Module 7: Making The System Work
Module 7: Making The System Work
Module 7: Making The System Work
• List corrective measures that may be taken by the Government and the
authority for each.
7-1
testing on all component systems, e.g. Duct Air Leakage Tests
(DALTS), Testing and Balancing Systems (TABS), HVAC Controls
System, electrical hi-pot tests. When possible, these
misunderstandings should be solved at the field level.
Personal one-on-one discussion and actions at the field level often provide
acceptable solutions to the problems. If discussions with onsite personnel
are not fruitful, the problem must be elevated to the next level. The
important thing is for the problem to be identified early so that it can be
prevented or corrective action can be taken. If an agreement cannot be
reached, the Government makes the final determination.
7-2
- While the Government is obligated to pay for satisfactorily
completed work, it has no obligation to pay a contractor for
deficient work.
7-3
- Conversely, outstanding work by a contractor is reflected in
outstanding performance appraisals, safety awards, and public
recognition.
C. Making the "System" Work: The QC Manager must act quickly and
confidently when problems are discovered. He cannot sit back and hope
that problems will correct themselves. His job is to control construction
quality by taking action to make certain that problems are corrected and
prevented. The Government is serious about CQC and will hold the
contractor responsible for contract compliance.
7-4
EXERCISE
Module 7
2. What options are available to the Government under the Contract Clauses
of the contract?
3. Analyze the cases on the following pages and answer the questions
included with each. Be prepared to discuss your answers with other
members of the class.
7-5
etc., which was in violation of the specifications. Work was stopped,
and after some investigation, contractor advised the resident engineer
that the best delivery on treated lumber was eight weeks, which would
delay enclosing the building and ultimately delay turnover to the
client/customer. The contractor requested waiver of treated lumber
requirement.
7-6
b. Contract involves construction of a major barracks complex including
25 dormitories. Project is 75% complete and occupied by troops when
the client/customer complains that the opaque panel in the lower
window section is allowing precipitation to penetrate during driving
rain. The leaks have stained carpet and ceiling tile. Investigation
reveals that leaking panels are improperly glazed and do not conform
with the contract drawings and specifications. All windows had been
factory glazed and were warehoused onsite. Although a vinyl strip
covered the glazing, careful examination of the windows prior to, and
after, installation would have revealed the construction deficiency.
(1) Identify the steps within the CQC system that failed, thereby
creating the construction deficiency.
(3) Keeping in mind that there are 4,200 windows involved in the
contract, what corrective measure should the resident engineer
employ?
7-7
completed?
7-8
(3) What measures should Government QA personnel now
employ?
7-9
(1) What questions first come to mind as to the effectiveness of the
contractor's quality control system?
(2) Where did the Government's quality assurance role first break
down?
7-10
(1) What is the government's first corrective action to be taken?
7-11
f. On an underground electrical distribution project, the contractor was to
install a run of 2/0 cable in the system. The project had been
completed and accepted two years ago, when it was discovered that
this run of cable was #2 instead of 2/0 and totally inadequate for the
future load.
g. The contract for construction of the outlet works at a flood control and
recreation reservoir required steel gates. The prime contractor to a
fabricator in Los Angeles subcontracted the gates. All CQC
requirements on the gates were delegated to the fabricator. The
resident engineer arranged for Government periodic QA visits to the
plant. The plant inspector advised the resident engineer that the
welding procedures and the welders had not been certified prior to
commencement of fabrication. The QC contained no entry on this
subject.
(1) In this instance, what role does the prime contractor assume?
7-12
(2) Where did the prime contractor fail in the quality control
system?
7-13
(1) Could the CQC system have prevented this? How?
(2) Did the Government fail in its QA role by not inquiring as to the
status of carpet manufacture?
(1) What was the first step that failed in the contractor's QC
program?
7-14
(2) How could the Government's QA role have prevented this
incident?
7-15
(1) In what meeting should the testing requirements of the contract
be discussed in general?
7-16
NOTES
CONSTRUCTION QUALITY MANAGEMENT
FOR CONTRACTORS
7-17
NOTES
CONSTRUCTION QUALITY MANAGEMENT
FOR CONTRACTORS
7-18