IRENA RRA Moldova 2019 EN
IRENA RRA Moldova 2019 EN
IRENA RRA Moldova 2019 EN
Unless otherwise stated, material in this publication may be freely used, shared, copied, reproduced, printed and/or
stored, provided that appropriate acknowledgement is given of IRENA as the source and copyright holder. Material
in this publication that is attributed to third parties may be subject to separate terms of use and restrictions, and
appropriate permissions from these third parties may need to be secured before any use of such material.
ISBN: 978-92-9260-109-6
Citation: IRENA (2019), Renewables Readiness Assessment: Republic of Moldova, International Renewable Energy Agency, Abu Dhabi.
About IRENA
The International Renewable Energy Agency (IRENA) is an intergovernmental organisation that supports countries
in their transition to a sustainable energy future and serves as the principal platform for international co-operation,
a centre of excellence and a repository of policy, technology, resource and financial knowledge on renewable
energy. IRENA promotes the widespread adoption and sustainable use of all forms of renewable energy, including
bioenergy, geothermal, hydropower, ocean, solar and wind energy, in the pursuit of sustainable development,
energy access, energy security and low-carbon economic growth and prosperity.
www.irena.org
Acknowledgements
This report was prepared by IRENA in close collaboration with the Government of the Republic of Moldova, as represented
by the Ministry of Economy and Infrastructure (MoEI). Special thanks are due to numerous other officials, especially from
the Energy Efficiency Agency, National Energy Regulatory Agency and Moldelectrica. This report benefited from the inputs
of various experts, notably including Alexandru Cosovan (European Bank for Reconstruction and Development), Gabriela
Cretu (Energy Community Secretariat), Giuseppe Grimaldi (European Bank for Reconstruction and Development), Adil
Hanif (European Bank for Reconstruction and Development), Marcela Lefter (Electra Norte), Tiago Oliveira (European
Bank for Reconstruction and Development), Denis Tumuruc (MoEI), and Nicolae Zaharia (Sinergetika). IRENA colleagues
including Abdulmalik Oricha Ali, Serkan Ata, Emanuele Bianco, Diala Hawila, Vanessa Interiano, Luis Janeiro, Sandra Lozo,
Hameed Safiullah, Jeffrey Skeer, Costanza Strinati, and Naida Taso also provided valuable guidance and input.
Contributing authors: Marcin Scigan (IRENA), Gürbüz Gönül (IRENA) and Igor Zanoaga (consultant)
Disclaimer
This publication and the material herein are provided “as is”. All reasonable precautions have been taken by IRENA to verify the
reliability of the material in this publication. However, neither IRENA nor any of its officials, agents, data or other third-party
content providers provides a warranty of any kind, either expressed or implied, and they accept no responsibility or liability for
any consequence of use of the publication or material herein.
The information contained herein does not necessarily represent the views of the Members of IRENA. The mention of specific
companies or certain projects or products does not imply that they are endorsed or recommended by IRENA in preference to
others of a similar nature that are not mentioned. The designations employed and the presentation of material herein do not
imply the expression of any opinion on the part of IRENA concerning the legal status of any region, country, territory, city or area
or of its authorities, or concerning the delimitation of frontiers or boundaries.
RENEWABLES READINESS
ASSESSMENT
Republic of
Moldova
FOREWORD
from the Minister of
Economy and Infrastructure
Given its high dependence on imported energy resources, the Republic of Moldova is crying out for a more
intensive use of renewable energy sources. Indeed, in a country where three quarters of energy needs
are covered by imports, the consistent and feasible implementation of a renewable energy strategy has a
tremendous importance for the Republic of Moldova’s energy security.
Therefore, the main pillars and vectors of the country’s energy policies are now orienting towards the
enhancement of energy security and security of supply, the reduction of CO2 emissions, and the sustainable
development of the economy. In the context of this fundamental role for renewable energy in the transition
towards a more competitive economy and towards ensuring a more secure and sustainable energy system
– the Ministry of Economy and Infrastructure is working hard to scale-up the importance of renewable
energy in the country’s energy mix, with the support of the Energy Community Secretariat, development
partners and the International Renewable Energy Agency (IRENA).
The development of this Renewables Readiness Assessment (RRA) report perfectly coincides with the
Government of Moldova’s efforts to align its national legislation with the commitments it has made under
the Energy Community Treaty and Association Agreement, signed with the EU.
Indeed, despite recent developments in the renewable energy sector, the need for a systematic assessment
of the sector’s potential – and its bottlenecks – was still necessary. As a result of fruitful collaboration
between the Ministry of Economy and Infrastructure and IRENA, this assessment has now been conducted.
Its conclusions include the opinions of all major stakeholders, bilateral and multilateral co-operation
agencies, financial institutions and private sector representatives. This study also sets the priority areas
that the Ministry of Economy and Infrastructure would like to continue working on, while also defining
perspectives for collaboration with all the relevant stakeholders. This is of paramount importance for the
country and serves in achieving a common goal – improved energy security.
Moreover, in addition to helping the government reduce consumption, optimise costs and secure the
country’s hope for a brighter and a more energy secure future, energy efficiency and renewable sources of
energy represent some of the most promising ways in which almost half of the target set and agreed by
the Paris Agreement on Climate Change can be achieved.
Last but not least, on behalf of the Ministry of Economy and Infrastructure, I would like to express our
appreciation to IRENA, our development partners, the business community and other stakeholders for their
commitment to develop the use of renewable sources of energy in the Republic of Moldova. Their support
and technical assistance are of great importance for the benefit of our country and we look forward to a
long and fruitful future relationship.
Chiril Gaburici
Minister of Economy and Infrastructure
Republic of Moldova
On the other hand, the country has vast renewable energy potential, which remains still largely untapped.
With renewables becoming increasingly cost-competitive, policy makers have recognised them as an
important means to address the Republic of Moldova’s energy challenges and achieve a sustainable future.
Notably, the country has already met several major targets set out in its National Renewable Energy Action
Plan for 2013-2020, including the objective to cover at least 17% of gross final energy consumption with
renewables.
This Renewables Readiness Assessment (RRA) – undertaken by the International Renewable Energy
Agency (IRENA) in close co-operation with the Government of the Republic of Moldova – examines the
energy sector holistically, identifying key actions to accelerate renewable energy deployment. It underlines
short- to medium-term regulatory, financing and public-awareness issues, as well as the need for long-
term planning. Specifically, the report suggests the adoption of an ambitious renewable energy target for
2030 and ways to strengthen the government’s on-going efforts to develop the bioenergy sector. It also
proposes measures to improve the bankability of renewable energy projects and enhance the capacity of
local banks to facilitate the financing of such projects.
I would like to thank Minister Gaburici and the staff of the Ministry of Economy and Infrastructure for their
support in preparing this study. The report was also enriched by insights from other government agencies
and a wide range of other stakeholders. IRENA looks forward to working with all partners to translate these
recommendations into practical action.
I sincerely hope these RRA findings will strengthen the Republic of Moldova’s pursuit of renewable energy
solutions as a source of economic growth, job creation and energy security. IRENA stands ready to assist in
accelerating the country’s transition to a sustainable energy future.
Adnan Z. Amin
Director-General
International Renewable Energy Agency
Republic of Moldova V
Contents
Figures VIII
Tables VIII
Boxes VIII
Executive Summary XI
1. Introduction 1
1.1 Country background 1
2. Energy context 5
2.1 Energy supply and demand 5
4.3 Bioenergy 35
• Develop a strategy for the bioenergy sector 35
• Encourage the use of and further develop the online platform for biomass trade 36
• Identify an optimal pathway to increase the role of biofuels 36
References 39
Tables
Table 1 Overview of the domestic power generation infrastructure in the Republic of Moldova 11
Table 2 Share of renewable energy in gross final energy consumption, by sector (%) 19
Table 3 RE capacity quotas under the new supporting scheme 25
Boxes
Box 1 IRENA’s South East Europe Initiative 3
Box 2 Asynchronous interconnection with Romania 13
Box 3 The business case for renewables 18
Box 4 Cost-competitive solar PV and wind potential in South East Europe 21
Box 5 Republic of Moldova Energy and Biomass Project 22
Box 6 Policy Guidelines on Competitive Selection and Support for Renewable Energy 26
Republic of Moldova IX
Chisinau at night
Photograph: Shutterstock
Republic of Moldova XI
In 2012, it pledged to achieve a 17% share of Challenges and recommended actions
renewables in gross final energy consumption
by 2020 and developed the National Renewable Adopt a renewable energy target for 2030
Energy Action Plan for the 2013-2020 period.
This envisages development of solar PV and wind The current share of renewables, 27.8%, was
technologies, amongst others. It also builds on reached mainly through the revision of biomass
the first steps to advance the use of renewables consumption data for the years 2010-2016. Thus,
in the power sector, which date back to 2007. The it neither provides long-term predictability,
Renewable Energy Law (No. 160-XVI of 12.07.2007) nor reflects the country’s vision of energy
introduced tariffs for 15 years, under the “cost-plus” sector development. Although the announced
principle, with these based on the actual eligible development of 168 MW of renewables capacity
costs incurred. in the coming years has captured the interest of
several investors, this could be considered a one-
Yet, as this framework was not considered sufficient off boost for the market, rather than an element of
to attract investments in the sector, the Law on the a solid strategy.
promotion of the use of energy from renewable
sources (Law no. 10 of 26.02.2016) came into force The Ministry of Economy and Infrastructure has
in March 2018. now begun various initiatives, including discussions
within the Energy Community, with a view to
This provides necessary guarantees for agreeing on a new renewable energy target for
investments, including: non-discriminatory grid 2030. IRENA’s recently-initiated regional REmap
connection; priority dispatch; and an obligation analysis for the countries of Central and Southeast
by the central electricity supplier to purchase all- Europe, including the Republic of Moldova, can
renewable-generated electricity for 15 years. In contribute to these efforts and help identify cost-
addition, the new law is expected to lead to the effective technology options for the deployment of
construction of up to 168 MW of new capacity, renewables in the power and end-use sectors.
mainly wind and solar PV, to be supported through
administratively set feed-in tariffs and an auctions- Conduct a production cost modelling study
based mechanism. Scheduled initially for 2019,
these auctions are expected to result in a capacity As renewables are becoming an increasingly cost-
of 80 MW of wind and 25 MW of solar PV. competitive source of energy, they are poised
to play a greater role in the power system of the
The recent adoption of these new support schemes Republic of Moldova. The increased use of solar PV
for renewable electricity has contributed greatly and wind, however, would present a new challenge,
to the rising interest of the business community – as the country does not have sufficient capacity
but additional efforts are necessary to cement the to balance its generation. Thus, a production cost
foundations of the sector. modelling study would allow the determination of
any potential operational constraints that could
In this context, in 2018, the RRA elaboration result in the unavailability of sufficient power to
process was launched at the request of the meet demand. Furthermore, it could investigate
Ministry of Economy and Infrastructure of the multiple scenarios for the generation mix, including
Republic of Moldova. This provided a venue for those with higher shares of renewables.
multi-stakeholder dialogue to identify challenges
in renewable energy deployment and to suggest The results could help build confidence among
the solutions required to further exploit indigenous policy makers, system operators and investors, as
renewable energy resources, while integrating well as identify the most cost-effective option for
growing shares of solar and wind energy in the balancing the system. To support countries in the
Republic of Moldova’s power system. assessment of power systems’ flexibility, IRENA
Strengthen the enabling regulatory framework Develop a strategy for the bioenergy sector
Even though the new Law on the promotion of the With limited availability of wooden biomass, the
use of energy from renewable sources (Law no. government is advised to develop a country-wide
10 of 26.02.2016) came into effect in March 2018, programme for the use of solid biofuels.
additional pieces of legislation are required to
ensure smooth implementation of the new support This strategy should not only provide a
mechanisms. comprehensive assessment of resource
potential, but also provide clarity on the most
In particular, clarity on all requirements and suitable technology options for a wide group of
procedures to be followed needs to be ensured beneficiaries in the Republic of Moldova. Some
well in advance for both project developers and failures to match beneficiary and technology have
financial institutions. For auctions-based support turned out to be costly in the past. In this context,
scheme, essential secondary legislation needs to the government could analyse the opportunity to
be adopted, including: standard documentation revise the relevant legislation with the objective
for the tendering procedure; eligible producer of increasing the role of local public authorities
status confirmation for small renewable electricity in promoting the bioenergy sector. As the owners
producers; and grid connection, including of a vast amount of land, those authorities could
provisions referring to renewables integration. strengthen their commitment to developing the
local industry and would benefit from locally
In addition, the regulatory framework could be harvested, cost-competitive heating resources.
strengthened by implementing a transparent
methodology to calculate feed-in-tariffs and The strategy should also address the potential
ceiling prices for tenders, as well as by facilitating for cultivation and wide use of energy crops that
introduction of the net metering scheme for can be grown on marginal and/or depleted lands.
distributed renewable energy generation. While Currently, despite promising resources, the energy
legislative framework is in place, the mechanism is crop sector faces several challenges, including
not widely used, due to lack of administrative clarity. land conversion issues, land suitability and the
availability of financial support.
Streamline administrative procedures and
facilitate their enforcement Encourage the use of and further develop the
online platform for biomass trade
Co-ordination between relevant stakeholders,
including the Ministry of Economy and Lack of proper communication and exchange
Infrastructure, the Ministry of Agriculture, Regional among actors in the biomass market is perceived
Development and Environment, the Ministry of as a major challenge of the sector, even though a
Finance and the transmission system operator is dedicated online platform was recently launched.
required to clarify and simplify some procedures The increased use of the tool would facilitate market
that are perceived by the private sector as an operations and the entry of new fuel suppliers,
administrative burden and hinder the deployment including producers of agricultural residues and
of renewable energy. local public authorities. It would also enhance
Republic of Moldova XV
Wind turbine in Busauca, Rezina
Photograph: Shutterstock
1 If not stated otherwise, data in this report is based on information relating to the right bank of the Dniester River
only. The territory of the Republic of Moldova also includes the region of Transnistria, located on the left bank of
the Dniester River, which declared independence in 1990. However, no United Nations member state recognises
its sovereignty. The report refers to electricity produced by entities located in Transnistria as “purchased from
MGRES”.
Republic of Moldova 1
Figure 1. Evolution of GDP and the MDL/USD The RRA is a country-led and consultative
exchange rate process. It provides a venue for multi-stakeholder
9.00 25 dialogue to identify challenges to renewable
energy deployment and to come up with solutions
20
recommendations are presented to governments to
guide the formation of new policies, or the reform
7.00 of existing ones, opening up a more enabling
environment for renewable energy. The RRA
15
6.00 also consolidates existing efforts and mobilises
resources for priority actions.
5.00 10
2013 2014 2015 2016 2017
The RRA elaboration process was launched at
MDL/USD GDP the request of the Ministry of Economy and
Source: Based on WB (2018b), NBM (2018) Infrastructure of the Republic of Moldova, in the
context of IRENA’s recently initiated South East
Economic activity is shifting progressively towards Europe Initiative (see Box 1). This coincided with
services, a sector that in 2017, accounted for nearly the government’s ongoing efforts to develop and
65% of GDP and provided employment for more finalise renewable energy-related legislation. These
than half of the workforce. The sector is driven by efforts have boosted the dialogue between policy
insurance, legal consultancy and telecommunications, makers and other interested parties, including
with foreign investment playing a substantial role. potential investors, relevant state authorities,
international financial institutions and civil society.
As the country has a moderate climate, along with
favourable climatic and soil conditions, agriculture During the first stage of the process, a background
is also an important sector, accounting for 16% of paper was prepared outlining a general overview
GDP and employing nearly 30% of the workforce, of the Moldovan energy sector, with a special focus
in 2017. The main areas of agricultural production on renewable energy. In addition, an issues paper
include vegetables, fruits, grapes, grain, sugar beets, was elaborated to identify potential barriers and
sunflower seeds, tobacco, beef and milk. bottlenecks that need to be addressed to ensure
successful deployment of renewables. The paper
In 2017, the national employment rate was 40.5% and includes the suggestions of interviewed experts.
the unemployment rate was 4.1%, although the labour
market varies greatly across the country (NBS, 2017). With the aim of validating these findings and
providing an open dialogue among a wide range of
The Republic of Moldova is also the 129th largest stakeholders, IRENA and the Ministry of Economy
export economy in the world. In 2016, the and Infrastructure organised an expert workshop
country exported USD 2.43 billion and imported on 4 June 2018. The main objectives were to discuss
USD 3.95
billion, resulting in a negative trade challenges for renewable energy development and
balance of USD 1.52 billion. Petroleum products are to provide preliminary recommendations on the
listed high among the imported commodities, at required actions to ensure favourable conditions
USD 370 million (OEC, 2016). for the sector. The event provided the opportunity
to review global renewable energy developments,
1.2 Renewables Readiness Assessment highlight the country’s international energy
commitments and present an overview of the
The International Renewable Energy Agency national energy sector.
(IRENA) developed the Renewables Readiness
Assessment (RRA) as a tool for carrying out a Subsequently, a set of recommended actions to
comprehensive evaluation of the conditions for further advance the renewable energy sector
renewable energy deployment in a particular country. was validated by local stakeholders within the
stakeholders.
Republic of Moldova 3
Solar PV application in Chisinau
Photograph: Ministry of Economy and Infrastructure
Figure 3. Total primary energy supply over the 2010-2017 period (ktoe)
2939
2796
2633 2676 2643 2669 2686 297
2624
290
267 277 292 289
285 290
764
537 698
512 650
574 584 629
2 This high ratio is a result of the lack of industry that would use energy for further purposes. In countries that have
such a sector in place, those losses reach up to 20-25% of primary energy.
Republic of Moldova 5
Figure 4. Final energy consumption in 2017, Figure 5. Electricity generation in 2017, by source
by sector
107 217
267 734
27%
17%
Local
Production
18%
55% 1%
1346
The Republic of Moldova is poorly endowed with plants, a non-pumped hydropower plant, and other
fossil fuel energy resources and is highly dependent small-scale renewable energy installations (see
on imported energy, in the form of natural gas, Figure 5). The rest of the electricity was imported
petroleum products and electricity. Almost 70% from Ukraine (27.2%) and purchased from MGRES
of the primary energy supply – 2 012 ktoe of the (54.8%), a power plant located in Cuciurgan (see
total 2 939 ktoe – is imported from neighbouring footnote 1).
countries. Thus, the country is vulnerable to risks
related to energy supply disruption. 2.2 Legal and regulatory framework
Nearly the entire volume of natural gas is imported In 2010, the Republic of Moldova became a full-
from the Russian Federation (from Gazprom). fledged member of the Energy Community, which
About 44% of this fuel is used to generate electricity implies a commitment to transpose core EU energy
and heat, while 28% is used in the residential sector. legislation, the acquis communautaire. Since then
Natural gas consumption has decreased over the all governmental efforts have been focused on
last decade: by 2017, it had declined by 13% of 2010 aligning the national legal framework for energy
levels, or 30% of 2005 levels (NBS, 2012 and NBS, with that of the EU. As a result, competition and
2018). Meanwhile, imports of petroleum products market principles have been introduced, especially
increased in 2017 to 809 272 tonnes, of which 70% in the natural gas and electricity fields, with the
was diesel, 21% was gasoline, and 9% was liquefied objective of unbundling vertically integrated
petroleum gas. The supply of petroleum products entities and introducing liberalised market
is more diversified, however, with imports coming principles.
mainly from Romania, the Russian Federation and
Belarus (ANRE, 2018). The above-mentioned reforms have had a positive
impact on the quality of services provided to
Of the 3.7 billion kilowatt-hours (kWh) of electricity final consumers and businesses and are expected
used in 2017, only 18% was generated domestically, to enhance the investment environment and
mainly by local combined heat and power (CHP) attractiveness of the country as a whole. Between
3 In addition, the Law on Labelling of Energy-related Products (Law No. 44 of 27.03.2014) and the Law on Eco-design for Energy-related Products (Law No. 151 of 17.07.2014)
aim to create an environment to enable lower energy consumption.
Republic of Moldova 7
2.3 Energy development plans other methods, promoting energy efficiency and
renewable energy. In this context, as a Contracting
Approved in December 2018, the Moldova 2030 Party of the Energy Community, the country has
National Development Strategy establishes the transposed EU Directive 2009/28/EC on the
country’s long-term sectoral priorities and is aimed promotion of the use of energy from renewable
at enhancing the quality of citizens’ lives. The sources, which establishes a conducive framework
strategy’s goal is to bring the focus of public policy for the production and promotion of energy from
onto people’s problems, interests and aspirations. these sources. In particular, it introduces:
The document includes four pillars of sustainable • A requirement for the whole EU to reach a share
development: a sustainable and inclusive economy; of at least 20% for renewable energy in its gross
human and social capital; honest and efficient final energy consumption by 2020.
institutions; and a sound environment. In this
context, ten sustainable development goals have • An obligation for all EU members (and
been established at the national level, including: the subsequently Contracting Parties of the Energy
guaranteeing of a quality education; the ensuring of Community) to fulfil their national targets for
efficient governance; the enhancement of people’s renewables and to develop National Renewable
access to infrastructure; and the improvement of Energy Action Plans that set out ways to achieve
labour conditions. their respective commitments.
The Energy Strategy of the Republic of Moldova • A mandatory sub-target of a 10% share for
until 2030 (“The Energy Strategy”), adopted in renewables in transport, for all countries in
2012, indicates three main strategic objectives (see question, by 2020.
Figure 6).
• Sustainability criteria for biofuels to ensure
The first objective relates to enhancing the that they are produced in a sustainable and
security of energy supply, mainly by strengthening environmentally friendly manner.
interconnections with Romania and, implicitly, with
other EU countries. The most important infrastructure In 2012, within the framework of the Energy
development projects are outlined in Section 2.4. Community, the Republic of Moldova pledged to
achieve a 17% share for renewables in gross final energy
The second objective refers mainly to consumption by 2020. It also developed the National
approximation of the legal framework with the Renewable Energy Action Plan (NREAP) for the 2013-
EU acquis, which includes transposition and 2020 period that envisages a set of legal, technical
implementation of the Third Energy Package. The and analytical measures to ensure achievement of the
most important pillars of the package – ensuring the target.4 In addition, in the energy efficiency field, the
prerequisites for market liberalisation – have already National Energy Efficiency Program 2011-2020 and
been introduced to the national legal system. two National Energy Efficiency Action Plans (NEEAP
2013-2015 and 2016-2018) were elaborated, with the
The third objective aims to ensure sustainable objective of achieving a total of 167 ktoe of energy
development of the Republic of Moldova by, among savings by 2020.
5 Two electricity market participants from the Transnistrian region requested and obtained licences from ANRE: MGRES for electricity production and Energokapital JSC for
supply of electricity. This allowed them to generate electricity and to supply it to Moldovan final customers.
6 Energocom has been mandated for three years, until 1 January 2021.
7 MGRES, built during 1964-1982, is the biggest generation capacity located in Transnistria. It has an installed capacity of 2 520 MW, with coal accounting for 1 600 MW, natural
gas for 500 MW and heavy fuel oil for 420 MW. It can be switched to natural gas with an available capacity of approximately 1 700 MW. It is currently owned and operated by
Inter RAO EES Corporation.
Republic of Moldova 9
Figure 7. Wholesale import electricity prices and electricity tariffs for end users
140
121.6 126.0 124.5
120
104.8
108.2 111.7 98.0
100
USD/MWh
89.2
80 68 68
67.3 67.95
60
59.9 47
56.7 49.5
40
20
0
2010 2011 2012 2013 2014 2015 2016 2017
Wholesale import electricity prices, USD/MWh Electricity tariffs for end users (low voltage) USD/MWh
Source: Based on ANRE (2018) and ANRE (2016)
8 Seven additional sugar mill-owned CHP plants with a total installed capacity of 98 MW are available for a limited period of time during the year. In addition, two power plants
are based in Transnistria: MGRES, with total installed capacity of 2 520 MW and HPP Dubasari, with an installed capacity of 48 MW.
330
16
37
Natural Gas
Hydro (non-pumping)
Renewables (non-hydro)
Table 1. Overview of the domestic power generation infrastructure in the Republic of Moldova
1. Termoelectrica JSC
CET - 2 (CHP) in Chisinau 1976-1980 240 MWe 210 MWe natural gas
CET - 1 (CHP) in Chisinau 1951-1961 66 MWe 40 MWe natural gas
4. Non-hydro renewable
2009-2018 37 MW 37 MW
energy power plants
Total 383 MW 327 MW
Note: *An additional capacity of 13.4 MW of internal combustion engines powered by natural gas is to be installed and commissioned at the beginning of 2019.
Source: Based on MoEI (2017) and MoEI (2018a)
Republic of Moldova 11
Grid infrastructure At the same time, the Energy Strategy 2030
envisages plans to strengthen bidirectional
The existing Moldovan power grid infrastructure transmission connections between the IPS/UPS
was mainly built during Soviet times, as part of a and ENTSO-E systems, enabling the Republic
jointly optimised system with the Soviet Union and of Moldova to become a power transit country.
the neighbouring countries of Bulgaria, Hungary Interconnection projects with the EU internal
and Romania. After the dissolution of the Soviet power market through new power lines, as well
Union, all countries in the region redesigned their as the enhancement of internal networks, are
electricity systems. While Bulgaria, Hungary and considered essential both for supply security and
Romania decided to synchronise their networks for social welfare. In addition, interconnection
with the Western system (former UCTE, currently with the ENTSO-E system is expected to enable
ENTSO-E), the Republic of Moldova and Ukraine increased competitiveness that will lead to more
joined the Eastern system (IPS). affordable energy prices.
Despite strong links between ex-Soviet republics In this context, the Moldovan and Ukrainian
and their western neighbours, electricity exchange governments are synchronising their energy
between the two systems is only feasible in “island agendas, especially those related to the
mode”, or via expensive back-to-back converter interconnection of their national power systems
stations. As the smallest country in the region, the with the ENTSO-E grid. In this regard, in June
Republic of Moldova was affected significantly by 2017, the transmission system operators of both
the dismantling of the region’s electricity system countries signed a Memorandum of Understanding
and consequently has inherited a poorly maintained with ENTSO-E confirming their intention.
and unsustainable power network.
Figure 9. Electricity network and power
In particular, because the country suffers from generation facilities in the
insufficient power generation capacity, it uses Republic of Moldova
its interconnections with Ukraine to ensure the
necessary system reserves and balancing energy.
This includes seven 330 kilovolt (kV) lines and
11 110 kV lines (see Figure 9).
Figure 10. Potential power interconnections of the Republic of Moldova with ENTSO-E
IPS/UPS
2
3
ENTSO-E
Source: MoEI (2018b)
Disclaimer: Boundaries and names shown on this map do not imply any official
endorsement or acceptance by IRENA.
Republic of Moldova 13
2.5 Organisational structure of the • Promotes and ensures fair competition
energy sector and efficient operation of energy markets,
monitoring the level and effectiveness of
Below is a list of the most important actors involved market opening, as well as competition, in the
in governing the energy sector. wholesale and retail energy markets.
The Ministry of Economy and Infrastructure is • Issues licences for activities in the energy
responsible for administration of the energy sector, market and monitors compliance with licensing
as well as for elaboration and implementation of the conditions.
necessary measures to ensure the energy security
of the country. In particular, the ministry develops • Monitors the investment plans of system
energy-related policies, strategies, normative acts operators.
and sector programmes and project concepts.9
In addition, the ministry leads international • Sets and approves standards and requirements
collaboration in the energy field, including, but not for distribution, transmission and supply
limited to, the supply of strategic energy resources, activities.
attraction of foreign investment, and facilitation of
power interconnections. • Approves tariffs with the objective of
considering the interests of both producers
The Energy Efficiency Agency provides support and customers.
to the Ministry of Economy and Infrastructure in
implementing energy efficiency and renewable • Supervises customers’ rights and protections.
energy policies. Its mission is to: manage all
activities in the energy efficiency and renewable The Competition Council aims to ensure the
energy sectors; ensure the continuation of country- supremacy of competitiveness principles in the
wide efforts to reach the objectives stemming from energy market, in line with the provisions of the
national strategies and programmes; and guarantee Law on Competition (Law no. 183 of 11.07.2012), as
timely and proper implementation of legislation well as the relevant legislation on electricity and
related to energy efficiency and renewable energy. natural gas.
Moreover, following institutional reform in 2018,
the agency has absorbed the Energy Efficiency Moldelectrica, a state-owned enterprise, performs
Fund. As a result, it also is responsible for providing the functions of a transmission system operator
financial support to the sector – in part through and manages the internal electricity transmission
funds allocated from the state budget, but also network, including the operation of 4 699 km of
through additional resources to be fundraised on 400 kV, 330 kV, 110 kV and 35 kV transmission lines.
local, regional and international financial markets. In August 2018, the government strengthened
ownership independence through the adoption
The National Energy Regulatory Agency (ANRE) of Decision no. 806/2018, with the objective of
is an independent regulatory authority, directly advancing the unbundling process. In a next step,
subordinated to parliament. It is responsible transmission system operators will be further
primarily for the introduction of market regulatory certified by the regulator to prove compliance with
mechanisms that protect the interests of both unbundling-related requirements.
consumers and investors. In particular, the agency:
The state-owned RED Nord10 and privately owned
• Supervises compliance with laws and RED Union Fenosa perform the functions of
regulations in the energy field. distribution system operators (MoEI, 2017).
9 For example, project concepts for development of the power sector, refurbishment of domestic CHP plants, implementation of energy efficiency measures in the
residential sector, etc.
10 JSC RED Nord absorbed another state-owned distribution system operator, JSC RED Nord-Vest, in 2017.
11 Based on an analysis of the Energy Community Secretariat. The national sources, e.g. the Moldovan Energy
Efficiency Agency, indicated significantly lower share.
Republic of Moldova 17
Box 3. The business case for renewables
Renewables have grown at unprecedented (GW), representing more than 29% of the world’s
rates over the past decade, with new records total power generating capacity. The bulk of this
being set each year. An increasing number renewable capacity was from hydropower (53%),
of countries have committed to those followed by wind power (23%) and solar power
developments, too. In 2016, at least 176 countries – mostly solar photovoltaics (PV), at almost 18%.
had renewable energy targets (IRENA, IEA and Between 2010 and 2017, the global installed
REN21, 2018). capacity of solar PV increased almost ten-fold
and onshore wind almost three-fold (IRENA,
The most spectacular changes have occurred in 2018a).
the power sector, where, since 2012, renewables
have outpaced conventional fuels in annual new Thus, the business case for renewables today
global capacity additions in electricity production is stronger than ever, with many technologies
(IRENA, 2018a). achieving spectacular cost reductions. Indeed, the
average costs of utility-scale solar PV and onshore
By the end of 2017, the global installed capacity wind declined by 73% and 22%, respectively,
of renewables amounted to 2 179 gigawatts between 2010 and 2017 (IRENA, 2018b).
Figure 11. Global levelised cost of electricity from utility-scale renewable power generation
technologies, 2010-2018
Offshore Onshore
Bioenergy CSP Geothermal Hydro Solar PV
wind wind
0.40
0.355
0.35
0.330
0.30
0.25
2017 USD/kWh
0.20
0.202
0.166
Fossil fuel power range cost
0.15
0.132
0.10
0.082
0.070 0.069 0.071
0.088
0.050 0.055
0.05
0.050
0.040
0.00
2010 2018 2010 2018 2010 2018 2010 2018 2010 2018 2010 2018 2010 2018
Year 2010 2011 2012 2013 2014 2015 2016 2017 Target
Heating and cooling 34.4 36.1 39.0 39.9 43.6 44.5 45.5 46.1 27
In the power sector, the most-used renewable The deployment of non hydro renewables had
energy technology is wind, with an installed been growing slowly since 2012, but it accelerated
capacity of 27 MW, followed by CHP using biogas greatly in 2016 (see Figure 13). This was due to
and almost 4 MW of solar PV (see Figure 12). investors seeking to obtain support before the new
The Republic of Moldova also has one, 16 MW law on the promotion of the use of energy from
hydropower plant, constructed in the late 1970s. renewable sources came into force in March 2018.
Figure 12. Installed renewable energy capacity, Figure 13. Dynamics of renewable
by source (as of March 2018) energy growth
40
3.9 MW
7%
16.3 MW 27.1 MW
31% 51% 30
Installed capacity, MW
20
10
5.7 MW 0
11%
2010 2012 2014 2016 2018
PV installations Wind installations PV installations Wind installations
CHPs on biogas Hydro installations CHPs on biogas
Republic of Moldova 19
Wind is the level up to which the potential is considered
by the report to be cost-competitive (see Box 4)
Wind is the most abundant renewable energy (IRENA et al., 2017).
source in the Republic of Moldova, with almost
the entire country offering technically suitable With 27 MW currently installed, wind is the most
locations for wind power investments (see widely used renewable energy technology in the
Figure 14). Moreover, as identified in the 2017 Moldovan power sector. This is based exclusively
IRENA report, Cost-competitive renewable power on second-hand turbines imported from European
generation: Potential across South East Europe, countries. With a new support regime (see Section
wind can provide up to 21 GW of power capacity, 3.2), up to 100 MW of new wind capacity is expected
much of which could be deployed with the levelised in the coming years. Further developments are also
cost of electricity (LCOE) below 90 EUR/MWh. This considered for industry self-consumption purposes.
Note: The study covers: Contracting Parties of the Energy Community (Albania, Bosnia and Herzegovina, Kosovo*, Montenegro, the Republic of Moldova, Serbia, the former
Yugoslav Republic of Macedonia, and Ukraine); and member states of the European Union (Bulgaria, Croatia, Romania and Slovenia).
Note that this designation of Kosovo* is without prejudice to positions on status and in line with the United Nations Security Council Resolution 1244 (1999).
Republic of Moldova 21
Box 5. Republic of Moldova Energy and Biomass Project
Over the last decade many development In addition, the project resulted in:
partners supported the Moldovan authorities
in replacing coal- and gas fired boilers, as well • Promotion of the use of bioenergy and
as basic stoves, with biomass heating units that increased awareness and social acceptance.
burn straw, pellets, briquettes and firewood.
• Vocational training for biomass boilers
One of the most important projects in this regard operators and foresters.
was the Energy and Biomass Project, financed
by the European Commission and implemented • Launch of the Biomass Energy Cluster and the
by UNDP. This aimed to increase the use of Bioenergy Association.
energy from biomass sources and laid the basis
for establishing functional markets for biomass • Creation of a web platform to connect biomass
technologies. Furthermore, it envisaged the energy producers and consumers.
creation of jobs and value-added chains at the
local and regional levels through the supply of • Several companies assembling and
biomass fuel and technologies (UNDP 2018a, manufacturing biomass boilers.
UNDP 2018b).
• Inauguration of public-private partnerships
With a total budget exceeding USD 28 million, for the provision of bioenergy services.
within its first phase (2011-2014) and second phase
(2015-2018), the project provided support for the • Accreditation of the first testing laboratory
installation of biomass-based heating systems for the physical and chemical parameters of
in more than 250 buildings – mostly schools, biofuels (see Figure 15).
kindergartens and medical facilities. Moreover,
almost 1 000 small residential boilers were installed
thanks to subsidies for renewable energy heating.
Overall, the installed capacity of equipment during
this period was 41.2 megawatts-thermal.
Figure 15. The Solid Biofuel Laboratory at the State Agrarian University of the Republic of Moldova
Long-term average
GHI kWh/m2
1225
1250
1275
1300
1325
1350
1375
1400
Source: IRENA, Global Atlas; map data: World Bank S map (2018); base map: OpenStreetMap (2018). Available at: http://irena.masdar.ac.ae/?map=3103.
Disclaimer: Boundaries and names shown on this map do not imply any official endorsement or acceptance by IRENA.
Republic of Moldova 23
Hydropower 3.2. Renewable energy support
mechanisms in the power sector
Despite its large number of rivers, the Republic of
Moldova has only one reservoir hydropower facility, Until March 2018, power generation from renewable
a 16 MW plant located in Costesti on the Prut River, sources was supported by the Renewable Energy
the second most important river in the country. In Law of 2007 (No. 160-XVI of 12.07.2007). The law
addition, 254 kilowatts (kW) of small hydropower envisaged the cost-plus principle.13 Under this, ANRE
installations are in operation (ANRE, 2017). issued a tariff for 15 years – based on the actual eligible
costs incurred – only after the investments had been
The best areas for development are located in the made. In addition, the regulator had the right to adjust
Dniester, Prut and Danube river basins, with the the tariff to regional benchmarks, if they were lower.
country’s total potential estimated at 3.36 terawatt- This approach was not sufficient to attract investments
hours per year (Ceban, 2015). As envisaged by the in the sector and was therefore revised.
Energy Strategy 2020, some mini-hydro stations,
totalling 1.2 MW in capacity, were planned for the The Law on the Promotion of the use of Energy from
Raut River, close to the village of Tribujeni in the Renewable Sources (Law No. 10 of 26.02.2016),
Orhei district (UNECE, 2009). came into effect in March 2018 in the form of a
tariff-based scheme and net metering. The law also
Geothermal provided the necessary guarantees for investments,
including: non-discriminatory grid connection;
The geothermal energy resource potential of the priority dispatch; and an obligation for the central
Republic of Moldova has been poorly investigated, electricity supplier to purchase all-renewable-
with no comprehensive quantified estimate existing. generated electricity for 15 years. In addition, the
Nevertheless, the country has significant availability new market-based scheme promotes competition
of low enthalpy geothermal potential, especially among investors, as it envisages auctions for projects
in the southern part of the country, which could above 4 MW in the case of wind and 1 MW for other
be widely used by heat pumps. The government’s technologies. At the same time, the law supports the
focus on this technology is limited, with no actions development of small-scale, community-promoted
envisaged in the National Action Plan for Renewable renewable energy projects.
Energy. The Energy Efficiency Agency, however, has
identified four operational geothermal installations, Figure 17 represents the support mechanisms
with a total installed capacity of 142 kW (EEA, 2016). under the 2016 law.
Figure 17. Graphic representation of the support mechanisms in the Republic of Moldova
Installed Capacity
Quotas (MW)
Threshold
# Type of technology for small
Classic installations
Auctions
feed-in tariff
1 Wind 20 80 4
2 Solar PV 15 25 1
3 Biogas installations 12 8 1
5 Small hydro 3 – 1
TOTAL 55 113 –
14 It also sets out a methodology for determining ceiling prices for auctions.
Republic of Moldova 25
Source: MoEI (2018c)
Box 6. Policy Guidelines on Competitive Selection and Support for Renewable Energy
In March 2018, the Policy areas of auction design: the competitive process
Guidelines on Competitive framework; procurement choices; selection
Selection and Support process choices; and the delivery mechanism for
for Renewable Energy renewable energy support.
were prepared jointly by
the EBRD and the Energy Guidelines are already being used in the policy
Community Secretariat, in work of the EBRD and the Energy Community
collaboration with IRENA Secretariat. In Albania and the former Yugoslav
(ERBD et al., 2018). Republic of Macedonia, EBRD is using the
guidelines to assist local authorities. In Ukraine,
Intended for countries of the guidelines are informing discussions on the
the Energy Community policy framework for supporting renewables.
Treaty that are also EBRD In the Republic of Moldova, EBRD has recently
countries of operation, these Guidelines build initiated its efforts to support the country in
on IRENA’s Renewable Energy Auctions: A Guide designing renewable energy auctions for onshore
to Design (IRENA and CEM, 2015). They provide wind and solar PV, including preparation of the
recommendations for governments in four required tender documentation.
Establishing of
Launching of the
the capacity Elaboration of
tendering
limits and tendering
procedure
maximum documentation Submission of
Offers
capacity quotas the offers and Signing of the
/Status - IN evaluation
/Status - IN their contract
PREPARATION, and awarding
/Status - DONE, PROCESS, qualification
Expected
Responsible Responsible
timeframe -
entity - MoEI, entity - MoEI/
mid. 2019 /
Government/
The recently approved regulation on tendering Figure 18. Additional tendering documentation and
(Government Decision No. 690 of 11.07.2018) an auctions calendar are yet to be prepared by the
provides an initial framework for organising auctions national authorities.15
that grant “eligible producer” status on large
investors. This is done through the establishment Auctions will be carried out by the Tendering
of unequivocal, objective, transparent and non- Commission, which comprises representatives of:
discriminatory procedures, conditions and criteria. the Ministry of Economy and Infrastructure, the
Ministry of Agriculture, Regional Development and
Under the new regulation, development of Environment, the Agency of Land Relations and
the renewable energy auctions will be carried Cadastre, the Energy Efficiency Agency, and the
out in compliance with the steps presented in Public Property Agency. Any bid that meets the pre-
15 As of December 2018.
Financial credibility
• Proved financial viability (equity, credits, guarantees)
• Business plan
• Project financing plan
Connection to grid
• Connection notice from the relevant TSO
Pre-qualification
criteria Technical credibility
• Compliance with technical requirements
• Feasibility study
• Proof of purchase/purchase intention of the equipment
Eligibility of location
• Ownership/right to use the land
• Proof of land designation change, if necessary
16 Manufactured no more than 48 months before the start-up of the power plant.
Republic of Moldova 27
3.3. Financing of renewable energy • MoSEEFF – the Moldova Sustainable Energy
Efficiency Financing Facility. With a total
Most of the renewable energy projects in the budget of EUR 42 million, this aimed to support
Republic of Moldova were financed by multilateral the use of renewables by local enterprises.
development banks or bilateral development Solar was one of the focus areas, and a diverse
agencies, or were self-financed by the private range of projects was implemented through
sector. Examples of the first source of funding the programme, from a 100 kW rooftop power
include the EBRD, the European Investment Bank plant installed on an agriculture warehouse, to a
(EIB), and the World Bank Group, while examples 500 kW solar PV farm installed on the grounds
of the second include the Swedish International of a carpet manufacturer.
Development Cooperation Agency and the
Japanese International Cooperation Agency • MoREEFF – the Moldova Residential Energy
(JICA). Private sector funding was used mainly in Efficiency Financing Facility. This had a total
the case of biogas and solar. budget of EUR 35 million and targeted the
residential sector during the period 2012-2017.
While some of these partners provided grants for
the financial products developed in collaboration In addition, the Republic of Moldova is one of the
with local commercial banks, others set up credit beneficiaries of the Green Climate Fund (GCF)
lines to support both renewables and energy EBRD Sustainable Energy Financing Facilities
efficiency. For example, the EBRD’s financing tools, programme. This is set to direct USD 1.4 billion to
implemented together with BCR Chisinau, Moldova financing facilities with local financial institutions
Agroindbank, Moldindconbank, ProCredit Bank in Armenia, Egypt, Georgia, Jordan, the Republic
and MobiasBanca, include: of Moldova, Mongolia, Morocco, Serbia, Tajikistan
Republic of Moldova 29
Wind turbine and transmission lines
Photograph: Shutterstock
With the costs of renewables falling rapidly over the past decade,
these technologies offer cost-competitive energy supply solutions
in an increasing number of countries, worldwide. The trend is set to
grow, too, as technological innovation continues to drive the next
generation of cost declines.
Republic of Moldova 31
• Adopt a renewable energy target for 2030 any potential operational constraints that could
result in the unavailability of sufficient power to
Since the renewable energy target of 17% by meet demand.
2020 has already been overachieved, it neither
provides long-term predictability, nor reflects the This study, including economic dispatch,
country’s vision of energy sector development. would allow investigation of multiple scenarios
The fact that the current share of renewables for the generation mix, including those with
(27.8%) was reached mainly through the revision higher shares of renewables, as well as any
of biomass consumption data adds another other policies and sensitivities. The modelling
level of uncertainty. Although the announced normally covers one year – with a higher
development of 168 MW of renewables capacity time resolution to provide more insights on
in the coming years has captured the interest of operational cost impacts – and aims to ensure
several investors, this could be considered a one- that the system load is supplied entirely and
off boost to the market, rather than an element most economically. The analysis would also
of a solid strategy. address the issue of ancillary services and
balancing, which are becoming increasingly
Therefore, the ongoing activities undertaken important with the deployment of intermittent
by the Ministry of Economy and Infrastructure, renewables and the increasing availability of
as well as the discussions within the Energy distributed generation.
Community, are undertaken with a view towards
agreeing on a new renewable energy target The results could help build confidence among
for 2030. IRENA’s recently initiated regional policy makers, system operators and investors,
REmap analysis for the countries of Central and as well as identify the most cost-effective
Southeast Europe, including the Republic of option for balancing the system. The study
Moldova, would contribute to these efforts and should consider the ongoing efforts to ensure
help identify cost-effective technology options interconnection and asynchronous operation
for the deployment of renewables in the power with Romania, expected within the next
and end-use sectors. The future long-term four to five years, as well as the plans of the
framework for renewables could also emphasise governments of the Republic of Moldova and
the important role that distributed generation Ukraine to ensure synchronous operation with
across the country can play in consolidating the ENTSO-E, in the long run.
national power system.
To support countries in assessments of power
• Conduct a production cost modelling study system flexibility, IRENA and the VTT Technical
Research Centre of Finland Ltd. have developed
Renewables are becoming an increasingly cost- the FlexTool. This analyses not only the
competitive source of energy in the Republic of traditional concept of flexibility (concerning,
Moldova and are poised to play a greater role in for example, flexible thermal and hydropower
the national power system. generation with high ramping capability
and very low start-up time), but also other
From a technical perspective, some research innovative technologies that enrich the concept
studies indicate that the system could absorb of flexibility. These include flexible demand,
around 1 GW of renewables – a level almost energy storage and sector coupling. The
equal to the maximum load, which reaches FlexTool is capable both of analysing system
1
100 MW (Gropa, 2017). The increased use operations using a time step that represents
of solar PV and wind technologies, however, real-world challenges (an hour or less in the
would present a new challenge, as the country case of VRE variability) and of carrying out long-
completely relies on Ukraine for balancing its term analyses and proposing possible flexibility
generation. Thus, the country should carry out solutions in a hypothetical future system with
a production cost modelling study to determine high VRE penetration (IRENA, 2018c).
18 As of December 2018. In addition, the recently approved regulation on tendering (Government Decision no. 690 of 11.07.2018) provides an initial framework for organising
auctions that grants an “eligible producer” status to large investors through the establishment of unequivocal, objective, transparent and non-discriminatory procedures,
conditions and criteria.
Republic of Moldova 33
• Streamline administrative procedures and assessments of the social and environmental
facilitate their enforcement impacts of a new power plant, are too lengthy.
The relevant national authorities are not seen
The lack of effective co-ordination among as having sufficient capacity to issue permits
different actors hinders the deployment of in a timely manner. Therefore, strengthening
renewable energy in the country. As a result, the capacity and optimising internal procedures,
private sector highlights some procedures as with the support of external technical
too costly and lengthy, or even catalogues them assistance, if necessary, could ensure that the
as an administrative burden. To ensure better legally set time frame and other requirements
harmonisation, the Ministry of Economy and are respected. In particular, efforts should be
Infrastructure is advised to initiate a dialogue focused on the practical implementation of the
with the Ministry of Agriculture, Regional provisions of the EU’s Directive 2014/52/ EU
Development and Environment, the Ministry of on the Assessment of the Effects of Certain
Finance, and Moldelectrica to clarify and simplify Public and Private Projects on the Environment,
such procedures. This effort could be part of the adopted by the Republic of Moldova in October
forthcoming revision of the National Renewable 2017, including the arrangements for early and
Energy Action Plan and the development of an effective opportunities for public participation
integrated National Energy and Climate Plan, (EnC, 2018).
and may include the following aspects:
3. Taxation
1. Land use designation
Incentives of a customs and fiscal nature
The national Land Code (Law No. 828-XII of are envisaged in the legislation,20 to ensure
25.12.1991) envisages the use for agriculture additional support to wind and solar PV
purposes only of sites/land parcels with a Soil investments. These incentives include reduced
Potential Index exceeding 60 points.19 As a customs fees at import, exemption from value-
consequence, most of the areas with abundant added tax on installation work and other inputs
wind resources might not be available for the for renewable energy projects. Yet, some of the
construction of renewable energy power plants, relevant provisions are considered unclear by
due to their status as agricultural land, despite both the investor community and the authorities
the vast economic feasibility associated with the responsible for implementation. In particular,
renewable energy business in such areas. Even specific technologies and sizes of projects are
with the presence of wind farms, however, land not treated in a coherent way. For example,
can fulfil other functions, such as agriculture: a project with only one wind turbine does
only some 10% of such land is occupied by wind not correspond to the “wind park” definition,
power equipment, while the remaining 90% is according to the interpretation of the Moldovan
available for grazing or cultivation. Moreover, Fiscal Service. Thus, a univocal understanding
a power plant could generate additional of those provisions has to be ensured, either
income for land owners and taxes for local by amendment of the legislation, or by
municipalities. elaboration of a fiscal practice to be followed
by the national fiscal authorities. Furthermore,
2. Environmental impact assessment any future changes in tax legislation should be
introduced with a sufficient vacatio legis21 to
The perception of stakeholders in the sector enable adaptation of the business models used
is that current procedures, in particular by investments already under development.
19 The Soil Potential Index, or SPI, is a calculation which rates soil on a scale of 0-100 points based on its capability to produce crops. For example, a rating of 10 would indicate
a soil poorly suited to growing crops, while a rating of 95 would mean top quality soil with virtually no impediment to crop production.
20 Law No 172 of 25.07.2014 on the Approval of the Combined Nomenclature of Goods and The Fiscal Code of the Republic of Moldova, No. 1163 of 24.04.1997.
21 Latin, meaning “absence of law”. Refers to the period of time between a law’s promulgation and it taking effect.
Republic of Moldova 35
of land, those authorities could strengthen their The online platform could also facilitate
commitment to developing the local industry the market operation and entry of new fuel
and would benefit from locally harvested, suppliers, including producers of agriculture
cost-competitive heating resources; public residues and local public authorities, as
institutions in more than 250 communities in well as enhance fuel price competition and
the country use biomass boilers for heating supply liquidity. In addition, this platform can
purposes. More common use of public-private offer a source of information on the benefits
partnerships and inter-municipal co-operation stemming from the use of bioenergy and be
would also facilitate development of this sector. a repository of available opportunities for
local consumers to switch to this source of
Finally, the programme should build on a energy. This type of bridge between biomass
comprehensive assessment, providing clarity on producers and potential customers would
the most suitable technology for each potential contribute to more stable and increasing
group of beneficiaries. As raised by stakeholders, demand. Furthermore, the platform could be
due to a large diversity of raw material, as well further developed based on best practices in
as different consumption profiles, there is a lack biomass exchange platforms, including the
of understanding of the available options. Some experience of Lithuania in the development of
failures to match beneficiary and technology the Baltpool biomass exchange (Energypost,
have turned out to be costly in the past. Thus, the 2017).
analysis should consider: all types of properties;
different groups of beneficiaries; several • Identify an optimal pathway to increase the
technologies, such as organic Rankine cycle role of biofuels
(ORC), pyrolysis, Stirling, and steam mini turbines;
and different consumer profiles. This exercise The country has committed to reach a 10%
will help determine different business models share of renewables in the transport sector by
for using biomass as a sustainable alternative – 2020, but no actions have been taken so far to
including in district heating – and provide clear promote the use of liquid biofuels. At present,
recommendations for implementation, based if the widespread perception that the country
possible, on successful pilots. lacks suitable areas to grow sugar cane and
rapeseed continues to hinder development in
• Encourage the use of and further develop the this area. In addition, with no infrastructure in
online platform for biomass trade place to cultivate such crops, adaptation costs
for the existing infrastructure would decrease
A major challenge for the sector is the lack of the competitiveness of locally produced liquid
proper communication and exchange among biofuels against imports, opponents say.
actors in the biomass market, even though a
dedicated online platform was recently launched. There is, however, a clear understanding of
The limited use of this tool causes considerable the need to find an adequate approach to
disruption to the value chain, as suppliers of ensure more sustainable use of energy sources
raw material and producers of fuel struggle to in this sector. An assessment is therefore
find effective communication channels – and as recommended, in order to identify an optimal
final beneficiaries face problems in identifying pathway towards the use of biofuels in transport.
reliable sources of biomass fuel. The country is The options currently under discussion include:
advised to actively promote the platform and full reliance on domestic production; import of
to encourage potential users to increase trade bioethanol and biodiesel; or a combination of
in all types of biomass, taking into account the two options, in light of the local production
factors such as price, quality, region of origin potential and price affordability. The results
and transport. With the expected development of the assessment could provide a clearer
of the energy crop industry, widespread use of indication of the potential way forward for the
such a tool is even more necessary. biofuels sector.
Republic of Moldova 37
by the limited knowledge of the renewable 4.5 Public awareness
energy sector and poor understanding of the
support mechanisms among local lenders who Due to technological developments and rapidly falling
appraise projects. Thus, technical support in, for costs, renewables are a viable energy choice for a
example, developing bankable project proposals growing number of countries, cities, companies and
and in structured finance principles, including households. The deployment of renewable energy is also
project finance, can increase the capacities of an effective tool to fuel economic growth, create new
local commercial banks. This support could be employment opportunities, enhance human welfare
facilitated by international financial institutions and contribute to a climate-safe future. Renewables are
that are well placed to provide such technical already a significant source of new employment, with
assistance. In addition, aside from long-tenor renewable energy jobs standing today at 10.3 million,
concessional loans provided at below commercial worldwide. Only a limited number of stakeholders in the
rates to local financiers, international financial Republic of Moldova, however, are aware of the socio-
institutions, such as development finance economic benefits that renewable energy can offer.
institutions (DFIs), can utilise hybrid, on-lending
and syndication structures to facilitate a more As the use of biomass for heating is perceived positively
active involvement from local investors. Such in the country and has allowed the development of a
structures include: significant number of local businesses around this
sector, the most advanced efforts to increase public
1. Mezzanine finance, whereby a DFI’s claim is awareness have occurred in the field of bioenergy.
subordinated to senior debt (provided by the Nevertheless, more needs to be done to increase the
local financier), but still senior to equity claims public acceptance and use of renewable energy to
on project cashflows. facilitate its long-run development.
2. On-lending structures, whereby DFIs can use • Develop a national communication strategy on
their high credit rating to borrow internationally renewable energy sources
at low rates and then on-lend the funds to
local financiers via credit lines, at lower rates Public awareness is necessary to influence political
than such financiers would otherwise face. decisions on strategies for the country’s future
development. A national strategy is needed to raise
3. Syndications (or co-financing) with local awareness and boost understanding of renewable
financiers to help spread the risks and energy sources and their benefits across the Republic
returns. This would also spread knowledge of of Moldova. This would also help consumers make
renewable energy financial structuring among more informed decisions regarding energy supplies and
a wider group of capital providers. DFIs should benefit from the opportunities offered by the sector.
be careful not to displace (i.e., crowd out) the
local private sector, or distort the market, but The strategy should address several stakeholders,
to instead act to crowd-in local investors and including state authorities, civil society, the banking
hence kick-start the local market. community and donors. It could envisage necessary
actions to ensure proper ways to disseminate the
Finally, public capital, including that provided most up-to-date information on renewables and the
by the DFIs, could be used to help de-risk or ongoing energy transition (e.g., a dedicated website,
lower the risk of renewable energy projects. This with translations of authoritative publications
would lower the cost of capital for renewables, into local language). It could also improve the
via the provision of risk mitigation instruments. curriculum of schools and universities to reflect
Such instruments could include: partial risk the growing role of renewables. At the same time,
guarantees for uncertain grid access; credit intensified government communication efforts on
guarantees to lower the power off-taker non- ongoing legislative changes would be beneficial for
payment risk; liquidity facilities to bridge short- stakeholders. This is especially so for local financial
term cash flow problems; and currency hedging institutions, as they prepare the relevant mechanism
instruments, to name but a few. to finance renewable energy projects.
Republic of Moldova 39
IRENA et al. (2017), Cost-competitive renewable power generation: Potential across South East Europe,
International Renewable Energy Agency, Joanneum Research and University of Ljubljana, Abu Dhabi,
www.irena.org/-/media/Files/IRENA/Agency/Publication/2017/IRENA_Cost-competitive_power_
potential_SEE_2017.pdf.
IRENA and CEM (2015), Renewable Energy Auctions – A Guide to Design, IRENA, Abu Dhabi,
www.irena.org/-/media/Files/IRENA/Agency/Publication/2015/Jun/IRENA_Renewable_Energy_
Auctions_A_Guide_to_Design_2015.pdf.
Lupusor, A. et al. (2016), Moldova Economic Growth Analysis, Expert-Grup, Chişinău,
www.expert-grup.org/media/k2/attachments/MEGA_XIV_-_April_2016_EN.pdf.
MoEI (2018a), Overview of the energy sector and renewable energy developments in the Republic of
Moldova, presented by Mr Denis Tumuruc, Deputy head of Energy Policies Department, Ministry of Economy
and Infrastructure, at the Expert Consultation Workshop, 4 June 2018, MoEI, Chişinău, unpublished.
MoEI (2018b), General overview of the sector and its competitive advantages, presented by Mr. Vitalie
Iurcu, State Secretary, Ministry of Economy and Infrastructure, at the Moldova Business Week, 28 November
2018, MoEI, Chişinău, www.mbw.md/en/presentations/ (accessed 31 December 2018).
MoEI (2018c), Renewable energy share for 2017, MoEI, Chişinău, unpublished.
MoEI (2018d), Information provided by Ministry of Economy and Infrastructure, December 2018,
unpublished.
MoEI (2017), Security of Supply Statement of the Republic of Moldova, MoEI, Chişinău.
www.energy-community.org/dam/jcr:038ab4ac-868f-4103-92c3-006fd19a9f0b/2017_SoS_ML.pdf
(accessed 31 December 2018).
Moldelectrica (2018), Indicatorii tehnico-economici, www.moldelectrica.md/ro/network/annual_report
(accessed 31 December 2018).
NBM (National Bank of Moldova) (2018), Official exchange rates for years 2013-2017, NBM, Chişinău,
www.bnm.md/en/content/official-exchange-rates (accessed 31 December 2018).
NBS (National Bureau of Statistics) (2018), Energy balance of the Republic of Moldova for 2017 year,
NBS, Chişinău, www.statistica.md/public/files/publicatii_electronice/balanta_energetica/BE_2018_eng.pdf
(accessed 31 December 2018).
NBS (2017), Population and demographic processes, NBS, Chişinău, http://statbank.statistica.md/
pxweb/pxweb/en/20 Populatia si procesele demografice/20 Populatia si procesele demografice__
POP010/?rxid=b2ff27d7-0b96-43c9-934b-42e1a2a9a774 (accessed 31 December 2018).
NBS (2012), Energy balance of the Republic of Moldova for 2011, NBS, Chişinău,
www.statistica.md/public/files/publicatii_electronice/balanta_energetica/BE_2012_eng.pdf.
OEC (2016), Observatory of Economic Complexity, https://atlas.media.mit.edu/en/profile/country/
mda/#Economic_Complexity_Ranking (accessed 31 December 2018).
UNDP (United Nations Development Programme) (2018a), Energy and Biomass (Phase 1), UNDP Moldova,
www.md.undp.org/content/moldova/en/home/operations/projects/climate_environment_energy/
proiecte-finalizate/moldova-energy-and-biomass-project01.html (accessed 31 December 2018).
UNDP (2018b), Energy and Biomass (Phase 2), UNDP Moldova, www.md.undp.org/content/moldova/en/
home/projects/moldova-energy-and-biomass-project2.html (accessed 31 December 2018).
UNDP (2017), Energy and Biomass Newsletter, No. 36, November-December 2017, www.md.undp.org/
content/moldova/en/home/library/climate_environment_energy/energy-and-biomass-newsletter/energy-
and-biomass-newsletter--no-36.html (accessed 31 December 2018).
UNDP and ECS (2016), Energy consumption in households, Results of the Survey on energy consumption,
UNDP Energy and Biomass Project and Energy Community Secretariat, www.md.undp.org/content/dam/
moldova/docs/Publications/Energy consumption households.pdf (accessed 31 December 2018).
Republic of Moldova 41
Annex. Key development steps for
renewable energy projects in the
Republic of Moldova
Renewable energy power plants Renewable energy power
with capacity of 5 MW and higher for plants with capacity below 5 MW
public consumption and 20 MW and for public consumption and below
No. higher for internal use 20 MW for internal use
Change of land destination from agricultural land to land for construction purposes
Competent institution: Government of Moldova or Local Public Administration
2.1 Other institutions involved: Central or local public authorities, Design Institute for Territorial
Planning, State Environmental Inspectorate of Moldova, General Inspectorate for Emergency
Situations, National Public Health Agency, Public Services Agency
Urban Planning Certificate for Design Documentation
Competent institution: Local public authority
3 Other institutions involved: National Public Health Agency, Agency for Environment
(Protection), General Inspectorate for Emergency Situations, Design institute “Urbanproiect”22
or “Chişinăuproiect”23
Detailed designing
4 Competent institution: Licensed institutions
Other institutions involved: Not applicable
Construction authorisation
Competent institution: Local public authority
5
Other institutions involved: Agency for Technical Supervision, Agency for Environment
(Protection)
24 Thermal power plants, industrial and heating boiler plants with capacity of 300 MW and above; complex hydrotechnical structures (ports, big dams and water storage
facilities); industrial sewage and wastewater treatment facilities in urban and rural areas, with a discharge of 10,000 cubic metres per day and higher; waste treatment and
incineration plants; any construction activity in river basins, within river and water basin protection areas; power transmission lines with a voltage level of 330 kV and higher,
wind farms with a height bigger than 20m, etc.
25 The difference between “fixed tariffs” and “fixed prices” supporting schemes is being determined by the power plant capacity and capacity limits set by the Government
through its decision no. 689 as of 11.07.2018
26 According to a MoEI initiative on amending national legislation related to power generation, launched in 2018, renewable energy project developers that won the tender
receive the government approval mentioned at pt. 6.1 automatically (ex officio).
Republic of Moldova 43
Renewable energy power plants Renewable energy power
with capacity of 5 MW and higher for plants with capacity below 5 MW
public consumption and 20 MW and for public consumption and below
No. higher for internal use 20 MW for internal use
Entering into force of the electricity supply contract and into operational phase
Competent institution: Central Electricity Supplier
12
Other institutions involved: Not applicable
27 Moldelectrica, which holds the license for electricity transmission and dispatch services in the Republic of Moldova.