DH3-31MA-T-SCT-0001 Commissioning Procedure of Complete-Set Startup of Steam Turbine REV.0
DH3-31MA-T-SCT-0001 Commissioning Procedure of Complete-Set Startup of Steam Turbine REV.0
DH3-31MA-T-SCT-0001 Commissioning Procedure of Complete-Set Startup of Steam Turbine REV.0
COMMISSIONING PROCEDURE
For
0 2016-5-11
Construction
Li bin Hu zhangwei Pu xiaoqin Guo Baodong
OWNER
VIETNAM ELECTRICITY
THERMAL POWER PROJECT MANAGEMENT BOARD 3
CONSULTANT
POWER ENGINEERING CONSULTING JOINT STOCK COMPANY 3
CONTRACTOR
THE CONSORTIUM OF CHENGDA-DEC-SWEPDI-ZEPC
SUBCONTRACTOR
THE COMMISSIONING & TEST INSTITUTE OF SICHUAN ELECTRIC
SECTI POWER INDUSTRY
CONTRACT No.
PROJECT DUYEN HAI 3 THERMAL POWER PROJECT
DH3-05082011
Contents
1. Objective of commissioning...................................................................................................... 3
2. Content of Commissioning........................................................................................................ 3
3. Compilation Basis ..................................................................................................................... 3
4. Tools and Instruments ............................................................................................................... 4
5. Conditions to be met prior to Commissioning .......................................................................... 4
6. Commissioning Procedure ........................................................................................................ 5
7. Safety measures ....................................................................................................................... 16
8. Appendix ................................................................................................................................. 19
CHENGDA-DEC-SWEPDI-ZEPC
1. Objective of commissioning
1.1 The commissioning is intended to test the correctness and reliability of function of the
control system via startup commissioning of unit.
1.2 It is intended to inspect whether the operation parameters of main equipment and
auxiliary equipment meets the rated output and meets the design requirement.
1.3 It is intended to complete the test that must be carried out during dynamic operation
of the unit such as overspeed test, vacuum tightness test, load rejection test, etc.
1.4 It is intended to examine the quality of construction, design and equipment.
To check the stability of operation of steam turbine generator set via continuous full-load
operation; to check the correctness of control system function and reliability of protection
system, to check whether the main and auxiliary system is optimized, the operation of the
equipment is well-performed, the parameters meet the design and manufacture
requirement and meet continuous operation demand of the steam turbine generator set.
2. Content of Commissioning
3. Compilation Basis
5.1 The installation work is over and the commissioning team agreed to accept the
system to start commissioning.
5.2 A Punch list covers all defects or unfinished works are confirmed by the
Owner/Engineer and the Commissioning Team that the defects or unfinished works
do not affect the Commissioning and normal operation of apparatus.
5.3 Work permit system is in working.
5.4 Safety isolation measures are implement.
5.5 All the equipment, instruments, valves have been officially tagged /labeled and
medium type and flow direction have been indicated on the pipelines.
5.6 Operation department is ready for the unit startup, operating manual and related
regulations and record forms are ready, and operation tools are ready.
5.7 Correct system drawing and curve for startup of unit have been hung on the
commissioning site.
5.8 The grid and switch yard is available.
5.9 Service power supply system works properly, UPS, DC supply are reliable and
diesel generator system is in standby state.
5.10 Firefighting system and equipment in the commissioning site has passed the
examination and ready for service. The local site must be equipped with enough
and suitable fire extinguisher , firefighting water pool/tank must be fulfilled.
Firefighting trucks and firemen are on duty. Safeguard personnel are located in
necessary area.
5.11 Fresh water and demineralized water is well prepared.
5.12 Domestic water supply is normal and air conditioner, ventilation system and sanitary
fixtures can work properly.
5.13 Steam blowing for boiler and turbine system is completed, all temporary system is
removed.
5.14 B-T-G interlock test is completed.
5.15 Equipment and systems required for the unit startup are commissioned and ready
for service, including but not limited to the following :
6. Commissioning Procedure
HP casing. When the metal temperature of inner wall of the upper half casing in the first
stage of the turbine HP casing exceed 150°C, close the HP casing pre-warming valve,
stop the HP casing pre-warming, and maintain it according to the time requirement.
During the HP casing pre-warming, monitor the turbine speed and the running conditions
of turning gear. In case of the turning gear tripping and turbine speed rise, immediately
close the pre-warming valve, and decrease the HP casing’s pre-warming pressure. After
the turbine speed is decreased and the rotor stops, put the turning gear into service again.
6.1.4 CV pre-warming
Trip the turbine. On the “CV WARMING” screen of DEH, press “ON” to confirm the
pre-start valve of the HP main steam valve (right) is opened. When the metal temperature
difference between inner and outer casings of CV valve is higher than 80°C, close the
pre-start valve of the HP main steam valve (right). When the temperature difference is
lower than 70°C, open the pre-start valve again. Repeat these actions for pre-warming the
HP regulating valve. When the metal temperature of inner and outer casings of HP
regulating valve exceeds 180°C, press “OFF” under “CV WARMING” to end the
pre-warming of HP regulating valve, and confirm the left and right main steam valves are
fully opened.
When the speed of the unit reaches 3000rpm, make sure the normal
operation of main oil pump, the inlet pressure of 0.098~0.147MPa and
the outlet oil pressure above 1.372MPa.
Carry out self-start test of emergency oil pump, startup oil pump and
auxiliary oil pump. After the test, stop the startup oil pump and auxiliary
oil pump, monitor the inlet and outlet oil pressures of main oil pump; put
the emergency oil pump, startup oil pump and auxiliary oil pump into
standby state.
Conduct the manual tripping at the site, make sure normal closure of HP
and IP main steam valves and regulating valves, speed reduction of the
unit and normal output; reset and raise the speed to 3000rpm.
(5) Precautions during impulse starting:
During impulse starting and warming of steam turbine, try to keep stable
steam pressure, water level and other parameters.
Not stay within the critical speed area during speed rising.
In case of large shaft vibration under low speed, implement the tripping
for shutdown, rather than speed reduction and warming.
Pay attention to checking whether steam turbine proper and pipes are
impacted by water or have abnormal vibration, and whether the drain
system of steam turbine is normal.
Pay attention to monitoring the thermal expansion of steam casing,
differential expansion, axial displacement, temperature difference
between upper and lower casings as well as between inner and outer
casings, bearing vibration and temperature.
Check the lube oil pressure and temperature, oil level in fuel tank,
generator hydrogen pressure and temperature, sealing oil pressure,
and hydrogen/oil pressure difference of sealing oil.
Pay attention to the vacuum and water level of condenser, change in
water level of HP and LP heater and deaerator.
Pay attention to the change in LP casing exhaust temperature and
actuation of LP casing spraying.
Pay attention to the operation condition of bypass and auxiliary
machines.
rate as 3MW/min. Raise the load to 20% MCR for four-hour warming.
When the load is increased to 10%, check that the LP casing spraying is
closed automatically. Pay attention to the checking that the HP section drain
valve is closed.
Depending on the circumstances, put DEH into the power control loop.
In case of unit load ≥20%, do the following works:
Check that the drain valves of main and reheat steam pipes for the turbine
are closed automatically.
Check that the drain valves of turbine proper and steam extraction pipes are
closed automatically.
Put the steam side of the HP heater into operation, and pay attention to the
feed water temperature and feed water flow change. After the HP heater
is put into operation normally, close the drain valve of steam extraction
pipe.
Check that the casing spraying control valve after the LP casing is closed
automatically, and pay attention to the exhaust temperature.
When the 4th stage steam extraction pressure is higher than the setting
pressure of deaerator (0.2MPa), switch the steam source of deaerator to
the 4th stage extraction steam supply automatically, interlock and close the
control valves from auxiliary steam header to the deaerator, and operate
the deaerator at the sliding pressure.
After warming, it is required to decrease the load, and it is out of
synchronization before the turbine over-speed test.
Note: During the test, main steam pressure shall >50% rated main steam pressure;
the motorized valve for pre-warming the HP casing is closed, and the vent valve
of the HP casing is opened.
(4) In the hot start, conduct shaft sealing before vacuum pumping. Pay attention
that the shaft seal temperature shall match the turbine metal temperature.
(5) In the hot start, check that the shaking degree of main shaft conforms to the
requirement and the condenser shall keep a high vacuum degree.
(6) Check and confirm that the drain valves of body, main and reheat steam
pipes are opened, and the main and reheat steam pipes are drained adequately.
(7) Before start-up of the unit, make all preparations for impulse starting and
speed rise as soon as possible. After necessary inspection at the constant speed
is OK, conduct synchronization with load as soon as possible to the load level
corresponding to the metal temperature of inner wall of the upper half casing in
the first stage of the turbine HP casing.
(8) Set the target speed at 3000r/min directly before impulse starting of the unit.
(9) In the process of start-up and speed rise, the shaft seal pressure and the
shaft seal temperature after desuperheating shall be normal.
(10) In the process of speed rise and load rise, strengthen the monitoring of unit
vibration, keep an eye on the changes in differential expansion, casing
expansion, axial displacement, main and reheat steam temperature, as well as
the changes in the metal temperature and temperature rise of HP and IP
casings.
(11) In case of idling of the turbine upon resetting, it is required to confirm that the
turbine speed is not within the range of critical speeds.
(12) Before impulse starting of the unit, the lube oil temperature of generators is
above 35°C, and the impulse starting is prohibited when the oil temperature is
less than 30°C.
(13) During impulse starting and speed rise of the turbine, start the first
steam-driven feed water pump, and make sure that the steam-driven feed water
pump can be connected to the feed water system timely during load rise.
(14) Other operation and inspection items are the same as the cold start.
Implement the 30-day reliability running (RR). During the reliability running, carry out
96-hour continuous full-load (622MW) operation, and implement the running under the
load required by the dispatcher at the rest of the time.
7. Safety measures
7.4 HAZID/HAZOP
Potential
Num Activity Potential Hazard Result Prevention Measure
Hazard Factor
Wear proper work clothes and keep the safe
High distance with high temperature object. If
1 Site work temperature Personnel scald need to contact with high temperature object,
object surface wear heat insulated gloves or protective
equipment.
4 Site work protection Mechanical injury communication when working, when the
8. Appendix