2da Referencia
2da Referencia
2da Referencia
net/publication/317830226
CITATIONS READS
29 1,095
4 authors, including:
Kay Wille
University of Connecticut
60 PUBLICATIONS 2,902 CITATIONS
SEE PROFILE
Some of the authors of this publication are also working on these related projects:
Development of a Rational Design Method for Shear Keys at In-Span Hinges in Multi-Frame Highway Bridges View project
All content following this page was uploaded by Arash E. Zaghi on 06 July 2018.
Abstract: Corrosion of girder ends is a prevalent problem that significantly reduces the bearing capacity of bridges. Current repair
methods are expensive and difficult to implement. A novel repair method was developed for steel girder ends with corrosion damage
using ultrahigh-performance concrete (UHPC) to encase the corrosion. For this repair, UHPC panels were attached to girders with shear
studs welded to the web and flange surrounding the corroded area. This allowed shear and bearing forces to transfer from the girder to
the UHPC panels. The UHPC panels provided a new load path, thereby increasing the bearing capacity of the girder. Half-scale experi-
ments were conducted on undamaged, damaged, and repaired rolled steel girder specimens. The test results were used to (1) determine
the decrease in bearing capacity attributable to section loss, (2) demonstrate the ability of the UHPC repair to restore lost girder capacity,
and (3) investigate the constructability of the repair method. The experimental results show that the UHPC repair was easily implemented
and succeeded in restoring bearing capacity lost as a result of corrosion damage. DOI: 10.1061/(ASCE)BE.1943-5592.0001067. © 2017
American Society of Civil Engineers.
Fig. 5. Detail of the reduced steel section, shear stud arrangement, and UHPC panel for the repaired girder
Fig. 6. (a) Uniform section loss applied to the girders; (b) welded stud arrangement on the repaired girder; (c) UHPC repair panel
thickness was removed. Fig. 6(a) shows the final reduced tee sec- (Nelson Fastener Systems, Elyria, Ohio) using a stud-welding gun
tion before it was reinstalled on the girder, and Fig. 6(b) shows per standard practice.
the dimensions of the tee section for the repaired girder after it A detailed drawing of the shear stud layout and the dimensions
was reinstalled. of the UHPC panels is shown in Fig. 5. The dimensions of the tee
section cut out of the girder to facilitate machining of the section
Repair Method loss and welding of the studs were slightly smaller than the dimen-
sions of the UHPC panel to ensure the welds were completely
The preliminary FEM investigated the performance of several dif- encased.
ferent repair geometries for the UHPC panel and shear stud layout. The headed shear studs were 9.53 mm (3/8 in.) in diameter and
The goal of the FEMs was to design a repair to recover the full bear- 31.75 mm (1.25 in.) in length and were welded in a 50.8-mm (2-in.)
ing capacity of a baseline, undamaged girder. Typically, bridge grid on both the web and flange with a 12.7-mm (1/2-in.) clear
girders are designed to have ductile failure modes and avoid frac- cover. The studs were staggered on opposite sides of the web to pre-
ture critical failure modes. Because the end-bearing capacity does vent heat damage as a result of welding and stud tear-off during
not affect the shear and flexural demand on the girder, the bearing loading. The studs were half-scale equivalents of the shear studs
capacity may be fully restored by the UHPC repair without altering used in typical bridge design with a diameter of 19.05 mm (3/4 in.)
the desired failure mode. The results from the FEM found that a and a length of 63.5 mm (2.5 in.). The final stud arrangement on the
half-height UHPC repair had the lowest rehabilitated capacity while repaired girder before encasement in UHPC is shown in Fig. 6(b).
still restoring the full bearing capacity of the girder. Therefore, this Mineral oil was applied to the web and flange of the girder to ensure
repair detail was chosen as a conservative measure to validate the that the concrete only bonded to the shear studs to simulate a deter-
versatility of the repair method. The half-height repair required iorated, painted steel surface.
shear studs to be welded on both the web and bottom flange of the The concrete repair panels were 635 mm (25 in.) long and 330
girder to achieve proper load transfer. Before the bottom tee section mm (13 in.) tall to cover the entire length of the reduced section and
was welded back onto the repaired girder, a professional contractor to accommodate four rows of shear studs on the web above the
installed Nelson Stud Welding H4L Headed Concrete Anchors reduced section. The thickness of the panels varied over the height.
Casting began by slowly mixing premix powder with ice and water. tion. Both rod- and spring-type Novotechnik (Ostfildern, Germany)
Three admixtures were added, Premia 150 (a plasticizer), Optima potentiometers were used. The rod-type potentiometers had either a
100 (a water reducer), and Turbocast 650 A (an accelerator), all 152-mm (6-in.) or 304-mm (12-in.) measuring capacity, and the
manufactured by CHRYSO (Issy les Moulineaux, France). The spring type had a 50.8-mm (2-in.) measuring capacity. Vertical dis-
UHPC turned over after approximately 25 min of mixing. A steel placements were measured at four different locations. All vertical
fiber ratio of 2% by volume was added to the UHPC and mixed for displacements referenced in this paper for stiffness calculations,
an additional 3 min to ensure the fibers were evenly dispersed. load-versus-displacement graphs, and maximum girder displace-
Molds were created out of dense insulation foam board using a ments were measured between the bottom flange of the specimens
CNC machine to form the geometry of the repair panel. The molds and the floor. Lateral displacements along the height of the web
was attached to each side of the beam. The specimen was tested 4 were measured with four rod potentiometers to capture out-of-plane
days after casting when the UHPC achieved a compressive strength web displacements. The rotation of the bearing at the studied end
of 110 MPa (16 ksi). was measured with two spring potentiometers. A shear box was cre-
ated on both sides of the girder to measure the global shear displace-
ment of the end panel using a transformation matrix converting the
Test Procedure
measured displacements to global deformations (Zaghi et al. 2015;
A point load was applied at approximately 2/9th of the girder span Zmetra 2015). Each shear box used five rod potentiometers.
from the studied end, 812.8 mm (32 in.) from the centerline of the Twenty-six strain gauges were attached to each of the girder
studied end bearing. A 2,446-kN (550-kip) Enerpac (Milwaukee, specimens. Ten Omega 6-mm (0.236-in.) uniaxial strain gauges
Wisconsin) hydraulic load ram attached to the load frame was used were installed to measure vertical strain on both sides of the web, as
to apply the load. The load ram was positioned to simulate a truck shown in Fig. 7(a). Eight Tokyo Sokki Kenkyujo Co. (Tokyo)
wheel load applied near the end of a girder. Concentrated loads 5-mm (0.197-in.) uniaxial strain gauges were positioned longitudi-
applied near the girder end maximize the bearing load on a girder. nally along the bottom surface of the bottom flange to measure flex-
By positioning the load closer and removing bearing stiffeners from ural strain, as shown in Fig. 7(b). Two strain gauge rosettes were
the studied end, web buckling was restricted to this location. placed on each side of the web to measure local shear strains in the
Loading and unloading cycles of increasing magnitude were web [indicated with an arrow in Fig. 7(a)].
applied to each girder during testing. The prefailure loading proto- Ten additional strain gauges were added to the repaired girder.
col was based on the applied force from the load ram. The postfai- Two Omega 6-mm (0.236-in.) uniaxial strain gauges were placed
lure loading protocol was based on the vertical displacement on the outer, top two shear studs to measure axial strain and capture
between the bottom flange of the specimen with respect to the floor. the load transfer between the studs and UHPC. Four Omega 30-mm
(1.18-in.) strain gauges were placed on each of the concrete panels:
one to measure strain at the centerline of the bearing and three to
Instrumentation
form a strain gauge rosette to measure shear strain on the concrete
Each of the three test girders was instrumented with several mea- surface. The strain gauge layout on the surface of the UHPC panel
surement devices to record force, displacement, and strain data. is shown in Fig. 7(c).
Two load cells were placed beneath the end bearings to measure Before testing, a whitewash of lime was applied to the studied
axial, shear, and moment reactions. The load cells were designed, end of each girder to aid in the identification of damage patterns on
manufactured, and calibrated by the authors, modeling the design of the steel.
Fig. 7. Strain gauge layout: (a) web of the steel girders; (b) bottom flange of the steel girders; (c) UHPC panels
Fig. 8. Final condition of the left and right side of the specimens: (a) undamaged girder; (b) damaged girder; (c) repaired girder
Experimental Results Flexural damage lines developed in the web beneath the load ram,
and horizontal shear damage lines became visible in the web near
the bearing at the studied end. Two vertical compression fields
Undamaged Girder
developed beneath the load ram and above the bearing. The flex-
The first damage patterns formed on the undamaged girder under ural damage was caused by high bending stresses in the steel at
a bearing reaction force of 623 kN (140 kip) at the studied end. the point of loading. The shear damage was caused by shear
displacement-controlled cycles continued to increase the out-of- tion of web remained relatively undeformed, with minimal
plane displacements of the web. The progression of web deforma- observed damage. A yield line formed at the bottom of the girder
tion is shown in Fig. 9. and extended to the end of the web exactly at the transition point
The stiffness of the undamaged girder system was 112 kN/mm from the reduced section to the full section. The yield line is indi-
(640 kip/in.), as shown in Fig. 10(a). The rate of change of global cated by an arrow in Fig. 8(b). A single plastic hinge formed in the
shear deformation calculated from the shear box with respect to bottom flange of the girder at the end of the reduced section, as
bearing force was 4.31 mm/mm/kN (19.1 in./in./kip). The rate of shown in Fig. 8(b). After failure, the displacement controlled load-
change of local shear strain from the strain gauge rosette with ing protocol continued to increase the horizontal deformation of the
respect to bearing force was 3.19 m« /kN (14.2 m« /kip). The maxi- reduced section of the web. The web began to rupture at the transi-
mum axial strain in the web before failure was 4,470 m« at a load of tion point between the reduced and full sections of the web. The
623 kN (180 kip). The bearing strain was taken to be the average of progression of the web deformation of the damaged girder is shown
the strain in the steel on the right and left side of the web. Fig. 11(a) in Fig. 12.
shows the distribution of bearing strain along the height of the The stiffness of the damaged girder system was 100 kN/mm
web as loading progressed to failure. The rate of change of flex- (573 kip/in.), as shown in Fig. 10(b). The rate of change of global
ural strain of the bottom flange with respect to bearing force shear deformation calculated from the shear box with respect to
Fig. 9. Failure progression of the undamaged girder based on the vertical displacement at the load ram: (a) 0 mm (0 in.); (b) 6.35 mm (0.25 in.);
(c) 19.1 mm (0.75 in.); (d) 31.8 mm (1.25 in.)
Fig. 10. Studied end-bearing load versus displacement between the bottom flange of the girder and the floor: (a) undamaged girder; (b) damaged
girder; (c) repaired girder
Fig. 11. Distribution of axial bearing strain on the steel girder along the height of the web: (a) undamaged girder; (b) damaged girder; (c) repaired
girder
Fig. 12. Failure progression of the damaged girder based on the vertical displacement at the load ram: (a) 0 mm (0 in.); (b) 12.7 mm (0.50 in.);
(c) 25.4 mm (1.00 in.); (d) 38.1 mm (1.50 in.)
bearing force was 6.79 mm/mm/kN (30.2 in./in./kip). The rate of cold joint formed during casting when a small amount of concrete
change of local shear strain from the strain gauge rosette with leaked from the right panel to the left panel before the left panel was
respect to bearing force was 3.43 m« /kN (15.3 m« /kip). The maxi- cast. A cold joint crack developed under a bearing force of 783 kN
mum axial strain in the web was 1,785 m« at a load of 191 kN (176 kip). The final crack patterns on both panels are shown in Fig.
(43 kip) before localized web buckling occurred. The axial strain 8(c); the crack patterns were outlined to make them more distin-
distribution along the height of the web is shown in Fig. 11(b). The guishable, but it should be noted all final cracks were fine cracks in
rate of change of flexural strain of the bottom flange with respect to the UHPC panel and were not regarded as significant damage.
bearing force varied from 0.499 m« /kN (2.22 m« /kip) at the bearing The UHPC repair prevented the girder from failing as a result
to 1.63 m« /kN (7.24 m« /kip) beneath the load ram. of web buckling at the bearing. Flexural damage lines formed
beneath the load ram at a bearing force of 783 kN (176 kip). The
Repaired Girder flexural damage in the web is circled in Fig. 8(c). The maximum
bearing force of the repaired girder was 1,023 kN (230 kip).
During the curing process for the repaired girder, a small number of Under this load, extensive flexural yielding occurred in the steel
hairline temperature and shrinkage cracks formed in the concrete beneath the load ram, and loading was halted. The maximum verti-
panel. The first loading cracks to develop were vertical cracks at the cal displacement of the repaired girder was 14.86 mm (0.585 in.).
top of the panels and vertical cracks at the bearing. These cracks No significant out-of-plane movement was recorded. The ultimate
began at a load of 156 kN (35 kip). The cracks at the top of the pan- strength of the concrete panel was not achieved because of yielding
els formed as the panels rotated about the bearing. Small displace- of the girder.
ments induced tension in the concrete as a result of the rotation. The stiffness of the repaired girder system was 118 kN/mm
Cracks formed by the vertical compression field at the bearing (674 kip/in.), as shown in Fig. 10(c). The rate of change of global
became visible at a load of 254 kN (57 kip). Shear cracks began shear deformation calculated from the shear box with respect to
forming at the bottom of the panel at a load of 307 kN (69 kip). The bearing force was 1.6 mm/mm/kN (7.1 in./in./kip). The rate of
shear cracks extended into the bevel of the concrete repair and pro- change of local shear strain from the strain gauge rosette with
gressed into the center of the panels as the applied load increased. A respect to bearing force was 1.77 m« /kN (7.9 m« /kip). The
(SS2), as shown in Fig. 13. The bearing strains of the concrete pan- was over five times greater than that of the damaged specimen. This
els are shown in Fig. 14. Before cracks developed through the strain was also over 28% larger than the undamaged girder. The final con-
gauges on the UHPC panel, the maximum bearing strains of the dition of each girder is shown in Fig. 16.
left and right panels were 115 m« at a load of 1,023 kN (230 kip) The stiffness of each girder specimen was calculated by compar-
and 70 m« at a load of 778 kN (175 kip), respectively. The rate of ing the bearing load at the studied end with the vertical displace-
change of strain of the left and right UHPC panels were 0.085 m« /kN ment between the bottom flange of the girder and the floor beneath
(0.38 m« /kip) and 0.09 m« /kN (0.40 m« /kip), respectively. the hydraulic cylinder. The potentiometer attached to the top flange
of the specimens and the spreader beam yielded stiffness values
consistently smaller than those from the potentiometer attached to
Discussion the specimen’s bottom flange and the floor. The loss in stiffness
may be attributed to the elasticity of the load frame. Fig. 17 shows
The results of the three half-scale experimental tests were compared the comparison of the load-versus-displacement relationships of
to determine the decrease in bearing capacity resulting from section each of the girders. The stiffness values were compared to investi-
loss and to demonstrate the ability of the UHPC repair to restore gate the effects of the reduced section and the UHPC repair on
lost girder capacity. bending performance under live loading. The stiffness of the dam-
aged girder was 10% lower than that of the undamaged girder
because of the reduction in cross-sectional area. The stiffness of the
repaired girder was 5% higher than that of the undamaged girder
because of the addition of the UHPC. Because the difference in
girder stiffness was minor, the reduced section of the steel and the
UHPC repair did not have an appreciable effect on the bending stiff-
ness of the damaged and repaired girders for the given loading.
Global shear strains calculated from the potentiometer shear box
illustrate the difference in force-carrying mechanisms between
the three girder specimens. The load distribution was caused by the
inclusion of the corrosion damage and the concrete repair to the
damaged and repaired girders. The rate of change of the global
shear deformation of the damaged girder with respect to bearing
force was 58% higher than that of the undamaged girder as a result
of the reduction in cross-sectional area. The reduced cross section
increased the shear deformation and lowered the capacity of the
Fig. 13. Load versus strain in the shear studs, SS1 (at the bearing) and damaged girder. The rate of change of the global shear deformation
SS2 (farthest from the bearing) of the repaired girder was 76% smaller than that of the damaged
girder as a result of additional stiffness from the UHPC panels. The
UHPC repair prevented extensive shear deformation of the end
panel.
The localized shear strain recorded by the rosette strain gauges
verified the trends from the potentiometer shear box. The applica-
tion of corrosion damage to the damaged girder increased the rate of
change of the local shear strain with respect to bearing force by 8%
compared with the undamaged girder. The addition of the UHPC
repair decreased the rate of change of the local shear strain with
respect to bearing force by 41% compared with the damaged girder.
At the failure load of the undamaged girder [801 kN (180 kip)], the
shear strain of the repaired girder (1,470 m« ) was 1.7 times smaller
than that of the undamaged girder (2,540 m« ). The decrease in shear
strain between the undamaged and repaired girders indicates that
shear forces were transferred from the web of the girder to the
UHPC repair.
Axial strains were measured along the height of the web to moni-
Fig. 14. Load versus axial bearing strain on the surface of the right
tor the distribution of bearing forces on the web column. The bear-
and left concrete panels
ing strain distribution of the three girder specimens at their
Fig. 15. Final condition of the end cross section after testing: (a) undamaged girder; (b) damaged girder; (c) repaired girder
Fig. 16. Final condition of the girder after testing: (a) undamaged girder; (b) damaged girder; (c) repaired girder
respective failure loads is shown in Fig. 18. The axial strain of the performance of the repair because of the minimal stress carried by
undamaged girder (411 m« ) was approximately 4.3 times smaller the remaining steel section.
than that of the damaged girder (1,785 m« ) at the failure load of the The flexural strains in the bottom flange were recorded to moni-
damaged girder [191 kN (43 kip)]. The axial strain of the repaired tor the effects of the reduced flange thickness and the UHPC repair
girder (252 m« ) was 21 times smaller than that of the undamaged on the bending performance of the girders. Compared with the
girder (4,470 m« ) at the failure load of the undamaged girder undamaged girder, the rate of change in the flexural strain of the
[801 kN (180-kip)]. The bearing strain data were taken to be the av- damaged girder increased by 29% directly beneath the reduced sec-
erage of the strain on the right and left side of the web at the location tion but decreased by 4% beneath the load ram. This variation in
of maximum bearing strain for the damaged and undamaged girders flexural strain resulted from load redistribution around the corroded
(WL11). One reason for the significant difference in axial web area. The rate of change in the flexural strain of the repaired girder
strain between each girder was the location of the strain gauges increased along the bottom flange compared with both the undam-
along the web. The bottom-most strain gauge on the undamaged aged and damaged girders. Compared with the damaged girder, the
girder was placed directly at the location of maximum bending after repair girder flexural strains increased by 5% under the reduced sec-
web buckling occurred, whereas on the damaged girder, the strain tion. The rate of change in the flexural strain of the repaired girder
gauge was between the two points of maximum bending in the web. beneath the load ram increased by 12% compared with the undam-
However, the variation in axial strain between the undamaged aged girder. The increased rate of change in the flexural strain of the
girder and the damaged girder may also have resulted from the repaired girder validates the composite action of the repair method.
lower buckling capacity of the specimen because of the reduced The strain gauges attached to the shear studs and concrete panels
section. The decrease in axial strain between the repaired girder and were used to monitor the composite response of the repaired girder.
the undamaged girder demonstrated the ability of the UHPC repair The compressive forces in the stud away from the bearing may be
to carry bearing loads and relieve a large portion of bearing stress attributed to early twisting of the top flange before the concrete
from the reduced web section. Therefore, the addition of bearing panel was engaged. Because the rate of change in the strain of the
stiffeners to the repaired girder may not have had an impact on the stud farther from the bearing was higher, a significant portion of
assistance of Peter Glaude and Jim Olney from the UConn School Numerical study.” J. Constr. Steel Res., 79, 166–182.
of Engineering machine shop is appreciated. Special thanks go to Hyashi, K., Ono, S., and Nakamura, S. (2003). “Experimental studies on ret-
rofit by partially encased concrete to the steel I-girder subjected to buck-
James Mahoney, Lori Judd, and Carolyn Ward of the Connecticut
ling deformation.” Technical Memorandum 3920, Public Works
Transportation Institute. In addition, the assistance of Manish Roy, Research Institute, Tsukuba, Ibaraki, Japan, 229–236.
Masoud Mehr, Alicia Echevarria, Man Xu, Javier Duluc, Michael Kayser, J. R., and Nowak, A. S. (1989). “Capacity loss due to corrosion
Humphreys, Amanda McBride, Alexandra Hain, Christopher in steel-girder bridges.” J. Struct. Eng., 10.1061/(ASCE)0733
Pawlowski, and Andy Dauphinais during the research project is -9445(1989)115:6(1525), 1525–1537.
appreciated. Khurram, N., Sasaki, E., Katsuchi, H., and Yamada, H. (2014b).
“Experimental and numerical evaluation of bearing capacity of steel
plate girder affected by end panel corrosion.” Int. J. Steel Struct., 14(3),
References 659–676.
Khurram, N., Sasaki, E., Kihira, H., Katsuchi, H., and Yamada, H. (2014a).
Abbas, S., Nehdi, M. L., and Saleem, M. A. (2016). “Ultra-high perform- “Analytical demonstrations to assess residual bearing capacities of steel
ance concrete: Mechanical performance, durability, sustainability, plate girder ends with stiffeners damaged by corrosion.” Struct.
and implementation challenges.” Int. J. Concr. Struct. Mater., 10(3), Infrastruct. Eng., 10(1), 69–79.
271–295. Koch, G. H., Brongers, M. P. H., Thompson, N. G., Virmani, Y. P., and
Ahn, J.-H., Kainuma, S., and Kim, I.-T. (2013a). “Shear failure behaviors of Payer, J. H. (2002). “Corrosion cost and preventive strategies in the
a web panel with local corrosion depending on web boundary condi- United States.” Rep. No. FHWA-RD-01-156, Turner-Fairbank Highway
tions.” Thin Wall. Struct., 73, 302–317. Researh Center, McLean, VA.
Ahn, J.-H., Kainuma, S., Yasuo, F., and Takehiro, I. (2013b). “Repair Kristoff, W. M. (2011). “In-depth inspection of Bridge No. 03399D: I-84
method and residual bearing strength evaluation of a locally corroded over parking lot, Hartford, CT.” Technical Rep., Connecticut Dept. of
plate girder at support.” Eng. Fail. Anal., 33, 398–418. Transportation, Newington, CT.
Albrecht, P., and Hall, T. T., Jr. (2003). “Atmospheric corrosion resist- Liu, C., Miyashita, T., and Nagai, M. (2011). “Analytical study on shear
ance of structural steels.” J. Mater. Civ. Eng., 10.1061/(ASCE)0899 capacity of steel I-girders with local corrosion nearby supports.”
-1561(2003)15:1(2), 2–24. Procedia Eng., 14, 2276–2284.
ASCE. (2014). 2013 report card for America’s infrastructure, Reston, VA. LS-DYNA 971 [Computer software]. Livermore Software Technology
Chang, L.-M., and Lee, Y.-J. (2001). “Evaluation and policy for bridge Corporation, Livermore, CA.
deck expansion joints.” FHWA/IN/JTRP-2000/1, Joint Transportation Miyashita, T., et al. (2015). “Repair method for corroded steel girder ends
Research Program, Indiana Dept. of Transportation and Purdue Univ., using CFRP sheet.” Proc., IABSE-JSCE Conf. on Advances in Bridge
West Lafayette, IN. Engineering-III, International Association for Bridge and Structural
Classen, M., Gallwoszus, J., and Stark, A. (2016). “Anchorage of com- Engineering, Zurich, Switzerland, 614–620.
posite dowels in UHPC under fatigue loading.” Struct. Concr., 17(2), Nakamura, S., Momiyama, Y., Hosaka, T., and Homma, K. (2002). “New
183–193. technologies of steel/concrete composite bridges.” J. Constr. Steel Res.,
Close, J., and Miller, P. C. (2011). “Preliminary design report—Putnam 58(1), 99–130.
Bridge, Bridge No. 00417. Project No. 53-175.” Technical Rep., Nakamura, S., and Narita, N. (2003). “Bending and shear strength of par-
Connecticut Dept. of Transportation, Newington, CT. tially encased composite I-girders.” J. Constr. Steel Res., 59(12),
ConnDOT (Connecticut Dept. of Transportation). (1955). “Bridge No. 1435–1453.
00352: Greenwich-Killingly Expressway Rt. 1 over Oil Mill Rd.” Ogami, H., Fujii, K., Yamada, T., and Iwashaki, H. (2015). “Renovation of
Technical Rep., Newington, CT. corroded girder end in plate girder bridge with resin and rebars.”
ConnDOT (Connecticut Dept. of Transportation). (1962). “Bridge No. Implementing innovative ideas in structural engineering and project
03399D: Rt. 84 on ramp over parking lot,” Technical Rep., management, S. Saha, Y. Zhang, S. Yazdani, and A. Singh, eds., ISEC,
Newington, CT. Fargo, ND, 1–6.
Elnashai, A. S., Takanashi, K., Elghazouli, A. Y., and Dowling, P. J. Reinhorn, A. M., and Bracci, J. (1992). “Multi-axis load cell design and con-
(1991). “Experimental behaviour of partially encased composite beam- struction.” Rep. No. NCEER-92-0027, National Center for Earthquake
columns under cyclic and dynamic.” Proc. Inst. Civ. Eng., 91(2), Engineering Research, Univ. of New York, Buffalo, NY.
259–272. Rossow, M. (2003). “FHWA bridge maintenance: Superstructure.” Bridge
Feldmann, M., Hechler, O., and Hegger, J., and Rauscher, S. (2011). maintence training reference manual, Continuing Education and
“Fatigue behavior of shear connectors in high performance concrete.” Development Engineering, Stony Point, NY.
Proc., Int. Conf. on Composite Construction in Steel and Concrete Russell, H., and Graybeal, B. A. (2013). “Ultra-high performance concrete:
2008, ASCE, Reston, VA, 310–321. A state-of-the-art report for the bridge community.” Rep. No. FHWA-
FHWA (Federal Highway Administration). (2014). “Design and con- HRT-13-060, Federal Highway Administration, McLean, VA.
struction of field-cast UHPC connections.” FHWA-HRT-14-084, Shaheen, E., and Shrive, N. (2008). Cyclic loading and fracture mechanics
Washington, DC. of ductal concrete, Springer Science & Business Media.
FLDOT (Florida Dept. of Transportation). (2011). “Section 6: Steel beam and Shi, X., Fay, L., Yang, Z., Nguyen, T. A., and Liu, Y. (2009). “Corrosion of
girder repair.” Bridge maintenance and repair handbook, Tallahassee, deicers to metals in transportation infrastructure: Introduction and recent
FL, 78–83. developments.” Corros. Rev., 27(1–2), 23–52.
WisDOT (Wisconsin Dept. of Transportation). (2015). “Bridge rehabilita- of Civil Engineering, Univ. of Connecticut, Storrs, CT.
tion.” Bridge manual, Madison, WI. Zmetra, K., Zaghi, A. E., and Wille, K. (2015). “Rehabilitation of steel
Yamaguchi, E., and Akagi, T. (2013). “Degradation of load-carrying bridge girders with corroded ends using ultra-high performance
capacity of steel I-girder end due to corrosion.” Proc., 13th East Asia- concrete.” Proc., Structures Congress 2015, ASCE, Reston, VA,
Pacific Conf. on Structural Engineering and Construction (EASEC-13). 1411–1422.