SAIC-A-2011 Rev 6 Pressure Test
SAIC-A-2011 Rev 6 Pressure Test
SAIC-A-2011 Rev 6 Pressure Test
EQUIPMENT ID NUMBER(S) EQUIPMENT DESCRIPTION EQPT CODE SYSTEM ID. PLANT NO.
LAYOUT DRAWING NUMBER REV. NO. PURCHASE ORDER NUMBER EC / PMCC / MCC NO.
SCHEDULED INSPECTION DATE & TIME ACTUAL INSPECTION DATE & TIME QUANTITY INSP. MH's SPENT TRAVEL TIME
SAUDI ARAMCO USE ONLY
SAUDI ARAMCO TIP NUMBER SAUDI ARAMCO ACTIVITY NUMBER WORK PERMIT REQUIRED?
ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.
A Test Preparation - General Requirements ... USE SATR-A-2001, 2002, 2003, 2004, 2005 & SATR-A-2006 as req'd.
Expansion joints and spring hangers or spring supports are provided with
SAES-L-150,
A7 temporary restraints where needed to prevent excessive travel or
Para. 6.4
deformation under the test loads. (Field Verify)
All joints including welded joints are accesible and left exposed for visual
leak detection during the strength test. External coating and priming of SAES-L-150,
A8
such joints are not allowed unless approved. Para. 7.3
Note: This excludes joints subject to 24-hr recorded test
Work permit is obtained for pressure testing and associated work within G.I.-2.102,
A9
restricted areas, as per G.I. 2.100, Work Permit System. Para. 5.1.6
Page 1 of 8
MSDS or Chemical Hazard Bulletins is available/reviewed for all
chemicals handled (corrosion inhibitor, bactericide, chlorine, oxygen G.I.-2.102,
A12
scavenger, etc). Written procedure to safely handle chemicals during Para. 5.1.9
testing & to ensure proper disposal after testing is approved.
Page 2 of 8
SAUDI ARAMCO ID/PID - REV - 18-May-05 (Standards Cutoff -March 2012) Rev 6 31-Mar-12
ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.
Access/Egress for Test areas is marked & warning signs posted to alert G.I.-2.102,
A 14
approaching personnel of pressure testing activities. Para. 5.1.11
Pressure testing manifolds were separately pressure tested to at least SAES-A-004 Para
C1
1.2 times system test pressure. (Manifold Test Report/Cert) 5.5.4
Page 3 of 8
SAUDI ARAMCO ID/PID - REV - 18-May-05 (Standards Cutoff -March 2012) Rev 6 31-Mar-12
ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.
D Test Relief Valve(s)
Relief valve is located in the system under test and near the test pump
G.I.-2.102,
D1 with Isolation valves on the inlet and outlet of the relief valve sealed open
Para. 5.1.5.1
during the test. (SAEP-1160, Bullet Item # 3)
Relief valve(s) of adequate capacity (*SIS Sheet & Calcs available) are
set to relieve at 5%* above the hydrotest pressure. SAES-A-004 Para
D2
*Note: Test pressures less than 85% of SMYS can have relief valves 5.5.1
set at 10% above test pressure. Verify SIS sheets calcs.
Relief valve(s) are tested, dated, and tagged (as valid) for a period of one SAES-A-004 Para
D3
week for project pressure tests. Stickers are legible & valid. 5.5.1
A minimum of two pressure gages are required for test systems, with
accuracy within 5% of one another.
Note 1: When large systems are tested, Inspection personnel will
determine the need for additional gages.
SAES-A-004 Para
E1 Note 2: Elevation changes (hydrostatic head considerations) &
8.1.5.4
hot weather create pressure testing problems with frequent popping of
relief valves. For this reason, gage accuracy within 2% is best.
Note 3: Careful handling of delicate instruments like test gages is
practiced by test crews. No gage damage or mishandling is found.
Pressure gages and pressure recorders are calibrated within (1) month SAES-A-004 Para
E2
prior to test. Stickers applied indicate latest calibration date. 8.1.5.2
G.I.-2.102,
Avoid the following typical examples of poor practices:Testing equipment
Sec.4 &
E3 with the test gauge located at the bottom of the equipment reading the test
SAES-A-004,
pressure,including the head of test water
Para 5.3
All gages have a range such that the test pressure is within 30% to 80% of SAES-A-004 Para
E4
the full range. 8.1.5.3
F Temperature Gages and Recorders (When Required, ie: 24-hr Recorded Tests)
REMARKS: Critical Safety Note 1: Surveys of test manifolds used on projects have resulted in many findings of inadequate ratings for isolation valves.
Test manifolds for testing specific pressure rating Classes require isolation valves of the next higher class. Example: Manifolds for testing Class 300 #
systems require Class 600 # isolation valves as a general rule. For Pressure tests against closed seats follow the 110% rule for safe test pressure
calculation. See ASME B16.34, Para 7.2 as applicable. Also, this same requirement must be carefully considered when determining test pressures where
an isolation valve serves as a test boundary limit and the valve seat will be pressurized. Ensure system test pressures are reduced to 110% as applicable
and show the valve seat as the test "limiting factor". Safety Note 2: Fabricated test implements of proper code construction receive
inspection and properly identification/marking for pressure rating, inspection acceptance/fitness (Insp Ok, initial, date). Never allow uninspected non-code
test implement use or those that are unfit for testing (deteriorated, damaged, heavily corroded). Unsafe/unfit test implements found are reported/removed
ASAP from Company Projects.
REFERENCE DOCUMENTS:
1. SAES-A-004, General Requirements for Pressure Testing, (30-Jan-2011)
2. GI-2.102, Saudi Aramco General Instruction-Pressure Testing Safely, (28 October, 2008)
3. SAES-L-150, Pressure Testing of Plant Piping and Pipelines, (25-April-2010)
4. Pro Forma Contract Schedule Q (Project Specific)
5. SAEP-1160-- Tracking and Reporting of Welding, NDT and Pressure Testing for Capital Projects (10-July-2011)
Page 4 of 8
SAUDI ARAMCO ID/PID - REV - 18-May-05 (Standards Cutoff -March 2012) Rev 6 31-Mar-12
ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.
*Person Responsible for Completion of Quality Work / Test Y = YES N = NO F = FAILED
Page 5 of 8
SAUDI ARAMCO ID/PID - REV - 18-May-05 (Standards Cutoff -March 2012) Rev 6 31-Mar-12
SAIC NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO INSPECTION CHECKLIST
Inspection of Pressure Test Preparation SAIC-A-2011 30-Apr-13 MECH-
Attachment 1 - SAEP-1160 Test Pkg Minimum Requirements
Page 6 of 8
SAUDI ARAMCO ID/PID - REV - 18-May-05 (Standards Cutoff -March 2012) Rev 6 31-Mar-12
SAIC NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO INSPECTION CHECKLIST
Inspection of Pressure Test Preparation SAIC-A-2011 30-Apr-13 MECH-
Attachment 2 - Component Safeguard Summary
Note: This Summary Checklist has been developed with concurrence of CSD
1. INSTALL THESE COMPONENTS IN LINE ONLY AFTER THOROUGH FLUSHING:
Components in new piping systems which interfere with filling, venting, draining or flushing shall not be installed until after line flushing
and pressure testing are completed. This includes Procedures/Test Package Instruction or details about specific component care as
listed below (SAES-A-004, Para 8.1.4):
a) Orifice plates -- Flow nozzles -- Sight glasses (incl. vessel trim) -- Venturies -- Meters (positive displacement, turbine)
b) In-line equipment (as determined by Proponent) includes valve care (corrosion, cleaning, lay-up considerations). A list shall be
obtained by Contractor from COMPANY relative to Component Safeguards. Contractor shall request specific instruction for specific
component safeguards from Company (Proponent, SAPMT, SA Inspection)
3. INSTALL THESE COMPONENTS (EXCLUDED FROM PRESSURE TEST) ON FINAL REINSTATEMENT:
Note: The following list defines the equipment that shall be excluded from the in-situ pressure testing of the
tested system. Also, other unlisted sensitive equipment or as designated by SA Inspector can be added (SAES-A-004-Para 8.2):
a) Rotating machinery, such as pumps, turbines and compressors;
b) Strainers and filter elements
c) Pressure relieving devices, such as rupture disks and pressure relief valves;
d) Locally mounted indicating pressure gauges, where the test pressure will exceed their scale range;
e) Equipment that cannot be drained (This includes valve cavities. See Valve Care below).
f) Instrument Devices.
g) Other unlisted sensitive equipment (propose exclusion in test package)
h) Equipment designated by Saudi Aramco Inspector (Approves procedures that list specific equipment in scope)
CSD VALVE SAFEGUARDS & CARE (TYPICAL FOR AMBIENT LAY-UP)
Valve Field Hydrotest Practice (separate from line/system testing) assures adequate preservation as listed below. Valves or
other equipment that are field tested prior to installation in a pipeline, plant, or other facility are likely to experience corrosion damage
if this is not performed with adequate diligence and precautions.
a) The following applies to valve trims Type 1, 4, 6, 7, 8, and 8A and all solid Type 400 SS (13 CR) valves.
b) Plan prior field testing of valves to minimize the length of time between test and installation in the system.
c) All critical isolation valves that are tested shall be tested with water containing less than 50 ppm chlorides. The water shall contain
0.5% by weight (5 grams per liter) Cortec VpCI 609. (Note:Chemical cost would be about $0.30 per liter. VpCI 609 is biodegradable
so there are no problems with its use. (See Environmental Protection Dept.)
d) After hydrotesting, gate valves will have their gates raised to allow full draining of water. Allow adequate drainage time. All traces
of
e) visible
Apply water shall be approved
manufacturer removed from the valve
lubricant bodyCortec
plus 10% and seat area. Blow
VpCI-329 (SAPdry with clean compressed
1000173887) added to all air.
interior critical surfaces such as
seal areas. Ball valves shall be full operated to distribute inhibited lubricant between ball and body.
Page 7 of 8
SAUDI ARAMCO ID/PID - REV - 18-May-05 (Standards Cutoff -March 2012) Rev 6 31-Mar-12
SAIC NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO INSPECTION CHECKLIST
Inspection of Pressure Test Preparation SAIC-A-2011 30-Apr-13 MECH-
f) Safeguards for 300 series (316 SS, etc) trimmed valves require similar care to assure complete cavity draining. Corrosion inhibitors
used shall be approved by CSD.
Page 8 of 8