Master Planning Process: Stage 1 Part A Key Findings
Master Planning Process: Stage 1 Part A Key Findings
Master Planning Process: Stage 1 Part A Key Findings
▪ In the medium term, new facilities for Emergency and Diagnostic Imaging
departments should be provided
▪ The new addition will also create: new main entrance and lobby new power plant, mechanical
penthouse; space for support services
▪ Services in Heritage House transferred to new facilities and Heritage House is turned over to the
Town of Petrolia
Phase 3
10 – 15 years, Anticipated improvements include:
▪ Construction of a new addition between existing diagnostic imaging and the eye centre that will
expand diagnostic imaging and laboratory, and provide administrative space
▪ New addition south of continuing care that will provide added space and house non -clinical
services
Long-term Concept
25+ years
▪ Hospital redevelopment complete, all services and departments up and running.
What is the Project Trying to Achieve?
Hospital MASTER PLAN objectives: