Methodology For Storm Water
Methodology For Storm Water
Methodology For Storm Water
CARRIAGEWAY CONSTRUCTION
The use of traffic cones with warning tapes bound around them to restrict the
movement of traffic into the working area will been done.
We will also incorporated warning signs all along the carriageways to warn motorists
of the ongoing activities.
Two employees dressed in bright reflective wear are placed at the entry and exit points
with warning flags so as to direct traffic flow.
We will also liaise with the Kenya Police traffic department to have traffic police
stationed in this section so as to assist in traffic management.
Speed bumps will be erected when and where they will be necessary on the deviations
DEVIATIONS
A deviation will be prepared on sections that might need one. The deviation will a 6 m
gravel road with proper signage and warnings.
PERSONNEL SAFETY
Safety and Protection gear
All employees will be dressed in the appropriate safety gear which includes:-
Overalls or dust coats,
Hand gloves
Hearing Protection
Eye Protection
Reflective jackets,
Helmets,
Respiratory Protection
Safety boots.
All employees will undergo a site induction and safety training undertaken by the KPA
safety department so as to ensure that they are familiar with the site rules prior to any
work commencing on site. In addition, the contractor will ensure that all operatives
responsible for handling fuel, oil, concrete or cement or other potential
pollutants undergo a thorough induction programme with respect to the
proposed pollution control measures. The programme will include, as a minimum,
the following:
• Habitat protection;
• Potential sources of pollution and their effects on the environment;
• Requirements of the contract and legislation with respect to pollution;
• The contractor’s pollution avoidance plan;
• Traffic management and routing, including areas where access is not permitted;
Safety hazards
• Training in the use of pollution control equipment.
Working Hours
The construction programme will be based on a working week of 6 days, 08:00 am to
6.00 pm on weekdays and Saturdays. Generally, night time or Sunday work will not
be permitted.
However, working on Sundays or outside normal working hours may be required if for
any reason work has not been completed within normal working hours.
Tower lights will be provided during extended working hours or periods of early
darkness to ensure safe working conditions. The Tower lights will be positioned in
such a way as to limit light pollution in the direction of traffic. Lighting will be
powered by a diesel engine.
Staff Movements
It is generally necessary for security guards to be present on the site. Other than the
security guards, there will be no overnight presence on the construction site.
All personnel will meet in the morning and depart after completing their work.
HEALTH
Necessary arrangements have been made for:-
Sanitary facilities: Adjacent to the work place, are some sanitary facilities
belonging to a hotel. Arrangements have been made for our staff to utilize it.
Clean drinking water and food,
Proper storage facilities.
The Contractor shall prepare and submit a specific Environmental Management Plan,
for the project and his operations, relating to the approved Environmental Impact
Assessment. The Environmental Management Plan shall outline potential
environmental hazards and risks, and provide an action plan to deal with the hazards,
minimize the risks, and mitigate adverse environmental impacts, and include a
general decommissioning plan covering all relevant aspects of the project. The
Environmental Management Plan shall identify monitoring indicators and reporting
requirements.
The Contractor shall ensure so far as is reasonably practicable and to the satisfaction
of the Engineer; that the impact of the construction on the environment shall be kept
to a minimum and that appropriate measures are taken to mitigate any adverse effects
during the construction.
(a) The Contractor shall exercise care to preserve the natural landscape and shall
conduct his construction operations so as to prevent any unnecessary
destruction, scarring, or defacing of the natural surroundings in the vicinity of
the work. Except where clearing is required for permanent works, all trees,
native shrubbery, and vegetation shall be preserved and shall be protected from
damage by the Contractor’s construction operations and equipment. All
unnecessary destruction, scarring, damage or defacing resulting from the
Contractor’s operations shall be repaired, replanted, reseeded or otherwise
corrected as directed by the Engineer, and at the Contractor’s expense.
(b) The Contractor shall ensure that measures are in place to control soil erosion
and water pollution, by use of berms, dykes, silt fences, brush barriers, dams,
sediment basins, filter mats, netting, gravel, mulches, grasses, slope drains,
contour banks, and other erosion control devices and methods. Temporary
erosion control provisions shall be coordinated with permanent erosion control
features to assure economical, effective and continuous measures throughout
the period of the works. The Contractor’s attention is drawn to the requirements
of Clause 502, in that works need to be progressively finished so that
permanent vegetation can establish quickly to mitigate soil erosion and erosion
of drains.
(c) The Contractor shall provide all the labour, equipment, materials, and means
required and shall carry out proper and efficient measures wherever and as
often as necessary to minimize the dust nuisance.
(d) The Contractor shall comply with all applicable Kenyan laws, orders and
regulations concerning the prevention, control and abatement of excessive
noise. Blasting, use of jackhammers, pile driving, rock crushing, or any other
activities producing high- intensity impact noise may be performed at night only
upon approval of the Engineer.
(e) Immediately after extraction of materials, all borrows pits shall be backfilled to
the satisfaction of the Engineer. In particular borrow pits near the project road
shall be backfilled in such a way that no water collects in them.
(f) Spilling of bitumen fuels Oils and other pollutants shall be cleared up.
Concrete
All concrete will be delivered directly to the location of the works and transferred to the
formwork by truck mounted concrete pump or by crane and skip method or in-situ
batching. Optionally direct discharge from the delivery truck into the formwork may
be used or excavator bucket or wheel loader bucket as appropriate.
Formwork will be constructed to ensure that no concrete loss occurs at joints. Any
concrete loss will be either removed or contained.
All vehicles, tools and buckets will only be cleaned within a designated area. The wash
out water from trucks carrying concrete to construction areas will be discharged away
from site. The wash out water will be removed from the site for appropriate disposal.
Vegetation
Revegetation of areas where vegetation was removed or destroyed should be done.
Traffic management
Need to develop a traffic management plan to provide for safe and efficient movement
of traffic during the maintenance works
Hazards/Risks
Activity Control Measures
Identified
Existing Work near significant - Worker Briefings to be carried out
Services existing services ie - Adhere to Codes of Practice for avoiding
- Electrical poles dangers from underground services
- Water mains - Use of trained plant operators
Heavy Plant - Telecommunicatio
Working adjacent to - Use
- of Banksman
Worker for to
Briefings equipment
be carried out
and Heavy Plant and - Plant to be operated by Competent
Equipment machinery including Personnel
excavation plant and - Plant to be in good order and inspected
lifting appliances prior to commencement of any works
Hazards on site
Noise, Operated by - Auxiliary devices and visual aids on
untrained Individual, plant to be placed on plant and
Incorrect use. vehicles
Speeding, Poor - Carry out plant checks and record on
maintenance. plant checklists
Unsupervised - Vehicle Banksmen to be utilized where
reversing, Overloading required
Biological Works which put - Areas of potential contaminated
Substances person at work at ground to be tested and areas
risk from Biological segregated
substances - Assessments to be carried out and
- Contact with briefed to workers
contaminated - Ensure adequate assessment of PPE
ground or objects requirements for surfacing operations
or materials - All operatives engaged in sewer tie in
- Working on works to wear appropriate PPE which
existing streams will include gloves and disposable
and drains, overalls.
particularly foul - All operatives to be briefed and trained
Manual drains.
Fractures, Strains, -Use Adequate
- of washing
mechanical facilities
assistance to provided
wherever
Handling Sprains, Cuts, possible, e.g. forklift, plant, lifting
Lacerations, appliance etc.
Abrasions, Injury - Reduce loads by making them smaller or
through aggravation of lighter.
previous/existing - Ensure the working environment is
medical condition, suitable i.e. - Access ways are unimpeded
burns due to hot and properly lighted.
asphalt concrete - Working platforms should be non-slip and
kept clean
-Ensure that the individual is lifting
correctly, maintains good posture, and lifts
with knees bent and back kept straight.
-All loads should be assessed individually for
size and weight, but generally loads greater
than 25kg should be handled by more
Adequate measures should be taken around quarries and gravel sites to ensure the
health and safety of the public. Fencing may be erected and ponds should be shallow
with gradual side slopes.
It should also be noted the following days have been added for every activity:-
a. 30 days have been set apart for breakdowns of the equipment.
b. 30 days have been set apart for rainy days.
SCOPE OF WORK
LOCATION OF CONTRACT
The site of the works shall be the area within the road reserve and any other places as
may be designated in the Contract. The works involve re-construction to bitumen
standard of the project road including junctions, and also installation of drainage
facilities such as pipe culverts etc. all as per drawings and relevant documentation
issued for the works. Any other works shall be as directed by the Engineer.
EXTENT OF CONTRACT
The major works to be executed under the Contract comprise mainly of but
are not limited to the following:
1. MOBILIZATION
Mobilization will start immediately after the Engineer’s order to commence and to be
completed within the 28 days. The following will be undertaken during the
mobilization period:
Items to be provided to the Engineer as per Bill No. 1 and contractual
requirements, will be made available after receiving instructions to do so i.e. the
supervision vehicle, computers, printers, publicity signs etc.
The Contractor will acquire a site camp and yard along the roads corridor at a
convenient location.
Acquisition of borrow pits and investigation of the gravel will be undertaken
from the borrow pits.
Testing of aggregates from our quarry will be undertaken.
Design and trial sections for the Asphalt concrete and graded crushed stone.
Any other preliminary material testing will be undertaken.
2. SETTING OUT
Setting out will start immediately. One survey team will undertake this exercise in
conjunction with the Resident Engineer’s team.
The setting out will include:-
Marking of the chainages at a 20 m interval.
Taking cross sectional OGL data at an offset of 12 m both sides.
Marking of areas that require regulations
Marking of areas that require pothole patching
Marking of areas that require Edge repairs
Marking of areas that require Removal of the damaged pavement and areas to
be stabilized.
Identify and take invert levels of the existing drainage facilities i.e. access
culverts, side drains, cross culverts, mitre drains etc.
Any other survey data that will be required.
3. SITE CLEARANCE
Site clearance by heavy bush clearing will commence immediately after the start of
setting out.
Setting out of cross-sections, marking of clearance area and submission to the
Engineer for approval before works commences.
Site clearance will only be undertaken in areas outside the existing road, but on the
road reserve as instructed by the Engineer.
A bulldozer will clear the road reserve and strip the topsoil, 200 mm deep. Unless
specified otherwise, the cleared vegetation and the perishable materials shall be burnt.
Otherwise they shall be stacked together, and then be loaded by the wheel loader and
carried to the spoil area by tippers.
The trees and bushes within the construction range shall be cut by hand.
The tree roots and stumps shall be dug out by excavators and burnt. The pits shall be
backfilled by materials approved by the Engineer and shall be compacted to 95%MDD.
The surfaces of the pits shall be kept at same level with the ground surface.
These works will be done by one team with the following resources:
Vehicles and equipment
Grader - 1 No.
Dozer - 1 No.
Shovel (wheel loader) - 1 No.
Tippers - 2 No.
Labour
1. Foreman - 1No.
2. Plant operator - 1 No.
3. General labourers - 4 No.
4. Drivers - 2 No.
The gabion boxes and mattresses will be procured from approved manufacturers.
Firstly, excavation works will commence to the required depth and line. The gabion
boxes will be fixed in place and filled with rockfill.
The boxes will be closed with binding wire and finally, grout cement applied on top as
required.
There will be one team that will handle the concrete works and will have the following
resources:-
Vehicles and equipment
Bobcat with back hoe - 1 No.
Vibratory roller - 1 No.
Tipper (7) Tons - 1No.
Mobile Concrete mixer - 1 No.
Mobile car mix concrete mixer - 1 No
Poker vibrator - 2 No.
Labour
1. Foreman - 1 No.
2. Plant operators - 5 No.
3. Drivers - 1 No.
4. Mason - 1 No.
5. Carpenter - 1 No.
6. General labourers - 5 No.
7. EXCAVATION FOR DRAINAGE WORKS AND CULVERTS AND DRAINAGE
WORKS
Immediately after undertaking the shoulder works, the access and cross culverts will
be cleaned to free flowing conditions. This will ensure that the material will not return
into the culverts.
The aggregates for concrete works required will be obtained from our quarry and
material testing will be undertaken to ensure the correct design mix is used for the
concrete batching. Cement and sand will be purchased locally.
The construction of access and cross culverts will be undertaken as instructed by the
Engineer, and it will be an independent activity which will be undertaken throughout
the contract period and in any section so long as there are no space constraints and
inconveniences to traffic.
The setting out and excavation shall be carried out according to the drawings and the
Engineer’s instruction. The lower 15cm depth to base will be compacted to 100%MDD,
and any unacceptable base will be dealt with according to the Engineer’s instruction.
The culvert and drainage works shall be finished before the completion of major works
of subgrade earthwork.
The base shall be poured with concrete immediately after the Engineer’s acceptance.
The prefabricated culvert pipe shall have an ogee joint. The purchased culvert pipe
shall get the Engineer’s prior approval. The culvert pipe shall be laid after the placing
of cement mortar (1:3) from a lower level to a higher level.
The Concrete shall be kept moist and cured for seven days.
Specification compliance and quality control testing shall be carried out in accordance
with requirements of specifications.
Preparation of construction
Setting out
Measurement control
Curing
Backfilling
There will be three teams that will handle the culvert works and they will have the
following resources:-
Vehicles and equipment
Pedestrian rollers - 3 No.
Tipper (7) Tons - 3 No.
Back hoe loader - 2 No.
Concrete trans-mix trucks - 1 No.
Mobile Concrete mixer - 3 No.
Poker vibrator - 3No.
Labour
Foreman - 3 No.
Plant operators - 11 No.
Drivers - 3 No.
Mason - 6 No.
Carpenter - 6 No.
General labourers - 30 No.
It is projected that, instructions for concrete works will be done at once so that the
teams can be able to do a complete one culvert within 2 days.
1 EARTHWORKS
The existing shoulders will be investigated to note the actual process of undertaking
the shoulder repair works. The scenarios will include:-
a. Some areas will only require scarifying of the existing ground, watering and
compaction. The gravel will be dumped and the next layer processed, watered
and compacted.
b. Some areas will require benching and removal of unwanted material, adding
gravel, watering and compaction.
c. Some areas will require only grading, watering and compaction.
Location and acquisition of borrow pits will be done as early as possible (testing of the
material to ensure requirements are met) and as near as possible to the road corridor.
The shoulder repair works will be done by one team with the following resources:
Vehicles and equipment
Grader - 2 No.
Excavator - 1 No.
Vibratory rollers - 1 No.
Tippers (20) Tons - 4 No.
Water browser - 1 No.
Set of survey equipment - 1 No.
Labour
1. Foreman - 1 No.
2. Plant operators - 4 No.
3. Drivers - 5 No.
4. Surveyor/leveler - 1 No.
5. Chainmen - 4 No.
6. General labourers - 4 No.
The hardcore will be placed manually, with the stones facing upwards. The initial
compaction will be done using mattocks, as smaller stones are filled in the voids.
A pedestrian roller will then undertake compaction as per the pre determined passes.
Thereafter, a layer of quarry dust will be olaced and compacted using the pedestrian
roller.
The activity will be done by one team with the following resources:
Vehicles and equipment
Excavator - 1 No.
Vibratory rollers - 1 No.
Tippers (20) Tons - 2 No.
Asphalt cutter - 1 No.
Water browser - 1 No.
Set of survey equipment - 1 No.
Labour
1. Foreman - 1 No.
2. Plant operators - 4 No.
3. Drivers - 3 No.
4. Surveyor/leveler - 1 No.
5. Chainmen - 4 No.
6. General labourers - 10 No.
3 WALKWAYS
After earthworks is completed, the walkways will be covered by paving slabs.
Firstly, a layer of sand will be placed, the paving slabs laid according to the
dimensions and drawings and mortar joints to join them will be undertaken.
The Asphalt batching shall be used to produce asphalt concrete after the design mix
has been approved. The bitumen and mineral fines shall be heated separately before
mixing to ensure the output temperature of the mixture. First the aggregate shall be
sent into the mixer, after 5-10 seconds, the bitumen shall be added, then the mineral
fines. When the bitumen and mineral fines are sent into the mixing cabin, the
temperature should be 110 + 3℃ above the bitumen soft point, and the temperature of
the mineral fines shall not be more than 15℃ of that of the bitumen, and the
kinematic viscosity shall reach 150-300.
The 15T tippers will be used to haul the bitumen mixture to the spreading site. Every
tipper shall use an insulating rainproof double-layer canvas to ensure good cover to
the mixture. The carriage metal bottom board of the hauling vehicles shall be tight,
clean and smooth.
In order to decrease the segregation of the mixture, the material shall be loaded in
three batches. The loading sequence will be middle, front and back.
The temperature of the bitumen mixture shall be checked before offloading into paver.
If the material of acceptable temperature and uncontaminated, the tipper shall drive
backwards to the front of the spreader about 10-30cm and change to neutral gear.
During the construction period, there will be 2-3 vehicles ready to unload the bitumen
mixture in front of the spreader to ensure continuously operation.
Two spreaders will be operated in parallel to cover the full layer width. The distance
between two spreaders will be about 5-10m. The operation will ensure that the
longitudinal joint is formed within the hot mix.
The first layer will be paved with line and the other layers will be paved with the non-
contact balance beam to control the elevation and thickness. The spreader will ride
with an even speed of 1~3m per minute.
The places, which the spreader cannot reach, shall be reported to the Engineer. With
the Engineer’s approval, the mixture shall be spread manually. Such places are
irregular shape or different depth or space limitation or manual structure etc.
During the process of spreading bitumen mixture, the width, depth, smoothness,
crown and temperature shall carry out tracking detection. The places which cannot
reach the standard should be adjusted immediately.
If there is an interruption during the spreading, the spreader will be moved forward at
once to ensure the continuous compaction on the paved layer and 1m will be left
without rolling, and this 1m part will be removed if the spreading is renewed.
If there are some cold joints formed, the joints will be cut to full depth and a layer of
hot bitumen (80/100) will be brushed on the joint prior the spreading.
The mixture temperature will be between 135-165℃ and the initial rolling temperature
will be not under 120℃. Temperature when the mixture will be poured into the
spreader shall be not under 135℃. The rolling shall be finished before the temperature
reduces to 90℃.
The double steel-wheel vibratory roller shall be carried out static rolling twice. The
speed of rolling will be 1.5-2.0km/h, and the maximum speed will be 3km/h. The
temperature of initial rolling cannot below 120℃. If the obvious displacement appears
during the rolling process, the Engineer shall determine the initial rolling temperature
on site. When the rolling will be carried out, the traction wheel will be in front and the
roller shall go forward in uniform speed. The roller shall go backwards along the
former track and carry out vibrated rolling. The mixture shall get preliminary stability
to prevent removal. The smoothness and crown shall be checked after initial rolling. It
will be necessary to correct some faults if required.
The subsequent rolling shall be carried out immediately after the initial rolling. The
temperature shall not below 115℃when the repetitive rolling will be finished. During
the repetitive rolling, two vibratory double-wheeled rollers will be rolled for 4 times,
and then 2 heavy tyred rollers will be rolled for 4~6 times with the rolling speed of 3.5-
4.5km/h. The repetitive rolling must achieve the required compaction densities
without obvious wheel marks. If the mixture sticks to the wheels, a little bit soap
water will be brushed by the mop. Actual rolling procedure will be as determined
during trial tests.
Double steel-wheel roller shall carry out static rolling twice in the final rolling
immediately after subsequent rolling. The speed of rolling will be 2.5-3.5km/h. The
temperature shall be above 90℃when the final rolling will be finished.
The rolling shall be carried out from lower to upper edges of the pavement cross-
section.. Every time the roller shall overlap with 1/3-1/2 wheel widths. The vibratory
frequency and amplitude shall be chosen according to the species, temperature and
layer depth of mixture.
The roller shall extend 5-10 cm outside when rolling the edges. The static rolling shall
be carried out first, then vibratory rolling, finally static rolling again.The operation
length of the roller shall match the speed of the spreader, and the roller shall go
forward as the spreader.
During the rolling, the wheel of the roller shall be kept continuously wet to avoid
sticking of the mixture. If required, it will be necessary to adopt batch spraying of
water. But the water quantity shall not be too much to cause fast cooling of mixture
surface.
The roller shall be forbidden to turn, turn back, move on both sides and brake
suddenly.
The traffic will be forbidden to pass 24 hours after the rolling is completed.
Quality control testing shall then be carried out by the Engineer in accordance with
requirements of the specifications.
The proposed construction procedure is as shown below.
Setting out
Compaction by rollers
Joint processing
ROAD FURNITURE/ANCILLARY WORKS - BILL NO 20
These works will commence towards the end of the contract period. The activities are
independent and can be undertaken at any time as the Engineer instructs, but
probably at the towards the end of the contract period. They include: -
Road making will be undertaken by hot thermoplastic paint. If need arises, a specialist
sub-contractor will be brought in to undertake the works.
The Contractor will make use of the existing government laboratories for investigative
tests. The laboratories will cover all aspects of testing requirements under the
Contract.
The contractor has employed a materials technologist who will work hand in hand
with the resident Engineer’s team to ensure quality control.
The contractor will have a test requisition form, to be submitted by the respective
foreman to the laboratory team, so as to undertake the necessary testing.
Start-up Phase
Establish quality required
Resolve conflicts
Ensure testing is performed
Establish detailed testing schedule based on production schedule
Review Safety
Production Phase
Ensure Contract Compliance
Conduct intermittent or continuous inspections to identify and correct
deficiencies
Inspect completed phases before scheduled Government acceptance
Ensure Testing reports are submitted
Ensure rework is completed
Identification, acquisition and exploration of the required borrow pits for fill for
shoulder to pavement and earthworks will start during the mobilization period and
proceed as per requirements until their needs are met.
Utilization of borrow pits will be carefully organized and coordinated such that the
fastest progress and most economic savings (overhaul) are achieved.
Approval will be sought to source gravel from the road reserve if it proves to be within
the specifications.
The Contractor shall excavate the gravel and stockpile in heap(s) for the efficient
loading by equipment
CEMENT
These products will be sourced locally and samples will first be availed to the
laboratory for testing to seek approval.