PPAM Final Notes
PPAM Final Notes
PPAM Final Notes
What is a Project?
– Construction
Defining Project:
• Heizer and Render (2010:90) define a project as “a series of related tasks directed
toward a major output.” A project is a temporary endeavour undertaken to create a
unique product, service or result (PMBOK Guide, 2004).
All projects have some elements in common and, according to Pycraft et al. (2010:464), these
include:
• Complexity. Several tasks are required to be undertaken to achieve the objectives. The
relationship between all these tasks can be extremely complex.
• Uncertainty. As all projects are planned before they are executed, they carry a certain
amount of risk.
• Life cycle. Projects normally go through three phases – planning, execution and
phase-out. Temporary nature. Resources may be moved from one project to the next
once the tasks have been completed.
FEATURES OF PROJECT
• Two essential features are present in every project no matter how simple or
complicated they are. In the first place, all projects must be planned out in advance if
they are to be successfully executed. Secondly, the execution of the project must be
controlled to ensure that the desired results are achieved.
• A project is an interrelated set of activities that has a definite starting and ending point
and results in the accomplishment of a unique, often major outcome.
• An activity, A project is a sequence of activities that has a definite start and finish, an
identifiable goal and an integrated system of complex but interdependent
relationships.
• A schedule, The schedule sets priorities, start times and finish times. More
specifically, It’s a temporary group activity designed to produce a unique product,
service or result.
• A project is temporary in that it has a defined beginning and end in time, and
therefore defined scope and resources.
• And a project is unique in that it is not a routine operation, but a specific set of
operations designed to accomplish a singular goal.
PROJECT MANAGEMENT
“Application of knowledge, skills, tools and techniques into project activities to meet
project requirements”.
– Initiating
– Planning
– Executing
– Closing
These knowledge areas are applicable to all stages of the project, in fact during the whole life cycle
of the project.
FUNCTIONING OF PROJECT MANAGEMENT
Integration Develop Develop Project Management Direct & Monitor & Close Project
Project Plan Manage Control Project or Phase
Charter Project Work
Execution Perform
Integrated
Change Control
1-Planning –
– The Business Criteria- Are the cost and time scale right for the business as a
whole?
2 - Organizing
• Organizing is about arranging the people, material and support resources in the
project to meet the project’s communication, integration and decision making
needs to achieve on time project delivery.
• Their responsibilities?
• Is committed to project.
• Communicates effectively
3 - Controlling
• Controlling means making sure that the project is managed as specified in the
planning documents and that attempts at organizing become a reality.
• The project against the three Criteria used during feasibility by asking the following
questions-
– Are we still going about the project at the right way? Are we within
Schedule?
• If one or more of these criteria is not satisfied, the board can consider three options-
• To plan thoroughly all aspects of the project, soliciting the active involvement of all
functional areas involved.
• To control the "technical" versus "cost" trade-offs determine the specific areas
where optimization is necessary.
• No risk management
• On time
• On budget
• Clearly defined goals. This should include the general project philosophy or general
mission of the project and a commitment to those goals on the part of the project team
members.
• Competent project manager. A skilled leader who has the technical, interpersonal
and administrative skills.
• Feedback capabilities. All parties that are involved in the project must be able to
review the project status on a regular basis and make suggestions and corrections
through formal feedback channels or review meetings.
• Project staff continuity. Key project personnel must be kept on for the duration of
the project. Frequent staff turnover results in the project losing the wealth of
knowledge, which may have been accumulated
– A customer-first orientation
• A good way forward would be through the establishment of success criteria for the
project. If you want the project to succeed (and who doesn't?), then you have to know
when you have succeeded. Success criteria can be described as being hard or soft:
Hard criteria
Hard criteria are often the most obvious criteria that are tangible and measurable and
can be expressed in quantitative terms. They tend to pose the question "what?", that
is "what should be achieved?“
– Performance specifications
– Meeting deadlines
– Resource constraints
Soft criteria
Soft criteria are usually less obvious, but not necessarily less important. They are often
intangible and qualitative. Consequently they may be difficult to measure. They would
tend to ask the question "how?”
• Lower costs
• Higher quality
• Improved productivity
Chapter -2
Generation and screening of project ideas: Generation of Ideas, Monitoring the
Environment, Corporate Appraisal, Identifying Investment Opportunity,
Scouting for Project Ideas, Preliminary Screening, Project Rating Index and
Sources of Positive – Net Present Value (NPV).
There are various considerations and guidelines which are helpful in the generation and
screening of project Ideas. There are following steps –
1. Generation of Ideas
3. Corporate Appraisal
6. Preliminary Screening
1. Generation of Ideas
Generation of ideas – The Search for ideas is the first step towards establishing a successful
venture. Identification of such opportunities requires imagination, sensitivity to environment
changes and realistic assessment of what the firm can do following. Steps are included in
Generation of Ideas –
Synetics: The term ‘synetics’ (a Greek Word) means ‘the fitting together of diverse
elements’. William J.J.Gordon developed this technique to stimulate creative solutions by
piecing together distinct, novel and sometimes irrelevant ideas. A synetics group consists of
members having varied background and training. The leader, at this stage, asks the members
to break the cake of custom and come out with novel ideas. Methods like role playing,
analogies, paradoxes are used to develop creative ideas. Members are even asked to remain in
a room until they find at least one novel idea. However, it may be used to solve complex and
technical problems.
Nominal Group Technique: The nominal group is a ‘paper group’, it is a group in name
only. Developed by two researchers at the University of Wisconsin, Andre Delbecq and
Andrew Van de Ven, the technique includes the following steps:
The leader explains the problem to the members of the target group.
Each member writes down his ideas silently and independently.
Each member then presents a single idea at a time to the group, which is written on a
black board for all to see.
A discussion is held to explain and evaluate the ideas,
Silent individual voting on priority.
The basic idea in NGT is to respect interpersonal communication and to increase the
deliberation and contributions of individual members. The NGT follows a highly structured
process and tries to integrate creative thinking, through group interaction in order to solve
organizational problems in a useful manner.
The Delphi Technique: The Delphi technique, developed by Norman Dalkey and Olaf
Helmer in the 50s at Rand Corporation, to forecast the damage that a Russian nuclear attack
on the United States would cause, does not required the physical presence of the group
members. It is a technique used to obtain information from physically dispersed experts,
through the use of written questionnaires. The two step process is generally used in the
Delphi technique. In the first stage, the problem is identified by the leader, the experts are
identified and contacted, a questionnaire is carefully structured and mailed out to experts, the
leader collects the responses sent by experts and prepares a feedback report. In the second
stage, the feedback report and in a more advanced second stage, questionnaires are sent to the
members once again for reaction and reassessment. Each member evaluates the feedback
report, develops new suggestions, votes on the priority of the ideas contained in it. This
process is continued until a clear solution emerges.
2. Monitoring the Environment: The Firm Must Systematically monitor the environment
and Assess its competitive abilities. For the Purpose of monitoring the business environment
may be divided in to Six categories –
1. Economic Sector -
2. Government Sectors
3. Technological Sectors
6. Suppliers Sectors
3. Corporate Appraisal
There are several factors that are helpful in identifying promising Investment
opportunities, these are -
6. Preliminary Screening
V. Reasonableness of Cost
Potential
Entrants
Substitutes
According to Schwalbe, project selection may take place using one or more of the following
methods:
• This usually involves the preparation of detailed company specific models used for
decision making purposes and financial analysis.
Weighted scoring model
III. Rate the Project Proposals on various factors, using a suitable rating scale
IV. For Each Factor – Multiply the factor rating with the factor weight to get the factors
score
V. All the factor scores to get the overall project rating index
There are 6(Six) main entry barriers that result in Positive NPV Projects – They are -
I. Economics of Scale
V. Technological Edge
• The project life cycle: Concept. Project initiation - Project Selection, Project Charter,
Project Request for Proposal. Project planning - purposes of project planning, Stages
in the project planning process, Project execution - Key outputs of the executing
process, Project closure and Summary
1. Project initiation
Projects are first selected based on the identification of a need, problem or opportunity. A
sponsor of a project usually identifies these needs and provides the funds necessary for the
project. Apart from the sponsor, a range of project stakeholders must also be identified in this
phase of the project. The following is a list of typical stakeholders in a project:
Project Sponsor – The person that provides the financial resources for the project.
Project Manager – The single point responsibility of a project.
PMO – The office provides support to the project.
Customer or user – This is the person or entity that will use the project’s product.
team – the members of the project team who are directly involved in executing the
functions.
Influencers – People or groups who are directly or indirectly interested or affected by
the project. They can also influence the project positively or negatively.
Investors – A person or entity making the investment in a project.
Contractor – A contractor is normally the person or organization that is entrusted with
supplying the services and/or goods to achieve project deliverables.
Government – The government is in most cases a stakeholder in projects whether they
are public or private sector projects because it has an interest in the project, e.g.
collecting taxes.
Project Selection
Clements and Gido explain the following four steps in the selection of a project:
i. Develop a set of criteria against which the project will be evaluated. This must take into
account, the company goals, sales volume and market share, investment, risks, resources,
competitors, regulations, etc.
ii. List the assumptions that will be used as the basis for each project.
iii. Gather data and information for each project.
iv. Evaluate each project against the identified criteria.
According to Schwalbe, project selection may take place using one or more of the following
methods:
Focus on strategy and organisational needs
Performing a financial model
Using weighted scoring model
Implementing a balanced scorecard
Addressing problems, opportunities and directives
Considering project time frames, and
Considering project priorities.
Project Charter
Once a project is selected, it is formally authorised and primed using a project charter. The
project charter includes the rationale or justification for the project and is usually the first
official document that initiates a project.
The typical contents of a project charter are:
Project title and date of authorisation
Background to the project
Key assumptions
Business needs and other commercial needs
Scope of work
Key milestones
Project scheduling including estimated start and finish dates
Project estimated budget
Approach
Roles, responsibilities of project team and project organisation.
Planning the project involves determining what needs to be done (scope, deliverables), how it
will get done (sequence of activities), who will perform it (human resources), how long it will
take (schedule), how much it will cost (budget) and what the risks are . These important
considerations are generally included in a comprehensive project proposal.
Planning may have to be carried out more than once during a project, due to changing
circumstances and demands. The result of the planning process is a baseline plan. The basic
stages in the planning process are illustrated in Figure .2
o Deliverables
o Resources
o Price considerations
o Risks
o Expected benefits
2. Project execution (performing)
After planning the project, the third phase involves the accomplishment of the project
objective(s). The executing process group consists of the processes used to complete the work
defined in the plan to accomplish the project’s requirements. The project team should
determine which of the processes are required for the team’s specific project. This process
group involves coordinating people and resources as well as integrating and performing the
activities of the project in accordance with the plan.
Project execution entails fulfilling the deliverables of the project within the client’s accepted
specifications and budget and time constraints. The function that matters most during this
phase is the monitoring and control of progress to ensure that everything is going according
to plan.
Key outputs of the executing process relating to the project integration management
include:
project deliverables,
Requested changes,
Implemented change requests,
Implemented corrective actions,
Implemented preventive actions, and
Implemented defect repair.
Executing outputs relating to project quality management include:
Requested changes,
Recommended corrective actions,
Organizational process assets update, and
Updated plans
Executing outputs relating to project human resources management knowledge area
include:
project staff assignments,
resource availability,
updated staffing management plan and,
team performance assessment.
During this phase, monitoring and controlling project work involves collecting, measuring,
and disseminating performance information as well as assessing measurements and analyzing
trends to determine what process improvements can be made. On the other hand, performing
integrated change control involves identifying, evaluating, and managing changes throughout
the project’s life cycle. Every project will experience changes at one point or another. It is
therefore important to develop a process of monitoring controlling and documenting project
changes.
3. Project closure
The closing process group is the most neglected project phase of all the phases in a project.
This phase includes processes used to formally terminate all the activities of the project or
phase. The project success or failure is evaluated and the project is handed over to the client.
The project experiences or lessons learnt are documented. Closing projects involves
stakeholder and customer acceptance of the final product or service, and bringing the project
to an orderly end.
Summary of the process
The process comprises the following steps:
i. Establish project objective.
ii. Define the scope.
iii. Create a work breakdown structure (WBS) by subdividing the scope into pieces or work
packages.
iv. Assign responsibilities.
v. Define specific activities.
vi. Sequence the activities using a network diagram.
vii. Estimate activity resources.
viii. Estimate activity durations.
ix. Develop a project schedule.
x. Estimate activity costs.
xi. Determine the budget.
Conclusion
General Managers often work closely with project managers in various projects within or
sometimes outside the organisation, and are therefore required to have an understanding of
and the techniques used in project planning and scheduling. Effective also allows firms to
create products and services for global markets. However, techniques do not solve all project
scheduling and management problems, and for this, good management practices, clear
responsibilities for tasks, timely reporting systems and contingency plans are necessary.
CHAPTER-5
PROJECT RISK MANAGEMENT
1. Introduction
This section outlines the most essential knowledge that you should acquire in the field of
project risk management. Be aware that, as a manager or co-ordinator of projects, there will
come a time when your efforts will fall short of necessary requirements. This failure could be
ascribed to numerous factors but, by engaging in constructive project risk management, you
will be able to mitigate the risks to your project.
Definitions
Risk
Risk is an uncertain event that can jeopardise the project objective. Risk includes the
expected losses (economic, time, infrastructure or resources) that a particular phenomenon
might cause. It is a function of the probability of particular occurrences and the losses that
each would cause (severity).
Risk management
Risk management includes the processes concerned with identifying, analysing and
responding to project risks. It includes both minimising the impact of adverse events and
maximising the likelihood of positive outcomes. Project risk management includes the
processes of risk assessment, risk mitigation and risk response.
Hazard
A hazard in the project management domain can be defined as a rare or extreme event, or the
probability of an occurrence in the natural or human-made environment, that adversely
effects the successful completion of the project, to the extent that it may cause economic,
time, infrastructure or resource loss.
Vulnerability
Vulnerability is the degree of loss to a given element (economic, time, infrastructure or
resources) that is at possible risk from the impact of a hazard of a given severity. It is specific
to a particular project and can be expressed on a scale of 0 to 10 (0 indicating no loss, 10
indicating total damage).
Probability
Risk probability in a project can be defined as which the risk event that is likely to occur. The
probability of certain risks influencing a project is determined by the nature of the project.
Frequency
Frequency refers to the number of times a particular risk can impact on a project, for example
rain interruption of a building project or systems downtime in an information technology
project.
Severity
The impact of a risk on a project can be defined by its severity. The severity of a risk is
mostly quantified into monetary terms, although other measuring tools are also often used.
Categories and types of risk
Clements and Gido identifies the following categories of risk:
• Technical
• Schedule
• Cost
• Human resources
• External
• Sponsor/customer
d) Develop a response
Risk response includes the development of proactive measures to counteract identified risks
and changes in risk over the course of a contingency planning. Clements and Gido (2011)
suggest the development of a separate risk response plan. Having identified, quantified and
prioritised the risks, you need to develop a risk response plan which defines ways to address
adverse risk and enhance entrepreneurial opportunities before they occur. The range of
responses includes:
• Eliminate risk.
• Mitigate risk.
• Deflect risk.
• Accept risk (contingency).
• Turn risk into an opportunity.
A contingency plan must also be formulated. A typical contingency plan should contain the
following information:
• Title
• WBS identification number
• Risk/risk events/threats
• Trigger events
• Contingency actions
• Responsible persons
• Cost implications
• Time implications
• Tasks effected
• Influence of critical path
e) Risk control
The risk control function implements the risk management plan to make it happen. This is the
most important part, but surprisingly is often neglected. The risk management plan needs to
be communicated to the entire project team, and where necessary, followed up with
appropriate training and practice runs. The risk management plan should consider:
• Changes in the scope work.
• Changes in the build method.
• Changes in the team members.
• Changes in the suppliers.
The ultimate goal of risk management is risk mitigation. Risk mitigation involves defining
the necessary steps to counter threats and to enhance opportunities. It is the active steps taken
to lessen the effects that a particular identified risk might have on a project outcome. It is also
the continuous measures taken during the life cycle of a project in order to ensure proactive
actions to unforeseen circumstances.
Conclusion
Effective risk management involves:
• Commitment to risk management by stakeholders, top management, the project steering
committee, the project manager and project team members, and
• An adequate project management approach (a capable project manager should take
responsibility for risk management, and he/she and the project team should have an
understanding of the technical and non-technical issues).
Risk management involves identifying, assessing, and responding to project risks in order to
minimise the likelihood and impact of the consequences of adverse events on the
achievement of the project objective. Risk identification includes determining which risks
may adversely affect the project objective and what the consequences of each risk might be if
they occur. Assessing each risk involves developing an action plan to reduce the impact or
likelihood of each risk, establish a trigger point for when to implement the actions to address
each risk, and assigning responsibility to specific individuals for implementing each response
plan. During the project, it is important to evaluate all risks to determine if there are any of
the risks, also, new risks maybe identified that were not considered as a risk earlier in the
project.
CHAPTER -6
PROJECT QUALITY MANAGEMENT
Introduction
The Project Management Institute defines quality as “the degree to which a set of inherent
characteristics fulfil requirements” (Rose, 2005). Rose (2005) states that:
- Quality involves products, defects, processes, customers and systems.
Project quality management includes the process required to ensure that the project will
satisfy the needs for which it was undertaken. Burke (2007) offers two definitions of project
quality management:
- “the processes required to ensure that the project will satisfy the need for which it was
undertaken” (PMBOK Guide, 2004); - “covering quality planning, quality control and quality
assurance.”
Project quality management is about the synergy of continuous improvement of the project
and the principle of project delivery. Using a quality approach plays a key role in assuring
that the project meets customer requirements. Quality management is the process for ensuring
that all project activities necessary to design, plan and implement a project are effective and
efficient with respect to the purpose of the objective and its performance.
This section covers the broad concepts associated with quality management, the different
costs of quality, quality planning, assurance and control, and quality management tools.
- Reliability: propensity of a product to perform consistently over its useful design life;
- Durability: the degree to which a product tolerates stress or trauma without failing;
- Aesthetics: subjective sensory characteristics such as taste, feel, sound, look and smell.
Quality is measured as the degree to which product attributes are matched to customer
preferences in terms of aesthetics;
- Quality Planning – the process of identifying the standards the project needs to comply with
order to achieve the required condition.
- Quality Control – defines the method of inspection (testing), in-process inspection and final
inspection to confirm that the product meets the required condition.
- Project Quality Plan – a detailed document explaining how the company will assure that the
product will be made to the client’s requirements.
- Project Quality Management includes the processes and activities that determine the quality
policies, objectives, and responsibilities necessary to assure that project requirements are met.
Processes critical to the Quality Management System include Quality Planning, Quality
Assurance, and Quality Control.
- Quality Assurance ensures that project management utilizes the quality processes needed to
meet project requirements in a planned and systematic manner.
- Quality Control monitors specific project outputs and determines compliance with
applicable standards. It also identifies project risk factors, their mitigation, and looks for ways
to prevent and eliminate unsatisfactory performance.
The work of quality ‘gurus’ has been incorporated into three popular quality frameworks:
Total Quality Management (TQM), International Organisation for Standardisation (ISO) and
Six Sigma. Many organisations use these frameworks to define and organize their quality
initiatives (Kloppenberg, 2009:284).
- Valuing employees,
Agility
- Management by fact,
- Social responsibility,
- Systems perspective.
The ISO 9000 series of standards addresses quality management systems. The ISO standards
encompass eight quality management principles as listed in Table 7.1.
ISO implementation provides many benefits. It forces analysis of all quality management
activities; it documents all aspects of the quality management system. The ISO approach is
prevention based; it focuses on prevention, not inspection. It is a framework for quality
improvement. Continual improvement is an essential part of the ISO approach (Rose,
2005:33).
Six Sigma
Six Sigma uses a process called DMAIC(define, measure, analyse, improve and control) to
plan and manage improvement. The DMAIC methodology is a 15-step process broken up
into 5 phases (Figure 7.1).
Quality management includes quality planning, quality assurance, quality control, and
quality improvement.
The quality management plan is part of the project plan. It includes the quality policy
(intended direction of the organisation regarding quality) and answers the questions:
Who is in charge (infrastructure and responsibilities)? Where are we going (goals)?
How are we going to get there (processes)?
Quality planning is identifying which quality standards are relevant to the project and
how to satisfy them.
1. Quality policy
This is the overall intentions and direction of an organization with regard to quality, as
formally expressed by the top management. In the case of a joint venture, a quality policy for
the individual project should be developed. The management team is responsible for
dissipating the quality policy to all project stakeholders through appropriate information
distribution channels.
2. Scope statement
The scope statement is a key input to quality planning because it documents major project
deliverables as well as project objectives which serve to define important stakeholder
requirements.
3. Product description
Although the elements of the product description may be embodied in the scope statement,
the product description often contains details of technical issues and other concerns that may
affect quality planning.
In addition to the scope statement and product description, processes in other knowledge
areas may produce outputs that should be considered as part of the quality planning.
The planning process must consider benefit/cost tradeoffs. The primary benefit is less
work, higher productivity, lower costs and increased stakeholder satisfaction. The
primary cost is the expenses associated with project quality management activities.
Benchmarking
Flowcharting
Design of experiments
This is an analytical technique which aims to define variables that have most
influence on the overall outcome.
The quality management plan should describe how a project management team will
implement its quality policy. The plan should define the organisational structure, roles and
responsibilities and resources needed for implementation of quality management. The quality
management plan should address Quality Control of the project, Quality Assurance and
Quality Improvement of the project.
QUALITY ASSURANCE
Quality assurance is evaluating the overall project performance on a regular basis to provide a
confidence that the project will satisfy the relevant quality standards.
Operational definitions
Results of quality control measurements which are records of quality control testing
and measurement in a format of comparison or analysis.
Quality audits which are a structured review of other quality management activities.
They may be timely or carried out randomly. They may be carried out by properly
trained internal auditors or by third parties such as quality systems registration
agencies.
Quality improvement includes taking action to increase the effectiveness and efficiency of the
project to be able to provide added benefits to the stakeholders of that project. In many cases,
the implementation of quality improvements will require preparation of change requests or
taking corrective actions and will be handled according to procedure for overall change
control.
QUALITY CONTROL
Quality control involves monitoring specific project results to determine if they comply with
relevant standards and identifying ways to eliminate causes of unsatisfactory results. Project
results mentioned include both product results such as deliverables and management results
such as cost and schedule performance. The project management team should have a working
knowledge of statistical quality control especially sampling and probability to help evaluate
and control outputs.
The project manager and team should be aware of the following:
- Prevention (keeping errors out of the process)
- Control limits (the process is in control if it falls within these defined limits).
Checklists.
Inspection
Control charts
These charts are graphical representations that display the result of a process over time and
are used to determine if the process is “in control”. Control charts may be used to monitor
any type of output variable. Control charts are most often used to monitor repetitive activity
in production but can also be used to monitor cost and schedule variances.
Pareto diagram
A Pareto diagram is a histogram ordered by frequency of occurrence which shows how many
results were generated by what category or identified cause. Typically the Pareto diagram
reflects that a relatively small number of causes are responsible for the majority of the
problems or defects.
Quality improvement
Acceptance decisions, where the inspected items will either be accepted or
rejected and those rejected may be reworked.
Completed checklists
a) Check sheets
Check sheets are data gathering tools. They are used to compile and record data from
observations or historical data.
b) Graphs
The purpose of a graph is to organise, summarise and display data, usually over time. The
different types of graphs include line graphs, bar graphs and circle graphs.
c) Histograms
A histogram is a type of bar graph that deals with data that exist in a continuous range from a
low number to a high number. Histograms display frequency distribution.
d) Pareto charts
Pareto charts are used to identify and prioritise problems to be solved. They are actually
frequency charts that are aided by the 80/20 rule. This rule states that roughly 80% of
problems are created by roughly 20% of causes (Pareto Principle). This means that there are a
vital few causes that create most of the problems. A Pareto chart is a bar graph with data in
descending order. It involves identifying the vital few contributors that account for most
quality problems in a system and uses a histogram or column chart that can help identify and
prioritize problem areas.
Pareto charts disclose two important types of information. First, the left-most bar indicates
the greatest opportunity for improvement because it represents the source of error responsible
for the most problems. Second, the chart identifies the “vital few”, those sources that account
for most of the defects or errors, and the “trivial many”. The steps in Pareto analysis include:
a. Gathering categorical data relating to quality problems.
b. Drawing a frequency chart of the data (the data is arranged in descending order
from left to right on the chart).
e) Scatter diagrams
A scatter diagram identifies possible relationships between two variables. The closer data
points are to a diagonal line, the more closely the two variables are related.
Figure : An example of a scatter diagram.
f) Flowcharts
A flow chart identifies the sequence of events in a process. Flow charts are graphic displays
of the logic and flow of processes that help analyse how problems occur and how processes
can be improved. They show activities, decision points, and the order of how information is
processed.
g) Run charts
A run chart is used to observe process performance over time. It is a line graph with data that
vary around a centre-line, usually the mean. Run charts a used for the following:
Display the history and pattern of variation of a process over time.
Are line charts that show data points plotted in the order in which they occur.
Control charts are tools for monitoring, controlling and improving processes over time.
Quality control charts:
Is a graphic display of data that illustrates the results of a process over time.
Are mainly used to prevent defects, rather than to detect or reject them.
When a process is in control, any variations in the results of the process are created by
random events; processes that are in control do not need to be adjusted. When a process is out
of control, variations in the results of the process are caused by non-random events; one
needs to identify the causes of those non-random events and adjust the process to correct or
eliminate them. Quality control charts and the seven-run rule can be used to look for patterns
in data. The seven-run-rule states that if seven data points in a row are all below the mean,
above the mean, or are all increasing or decreasing, then the process needs to be examined for
non-random problems.
Figure : An example of a quality control chart and the seven-run rule.
Can also use the 5-whys technique where question “Why” is repeated five times to
peel away the layers of symptoms that can lead to the root cause.
CHAPTER -7
PROJECT COMMUNICATION
Introduction
Communication in any institution is critical to its success, and this is certainly true of
projects. The aim of communication is to ensure that the information necessary for the
management of projects is collected and exchanged or distributed on time, and that when
required, is adequately stored for easier retrieval. This requires a communication plan, as part
of the project plan, which specifies what information will be collected and when, who will be
responsible for the collection and analysis of the data, and to whom, how and when it will be
distributed.
Communication skills and planning are essential to address the issues and challenges
associated with project management. Communication is the basis for gaining understanding
between project team members, for discussing project issues and for settling team disputes.
People in an institution must communicate, but the criteria that characterise project activities
means that they must communicate effectively and efficiently if the work is to be well
directed and managed.
The way project outcomes are communicated can affect how people perceive and accept
those outcomes. Project managers and project team members should be effective
communicators. Communication is a key tool that project team members must use in dealing
with the concerns, service needs and enquiries of clients and role players.
In this section, a broad overview of personal communication is provided. Communication is
defined within a project setting, after which the significance of communication in projects is
explained. Project communication planning, documentation management and meeting and
presentation fundamentals, also come under scrutiny. Lastly, the project communication plan
is discussed.
• Writing style (active versus passive voice, sentence structure word choice, etc.);
• How the project team, and specifically the project manager, liaise with senior management
and internal stakeholders on project resources and progress;
• How the project team liaise with external stakeholders such as the media and community
leaders;
• The distribution of information to all project stakeholders and role-players using appropriate
media and technology;
Personal communication
Written
There is always potential for conflict between the desire to limit the quantity of
correspondence that is a feature of large projects, and the need to ensure that the essential
communications are properly maintained. All project team members should be instructed to
adopt the “need to know” principle, so that copies of written communications are limited to
those who need the information. The need for clarity and simplicity in written communication
also requires constant emphasis.
Graphical
Design and construction drawings (e.g. housing projects) are an essential basis for project
management. In a large project there will be numerous drawings to be issued and approved.
Charts and graphs are also used to convey information. This applies particularly to planning
and progress data and reports. It is important that this data is presented in a clear and accurate
way, and supported by adequate written explanations so that ambiguity is avoided.
Numerical
Tables of data are also used to convey project information. It is important that adequate
explanatory notes are provided, so that readers gain a rapid and accurate understanding of the
numerical information. Numerical data should be presented in a form that can be readily
understood by management.
Electronic
In modern project management, applied and computer technology are in general use. There is
a tendency to believe implicitly in the output from computers. However, output should be
regarded critically. It will have the same degree of accuracy as the input.
Project communication has a dual purpose: the first is to cause some action or agreement to
take place, and the second is to make a record that might be needed later. The larger the
number of people involved in the project, the more communication paths there are, and the
more project time is spent on simply sharing information and keeping stakeholders and role
players up to date.
Proper communication in a project is a critical success factor for managing the expectations
of the customer and the stakeholders. There is a much greater chance of problems and
difficulties occurring due to differing levels of expectations. In fact, in many cases where
conflicts arise, it is not because of the actual problem but because the customer or manager
was surprised. Project communication management provides the critical link among people,
ideas and information that is necessary for success. Everyone involved in the project
‘language’, must understand how the communications they are involved in as individuals,
affect the project as a whole.
Project meetings
The primary purposes of such a meeting are to inform, identify problems, and to identify
action items. According to Clements and Gido, the following are some of the subjects that
might be discussed as part of the agenda:
• Accomplishments since the last meeting
• Corrective actions
Problem-solving meetings
The purpose is to identify and resolve the problem as early as possible for a project to be
successful. According to Clements and Gido (2011:376), the problem solving meeting should
follow a good problem solving approach, such as:
Projects that involve a design phase, such as an information system project or development of
a new marketing brochure, may require one or more technical design review meetings to
ensure that the customer agrees with, or approves of, the design approach developed by the
project contractor.
The two types of design review meetings are:
Clements and Gido also describe some general steps to effectively prepare for meetings:
Project presentations
Clements and Gido also describe some important points to take note of in preparation of and
during a presentation: the guidelines for effective project presentation are
• Prepare notes or a final outline that you will use or refer to during your presentation.
• Go into the meeting room when it is empty or not in use and get a feel for the surroundings.
• Break the material into short sections to facilitate questions and discussion.
• Create tension slides to help the audience move from one section or point to the next.
• When making key points, explain to the audience why they are important.
Project reports
According to Clements and Gido , the two most common types of project reports are:
Progress /Status reports and Final Reports.
• Accomplishments.
• Future considerations.
• Documents (e.g. project charter, contract, scope document, WBS, quality plan, etc.)
• Author or originator
• Recipients
• Action required
• Comments