Fundamental of Surveying 2
Fundamental of Surveying 2
(FUNSURVEY2)
MODULE
Fundamental of Surveying 2
Holy Angel University
School of Engineering and Architecture
Department of Civil Engineering
Transportation Engineering
Station 5
Earthworks - Volume
References Charles D. Ghilani and Paul R. Wolf, 2015. Elementray Surveying: An Introduction to
Geomatics, 14th Edition
Persons engaged in surveying (geomatics) are often called on to determine volumes of various
types of material. Quantities of earthwork and concrete are needed, for example, on many types of
construction projects. Volume computations are also required to determine the capacities of bins,
tanks, reservoirs, and buildings, and to check stockpiles of coal, gravel, and other materials. The
determination of quantities of water discharged by streams and rivers, per unit of time, is also
important.
Volume
Direct measurement of volumes is rarely made in surveying, since it is difficult to actually apply a
unit of measure to the material involved. Instead, indirect measurements are obtained by measuring
lines and areas that have a relationship to the volume desired. Here in earthworks, we can have the
volume using different type of indirect method.
Prismoidal Formula
The prismoidal formula applies to volumes of all geometric solids that can be
considered prismoids. A prismoid, illustrated in the figure below, is a solid having ends that are
parallel but not congruent, and trapezoidal sides that are also not congruent. Most earthwork
solids obtained from cross-section data fits this classification. However, from a practical
standpoint, the differences in volumes computed by the average-end-area method and the
prismoidal formula are usually so small as to be negligible. Where extreme accuracy is needed,
such as in expensive rock cuts or concrete placements, the prismoidal method can be used.
One arrangement of the prismoidal formula is
𝐴1 +4𝐴𝑚 +𝐴2
𝑉𝑝 = 𝑥𝐿
6
Where:
Vp = Prismoidal Volume
A1 and A2 = areas taken in the field
Am = Area of a computed section midway between A1 and A2. This is found by usual
computation after averaging the heights and widths of the two end sections.
L = The distance between the two stations.
𝐿
𝐶𝑝 = (𝑐 − 𝑐2 )(𝑤1 − 𝑤2 )
12 1
Where:
Cp = Volume of the prismoidal correction
c1 , c2 = center heights in cut or fill
w1 , w2 = widths of sections (from slope intercept to slope intercept)
L = The distance between the two stations.
The most commonly used method on solving the volume of the earthworks is the
combination of end-area method and prismoidal correction.
𝑉 = 𝑉𝑒 − 𝐶𝑝
Sample Problem:
1. From station 0+040 with center height of 1.40m fill, the ground line makes a uniform slope
of 5% to station 0+100, whose center height is 2.80m cut. Assume both sections to be level
sections with side slopes of 2:1 for fill and 1.5:1 for cut.
a) Find the grade of the finished road surface.
b) Find the area at each station
c) By end area method, find the amount of cut and fill.
Solution:
First, illustrate the problem
𝑦
5% =
60
𝑦=3
1.2
𝑆𝑙𝑜𝑝𝑒 =
60
𝑆𝑙𝑜𝑝𝑒 = 2% 𝑑𝑜𝑤𝑛𝑤𝑎𝑟𝑑
14.6+9
𝐴= 𝑥 1.40
2
10 +18.40
𝐴= 𝑥 2.80
2
C)
We need to identify the distance of fill and cut
Fill = x
Cut = 60 -x
16.52 + 0
𝑉𝑓 = 𝑥 20𝑚
2
𝑉𝑓 = 165.20 𝑐𝑢. 𝑚
0 + 39.76
𝑉𝑐 = 𝑥 40𝑚
2
𝑉𝑐 = 795.20 𝑐𝑢. 𝑚
STATION A
6.60 0 4.8
+2.4 12 +1.2
STATION B
6.3 0 7.2
+2.2 𝑥 +2.80
𝐵
6.9 = 2.2𝑠 + ---- Eq. 1
2
𝐵
7.2 = 2.8𝑠 + ---- Eq. 2
2
0.9 = 0.6𝑠
𝑠 = 1.5
𝑋+2.2 1 𝑋+2.8 1
16.82 = [(3.3 + 3) (
2
)] − [2 (3.3)(2.2)] + [(3 + 3.9) ( 2
)] − [2 (3.9)(2.8)]
𝑋 = 1.38𝑚
2.4+2 1 2+1.2 1
𝑆𝑡𝑎. 𝐴 𝐴𝑟𝑒𝑎 = [(6.6) (
2
)] − [2 (3.6)(2.4)] + [(4.8) ( 2
)] − [2 (1.8)(1.2)]
𝑆𝑡𝑎. 𝐴 𝐴𝑟𝑒𝑎 = 16.80 𝑠𝑞. 𝑚
𝑉 = 𝑉𝑒 − 𝐶𝑝
𝑉 = 336.20 − (−2.17)
𝑽 = 𝟑𝟑𝟖. 𝟑𝟕 𝒄𝒖. 𝒎
3. At station 1+100 of a portion of a highway stretch has an area of 100 sq. meter in cut while
that of station 1+200 the area is 240 sq. meters in cut. At station 1+100, the ground surface
to the left of the center line is flat and the height of the right slope stake above the grade
line is one half of the left , while that of station 1+200, the height of the right slope stake is 3
times higher than that of the left slope stake. The center cut at station 1+200. The width of
the roadway is 10m with a side slope 2:1.
a) Determine the height of cut at the center of station 1+100
b) Determine the height of the right slope stake at 1+200
c) Determine the volume between station 1+100 and 1+200 by applying prismoidal
correction.
Sample Problem
1. A rectangular plot show below, which is to be excavated to the given reduced level. Assuming
area is subdivided into equal rectangular system, calculate the volume of earth to be
excavated.
(Excavated level = 10.0m)
a) Compute by formula
[(𝐴)+(2𝐵)+𝐶+(2𝐷)+(4𝐸)+(2𝐹)+𝐺+(2𝐻)+𝐼]
𝑉=
4
[(16.54)+(2𝑥17.25)+15.40+(2𝑥16.32)+(4𝑥12.95)+(2𝑥15.55)+16.17+(2𝑥15.84)+13.38]
𝑉=
4
𝑉 = 𝐴 𝑥 60.8025
𝑉 = 183.75 𝑥 60.8025
𝑽 = 𝟏𝟏𝟏𝟕𝟐. 𝟒𝟔 𝒄𝒖. 𝒎
Questions
Chapter 5:
Charles D. Ghilani and Paul R. Wolf, 2015. Elementray Surveying: An Introduction to Geomatics, 14th
Edition
Jerry Nathanson, Michael T. Lanzafama, and Philip Kissam, 2011. Surveying Fundamentals and Practices,
6th Edition
Transportation Engineering
Holy Angel University
School of Engineering and Architecture
Department of Civil Engineering
Transportation Engineering
Station # 6
Mass Diagram
Introduction After knowing how to solve the earthworks volume. Here comes t
application of designing the land profile. An economical project is
the job of an engineer.
References Charles D. Ghilani and Paul R. Wolf, 2015. Elementray Surveying: An Introduction to
Geomatics, 14th Edition
Freehaul
Distance with which there is a fixed price for excavating, hauling and dumping regardless
of the distance moved.
Overhaul
Is the number of cubic meters of overhauled material multiplied by the overhaul
distance, this distance is measured between the center of gravity of cut and fill.
Borrow
It is the location away from the Right of Way and it is chosen by the Engineer. The
borrow pits soil should be comply with the followed specification.
Waste
It is the unwanted excavation material which should be disposed out of Right of Way.
Waste
Overhaul
Borrow
Formula:
𝐶𝑏 𝐶
𝐿𝐸𝐻 = + 𝐹𝐻𝐷
𝐶ℎ
Where:
Cb = Cost of Borrow
C = Distance between Stations
Ch = Cost of Haul
Solution:
a) Volume of Overhaul
Using ratio and proportion
Triangle 1:
ℎ 50
=
26.88 300
ℎ = 4.48
Triangle 2:
𝑎 50
=
241.97 300
𝑎 = 40.33
b) Volume of Waste
Using the trapezoid:
𝑎+50
𝑊𝑎𝑠𝑡𝑒 𝑉𝑜𝑙𝑢𝑚𝑒 = 𝑥 58.03
2
40.33+50
𝑊𝑎𝑠𝑡𝑒 𝑉𝑜𝑙𝑢𝑚𝑒 = 𝑥 58.03
2
2. The given data off a proposed Manila-Cavite Coastal road is tabulated below. The free haul
distance is 50m, and the cost of borrow is 420 pesos per cu.m, cost of excavation is 350 pesos
per cu.m and the cost of haul is 21 pesos per meter station. Assuming the ground surface to be
uniformly sloping towards the balancing point.
Solution:
First, illustrate the problem
a) LEH
𝐶𝑏 𝐶
𝐿𝐸𝐻 = + 𝐹𝐻𝐷
𝐶ℎ
(420)(20)
𝐿𝐸𝐻 = + 50
21
𝐿𝐸𝐻 = 450 𝑚.
4.57(26.88)
𝐹𝑟𝑒𝑒 𝐻𝑎𝑢𝑙 𝑉𝑜𝑙𝑢𝑚𝑒 =
2
c) Overhaul Volume
Using the trapezoid
41.13+ℎ
𝑂𝑣𝑒𝑟ℎ𝑎𝑢𝑙 𝑉𝑜𝑙𝑢𝑚𝑒 = 𝑥 (241.97 − 𝑥)
2
41.13+4.57
𝑂𝑣𝑒𝑟ℎ𝑎𝑢𝑙 𝑉𝑜𝑙𝑢𝑚𝑒 = 𝑥 (241.97 − 26.88)
2
𝑂𝑣𝑒𝑟ℎ𝑎𝑢𝑙 𝑉𝑜𝑙𝑢𝑚𝑒 = 4915 𝑐𝑢. 𝑚
Mass Diagram
It is a diagram provides a suitable means for studying haul and overhaul to compute the total
payment. It’s x-axis represents the distance in stations, while the y-axis represents the cumulative
volume (the algebraic sum of excavations and embankment between any selected points) after
correction due to soil condition.
Questions
Chapter 6:
Charles D. Ghilani and Paul R. Wolf, 2015. Elementray Surveying: An Introduction to Geomatics, 14 th
Edition
Jerry Nathanson, Michael T. Lanzafama, and Philip Kissam, 2011. Surveying Fundamentals and Practices,
6th Edition