Saic A 2011
Saic A 2011
Saic A 2011
Rev 4
SAIC NUMBER
SAIC-A-2011
PROJECT TITLE
WBS / BI / JO NUMBER
EQUIPMENT ID NUMBER(S)
EQUIPMENT DESCRIPTION
REV. NO.
31-Mar-10
DATE APPROVED
QR NUMBER
MECH-
31-Aug-11
CONTRACTOR / SUBCONTRACTOR
EQPT CODE
SYSTEM ID.
PLANT NO.
MH's SPENT
TRAVEL TIME
ITEM
No.
ACCEPTANCE CRITERIA
REFERENCE
PASS
FAIL
N/A
Test Preparation - General Requirements ... USE SATR-A-2001, 2002, 2003, 2004, 2005 & SATR-A-2006 as req'd.
A1
SAEP-1160,
Section 8
A2
SAEP-1160,
Section 8
A3
SAEP-1160,
Section 8
A4
SAES-A-004,
Para. 8.1.2
A5
SAES-A-004,
Section 8
A6
SAES-A-004,
Para. 8.5.2
A7
Expansion joints and spring hangers or spring supports are provided with
temporary restraints where needed to prevent excessive travel or
deformation under the test loads. (Field Verify)
SAES-L-150,
Para. 6.4
A8
All joints including welded joints are accesible and left exposed for visual
leak detection during the strength test. External coating and priming of
such joints are not allowed unless approved.
Note: This excludes joints subject to 24-hr recorded test
SAES-L-150,
Para. 7.3
A9
Work permit is obtained for pressure testing and associated work within
restricted areas, as per G.I. 2.100, Work Permit System.
G.I.-2.102,
Para. 5.1.6
A10
G.I.-2.102,
Para. 5.1.7
A11
G.I.-2.102,
Para. 5.1.7,
SAES-A-004
Para 8.3
A12
G.I.-2.102,
Para. 5.1.9
Page 1 of 5
RE-INSP DATE
ITEM
No.
Rev 4
DATE APPROVED
SAIC-A-2011
31-Aug-11
WBS / BI / JO NUMBER
ACCEPTANCE CRITERIA
REFERENCE
A 13
G.I.-2.102,
Para. 5.2.1
A 14
Access/Egress for Test areas is marked & warning signs posted to alert
approaching personnel of pressure testing activities.
G.I.-2.102,
Para. 5.1.11
A 15
G.I.-2.102,
Para. 5.1.11
G.I.-2.102,
Para. 5.1.12
A 17
31-Mar-10
SAIC NUMBER
Copy of the approved pressure testing procedure & the GI-2.102 are
available at site. Test Personnel are safety trained/experienced.
Verification of Actual Test Set-up & SIS Sheet Data:
B1
SAEP-1160,
Section 8
Bullet Item 2
B2
SAEP-1160,
Section 8
Bullet Item 2
C1
SAES-A-004
Para 5.5.4
C2
G.I.-2.102,
Para. 5.1.5.5
C3
G.I.-2.102,
Para. 5.1.2.5
C4
G.I.-2.102,
Para. 5.1.5.5
C5
G.I.-2.102,
Para. 5.1.5.3
C6
G.I.-2.102,
Section 5.1.5
C7
SAES-A-004
Para. 7.3
MECH-
CONTRACTOR / SUBCONTRACTOR
PASS
SAES-A-004,
Para. 5.6.1
QR NUMBER
Page 2 of 5
FAIL
N/A
RE-INSP DATE
Rev 4
31-Mar-10
SAIC NUMBER
DATE APPROVED
SAIC-A-2011
PROJECT TITLE
31-Aug-11
WBS / BI / JO NUMBER
ITEM
No.
ACCEPTANCE CRITERIA
REFERENCE
D1
Relief valve is located in the system under test and near the test pump
with Isolation valves on the inlet and outlet of the relief valve sealed open
during the test. (SAEP-1160, Bullet Item # 3)
G.I.-2.102,
Para. 5.5
D2
Relief valve(s) of adequate capacity (*SIS Sheet & Calcs available) are
set to relieve at 5%* above the hydrotest pressure.
*Note: Test pressures less than 85% of SMYS can have relief valves
set at 10% above test pressure. Verify SIS sheets calcs.
SAES-A-004
Para 5.5.1
D3
Relief valve(s) are tested, dated, and tagged (as valid) for a period of one
week for project pressure tests. Stickers are legible & valid.
SAES-A-004
Para 5.5.1
E1
A minimum of two pressure gages are required for test systems, with
accuracy within 5% of one another.
Note 1: When large systems are tested, Inspection personnel will
determine the need for additional gages.
Note 2: Elevation changes (hydrostatic head considerations) & hot
weather create pressure testing problems with frequent popping of relief
valves. For this reason, gage accuracy within 2% is best.
Note 3: Careful handling of delicate instruments like test gages is
practiced by test crews. No gage damage or mishandling is found.
SAES-A-004
Para 8.1.5.4
E2
Pressure gages and pressure recorders are calibrated within (1) month
prior to test. Stickers applied indicate latest calibration date.
SAES-A-004
Para 8.1.5.2
E3
G.I.-2.102,
Sec.4 &
SAES-A-004,
Para 5.3
E4
All gages have a range such that the test pressure is within 30% to 80%
of the full range.
SAES-A-004
Para 8.1.5.3
Temperature Gages and Recorders (When Required, ie: 24-hr Recorded Tests)
F1
SAES-A-004
Para 5.6.3
F2
SAES-L-150,
Para. 11.3
QR NUMBER
MECH-
CONTRACTOR / SUBCONTRACTOR
PASS
FAIL
N/A
RE-INSP DATE
REMARKS: Critical Safety Note 1: Surveys of test manifolds used on projects have resulted in many findings of inadequate ratings for isolation
valves. Test manifolds for testing specific pressure rating Classes require isolation valves of the next higher class. Example: Manifolds for testing Class
300 # systems require Class 600 # isolation valves as a general rule. For Pressure tests against closed seats follow the 110% rule for safe test
pressure calculation. See ASME B16.34, Para 7.2 as applicable. Also, this same requirement must be carefully considered when determining test
pressures where an isolation valve serves as a test boundary limit and the valve seat will be pressurized. Ensure system test pressures are reduced to
110% as applicable and show the valve seat as the test "limiting factor".
Safety Note 2: Fabricated test implements of proper
code construction receive inspection and properly identification/marking for pressure rating, inspection acceptance/fitness (Insp Ok, initial, date). Never
allow uninspected non-code test implement use or those that are unfit for testing (deteriorated, damaged, heavily corroded). Unsafe/unfit test
implements found are reported/removed ASAP from Company Projects.
REFERENCE DOCUMENTS:
1. SAES-A-004, General Requirements for Pressure Testing, (14-Dec-2009)
2. GI-2.102, Saudi Aramco General Instruction-Pressure Testing Safely, (28 October, 2008)
3. SAES-L-150, Pressure Testing of Plant Piping and Pipelines, (1-Nov-2008)
4. Pro Forma Contract Schedule Q (Project Specific)
5. SAEP-1160 (2-Aug-2009)
Contractor / Third-Party
Construction Representative*
Saudi Aramco
PMT Representative
T&I Witnessed
QC Record Reviewed
T&I Witnessed
QC Record Reviewed
T&I Witnessed
QC Record Reviewed
Work Verified
QC Inspector
PID Representative
Performed Inspection
Work Verified
QC Supervisor
Name, Organization,
Initials and Date:
Y = YES
Page 3 of 5
Work Verified
N = NO F = FAILED
Rev 4
SAIC NUMBER
SAIC-A-2011
31-Mar-10
DATE APPROVED
31-Aug-11
QR NUMBER
MECH-
Page 4 of 5
Rev 4
SAIC NUMBER
SAIC-A-2011
31-Mar-10
DATE APPROVED
31-Aug-11
QR NUMBER
MECH-
2. INSTALL THESE COMPONENTS IN LINE AFTER FLUSHING & TEST COMPLETION (ON REINSTATEMENT):
Components in new piping systems which interfere with filling, venting, draining or flushing shall not be installed until after line
flushing and pressure testing are completed. This includes Procedures/Test Package Instruction or details about specific component
care as listed below (SAES-A-004, Para 8.1.4):
a) Orifice plates -- Flow nozzles -- Sight glasses (incl. vessel trim) -- Venturies -- Meters (positive displacement, turbine)
b) In-line equipment (as determined by Proponent) includes valve care (corrosion, cleaning, lay-up considerations). A list shall be
obtained by Contractor from COMPANY relative to Component Safeguards. Contractor shall request specific instruction for specific
component safeguards from Company (Proponent, SAPMT, SA Inspection)
Page 5 of 5