Internship Report Khan Khwar Besham
Internship Report Khan Khwar Besham
Internship Report Khan Khwar Besham
Submitted By:
FAZAL ELAHI
Bs. Applied Geology
University Of Azad Jammu & Kashmir
MUZAFFARABAD
Supervised By:
Sr. Geologist Jehan Parviz
Submitted To:
Chief Engineer;
-1-
-2-
ACKNOWLEDGEMENT
All praise to almighty Allah who is most beneficent and merciful. Who
enabled me to read and write, then to holy prophet Muhammad (PBUH),
who gave the light of Islam to mankind.
-3-
ABSTRACT
On 27th July 2010 we Start our internship.
According to the schedule of our field work we studied the
geology of the Project area, its surrounding areas.
During our field we studied various rocks and geological
structures and also studied how to classify Rock?
During this field work we visited the following sections
· WEIR SITE.
· Power House.
· Tunnels.
· And other surrounding places.
-4-
INTRODUCTION:
-5-
INVESTIGATION WORKS:
Between December 1994 and October 1995 , the following field works and
geological investigation have been carried out of khan khwar HHP covering all
alternative, studied during the Feasible phase::
2. Geological field mapping of the whole project area with emphasis to hydro-
geological and engineering geological questions.
4. Carrying out 108 water pressure tests (LUGEON) with more then 160 packer
settings as well as six permeability tests . (LEFRANCE/MAAG)
The results of all investigation work are compile in Appendices 5.1 to 5.2 to the
feasibility study. The following description and relevant annexes are given with
reference to the selected plant layout (powerhouse alternative "south" and weir
alternative "B" ) out of the studied alternative.
-6-
GEOLOGY OF THE PROJECT AREA
The project area is situated on the Besham nappe, which is dominated by the
gneisses of the Precambrian Besham Group, consisting of heterogeneous mixture of
granite and biotite-rich Ortho-gneisses together with a sequence of
metasedementary gneisses and schist’s, marbles and amphibolites. As most of the
contacts are sheared the original relationship between the ortho and para gneisses
are uncertain. the gneissic texture and fabrics with a quartz, feldspar, muscovite,
biotite, garnet and hornblendic amphibole mineralogy are the products of the pre
Himalaya high grade deformation and metamorphism , being associated with
granite and pegmatite intrusion.
Granite GNEISS:
Leucco Granite:
this unit consists with the granite gneiss. The rock is hard, compact, massive,
relatively less deformed. And whitish gray to dark grey. course grain quartz veins
contain tourmaline crystals. contact zones of leucco granite with granite gneisses
are sheared.
Pegmatite:
Course grained pegmatite veins are intruding the leuco granites. These pegmatite
resembles more to the leuco granite. although they are course grained and contain
-7-
no mafic minerals.
Amphibolites Bodies:
Graphitic Schists:
The rock is grey to black, the graphitic contents ranges to 4% to 10% with small
pyrite crystals. This unit occurs as lateral discontinuous layers and pods up to 30
meter thick. This schists are medium to fine grained. And soft to moderately hard.
Mica schists:
They are grayish black to early grey fine hard thinly t massive bedded and have a
schistose to weakly gneissic fabric.
Quartzites:
They are rusty brown to light grey hard, well compacted and medium bedded some
thick beds up to 20 m thick of quartzite are also present.
i. Graphitic Phyllites
iii. Carbonates.
iv. Quartzite.
v. Quaternary Deposits.
-8-
72 MW KHAN KHWAR HYDROPOWER PROJECT
The Khan Khwar Hydropower Project is located on the river Khan Khwar, a right
bank tributary of the river Indus in the Shangla district of NWFP at a distance of
about 262 Km from Islamabad and 270 Km from Peshawar. The maximum power
output of this hydropower plant will be 72 MW, corresponding to a turbine design
discharge of 35 m3/s at a mean gross head of 257 m. The Khan Khwar Hydropower
Project will produce an annual energy of 306 GWh out of which approximately 105
GWh/annum will be available during a 4 hour/day period of Peaking operation.
OBJECTIVES
3 To achieve cheap annual energy of 306 GWh out of which 105 GWh will be
available during 4 hours per day peak period.
-9-
MAIN COMPONENTS OF THE PROJECT: -
The weir / dam is build at the intake structure across Khan Khwar for the collection
& storage of water from the catchment area,
Ø To regulate the water flow through the tunnel for the generation of power at
the power stations.
Ø To release the extra water through the spillway gates in the downstream
Khwar channel.
Ø To release the water through outlet gates for the flushing of sand and trash
from the reservoir.
(b). TUNNEL
The water from the intake reservoir flows through 5125 meter long tunnel for
operation of the Generating Units at Khan Khwar Power Station. Different portions
of the tunnel are: -
I. Head Race Tunnel (HRT): - This portion of tunnel lies between weir &
pressure shaft and is 4530 meter long, and 3.85 meter internal dia of
concrete lining.
II. Pressure Shaft: - It is concrete lining vertical shaft between HRT &
Pressure Tunnel. It has 183 meter length and 3.25 meter internal diameter.
III. Pressure Tunnel: - It is steel lining tunnel between pressure shaft and
spiral case of 425 meter length, 3.25 meter internal dia upto bifurcation.
(c). POWER HOUSE
- 10 -
The total capacity of the power station is 72 MW comprising two main generating
units each of 34 MW and one auxiliary unit of 4 MW capacity. The water flowing
from the penstock enters into the turbine spiral case through the inlet valve
operating the runner / turbine at a speed of 500 rpm. As the generator is coupled to
the turbine through the intermediate shaft thus running at the same speed producing
34 MW power at terminal voltage of 11 KV. The water after operating the turbine
flows to the tail race into the river Indus.
(d). SWITCHYARD: -
- 11 -
PROJECT DIGEST
- 12 -
iii. Scheduled date of completion Feb-2010
1. Reservoir
Total Storage Capacity 1.05 million m3
Live Storage Capacity 0.40 million m3
Length 1.6 Km
3. Headrace Tunnel
Type Pressure Tunnel
(Circular)
Length 4535 m
Size 3.85 m (Int: dia)
Discharge Capacity 35 m3/Sec
- 13 -
MAIN FEATURES
Powerhouse
4. Powerhouse Shaft
Type Internal Type
Shaft Size 30.6 x 25.78 x 27.7 m
Machine Hall 25 x 30.6 x 16 m
Machine Hall Elevation 586.00 floor
601.70 top
5. Pressure Shaft
Shaft Size 3.25 m dia
Length of Shaft 190 m
6. Pressure Tunnel
Length 407 m
Size 3.25 m (Int.dia)
7. Surge Shaft 31 m
8. Upper Chamber 85 m
9. Lower Chamber 65 m
10.Tailrace Tunnel 58 m
11.Head
Max. operation level 825 masl
Min. operation level 818 masl
- 14 -
Max. Gross level 257 m
Min. Gross level 247 m
MAIN FEATURES
Electro Mechanical
13.Electrical Equipment
Main Generators 2 No (34 MW)
Auxiliary Generator 1 No (4 MW
Speed 500 rpm
Output 34 MW (each)
14.Energy Output 72 MW
- 15 -
ROCK CLASSIFICATION
B. Poor 25 -50
C. Fair 50 -75
D. Good 75 -90
E. Excellent 90 -100
G. Four or more joint sets plus random, heavily jointed,” sugar cube” etc ……...15
A. Discontinuous joints……………………………………………,..4
- 16 -
D. Slickenside, undulating…………………………………………1.5
F. Smooth planar………………………………………………….1.0
G. Slickenside, planar…………………………………………….0.5
- 17 -
B. Medium inflow or pressure, occasional outwash of joint fillings…..0.66
- 18 -
L. low stress near surface…………………………………….>200
P. medium stress……………………………………………….200-10
M. high stress……………………………………………………10.5
(C) Squeezing rock plastic flow of incompetent rock under the influence of high
rock pressure
General Diagram.
- 19 -
- 20 -
CONTENTS
S/no Name Page
1. Introduction.
2. KhanKhwar Hydro Power Project.
3. Objectives
4. Main components of the project.
5. Project Digest.
6. Khan Khwar HHP main Features
Weir SITE.
7. Main features Power House.
8. Main features ELECTRO
MECHANICAL.
9. Investigation Works.
10. Geology of project Area
11. Rock classification.
12. General Diagram.
- 21 -