CCBA Practice Questions
CCBA Practice Questions
CCBA Practice Questions
142q
Exam A
A. Procurement needs
B. Risk level
C. Unique number
D. Roles and responsibilities
Correct Answer: C
Section: (none) Explanation
Explanation/Reference:
Explanation:
Each task in the task list should have a unique number to identify the specific task and it should
have a description of what the task is. Answer: B is incorrect. The risk level is not associated
with the task list.
Answer: D is incorrect. Roles and responsibilities are not included directly in the task list.
Answer: A is incorrect. Procurement needs are not included in the task list.
QUESTION 2
Shelly is the business analyst for her organization and she's working with Thomas to review the
business requirements. They are discussing the identified requirements, how the requirements
will transition to the operations, and the longevity of the solution. Thomas is concerned that
the identified requirements may not map to the desired future state of the organization. What
business analysis task is Shelly facilitating in this scenario?
QUESTION 3
Which of the following are documented approaches to the business analysis work? Each correct
answer represents a complete solution.
QUESTION 4
You are the business analyst for your organization and working with the stakeholders to
prioritize the requirements. The stakeholders are concerned about the financial impact of the
requirements should some of them fail during the implementation. You would like to rank the
risk tolerance of the stakeholders based on their comments about the solution and the
requirements. The following are the three categories of risk tolerance associated with the
stakeholders except for which one?
A. Neutrality
B. Mitigation
C. Risk-seeking
D. Risk-aversion
Correct Answer: B
Section: (none) Explanation
Explanation/Reference:
Explanation:
Mitigation is a risk response that seeks to lower the risk's probability and/or impact. It is not
one of the three categories of risk tolerance.
Correct Answer: D
Section: (none) Explanation
Explanation/Reference:
Explanation:
Requirements must be communicated before they are managed. Tracy must communicate the
requirements to the stakeholders for their consent and approval before managing the
requirements.
Answer: A is incorrect. Before Tracy decomposes the requirements, she should have the
approval of the stakeholders. Answer: B is incorrect. To begin managing the requirements,
Tracy needs the approval and consent of the stakeholders. Answer: C is incorrect. This isn't a
valid statement, as the best thing to do is to gain the approval of the stakeholders first.
QUESTION 6
Ben is the business analyst for his organization. Ben is currently working on a solution to
improve a laser printer. He has taken the laser printer apart, identified each component, and
documented each component's purpose. What type of requirements organization is Ben doing
in this scenario?
A. Functional decomposition
B. Process modeling
Correct Answer: A
Section: (none) Explanation
Explanation/Reference:
Explanation:
Ben is completing the functional decomposition technique for the organize requirements
process. Each component in the printer can have its own set of requirements, while the
improved printer to be manufactured is the ultimate goal of the requirements.
Answer: D is incorrect. Data modeling describes the concepts and relationships relevant to the
solution or business domain. Answer: C is incorrect. Scope modeling allows the requirements to
be organized by the solution component they're relevant to.
Answer: B is incorrect. Process modeling is the activity of representing processes of an
enterprise, so that the current process may be analyzed and improved in future. It allows the
requirements to be organized around the related processes. Processes are also considered to
have sub-processes, inputs, and outputs.
QUESTION 7
You are the business analyst for your organization and you're working with Fran on business
analysis processes. Fran is a stakeholder who wants to ensure that your business analysis
approach and activities are compatible with the project activities. Of the following, what type of
business analysis stakeholder is Fran?
A. Regulator
B. Project manager
C. Sponsor
D. Domain subject matter expert
QUESTION 8
You are a business analyst for your organization and you're working with Mary. Mary wants to
know what you need to complete the process of planning the business analysis approach if
you're already the business analyst for your organization. Which of the following statements is
true regarding the plan business analysis approach?
A. The plan business analysis approach describes the amount of budget needed for the
requirements elicitation. B. The plan business analysis approach is required to select an
approach that will perform business analysis.
C. The plan business analysis approach describes the processes the business analyst will or will
not do, based on the time and budget available. D. The plan business analysis approach
describes the amount of time needed for the business analysis approach.
Correct Answer: B
Section: (none) Explanation
Explanation/Reference:
Explanation:
QUESTION 9
You are the business analyst for a large software development project. There are several issues
that must be resolved by certain dates or the problem will prevent the project from advancing.
What technique can you use to track problems with the requirements?
A. Issue tracking
B. RTM
C. Problem tracking
D. Baselining
Correct Answer: C
Section: (none) Explanation
Explanation/Reference:
Explanation:
The technique you'll use is simply problem tracking. This technique allows the business analyst
to manage any issues identified within requirements by stakeholders and to ensure that those
issues are resolved.
Problem tracking allows the business analyst to manage any issues identified within
requirements by stakeholders and to ensure that those issues are resolved. It provides an
organized approach to tracking, management, and resolution of defects, issues, problems, and
risks throughout business analysis activities. Management of issues is important so that they
can be resolved in a timely manner to ensure success.
QUESTION 10
Which one of the following statements is most true about changing requirements in a change-
driven approach to business analysis and requirements management?
A. Change-driven approaches must use a change control system with a change control board.
B. Change-driven approaches only use a change control system for approved changes.
C. Change-driven approaches don't use a formal change control process. D. Change-driven
approaches are driven by change control processes.
Correct Answer: C
Section: (none) Explanation
Explanation/Reference:
Explanation:
Change-driven approaches typically do not use a formal change control process, as
requirements are prioritized and selected for implementation at the beginning of each iteration
and no changes to the requirements occur during the iteration process.
Answer: A is incorrect. Change-driven approaches don't typically use a change control board.
Answer: B is incorrect. This isn't a valid statement to describe the processes of change within a
change-driven approach to requirements management. Answer: D is incorrect. This isn't a valid
statement to describe the processes of change within a change-driven approach to
requirements management.
Correct Answer: A
Section: (none) Explanation
Explanation/Reference:
Explanation:
Current capability analysis is an approach of assessing the organization's capability gaps. This
process reviews the process and helps determine what capabilities exist now and how large the
gap may be.
Answer: C is incorrect. This isn't a valid assessment type so this choice is not valid. Answer: B is
incorrect. This isn't a valid assessment type so this choice is not valid. Answer: D is incorrect.
This isn't a valid assessment type so this choice is not valid.
QUESTION 12
Beth is the business analyst for her organization and she wants to be certain that she and her
team follow the correct procedures for enterprise analysis. What document can provide the
governances for enterprise analysis efforts?
QUESTION 13
Henry and Fred are working together on business analysis duties for the implementation of new
software. Henry, the business analyst, tells Fred that they should take the current
measurement of productivity, and then measure again after the solution has been
implemented. This benchmarking approach will allow Henry and Fred to see the real effect of
the solution on the business need. What term is assigned to this measurement?
Correct Answer: C
Section: (none) Explanation
Explanation/Reference:
Explanation:
The measurements are known as key performance indicators. It's an approach for measuring
how well the solution has affected the organization.
QUESTION 14
Kendra is the business analyst for her organization. She's working with the project manager and
the project sponsor to discuss the current requirements. Kendra believes it's important for the
project manager to first implement the requirements with the highest amount of risks. Is this a
good idea?
A. No, the project manager and team should actually implement the lowest risk requirements
first.
B. Yes, if the risky requirements cause the project to fail, the organization will not suffer much
loss, as it hasn't invested much time or money on the project.
C. No, the project manager and team should implement the requirements with the highest
risks last.
D. Yes, this allows the project manager to get the risky work done as soon as possible in the
schedule.
Correct Answer: B
Section: (none) Explanation
Explanation/Reference:
Explanation:
It's often best to implement the most risky requirements first in the project. If the risky
requirements cause the project to fail, the organization will not suffer much loss, as it hasn't
invested much time or money on the project.
Answer: A is incorrect. It's not the best idea to implement the lowest risk requirements first.
Answer: C is incorrect. Implementing the highest risk requirements last could cause all of the
prior work to be worthless if the risky requirements fail. Answer: D is incorrect. This choice is
tempting, but the best reason is the financial consideration of the risky event in the project.
A. Payback period
B. Average rate of return
C. Cost-benefit analysis
D. Discounted cash flow
Correct Answer: A
Section: (none) Explanation
Explanation/Reference:
Explanation:
Payback period quantifies the duration that the project will need to exist and generate revenue
in order to pay back the original investment of the project. The payback period is also known as
management horizon or the breakeven point.
Answer: B is incorrect. Average rate of return describes the rate of return the project will
create. Answer: C is incorrect. Cost-benefits analysis describes the relation of costs to benefits
in a project. Answer: D is incorrect. Discounted cash flow describes the future value on the
investment of the project.
QUESTION 16
When a business analyst completes the elicitation process, she will create four outputs. Which
one of the following is an output of the elicitation process?
QUESTION 17
When using a change-driven approach, the business analyst may create an initial list of high-
level requirements for the initiative. This high-level requirements list is also known as what
term?
A. Requirements envisioning
B. Project scope
C. Product scope
D. Requirements foundation
Correct Answer: A
Section: (none) Explanation
Explanation/Reference:
Explanation:
The initial high-level listing of requirements in a change-driven approach is also known as
requirements envisioning. Answer: B is incorrect. Project scope defines all of the required work
to satisfy the requirements of the project.
Answer: C is incorrect. Product scope defines all of the features and functions of the thing,
solution, or service the project or organization will create. Answer: D is incorrect. Requirements
foundation is not a valid term for business analysis.
Correct Answer: B
Section: (none) Explanation
Explanation/Reference:
Explanation:
The work breakdown structure (WBS) is a tool used to define the scope of work and to develop
estimates. This tool creates a hierarchy of work by decomposing the project scope into smaller
and smaller pieces. WBS can perform the following tasks:
It may break the project into iterations, releases, or phases. It can break deliverables into work
packages.
It may break activities into smaller tasks.
Answer: C is incorrect. The project management plan could be helpful, in some instances, but
for this question, the best answer is WBS.
Answer: D is incorrect. A Pareto chart is a special type of bar chart where the values being
plotted are arranged in descending order. The graph is accompanied by a line graph, which
shows the cumulative totals of each category, left to right. The chart is named after Vilfredo
Pareto, and its use in quality assurance was popularized by Joseph M. Juran and Kaoru
Ishikawa.
Answer: A is incorrect. Organizational process assets are elements of historical information,
guidelines, processes, and standard procedures within an organization. They mandate certain
deliverables and the lessons learned from business analysis activities can be used in the
development of business analysis plans.
Correct Answer: B
Section: (none) Explanation
Explanation/Reference:
Explanation:
The stakeholder management strategy is generally not included in the stakeholder registry
because it may contain sensitive information that should not be shared with project team
members or certain other individuals that could see the stakeholder register. The stakeholder
register is a project management document that contains a list of the stakeholders associated
with the project. It assesses how they are involved in the project and identifies what role they
play in the organization. The information in this document can be very perceptive and is meant
for limited exchange only. It also contains relevant information about the stakeholders, such as
their requirements, expectations, and influence on the project.
Answer: D is incorrect. Stakeholder identification should be included in the stakeholder register.
Answer: A is incorrect. Assessment information should be included in the stakeholder register.
Answer: C is incorrect. Stakeholder classification should be included in the stakeholder register.
A. Class model
B. Project network diagram
C. Data flow diagram
D. WBS
Correct Answer: A
Section: (none) Explanation
Explanation/Reference:
Explanation:
The class model is most often used with object-oriented development, while the entity-
relationship diagram is preferred for relational databases. Answer: D is incorrect. WBS isn't a
data model, but a decomposition of the project scope.
Answer: B is incorrect. The project network diagram is an illustrated flow of project activities.
Answer: C is incorrect. A data flow diagram shows how data moves into, through, and out of a
system.
QUESTION 21
You are the business analyst for your organization and you're performing the solution
assessment process. When you assess a solution, what are you actually looking for?
A. To determine the value of the proposed solution to the stakeholder requirements
B. To determine the quality of the proposed solution to the stakeholder requirements
C. To determine the cost of the proposed solution to the stakeholder requirements
D. To determine the accuracy of the proposed solution to the stakeholder requirements
QUESTION 22
Beth is the business analyst for her organization and she's creating a data dictionary for her
organization. All of the following information should be included in the data dictionary for an
endeavor Beth is leading except for which one?
A. Description
B. Aliases
C. Name
D. Code of account identifier
QUESTION 23
You are a business analyst for your organization. Your current business analysis endeavor
includes working with stakeholders who are located in offices around the world. Because these
stakeholders are dispersed, what are likely to increase in this endeavor as opposed to a
collocated group of stakeholders?
A. Face-to-face meetings
B. Communication needs
C. Risks
D. Costs
QUESTION 24
What's the difference between a desired outcome and a solution?
Choose the best answer.
A. The desired outcome is how the organization will operate in the future; the solution is the
method to reach the desired outcome.
B. They are synonymous.
C. The solution is the ideal fulfillment of the business goals; the desired outcome is the
financial gain created by the implementation of the solution.
D. The desired outcome is what the solution will remove.
Correct Answer: A
Section: (none) Explanation
Explanation/Reference:
Explanation:
Of all the choices, only this answer properly identifies the desired outcome as how the
organization will operate once the solution has been implemented. Answer: B is incorrect.
Business goals and desired outcomes are not the same.
Answer: D is incorrect. The solution doesn't remove the desired outcome.
Answer: C is incorrect. The solution is not always a financial gain so this choice is not valid.
QUESTION 25
In order to plan the business analysis approach, the business analyst must understand the
organizational process needs and what other thing?
Correct Answer: A
Section: (none) Explanation
Explanation/Reference:
Explanation:
The business analyst must understand how the organization operates and the objectives of
business analysis duties. Without a clear understanding of what the expected outcomes are to
be of the business analysis duties, the business analyst cannot adequately plan for the business
analysis duties.
Answer: B is incorrect. It's important for the business analyst to identify and categorize
stakeholders, but this isn't the best answer for this question.
Answer: D is incorrect. The purpose of the proposed solution is valid only if the initiative is to
solve a problem. Business analysis can also occur to detail an opportunity, not just to create
solutions to identified problems.
Answer: C is incorrect. This isn't the best answer for this question.
QUESTION 26
You are the business analyst for your organization. Management has asked you to define and
document the requirements of an endeavor so that the requirements may be reused again in
the organization. Why would an organization want to re-use requirements?
A. Re-using requirements is useful if the organization wants to sell the set of requirements to
its customers.
B. Re-using requirements is useful if the current solution fails.
C. Re-using requirements is useful when the requirements are something the organization
must do on an ongoing basis.
Correct Answer: C
Section: (none) Explanation
Explanation/Reference:
Explanation:
When an organization identifies a set of requirements for an ongoing set of activities, it's useful
to craft the requirements so that the requirements may be used over and over. This saves time,
effort, and cost.
Answer: B is incorrect. This is not a valid statement about re-using requirements in an
organization. Answer: A is incorrect. This is not a valid statement about re-using requirements
in an organization. Answer: D is incorrect. This is not a valid statement about re-using
requirements in an organization.
QUESTION 27
In the life of a project, when do the number and impact of change requests often increase?
Correct Answer: C
Section: (none) Explanation
Explanation/Reference:
Explanation:
As the life of the project draws towards its end, there's often an increase in the number of
change requests. When change requests are made towards the end of a project, however, the
cost and impact of the change increases significantly.
QUESTION 28
You are the business analyst for your organization and preparing to plan the business analysis
approach. There are three inputs to the business analysis approach. Which one of the following
is not an input to this approach?
Correct Answer: C
Section: (none) Explanation
Explanation/Reference:
Explanation:
Enterprise environmental factors are the rules, policies, and procedures that the business
analyst must adhere to. These are already established and therefore are not considered to be
inputs to this process. The three inputs to the plan business analysis approach are business
needs, expert judgment, and organizational process assets.
QUESTION 29
Bradley is working with the business analyst Marsha to prioritize requirements for their
organization. Marsha insists that the requirements be ranked on the cost- benefits analysis of
the relative value to the organization. What type of prioritization approach does Marsha want
to use in this scenario?
Correct Answer: B
Section: (none) Explanation
Explanation/Reference:
Explanation:
Marsha wants to utilize the business value of the requirements using a cost-benefit analysis of
each requirement. The requirements with the higher value are most important.
Answer: A is incorrect. This is not a valid approach to be used in this scenario.
Answer: D is incorrect. There is not a basis for prioritization called the CBR ratio; this is not a
valid choice. Answer: C is incorrect. Urgency prioritizes requirements based on time sensitivity.
QUESTION 30
Billy is the business analyst for her organization and she's working with a team to select a
model. Richard doesn't understand why a model is needed for the requirements. Which one of
the following statements best describes the reason to use a model?
Correct Answer: A
Section: (none) Explanation
Explanation/Reference:
QUESTION 31
What business analysis process is needed to define the solution scope and prepare the business
plan for the endeavor?
A. Verify requirements.
B. Define requirements management and communication. C. Prioritize requirements.
D. Determine solution approach.
Correct Answer: D
Section: (none) Explanation
Explanation/Reference:
Explanation:
The business analysis process of determining the solution approach is the process that's needed
in order to define the solution scope and prepare the business plan for the endeavor.
Answer: C is incorrect. Prioritization of requirements is needed to rank requirements from the
most important to the least important based on the identified needs. Answer: B is incorrect.
Defining requirements management and communication is not related to the solution scope.
Answer: A is incorrect. Verifying requirements is the verification of the requirements for the
stakeholders and completeness of the endeavor.
A. The baseline represents the final collection and approval of all requirements. B. The
baseline represents the future set of physical deliverables.
C. The baseline represents the approved set of requirements and no additional changes are
allowed.
D. The baseline represents the approved requirements and any changes must go through a
change control system.
Correct Answer: D
Section: (none) Explanation
Explanation/Reference:
Explanation:
Of all the choices, this is the best answer, as it acknowledges that although the current set of
requirements is approved, any future changes to the requirements must pass through a change
control system.
Answer: B is incorrect. This statement is moderately true, but current requirements don't
always equate to complete future deliverables. Answer: A is incorrect. This statement is
moderately true, but current requirements don't always equate to complete future
deliverables. Answer: C is incorrect. This statement is not valid, as changes can enter the set of
requirements through the change control process.
A. You define the requirements of the initiative. B. You define the roles and responsibilities.
C. You define the communication needs.
D. You define the business analysis approach.
Correct Answer: D
Section: (none) Explanation
Explanation/Reference:
Explanation:
The purpose of the plan business analysis approach is to define the business analysis approach.
Answer: A is incorrect. The plan business analysis approach does not define the requirements.
Answer: B is incorrect. The plan business analysis approach does not define the roles and
responsibilities. Answer: C is incorrect. The plan business analysis approach does not define the
communication needs.
QUESTION 34
A business analyst has just hosted a brainstorming session that has generated 57 ideas for a
solution. What should the business analyst do with the ideas now?
QUESTION 35
Which of the following is used as a means of validating a created, selected, or tailored business
analysis approach?
A. Process modeling
B. Progressive elaboration
C. Decision analysis
D. Structured walkthrough
Correct Answer: D
Section: (none) Explanation
Explanation/Reference:
Explanation:
Structured walkthrough is used as a means of validating a created, selected, or tailored
business analysis approach.
Answer: C is incorrect. Decision analysis is used to rate available methodologies against
organizational needs and objectives. Answer: A is incorrect. Process modeling is used to define
and document the business analysis approach.
QUESTION 36
As a business analyst in your organization, you must understand the difference between
operative rules and structural rules. What is the difference between structural rules and
operative rules?
A. Structural rules are rules that the organization chooses to enforce as a matter of policy.
Operative rules are intended to help determine when something is or is not true, or when
things fall into a specific category.
B. Operative rules are rules that the organization chooses to enforce as a matter of policy.
Structural rules are intended to help determine when something is or is not true, or when
things fall into a specific category.
C. Operative rules are rules that describe the organizational process assets of the organization.
Structural rules are policies that restrict the authority of each line of
business.
D. Operative rules are rules that define how an organization operates. Structural rules define
the boundaries of the structure, business units, and departments within the organization.
Correct Answer: B
Section: (none) Explanation
Explanation/Reference:
Explanation:
Operative rules are the policies of the organization. Structural rules create categories of things,
actions, and departments within an entity. Answer: A is incorrect. This is not a valid statement
about structural rules and operative rules.
Answer: C is incorrect. This is not a valid statement about structural rules and operative rules.
Answer: D is incorrect. This is not a valid statement about structural rules and operative rules.
A. For defining the specifications for the desired future state based on the solution
B. For gaining approval of chartering the project
C. For defining the information to allow additional work to be performed
D. For gaining approval of cost and schedule
Correct Answer: C
Section: (none) Explanation
Explanation/Reference:
Explanation:
Requirement's verification allows the business analyst and key stakeholders to define any
additional information that will allow any additional work to be performed. In other words,
once the current requirements are approved, the tasks may continue forward based on what's
been analyzed so far.
Answer: D is incorrect. Gaining approval of the cost and schedule is not an accurate answer.
Answer: B is incorrect. Chartering a project isn't the best answer for this question.
Answer: A is incorrect. The requirements comprise the solution scope for the business need, so
this isn't the best answer for the question.
QUESTION 38
Which technique in organizing requirements is best described as showing the concepts and
relationships relevant to the solution or business domain?
QUESTION 39
A business analyst is helping management determine which solution they should choose. As it
happens that the organization can only choose one of the two solutions due to time and
resource restrictions. Solution A worth $456,000 to the organization while solution B worth
$565,000 to the organization. While solution A costs less, it is less risky and takes less time to
complete so management elects to seize Solution A. What is the opportunity cost?
A. $565,000
B. There is not enough information to know how much the solution will cost the organization.
C. $109,000
D. $456,000
Correct Answer: A
Section: (none) Explanation
Explanation/Reference:
Explanation:
The opportunity cost is the total value of the opportunity that can be taken advantage of.
A. Project manager
B. Domain subject matter expert
C. Sponsor
D. Regulator
Correct Answer: B
Section: (none) Explanation
Explanation/Reference:
Explanation:
The domain subject matter expert is a person who is steeped in knowledge regarding the
project's purpose.
Answer: A is incorrect. The project manager must ensure that the business analysis approach is
compatible with other project activities. Answer: D is incorrect. The regulator approves any
tailoring to the business analysis processes or activities.
Answer: C is incorrect. The sponsor allows the business analysis activities and resources to exist
in support of the organization.
QUESTION 41
You are the business analyst for your organization. You are currently identifying opportunities
for a customer to improve their business processes. The customer wants to streamline their
business efforts either through new technologies, better processes, or a combination of both.
The customer demands, however, that the solution should not cost more than $300,000 to
implement and support for one year. What does the $300,000 represent?
Correct Answer: B
Section: (none) Explanation
Explanation/Reference:
Explanation:
The maximum price of $300,000 is a constraint that the solution must be bound to. The
solution does not have to cost $300,000, it just cannot exceed this limit. Answer: A is incorrect.
A budget is the defined amount of funds to implement a solution. In this instance, the
stakeholder will accept a maximum of $300,000 or less for a solution. Because a solution has
not been identified the budget is not yet known.
Answer: D is incorrect. Requirements are the characteristics of the solution, not the constraint
of the price. Answer: C is incorrect. A solution has not yet been proposed so the cost of the
solution is still unknown.
QUESTION 42
You are the business analyst for your organization. On your current project you'll be using the
change-driven approach for defining requirements and gathering feedback. Which of the
following statements best describes the change-driven approach?
QUESTION 43
According to the business analysis book 'A Guide to the Business Analysis Body of Knowledge',
which your exam is largely based on, almost all methodologies fit somewhere along a spectrum
between plan-driven and what other methodology?
A. Risk-driven
B. Cost-driven
C. Change-driven
D. Reward-driven
Correct Answer: C
Section: (none) Explanation
Explanation/Reference:
Explanation:
The methodology that defines the business analysis approach is either plan-driven or change-
driven. Answer: A is incorrect. Risk-driven is not a valid approach for planning business analysis
QUESTION 44
Which of the following is used to rate available methodologies against organizational needs?
A. Structured walkthrough
B. Progressive elaboration
C. Decision analysis
D. Process modeling
Correct Answer: C
Section: (none) Explanation
Explanation/Reference:
Explanation:
Decision analysis is used to rate available methodologies against organizational needs and
objectives. Answer: D is incorrect. Process modeling is used to define and document the
business analysis approach.
Answer: A is incorrect. Structured walkthrough is used as a means of validating a created,
selected, or tailored business analysis approach.
Answer: B is incorrect. Progressive elaboration describes the process of providing more and
more information through incremental details. It is a form of deductive reasoning to go from a
very broad set of requirements to the exact details on the requirements.
QUESTION 45
You're organizing the business analysis approach for your organization. Jane wants to know
when changes to requirements are most likely to happen in business analysis processes. Which
one of the following statements best describes when changes to requirements may happen?
A. Changes to requirements usually happen at the end of the business analysis processes. B.
Changes to requirements usually happen early in the business analysis processes.
Correct Answer: C
Section: (none) Explanation
Explanation/Reference:
Explanation:
Changes to requirements may happen at any time in the business analysis processes and
throughout the project. When these changes happen later in the process, it becomes more
difficult to accept, communicate, and manage those changes.
Answer: B is incorrect. Changes may happen at any time, not just at the beginning of the
processes. Answer: A is incorrect. Changes don't just happen at the end of the business analysis
processes. Answer: D is incorrect. Changes may happen at any time, not just after the business
analysis processes.
QUESTION 46
There are three inputs for stakeholder analysis. Which input describes the organizational units
that exist and their interactions with one another?
A. Business need
B. Enterprise architecture
C. Matrix structure
D. Organizational process asset
QUESTION 47
You are the business analyst in your organization. Management comes to you with a customer
complaint that they'd like you to analyze. What's the common task associated with customer
complaints or loss of revenue?
Correct Answer: C
Section: (none) Explanation
Explanation/Reference:
Explanation:
When there are customer complaints, loss of revenue, or new market opportunities, the best
course of action is the evaluation of a business need. Answer: D is incorrect. Capability
assessments are useful, but they happen after defining and evaluating the business need.
QUESTION 48
Kelly is the business analyst for her organization and she's identifying roles and responsibilities
of the people involved in business analysis activities. Her manager has asked Kelly to create the
RACI matrix to accomplish this task. What is the RACI matrix?
A. The RACI matrix is a roles and responsibilities chart that uses the legend of Responsible,
Action, Controlled, and Informed. B. The RACI matrix is a roles and responsibilities chart that
uses the legend of Role, Action, Controlled, and Information.
C. The RACI matrix is a roles and responsibilities chart that uses the legend of Responsible,
Accountable, Consulted, and Informed. D. The RACI matrix is a roles and responsibilities chart
that uses the legend of Risk, Action, Cost, and Information.
Correct Answer: C
Section: (none) Explanation
Explanation/Reference:
Explanation:
The RACI matrix is a roles and responsibilities chart that uses the legend of Responsible,
Accountable, Consulted, and Informed.
QUESTION 49
Beth is a business analyst for her organization and she's discussing the solution with her key
stakeholders. Beth is considering that moving to a new operating system, new office software,
and new customized applications will be too much for the end users to learn and to manage
their ongoing responsibilities. What task is Beth completing in this scenario?
Correct Answer: D
Section: (none) Explanation
Explanation/Reference:
Explanation:
Beth is performing the assessment of organizational readiness. This task reviews the
organization's ability to accept and use the solution. Answer: A is incorrect. Stakeholder
management is not an applicable business analysis task for this scenario.
Answer: C is incorrect. The task of defining transition requirements describes the process of
moving from one solution to another. Answer: B is incorrect. Evaluation of solution
performance is the task of reviewing current solutions for improvement.
QUESTION 50
Management comes to you and asks you to complete some specifications and models about
the current state of the organization.
Management wants you to complete this business analysis activity as soon as possible and
report back to them with your findings. What is the primary purpose of the specify and model
requirements process?
A. To analyze the roles and responsibilities of users within the organization to determine how
the processes may be improved.
B. To analyze the utility function within the organization to determine how risk tolerance may
allow for new opportunities.
C. To analyze the functioning of an organization and to provide an insight into opportunities for
improvement.
D. To analyze the processes of an organization to determine what processes can be improved,
removed, or added.
QUESTION 51
In preparation for your business analysis examinations, you should be familiar with the tasks to
complete requirements management and communication activities. How many tasks are there
in the knowledge area of requirements management and communication?
A. 7
B. 4
C. 5
D. 6
Correct Answer: C
Section: (none) Explanation
Explanation/Reference:
Explanation:
Following are the tasks in Requirements Management and Communication: Manage solution
scope and requirements.
Manage requirements traceability. Maintain requirements for reuse. Prepare requirements
package. Communicate requirements.
A. Communicate requirements.
B. Prepare the requirements package.
C. Manage requirements traceability.
D. Document requirements for review.
Correct Answer: C
Section: (none) Explanation
Explanation/Reference:
Explanation:
The question describes the task of managing requirements traceability.
Answer: B is incorrect. Preparing the requirements package is a task that selects and structures
a set of requirements to ensure that the requirements are effectively communicated to,
understood by, and usable by a stakeholder group or groups.
Answer: A is incorrect. Communicating requirements is the process of discussing the
requirements through communication channels to ensure that the stakeholders understand the
requirements.
Answer: D is incorrect. Documenting requirements for review is not a valid answer, as this is not
a business analysis task in the requirements management and communication knowledge area.
QUESTION 53
Which of the following describes the organizational policies, procedures, forms, and
methodologies the business analyst is to follow?
A. Organizational process asset
B. Enterprise architecture
Correct Answer: A
Section: (none) Explanation
Explanation/Reference:
Explanation:
Organizational process assets describe the organizational policies, procedures, forms, and
methodologies the business analyst is to follow. Answer: C is incorrect. The business need
describes business requirements, solution scope, and solution requirements.
Answer: B is incorrect. The enterprise architecture describes the relationship among the
organizational units and how the organizational units act with one another. Answer: D is
incorrect. A matrix structure is not one of the three inputs to the business analysis process.
QUESTION 54
You are the business analyst for your organization. You've believed that your solution can
actually be purchased from outside vendor rather than trying to create the solution internally.
You decide to ask the vendor to provide a fee for their services based on the statement of work.
What document will you give the vendor along with the statement of work?
Correct Answer: A
Section: (none) Explanation
Explanation/Reference:
Explanation:
QUESTION 55
Which requirements allocation technique is best described as the breaking down of the solution
scope into smaller units for allocation?
A. Functional decomposition
B. Resource allocation granularity
C. WBS creation
D. Process modeling
Correct Answer: A
Section: (none) Explanation
Explanation/Reference:
Explanation:
Functional decomposition takes the solution scope and decomposes it into smaller, more
manageable units.
Answer: B is incorrect. Resource allocation granularity isn't a business analysis term and is not
acceptable for this question. Answer: D is incorrect. Process modeling maps activities in a
process model to different roles, vendors, and contractors.
Answer: C is incorrect. WBS creation also uses a decomposition of the project scope into work
packages, but it's not the process described in this question.
Correct Answer: C
Section: (none) Explanation
Explanation/Reference:
Explanation:
Requirements verification activities are performed iteratively throughout the requirements
analysis process.
Answer: A is incorrect. Requirements verification happens in iterations, not just at milestones
(assuming there are milestones in the process).
Answer: B is incorrect. Verification activities don't happen just at the end of the requirements
gathering process, but iteratively throughout the process. Answer: D is incorrect. This answer is
tempting, but it's not the best answer.
QUESTION 57
Business needs do not always originate from the business analyst or from business owners.
There are several stakeholders which may identify or contribute to the identification of a
business need. Which one of the following stakeholders are most likely to have the most direct
awareness of problems that could lead to a business need?
A. End users
B. Business analysts
Correct Answer: A
Section: (none) Explanation
Explanation/Reference:
Explanation:
End users of a system are the stakeholders that are to have the most direct awareness of
problems. The end users typically represent the largest group of stakeholders and are closest to
the applications, services, and facilities where business needs may be represented.
Answer: C is incorrect. Project managers may be aware of business needs, but they aren't the
most likely stakeholders.
Answer: D is incorrect. Functional managers oversee end users and other resources, but may
not be the stakeholders closest to the need. Answer: B is incorrect. Business analysts can help
identify and clarify the need, but this isn't the best choice for the question.
QUESTION 58
You are the business analyst for your organization and are leading a presentation about an
identified problem. This presentation will help the stakeholders to understand the problem and
it will help you when you begin to elicit requirements from the stakeholders. Which type of
learner learns best through the presentation of models?
A. Kinesthetic learners
B. Auditory learners
C. Communication model learners
D. Visual learners
QUESTION 59
Brian is the business analyst for his organization and he's hosting a brainstorming session. He is
facilitating the session with eight stakeholders. Why is it important for Brian to not set a goal
for the number of ideas the group should generate in the session?
Correct Answer: D
Section: (none) Explanation
Explanation/Reference:
Explanation:
When a business analyst sets a goal for the number of ideas to be generated during a
brainstorming session, it actually limits the number of ideas that the group can generate. For
example, if Brian sets the goal of 25 ideas, then once the group reaches 25, the session ends
instead of urging more ideas into the session. Answer: C is incorrect. While it's possible that the
goal may be too large to be feasible for the session, this isn't the best choice presented.
QUESTION 60
You are the business analyst for your organization and you're preparing the solution for your
organization's review and implementation. Some of the requirements of the solution, however,
must be inspected by compliance officers before the project and implementation can move
forward. The requirements of the inspection can be best described as what?
A. Bottleneck
B. Requirements
C. Cost-negativity
D. Constraint
Correct Answer: D
Section: (none) Explanation
Explanation/Reference:
Explanation:
Requirements that require a compliance officer to be regulated and inspected are constraints
that limit the project's options.
Answer: B is incorrect. While these are requirements, the best answer is a constraint.
Constraints limit the project's ability to move forward. A delay in the inspection can delay the
project.
Answer: C is incorrect. This isn't a valid term and isn't applicable to this scenario.
Answer: A is incorrect. While some business analysts and project managers may call this a
bottleneck in the flow of the project, the correct business analysis term for this is constraint.
A. Risk
B. Assumption
C. Constraint
D. Boundary
QUESTION 62
All of the following are examples of elicitation techniques that are used as part of the business
analyst elicitation task except for which one?
A. Brainstorming
B. Observation
C. Decomposition
D. Prototyping
QUESTION 63
You are the business analyst for your organization and you're preparing to elicit requirements
from the stakeholders. You've gathered several inputs to help with the elicitation process.
Which input(s) will be used to ensure that you understand the type of information that should
be elicited from the stakeholders?
A. Stakeholder list
B. Risk assessment
C. Business need
D. Roles and responsibility
Correct Answer: C
Section: (none) Explanation
Explanation/Reference:
Explanation:
The business need and the solution scope are the two inputs which help the business analyst
understand what should be elicited from the stakeholders. Answer: A is incorrect. Stakeholder
list, roles, and responsibilities help the business analyst understand from whom the
QUESTION 64
You are a business analyst for your organization and you're working with the stakeholders to
identify the primary inputs to the business analysis approach. Which one of the following is a
primary input to the business analysis approach?
A. The business analysis approach will be shaped by the problem or opportunity faced by the
organization.
B. The business analysis approach will be shaped by the penalty of not seizing the opportunity.
C. The business analysis approach will be shaped by the time allowed for business analysis
planning.
D. The business analysis approach will be shaped by the risks faced by the organization.
Correct Answer: A
Section: (none) Explanation
Explanation/Reference:
Explanation:
A primary input to the business analysis approach is to consider the problem or opportunity
faced by the organization.
Answer: C is incorrect. The time allowed for business analysis planning does have an effect on
the thoroughness of the business analysis activities, but this isn't the best answer for the
question.
Answer: D is incorrect. While risk and reward are considerations, consideration of the problem
or opportunity is a better choice for this question.
Answer: B is incorrect. This answer doesn't consider the reward of the opportunity or
acknowledge, as there may also be problems to be solved, not just opportunities to seize.
A. The communications management plan will dictate what will happen to the business
analysis communications.
B. All formal communication must be destroyed once the project is completed.
C. All communications must be archived and will become part of the organizational process
assets.
D. All communications must be documented and passed onto the solution's project manager
for analysis and to serve as supporting detail.
Correct Answer: C
Section: (none) Explanation
Explanation/Reference:
Explanation:
Communications in a plan-driven approach to business analysis must use formal
communication. Formal communications should be archived as part of the organizational
process assets.
Answer: A is incorrect. The communications management plan may dictate that the
communications be archived, but this is not a requirement of the communications
management plan.
Answer: D is incorrect. The project manager may want to reference the communication but
doesn't always need. If the communications are archived, then the project manager can access
them as needed.
Answer: B is incorrect. Communication documents are not destroyed; they are archived as part
of the organizational process assets.
Correct Answer: D
Section: (none) Explanation
Explanation/Reference:
Explanation:
Prioritization of requirements is used to make certain that analysis and implementation efforts
focus on the most critical requirements. The requirement prioritization process ranks the
requirements by importance. It is a decision process. This process is used for determining the
relative importance of requirements. These priorities determine which requirements should be
targets for further analysis.
Answer: C is incorrect. Requirements prioritization does not rank the requirements by the
stakeholders, but by the needs of the stakeholders and the requirements that are most
important to satisfy those needs.
Answer: A is incorrect. Requirements prioritization does not rank the requirements according to
the cost and schedule, but by importance. Answer: B is incorrect. Requirements prioritization
does not rank the requirements on a weighted scale; this isn't a valid statement.
Correct Answer: C
Section: (none) Explanation
Explanation/Reference:
Explanation:
In order to use the matrix documentation approach to model requirements, the identified
requirements must have the uniform structure of their characteristics and identification.
Answer: A is incorrect. The requirements do no need to have opposing values to use the matrix
documentation approach. Answer: B is incorrect. While this choice is tempting, the best answer
is the uniform structure.
Answer: D is incorrect. This isn't a valid answer, as requirements don't need rated goals.
QUESTION 68
Which of the following is a business management strategy originally developed by Motorola,
USA in 1986?
A. Quality Circle
B. Waterfall model
C. Lean
D. Six Sigma
QUESTION 69
As a business analyst, you'll often have to coach stakeholders on the processes, knowledge
areas, and tasks you'll complete for an organization. One of the knowledge areas is enterprise
analysis. This knowledge area completes all of the following activities except for which one?
Correct Answer: D
Section: (none) Explanation
Explanation/Reference:
Explanation:
The Requirements Management and Communication knowledge area describes the activities
and considerations to manage and express requirements to a broad and diverse audience. The
execution of these tasks ensures the following facts:
The stakeholders have a shared understanding of the nature of a solution.
QUESTION 70
You are the business analyst for your organization and you're working with your manager to
discuss the constraints and assumptions that may affect the requirements. Your manager wants
to know from where you've derived the list of constraints and assumptions. What's the best
answer as to where assumptions and constraints are identified?
Correct Answer: B
Section: (none) Explanation
Explanation/Reference:
Explanation:
Assumptions and constraints are identified through elicitation from stakeholders.
Answer: D is incorrect. Assumptions and constraints are not identified through document
analysis.
Answer: C is incorrect. Assumptions and constraints are not identified through risk
identification, though false assumptions may be subject to risk analysis. Answer: A is incorrect.
Assumptions and constraints are not identified through a review of project requirements.
Correct Answer: B
Section: (none) Explanation
Explanation/Reference:
Explanation:
The work breakdown structure (WBS) is a tool used to define the scope of work and to develop
estimates. This tool creates a hierarchy of work by decomposing the project scope into smaller
and smaller pieces. WBS can perform the following tasks:
It may break the project into iterations, releases, or phases. It can break deliverables into work
packages.
It may break activities into smaller tasks.
Answer: C, A, and D are incorrect. The inputs to requirements management and communication
are as follows: Business Analysis (BA) communication plan
Requirement Management Plan
Solution Scope Requirements Structure Organizational Process Assets
Stakeholder, List, Roles, and Responsibilities
Requirements
Correct Answer: C
Section: (none) Explanation
Explanation/Reference:
Explanation:
The Identify Stakeholders process identifies all people or organizations that are impacted by the
project. It also documents relevant information regarding their interests, involvement, and
impact on project success. Stakeholder register and stakeholder management strategy are
outputs of this process.
Answer: B is incorrect. Project charter is one of the inputs of the Identify Stakeholders process.
Answer: A is incorrect. Scope baseline is one of the outputs of the Create Work Breakdown
Structure (WBS) process. Answer: D is incorrect. Project scope statement is one of the outputs
of the Define Scope process.
QUESTION 73
You are documenting the requirements attribute for your requirements management plan.
Which attribute would you use if you want to identify the person who created the
requirements?
A. Absolute reference
B. Ownership
C. Requirements sponsor
D. Author of the requirements
QUESTION 74
A business analyst has just completed an elicitation event. What stakeholder(s) is/are involved
in the documentation of the elicitation results?
Correct Answer: B
Section: (none) Explanation
Explanation/Reference:
Explanation:
Only the business analyst is involved in the documentation of the elicitation results.
Answer: D is incorrect. Only the business analyst is involved in the documentation of the
elicitation results, not the project manager and project sponsor. Answer: C is incorrect. Only the
QUESTION 75
Consider a business analyst who is completing the business analysis tasks of specifying and
modeling requirements for an organization. This task can help an organization achieve all of the
following objectives except for which one?
Correct Answer: D
Section: (none) Explanation
Explanation/Reference:
Explanation:
The task of specifying and modeling requirements does not ensure that revenues will increase
or that costs will be reduced. However, the task does allow for some insight into operational
improvements.
Answer: C is incorrect. The task of specifying and modeling requirements does help with
compliance to contracts and regulations. Answer: B is incorrect. The task of specifying and
modeling requirements does help the stakeholders communicate better. Answer: A is incorrect.
The task of specifying and modeling requirements can help with training and knowledge
management.
A. Required capability
B. Assumptions and constraints
C. Business need
D. Allocation of requirements
Correct Answer: D
Section: (none) Explanation
Explanation/Reference:
Explanation:
The task of allocating requirements is the future task in the business analysis domain that will
need the solution scope. The four inputs to the solution scope are assumptions and constraints,
business need, required capabilities, and solution approach.
Answer: B is incorrect. Assumptions and constraints is one of the four inputs to the solution
scope. Answer: C is incorrect. Business need is one of the four inputs to the solution scope.
Answer: A is incorrect. Required capability is one of the four inputs to the solution scope.
QUESTION 77
What can be considered the only input to the task of defining assumptions and constraints?
A. Business case
B. Prioritized requirements
C. Requirements
D. Stakeholder concern
QUESTION 78
A business analyst wants to elicit requirements from a large group of stakeholders. One of her
primary goals of this event is to produce a broad set of options for solutions. Which elicitation
technique would you recommend for this business analyst?
Correct Answer: B
Section: (none) Explanation
Explanation/Reference:
Explanation:
Brainstorming is the business analysis solution the business analyst should use to generate a
broad set of options.
Answer: C is incorrect. Benchmarking compares two comparable businesses, solutions, systems,
or other entities for measurement, goal setting, and idea generation.
QUESTION 79
Which of the following is the prime purpose of the Manage Stakeholders Expectations process?
A. Identify stakeholders
B. Close project
C. Resolve issues
D. Updating risk registers
Correct Answer: C
Section: (none) Explanation
Explanation/Reference:
Explanation:
The prime purpose of the Manage Stakeholders Expectations process is to resolve issues. These
issues may be from different areas of the project. An issue log or action item log can be used to
document and monitor the resolution of issues. It can be used to facilitate communication and
ensure a common understanding of issues. Issues are resolved to maintain good, constructive
working relationships among various stakeholders, including team members.
Answer: B is incorrect. Although, the Manage Stakeholders Expectations process helps in
closing the project, it is not the prime purpose of this process. Answer: A is incorrect.
Stakeholders identification is done in the separate process named Identify Stakeholders.
Answer: D is incorrect. Risk register is a document that contains the results of the qualitative
risk analysis, quantitative risk analysis, and risk response planning. Description, category, cause,
probability of occurring, impact on objectives, proposed responses, owner, and the current
status of all identified risks are put in the risk register. Updating risk registers is done
throughout the project duration. It is not the prime purpose of the Manage Stakeholders
Expectations process.
A. Risk analysis
B. Business need
C. Requirements management plan
D. Business case
Correct Answer: A
Section: (none) Explanation
Explanation/Reference:
Explanation:
Risk analysis is not considered for prioritization of requirements. The correct inputs are
business case, business need, requirements, requirements management plan, and the
stakeholder list, roles, and responsibilities.
Answer: D is incorrect. Business case is needed as an input for the task of prioritizing
requirements. Answer: B is incorrect. Business need is needed as an input for the task of
prioritizing requirements.
Answer: C is incorrect. The requirements management plan is needed as an input for the task of
prioritizing requirements.
QUESTION 81
What elicitation technique is best described as a study to compare the strengths and
weaknesses of an organization against its peers and competitors?
A. Brainstorming
B. Market analysis
C. Comparative analysis
D. Benchmarking
QUESTION 82
You are the business analyst for your organization and you and your staff are creating as many
solutions as possible to an identified problem in the solution approach process. What is this
activity element called?
A. Alternative generation
B. Brainstorming
C. Prototyping
D. Lateral thinking
Correct Answer: A
Section: (none) Explanation
Explanation/Reference:
Explanation:
When the business analyst and stakeholders are generating as many potential options as
possible for a solution, it's called alternative generation. Answer: B is incorrect. Brainstorming is
not used as an element for the solution approach process.
QUESTION 83
What type of requirements elicitation technique is the Delphi Technique?
A. Survey
B. Workshop
C. Prototyping
D. Round table
Correct Answer: A
Section: (none) Explanation
Explanation/Reference:
Explanation:
The Delphi Technique uses rounds of anonymous surveys to build consensus among the
stakeholders. Answer: B is incorrect. The workshop is not an example of the Delphi Technique.
Answer: D is incorrect. The round table is a discussion of a topic, not a requirements elicitation
technique. Answer: C is incorrect. Prototyping is not the equivalent of the Delphi Technique.
QUESTION 84
Which one of the following is not an event-based elicitation technique?
A. Focus group
B. Interface analysis
C. Interview
D. Workshop
QUESTION 85
What do business goals and objectives of enterprise analysis actually describe?
A. Business goals and objectives describe the increased revenue that the organization is
seeking to gain.
B. Business goals and objectives describe the solution scope that the organization is seeking to
accomplish. C. Business goals and objectives describe the ends that the organization is seeking
to achieve.
D. Business goals and objectives describe the desired future state of problems.
Correct Answer: C
Section: (none) Explanation
Explanation/Reference:
Explanation:
Business goals and objectives describe the ends that the organization is seeking to achieve. It is
the assessment of the desired future state of the organization. Answer: B is incorrect. The best
answer is that the ends of the solution are defined, not just the solution scope.
Answer: A is incorrect. Business goals and objectives aren't always focused on increased
revenue so this isn't the best choice for the question. Answer: D is incorrect. This answer is
close, but it's not the future state of the problems that is defined, but the future state of the
organization.
A. Risk analysis
B. Prototyping
C. Stakeholder management
D. Structured walkthrough
Correct Answer: D
Section: (none) Explanation
Explanation/Reference:
Explanation:
Structured walkthroughs are meetings that help determine if the stakeholders agree that their
needs are being met with the identified requirements. Answer: A is incorrect. Risk analysis
reviews identified risks in the requirements to determine the probability and impact of the risk
event.
Answer: B is incorrect. Prototyping is used to gain user agreement with the proposed solution
and requirements for the solution. Answer: C is incorrect. Stakeholder management is not a
technique that is used as part of validating requirements.
QUESTION 87
You are a business analyst for your organization and you're working with the stakeholders to
identify the primary inputs to the business analysis approach. Which of the following are
primary inputs of planning the business analysis approach?
Each correct answer represents a complete solution.
A. Organizational process assets
B. Penalty of not seizing the opportunity
C. Expert Judgement
D. Business need
QUESTION 88
A business analyst needs to prepare the requirements package for her endeavor in a predefined
template for her company. What term can be assigned to this standardized template for
packaging the requirements?
Correct Answer: A
Section: (none) Explanation
Explanation/Reference:
Explanation:
Templates for requirements packages are taken from organizational process assets. Answer: C
is incorrect. Essential isn't a valid explanation for this question.
Answer: D is incorrect. Enterprise environmental factors aren't where templates originate from
for business analyst requirements packages. Answer: B is incorrect. This isn't a valid term for
organizational process assets or templates needed by the business analyst.
Correct Answer: D
Section: (none) Explanation
Explanation/Reference:
Explanation:
Changes generally increase towards the end of the project. This can be due to a loosely defined
scope, lack of requirements, and other reasons. Answer: B is incorrect. The scope management
process happens throughout the project until the scope is completed.
Answer: C is incorrect. Changes are easier to incorporate at the launch of the project but
generally do not happen until later in the project. Answer: A is incorrect. Scope changes
generally happen towards the end of the project.
QUESTION 90
You are the business analyst for your organization and you're working with the key
stakeholders to validate the requirements. In your review, you have determined the business
value of each requirement and you've discovered three requirements that do not deliver direct
or indirect value to the stakeholders. What should you do with these requirements?
QUESTION 91
According to 'A Guide to the Business Analysis Body of Knowledge', when should the business
analyst and an organization actually start requirements allocation?
QUESTION 92
You are working with the project stakeholders to analyze and prioritize their requirements for
the project. One of the project requirements is to achieve a high-level of customer satisfaction
for the project deliverable. What is the danger in this project requirement?
A. Achieving customer satisfaction is a risk, as the project manager cannot control how
satisfied the customer will be with the project deliverables.
B. Achieving customer satisfaction is an assumption and should be documented in the project
scope.
C. Achieving customer satisfaction should always map to the quality requirements for the
project.
D. Achieving customer satisfaction is a subjective requirement and entails a high level of risk of
being successfully accomplished.
Correct Answer: D
Section: (none) Explanation
Explanation/Reference:
Explanation:
While every project manager wants to achieve customer satisfaction, this subjective term is too
vague to be measured or accounted for.
What one person deems customer satisfaction may be low compared to another. Requirements
need metrics to determine the level of success. Answer: C is incorrect. The subjective
requirements cannot be measured or mapped to quality requirements.
Answer: B is incorrect. This is not an assumption, but a subjective requirement.
Answer: A is incorrect. This is not a risk, but a requirement that needs metric for measurement
attached to it.
A. Work with the appropriate stakeholders to determine how the business analysis work
should be completed.
B. Define the organizational standard first.
C. Create a business case for the need of organizational standards for business analysis.
D. Take charge and begin the business analysis activities, but document your approach to serve
as a template for future business analysis initiatives.
QUESTION 94
You are the business analyst for your organization and you're working with the project manager
to complete some business analysis activities. The project manager has the authority to
approve the requirements based on the short iterations of business analysis activities.
What approach of business analysis are you using in this scenario?
QUESTION 95
In a change-driven environment, what's more important than formal communications in regard
to effective requirements management?
A. Correct communication
B. Frequency of communication
C. Message of communication
D. Type of communication
QUESTION 96
When a business analyst performs requirements tracing, he may need to trace the
requirements backward through their lineage and may need to trace the requirements forward
through their relationship to other requirements. What is the forward tracing activity called in
requirements traceability?
A. Lineage tracking
B. Backwards pass
C. Derivation
D. Allocation
QUESTION 97
You are the business analyst for the NHQ Project. You have identified several stakeholders that
need different types of information related to the requirements. Which stakeholder would
need detailed technical interface requirements?
A. Project manager
B. Testers
C. Implementation subject matter experts
D. Regulators
Correct Answer: C
Section: (none) Explanation
Explanation/Reference:
Explanation:
The implementation subject matter experts will need requirements that provide detailed
interface requirements, so that they may construct the solution. They are responsible for
designing and implementing potential solutions. Implementation subject matter experts will
provide specialist expertise on the design and construction of the solution components.
QUESTION 98
As a business analyst, you should be able to identify the characteristics of each business
analysis task and domain area. Which one of the following statements best describes the
characteristics of the business analysis knowledge area of requirements analysis?
A. It describes the activities and considerations for managing and expressing requirements to a
broad and diverse audience.
B. It describes the business analysis activities necessary to identify a business need, problem,
or opportunity, define the nature of a solution that meets that need, and justify the investment
necessary to deliver that solution.
C. It describes the tasks and techniques used by a business analyst to analyze stated
requirements in order to define the required capabilities of a potential solution that will fulfill
stakeholder needs.
D. It is the act of eliciting business, stakeholder, solution, or transition requirements.
Correct Answer: C
Section: (none) Explanation
Explanation/Reference:
Explanation:
This is the only statement that correctly defines the business analysis knowledge area of
requirements analysis. Answer: B is incorrect. This statement describes the enterprise analysis
knowledge area.
Answer: A is incorrect. This statement is the definition of the requirements management and
communication domain. Answer: D is incorrect. This statement describes the process for the
elicitation of requirements in an organization.
A. To define the historical information that is available for the business analyst to rely on for his
research.
B. To define the rules that govern decisions in and organization and that define, constrain, or
enable organizational policies.
C. To define the people that govern decisions in and organization and that define, constrain, or
enable organizational policies.
D. To define the job functions, roles and responsibilities, and the designation of power among
the project stakeholders.
Correct Answer: B
Section: (none) Explanation
Explanation/Reference:
Explanation:
The process of the business rules analysis is the documentation and understanding of the
enterprise environmental factors that enable the organization to operate while also creating
boundaries for the people and processes within the organization.
Answer: A is incorrect. This is a description of the organizational process assets.
Answer: D is incorrect. This is an identification of the stakeholders and their positions and
characteristics for the business analysis duties.
Answer: C is incorrect. The identification of the people that create the enterprise
environmental factors are not relevant for this business analysis process.
Correct Answer: A
Section: (none) Explanation
Explanation/Reference:
Explanation:
Models do not typically address the resources needed for the project team so this choice is
incorrect.
Models can describe a situation or problem, define boundaries for the business domain,
describe thought processes and action flows, categorize and create hierarchies of items, show
components and relationships, and show business logic.
Answer: C, B, D are incorrect. These are valid components of a model; so these choices are
incorrect.
QUESTION 101
You are the business analyst for a large project that will create new software for the entire
organization. This new software will affect all of the administrative assistants in the
organization schedule meetings, reserve facilities, and share calendars. There are
approximately 2,400administrative assistants in your organization and not all of these people
can attend requirements gathering workshops. What approach can you use to manage and
gather requirements from these
A. You can meet with a small group of administrative assistants that will serve as
representatives for the remaining administrative assistants.
B. You will need to meet with all of the administrative assistants as part requirements
elicitation.
C. You can meet with a small group of administrative assistants and assume their requirements
are reflective of the remaining group of administrative assistants.
D. You can meet with the administrative assistants' managers.
Correct Answer: A
Section: (none) Explanation
Explanation/Reference:
Explanation:
When there are large groups of stakeholders, such as in this example, it's practical to find a
group of stakeholders that can serve as representatives for the remainder of the stakeholders.
Answer: B is incorrect. It's not feasible, as the question indicates, for this large group of
administrative assistants to attend requirements gathering workshops.
Answer: C is incorrect. You can't assume that one small group of the administrative assistants
needs is truly indicative of the reminder of the administrative assistants.
Answer: D is incorrect. The administrative assistants' managers likely don't know enough detail
of how the administrative assistants currently do their work to speak on their behalf.
QUESTION 102
Enterprise analysis provides many things for an organization. All of the following are tasks
included in enterprise analysis except for which one?
A. Assess capability gaps
B. Determine solution approach
C. Define business need
D. Solution performance assessment
QUESTION 103
You are the business analyst for a large project in your organization. While your company
prefers face-to-face communications there are many stakeholders located in different
geographical locations. How can you still effectively serve as a business analyst when the
stakeholders are not collocated?
Correct Answer: D
Section: (none) Explanation
Explanation/Reference:
Explanation:
According to the BABOK, the best solution in these instances is to increase videoconferences
and teleconferences to complete the business analysis duties.
Answer: C is incorrect. Adding more business analysts will increase the cost of the business
analysis duties.
QUESTION 104
You are the business analyst in your organization and you've just completed the assessment on
three different proposed solutions. In your judgment, you don't think any of the solutions
provide enough value to justify being implemented. What should you tell the stakeholders?
Correct Answer: C
Section: (none) Explanation
Explanation/Reference:
Explanation:
When there is no business value to implement the solution, then you should recommend that
the initiative be terminated. Answer: A is incorrect. Choosing the least costly solution that
doesn't add value doesn't make sense for the organization.
Answer: D is incorrect. While this is tempting, the best choice is to recommend that the
initiative be terminated. There's not a good reason to implement a solution that doesn't bring
value to the organization.
Answer: B is incorrect. Asking for more time isn't the best answer when you've already
determined there's no business value in the solutions.
Correct Answer: B
Section: (none) Explanation
Explanation/Reference:
Explanation:
The implementation subject matter expert will be involved in the process to ensure that the
requirements can be implemented.
Answer: A is incorrect. The domain subject matter expert may be involved in the review and
approval of requirements as defined by the stakeholder by the stakeholder roles and
responsibility designation.
Answer: C is incorrect. Project team members aren't involved in the decision of
implementation, so this isn't a valid choice for this answer.
Answer: D is incorrect. The project sponsor reviews the business case, solution, product scope,
and all requirements and approves the documents before implementation.
QUESTION 106
You are the business analyst for your organization and you're working to identify all of the
stakeholders within your organization and outside
your organization to ensure that you've captured the correct requirements for a project. Which
one of the following techniques can be best suited for identifying stakeholders?
A. Interviews
B. User stories
C. Acceptance and Evaluation Criteria
Correct Answer: A
Section: (none) Explanation
Explanation/Reference:
Explanation:
An interview is a systematic approach. It is used for eliciting information from a person or a
group of people in an informal or formal setting by talking to an interviewee, asking relevant
questions, and documenting the responses. Interviewees are also able to identify other
stakeholders.
Answer: C is incorrect. Acceptance and evaluation criteria are useful for identifying who has the
authority to accept or reject solutions.
Answer: D is incorrect. Risk analysis is the study of the probability, impact, and scoring of
identified risk events. Risk analysis is the science of risks and their probability and evaluation in
a business or a process. It is an important factor in security enhancement and prevention in a
system. Risk analysis should be performed as part of the risk management process for each
project. The outcome of the risk analysis would be the creation or review of the risk register to
identify and quantify risk elements to the project and their potential impact.
Answer: B is incorrect. User stories are useful to capture requirements, stakeholder attitudes,
and for identifying actors and roles.
QUESTION 107
When an organization implements a new solution, the organization will often have to provide
dual-support for the new solution and the solution that's being replaced. Which one of the
following is not an input to the transitional requirements definition?
QUESTION 108
The initial high-level listing of requirements in a change-driven approach is also known as what?
A. Requirements envisioning
B. Requirements foundation
C. Product scope
D. Project scope
Correct Answer: A
Section: (none) Explanation
Explanation/Reference:
Explanation:
The initial high-level listing of requirements in a change-driven approach is also known as
requirements envisioning. Answer: D is incorrect. The project scope defines all of the required
work to satisfy the requirements of the project.
QUESTION 109
Martha is the business analyst for her organization and she's been asked to help create a
SMART goal for her company. Which one of the following organizational goals could be
considered SMART?
Correct Answer: B
Section: (none) Explanation
Explanation/Reference:
Explanation:
SMART means that the goals are specific, measurable, achievable, relevant, and time-bounded.
The only goal that meets all of these requirements is the goal to increase revenue by ten
percent by January 15.
Answer: C is incorrect. This is not an example of a SMART goal because there is no deadline.
Answer: D is incorrect. This is not an example of a SMART goal because there is no deadline.
Answer: A is incorrect. This is not an example of a SMART goal because there is no deadline.
Correct Answer: B
Section: (none) Explanation
Explanation/Reference:
Explanation:
From external drivers is used when there's recognized competition in the marketplace. Answer:
D is incorrect. From the top down is defined as the need to achieve a strategic goal.
Answer: A is incorrect. From the bottom up is described as a problem with the current state of a
process, function, or system.
Answer: C is incorrect. From middle management is described as a manager needs additional
information to make sound decisions or must perform additional functions to meet business
objectives.
QUESTION 111
You are the business analyst for your organization. You are currently writing the business goals
and objectives as part of the elements for the define business process. Which one of the
following statements best describes the business goals and objectives element?
A. They describe all of the required work the project will need to complete in order to reach its
objectives.
B. They describe the ends that the organization is seeking to achieve.
C. They describe the processes the solution will need to improve for the project to be
successful. D. They describe all of the positive benefits in ratio to the risk and costs of the
project.
QUESTION 112
You are the business analyst for a large project for your organization. Your project has 65
stakeholders and this will greatly increase the complexity of the communication in this project.
To demonstrate how complex this project and its communication will be, you show the
management the number of communication channels in this project. How many channels exist
in this project based on the number of stakeholders?
A. 4160
B. 4225
C. 65
D. 2080
Correct Answer: D
Section: (none) Explanation
Explanation/Reference:
Explanation:
There are 2,080 communication channels in this project. You can find the number of
communication channels by using the formula N(N-1)/2 where N represents the number of
stakeholders.
Answer: B is incorrect. This is simply 65 times 65. Answer: A is incorrect. This is simply 65 times
64.
QUESTION 113
In order to have high quality in requirements, all of the following characteristics should exist in
the requirements except for which one?
A. Cohesive
B. Consistent
C. Complete
D. Constrained
Correct Answer: D
Section: (none) Explanation
Explanation/Reference:
Explanation:
Constrained is not an attribute of high quality in a requirement. The requirements should be
cohesive, complete, consistent, correct, modifiable, unambiguous, and testable.
Answer: A is incorrect. Cohesive is one of the characteristics of quality in a requirement.
Answer: B is incorrect. Consistent is one of the characteristics of quality in a requirement.
Answer: C is incorrect. Complete is one of the characteristics of quality in a requirement.
QUESTION 114
All of the following stakeholders participate in the prioritization of requirements except for
which one?
A. Project team
B. Implementation subject matter expert
C. Domain subject matter expert
D. Project manager
QUESTION 115
In order to define the business need for an organization, there are two inputs. What are the
two inputs a business analyst will need to define the business need?
Correct Answer: A
Section: (none) Explanation
Explanation/Reference:
Explanation:
In order to conduct the task of defining the business need, the business analyst will need
business goals and objectives.
Answer: C is incorrect. This isn't a valid answer, as Requirements and Business analysis
approach are actually outputs of the task of defining the business need. Answer: B is incorrect.
This isn't a valid answer, as stakeholder identification and stakeholder analysis are actually
outputs of the task of defining the business need. Answer: D is incorrect. This isn't a valid
answer, as Elicitation approach and Solution approach aren't valid inputs.
A. Technical assessment
B. Stakeholder impact analysis
C. Organizational assessment
D. Operational analysis
Correct Answer: B
Section: (none) Explanation
Explanation/Reference:
Explanation:
The stakeholder impact analysis captures the stakeholders' functions, locations, tasks, and
concerns about the solution. Answer: C is incorrect. An organizational assessment isn't a valid
element for the assessment of organizational readiness.
Answer: D is incorrect. The operational analysis will predict if the organization will actually take
advantage of the solution once it's implemented.
Answer: A is incorrect. A technical assessment, like an operational assessment, reviews the
implementation to see if the stakeholders will use the solution once it's been implemented.
QUESTION 117
In order to assess proposed solutions, business analysts will need three inputs. Which one of
the following is not an input to the task of assessing proposed solutions?
A. Solution options
B. Requirements
C. Risk assessments
D. Assumptions and constraints
QUESTION 118
There are three inputs in the plan business analysis approach. Which one of the following is not
one of the three inputs?
Correct Answer: C
Section: (none) Explanation
Explanation/Reference:
Explanation:
Risk and rewards analysis is not, of itself, an input to the business analysis approach process.
Answer: D, B, and A are incorrect. Following are the inputs in the plan business analysis
approach: Business need
Expert judgment
Organizational process assets
A. Implementation SME
B. Traceability
C. Coverage matrix
D. Integrated change control
Correct Answer: B
Section: (none) Explanation
Explanation/Reference:
Explanation:
Traceability can help a business analyst determine the full impact of a change on requirements.
When changes are presented and/or approved, traceability helps the business analyst
determine what changes affect other requirements within the set.
Answer: C is incorrect. A coverage matrix can be used to help facilitate tracing of requirements.
Answer: A is incorrect. An Implementation SME is a stakeholder, not a tool, who may help link
requirements to the solution components. Answer: D is incorrect. Integrated change control is a
project management activity, not a business analysis tool, so this choice is incorrect.
QUESTION 120
You are the business analyst for your organization and you're working with Nancy, the Sales
Director. You've been identifying requirements for Nancy about the sales force and her desire
to add a customer management solution to the sales process. Nancy believes that the software
can help automate the sales process, keep things better organized than the current approach,
and ultimately create more sales for the organization. As a business analyst, which one of the
following should you advise Nancy about her need?
QUESTION 121
If a requirement has been satisfied, why is it still considered a requirement?
QUESTION 122
You need to identify assumptions as part of the assessment of capability gaps. Which of the
following is an example of an assumption?
A. The project manager believes that her project team members can program in COBOL.
B. The software must be compatible with the current operating system.
C. The risk in the project must be quantified.
D. All vendors must have security clearance.
Correct Answer: A
Section: (none) Explanation
Explanation/Reference:
Explanation:
Of all the choices, the belief about the project team members is the best example of an
assumption. An assumption is something that is believed to be true, but it has not been proven
to be true.
Answer: B is incorrect. This is an example of a constraint. Answer: D is incorrect. This is an
example of a requirement.
QUESTION 123
You are the business analyst for a smaller project where there are few requirements.
Management would still like you to create a method to trace the few
requirements for this project. What type of matrix would be best in this instance?
A. Coverage matrix
B. Requirements trace matrix
C. Roles and responsibility matrix
D. RACI matrix
Correct Answer: A
Section: (none) Explanation
Explanation/Reference:
Explanation:
A coverage matrix is a table used to manage tracing. It is ideal for smaller projects where there
are few requirements to trace. It's also ideal for when only the high- level requirements need to
be traced.
Answer: B is incorrect. A requirements trace matrix is a table used to track requirements'
relationships. The columns in the table provide requirements information and associated
project. It is ideal for a solution with many requirements to trace throughout the solution.
Answer: C is incorrect. A roles and responsibility matrix maps team members to their work in
the project or business analysis duties.
Answer: D is incorrect. A RACI chart is a type of roles and responsibilities matrix that uses the
legend of responsible, accountable, consult, and inform.
A. The business analyst should determine which solution has the greatest business value. B.
The business analyst should determine the opportunity cost of each assessment.
C. The business analyst should only have one solution, not five.
D. The business analyst should determine which solution is quickest to implement.
Correct Answer: A
Section: (none) Explanation
Explanation/Reference:
Explanation:
The purpose of assessing proposed solutions is to determine how closely they meet stakeholder
and solution requirements. The business analyst, while assessing a single solution, determines
whether the solution delivers enough business value to justify its implementation.
However, the business analyst has the additional goal of attempting to determine which
solution delivers the greatest business value while assessing multiple alternative solutions.
Answer: C is incorrect. The business analyst can have multiple solutions for a business need.
Answer: B is incorrect. The opportunity cost is not applicable to this scenario.
Answer: D is incorrect. The fastest implementation may not necessarily be the best solution for
an organization.
QUESTION 125
Which approach to business analysis activities deals with rapid delivery of the business value?
A. Quality-driven
B. Change-driven
C. Plan-driven
D. Stakeholder-driven
QUESTION 126
Fred is the business analyst for his organization. His current initiative is quite large, so Fred
decides to create a high-level plan for the business analysis approach, and then to create a
detailed plan for the most imminent activities. What type of business analysis planning is Fred
using in this scenario?
A. Step planning
B. Iterative planning
C. Cyclic planning
D. Rolling wave planning
QUESTION 127
As a business analyst, you'll need to communicate with the stakeholders of the solution you
propose. Why is it important for the business analyst to review the stakeholder concerns as
part of the assessment of the organization for the readiness of the solution?
Correct Answer: D
Section: (none) Explanation
Explanation/Reference:
Explanation:
Stakeholder concerns can magnify to problems and issues with the implementation of the
solution. It's best to address these concerns, issues, threats, and perceived threats before the
actual transition to the new solution.
QUESTION 128
As a business analyst, you should work to identify opportunities to improve the operations of
your organization. Which one of the following improvement opportunities aims to improve the
experience of the customer?
A. Eliminate redundancy.
B. Automate or simplify the work people perform.
C. Increase consistency of behavior.
D. Improve the purchasing process.
Correct Answer: C
Section: (none) Explanation
Explanation/Reference:
Explanation:
When customers experience the same process, such as checkout in different ways, it's
frustrating. This improvement opportunity aims to create consistency in all behaviors to
improve the customer experience.
Answer: B is incorrect. Automating or simplifying the work people perform helps streamline
costs and improve quality by doing the work in the same way each time the work is performed.
Answer: A is incorrect. Eliminating redundancy considers that stakeholders may have common
needs that can be met with a single solution, reducing the cost of implementation.
Answer: D is incorrect. While this choice is tempting, it's not an actual improvement
opportunity for the business analyst to consider.
A. Standards
B. Organizational process assets
C. Governance
D. Regulations
Correct Answer: B
Section: (none) Explanation
Explanation/Reference:
Explanation:
The best answer is organizational process assets. These include the organization's preference
for presenting requirements, forms, processes, and internal requirements.
Answer: D is incorrect. Regulations don't represent the best answer for this question.
Answer: A is incorrect. Standards are guidelines and don't represent the best answer for this
question.
Answer: C is incorrect. While governance is tempting, the best answer is organizational process
assets, as it represents the rules and policies of the organization.
QUESTION 130
You are the business analyst for your organization and your requirements for the endeavor
have recently been approved. Your organization creates a baseline for the requirements based
on the approval of the requirements. What must happen in your business analysis activities if
the requirements for your endeavor need to be changed?
A. You'll need to create new baselines.
B. You'll need to implement configuration management.
Correct Answer: C
Section: (none) Explanation
Explanation/Reference:
Explanation:
If an organization baselines requirements and the requirements change after approval, then the
organization must use a change control system. The change control system helps to manage
desired changes, provides governance for the change, and documents the proposed change.
Answer: A is incorrect. Rebaselining is rarely appropriate; sending the changes through the
change control system is the best answer.
Answer: D is incorrect. Requirements versioning may be appropriate if the changes are actually
approved after they've passed through the change control system. Answer: B is incorrect.
Configuration management controls the features and functions of the requirements. The best
choice is to send the proposed change through the change control system.
QUESTION 131
When can changes to requirements occur in a business analysis planning and monitoring
assignment?
A. Changes to requirements can occur any time after the project's change control system has
been enacted.
B. Changes to requirements can occur at any time.
C. Change to requirements can occur any time before the project scope statement is created.
D. Change to requirements can occur at any time before the key stakeholders approve the
identified requirements.
QUESTION 132
You are the business analyst for your organization. You are coaching Tom about the different
approaches to business analysis. Which type of business analysis approach has the most
business analysis work at the beginning of the project or during the start of a project phase?
A. Requirements-driven approach
B. Change-driven approach
C. Plan-driven approach
D. Value-driven approach
Correct Answer: C
Section: (none) Explanation
Explanation/Reference:
Explanation:
The plan-driven approach has the most business analysis work at the beginning of the project
or during the start of a project phase. This approach has a high amount of formality and detail
for all areas of the business analysis duties, requirements gathering, and monitoring.
QUESTION 133
Some of the requirements in the solution must be completed because of laws and regulations
in your industry. Management would like you, the business analyst, to rank the requirements
according to the relevant laws. What type of requirements prioritization is management having
you complete?
Correct Answer: D
Section: (none) Explanation
Explanation/Reference:
Explanation:
This is an example of a regulatory ranking as you're prioritizing the requirements based on the
requirements that must be implemented based on the regulatory demands.
Answer: B is incorrect. Risk ranking is a prioritization of requirements based on their associated
technical risks. Answer: C is incorrect. This is not a valid prioritization method.
Answer: A is incorrect. The business value ranking prioritizes requirements based on their cost-
benefit analysis.
A. Business need
B. Enterprise architecture
C. Matrix structure
D. Organizational process asset
Correct Answer: B
Section: (none) Explanation
Explanation/Reference:
Explanation:
The enterprise architecture describes the relationship among the organizational units and their
interactions with one another. Answer: A is incorrect. Business need describes business
requirements, solution scope, and solution requirements.
Answer: C is incorrect. A matrix structure is not one of the three inputs for stakeholder analysis.
Answer: D is incorrect. Organizational process assets describe the organizational policies,
procedures, forms, and methodologies the business analyst is to follow.
QUESTION 135
Which of the following defines all of the features and functions of the thing, solution, or service
the project or organization will create?
A. Requirements envisioning
B. Project scope
C. Requirements foundation
D. Product scope
QUESTION 136
You are the business analyst for your organization. You're considering if you should make a
solution or purchase it from a vendor. If your team creates the solution, it will cost $286,000
and will cost $2,400 per month to support. The vendor's solution, however, will cost $239,000
and will cost $2,850 per month to support. How long will you need to use your in-house
solution to be more cost effective than the vendor's proposed solution?
A. 105 months
B. 32 months
C. 64 months
D. 19 months
Correct Answer: A
Section: (none) Explanation
Explanation/Reference:
Explanation:
In 105 months, your solution will equate to the cost savings offered by the vendor. In other
words, if your solution will be kept longer than
QUESTION 137
You are the business analyst for your organization and you're notifying the key stakeholders of
a need to gather requirements for an endeavor. One of the stakeholders that you'll need to
attend your requirements workshop is the project manager. What role will the project manager
have in this workshop?
Correct Answer: B
Section: (none) Explanation
Explanation/Reference:
Explanation:
The role of the project manager in elicitation tasks is to ensure that the needed resources are
available. Answer: C is incorrect. The project manager will likely be involved in the
requirements workshop.
Answer: A is incorrect. The project manager won't facilitate the requirements workshop, the
business analyst will.
Answer: D is incorrect. The project manager may help elicit requirements from stakeholders,
but this isn't the best choice for the question.
Correct Answer: C
Section: (none) Explanation
Explanation/Reference:
Explanation:
The inputs required to prepare for elicitation are as follows:
Business Need. It guarantees that the type of information elicited from stakeholders is
understood to the business analyst. This input is used at the time of eliciting business
requirements.
Solution Scope and Business Case. It guarantees that the type of information elicited from
stakeholders is understood to the business analyst. This input is used at the time of eliciting
stakeholder, transaction requirement, and solution.
Stakeholder List, Roles, and Responsibilities. It is required for the identification of stakeholders
that are required to participate in elicitation activity. Answer: D is incorrect. Risk Assessment is
a review of the risks in the project, and isn't an input to the elicitation business analyst tasks.
A. Tracing a requirement means to look at a requirement and the others to which it is related.
It links business requirements to components in the project's work breakdown structure.
B. Tracing a requirement means to track a requirement from its first identification all the way
to its completion to see what issues, risks, costs, quality, and defects have surrounded the
requirement.
C. Tracing a requirement means to look at a requirement and the others to which it is related.
It links risk, cost, quality, and scope elements to stakeholder and solution requirements to other
artifacts created by the team and to solution components.
D. Tracing a requirement means to look at a requirement and the others to which it is related.
It links business requirements to stakeholder and solution requirements to other artifacts
created by the team and to solution components.
Tracing a requirement is the linkage of the requirements to all the parts of solution including its
execution and creation.
Answer: C is incorrect. This is not a valid definition of tracing a requirement. Requirement
tracing does not consider risk, cost, quality, and other scope elements. Answer: A is incorrect.
This is not a valid definition of tracing a requirement. It does not examine its position in the
project WBS.
QUESTION 140
Which elicitation activity is best described to ensure that the needed resources are organized
and available for the elicitation?
QUESTION 141
You are the business analyst for your organization. You're creating a document that states the
business need, identifies the key stakeholders, and defines the positive impact the solution will
bring to the organization and stakeholders. What document are you creating?
A. Requirements documentation
B. Business case
C. Project charter
D. Vision statement
Correct Answer: D
Section: (none) Explanation
Explanation/Reference:
Explanation:
This is an example of a vision statement. A vision statement, also called a problem statement,
shows the categories of stakeholders and how the solution will help each stakeholder.
Answer: C is incorrect. A project charter authorizes the project.
QUESTION 142
You are the business analyst for your organization. Management has asked you to create a plan
that will define the proposed structure and schedule for communicating the business analysis
activities to the appropriate stakeholders. What plan does management want you to create?
Correct Answer: D
Section: (none) Explanation
Explanation/Reference:
Explanation:
Management is asking you to create the business analysis communication plan.
Answer: C is incorrect. This is a specific question asking for the BABOK definition of the business
analysis communication plan. Answer: B is incorrect. The business analysis plan defines the
activities and scope of work.
Answer: A is incorrect. The stakeholder management plan defines how the business analyst will
manage the fears, threats, requirements, and demands of the stakeholders.