redding 2,440 8.2% 200 2,640
California Bakersfield 2,440 10.0% 243 2,683
California Sacramento 2,440 10.5% 257 2,697
California San Francisco 2,440 18.6% 453 2,893
Colorado Denver 2,440 2.2% 54 2,494
Connecticut Hartford 2,440 6.6% 162 2,602
Delaware Dover 2,440 4.6% 111 2,551
District of Columbia Washington 2,440 7.4% 182 2,622
Florida Tallahassee 2,440 -5.3% (128) 2,312
Florida Tampa 2,440 -2.2% (53) 2,387
Georgia Atlanta 2,440 -3.9% (94) 2,346
Hawaii Honolulu 2,440 27.4% 668 3,108
Idaho Boise 2,440 3.4% 83 2,523
Illinois Chicago 2,440 14.2% 346 2,786
Indiana Indianapolis 2,440 0.3% 8 2,448
Iowa Davenport 2,440 4.5% 111 2,551
Iowa Waterloo 2,440 0.7% 18 2,458
Kansas Wichita 2,440 1.9% 46 2,486
Kentucky Louisville 2,440 -2.9% (70) 2,370

21-4
Base
Project Location Delta Cost Total Location
Cost Percent Difference Project Cost
State City ($/kW) Variation ($/kW) ($/kW)
Louisiana New Orleans 2,440 -5.4% (132) 2,308
Maine Portland 2,440 6.4% 155 2,595
Maryland Baltimore 2,440 1.7% 41 2,481
Massachusetts Boston 2,440 11.1% 270 2,710
Michigan Detroit 2,440 2.7% 67 2,507
Michigan Grand Rapids 2,440 -3.2% (78) 2,362
Minnesota St. Paul 2,440 7.5% 183 2,623
Mississippi Jackson 2,440 -3.5% (85) 2,355
Missouri St. Louis 2,440 3.6% 88 2,528
Missouri Kansas City 2,440 1.7% 41 2,481
Montana Great Falls 2,440 3.9% 95 2,535
Nebraska Omaha 2,440 3.5% 86 2,526
New Hampshire Concord 2,440 5.3% 128 2,568
New Jersey Newark 2,440 10.5% 257 2,697
New Mexico Albuquerque 2,440 3.8% 93 2,533
New York New York 2,440 24.6% 600 3,040
New York Syracuse 2,440 0.8% 20 2,460
Nevada Las Vegas 2,440 9.0% 219 2,659
North Carolina Charlotte 2,440 -4.9% (120) 2,320
North Dakota Bismarck 2,440 2.1% 50 2,490
Ohio Cincinnati 2,440 -1.9% (47) 2,393
Oregon Portland 2,440 8.0% 196 2,636
Pennsylvania Philadelphia 2,440 6.1% 150 2,590
Pennsylvania Wilkes-Barre 2,440 -1.8% (44) 2,396
Rhode Island Providence 2,440 2.1% 51 2,491
South Carolina Spartanburg 2,440 -5.7% (140) 2,300
South Dakota Rapid City 2,440 0.7% 17 2,457
Tennessee Knoxville 2,440 -4.6% (111) 2,329
Texas Houston 2,440 -4.8% (118) 2,322
Utah Salt Lake City 2,440 3.7% 90 2,530
Vermont Burlington 2,440 3.4% 83 2,523
Virginia Alexandria 2,440 1.9% 46 2,486
Virginia Lynchburg 2,440 -3.1% (75) 2,365
Washington Seattle 2,440 4.4% 107 2,547
Washington Spokane 2,440 4.9% 120 2,560
West Virginia Charleston 2,440 -0.1% (3) 2,437
Wisconsin Green Bay 2,440 -1.0% (25) 2,415
Wyoming Cheyenne 2,440 4.3% 105 2,545
Puerto Rico Cayey 2,440 6.9% 167 2,607

21.5O&M ESTIMATE
In addition to the general items discussed in the section of the report entitled O&M Estimate, the
major areas for O&M for an Onshore Wind Facility include periodic gearbox, WTG, electric

21-5
generator, and associated electric conversion (e.g., GSU) technology repairs and replacement.
These devices typically undergo major maintenance every five to seven years. Table 21-3
presents the O&M expenses for the WN Facility.
TABLE 21-3 – O&M EXPENSES FOR WN
Technology: WN
Fixed O&M Expense $28.07/kW-year
Variable O&M Expense $0/MWh

21.6ENVIRONMENTAL COMPLIANCE INFORMATION


Since wind utilizes a renewable fuel and no additional fuel is combusted to make power from an
Onshore Wind Facility, air emissions are not created. Table 21-4 presents environmental
emissions for the WN Facility.
TABLE 21-4 – ENVIRONMENTAL EMISSIONS FOR WN
Technology: WN
NOX 0 lb/MMBtu
SO2 0 lb/MMBtu
CO2 0 lb/MMBtu

21-6
22. OFFSHORE WIND (WF)

22.1MECHANICAL EQUIPMENT AND SYSTEMS


The Offshore Wind (“WF”) Facility is based on 80 offshore WTGs, each with a rated capacity of
5.0 MW. The total design capacity is 400 MW.

The turbines are each supported by a conical steel tower, which is widest at the base and tapers
in diameter just below the nacelle. A foundation provides the tower with a firm anchor to the
ground. The nacelle is attached to the top of the tower and contains the main mechanical
components of the wind turbine, which include a variable-speed generator, transmission, and
yaw drive. The rotor hub connects to the transmission through one end of the nacelle, and the
rotor is then connected to the hub. The WTG has a three-bladed rotor with a diameter of
approximately 125 meters. The WTG has an active yaw system in the nacelle to keep the rotor
facing into the wind. The WF WTG is designed to withstand the conditions of the high seas,
including additional redundancy of key components to enhance availability, corrosion protection
and permanent monitoring.
Power is generated by the wind turbines, then converted using an onboard transformer to
34.5 kV AC. It is then delivered to a collection system at the base of each turbine. Power from
all turbines is collected by the underground collection circuit.
The collection system supplies power to a new substation designed to step up the voltage to
115 kV for interconnection with the transmission system. Figure 22-1 presents a picture of a
currently operating WF Facility.

22-1
FIGURE 22-1 – WF DESIGN CONFIGURATION

22.2ELECTRICAL AND CONTROL SYSTEMS


The WF Facility has 80 wind turbine-driven electric generators. Each generator is a doubly-fed
induction generator that feeds an AC/DC/AC power converter that provides an output of three-
phase, 60 Hz electrical power. The power output available is approximately 5.5 MVA with an
output voltage of 690 V stepped up to 34.5 kV using a transformer installed in the wind turbine
pylon. The wind turbine transformers are interconnected on one or more underwater collector
circuits trenched into the seabed that are connected to a collector bus (or several collector busses)
through a circuit breaker for each circuit. The collector bus is connected to a high-voltage
transmission system through the facility substation that includes a 34.5 kV switch or circuit
breaker, GSU, high-voltage circuit breaker and a disconnect switch. If there are multiple
collector busses this arrangement may be replicated for each bus. The GSU increases the voltage
from the electric generator from 34.5 kV to interconnected transmission system high voltage.
The WF Facility is controlled using a SCADA system. The SCADA system provides centralized
control of the facility by integrating the control systems provided with each of the wind turbines
and the control of BOP systems and equipment.

22.3OFF-SITE REQUIREMENTS
Similar to the WF Facility, the most significant off-site requirement for the WF Facility is the
electrical interconnection to the utility transmission system, as discussed directly above.

22-2
22.4CAPITAL COST ESTIMATE
The base Cost Estimate for the WF Facility with a nominal capacity of 400 MW is $5,975/kW.
Table 22-1 summarizes the Cost Estimate categories for the WF Facility.
TABLE 22-1 – BASE PLANT SITE CAPITAL COST ESTIMATE FOR WF
Technology: WF
Nominal Capacity (ISO): 400,000 kW
Nominal Heat Rate (ISO): N/A Btu/kWh-HHV

Capital Cost Category (000s) (October 1, 2010$)

Civil Structural Material and Installation 252,000

Mechanical Equipment Supply and


Installation 835,328

Electrical / I&C Supply and Installation 148,302

Project Indirects (1) 463,856

EPC Cost before Contingency and Fee 1,699,486

Fee and Contingency 212,436

Total Project EPC 1,911,922

Owner Costs (excluding project finance) 477,981

Total Project Cost (excluding finance) 2,389,903

Total Project EPC / kW 4,780

Owner Costs 25% (excluding project finance) / kW 1,195

Total Project Cost (excluding project finance) / kW 5,975

(1) Includes engineering, distributable costs, scaffolding, construction management, and start-up.

For this type of technology and power plant configuration, our regional adjustments took into
consideration the following: seismic design differences, remote location issues, labor wage and
productivity differences, location adjustments, owner cost differences, and the increase in
overheads associated with these five location adjustments. The assumption was made that
offshore wind projects would only be constructed offshore of the following states (where
significant offshore wind resource is available): Alaska, California, Connecticut, Delaware,
District of Columbia, Georgia, Hawaii, Illinois, Indiana, Maine, Maryland, Massachusetts,
Michigan, Minnesota, New Jersey, New York, North Carolina, Oregon, Rhode Island, South
Carolina, Texas, Virginia, Washington, Wisconsin and Puerto Rico.

22-3
Seismic design differences among the various locations were based on U.S. seismic map
information that detailed the various seismic zones throughout the U.S. No cost increases were
associated with seismic Zone 0 and cost step increases were considered for Zones 1, 2, 3 and 4.
Remote locations issues are related to geographic areas that typically require installation of man
camps, higher craft incentives, and higher per diems for construction, because such areas are
long distances from urban areas, where labor is generally abundant. Remote location
designations were also considered in locations where higher equipment freight costs are typically
incurred, which for example are regions not near established rail or highway access. Remote
locations related to the Offshore Wind Facility include Fairbanks, Alaska; Honolulu, Hawaii; and
Cayey, Puerto Rico.
Labor wage and productivity differences were handled as discussed in Section 2.5.1, taking into
consideration the amount of labor we estimated for the WF Facility.
Location adjustments were made to locations where higher cost of living levels are incurred
and/or where population density generally correlates to higher construction costs for power and
other infrastructure projects. These locations include Alaska, California, Connecticut, Delaware,
District of Columbia, Hawaii, Maine, Maryland, Massachusetts, New York, and Wisconsin.
Owner costs were reviewed based on the need for utility upgrades and/or infrastructure costs
such as new facility transmission lines to tie to existing utility transmission substations or
existing transmission lines.
Table 22-2 presents the WF Facility capital cost variations for alternative U.S. plant locations.

22-4
TABLE 22-2 – LOCATION-BASED COSTS FOR WF
(OCTOBER 1, 2010 DOLLARS)
Base
Project Location Delta Cost Total Location
Cost Percent Difference Project Cost
State City ($/kW) Variation ($/kW) ($/kW)
Alaska Anchorage 5,975 15.9% 952 6,927
Alaska Fairbanks 0 0.0%
Alabama Huntsville 0 0.0%
Arizona Phoenix 0 0.0%
Arkansas Little Rock 0 0.0%
California Los Angeles 5,975 7.7% 460 6,435
California Redding 0 0.0%
California Bakersfield 0 0.0%
California Sacramento 0 0.0%
California San Francisco 5,975 16.6% 993 6,968
Colorado Denver 0 0.0%
Connecticut Hartford 5,975 5.7% 342 6,317
Delaware Dover 5,975 3.1% 184 6,159
District of Columbia Washington 5,975 1.8% 110 6,085
Florida Tallahassee 0 0.0%
Florida Tampa 0 0.0%
Georgia Atlanta 5,975 -7.0% (418) 5,557
Hawaii Honolulu 5,975 14.5% 864 6,839
Idaho Boise 0 0.0%
Illinois Chicago 5,975 16.0% 958 6,933
Indiana Indianapolis 5,975 -1.0% (58) 5,917
Iowa Davenport 0 0.0%
Iowa Waterloo 0 0.0%
Kansas Wichita 0 0.0%
Kentucky Louisville 0 0.0%
Louisiana New Orleans 0 0.0%
Maine Portland 5,975 -2.6% (156) 5,819
Maryland Baltimore 5,975 -2.1% (126) 5,849
Massachusetts Boston 5,975 13.2% 787 6,762
Michigan Detroit 5,975 2.8% 165 6,140
Michigan Grand Rapids 5,975 -6.7% (403) 5,572
Minnesota St. Paul 5,975 4.8% 288 6,263
Mississippi Jackson 0 0.0%
Missouri St. Louis 0 0.0%
Missouri Kansas City 0 0.0%
Montana Great Falls 0 0.0%
Nebraska Omaha 0 0.0%
New Hampshire Concord 0 0.0%
New Jersey Newark 5,975 12.7% 761 6,736
New Mexico Albuquerque 0 0.0%

22-5
Base
Project Location Delta Cost Total Location
Cost Percent Difference Project Cost
State City ($/kW) Variation ($/kW) ($/kW)
New York New York 5,975 29.4% 759 7,734
New York Syracuse 5,975 -1.2% (69) 5,906
Nevada Las Vegas 0 0.0%
North Carolina Charlotte 5,975 -9.3% (557) 5,418
North Dakota Bismarck 0 0.0%
Ohio Cincinnati 0 0.0%
Oregon Portland 5,975 5.1% 302 6,277
Pennsylvania Philadelphia 0 0.0%
Pennsylvania Wilkes-Barre 0 0.0%
Rhode Island Providence 5,975 2.5% 48 6,123
South Carolina Spartanburg 5,975 -6.6% (391) 5,584
South Dakota Rapid City 0 0.0%
Tennessee Knoxville 0 0.0%
Texas Houston 5,975 -8.2% (487) 5,488
Utah Salt Lake City 0 0.0%
Vermont Burlington 0 0.0%
Virginia Alexandria 5,975 -2.7% (161) 5,814
Virginia Lynchburg 5,975 -5.7% (340) 5,635
Washington Seattle 5,975 4.8% 287 6,262
Washington Spokane 0 0.0%
West Virginia Charleston 0 0.0%
Wisconsin Green Bay 5,975 -2.7% (164) 5,811
Wyoming Cheyenne 0 0.0%
Puerto Rico Cayey 5,975 -1.2% (72) 5,903

22.5O&M ESTIMATE
The types of maintenance performed on the WF Facility are materially similar to the WN
Facility, discussed in Section 19.5; however, the expenses are higher because maintaining
offshore parts is considerably more complicated, due to staging on ships and with helicopters.
Table 22-3 presents the FOM and VOM expenses for the WF Facility.
TABLE 22-3 – O&M EXPENSES FOR WF
Technology: WF
Fixed O&M Expense $53.33/kW-year
Variable O&M Expense $0/MWh

22.6ENVIRONMENTAL COMPLIANCE INFORMATION


Since the WF Facility uses a renewable fuel and no additional fuel is combusted, there are no air
emissions. Table 22-4 presents environmental emissions for the WF Facility.

22-6
TABLE 22-4 – ENVIRONMENTAL EMISSIONS FOR WF
Technology: WF
NOX 0 lb/MMBtu
SO2 0 lb/MMBtu
CO2 0 lb/MMBtu

22-7
23. SOLAR THERMAL - CENTRAL STATION (SO)

23.1MECHANICAL EQUIPMENT AND SYSTEMS


The 100 MW Solar Thermal (“SO”) Facility uses a solar concentrating thermal process based on
direct steam, power towers, and heliostat mirror technology. The SO Facility incorporates a
Rankine-cycle reheat ST which receives steam from a solar steam generator and a solar
superheater and reheated steam from a solar reheater. The solar steam generator, solar
superheater, and solar reheater are all installed at the top of a tower adjacent to a power block
located at grade. The tower and power block are generally in the center of a heliostat solar field.
The solar energy heats water in the steam generator, superheater and reheat boiler to make steam
that runs the ST. The solar field and power generation equipment are started up each morning
after sunrise and insolation (or light intensity) build-up, and are shut down in the evening when
insolation drops below the level required for keeping the ST online.
A partial load natural gas-fired boiler is used for thermal input to the ST during the morning
start-up cycle. The boiler is also generally operated during transient cloudy conditions, in order
to keep the ST online and ready to resume production from solar thermal input, after the clouds
clear. After the cloud passes and solar-to-thermal input resumes, the ST will be returned to full
solar production and the gas-fired boiler is shut down. While permitting SO facilities with
respect to water usage continues to be a challenge, our base assumption is that the SO Facility
uses wet cooling technology.
The power block consists of one solar power tower and an ST with a reheat cycle, and it uses
typical auxiliary components for heat rejection, water treatment, water disposal, and
interconnection to the grid. Figure 23-1 presents a picture of a typical SO Facility.

23-1
FIGURE 23-1 – SO DESIGN CONFIGURATION

23.2ELECTRICAL AND CONTROL SYSTEMS


The SO Facility has one ST electric generator. The generator is a 60 Hz machine rated at
approximately 120 MVA with an output voltage of 13.8 kV. The ST electric generator is
connected to a high-voltage bus in the facility switchyard via a dedicated generator circuit
breaker, GSU, high-voltage circuit breaker and a disconnect switch. The GSU increases the
voltage from the electric generator from 13.8 kV to interconnected transmission system high
voltage.

23-2
The SO Facility is controlled using a DCS. The DCS provides centralized control of the facility
by integrating the control systems provided with the solar steam generator/superheater/reheater
system, ST and associated electric generator, and the control of BOP systems and equipment.

23.3OFF-SITE REQUIREMENTS
Natural gas is delivered to the facility through a lateral connected to the local natural gas trunk
line. Water for all processes at the SO Facility is obtained from a one of several available water
sources (e.g., municipal water supply); however, due to the remote location of most solar thermal
power plants, water is often sourced through on-site wells. The SO Facility uses a water
treatment system and a high-efficiency reverse osmosis system to reduce the dissolved solids
from the cooling water and to provide distilled water for HRSG make-up. Processed wastewater
is sent to a municipal wastewater system, re-injected on-site, or an on-site ZLD system. Further,
the electrical interconnection from the SO Facility on-site switchyard is effectuated by a
connection to an adjacent utility substation.

23.4CAPITAL COST ESTIMATE


The base Cost Estimate for the SO Facility with a nominal capacity of 100 MW is $4,692/kW.
Table 23-1 summarizes the Cost Estimate categories for the SO Facility.

23-3
TABLE 23-1 – BASE PLANT SITE CAPITAL COST ESTIMATE FOR SO
Technology: SO
Nominal Capacity (ISO): 100,000 kW
Nominal Heat Rate (ISO): N/A Btu/kWh-HHV (2)

Capital Cost Category (000s) (October 1, 2010$)

Civil Structural Material and Installation 48,475

Mechanical Equipment Supply and


Installation 254,250

Electrical / I&C Supply and Installation 40,750

Project Indirects (1) 39,500

EPC Cost before Contingency and Fee 382,975

Fee and Contingency 25,000

Total Project EPC 407,975

Owner Costs (excluding project finance) 61,196

Total Project Cost (excluding finance) 469,171

Total Project EPC / kW 4,080

Owner Costs 15% (excluding project finance) / kW 612

Total Project Cost (excluding project finance) / kW 4,692

(1) Includes engineering, distributable costs, scaffolding, construction management, and start-up.
(2) Does not include natural gas firing, as such usage is sporadic and highly dependent on time of year and
method of operation.

For this type of technology and power plant configuration, our regional adjustments took into
consideration the following: seismic design differences, remote location issues, labor wage and
productivity differences, location adjustments, owner cost differences, and the increase in
overheads associated with the previous five location adjustments.
Seismic design differences among the various locations were based on U.S. seismic map
information that detailed the various seismic zones throughout the U.S. No cost increases were
associated with seismic Zone 0 and cost step increases were considered for Zones 1, 2, 3 and 4.
Remote location issues are related to geographic areas that typically require installation of man
camps, higher craft incentives, and higher per diems are generally required with respect to
construction, due to the fact that such areas are long distances from urban areas, where labor is
generally abundant. Remote location designations were also considered in locations where
higher equipment freight costs are typically incurred, which for example are regions not near

23-4
established rail or highway access. Remote locations related to the Solar Thermal Facility
include Honolulu, Hawaii; Albuquerque, New Mexico; Cheyenne, Wyoming; and Cayey, Puerto
Rico.
Labor wage and productivity differences were handled as discussed in Section 2.5.1, taking into
consideration the amount of labor we estimated for the SO Facility.
Location adjustments were made to locations where higher cost of living levels are incurred
and/or where population density generally correlates to higher construction costs for power and
other infrastructure projects. These locations include Alaska, California, Connecticut, Delaware,
District of Columbia, Hawaii, Illinois, Maine, Maryland, Massachusetts, Michigan, Minnesota,
New York, Ohio, and Wisconsin.
Owner costs were reviewed based on the need for utility upgrades and/or infrastructure costs
such as new facility transmission lines to tie to existing utility transmission substations or
existing transmission lines.
Table 23-2 presents the SO Facility capital cost variations for alternative U.S. plant locations.

23-5
TABLE 23-2 – LOCATION-BASED COSTS FOR SO
(OCTOBER 1, 2010 DOLLARS)
Base
Project Location Delta Cost Total Location
Cost Percent Difference Project Cost
State City ($/kW) Variation ($/kW) ($/kW)
Alaska Anchorage 4,700 23.8% 1,119 5,819
Alaska Fairbanks 4,700 35.4% 1,662 6,362
Alabama Huntsville 4,700 -11.3% (532) 4,168
Arizona Phoenix 4,700 -8.9% (417) 4,283
Arkansas Little Rock 4,700 -9.3% (435) 4,265
California Los Angeles 4,700 11.4% 538 5,238
California Redding 4,700 6.3% 297 4,997
California Bakersfield 4,700 6.7% 316 5,016
California Sacramento 4,700 13.3% 623 5,323
California San Francisco 4,700 26.8% 1,261 5,961
Colorado Denver 4,700 -7.3% (344) 4,356
Connecticut Hartford 4,700 9.2% 431 5,131
Delaware Dover 4,700 4.7% 220 4,920
District of Columbia Washington 4,700 1.6% 74 4,774
Florida Tallahassee 4,700 -15.5% (727) 3,973
Florida Tampa 4,700 -6.4% (300) 4,400
Georgia Atlanta 4,700 -12.3% (578) 4,122
Hawaii Honolulu 4,700 39.8% 1,871 6,571
Idaho Boise 4,700 -4.8% (225) 4,475
Illinois Chicago 4,700 26.8% 1,262 5,962
Indiana Indianapolis 4,700 -1.9% (90) 4,610
Iowa Davenport 4,700 0.4% 20 4,720
Iowa Waterloo 4,700 -10.8% (505) 4,195
Kansas Wichita 4,700 -8.3% (392) 4,308
Kentucky Louisville 4,700 -9.4% (440) 4,260
Louisiana New Orleans 4,700 -15.9% (748) 3,952
Maine Portland 4,700 -5.9% (278) 4,422
Maryland Baltimore 4,700 -4.4% (209) 4,491
Massachusetts Boston 4,700 22.2% 1,043 5,743
Michigan Detroit 4,700 4.8% 224 4,924
Michigan Grand Rapids 4,700 -11.8% (554) 4,146
Minnesota St. Paul 4,700 7.2% 340 5,040
Mississippi Jackson 4,700 -11.2% (528) 4,172
Missouri St. Louis 4,700 5.7% 270 4,970
Missouri Kansas City 4,700 3.1% 144 4,844
Montana Great Falls 4,700 -5.3% (248) 4,452
Nebraska Omaha 4,700 -3.5% (165) 4,535
New Hampshire Concord 4,700 -1.7% (80) 4,620
New Jersey Newark 4,700 22.2% 1,042 5,742
New Mexico Albuquerque 4,700 -4.6% (217) 4,483

23-6
Base
Project Location Delta Cost Total Location
Cost Percent Difference Project Cost
State City ($/kW) Variation ($/kW) ($/kW)
New York New York 4,700 50.1% 2,355 7,055
New York Syracuse 4,700 -2.4% (114) 4,586
Nevada Las Vegas 4,700 11.5% 542 5,242
North Carolina Charlotte 4,700 -16.4% (772) 3,928
North Dakota Bismarck 4,700 -8.8% (412) 4,288
Ohio Cincinnati 4,700 -6.6% (310) 4,390
Oregon Portland 4,700 5.9% 277 4,977
Pennsylvania Philadelphia 4,700 16.1% 758 5,458
Pennsylvania Wilkes-Barre 4,700 -7.3% (341) 4,359
Rhode Island Providence 4,700 4.2% 196 4,896
South Carolina Spartanburg 4,700 -18.8% (882) 3,818
South Dakota Rapid City 4,700 -12.8% (604) 4,096
Tennessee Knoxville 4,700 -14.4% (677) 4,023
Texas Houston 4,700 -14.2% (670) 4,030
Utah Salt Lake City 4,700 -6.9% (325) 4,375
Vermont Burlington 4,700 -7.2% (338) 4,362
Virginia Alexandria 4,700 -4.8% (225) 4,475
Virginia Lynchburg 4,700 -10.0% (471) 4,229
Washington Seattle 4,700 8.0% 377 5,077
Washington Spokane 4,700 -2.7% (127) 4,573
West Virginia Charleston 4,700 -3.3% (155) 4,545
Wisconsin Green Bay 4,700 -4.9% (232) 4,468
Wyoming Cheyenne 4,700 -7.0% (320) 4,371
Puerto Rico Cayey 4,700 -4.0% (190) 4,510

23.5O&M ESTIMATE
The typical O&M expenses for the SO Facility include mirror cleaning, repair, and replacement;
thermal tube replacements; and BOP major maintenance. The BOP major maintenance is similar
to that which is performed on a combined-cycle plant: HRSG, ST, and electric generator major
maintenance, typically performed approximately every seven years. Additionally, most thermal
solar operators do not treat O&M on a variable basis, and consequently, all O&M expenses are
shown below on a fixed basis. Table 23-3 presents the O&M expenses for the SO Facility.
TABLE 23-3 – O&M EXPENSES FOR SO
Technology: SO
Fixed O&M Expense $64.00/kW-year
Variable O&M Expense $0/MWh

23.6ENVIRONMENTAL COMPLIANCE INFORMATION


Table 23-4 presents environmental emissions for the SO Facility.

23-7
TABLE 23-4 – ENVIRONMENTAL EMISSIONS FOR SO
Technology: SO
NOX 0 lb/MMBtu
SO2 0 lb/MMBtu
CO2 0 lb/MMBtu

23-8
24. PHOTOVOLTAIC (CENTRAL STATION) FACILITY (PV)

24.1MECHANICAL EQUIPMENT AND SYSTEMS


The following describes a nominally 7 MW Photovoltaic (“PV”) Facility. An analysis is also
provided for a nominally 150 MW PV Facility, which is essentially a significant expansion of the
7 MW Facility; however, a detailed technical description (due to the similarities with the 7 MW
Facility and the technology associated therewith) is not provided herein. The PV Facility uses
several ground-mounted, fixed-tilt semiconductor panels in an array to directly convert incident
solar radiation in the form of photons into DC electricity, which can then be inverted to AC.
Additional BOP components include metal racks and foundations to support fixed panels and
keep them aligned at the correct angle, a DC-to-AC inverter, AC and DC wiring, combiner boxes
where individual strings of panels are connected prior to being fed into the inverter, and a control
system to control and monitor output by adjusting the balance of voltage and current to yield
maximum power. Figure 22-1 presents a picture of a typical PV Facility.
FIGURE 24-1 – PV DESIGN CONFIGURATION

24.2ELECTRICAL AND CONTROL SYSTEMS


The PV Facility is comprised of 20 half-megawatt building blocks, each block consisting of
groups of PV cells connected to a 500 kW inverter module. Groups of PV cells, or modules, are
connected in parallel to a combiner box which contains a fuse for each module. The PV cells
create DC electricity. The cables are routed from the modules to a combiner box and a number

24-1
of combiner boxes are connected to the input of a 500 kW inverter module, which converts the
aggregate power from DC to three-phase AC electricity at an output voltage of 265 V. The
output voltage of the inverter modules is stepped up to a level of 13.8 kV through a series of
GSUs connected to the modules. Two modules are combined on each of transformer, each of
which is rated 1 MVA. The transformers are connected in groups to form circuits on an
underground collection system. The circuits are connected to a 13.8 kV circuit breaker and then
to the local utility distribution grid.
Each inverter module has its own integral control system. The aggregate of all the modules are
controlled through a SCADA system, typically provided by the inverter manufacturer.

24.3OFF-SITE REQUIREMENTS
Unlike other power technologies discussed in this report, the essential off-site requirement for
which provisions must be made on a PV Facility are water supply (generally in limited
quantities) and an electrical interconnection between the PV Facility switchyard and the local
utility distribution system.

24.4CAPITAL COST ESTIMATE


The base Cost Estimate for the PV Facility with a nominal capacity of 7 MW is 6,050/kW and
with a nominal capacity of 150 MW is $4,755/kW. Table 24-1 and Table 24-2 summarize the
Cost Estimate categories for the PV Facility.

24-2
TABLE 24-1 – BASE PLANT SITE CAPITAL COST ESTIMATE FOR PV
Technology: PV
Nominal Capacity (ISO): 7,000 kW
Nominal Heat Rate (ISO): N/A Btu/kWh-HHV

Capital Cost Category (000s) (October 1, 2010$)

Civil Structural Material and Installation 6,100

Mechanical Equipment Supply and


Installation 20,500

Electrical / I&C Supply and Installation 3,550

Project Indirects (1) 3,665

EPC Cost before Contingency and Fee 33,815

Fee and Contingency 4,000

Total Project EPC 37,815

Owner Costs (excluding project finance) 4,538

Total Project Cost (excluding finance) 42,353

Total Project EPC / kW 5,402

Owner Costs 12% (excluding project finance) / kW 648

Total Project Cost (excluding project finance) / kW 6,050

(1) Includes engineering, distributable costs, scaffolding, construction management, and start-up.

24-3
TABLE 24-2 – BASE PLANT SITE CAPITAL COST ESTIMATE FOR PV
Technology: PV
Nominal Capacity (ISO): 150,000 kW
Nominal Heat Rate (ISO): N/A Btu/kWh-HHV

Capital Cost Category (000s) (October 1, 2010$)

Civil Structural Material and Installation 65,000

Mechanical Equipment Supply and


Installation 391,583

Electrical / I&C Supply and Installation 64,350

Project Indirects (1) 52,762

EPC Cost before Contingency and Fee 573,695

Fee and Contingency 68,843

Total Project EPC 642,538

Owner Costs (excluding project finance) 70,679

Total Project Cost (excluding finance) 713,217

Total Project EPC / kW 4,283

Owner Costs 12% (excluding project finance) / kW 471

Total Project Cost (excluding project finance) / kW 4,755

(1) Includes engineering, distributable costs, scaffolding, construction management, and start-up.

For this type of technology and power plant configuration, our regional adjustments took into
consideration the following: seismic design differences, remote location issues, labor wage and
productivity differences, location adjustments, owner cost differences, and the increase in
overheads associated with these five location adjustments.
Seismic design differences among the various locations were based on U.S. seismic map
information that detailed the various seismic zones throughout the U.S. No cost increases were
associated with seismic Zone 0 and cost step increases were considered for Zones 1, 2, 3 and 4.
Remote location issues are related to geographic areas that typically require installation of man
camps, higher craft incentives, and higher per diems are generally required with respect to
construction, due to the fact that such areas are long distances from urban areas, where labor is
generally abundant. Remote location designations were also considered in locations where
higher equipment freight costs are typically incurred, which for example are regions not near
established rail or highway access. Remote locations related to the Photovoltaic Facility include

24-4
Fairbanks, Alaska; Honolulu, Hawaii; Albuquerque, New Mexico; Cheyenne, Wyoming; and
Cayey, Puerto Rico.
Labor wage and productivity differences were handled as discussed in Section 2.5.1, taking into
consideration the amount of labor we estimated for the PV Facility.
Location adjustments were made to locations where higher cost of living levels are incurred
and/or where population density generally correlates to higher construction costs for power and
other infrastructure projects. These locations include Alaska, California, Connecticut, Delaware,
District of Columbia, Hawaii, Illinois, Maine, Maryland, Massachusetts, Michigan, Minnesota,
New York, Ohio, and Wisconsin.
Owner costs were reviewed based on the need for utility upgrades and/or infrastructure costs
such as new facility transmission lines to tie to existing utility transmission substations or
existing transmission lines.
Table 24-3 and Table 24-4 present the PV Facility capital cost variations for alternative U.S.
plant locations.

24-5
TABLE 24-3 – LOCATION-BASED COSTS FOR PV (7 MW)
(OCTOBER 1, 2010 DOLLARS)
Base
Project Location Delta Cost Total Location
Cost Percent Difference Project Cost
State City ($/kW) Variation ($/kW) ($/kW)
Alaska Anchorage 6,050 16.8% 1,016 7,066
Alaska Fairbanks 6,050 25.6% 1,548 7,598
Alabama Huntsville 6,050 -7.3% (441) 5,609
Arizona Phoenix 6,050 -5.7% (344) 5,706
Arkansas Little Rock 6,050 -5.9% (359) 5,691
California Los Angeles 6,050 8.1% 490 6,540
California Redding 6,050 4.6% 277 6,327
California Bakersfield 6,050 5.0% 301 6,351
California Sacramento 6,050 9.1% 549 6,599
California San Francisco 6,050 18.1% 1,096 7,146
Colorado Denver 6,050 -4.3% (263) 5,787
Connecticut Hartford 6,050 6.2% 376 6,426
Delaware Dover 6,050 3.3% 198 6,248
District of Columbia Washington 6,050 1.6% 96 6,146
Florida Tallahassee 6,050 -10.0% (605) 5,445
Florida Tampa 6,050 -4.1% (250) 5,800
Georgia Atlanta 6,050 -7.9% (480) 5,570
Hawaii Honolulu 6,050 29.9% 1,812 7,862
Idaho Boise 6,050 -2.7% (162) 5,888
Illinois Chicago 6,050 17.8% 1,075 7,125
Indiana Indianapolis 6,050 -1.2% (70) 5,980
Iowa Davenport 6,050 0.6% 38 6,088
Iowa Waterloo 6,050 -6.6% (399) 5,651
Kansas Wichita 6,050 -5.0% (303) 5,747
Kentucky Louisville 6,050 -6.0% (364) 5,686
Louisiana New Orleans 6,050 -10.3% (622) 5,428
Maine Portland 6,050 -3.4% (203) 5,847
Maryland Baltimore 6,050 -2.6% (158) 5,892
Massachusetts Boston 6,050 14.6% 885 6,935
Michigan Detroit 6,050 3.1% 188 6,238
Michigan Grand Rapids 6,050 -7.6% (461) 5,589
Minnesota St. Paul 6,050 5.1% 308 6,358
Mississippi Jackson 6,050 -7.2% (438) 5,612
Missouri St. Louis 6,050 3.9% 233 6,283
Missouri Kansas City 6,050 2.0% 123 6,173
Montana Great Falls 6,050 -2.9% (178) 5,872
Nebraska Omaha 6,050 -1.9% (114) 5,936
New Hampshire Concord 6,050 -0.7% (42) 6,008
New Jersey Newark 6,050 14.4% 869 6,919
New Mexico Albuquerque 6,050 -2.5% (154) 5,896

24-6
Base
Project Location Delta Cost Total Location
Cost Percent Difference Project Cost
State City ($/kW) Variation ($/kW) ($/kW)
New York New York 6,050 32.9% 1,988 8,038
New York Syracuse 6,050 -1.4% (86) 5,964
Nevada Las Vegas 6,050 7.9% 476 6,526
North Carolina Charlotte 6,050 -10.6% (640) 5,410
North Dakota Bismarck 6,050 -5.3% (318) 5,732
Ohio Cincinnati 6,050 -4.2% (256) 5,794
Oregon Portland 6,050 4.3% 260 6,310
Pennsylvania Philadelphia 6,050 10.5% 634 6,684
Pennsylvania Wilkes-Barre 6,050 -4.6% (281) 5,769
Rhode Island Providence 6,050 2.7% 166 6,216
South Carolina Spartanburg 6,050 -12.1% (731) 5,319
South Dakota Rapid City 6,050 -7.9% (477) 5,573
Tennessee Knoxville 6,050 -9.3% (562) 5,488
Texas Houston 6,050 -9.2% (557) 5,493
Utah Salt Lake City 6,050 -4.0% (240) 5,810
Vermont Burlington 6,050 -4.2% (256) 5,794
Virginia Alexandria 6,050 -3.1% (185) 5,865
Virginia Lynchburg 6,050 -6.5% (391) 5,659
Washington Seattle 6,050 5.3% 322 6,372
Washington Spokane 6,050 -1.3% (81) 5,969
West Virginia Charleston 6,050 -2.0% (124) 5,926
Wisconsin Green Bay 6,050 -3.1% (190) 5,860
Wyoming Cheyenne 6,050 -4.0% (240) 5,810
Puerto Rico Cayey 6,050 -1.9% (117) 5,933

24-7
TABLE 24-4 – LOCATION-BASED COSTS FOR PV (150 MW)
(OCTOBER 1, 2010 DOLLARS)
Base
Project Location Delta Cost Total Location
Cost Percent Difference Project Cost
State City ($/kW) Variation ($/kW) ($/kW)
Alaska Anchorage 4,755 19.9% 947 5,702
Alaska Fairbanks 4,755 30.9% 1,470 6,225
Alabama Huntsville 4,755 -8.0% (379) 4,376
Arizona Phoenix 4,755 -6.2% (294) 4,461
Arkansas Little Rock 4,755 -6.5% (307) 4,448
California Los Angeles 4,755 9.6% 458 5,213
California Redding 4,755 5.5% 263 5,018
California Bakersfield 4,755 6.1% 291 5,046
California Sacramento 4,755 10.5% 498 5,253
California San Francisco 4,755 20.7% 985 5,740
Colorado Denver 4,755 -4.4% (208) 4,547
Connecticut Hartford 4,755 7.1% 339 5,094
Delaware Dover 4,755 3.8% 183 4,938
District of Columbia Washington 4,755 2.3% 111 4,866
Florida Tallahassee 4,755 -11.0% (522) 4,233
Florida Tampa 4,755 -4.5% (216) 4,539
Georgia Atlanta 4,755 -8.7% (413) 4,342
Hawaii Honolulu 4,755 37.2% 1,771 6,526
Idaho Boise 4,755 -2.5% (119) 4,636
Illinois Chicago 4,755 19.9% 949 5,704
Indiana Indianapolis 4,755 -1.2% (57) 4,698
Iowa Davenport 4,755 1.1% 51 4,806
Iowa Waterloo 4,755 -6.9% (327) 4,428
Kansas Wichita 4,755 -5.1% (242) 4,513
Kentucky Louisville 4,755 -6.6% (313) 4,442
Louisiana New Orleans 4,755 -11.3% (537) 4,218
Maine Portland 4,755 -3.2% (152) 4,603
Maryland Baltimore 4,755 -2.6% (124) 4,631
Massachusetts Boston 4,755 16.4% 778 5,533
Michigan Detroit 4,755 3.4% 163 4,918
Michigan Grand Rapids 4,755 -8.4% (398) 4,357
Minnesota St. Paul 4,755 6.0% 286 5,041
Mississippi Jackson 4,755 -7.9% (377) 4,378
Missouri St. Louis 4,755 4.4% 208 4,963
Missouri Kansas City 4,755 2.3% 109 4,864
Montana Great Falls 4,755 -2.7% (130) 4,625
Nebraska Omaha 4,755 -1.7% (79) 4,676
New Hampshire Concord 4,755 -0.3% (15) 4,740
New Jersey Newark 4,755 15.8% 751 5,506
New Mexico Albuquerque 4,755 -2.3% (111) 4,644

24-8
Base
Project Location Delta Cost Total Location
Cost Percent Difference Project Cost
State City ($/kW) Variation ($/kW) ($/kW)
New York New York 4,755 36.6% 1,739 6,494
New York Syracuse 4,755 -1.4% (68) 4,687
Nevada Las Vegas 4,755 9.1% 432 5,187
North Carolina Charlotte 4,755 -11.6% (549) 4,206
North Dakota Bismarck 4,755 -5.3% (254) 4,501
Ohio Cincinnati 4,755 -4.6% (220) 4,535
Oregon Portland 4,755 5.2% 249 5,004
Pennsylvania Philadelphia 4,755 11.6% 550 5,305
Pennsylvania Wilkes-Barre 4,755 -5.0% (240) 4,515
Rhode Island Providence 4,755 3.1% 146 4,901
South Carolina Spartanburg 4,755 -13.2% (628) 4,127
South Dakota Rapid City 4,755 -8.2% (392) 4,363
Tennessee Knoxville 4,755 -10.2% (483) 4,272
Texas Houston 4,755 -10.1% (481) 4,274
Utah Salt Lake City 4,755 -3.8% (183) 4,572
Vermont Burlington 4,755 -4.2% (201) 4,554
Virginia Alexandria 4,755 -3.3% (159) 4,596
Virginia Lynchburg 4,755 -7.1% (336) 4,419
Washington Seattle 4,755 6.0% 284 5,039
Washington Spokane 4,755 -1.0% (49) 4,706
West Virginia Charleston 4,755 -2.2% (103) 4,652
Wisconsin Green Bay 4,755 -3.4% (161) 4,594
Wyoming Cheyenne 4,755 -3.8% (180) 4,575
Puerto Rico Cayey 4,755 -1.4% (68) 4,687

24.5O&M ESTIMATE
The significant O&M items for a PV Facility include periodic inverter maintenance and periodic
panel water washing. Additionally, most thermal solar operators do not treat O&M on a variable
basis, and consequently, all O&M expenses are shown below on a fixed basis. Table 24-5 and
Table 24-6 present the O&M expenses for the PV Facility.
TABLE 24-5 – O&M EXPENSES FOR PV FACILITY (7 MW)
Technology: PV
Fixed O&M Expense $26.40/kW-year
Variable O&M Expense $0/MWh
TABLE 24-6 – O&M EXPENSES FOR PV FACILITY (150 MW)
Technology: PV
Fixed O&M Expense $16.70/kW-year
Variable O&M Expense $0/MWh

24-9
24.6ENVIRONMENTAL COMPLIANCE INFORMATION
Table 24-7 presents environmental emissions for the PV Facility.
TABLE 24-7 – ENVIRONMENTAL EMISSIONS FOR PV
Technology: Photovoltaic
NOX 0 lb/MMBtu
SO2 0 lb/MMBtu
CO2 0 lb/MMBtu

24-10

You might also like