EIA Systems in Nigeria Evolution Current
EIA Systems in Nigeria Evolution Current
EIA Systems in Nigeria Evolution Current
Abstract
1. Introduction
2. Literature review
EIA systems have been developing all over the world since the late 1960s when
EIA was first given legal status through the 1969 United States National Environ-
mental Policy Act (NEPA). NEPA required EIAs for federally funded or supported
projects in the US that were likely to have environmental effects, and has become
an important model for other EIA systems internationally. Many state level EIA
systems have been established in the USA in addition to NEPA. Indeed, 16 of the
USA’s 50 states have so-called ‘‘little NEPAs’’ for actions that require state funding
or permission (Glasson et al., 1999). Since the enactment of NEPA, EIA systems
have been established in various forms throughout the world beginning with more
developed countries such as Canada (1973), Australia (1974), W. Germany (1975)
and France (1976). The approval of a European Directive on EIA in 1985 made
mandatory the enactment of EIA legislation in many European countries, as for
example UK’s Town and Country Planning (Assessment of Environmental effects)
Regulations 1988. Following the breakup of the Soviet Union, EIAs were also
O.A. Ogunba / Environ. Impact Asses. Rev. 24 (2004) 643–660 645
enacted in the former Union countries in the early to mid-nineties. The early 1990s
also saw a large growth in EIA systems in Africa (such as in Nigeria) and also in
South America (Sadler, 1996; Glasson et al., 1999).
In assessing EIA systems to determine what constitutes a ‘good’ system, Weston
(1997) argues against international comparisons. He appraised the UK EIA system
and declined to categorize it as inefficient relative to the US system, despite critical
reviews of authors such as Wood (1995). To support this position, he reasoned that
the adoption of EIA in the UK was actually considered in that country as a
superfluous addition to an already highly developed Town Planning system. EIA
was only taken up under compulsion of European Union directives. The so-called
deficiencies of the UK EIA system as noted by Wood (1995) were a reflection of
reluctance, in the UK, to replace or duplicate efficient provisions in the existing UK
Town Planning system with US EIA provisions that were not necessarily better. It
would be wrong to classify the UK system as inefficient for not incorporating all the
provisions of the US NEPA. The corollary of Weston’s arguments is that it might
not be wise to compare systems operated in Nigeria with those of the US and UK,
for the reason that origins, legislations and operating environments are dissimilar.
Consequently, it appears better to approach the appraisal of Nigerian EIA
systems from the viewpoint of how well it has progressed along a path of evolution.
The model proposed by Gibson (2002), based on his studies in Canada, is
particularly relevant to such an appraisal, and it is possible to evaluate the
development and structure of individual Nigerian EIA systems against this model
to evaluate how well the systems are progressing towards the best possible concept
and practice.
Gibson (2002) modeled the transition of EIA systems in Canada into four
basic stages of evolution. The stages postulated are as follows:
Gibson observed that transition from one stage to another comes about by
means of concerted effort, often in the face of stiff resistance, but he noted that
the transition consistently brought about a more mandatory, participative and
comprehensive EIA system. Specifically, he observed that EIA systems mature in
nine aspects to become:
different technical solution. Skeham (1993), West et al. (1993) and others argue
that the use of experienced EIA consultants is a fundamental aspect towards
which EIA systems should evolve, and they observed a correlation between EIA
quality and the experience of consultants and planning authorities. Kakonge and
Imevbore (1993) develop the issue of experience further by arguing that it is not
just experience in personal terms which hinders good quality impact assess-
ments, but the knowledge and data that is built with experience. Weston (1997),
Bulleid (1997) and others point out that the provision of technical guidance on
the content of Environmental Statements is another fundamental feature towards
which EIA systems should evolve, since it leads to standardization of contents.
Lee-Wright (1997) emphasizes the use of qualified multidisciplinary staff as
another component of a good EIA system. She insists that EIA is team activity,
and it is ‘‘almost impossible to envisage circumstances where the range of issues
could be adequately addressed by a single individual’’. Alo (1999) argues that
for any good EIA system, EIA assessors and agencies must possess substantial
analytical capabilities for fieldwork, laboratory testing, research, data processing
and predictive modeling. Andrews et al. (1977), Read (1997), Beanlands and
Duinker (1982), Westman (1985), the DoE Draft Guidance (1994) submit that
EIA systems should mature towards inculcating an early consideration of
scoping, that is, an early decision on what are the likely significant impacts
of a project/action. While there is substantial agreement that scoping is
important, there is nevertheless considerable discussion as to just what is
significant.
The movement of transition towards EIA maturity is often gradual and fraught
with problems. Nevertheless, the movement is generally positive, and this is
apparent if one takes a closer look at the transition of Nigerian EIA systems from
the reactive pollution control of the 1960s up till the relatively advanced
environmental assessment of the present time.
As stated earlier, Gibson (2002) has modeled the transition of EIA systems
into four basic stages of evolution. The Nigerian evolutionary process shows
some adherence to Gibson’s model, though the following discussion would show
that this is not always the case.
An analysis of papers by Dan-Habu (1996), Okorodudu-Fabura (1988) and
Isichei (2000) shows that the initial focus of environmental awareness and
legislation in Nigeria was on the petroleum industry. The initial belief in the
country was that only the petroleum sector required close environmental
monitoring. Environment legislations came in the form of pollution reduction
measures that reacted to local problems within the petroleum industry. Several
industry regulations—under the authority of the Petroleum Act, 1969—were
promulgated to regulate the exploration of petroleum in Nigeria, and control
648 O.A. Ogunba / Environ. Impact Asses. Rev. 24 (2004) 643–660
pollution. The regulations were more reactive than proactive and bear a
resemblance to the first of the Canadian EIA evolutionary stages noted by
Gibson (2002).
Outside of the petroleum industry, however, there were as yet no environ-
mental regulatory institutions or legislations. Environmental awareness was
nonetheless gradually building up, largely owing to the country’s participation
in international environment conferences. Nigeria was one of the 114 govern-
ments represented at the historic United Nations 1972 Stockholm Conference,
which addressed problems of the human environment. As an aftermath of this
Conference, an Urban Development and Environment Division was created in
the Federal Ministry of Economic Development in 1975. Moreover, in the
1981 –1986 Five-Year Development Plan, there was a provision that ‘‘feasi-
bility and viability studies for all projects, both private and public should be
accompanied by environmental impact assessments’’ (Okorodudu-Fabura,
1988). This provision was not, however, accompanied by any formalized
environmental legislation.
Nigeria also participated in the May 1982 10th Anniversary of the Stockholm
Conference, which reaffirmed participants’ commitment to the protection and
enhancement of the quality of the human environment. In April 1982, Nigeria
hosted the 69th Inter-Parliamentary Union Spring Meetings at which the
Committee on Education, Culture and Environment adopted a draft resolution
on the ‘State of the World Environment Ten Years after the UN Conference on the
Human Environment’ and the steps to be taken for improvement including the
fields of national and international legislation. Participation in such international
conferences served to build awareness, policy and preliminary institutions.
The above build-ups to full-blown EIA (outside of the petroleum sector) in the
1970s and early 1980s find no place in Gibson’s four-stage model. This is
possibly because Canada did not have much of a build-up stage; they adopted
EIAs very soon after the US in 1973. A build-up stage is nevertheless an
important part of the EIA evolutionary process in Nigeria and possibly in many
countries of Africa. For widespread applicability, it would be helpful if Gibson’s
ideas can be updated to include a build-up stage following what he (Gibson)
describes as stage 1.
Sequel to the build-up of awareness came the formalization of Nigeria’s
environmental policies. This was jump-started only after the Koko incident in
1987. The Koko incident was an incident involving dumping of toxic waste in
Koko, a southern Nigerian village, by an Italian ship. This caught the country
unprepared, as it had neither effective environmental legislation nor environment
controlling body to manage the incident effectively. As a reaction to the Koko
incident, the Federal Environmental Protection Agency (FEPA) was established
under Decree 58 of December 30, 1988. The next year, FEPA published its
National Policy on the Environment. Then, the National Council on the
Environment at its meeting in 1990 recognized EIA as an indispensable
prerequisite for the effective implementation of the National Policy on the
O.A. Ogunba / Environ. Impact Asses. Rev. 24 (2004) 643–660 649
Environment, and directed that EIA be made mandatory for all development
projects with effect from March 1991. The body also made environmental
auditing mandatory for all existing industries and urged FEPA to establish
guidelines and procedures for operation all over the country.
At this time (1991), the environmental regulations operated in the petroleum
industry were maturing from reactive control measures to a proactive EIA
system, that is, from the first to the second stage described by Gibson in his
paper. This was occasioned by the release of Environmental Guidelines and
Standards for the Petroleum Industry in Nigeria (EGAS) in 1991. In 1992, in
response to the realization that all sectors of the economy required EIAs, two
distinct legislations emerged (in addition to that already operating in the
petroleum industry), adding up to three separate Environmental Impact Assess-
ment systems in the country. The two newer EIA systems, which made a first
appearance in 1992 by legislation, involved a jump over stage 1 into stage 2. The
jump was occasioned by the exigent situation (the Koko incident and interna-
tional pressure) as well as the fact that the country was able to produce EIA
legislations which were learnt from 20 years of evolution in countries such as the
US and Canada.
The budding of three different EIA systems in 1992 is a matter that would
generate some curiosity. An explanation is derivable from the process of
evolution of the different systems. As earlier stated, the country’s first EIA
system (that in the petroleum industry) evolved out of guidelines, standards and
procedures for petroleum industry environmental control since the late 1960s.
Over a period of 20 years, the EIA system in this industry evolved (in a manner
quite in keeping with Gibson’s model) into what that author describes as stage 2.
By contrast, the Town Planning EIA system promulgated into law in 1992 was
not the result of a long evolutionary process and did not pass through Gibson’s
first stage; it was more or less jump-started by legislation and bears resemblance
to the UK EIA system which was compulsorily created by an EU directive in
1988. Prior to the promulgation of the enabling decree, the urban and regional
planners had operated various regulations for development control, which were
usually derived from the UK Town Planning system. When under compulsion
from the EU, the UK enacted its Town and Country Planning Regulations 1988
(which covers development activities, and specifies town planners as the
principal environment assessors); Nigeria also developed a similar legislation
in 1992. The third EIA system (the EIA Decree no. 86) was also jump-started into
Gibson’s stage 2 by legislation in 1992. This system more or less follows the
pattern of the US NEPA Act.
The result was three independent systems: one for the petroleum sector
(governed by the Directorate of Petroleum Resources, DPR), another for the
urban and regional planner’s development control (governed by local government
councils and the town planning divisions of the State Ministries of Lands), and
yet another which attempts to span all sectors (governed by the FEPA). By 1992
all the three systems had in one form or the other advanced legislations
650 O.A. Ogunba / Environ. Impact Asses. Rev. 24 (2004) 643–660
4. Methodology
The empirical sections of this study evaluate current EIA practice and
shortcomings. The study is set in the southwest of Nigeria, specifically Lagos
metropolis (the former capital of Nigeria and the largest city in West Africa), with
a population of about 6 million people. Lagos metropolis is the main economic
center of the country. The metropolis was chosen as the study area because it is
one area where all the three EIA systems operate concurrently. Data collection
was in March 2002.
The study adopted an interview approach to data collection on the three EIA
systems. The subjects of interview under each system were first, EIA consultant
firms, and second, the statutory receiving authorities. Initial questioning evalu-
ated the socioeconomic background of all the interviewees (EIA consultant firms
and the statutory receiving authorities). This showed that respondents were
invariably university graduates in basic, agricultural or environmental sciences.
Further questions investigated the adherence of the three EIA systems to criteria
identified in the Literature review.
A total of 46 respondents were interviewed. With regard to EIAs conducted
under Decree 88, interviews were conducted on random samples of firms of 10
Estate Surveyors and 10 Town Planners (these are the two professions designated
as impact assessors under Decree 88), as well as an officer of the Town Planning
Department of the Ministry of Lands (the statutory receiving authority under
Decree 88). As for EIAs conducted under the Petroleum Act, interviews focused
on 10 registered EIA consultant firms as well as an officer of the statutory
receiving authority—the Department of Petroleum Resources. Interviews for
EIAs conducted under Decree 86 likewise focused on 10 registered consultant
firms as well as an officer of the Federal Environmental Protection Agency in the
Ministry of Environment and Physical Planning (the statutory receiving author-
ity). To obtain some degree of academic perspective, three members of the
O.A. Ogunba / Environ. Impact Asses. Rev. 24 (2004) 643–660 651
5. The results
Table 1
Assessment of Nigerian EIA systems according to indicators of best practice
Criterion Average scores
EIA Decree 86 Town and Country DPR
Planning Decree 88 (Petroleum Act)
Public participation in EIA 1 0 1
decision-making
1 0 1
Post decision and implementation 2 0 2
monitoring and audit provisions
Provision of adequate powers of 1 1 1
enforcement to EIA agencies
Examination of alternatives to the 1 0 1
project in the EIA process
and report
The use of qualified 2 0 2
multidisciplinary staff
Use of experienced EIA 2 0 2
consultants
The provision of technical 2 0 2
guidance on the content of
Environmental Statements
Possession of analytical capabilities 1 0 1
required for fieldwork, laboratory
testing, and research
Possession of analytical capabilities 0 0 0
required for data processing
predictive modeling
652 O.A. Ogunba / Environ. Impact Asses. Rev. 24 (2004) 643–660
6. Discussion
Other awkward concerns rose in the course of the interviews. First, there is
unease on the multiplicity of designated authorities for the approval of EIAs in
the country. Most of the respondents agree that there are considerable areas of
overlap between the three EIA systems. A recent attempt by the Minister of the
Environment to bring the Department of Petroleum Resources into the Ministry
of Environment was stoutly opposed by the Department. Prospective permit
seekers strive to satisfy all these bodies with the attendant problems, especially
costs and time of executing reports for two or more of the controlling authorities.
Sometimes, permit seekers simply ignore one of the agencies. An official of a
State Environmental Protection Agency who was interviewed complained that his
agency is rendered superfluous as permit seekers go to obtain approval from the
(rival?) ministry of lands and housing.
Some respondents complain that Nigeria’s efforts at environmental conserva-
tion depend excessively on regulatory powers given to FEPA, the DPR or the
Ministry of Lands. They believe that economic incentives can complement such
regulations to reduce and prevent pollution. In essence, the argument is that profit
should be removed from environmental violators.
Some legal respondents believe that the Environmental Impact Assessment
Decree 86 has flawed legal drafting. An important instance cited is where the
decree allows the President, in Section 15, to exclude projects from Envi-
ronmental Impact Assessment where in his opinion the environmental effects
of the projects are likely to be minimal. The expertise of the President in
determining the effect on the environment was questioned, as was the same
section of the decree that allows projects to be excluded from Environmental
Impact Assessment in cases of ‘‘national emergency’’. The drafting of
sections relating to EIA in Decree 88 was also criticized as being brief
and vague, and as not describing powers of enforcement for the competent
authority (the Ministry of Lands).
Other respondents voice concern as to the low degree of advertisement of the
procedural guidelines for environmental impact assessment of FEPA and the
DPR. It is suggested that the guidelines have not been given wide circulation to
enable the public and stakeholders to know the process and procedure involved in
EIA in Nigeria. Consequently, a lot of affected stakeholders do not know of their
rights to public hearings on proposed projects nor of their rights to object to
proposed developments that could affect the sustainability of their health and
livelihood.
O.A. Ogunba / Environ. Impact Asses. Rev. 24 (2004) 643–660 655
Some respondents believe that FEPA and the DPR are much too centralized
and are consequently under excessive pressure to handle the huge numbers of
EIA applications nationwide. A member of the staff suggests that the Agency is
handicapped by a number of constraints (including shortage of funds and
inadequate manpower), which inhibit its ability to cope with its enormous terms
of reference. Views were put forward that the functions of FEPA should be
distributed amongst state protection agencies with FEPA’s role limited to advisory
and supervisory roles. In other words, FEPA should concentrate on research,
review of EIA standards, the building of regulations, specification of guidelines,
organization of training programmes and creation of public awareness on
environmental matters.
The assessment of the three Nigerian EIA systems has yielded important
insights and conclusions. A first insight gained pertains to the manner of
evolution of Nigeria’s three EIA systems along the path of the four-stage
transitional movement of EIA evolution put forward by Gibson (2002).
Nigeria’s pioneering EIA system, that of the petroleum industry, evolved
from reactive pollution control measures in the 1960s to proactive EIAs in
the 1990s, thereby moving forward from the first stage (of merely identifying
local problems and prescribing solutions addressed through negotiations), to a
position juxtaposed between the second and third of Gibson’s stages. The
second EIA system (that operated by FEPA) evolved in a hurry by way of a
jump-start into the second stage, and its present position, like that of the
petroleum industry, is a juxtaposition between the second and third stages.
These two systems (FEPA and the DPR) are described as in a juxtaposed
position between stages 2 and 3 because they contain features of both stages;
Gibson’s Canadian model suggests that in stage 2 socioeconomic impacts are
not considered and public participation is not yet taken seriously. The
experience in Nigeria, on the other hand, suggests that these two aspects
(consideration of socioeconomic impacts and public participation) can occur
simultaneously, even if inadequately. Nigeria’s third system (the Town and
Country Planning system) was jump-started in a hurry by legislation into
stage 2, but does not yet contain any of the features of stage 3.
In consideration of the above comments and other comments made earlier, this
paper suggests a modification of Gibson’s model of EIA evolution as being more
appropriate to the rather complex situation in Nigeria. This six-stage model of
transition (see Fig. 1) allows the flexibility of a stage running concurrently with
the next, or a stage being skipped altogether. Such elasticity might hold true for
other African countries as well.
The second insight is that the existence of three systems in Nigeria is the
result of an uncoordinated attempt of Nigerian policy makers to imitate the
656 O.A. Ogunba / Environ. Impact Asses. Rev. 24 (2004) 643–660
Fig. 1.
dissimilar EIA evolutions of the US and the UK. As earlier stated, the EIA
decree (1992) is patterned after the US NEPA Act, covering all sectors of the
economy, while the Town and Country Planning Decree (1992) is patterned
after the UK Town and Country Planning Regulations 1988, which covers
planning development activities and specifies Town Planners as the principal
environment assessors. The third EIA system, operated under the Petroleum
Act, is an evolution from 1969 petroleum regulations in Nigeria, and
apparently, the petroleum sector is unwilling to relinquish its sector’s
environmental regulatory duties to FEPA. This has resulted in an unnecessary
duplication of the duties of FEPA. The necessity of operating three dissimilar
EIA systems in Nigeria is certainly very questionable, and respondents agree
that the three systems are not mutual complements. On the contrary,
responses in the interviews clearly show that the concurrent use of the three
systems results in applicants having to repeat EIA preparation to satisfy all
systems with the attendant duplication of time and money costs. It is
recommended, in the interests of efficiency, that the country should decide
for only one approach; whether the UK style, the US style or it could
develop its own indigenous style as was suggested in a recent EIA study of
Ghana by Appiah-Opoku (2001). The consideration of indigenous styles in
Nigeria would be a matter for future research. From this paper’s assessment,
however, it appears that the FEPA system (Decree 86) is the most compre-
hensive system, which also best captures the criteria of good EIA systems.
O.A. Ogunba / Environ. Impact Asses. Rev. 24 (2004) 643–660 657
The Urban and Regional Planning Decree 88 of 1992 provides for planned
development of the towns, cities rural areas and regions. Section 33 of the
decree deals with EIAs to be administered by ‘‘control agencies’’ (usually
State Ministries). As was mentioned earlier, Decree 88 focuses on develop-
ment projects while Decree 86 covers all aspects of the Nigeria Economy
(Olomola, 1996). Decree 88 EIAs are meant to guide in the approval of
otherwise development permits from national/state government departments
responsible for urban/regional planning controls. Section 33 of the Nigerian
Urban and Regional Planning Decree provides as follows: A developer shall
at the time of submitting his application for development submit to an
O.A. Ogunba / Environ. Impact Asses. Rev. 24 (2004) 643–660 659
References
Abracosa A, Ortolano E. Environmental impact assessment in the Philippines: 1977 – 1985. Environ-
mental Impact Assessment Review 1987;7(3):293 – 310.
Andrews RNL, Cromwell P, Enk CA, Farnworth EG, Hibbs J, Sharp VL. Substantive guidance for
environmental impact assessment. Washington D.C.: Institute of Ecology; 1977.
Alo B. Environmental impact analysis: policy formulation and implementation in Nigeria. Paper
presented at the FEDEN National Training Session for the 6th Cohort of LEAD Associates in
Nigeria (30th March); 1999.
Appiah-Opoku S. Environmental impact assessment in developing countries: the case of Ghana.
Environmental Impact Assessment Review 2001;21(3):59 – 71.
Beanlands GE, Duinker PN. Environmental impact assessment in Canada—an ecological contri-
bution. Halifax: Institute for Resource and Environmental Studies, Dalhousie University;
1982.
Bulleid P. Environmental impact assessment. In: Weston J, editor. Planning and Environmental Impact
Assessment in Practice. Addison Wesley Longman; 1997. p. 26 – 41.
Commission of the European Communities, 1992. Report from the commission of the implementation
of directive 85/337/eec. Brussels: CEC.
DoE J. Evaluation of environmental information for planning projects: a good practice guide. London:
HMSO; 1994.
Directorate of Petroleum Resources (DPR) J. Nigeria: environmental guidelines and standards for the
petroleum industry in Nigeria (EGAS). Lagos, Nigeria: Department of Petroleum Resources; 1991.
Directorate of Petroleum Resources (DPR) J. Nigeria: environmental guidelines and standards for the
petroleum industry in Nigeria (EGAS). Lagos, Nigeria: Department of Petroleum Resources; 1999.
Draft Revised Edition.
Federal Environmental Protection Agency (FEPA) J. Nigeria: environmental impact assessment pro-
cedural guidelines. Abuja; 1995.
Frost R. Environmental impact assessment monitoring and audit. In: Weston J, editor. Planning and
Environmental Impact Assessment in Practice. Addison Wesley Longman; 1997.
Gibson RB. From Wreck Cove to Voisey’s Bay: the evolution of federal environmental assessment in
Canada. Impact Assessment and Project Appraisal 2002;20(3):151 – 9 [September].
Glasson J, Therivel R, Chadwick A. Introduction to environmental impact assessment. 2nd ed. UCL
Press; 1999.
Ifeadi, C.N., Orbima, I.I., 1996. Critical review of the implementation of environmental impact
assessment in the Nigerian petroleum industry. Mimeograph, 1 – 26.
Isichei AO. Environmental impact assessment and environmental evaluation reports. Paper presented
at the Workshop of the Nigerian Corrosion Association, Warri (27th March); 2000.
Kakonge AO, Imevbore AO. Constraints on implementing environmental impact assessments in
Africa. Environmental Impact Assessment Review 1993;13(3):299 – 308.
660 O.A. Ogunba / Environ. Impact Asses. Rev. 24 (2004) 643–660
Lee-Wright M. Taking charge of the environmental team. In: Weston J, editor. Planning and Environ-
mental Impact Assessment in Practice. Addison Wesley Longman; 1997. p. 42 – 59.
Okorodudu-Fabura MT. Law of environmental protection materials and text. Ibadan, Nigeria: Caltop
Publications; 1988.
Read R. Planning authority review. In: Weston J, editor. Planning and Environmental Impact Assess-
ment in Practice. Addison Wesley Longman; 1997.
Sadler B. Environmental assessment in a changing world: evaluating practice to improve performance.
International study on the effectiveness of environmental assessment. Ottawa: Canadian Environ-
mental Assessment Agency; 1996.
Skeham DC. EIA in Ireland. Paper Presented at EIA Conference, Bloomsbury Hotel, London (25 – 26
November); 1993.
West C, Bissett R, Snowden R. Developing countries environmental impact assessment. Paper Pre-
sented at EIA Conference, Bloomsbury Hotel, London (November).1993;25 – 6.
Westman WE. Ecological impact assessment planning. London: Wiley; 1985.
Weston J, editor. Planning and environmental impact assessment in practice. Addison Wesley Long-
man; 1997. p. 180 – 7.