TWF Temporary Works Toolkit Part 19
TWF Temporary Works Toolkit Part 19
stuctures www.twforum.org.uk
Angus Holdsworth
IEng, MICE Figure 1
Specialist cranes developed
by Coleman & Co and Andun
Figure 2
Specialist
cranes and
for Birmingham New Street crane rails
Managing Director, Andun, Chelmsford, UK station project developed by
Coleman &
Co and Andun
for demolition
of MAN gas
Introduction holders
Figure 3
Dismantling of shopping centre
As with most forms of engineering, the scaffolding designer has considered this in
"PROGRESSIVE DEMOLITION success of the project comes down to the their design calculations.
buildings, as they are prone to uncontrolled secondary beams. Sit cuts and hinge cuts will Concrete structures
collapse due to latent defects. be formed in the column sections to ensure To prepare concrete structures for deliberate
For the demolition of an LPS building, that the structure collapses as required. collapse, key structural elements are
consideration should be given to the The final cuts should be made only when weakened. Explosives are typically placed in
temporary restraint of panels and the everything is ready. Explosive or pulling with holes pre-drilled into the key elements that
provision of temporary bracing. a wire rope is then used to provide the trigger are to be fragmented. Once detonated, the
Rubble should be cleared regularly; if to cause the structure to collapse, generally solid explosive converts instantly to a gas of
rubble is allowed to build up, it can lead to by knocking out columns. much higher volume, which effectively blows
unintended collapse. These works need careful planning to the concrete off the reinforcement; gravity
minimise the risks of working in a weakened does the rest.
Dismantling structure. However, the use of cutting
In this method, the structure will typically charges (shaped charges) is becoming more Key points
be dismantled using cranes (Figure 3) with common, reducing the risk of undertaking the These are similar to the key points
cutting techniques to release suitably sized final cuts. presented earlier for pre-weakening a steel
sections. In some cases, it may be possible structure.
to simply reverse the original construction Key points
methodology by undoing bolts; or in the case If shaped charges can be used, they General considerations
of precast sections, simply breaking out in should be used. They significantly reduce Key information
situ concrete to release. the hazards associated with the works, The availability of original drawings of the
although the risk of damaging adjacent structure can give the engineer a head-
Key points buildings with the air overpressure needs to start when working out how a structure
Weights should be accurately calculated. be given careful consideration. behaves. However, the information contained
Sufficient load factors should be applied The deliberate collapse of structures in the drawings should be verified on site
to estimated weights in line with industry can be completed within a few seconds; by carrying out opening-up works. If all is
practice. Refer to BS 71213,4 and speak however, it should be borne in mind that well, the capacity of the structure can be
to an Appointed Person for further the preparation of these works can take a ascertained using traditional design formulae
information. long time. suited to the material in question. Suitable
Consideration must be given to stability of The simplest collapse mechanism possible design formulae can be found within the
remaining elements; temporary works may should be used to ensure the lowest risk; Eurocodes or British Standards.
be required to provide stability. as is often the case with any design: ‘keep If the original drawings are not available,
Proposed sections must be suitable for it simple’. then the assessment of the structure
lifting, and the centre of gravity must be Design should utilise the minimum of pre- will require site investigation. This will
accurately assessed if required. weakening necessary. Positioning of the require opening up the works following the
Changes in wind loadings must be cuts should be considered carefully. completion of the soft strip. This should
considered, particularly the effects of The works should be planned by a suitably include breaking holes in slabs to expose
dominant openings being created. See BS experienced engineer with a track record the reinforcement, as well as breaking out
EN 1991-1-45 and the National Annex6. of undertaking similar works. sections of beams and columns to expose
Calculations should be sufficient to justify steelwork, connections and reinforcement.
Deliberate collapse mechanism the design. This information will be the key input for
Typically, this is referred to as a ‘blowdown’ The age of the structure must be design appraisal.
or a ‘pull-down’. Many people mistakenly recognised and appropriate design factors
believe that an explosive actually blows the and material strengths incorporated. Key points
structure apart; in reality, it is used to trigger Clear drawings should be provided detailing It is worth considering that the design
the collapse of the structure by weakening or all cuts and locations, and workmanship codes in use at the time the structure was
removal of key structural elements, allowing tolerances. designed and constructed are likely to
gravity to do the rest. The mechanism Stability must be maintained; release cuts differ significantly to those in use today.
for triggering the collapse can be either should be made only after all preparations In addition, the materials will be different;
explosive charges or pulling with a wire or are completed. concrete strength is likely to be lower,
chain attached to an excavator. Accurate setting-out of the cuts is critical reinforcement may well be mild steel,
Planning the deliberate collapse of a and must be given particular attention. the yield stress of steel lower. There is
structure requires an engineer to have a Workmanship is critical when pre- guidance available on this subject from
very good understanding of the structure weakening a structure, and only suitably numerous sources7–9.
and experience of how structures behave qualified and competent burners should Any historical information or site
in extreme conditions. Steel and concrete be permitted to undertake this work. There investigation of the structure should be
structures require different approaches. should be a clear specification and method passed to the engineer planning the
statement. demolition works.
Steel structures An exclusion zone(s) should be planned Beware of using the latest design codes
For the deliberate collapse of a steel and enforced, based on the worst-case to analyse older structures; they are not
structure, the structure is pre-weakened. collapse radius. See BS 61872 for detailed necessarily the correct choice. In particular,
This can include cutting out bracing and guidance on exclusion zones. Eurocodes specifically exclude the use
CASE STUDY: WHITE HART LANE – DEMOLITION OF SOUTH STAND PRIMARY TRUSS
e
fre
Figure 4 Tandem
uss
excavator if
n tr
mechanism Planned pull-down of required
he
pw
340t truss at Tottenham EXCAVATOR TRACK Aim is for excavator to pull truss
Sto
1m before West excavator pulls
Demolition contractor: DSM Demolition Hotspur FC stadium
LIMITS FROM POINT
WHEN STRUCTURE
MOVEMENT
EXCAVATOR TRACK
LIMITS FROM POINT
WHEN STRUCTURE
COMMENCES MOVEMENT
COMMENCES
Stop when
Background
40mm 6x19 Filler Wire
truss free
During the demolition of Tottenham Hotspur 40mm 6x19 Filler Wire
Rope. Min 870kN BS
Rope. Min 870kN BS
FC’s White Hart Lane stadium, the south OPERATIONS NOT TO COMMENCE IF WIND SPEED EXCEEDS 12m/s
This end
between if pulled first
was approx. 250t. The truss was set 26m 20m from stand
pulled first