Part 4 Earthworks
Part 4 Earthworks
Part 4 Earthworks
Part 4
EARTHWORKS
Prepared by:
Engr. Rommel G. Arapo
CE - Faculty
103
E A RT H WO R K S
104
rga 1
08/06/2021
E A RT H WO R K S
CROSS SECTIONS AND AREAS
A cross section is a short profile taken perpendicular A side slope is expressed as the ratio of a horizontal
to the centerline of a roadway or other facility. The distance to a corresponding unit of vertical distance for
cross section at a station along a road will typically the cut or fill slope (Figure 10-29). This ratio depends
show the profile of the original ground surface, the largely on the type of soil and on the natural angle of
base of the roadway, and the side slopes of the cut repose at which it remains stable. A side slope of 1:1 is
or fill. The base is the horizontal line to which the cut possible for some compacted embankment sections,
or fill is first constructed; its width depends primarily whereas a flatter ratio of 2:1 or more is typical for a side
on the number of lanes and width of roadway slope in a cut section. Of course, a vertical concrete
shoulders. retaining wall may be built to hold back the soil where
very flat side slopes would require excessively wide right-
of-way acquisition.
105
E A RT H WO R K S
106
rga 2
08/06/2021
E A RT H WO R K S
Section Areas
The area enclosed in a section by the natural terrain, the side slopes, and
the base can be determined in several ways. These include approximate
methods such as simply counting the number of enclosed grid boxes. In a
method called stripping, the section is divided into several vertical strips,
or “slices,” of constant width. The sum of the altitudes of the strips is
determined by placing a long strip of paper successively over each slice,
as shown in the figure, and marking the accumulated heights. The total
length of the paper strip is multiplied by the constant width (w) of a
section or slice to compute the area of the cross section.
Plane geometry may be used to compute a cross-section area by first dividing the section into regular shapes,
including triangles and trapezoids. The dimensions of those figures can be determined by scaling or from field
note data, and their areas computed from basic geometric formulas. The sum of those areas is the area of the
cross section.
107
E A RT H WO R K S
Area by Planimeter
A planimeter is an instrument that will measure the area of a plane figure
of any shape when the tracer point of the instrument is moved around the
perimeter or edge of the figure. The planimeter is used by surveyors and
civil engineering technicians for determining storm drainage basin areas,
checking property survey areas, determining areas of roadway cross
sections, and performing other tasks. It is particularly useful for measuring
the areas of irregularly shaped figures, and accuracies be er than ―1
(a)
percent can be obtained under most circumstances.
An electronic planimeter displays area measurements in digital readout
directly in square inches or square centimeters; it can be instantly set on
zero, and most models are designed to facilitate the cumulative adding
and averaging of areas (figure a). A mechanical planimeter includes a
graduated drum and a disk that is read to four digits with a vernier; most
have an adjustable tracer arm, making it possible to set the instrument so
that the drum and disk readings are related to the area by a convenient
ratio (figure b). For some electronic planimeters, and most mechanical (b)
planimeters, it is necessary to convert the instrument reading to an area
that is related to the scale of the drawing used.
108
rga 3
08/06/2021
E A RT H WO R K S
Volume of Earthworks
1. End-Area Formula:
𝐀𝟏 + 𝐀𝟐
𝐕𝐄 = 𝐋
𝟐
2. Prismoidal Formula:
𝐋
𝐕𝐏 = 𝐀 + 𝟒𝐀𝐦 + 𝐀𝟐
𝟔 𝟏
A = Area at mid section
𝐕 = 𝐕𝐄 − 𝐕𝐜𝐩
𝐋
𝐕𝐜𝐩 = (𝐂 − 𝐂𝟐 )(𝐃𝟏 − 𝐃𝟐 )
𝟏𝟐 𝟏
109
E A RT H WO R K S
Problem no.1 @ sta 1+040 (fill section):
In a certain portion of road to be constructed the ff data CL
X1 X2
were taken:
8m
For 1+040 Road Base
0.42
X1 0 X2 1
1.5 1.22 1.5
−1.84 −1.22 −0.42 1.84 1
For 1+100
existing grade line
X3 0 X4
0.98 3.05 0.50
Base for cut = 9m Side Slope for cut = 1:1 @ sta 1+100 (cut section):
Base for fill = 8m Side Slope for fill = 1.5:1 existing grade line
110
rga 4
08/06/2021
E A RT H WO R K S
Solution:
6.76 4.63
(a) Area at sta. 1+040
note: area of the whole section is equal to the sum of areas of 2.76 4 4 0.63
the triangles that made-up the whole sections, that is: A4 0.42
A1 1
Area = A + A + A + A 1.5 1.22 A3 1.5
1.84 1 A2
For the individual triangle, use the formula:
1
A∆ = bh
2
For the area of the whole section:
1 1 1 1
Area = 4 1.84 + 1.22 6.76 + 1.22 4.63 + (4)(0.42)
2 2 2 2
𝐀𝐫𝐞𝐚 = 𝟏𝟏. 𝟒𝟔𝟖 𝐬𝐪. 𝐦. (𝐟𝐢𝐥𝐥)
A2
3.05
(b) Area at sta. 1+100 A3
0.98 1 1
Area = A + A + A + A 1 A1 A4
1 0.50
1 1 1 1 0.50
Area = 4.5 0.98 + 3.05 5.48 + 3.05 5 + (4.5)(0.5) 0.98 4.5 4.5
2 2 2 2
5.48 5.0
𝐀𝐫𝐞𝐚 = 𝟏𝟗. 𝟑𝟏𝟐 𝐬𝐪. 𝐦. (𝐜𝐮𝐭)
CL
111
E A RT H WO R K S
Solution:
Determine the Volume of Fill (using end
(c) difference in volume between two stations area formula):
using end area method
A +A
Note: assuming straight road base from sta 1+040 to sta V =L =V
2
1+100. Plot the computed area in both section of the road.
11.468 + 0
V = 22.355
2
𝐀𝐂 = 𝐕𝐅 = 𝟏𝟐𝟖. 𝟏𝟖𝟒 𝐜𝐮. 𝐦.
volume 𝟏𝟗. 𝟑𝟏𝟐
1+040 of cut
volume
Determine the Volume of Cut (using end
finish grade line
𝐀𝐅 = of fill 1+100 area formula):
𝟏𝟏. 𝟒𝟔𝟖
A +A
V =L =V
X 2
60 m 0 + 19.312
V = 37.645
2
diff. in vol. = Vol − Vol
𝐕𝐂 = 𝟑𝟔𝟑. 𝟓𝟎𝟎 𝐜𝐮. 𝐦.
Determine the location of zero vol., x:
A +A A diff. in vol. = Vol − Vol
=
60 x
diff. in vol. = 128.184 − 363.500
11.468 + 19.312 11.468
= 𝐱 = 𝟐𝟐. 𝟑𝟓𝟓 𝐦 𝐝𝐢𝐟𝐟. 𝐢𝐧 𝐯𝐨𝐥. = 𝟐𝟑𝟓. 𝟑𝟏𝟔 𝐜𝐮. 𝐦.
60 x
112
rga 5
08/06/2021
E A RT H WO R K S
Problem no.2 @ sta 1+020 (cut section):
From the given cross section of proposed road:
existing grade line
a) Determine the volume between two stations @ sta 1+040 (cut section):
using prismoidal formula.
b) Determine the volume between two stations existing grade line
using end area with prismoidal correction.
2.60
2.0 1.20
Road Base
width of road
6.0 6.90
CL
113
E A RT H WO R K S
Solution: Solving simultaneous equation:
(a) volume between two stations using B = 6.0 m
prismoidal formula:
L determining the Area of the section (A1):
V = A + 4A + A
6 1 1 1 1
A = 3 2.3 + 1.5 6.45 + 3 1.0 + (1.5)(4.5)
@ sta 1+020 (A1): 2 2 2 2
𝐀𝟏 = 𝟏𝟑. 𝟏𝟔𝟐 𝐬𝐪. 𝐦
6.45 4.50
2.60
2.0 1.20
B = width of road
S = side slope (horizontal, since vertical is always 1)
3.0 3.0
determining the width of road:
6.0 6.90
2.3S + 0.5B = 6.45
1S + 0.5B = 4.50
114
rga 6
08/06/2021
E A RT H WO R K S
Solution:
determining the volume using prismoidal
determining the Area of the section (A2):
formula:
1 1 1 1
A = 3 2 + 1.2 6.0 + 3 2.6 + (1.2)(6.9) L
2 2 2 2 V = A + 4A + A
6
𝐀𝟐 = 𝟏𝟒. 𝟔𝟒 𝐬𝐪. 𝐦
20
For the value of Am: V = 13.162 + 4(13.974) + 14.64
6
Note: The dimension of the section for Am is the average 𝐕𝐏 = 𝟐𝟕𝟖. 𝟗𝟗𝟑 𝐜𝐮. 𝐦.
of the dimension of the section of the two stations.
1.8
2.15 1.35
3.0 3.0
6.225 5.7
115
E A RT H WO R K S
Solution:
Determining prismoidal
(b) volume between two correction, Vcp: L
V = (C − C )(D − D
stations using end area with 12
prismoidal correction. @ sta 1+020 (A1): 20
V = (1.5 − 1.2)(10.95 − 12.9)
V=V −V 12
L V = −0.975 cu. m.
V = (C − C )(D − D ) 2.30 1.50 C1
12 1.0
3.0 3.0
6.0 6.90
D2
116
rga 7
08/06/2021
E A RT H WO R K S
117
E A RT H WO R K S
Solution:
(a) distance of the right slope @ sta 1+200 (c) difference in elevation of
stake from the center (XR): CL the slope stakes:
118
rga 8
08/06/2021
E A RT H WO R K S
Problem no.4
In a 20m road stretch, the ff cross section of the existing
ground and corresponding subgrade cross section notes were a) Compute the cross sectional area at
taken: 10+280.
b) Compute the cross sectional area at
Existing Ground Cross Section: 10+300.
Sta. Left Center Right c) Compute the volume between the two
10 + 280
. stations.
. .
10 + 300
.
119
E A RT H WO R K S
Solution:
(a) cross sectional area at sta 10+280: sta 10+280 (cut)
120
rga 9
08/06/2021
E A RT H WO R K S
Solution:
sta 10+300 (cut)
(b) cross sectional area at sta 10+300:
(-7,1) (0,1) (5,1)
Plotting the data of the sta 10+300 (9,0)
existing grade line
specifying their coordinates: (-10,-2)
(17,-1.5)
(-13.5,-3) (-6,-7) (6,-7) finish grade line
(0,-7)
(-7,-7.5) (7,-7.5)
Determine the area using the coordinates:
1 0 −7 −10 −13.5 −7 −6 6 7 17 9 5 0
A=
2 1 1 −2 −3 −7.5 −7 −7 −7.5 −1.5 0 1 1
0 1 + −7 −2 + −10 −3 + −13.5 −7.5 + −7 −7 + −6 −7 + 6 −7.5 + 7 −1.5 + 17 0 + 9 1 + 5(1) −
A = 0.5
−7 1 + −10 1 + −13.5 −2 + −7 −3 + −6 −7.5 + 6 −7 + 7 −7 + 17 −7.5 + 9 −1.5 + 5 0 + 0(1)
121
E A RT H WO R K S
HAUL AND MASS DIAGRAM
Haul:
1 cu. m. (LEH − FHD)C
The product of the volume of earth excavated and the distance it is Cost of Haul =
C
transported to form an embankment or to be disposed as waste.
Free Haul Distance (FHD): Cost of Borrow = 1 cu. m. (C )
A fixed distance within which the hauling of materials is not paid but is
where:
assumed to be already included in the cost of excavation.
Ch = unit cost of haul
Overhaul:
Cb = unit cost of borrow
The product of the volume in excess of the free haul mass and the
C = length of basis of cost of haul,
length of haul, in which payment is already required.
(cost is per meter station, C = 20m)
Length of Overhaul:
The distance between the center of gravity of the mass of excavation
beyond the free haul mass and the center of gravity of the resulting C C
LEH = + FHD
embankment minus the free haul distance. C
Limit of Economical Haul (LEH):
It is the distance within which it is more economical to haul materials
than to throw them as waste or beyond which it is more economical to
borrow than to haul. At this limiting distance the cost of haul is
approximately equal to the cost of borrow.
122
rga 10
08/06/2021
E A RT H WO R K S
HAUL AND MASS DIAGRAM
Waste:
Materials excavated and thrown away which is no longer necessary to form embankments.
Borrow:
Excavated materials obtained from borrow pits located beyond the limits of the road when
excavation for the roadway is not sufficient to form the embankments.
The figure below shows the profile of the ground surface, the grade line, the limits of free haul,
limit of economical haul, waste and borrow:
Profile Diagram
123
E A RT H WO R K S
MASS DIAGRAM
One of the objectives in vertical alignment design is to balance the volumes of cut and fill. This is to minimize the
quantity of earth that must either be “borrowed” from somewhere else and hauled to the site or be disposed of
off-site. The preliminary grade line can be located on the profile so that earthwork appears to be balanced, but
this is difficult to do visually because of the effect of shrinkage. Shrinkage refers to the decrease in volume of soil
due to compaction in an embankment.
A mass diagram may be used to determine the extent to which cut and fill are balanced in a preliminary
alignment design. The mass diagram is also useful to evaluate haul distances and to plan the overall earthwork
operation. It is simply a graph that depicts the accumulation of cut-and-fill quantities along the route. Volumes
of cut are positive, and volumes of fill are negative. The fill volumes are adjusted for shrinkage so that all
volumes shown on the diagram are equivalent to natural or “in situ” soil conditions.
The ordinates (y values) are the cumulative algebraic sums of earthwork volume starting at station 0 + 00. The
abscissas (x values) are the stations. The ordinates are connected by a smooth curve to form the mass diagram.
Usually, the mass diagram is plotted directly below the profile of the grade line; this facilitates visualization of
earthmoving activities.
124
rga 11
08/06/2021
E A RT H WO R K S
MASS DIAGRAM
125
E A RT H WO R K S
Problem no.5
The earthwork data of a proposed highway is shown on
the data below: a) Compute the overhaul volume.
length of economical haul (LEH) = 450m
b) Compute the volume of waste.
Sta of limits of LEH = 2+498.03 , 2+948.03
Free Haul Distance (FHD) = 50m c) Compute the volume of borrow.
Sta of limits of FHD = 2+713.12, 2+763.12
Assume the ground is uniformly sloping
Area (sq.m)
Station
CUT FILL
2 + 440 50
2 + 740 0
3 + 040 70
126
rga 12
08/06/2021
E A RT H WO R K S
Solution:
b) Volume of waste, VW:
FHD = 50 m
58.03 215.09 50 + b
2 + 948.03
2 + 763.12
V = 58.03
26.88 2
3 + 040
50
VW b VOH a 50 + 40.328
V = 58.03
c 2
2 + 740
VB
2 + 498.03
2 + 713.12
2 + 440
70
208.03
𝐕𝐖 = 𝟐, 𝟔𝟐𝟎. 𝟖𝟔𝟕 𝐜𝐮. 𝐦.
91.97
c) Volume of borrow, VB:
LEH = 450 m
70 + c
Profile Diagram V = 91.97
2
For the value of c:
a) overhaul volume, VOH:
70 c
a+b a = 4.48 sq. m. = c = 48.540 sq. m.
V = 215.09 300 208.03
2 b = 40.328 sq. m.
70 + 48.540
4.48 + 40.328 V = 91.97
For the value of a and b: V = 215.09 2
2
50 a b
= = 𝐕𝐁 = 𝟓, 𝟒𝟓𝟏. 𝟎𝟔𝟐 𝐜𝐮. 𝐦.
300 26.88 241.97 𝐕𝐎𝐇 = 𝟒, 𝟖𝟏𝟖. 𝟖𝟕𝟔 𝐜𝐮. 𝐦.
127
E A RT H WO R K S
Problem no.6
Shows below is a table of quantities of earthworks of a
proposed highway. FHD = 50m, LEH = 462.76 m. Assume the a) Compute the overhaul volume.
ground to be sloping uniformly. b) Compute the volume of waste.
c) Compute the volume of borrow.
Area (m2)
Sta Remarks
Cut Fill
10+020 80 initial point
10+115.65 54.57 limit of economical haul
10+297.92 5.90 limit of free haul
10+320 0 balancing point
10+347.92 4.66 limit of free haul
10+578.41 43.15 limit of economical haul
10+620 50 end point
128
rga 13
08/06/2021
E A RT H WO R K S
Solution:
10 + 578.41
10 + 347.92
10 +620
54.57
80 5.90
VW VOH
VB
10 + 115.65
10 + 297.92
10 + 020
10 + 320
50
4.66
43.15
Profile Diagram
129
E A RT H WO R K S
Problem no.7
The profile of the ground surface along which the
centerline of the roadway is sloping uniformly at a 28.60
certain grade. Area at Sta 5+400 is 20.89 m2 (Fill) and at
5 + 400
130
rga 14
08/06/2021
E A RT H WO R K S
Solution:
28.6 y
Given: = y = 0.143(50 − x) 28.60
200 50 − x FHD = 50
5 + 400
FHD = 50 m
Ch = P 0.20 per meter station Note: in the FHD, the volume A X Y2
Cb = P 4.00 per cu.m. of cut must be equal to Y1 50 - x B
5 + 850
5 + 650
volume of fill.
a) Length of Economical Haul, 20.89
LEH: 0.5 x y = 0.5(50 − x)(y )
C C
LEH = + FHD
0.5 x 0.084x = 0.5(50 − x)(0.143)(50 − x) Profile Diagram
C
4 (20) x = 28.306 m
LEH = + 50 c) Free Haul Volume:
0.20
sta @ A = 5 + 650 − x (volume of cut in the FHD)
𝐋𝐄𝐇 = 𝟒𝟓𝟎 𝐦
sta @ A = 5 + 650 − 28.306
b) Sta of FHD limits: V = 0.5(50 − x)(y )
𝐬𝐭𝐚 @ 𝐀 = 𝟓 + 𝟔𝟐𝟏. 𝟔𝟗𝟒
sta @ A = 5 + 650 − x y = 0.143(50 − x)
sta @ B = 5 + 650 + (50 − x) sta @ B = 5 + 650 + (50 − x) y = 0.143(50 − 28.306)
For the value of x: sta @ B = 5 + 650 + (50 − 28.306) y = 3.102 sq. m.
using similar triangle, 𝐬𝐭𝐚 @ 𝐁 = 𝟓 + 𝟔𝟕𝟏. 𝟔𝟗𝟒
V = 0.5(50 − 28.306)(3.102)
20.89 y
= y = 0.084x 𝐕𝐅𝐇 = 𝟑𝟑. 𝟔𝟒𝟕 𝐜𝐮. 𝐦.
250 x
131
E A RT H WO R K S
10 + 120 140
Free haul Distance = 50m 10 + 160 110
LEH = 400m 10 + 200 190
Mass ordinate of Initial limit of 10 + 240 50
FHD = +910 cu.m.
10 + 280 40
Mass ordinate of Initial limit of
10 + 320 120
Economical Haul = +350 cu.m.
10 + 360 90
10 + 400 80
Determine:
a. Volume of Waste 10 + 440 200
10 + 560 320
10 + 600 280
132
rga 15
08/06/2021
E A RT H WO R K S
Solution:
Stations Volume Mass Ordinate
Compute the mass ordinate of each
10 + 000 +200 +200
station:
Assigned positive sign on cut and 10 + 040 +100 +300
negative sign on fill. 10 + 080 +150 +450
Mass ordinate of the first station is
10 + 120 +140 +590
equal to the volume of the first
station 10 + 160 +110 +700
Mass ordinate of the next station is 10 + 200 +190 +890
equal to the mass ordinate of the
10 + 240 +50 +940
preceding station plus the volume
of that station. 10 + 280 -40 +900
133
E A RT H WO R K S
Solution:
a. Volume of Waste
Draw the mass diagram:
Plot the following: +940 V = 350 − 200
FHD = 50m
First Mass Ordinate +910
𝐕𝐖 = 𝟏𝟓𝟎 𝐜𝐮. 𝐦.
Last Mass Ordinate
Highest Mass Ordinate b. Volume of Overhaul
Mass Ordinate
Vol of Waste
VOH VFH
Vol of Borrow
134
rga 16