Name: Kuna Satya Srinivasa Raju ROLL NO:200914006 (CEM) Project Management Lab-2 Assignment No - 6
Name: Kuna Satya Srinivasa Raju ROLL NO:200914006 (CEM) Project Management Lab-2 Assignment No - 6
Name: Kuna Satya Srinivasa Raju ROLL NO:200914006 (CEM) Project Management Lab-2 Assignment No - 6
Develop the schedule, apply the resources and estimate the cost of the project. The activities
and the resources are given below. The activities are listed according to the WBS levels. Apply
WBS and organize the activities. Create a Project calendar (6 days/week and 10 hr/day
working). Link this calendar with a Global base calendar. Create the OBS and EPS of your
OBS created
NAME: KUNA SATYA SRINIVASA RAJU
ROLL NO :200914006 (CEM)
PROJECT MANAGEMENT LAB-2 ASSIGNMENT NO -6
EPS Created
Global Calendar
NAME: KUNA SATYA SRINIVASA RAJU
ROLL NO :200914006 (CEM)
PROJECT MANAGEMENT LAB-2 ASSIGNMENT NO -6
Project Created
Time Period
When entered In Weeks in duration primavera converts to days (say 4 weeks= to be entered as
4w)
Predecessor entering
NAME: KUNA SATYA SRINIVASA RAJU
ROLL NO :200914006 (CEM)
PROJECT MANAGEMENT LAB-2 ASSIGNMENT NO -6
Scheduling
Unit Rate & Measuring Unit Created for Project Manager Since its 1 it is mentioned as Each.
NAME: KUNA SATYA SRINIVASA RAJU
ROLL NO :200914006 (CEM)
PROJECT MANAGEMENT LAB-2 ASSIGNMENT NO -6
Batched Report
NAME: KUNA SATYA SRINIVASA RAJU
ROLL NO :200914006 (CEM)
PROJECT MANAGEMENT LAB-2 ASSIGNMENT NO -6
Batched Report