Approval Project Manager: Ministry of Electricity (Moe) Republic of Iraq
Approval Project Manager: Ministry of Electricity (Moe) Republic of Iraq
Approval Project Manager: Ministry of Electricity (Moe) Republic of Iraq
Project manager
CONTRACTOR:
DESIGNED BY DATE
CHECKED BY DATE
TITLE:
THE PROCEDURE FOR INSTALLATION OF POWER
Florinel Petrilă November ‘17
AND CONTROL CABLES
APPROVED BY DATE
Gheorghe Ţăranu November ‘17
2|9
1. PURPOSE
This procedure describes the assembling activities for realizing installations of lightning
protection and grounding of the equipment and installations.
2. DOMAIN
It applies at assembling installations of grounding and lightning protection in industrial
domain and tertiary, realized by S.C. ELCOMEX I.E.A. S.A.
3.1.2 The other definitions and abbreviations are according to Chapter 3 of the “Integrated
Management Manual”, code MMI-01, of S.C. ELCOMEX I.E.A. S.A. latest revision.
4. REFERENCE DOCUMENTS
NOTE: The user’s responsibility is to ensure that it is using the valid editions of the
documents, by reading the reference list of the documents.
5. RESPONSIBILITIES
Position / Competence
3|9
5.1. Head of Site
5.1.1. Provides diffusion of this procedure to the subordinate organizational entities and checks its
implementation.
5.1.2. Makes sure that the work will be carried out in conformity with the execution and compliance with
this procedure.
5.1.3. Makes sure that the works will be performed with adequate tools and devices and measuring
instruments with metrological approval in term.
5.1.4. Makes sure that he works will be performed by trained, qualified and authorized staff as needed.
5.4 QC Supervisor
5.4.1. Checks whether the work is performed in accordance with the execution documentation and with
provisions of other applicable documents.
5.4.2. Checks installing activities in accordance with the specific ITP.
5.4.3. Shall confirm the quality of works by signing, dating and stamping related quality records.
5.4.4. Proposes corrective / preventive measures throughout the work, if there are found manifested or
potential nonconformities.
6. PROCEDURE
6.1 Generalities
6.1.1. A grounding installation consists of the following main elements:
a) natural and artificial earthling as well as connection conductors between them;
b) grounding conductors network:
- main conductors;
- branch conductors from main conductors;
- connection conductors between main and earthling conductors.
6.1.2. A lightning protection system consists of:
a) capture elements (rods, stretched conductors, capture networks) and their
connections;
b) descent conductors;
c) earthing system, which can be common with earthing installation socket.
6.1.3. Location, configuration, materials, dimensions, components elevations of the earthing
and lightning protection installations shall be in accordance with the installation documentation.
Common materials are carbon steel protected by hot galvanizing and copper.
6.1.4. Connections of constituents are usually non-demountable. Where demountable joints
are needed (for example, to achieve separation measurements) this will be detailed in the
installation documentation.
4|9
6.1.4.1. The permanent joints of carbon steel components are achieved by overlapping,
welded on three parts as in PS-G00-058.
The permanent joints of copper elements are performed by exothermic
processes according to PS-G00-091.
Demountable connections are done with crimped slippers, mechanical
connectors, overlapping or bolted cover plates by case.
Restoring the protection coatings damaged during the installation is done
according to PTE-ELC-046.
6.1.5. For all parts from installations which are buried in the ground or locks in the
construction, H.W.R. will be made, unless the customer agrees to use other types of records.
5|9
Where there are conductor reserves, taken out of the concrete, for subsequent
connections, the dimensions foreseen in the project will be followed and measures for protection
against damage should be taken.
6.4.3. The apparently mounted conductors will respect the configuration. the type of
supports, the distances between supports and derivations specified in the installation
documentation. Where there are no specifications, the following distances are recommended:
- height above the finished floor of about: 300 mm;
- distance between supports: 0.8 ÷ 1 m;
- in the branch or changes of direction points, the supports are mounted at 0.5 m
from the point;
- the last support on the derivate will be at 150 mm from the ends of derivate.
6.4.3.1. On concrete or brickwork surfaces supports are fixed with anchors / dowels
according to PTE-ELC-045.
6.4.3.2. On metallic structures, supports are fixed by welding according to PS-G00-058
or with screws. Copper conductors can also be attached through exothermic connections
according to PS-G00-091.
6.4.4. Apparently mounted copper conductors are mechanically protected in metallic pipes,
mounted according to IM-ELC-089. In this case, it is mandatory to create a secure electrical
connection between pipe and conductor, at both ends of the pipe.
6.4.5. When passing through walls and / or ceilings, conductors shall be protected in
adequate sized pipe.
6.4.6. Network connecting for grounding conductors is done according to the installation
documentation, but through at least 2 connections located preferable at the ends.
6|9
6.5.5. The earthings for installations of lightning protector are usually shared with the ones
for electrical installations. When installation documentation provides separate outlets, there are
made according to section 6.3.
7|9
7.2 Annexes
7.2.1. Hidden works record, from code FORM-ELC-180, revision 4.
8|9
HIDDEN WORKS QUALITY Page
VERIFICATION REPORT
from
No. Date
Work
Unit BSI / Code
Object Form
Contractor Contract / Work Packet
(WP#)
Work phase to be verified:
Drawings No.
SD No. From
Applied technical
regulations in force:
Conclusions:
DISSEMINATION: Original - at the Project File, copy - to the Client and to the other participants
9|9