a) It is the concealed weld surface on the side opposite from which the welding
was done
b) It is the longitudinal view of a weld that has been split down the middle for
inspection
c) It is the elevation view of a weld that has been cut out to show its cross
section
d) It is the exposed surface of a weld on the side from which the welding was
done
2. How is a fluid service classified in which the potential for personnel exposure is
judge to be significant and a single exposure to a very small quantity, can produce
serious health damages by breathing or body contact, even when prompt
restorative measures are taken
a) M
b) H
c) D
d) N
4. On an impact test. What is the minimum energy requirement for carbon steel ASTM
A53 Grade B (average for 3 specimens-fully deoxidized sheets)?
a) 7 ft-lbs
b) 10 ft-lbs
c) 13 ft-lbs
d) 15 ft-lbs
Adiestramiento para certificación
API 570 “Inspección, reparación y alteración
De Sistemas de tuberías”
5. Name a backing ring that shall not be used under cyclic conditions
6. A NPS 2 Schedule 80 (0.218” wall) is welded into NPS 6 Schedule 40 (0.0289” wall)
header. What size cover fillet weld (tc) is required around the fully penetrated
groove weld of the branch into the header? Express answer to nearest hundredth)
a) 0.15”
b) 0.20”
c) 0.25”
d) 0.22”
7. A NPS 4 Schedule 40 (0.241” wall) branch connection is welded into NPS 6 Schedule
40 (0.0280” wall) header. A 1/4" reinforcing pas is used around the branch
connection. The branch connection is inserted into the header. The material of the
branch and the header is ASTM A105 Grade B. What thickness would be used to
determinate whether heat treatment of this connection is required (Express answer
to nearest hundredth)
a) 0.77”
b) 0.70
c) 0.6”
d) 0.66”
a) 25° F
b) 175° F
c) 50° F
d) None
Adiestramiento para certificación
API 570 “Inspección, reparación y alteración
De Sistemas de tuberías”
9. If a relief valve has a stop valve at the inlet or outlet. Is it permissible to close either
or both these valves while the equipment the relief valve is protecting is in service
11. What would be the minimum temperature without impact testing for a material 2”
thick and on Curve D?
a) 90° F
b) 120° F
c) -20° F
d) -4° F
13. If the stress ratio for a pipe material is 0.55, what temperature reduction can be
taken?
a) 20° F
b) 45° F
c) 108° F
d) None
14. It is required to pull two pieces into alignment while assembling a piping system.
This distorts one of the pieces (puts a bend into one of the pipe sections). The
inspector feels that the assembly (in a strain) would be prejudicial to the equipment.
What should the inspector do?
a) Since any distortion that introduces a strain is prohibited, the details (s)
should be removed and the problem corrected
b) As long as the system will fit together and the flanges and other connections
will make connection, the Inspector should require the problem to be
corrected; however, if it connects without leaks, the Inspector may accept it
c) If the system will not make connection the Inspection should require the
problem to be corrected; however , if it connects without leaks, the Inspector
may accept it
d) Since the pipe details fit up and there appears to be no problem, the system
may be tested and if no leaks the Inspector may accept it
15. In-process examination ___ is used unless additional methods are specified in the
engineering design
a) UT
b) RT
c) VT
d) MT
16. An ASTM A335 Grade P11, NPS 8 Schedule 120 (0.718”wall) pipe is to be welded to
an ASTM A335 Grade P9, Schedule 80 (0.500” wall) pipe. What Brinnell Hardness
number is required after post weld heat treatment?
17. When an entire piping assemble to be heat treated cannot be fitted into the
furnace, it is permissible to heat treat in more than one heat, provided there is at
least ____ overlap between successive heats, and that parts of the assembly outside
the furnace from harmful temperature gradients
a) 6 inches
b) 2 feet
c) 1 foot
d) 3 feet
18. Select the one that may be used only for category D fluid service
a) An excursion
b) An operating condition
c) A design condition
d) A duration
20. An ASTM A53 Grade B NPS 10 pipe operates at 700 psi and 750° F. A blank of ASTME
A561 Grade 60 plate is to be used. The blank is to used between Class 600 flanges.
The corrosion allowance on each side of the blank is 0.14” and applies to both sides.
The ID of the gasket is 9.75”. What thickness of blank is required? Run the answer to
the nearest hundredth
a) 3.000 in.
b) 0.999 in.
c) 1.083 in.
d) 1.263 in.
21. Expose copper and copper alloys to ammonia would cause ______________
a) Sulfidation
b) Embrittlemnt
c) Stress corrosion cracking
d) Hydrogen attack
Adiestramiento para certificación
API 570 “Inspección, reparación y alteración
De Sistemas de tuberías”
22. A fluid that do not operate at high temperature. The fluid is not toxic or flammable.
Exposure to it will not cause damage to human tissue. The design gage pressure is
120 psi and the operating temperature is 100° F. The owner requires metal piping to
be used and he does not designate the category. No cyclic problem will occur. What
category would suit it?
24. Who has the overall responsibility for compliance with ASME B31.3?
a) owner
b) Engineer
c) Jurisdiction
d) Inspector
25. In the equation tm=t+c, what does the value “t” means?
26. Knowing that ERW (electric resistance welds) pipe is used in a piping system. What
longitudinal joint factor (Ej) would be used to calculate the required thickness for
pressure?
a) 0.85
b) 0.9
c) 0.6
d) 0.8
Adiestramiento para certificación
API 570 “Inspección, reparación y alteración
De Sistemas de tuberías”
27. The pressure test for a pneumatic leak test shall be ____% of design pressure
a) 150
b) 50
c) 125
d) 110
29. The joint factor cannot be increase by additional examination on the following
longitudinal pipe joint:
30. As an inspector, you should check threaded joints prior to seal welding them. An
important item to check shall be ______________________________
31. The test pressure of a piping exceeds the vessel test pressure, and it not considered
practicable to isolate the piping from a vessel, both piping and vessel may be tested
together at the vessel test pressure, provided the owner approves and the vessel
test pressure is not less than ____% of the piping test pressure calculated by ASME
B31.3, paragraph 345.4.2 (B)
a) 77
b) 85
c) 67
d) 110
Adiestramiento para certificación
API 570 “Inspección, reparación y alteración
De Sistemas de tuberías”
32. What must a non-toxic flammable liquid have if it is used as a leak testing medium?
33. In elevated temperature service, the life assigned to a piping system for design
purpose, in hours is known as the:
a) Excursion life
b) Estimated life
c) Service life
d) Equivalent life
36. How is a fluid service classified that is nonflammable, nontoxic and not damaging to
human tissue and its gage pressure does not exceed 150 psi and the design
temperature is from -20 degrees through 366 degrees F?
a) N
b) C
c) M
d) D
Adiestramiento para certificación
API 570 “Inspección, reparación y alteración
De Sistemas de tuberías”
37. Some of the standards for components in ASME B31.3, Table 326.1 (e.g, ASME
B16.9, B16.11, and B16.28) state that pressure-temperature ratings are based on
straight seamless pipe. Except as limited in the standards or elsewhere in B31.3,
such a component, made of a material having the same allowable stress as the pipe
shall be rated using not more than ____% of the nominal thickness of seamless pipe
corresponding to the schedule, weight, or pressure class of the fitting, less all
allowances applied to the pipe (e.g., thread depth and/or corrosion allowance)
a) 90.0
b) 87.5
c) 85.0
d) 80.0
a) Caulking weld
b) Seal weld
c) Fissure weld
d) Fillet weld
39. Loads on a piping system that include the weight of the medium transported or the
medium used for test and snow loads or ice loads are examples of _______loads
a) Live
b) Dead
c) Vortex
d) Normal
40. According to ASME B31.3 a Piping Inspector must have ________ experience in
design, fabrication or inspection of industrial pressure piping
a) 10 years
b) 8 years
c) 6 years
d) 5 years
Adiestramiento para certificación
API 570 “Inspección, reparación y alteración
De Sistemas de tuberías”
44. If a full size specimen was used for a pipe of specification A451 CPF8M. What would
be the impact test acceptance criteria?
45. An ASTM A106 Grade B pipe operates at 300 psi and 600° F with the test being
conducted at 400° F. The hydrostatic test pressure required would be:
a) 450 psi
b) 487 psi
c) 900 psi
d) 330 psi
Adiestramiento para certificación
API 570 “Inspección, reparación y alteración
De Sistemas de tuberías”
46. You are checking bolts on flanges and you find 3 bolts in NPS 6, 300# class flange
that will not meet ASME B31.3 bolt length specification. What did you find?
47. Before bolting up flanged joints, the Inspector should check alignment to the design
plane. It should be within ____ in/ft measured across any diameter
a) 1/8
b) 1/16
c) 1/64
d) 1/32
48. What should the inspector do if spot or random examination reveals a defect?
a) Seamless pipe
b) Spiral welded pipe
c) Electric-fusion welded pipe
d) ERW pipe
Adiestramiento para certificación
API 570 “Inspección, reparación y alteración
De Sistemas de tuberías”
50. An NPS 12 seamless pipe made from ASTM A-53 Grade B material operates at 600
psi and 600 degree F. The conditions require that a corrosion allowance of 0.125” be
maintained. Calculate the minimum required thickness for these conditions
a) 0.218”
b) 0.436”
c) 0.330”
d) 0.343”
51. Stress value for material “S” come from table A-1 of ASME B31.3. Select the “s”
value when the material is ASTM A335 Grade P9 and 950°
a) 7400 psi
b) 11400 psi
c) 10600 psi
d) 20000 psi
52. Tapped holes for pressure retaining bolting in metallic piping components shall be
of sufficient depth that the thread engagement will be at least ___ times the
nominal thread diameter
a) 5/8
b) 3/4
c) 1/2
d) 7/8
53. A piping system may be subject to a preliminary test (before hydrostatic test) using
air at no more than ___ psi gage to locate major leaks
a) 15
b) 45
c) 35
d) 25
55. If the design temperature of the system is the same as the hydrostatic test
temperature, the hydrostatic test pressure shall be not less than
__________________________
56. Calculate the required test pressure for an ASTM A216 Grade WCB that operates at
580 psi and 750° F
a) 638 psi
b) 605 psi
c) 654 psi
d) 825 psi
57. In elevated temperature service any condition of pressure and temperature under
which the design conditions are not exceeded is known as the ______________
58. Category fluid service that may be subject to an initial-in-service leak test:
a) Category H
a) Category N
b) Category D
c) Category M
59. The longitudinal weld joint factor Ej, for API 5L ERW(Electric Resistance Welded)
pipe is ____
a) 0.95
b) 1.00
c) 0.85
d) 0.6
Adiestramiento para certificación
API 570 “Inspección, reparación y alteración
De Sistemas de tuberías”
60. Select the hydrostatic leak test value required under these conditions. Temperature
70° F. Round the nearest psi
a) 500 psi
b) 649 psi
c) 600 psi
d) 440 psi
62. An NPS 12 seamless pipe made from ASTM A-53 Grade B material operates at 600
psi and 600 degree F. Calculate the minimum required thickness for these
conditions.
a) 0.218”
b) 0.205”
c) 0.191”
d) 0.442”
63. If a piping system that has a gas or vapor in it (like steam). It is allowed to cool
significantly. What might happen?
64. _________ is known as the heating of metal and holding at suitable temperature
and the cooling at a suitable rate for such purpose as: reducing hardness, improving
machinability, facilitating cold working, producing a desired microstructure, or
obtaining desired mechanical, physical, or other properties
a) Stress-relieving
b) Normalizing
c) Annealing
d) Quenching
Adiestramiento para certificación
API 570 “Inspección, reparación y alteración
De Sistemas de tuberías”
65. ___________ is known as the pressure in a piping system at the most severe
condition of coincident internal or external pressure and temperature (min or max)
expected during service (except for allowances for occasional variations of pressure
or temperature, or both, above operating levels which are characteristics of certain
services)
a) Absolute pressure
b) Excursion pressure
c) Test pressure
d) Design pressure
66. If a piping system has fluids in it and the fluids are heated with the system blocked.
What would happen?
a) The bolt diameter must be 1/8” less than that required for the lower rated
flange
b) They are not acceptable and one flange shall be changed where they both
match
c) The rating of the joint shall not exceed that of the higher rated flange
d) The rating of the joint shall not exceed that of the lower rated flange
68. What Brinnell Hardness is required after post weld heat treatment if an ASTM A335
Grade P9, NPS 8 Schedule 120 (0.79” wall) pipe is to be welded to an ASTM A335
Grade P9, NPS 8 Schedule 120 (0.719”wall)pipe?
a) 225
b) 200
c) 250
d) 241
Adiestramiento para certificación
API 570 “Inspección, reparación y alteración
De Sistemas de tuberías”
69. Socked welded joints should be avoided in any service where _____________ or
___________ occur
70. Where a hardness limit is specified in Table 331.1.1, at least ____% of welds, hot
bends, and hot formed components in each furnace heat treated batch and 100% of
those locally heat treated shall be tested
a) 15
b) 10
c) 20
d) 5
71. An ASTM A53 Grade B pipe with a maximum wall thickness of 0.75” is being
considered for use in a cold service. What minimum temperature can it be used and
not have an impact test?
a) + 15 degrees F
b) + 10 degrees F
c) + 20 degrees F
d) 0 degrees F
72. When fitting up a socket weld joint, the male end is welded in the female socket
with:
73. The casting quality factor, Ec of a A216 carbon steel casting that is not upgraded per
B31.3 paragraph 302.3.3 (c) and table 302.3.3C is ____
a) 0.60
b) 0.75
c) 0.80
d) 0.85
Adiestramiento para certificación
API 570 “Inspección, reparación y alteración
De Sistemas de tuberías”
74. Why would you not use cast iron material in the majority of cases in oil refinery or
chemical plant applications?
75. Clauses in the B31 code are not necessarily numbered consecutively. Such
discontinuities result form:
a) The age of the code and the number of changes that have been made
b) Following a common outline, insofar as practical for all Code Sections
c) Practices followed by all Codes to make the difficult to reproduce
d) No particular logic was followed in the original versions of the Code
76. ASME B31.3 set forth engineering requirements deemed necessary for ___________
and _________ of piping installations
77. If a piping system is subject to a self-limiting (e.g., due to a pressure relieving event)
and its lasts no more than 50 hours at any one time and not more than 50 hours at
any one time and not to more than 500 hours/year, it is permissible to exceed the
pressure rating or the allowable stress for pressure design at the temperature of the
increased condition by not more than ______%
a) 20
b) 15
c) 10
d) 25
Adiestramiento para certificación
API 570 “Inspección, reparación y alteración
De Sistemas de tuberías”
a) Abnormal potential
b) Impact forces
c) Virtual Kinetics
d) Normal dynamism
79. For a liquid thermal expansion relief device which protects only a blocked-in
portion of a piping system, the set pressure shall not exceed the lesser of the system
test pressure or ____% of design pressure
a) 110
b) 120
c) 105
d) 115
80. __________________is responsible for verifying that all required examinations and
testing have been completed and to inspect the piping to the extent necessary to
be satisfied that it conforms to all applicable examination requirements of the ASME
B31.3 Code and the engineering design?
81. As an inspector, what is the best course of action for you to take, if you find a
flanged joint with two gaskets used to make up the joint?
a) Remove the gaskets and replace them with two wrapped with grafoil tape
b) Remove the gaskets and replace them with two spiral wound grafoil filled
gaskets
c) The joint is acceptable as is because the gaskets are fiber
d) Two gaskets are unacceptable, have the joint repaired to take only one gasket
Adiestramiento para certificación
API 570 “Inspección, reparación y alteración
De Sistemas de tuberías”
82. Between carbon steel, Monel, 18Chr-8Ni, Aluminum which one will expand more at
70 degree F to 550 degree F?
a) Aluminum
b) Monel
c) Carbon steel
d) 18Chr-8Ni
83. Before bolting up flanged joints, the Inspector should check alignment of the flange
bolt holes. They shall be aligned within ____ inc maximum offset
a) 1/32
b) 9/64
c) 1/16
d) 1/8
84. When components of a piping system are joined by welding, the thickness to be
used in applying the heat treatment provisions of ASME B31.3, table 331.1.1 shall
be:
85. Below what temperature is impact testing required, for an ASTM A106 Grade B pipe
0.75 in. thick, the nominal pressure stress is 8000 psi and the design temperature is
-20°F?
a) -93° F
b) -20° F
c) 15° F
d) 108° F
Adiestramiento para certificación
API 570 “Inspección, reparación y alteración
De Sistemas de tuberías”
86. What is the temperature required to weld an ASTM A106 Grade B, NPS 8, Schedule
40 (0.322” wall) pipe to an ASTM A335 Grade P9, NPS 8 Schedule 40 (0.322”
wall)pipe?
a) 350° F
b) 300 °F
c) 175° F
d) 50° F
87. For normal fluid service ______ of piping weld (circumferential and miter groove
welds) shall be examined by random radiography
a) 3%
b) 10%
c) 5%
d) 33%
88. What is the minimum requirement of weld length to extent radiography considering
longitudinal welds?
a) 4
b) 12
c) 9
d) 6
a) Displacement
b) Post stress
c) Hot spring
d) Cold spring
90. ________ is the minimum wall schedule that can be sued in a male threaded joint in
normal fluid service, carbon steel (notch-sensitive) and NPS 1.5 and smaller
a) Sch 40
b) Sch 80
c) Sch 160
d) Sch 10
Adiestramiento para certificación
API 570 “Inspección, reparación y alteración
De Sistemas de tuberías”
91. The use of slip-on flanges should be ____________where many large temperature
cycles are expected particularly if the flanges are not insulated
92. Two service piping systems are connected. Both operate at 300 degrees F. One of
them operates at 230 psi and other operates at 550 psi. The system is separated by
a block valve. What determinates the rating of the block valve?
a) Their must be two valves separating the two services, one to satisfy each
service
b) The valve segregating the two services shall be rated for the less severe
service
c) The services must be separated by double valves rated at the less severe
service
d) The valve segregating the two services shall be rated for the more severe
service
93. Determinate the coefficient Y, for a NPS 10 pipe made from ASTM A53 Grade B
carbon steel that is to be checked for thickness (t). The pipe operates at 975 degrees
F and the existing thickness is 0.29”.
a) 0.6
b) 0.7
c) 0.4
d) 0.5
94. Piping not protected by a pressure relieving device, or that can be isolated from a
pressure relieving device, shall be designed for at least the
_______________________
a) Fissure weld
b) Face weld
c) Tack weld
d) Seal weld
97. An NPS 4 seamless pipe made from ASTM A106 Grade A material operates at 300
psi and 400 degrees F. The pipe must cross a small ditch and it must be capable of
supporting itself without any visible sag. A piping engineer states that the pipe must
have a structural tmin of at least 0.25” thick just to support itself and the liquid
product. He also states that a 0.10” corrosion allowance must be included.
Determinate the thickness required for the pipe
a) 0142”
b) 0.292”
c) 0.391”
d) 0.350”
98. How is called a fillet weld whose size is equal to the thickness of the thinner
member joined?
99. A piping joint that for the purpose of mechanical strength or leak resistance, or
both, in which the mechanical strength is developed by threaded, grooved, rolled,
flared, or flange pipe end; or by bolts, pins, toggles or rings; and the leak resistance
is developed by threads and compounds, gaskets, rolled ends, caulking or machined
and mated surface is known as:
a) Fused joint
b) Mechanical joint
c) Juke joint
d) Bonded joint
a) Flanged joints
b) Expanded joints
c) Welded joints
d) Tap joints
101. Compatibility of materials with the service and hazard from instability of contained
fluids
103. The minimum time that a leak test must be maintained (all joints and connections
shall be examined for leaks) is _________
a) 60 minutes
b) 10 minutes
c) 30 minutes
d) 45 minutes
Adiestramiento para certificación
API 570 “Inspección, reparación y alteración
De Sistemas de tuberías”
104. If it becomes necessary to use a “sensitive leak test” method, the test pressure shall
be at least the lesser of ______ psi or_____% of the design pressure
a) 20,20
b) 17,23
c) 15,25
d) 10, 33
105. A NPS 10 ASTM A335 Grade P9 has to be changed by adding and NPS 6 ASTM A335
Grade P9 branch connection. The weld(s) were post weld heat treated. When
should this section of piping be leak tested or should it be leak tested?
a) 2
b) 5
c) 8
d) 10
107. If a full size specimen were used for a pipe of ASTM A451 CPF8M. What would be
the impact test acceptance criteria?
a) 37 mm lateral expansion
b) 15 ft-lbf
c) 0.015 in. lateral expansion
d) 10 ft-lbf
108. A pipe of P-No 1 material has a minimum specified tensile strength of 70 ksi and is
fully deoxidized. What would be the ft-lbf values for the average of three specimens
and the minimum of one specimen if a 2/3 size test bar was used?
a) 44,22
b) 22,16
c) 15,12
d) 10,8
Adiestramiento para certificación
API 570 “Inspección, reparación y alteración
De Sistemas de tuberías”
109. Prior to initial operation each piping installation, including components and
workmanship shall be examined in accordance with ASME B31.3, paragraph 341.
When should examination of P-Numbers 3, 4 and 5 materials be carried out?
110. Flattering of a bend, the difference between maximum and minimum diameters at
any cross section, shall not exceed ____% on nominal outside diameter for internal
pressure
a) 10
b) 5
c) 8
d) 12
111. Stop valves are allowed on the inlet and outlet side of a pressure relieving device, as
long as:
113. What can be caused by low operating temperatures, including the chilling effect of
sudden loss of pressure on highly volatile fluids or in alloy piping, the failure to
properly post weld heat after welding?
114. The __________ has the responsibility of determining which Code Section is
applicable to piping installations, i.e., B31.1, B31.3, etc?
a) Jurisdiction
b) Owner
c) Inspection
d) Engineer
115. Slip-on flanges shall ____________ when the service is erosive, if there is crevice
corrosion present, or cyclic loadings occur
a) Not be used
b) Be bolted together with machine bolts
c) Be bolted together with double nutted machine bolts
d) Be double welded
116. Determinate the thickness required for a blank between two NPS 8, 150 pound class
flanges. The maximum pressure in the system is 285 psi at 100 degrees F. A
corrosion allowance 0f 0.10” is required. The inside diameter of the gasket surface is
8.25”. The blank is ASTM A-285 Grade C material.
a) 0.545”
b) 0.552”
c) 0.530”
d) 0.584”
117. Bolting having not more than ____ ksi specified minimum yield strength shall not be
used for flanged joints rated ASME B16.5 Class 400 and higher
a) 40
b) 35
c) 30
d) 45
Adiestramiento para certificación
API 570 “Inspección, reparación y alteración
De Sistemas de tuberías”
118. A thicker wall pipe is joined to a thinner wall pipe. The thicker pipe is taper bored to
facilitate the fit up. What is the maximum slope of the taper bore?
a) 30 degrees
b) 25 degrees
c) 20 degrees
d) 15 degrees
119. How many specimen bars shall have each set of impact test specimens?
a) 3
b) 2
c) 4
d) 5
120. __________ is considered to furnish no strength and is only used to prevent leakage
of threaded joints
a) Seal weld
b) Fillet weld
c) Butt weld
d) Tack weld
a) If the incomplete penetration is 1/32” or less (or ≤ Tw) deep, he may accept
b) If the incomplete penetration is 1/32” or less (or ≤0.2 Tw) deep, he may accept
c) He may not accept the incomplete penetration
d) If the incomplete penetration is 1/16” or less (or ≤0.2 Tw) deep, he may accept
Adiestramiento para certificación
API 570 “Inspección, reparación y alteración
De Sistemas de tuberías”
123. How is called a preplaced filler metal which is completely fused into the root of a
welded joint and becomes part of the weld?
a) A preplaced ligament
b) A consumable insert
c) A depleted appendage
d) A caulked joint
124. The requirements of the lasts edition of ASME Code Section B31.3 and any
subsequent Addenda:
a) Are retroactive and all equipment installed per earlier additions must be
upgraded
b) Are not retroactive & all equipment installed per early
c) May be used without regard to the acceptability of Code revisions to the
jurisdiction
d) Must be followed explicitly as soon as the latest edition is issued
125. If a socket welds is larger than NPS____ shall not be used under severe cyclic
conditions
a) 2
b) 1.5
c) 3/4
d) 1
126. A 1/3 size impact test bar was used instead of full size bar during an impact testing
of an A358 Grade 304 pipe. The design temperature is 50° F below the minimum
temperature requiring impact testing. At what temperature must the impact be
performed?
a) _50°F
b) -510°F
c) -475° F
d) -20° F
Adiestramiento para certificación
API 570 “Inspección, reparación y alteración
De Sistemas de tuberías”
127. Determinate the coefficient Y, for a NPS 10 pipe made from ASTM A106 Grade B
carbon steel that is to be checked for thickness (tm). The pipe operates at 900
degrees F and the existing thickness is 0.29”.
a) 0.6
b) 0.5
c) 0.7
d) 0.4
129. Double welded slip-on flanges should be ____ between the welds for fluid services
that required leak testing of the inner fillet weld, or when fluid handled can diffuse
into the enclosed space, resulting in possible failure
a) Scored
b) Machined
c) Vented
d) Sanded
Adiestramiento para certificación
API 570 “Inspección, reparación y alteración
De Sistemas de tuberías”
PREGUNTAS PRACTICAS
ASME B16.5
Adiestramiento para certificación
API 570 “Inspección, reparación y alteración
De Sistemas de tuberías”
a) + 5mm
b) -0.12 mm
c) +0.12 in.
d) -0.0 in.
2. How much time does the pressure test take for an NPS 2 flanged fitting?
a) 1 minute
b) 10 minutes
c) 180 sec
d) 120 sec
a) Size
b) Trademark
c) Rating designation
d) Temperature
a) A216 Gr WCC
b) A351 Gr CK20
c) A217 Gr C5
d) A217 Gr WC6
a) 3.5
b) 1.14
c) 2.2
d) 2.4
Adiestramiento para certificación
API 570 “Inspección, reparación y alteración
De Sistemas de tuberías”
6. Which of the following applies when two flanges in a flanged joint do not have the
same pressure-temperature rating?
7. Low strength bolting has specified minimum yield strength of not more than:
a) 40 Ksi
b) 30 Ksi
c) 60,00 Ksi
d) 30,000 Ksi
a) Bolting
b) Joint compound
c) Piping
d) Welds
9. What would be the maximum working pressure permitted for an A351 Grade CF3
casting, class 600 that is to be used at a temperature of 1000° F?
a) 1400 psi
b) Cannot be used over 800° F
c) 710 psi
d) None of above
10. The inside diameter of a class 400 NPS 14 flanged fittings is _________
a) 12.88 in.
b) 13.22 in.
c) 11.38 in.
d) 14.00 in.
Adiestramiento para certificación
API 570 “Inspección, reparación y alteración
De Sistemas de tuberías”
11. The diameter of the bolt holes for a NPS 6 flange of class 400 is _______
a) 1-1/8 in.
b) 2.88 in.
c) 1.00 in.
d) 5/8 in.
12. The maximum gasket contact surface finish for a tongue and groove and small male
and female flange facing is:
a) 125 µin.
b) 63 µin.
c) 250 µin.
d) 500 µin.
a) 500
b) 150
c) 1500
d) 500
a) Bolt loosening
b) Nothing
c) Flange rotation
d) Develop leakage problems
15. What gasket should be used when class 300 steel flanges are bolted to class 250
cast iron flanges?
16. A flanged fitting, class 300, NPS 10 is measured at one area to be 0.415 in. thick. Is
this an acceptable thickness?
a) No
b) Yes
c) No, should be at least 0.440 in.
d) No, should be at least 0.500 in.
17. What is the largest diameter of the sub-minimum thickness that is permitted using
the data from #16?
a) 1.200 in.
b) 0.782 in.
c) 0.480 in.
d) 0.500 in.
18. Using the data in # 16, how far apart must areas of sub-minimum thickness be?
a) 6.128 in.
b) 7.000 in.
c) 3.913 in.
d) 3.226 in.
19. The maximum depth and radial projection of an imperfection that is deeper than
the bottom of the serrations for a NPS 16 flange is ________
a) 0.38 in.
b) 0.50 in.
c) 0.18 in.
d) 0.28 in.
20. What is the shell test pressure for a flanged fitting of specification A217 Gr WC9 of
Class 600 that will operate at 800° F?
a) 2275 psi
b) 1500 psi
c) 1015 psi
d) 2250 psi
Adiestramiento para certificación
API 570 “Inspección, reparación y alteración
De Sistemas de tuberías”
21. The minimum thickness of a NPS 12 flange for Class 900 is _________
a) 4.88 in.
b) 1.500 in.
c) 3.120 in.
d) 5.00 in.
22. The minimum wall thickness of a Class 150 flanged fitting, size NPS 6 is ________
a) 0.51 in.
b) 0.92 in.
c) 0.38 in.
d) 0.28 in.
a) 4
b) 6
c) 8
d) 3
24. High strength bolting has allowable stresses not less than those for _____________
a) None required
b) As required by the purchaser
c) 1.5 time the 100°F Class rating
d) 1.1 time the Class designation
26. Flanged joints and flanged fittings may be subjected to a system hydrostatic test at a
pressure of 1.5 times the 100° F rating rounded to the ___________________
1 D,
2 A,
3 D,
4 C,
5 D,
6 C,
7 B,
8 A,
9 B,
10 B,
11 C,
12 A,
13 D,
14 D,
15 B,
16 B,
17 B,
18 C,
19 C,
20 D,
21 C,
22 D,
23 A,
24 C
25 A,
26 A,
Adiestramiento para certificación
API 570 “Inspección, reparación y alteración
De Sistema de tuberias”
PREGUNTAS PRACTICAS
ASME SECCION IX
Adiestramiento para certificación
API 570 “Inspección, reparación y alteración
De Sistema de tuberias”
1. Where can you find the acceptance standards used to qualified welders by
radiographs?
a) ASME Section IX
b) ASME Section V
c) The referencing code
d) ASME Section VII
a) Essential variables
b) Nonessential variables
c) Range for 1 & 2 above
d) All of the above
3. Wiich of the following are the tests used to qualify a normal WPS?
a) Nothing
b) The WPS must be requalified
c) The Welding Engineer notes the charge on the WPS.
d) None of the above
a) Electrodes
b) Flux
c) Base Metal
d) Joints
Adiestramiento para certificación
API 570 “Inspección, reparación y alteración
De Sistema de tuberias”
a) WPS
b) WQR
c) PQR
d) WPQ
8. If you are performing a charpy V-notch test on a PQR specimen. You are performing
a/an _______________
a) Thickness test
b) Impact Test
c) Brinell hardness test
d) Bend test
9. A welder making a groove weld using the SAW process on P1 materials may be
qualified using ______________
a) Visual examination
b) PT examination
c) Radiography
d) MT examination
a) Fillet welds
b) Overhand welds
c) Stud welds
d) All of the above
11. What is the earliest Edition of Section IX recognized by the current edition?
a) 1958
b) 1987
c) 1992
d) 1962
a) Ductility
b) Tensile strength
c) Notch toughness
d) All of above
Adiestramiento para certificación
API 570 “Inspección, reparación y alteración
De Sistema de tuberias”
a) P-1-P-11 to P-1-P-11
b) P-21 to P-21 only
c) P-8 to P-8
d) Any P-21 thru P-25
14. If a welder qualified with the SMAW process on Jan. 1, 1997 and last welded with
SMAW on March 15, 1997. What is the latest date he could weld within the
qualification period?
a) Inspector
b) Welder
c) Manufacturer or contractor
d) All of the above
17. For the SMAW process ____________________ is an essential variable for the WPS.
a) Groove design
b) Post Weld heat treatment
c) Root Spacing
d) Method of cleaning
18. For the SAW process ____________________ is an essential variable for the WPS.
a) Preheat maintenance
b) Filler metal diameter
c) Addition or deletion of peening
d) Flux/wirw classification
Adiestramiento para certificación
API 570 “Inspección, reparación y alteración
De Sistema de tuberias”
19. The purpose of the WPS and PQR is to determine that ________________________
20. The record of procedure, welder and welding operator qualification must be available
to the _________________.
a) Manufacture
b) Inspector
c) Foreman
d) Welder
22. When a tensile specimen breaks in the base metal outside of the weld or fusion line,
the strength recorded may be _____ below the specified tensile and be accepted.
a) 0.5%
b) 5%
c) 3.5%
d) All of the above
23. New Welding Procedure Specifications must meet the _________ Edition and
addenda of Section IX.
a) 1995
b) 1962
c) Current
d) 1986
24. If a welder depositing 1/2" of weld metal with at least 3 passes using the SMAW
process is qualified to deposit up to ___________ of weld metal.
a) 1”
b) 1/2“
c) 8”
d) Max to be welded
Adiestramiento para certificación
API 570 “Inspección, reparación y alteración
De Sistema de tuberias”
25. When a welder qualifies with double welded groove weld, the welder is qualified to
weld?
26. Which of the following is a reason for a welding foreman to request the requalification
of a welder?
27. When a welder qualifies by making a groove weld on pipe with an O.D of 3/4" in the
5G position, the welder is qualified to weld groove welds in:
a) ASME specification
b) “F” number
c) AWS class
d) SFA
30. Which of the following is an essential variable for welder qualification with the SMAW
process?
a) Electrode diameter
b) P-number
c) Peening
d) Base metal thickness
Adiestramiento para certificación
API 570 “Inspección, reparación y alteración
De Sistema de tuberias”
31. A welder qualifying with plate fillet welds in the 3F and 4F positions is qualified to weld
groove welds in plate in the ________________ positions.
a) Essential variables
b) Project description & NDE methods
c) Nonessential variables
d) Full range of variables permitted on the WPS
34. Welder performance qualification records must describe all the _______________
variables specified:
a) Brazing
b) Nonessential
c) Essential
d) Essential & nonessential
35. How may the ferrous weld metal chemical composition be designated with?
a) “A” number
b) Page number
c) Welder I.D
d) “P” number
36. Who shall conduct the test required by Section IX to qualify the WPS used during the
construction, alteration, or repair?
a) Inspector
b) Manufacture or contractor
c) Welder or welding operator
d) All of the above
Adiestramiento para certificación
API 570 “Inspección, reparación y alteración
De Sistema de tuberias”
37. Guided-bend specimens shall have no open defects in the weld or heat effected zone
exceeding _____________ measured in any direction on the convex of the specimen
after bending.
a) 3/32”
b) 1/8”
c) 1/16”
d) None of the above
38. A welder qualifying with a groove weld in plate in the 4G position is qualified to weld
groove welds in plate and pipe over 24” O.D in the __________________ positions.
a) Overhead
b) Flat & horizontal
c) Flat & overhead
d) Horizontal
40. Tensile test have been performed on two specimens with the following characteristics
and result: Specimen #1, 0.76 in. wide, 0.52 in. thick and ultimate tensile strength of
75,265 psi. Specimen #2, 0.75 in. wide, 0.50 in. thick and ultimate tensile strength of
90,236 psi. What was the tensile machine load for each specimen?
RESPUESTA ASME IX
1. A 21. A
2. D 22. D
3. B 23. C
4. B 24. D
5. C 25. A
6. C 26. D
7. D 27. C
8. B 28. D
9. C 29. B
10. A 30. B
11. D 31. D
12. C 32. A
13. D 33. D
14. D 34. C
15. B 35. A
16. C 36. B
17. B 37. B
18. D 38. C
19. A 39. A
20. B 40. D
Adiestramiento para certificación
API 570 “Inspección, reparación y alteración
De Sistema de tuberias”
PREGUNTAS PRACTICAS
ASME SECTION V
Adiestramiento para certificación
API 570 “Inspección, reparación y alteración
De Sistema de tuberias”
1. What is the maximum prod spacing permitted when using the MT prod technique?
1. 3 Plg
2. 8 Plg
3. 1 Foot
4. 6 Plg
2. The sulfur content of a penetrant is measured to be less than .0025g. This material is
acceptable for use on:
1. Nickel-base alloys
2. Carbon steel
3. Ferritic steel
4. All of the above
3. Lipophilic emulsification time shall not pass the levels _____ minutes, unless other times have
been qualified by actual test.
1. 5
2. 10
3. 15
4. None of the above
4. Dry particle magnetic test shall not be performed if the surface temperature of the part
exceeds the temperature__?
1. 500 F
2. Those set by the particle manufacturer.
3. 60 F
4. 50 F
5. Prior to examination using PT, each adjacent surface shall be cleaned within at least ___ of
the area to be examined.
1. 1"
2. 1.5"
3. 2"
4. 3"
1. Densitometer
2. Step Wedge Comparison Strip
3. Light Meter
4. Transmission monitor
Adiestramiento para certificación
API 570 “Inspección, reparación y alteración
De Sistema de tuberias”
8. For the MT Prod technique which is the minimum amp/in. of current for a section thickness of
1/2" is?
1. 1000 amp/in.
2. 90 amp/in.
3. 125 amp/in.
4. 200 amp/in.
9. When a PT cannot be conducted between 50°- 125°F, what must be done, per ASME V?
10. The correct filmside IQI designation for a weld that is 1.56" thick Is___?
1. 30
2. 50
3. 12
4. 8
11. Surfaces may be dried and clean after preparation for PT examination by:
1. Normal Evaporation
2. Forced Hot Air
3. Forced Cold Air
4. All of the above
12. What is the minimum number of IQI's required for the following:
13. When using fluorescent PT, the examiner shall be in a darkened area for at least___minutes
prior to performing the exam.
1. 7
2. 10
3. 9
4. 5
15. One procedure requirement for conducting PT is to address the processing details is?
1. Post-examination cleaning
2. Pre-examination cleaning
3. Apply the penetrant
4. All of the above
16. An MT field strength indicator is composed of ___ low carbon steel pie sections, fyrnace
brazed together.
1. 2
2. 6
3. 10
4. 8
1. carbon steels
2. Ferritic stainless steels
3. Austenitic stainless steels
4. None of the above
1. before
2. after
3. at least once during
4. through out
Adiestramiento para certificación
API 570 “Inspección, reparación y alteración
De Sistema de tuberias”
19. Black light intensity shall be measured prior an examination with a ____ when
conducting fluorescent PT.
20. A dark image of the "B" on a lighter background for an examination must be ____
1. Acceptable
2. Rejectable
3. Sometimes rejectable
4. None of the above
1. ASME VIII
2. ASME V
3. The referencing Code section
4. The written procedure
22. The accuracy of a piece of magnetizing equipment that is equipped with an ammeter shall
be verified at least how many times__?
1. Each year
2. Each two years
3. When possible
4. Evory 6 months
23. The ammeter on magnetic test equipment shall not vary by more than ___of full scale.
24. Wire diameter 0.032 in. is common to which of the following ASTM sets:
1. A
2. B
3. C
4. None of the above
25. Direct current yokes may be used for detecting ___discontinuities of what kind.
Adiestramiento para certificación
API 570 “Inspección, reparación y alteración
De Sistema de tuberias”
1. Near surface
2. Surface
3. Volumetric
4. Any
26. Shims are normally made from which of the following metals:
1. NDE technician
2. Minimum light intensity
3. Prod manufacturer
4. Last calibration date
29. How many total liquid penetrant techniques for examinations are listed in ASME V?
1. 4
2. 6
3. 2
4. 1
30. When using fluorescent penetrant for the PT method the examiner shall be in the darkened
area for at least _ prior to performing the examination.
1. 5 minutes
2. 1 minute
3. 15 minutes
4. None of the above
31. When performing a radiographic test of a weld on a vessel seam, where should the lead
letter B be placed?
Adiestramiento para certificación
API 570 “Inspección, reparación y alteración
De Sistema de tuberias”
32. Which of the following technique is commonly used to detect both surface and near surface
flaws?
33. Which of the following applies when qualifying a penetrant procedure lower than 50°F?
1. Qualifying at a temperature lower than 50°F qualifies from the lower temperature to 50°F
2. Qualify at the upper and lower ranges to be used at the lower temperature
3. Qualifying at a temperature lower than 50°F qualifies from the lower temperature to 125°F
4. None of the above
35. Which of the following is not usually found in a radiographic report after a test has been
perfomed?
37. Which of the following inspection techniques require visual examination of the test specimen
during testing?
1. Radiography testing
2. Ultrasonic testing.
3. magnetic particle
4. Eddy current
Adiestramiento para certificación
API 570 “Inspección, reparación y alteración
De Sistema de tuberias”
38. A single film technique was used to make a radiographic test using a Cobalt-60 source. The
minimum permitted density in the area of interest is:
1. 4.0
2. 1.8
3. 2.0
4. 1.3
1. Compensate for the excess thickness through the weld relative to the base material when the
IQI is placed adjacent to the weld
2. Level the piece being radiographed
3. Compensate for the excess thickness through the base metal
4. Change the density from 2.0 to 2.6
40. A ____is a device used to determine the necessary sensitivity of a radiograph for the correct
examination.
RESULTADO
30. 1
1 2.
31 3.
2 4. 32 2.
3 4. 33 1.
4 2. 35 3.
5 1. 36 2.
6 2. 37 3.
7 2. 38 3.
8 2. 39 1.
9 1. 40 3.
10 1.
11 4
12 a) 3, b)1
13 4.
14 2.
15 4.
16 4.
17 3.
18 2.
19 3.
20 1.
21 3.
22 1.
23 1.
24 3.
25 2.
26 2.
27 2.
28 2.
29 2.
Adiestramiento para certificación
API 570 “Inspección, reparación y alteración
De Sistema de tuberias”
Adiestramiento para certificación
API 570 “Inspección, reparación y alteración
De Sistemas de tuberías”
PREGUNTAS PRACTICAS
API 570
Adiestramiento para certificación
API 570 “Inspección, reparación y alteración
De Sistemas de tuberías”
a) 10 inches, 20
b) 12 feet, 10
c) 12 inches, 10
d) 10 feet, 10
a) Second change in flow direction past the injection point, or 25 feet beyond
the first change in flow direction whichever is less
b) Second change in flow direction past the injection point, or 25 feet beyond
the first change in flow direction whichever is greater
c) Second change in flow direction past the injection point, or 25 inches beyond
the first change in flow direction whichever is less
d) Second change in flow direction past the injection point, or 25 inches beyond
the first change in flow direction whichever is greater
9. If a coating of coke is found on the interior of a large pipe off a reactor on a Fluid
Catalytic Cracking Unit. What course of action should be followed?
10. Both the stagnant end and the connection to an active line of a deadleg should be
monitored. In a hot piping system, why does the high point of a deadleg corrode
and need to be inspected?
11. What should the inspector do, if external or internal coatings or refractory liners on
a piping circuit are not in good condition?
a) 8
b) 5
c) 15
d) 10
Adiestramiento para certificación
API 570 “Inspección, reparación y alteración
De Sistemas de tuberías”
13. Select thickness measurement locations (TMLs) within the injection point circuits
subject to localized corrosion according to the following guidelines. Select the one
that DOES NOT belong
14. API 570 covers inspection, repair, alteration, and rerating procedures for metallic
piping systems that ____________________
15. What should the inspector do, when suspects or is advised that specific piping
circuits may be susceptible to environmental cracking?
16. Who shall be responsible to the owner-user for determining that the requirements
of API 570 for inspection, examination, and testing are met
a) Piping engineer
b) Inspector
c) Repair Organization
d) Operating Personnel
17. Protective equipment shall be worn when required by either of the following two
entities
19. When injection points subject to accelerated or localized corrosion may be treated
as __________________
22. Depending of the climatic area, corrosion under insulation may require different
programs. Which of the following may require a very active program?
23. Some of the classes of piping systems that are excluded or optional for coverage
under API 570 are listed below. Which one is a mandatory included class?
a) Water
b) Catalyst lines
c) Steam
d) Boiler feed water
26. API 570 was developed for the petroleum refining and chemical process industries
27. Soil-to-air (S/A) interfaces for buried piping are location where localized corrosion
may take place. If the buried part is excavated for inspection, how deep should be
excavation be to determinate if there is hidden damage?
a) 12 to 18 inches
b) 6 to 12 inches
c) 12 to 24 inches
d) 6 to 18 inches
Adiestramiento para certificación
API 570 “Inspección, reparación y alteración
De Sistemas de tuberías”
28. One of the item listed is not a qualification for an Authorized Piping Inspector. Select
the one that does not belong in this list
29. What should the inspector do, if an environmental cracking is detected during
internal inspection of pressure vessel?
30. When a deadleg is no longer in service, what is the best thing to do?
31. The combination of corrosion and erosion involve significantly greater metal loss
that can be expected from corrosion or erosion alone. Where does this type of loss
occur?
33. API ____ be used as a substitute for the original construction requirements
governing a piping system before it is placed in-service
a) Shall not
b) should
c) may
d) can
34. One of the items listed below is not a specific type of an area of deterioration. Pick
the one that does not belong in this list
a) Rectifier performance
b) Injection point
c) Deadlegs
d) Environmental cracking
35. When may the inspector give the authorization for alteration work to a piping
system?
36. The person who shall maintain appropriate permanent an progressive records of
each piping system covered by API 570 is the _______________
a) Jurisdiction
b) Owner-user
c) Examiner
d) Inspector
Adiestramiento para certificación
API 570 “Inspección, reparación y alteración
De Sistemas de tuberías”
37. You must determine the minimum thickness of a pipe unknowing the materials, if
computations must be made, what can you do as an inspector or the piping
engineer to establish the minimum thickness?
38. The fasteners and gaskets should be examined to determine whether they meet the
material specifications. What is the procedure for it?
39. A new piping system has just been installed. It is completely new without any
information to establish a corrosion rate. Also, information is not available on
similar system. Knowing this you decide to start up the system and leave for later
NDT. How long do you allow the system to stay in service before you take your first
thickness readings?
a) 12 months
b) 6 months
c) 1 month
d) 3 months
Adiestramiento para certificación
API 570 “Inspección, reparación y alteración
De Sistemas de tuberías”
40. All process piping systems must be categorized into different classes. On what are
the classifications selection based?
41. Using a typical digital thickness gages may have some problems measuring thickness
less than ______ inches.
a) 0.2188
b) 0.1562
c) 0.1250
d) 0.2188
42. Piping fabricated of or having components of 300 series stainless should be tested
with:
a) Steam condensate
b) Water with a pH of 4
c) Water with a chloride content of less than 400 ppm chlorides
d) Water with a pH of 6
a) Hydrocarbon
b) Steam
c) Air
d) Water
44. Preheating to not less than ____ degrees F may be considered as an alternative to
post weld heat treatment for alterations or repairs of P-1 piping initially post weld
heat treated as a code requirement (may not be used if the piping was post weld
heat treated due to environmental cracking prevention)
a) 150
b) 300
c) 200
d) 350
Adiestramiento para certificación
API 570 “Inspección, reparación y alteración
De Sistemas de tuberías”
45. When a leak sealing fluid (pumping) is used for a temporary leak seal repair. The
inspector do NOT need to ____________________________
46. Which of the items listed below may be used to test repairs to coatings on buried
piping?
47. If a buried piping system that is not cathodically protected has to have an inspection
interval set. The soil resistivity is checked and found to be 3400 ohm-cm. What
interval would you set as an inspector?
a) 2.5 years
b) 7.5 years
c) 10 years
d) 5 years
49. Piping stress analysis is done during the system’s original design. How can the
inspector make use of stress analysis information?
a) The inspector should use this information to evaluate the need for conducting
additional piping stress analysis
b) It can be used to make sure the piping system was originally evaluated and
designed correctly
c) It can be used to concentrate inspection efforts at locations most prone to
fatigue or creep damage, and to solve vibration problems
d) An inspector cannot use this information. It is only meaningful to a piping
engineer
50. When corrosion product buildup is noted during an external visual inspection at a
pipe support contact area lifting off such supports may be required for inspector.
When doing this, care should be:
a) One half the remaining life determined from corrosion rate or the maximum
interval of 5 years whichever is shorter
b) One fourth the remaining life determined from corrosion rate or the
maximum interval of 10 years whichever is shorter
c) One half the remaining life determined from corrosion rate or the maximum
interval allowed by API 570 in table 6-1, whichever is shorter
d) One quarter the remaining life determined from corrosion rates or the
maximum interval allowed by API 570 in table 6-1, whichever is shorter
52. A piping service is being designed by a piping engineer with high potential
consequences if a failure occurs, i.e., a 350 psi natural gas line adjacent to a high
density population area. What else should he consider doing to prevent
unanticipated situations?
a) That are flammable but do not significantly vaporize when the leak and are
not located in high-activity
b) With the highest potential of resulting in an immediate emergency if a leak
occurs
c) That is not class 1 and 2
d) That is not flammable and pose no significant risk to populated areas
54. The design temperature of a piping system component is the temperature at which,
under the coincident pressure, the _______________________ is required
55. Piping systems that are known to have a remaining life over ____ years or that are
protected against external corrosion need to not have insulation removed for the
periodic external inspection.
a) 20
b) 15
c) 5
d) 10
a) Imperfection
b) Indication
c) Division
d) Breach
57. What is the maximum size of a small repair patch that may be sued to cover the
corroded are on a 14"?
a) 6.5”
b) 3.5”
c) 7”
d) 6”
Adiestramiento para certificación
API 570 “Inspección, reparación y alteración
De Sistemas de tuberías”
58. When repairing a piping by join a new or replacement section to an existing system.
A pressure test most be performed to the final closure weld. If it is not practical,
several requirements shall be satisfied. One of following is NOT a requirement:
a) Any final closure butt weld shall be of 100% radiographic quality; or angle-
beam UT may be used, provide the appropriate acceptance criteria is
establish
b) The new or replacement piping is pressure tested
c) The closure weld is a full-penetration fillet weld between a weld neck flange
and standard piping component or straight sections of pipe of equal diameter
and thickness, axially aligned, and of equivalent materials. For design cases up
to Class 300 and 500° F, slip-on flanges are acceptable alternative.
d) MT or PT shall be performed on the root pass and the completed weld. Fillet
welds must have PT
59. The inspection of a buried process piping (not regulated by DOT) is different from
other process piping inspection because ___________________________________
a) The insulating effect of the soil increase the possibility of more internal
corrosion
b) Significant external deterioration can be caused by corrosive soil conditions
c) Internal corrosion must be controlled by internal coatings
d) Internal corrosion has to be controlled by cathodic protection
a) Pressure tests are normally required after are alterations and major repairs
b) Pressure tests are normally required only as specified by the owner-user
c) Pressure tests are normally required after major and minor repairs
d) Pressure tests are normally required after are alterations and any repairs
61. The _____________ must give approval for any on-stream welding
a) Analyst
b) Examiner
c) Jurisdiction
d) Owner-user
Adiestramiento para certificación
API 570 “Inspección, reparación y alteración
De Sistemas de tuberías”
62. What shall be used in lieu of a pressure test when it not practical or necessary?
a) Nondestructive examination
b) Vacuum visual examination
c) NBE
d) NPS
63. A piping system has a damaged or corroded area on it. The piping engineer designed
a full encirclement welded split sleeve as a temporary repair. When should a
permanent repair be made?
64. Buried piping also may be surveyed for integrity by removing the line from service
and performing a leak test. This inspection method typically involves pressurizing
the line with a _______, allowing time for the _______ to diffuse to the surface, and
surveying the buried line with gas-specific detector to detect the __________.
65. When a pin hole leak is detected in a weld during an on-stream inspection of a
piping system. Which of the following may be a permissible temporary repair?
68. According to API 570 when some welds in a piping system has been subjected to
radiography according to ASTM B31.1:
a) Will not meet random radiograph requirements, and will not perform
satisfactorily in-service even though hydrotested
b) Will meet random radiograph requirements, and will not perform
satisfactorily in- service after a hydrotested
c) Will not meet random radiograph requirements, but will still perform
satisfactorily in-service after being hydrotested
d) Will meet random radiograph requirements, and will perform satisfactorily in-
service without a hydrotested
69. Thickness measurement locations (TML’s) can be eliminated for piping system with
the following characteristics:
70. When a piping circuit present perfectly uniform corrosion, in theory could be
adequately monitored with _____ TML/s
a) 1
b) 2
c) 4
d) 3
Adiestramiento para certificación
API 570 “Inspección, reparación y alteración
De Sistemas de tuberías”
71. A seamless 10” NPS pipe, ASTM A 106 Gr. B material, operates at 750 psi and 700
degree F (maximum). The thickness of the pipe as determined by the last inspection
is 0.354”. The pipe has been in service for 10 years. The original thickness (measured
when installed) was 0.42”. Two years previous to the 0.354” measurement the
thickness of the pipe was 0.366”. Determine the greatest corrosion rate, i.e., short
or long term
72. What shall fillet welded lap patches have? (Overlay patches)
a) Right-angled corners
b) No membrane stresses
c) Rounded corners
d) Burnished corners
73. When using local PWHT repairs as a substitute for 360 degrees banding on local
repairs of PWHT’d piping. Which of the following items is NOT considered?
a) The PWHT is performed for code compliance and not for environmental
cracking
b) A preheat of 300° F, or higher is maintained while welding
c) The application is reviewed, and a procedure is developed by the piping
engineer
d) The locally PWHT’d area of the pipe must be RT’d or UT’d
75. An 8” diameter piping system is installed on December 1979. The original thickness
(measured when installed) was 0.33”. The minimum required thickness of the pipe
is 0.20”. In 1983 it is inspected and the measurement result was 0.31”. An
inspection in 1987 reveals a loss of 0.01” from 1983 thickness. During 1989 the
thickness was found to be 0.28”. In 1995 (last inspection) the thickness of the pipe
was 0.246”. What is the long term corrosion rate of the system?
a) 0.00373”/year
b) 0.00525” /year
c) 0.0025” /year
d) 0.0075” /year
76. Calculate the short term corrosion rate using the information in question 75. Round
answer to the nearest whole number
a) 0.0057” /year
b) 0.0075” /year
c) 0.0092” /year
d) 0.005”/year
77. Determinate the remaining life of the system using the information in questions 75
& 76
a) 8 years
b) 6 years
c) 12 years
d) 15 years
78. The leak test for an 8” diameter piping system is 300 psi. After 7 hours, the pressure
reads 273 psi. What should the inspector do?
a) Nothing is required. The loss of pressure is negligible and will not affect the
test. The loss can be disregarded
b) The test charts and the temperature should be reviewed to determine if any
change in temperature caused the pressure drop
c) The piping should be visually inspected externally and/or inspected internally
to find the leak and assess the extent of corrosion
d) The system should be repressured to the original leak test pressure and the
test should begin again
Adiestramiento para certificación
API 570 “Inspección, reparación y alteración
De Sistemas de tuberías”
79. When making a repair utilizing a welded full encirclement repair sleeve and the
sleeve material is different from the pipe material, you should
a) The date of installation shall be marked on the clamp for future identification
b) A record of the location and the date of installation shall be maintained
c) The clamped line shall be leak tested
d) No further action is required unless the piping leaks again
81. The diameter of electrodes used to weld a small repair patch should not exceed:
a) 1/8”
b) 5/32”
c) 1/4"
d) 3/16”
82. Corrosion cells can form on both bare and coated pipe where bare steel contacts
the soil. How can these cells be detected?
83. A 10” diameter piping system with 4” diameter and 6” diameter reinforced branch
connections is to have changes made to it. In this case it is considered an alteration
if:
84. What type of bends are usually required, if an “intelligent pigging” system is used to
inspect buried piping?
85. The purpose of a pipe coating holiday survey is to locate defects on coated pipes. It
can be used on newly constructed pipe systems to ensure that the coating is intact
and holiday-free. Nevertheless it fairly used on buried pipe to
____________________
a) 10
b) 25
c) 30
d) 5
Adiestramiento para certificación
API 570 “Inspección, reparación y alteración
De Sistemas de tuberías”
a) A jurisdictional inspection
b) An NDE examiner
c) An owner-user inspector
d) An insurance inspector
89. What is the frequency of pipe coating holiday survey on buried piping?
90. ____________ are not routinely taken for thickness measurement of a piping
system
a) Expansion loops
b) Valves
c) Tees
d) Elbows
91. When should a pressure test be performed, if a pipe requires post weld heat
treatment?
92. Repair and alteration work must be done by a repair organization as defined in API
570 and must be authorized by the ____________ prior to its commencement
a) Inspector
b) Owner-user
c) Examiner
d) Jurisdiction
Adiestramiento para certificación
API 570 “Inspección, reparación y alteración
De Sistemas de tuberías”
a) Four quadrants
b) Six points
c) Three locations
d) Two quadrants
94. How may perform the analysis of an imperfection in an original fabrication weld, if it
is required to assess the impact of the weld quality on piping integrity?
a) Electromagnetic techniques
b) MT and/or PT
c) Hammer testing
d) Ultrasonic scanning or radiography
96. TML’s are specific ___________ along the piping circuit where inspections are to be
made
a) Areas
b) Items
c) Points
d) Junctures
97. An example of where creep cracking has been experienced in the industry is in the
problems experienced with cracking of 1.25% Chrome steels operating at
temperatures above _____ degrees F
a) 1200
b) 1000
c) 900
d) 500
Adiestramiento para certificación
API 570 “Inspección, reparación y alteración
De Sistemas de tuberías”
100. Measurement technique that does not require the removal of some external piping
insulation:
a) AE
b) RT
c) UT
d) ET
101. Brittle fracture can occur in carbon, low-alloy, and other ferritic steels at or below
_____ degree F.
a) Ambient
b) 140 degree
c) 100 degree
d) 30 degree
Adiestramiento para certificación
API 570 “Inspección, reparación y alteración
De Sistemas de tuberías”
102. Depending on the circumstances and the piping system. Different types of
inspection and surveillance are used. Which of the following does not belong to this
group?
a) Jurisdictional personnel
b) Maintenance personnel
c) Operating personnel
d) OSHA personnel
a) 200
b) 150
c) 175
d) 250
105. On an installed pipe larger than NPS 1, the most accurate technique for obtaining
thickness measurements is usually ______
a) UT
b) MT
c) PT
d) ET
107. What should an inspector do if he finds threaded small bore piping (SBP) associated
with machinery and subject to fatigue damage?
108. A repair procedure involving welding requires that the root pass of the weld be
inspected before continuing the weld. A “hold” on the repair is required at this
point. Who designates this “hold”?
a) The owner-user
b) The welder Supervisor
c) An API 570 inspector
d) A metallurgist
109. For Class 3 piping systems, the examination for corrosion under insulation (CUI)
should include at least ___ percent of all suspect areas
a) 50
b) 10
c) 30
d) 0
110. Who approves all proposed methods of design, execution, materials, welding
procedures, examination and testing of in-service piping?
111. The more TML’s measured for each piping circuit, the ________________________
112. A ______________ should be used when welding a full encirclement repair sleeve
a) Low-hydrogen electrode
b) Low-nitrogen electrode
c) Low chrome electrode
d) Low- phosphorus electrode
113. A test point is an area defined by a circle having a diameter not greater than ___
inches for a line diameter not exceeding 10 inches or not greater than ___ inches for
large lines
a) 3/4, 1
b) 3, 4
c) 2, 3
d) 1, 2
a) E 7014
b) E 7011
c) E 6010
d) E7016
a) NFPA 704
b) API Publication 2201
c) API Standard 510
d) ASME B31.3
Adiestramiento para certificación
API 570 “Inspección, reparación y alteración
De Sistemas de tuberías”
117. A seamless 10” NPS pipe, ASTM A106 Gr B material, operates at 750 psi and 700°F
(maximum). The thickness of the pipe as determined by the last inspection is 0.30”.
The pipe has been in service for 10 years. The original thickness (measured when
installed) was 0.31”. The next planned inspection is scheduled for 7 years. Using the
worst corrosion rate (short or long term) determine what pressure the pipe will
resist at the end of its next inspection period?
a) 642 psi
b) 1120 psi
c) 782 psi
d) 920 psi
118. It is required to evaluate the effects of fire damage according to API RP 579. Which
of the following fitness-for-service techniques would be used?
a) Section 9
b) Section 4
c) Section 11
d) Section 6
a) Supervises
b) Directs
c) Supplants
d) Assists
120. What are points where chlorine is introduced in reformers, water is added in
overhead systems, etc. called?
121. One of the following would not be classified as an applicable code to which a piping
system was built. Choose the right one
a) ASME B31.3
b) ASME Section VII, Division 1
c) ASME B31.8
d) ASME 31.1
Adiestramiento para certificación
API 570 “Inspección, reparación y alteración
De Sistemas de tuberías”
122. When damage or a repair area of the pipe (pin-holes or pitting) is localized and the
specified minimum yield strength (SMYS) do not exceed _________psi, a temporary
repair may be made by fillet welding a properly designed plate patch over the pitted
area
a) 55,000 psi
b) 30,000 psi
c) 40,000 psi
d) 36,000 psi
124. When a buried piping is contained inside a casing pipe, the casing should be:
126. Special procedure in place of a pressure test after an alteration or repair may be
done only after consultation with _________________
a) The jurisdiction
b) The examiner and the inspector
c) The operators and the repair organization
d) The inspector and the piping engineer
Adiestramiento para certificación
API 570 “Inspección, reparación y alteración
De Sistemas de tuberías”
127. One of the following is NOT a requirement for rerating a piping system by changing
the temperature or the MAWP
129. What should the inspector do before repairing a crack in the parental metal of a
pipe adjacent to a support lug knowing that the pipe was being inspected after a 5
years run?
a) API RP 580
b) API RP 579
c) NBIC
d) NFPA, Para: 62
Adiestramiento para certificación
API 570 “Inspección, reparación y alteración
De Sistemas de tuberías”
131. During an inspection of a gas oil piping (used as reboiler oil, temperature 500 degree
F), a significant loss of material was found (a major increase of corrosion rate) on a
Fluid Catalytic Cracking Unit. As an inspector what should be done next?
132. Which of the following includes the majority of the unit process and selected off-site
piping?
a) Class 1
b) Class 2
c) Class 3
d) Combination class 1 and 2
133. On the first external inspections for potential corrosion under insulation (CUI) on
class 1 systems, the examination should include at least ___ percent of all suspect
areas and ___ percent of all areas of damaged insulation
a) 20, 20
b) 30, 30
c) 10, 10
d) 50, 75
134. For sensitized austenitic stainless steel piping subject to polythionic stress corrosion
cracking, consideration should be given to using ____________ for pressure testing
a) An acidic-water solution
b) A water with a pH of 5
c) An alkaline-water solution
d) A water with a pH of 4
136. In order to detect fatigue cracking, which of the following methods are the most
suitable for it?
137. On a piping system the water and aqueous solutions may freeze and cause failures
due to _______________
138. The leak test for buried piping should be for a period of ___ hours
a) 8
b) 24
c) 12
d) 4
139. Secondary process piping is small-bore (less than or equal to___) process piping
downstream of normally closed block valves
a) NPS 1
b) NPS 2
c) NPS 3
d) NPS 3/4
141. When an imperfection of a type or magnitude exceed the _________ criteria. This
imperfection is called a defect.
a) General
b) Nonspecific
c) Acceptable
d) Imprecise
142. What is the loss of ductility and notch toughness in susceptible low-alloy steel such
as 1 ¼ and 2 ¼, due to prolonge exposure to high-temperature service called?
a) Graphitization
b) Incipient melting
c) Creep
d) Temper embrittlement
144. When a piping buried in lengths greater than ____ feet and not cathodically
protected, evaluation of soil corrosivity should be performed at 5 year intervals
a) 150
b) 100
c) 75
d) 50
145. ______________ shall be performed (if the inspector agrees to it) after welding is
completed on a repair or alteration in accordance with API 570.
a) NBE
b) A pressure test
c) NPS
d) Safety sanctions
Adiestramiento para certificación
API 570 “Inspección, reparación y alteración
De Sistemas de tuberías”
147. Repair and alterations to piping systems shall be done according to ___________ or
the code to which the piping system was built
a) API 574
b) API 570
c) ASME & PV code
d) ASME B31.3
148. What type of repairs and procedures may the inspector give prior general
authorization to continue provided the inspector is satisfied with the competency or
the repair organization?
149. Materials used in making welding repairs or alterations ____ be of known welable
quality
a) Should
b) Can
c) May
d) Shall
150. During a pressure test, where the test pressure will exceed the set pressure of the
safety relief valve or valves on a piping system the safety relief valve or valves
should be _____________ when carrying out the test
a) Removed or blanked
b) Checked or tested
c) Reset to exceed the test pressure
d) Altered by screwing down on the adjusting screw
Adiestramiento para certificación
API 570 “Inspección, reparación y alteración
De Sistemas de tuberías”
151. Several methods may be used In order to verify that the correct alloy is in a system.
One of the following is not the right method
152. Which of the items listed below does not belong to examples of a CLASS 1 piping
system?
153. If an inspector finds a flange joints that has been clamped and pumped with sealant,
he should:
a) No action is required since the joint has been pumped with a sealant
b) Disassemble the flange joint; renew the fasteners and gaskets. The flanges
may also require renewal or repair
c) Renew all the fasteners and renew the gasket if leakage is still apparent
d) Check for leakage at the bolts; if repumping is contemplated, affected
fasteners should be renewed
154. Welders and welding procedures used in making piping repairs, etc. shall be
qualified in accordance with:
155. Which of the listed below shall be used on repairs and alterations welding to piping
systems?
a) Exact procedures of ASME B31.1 or the code to which the piping it built
b) Principles of ASME B31.1 or the code to which the piping it built
c) Standards of ASME B31.1 or the code to which the piping it built
d) Ideals of ASME, NBIC, or API standards
Adiestramiento para certificación
API 570 “Inspección, reparación y alteración
De Sistemas de tuberías”
156. An existing seamless 10” NPS pipe, ASTM A106 Gr B material, operates at 750 psi
and 700 degrees F (maximum). Considering only pressure design thickness for
straight pipe, what the minimum thickness is required?
a) 0.24”
b) 0.17”
c) 0.2”
d) 0.28”
157. Insert patches, flush patches may be used to repair damaged or corroded areas of
pipe if several requirements are met. One of these is that an insert patch (flush
patch) may be of any shape but it shall have rounded corners with ____ minimum
radii
a) 0.5”
b) 1”
c) 0.75”
d) 0.275”
a) Once a year
b) Once every 3 months
c) Approximately 6 month intervals
d) Once a month
a) Intermittently
b) Erratically
c) Regularly
d) Frequently
Adiestramiento para certificación
API 570 “Inspección, reparación y alteración
De Sistemas de tuberías”
161. Hold point is a point in the repair or alteration process beyond which work may not
proceed until the __________ ___________ has been performed and documented
a) PWHT required
b) Ultrasonic testing
c) RT required
d) Required inspection
162. When a welded repair or alteration was carried out, the acceptance shall include
____________ in accordance with the applicable code and the owner-user’s
specification, unless otherwise specified in API 570
166. Fewer TML’s can be selected for piping systems with any of the following
characteristic:
167. Who may designate the pressure if a lower pressure test (lower than prescribed by
code) is used only for tightness of piping systems?
a) Contractor
b) Jurisdiction
c) Owner-user
d) Inspection
168. If a non-toxic hydrocarbon (flammable) is used as the test medium, the liquid flash
point shall be at least ______degrees F or greater
a) 95
b) 100
c) 110
d) 120
a) Chemical engineer
b) Piping engineer and the jurisdiction
c) Owner-user or the Inspector
d) Piping engineer
170. What type of defect, corrosion, pitting and/or discontinuity should not be repaired
by a full encirclement welded split sleeve?
171. Poorly coated pipes with inconsistent cathodic protection potentials should have a
pipe-to-soil potential survey _____________
a) Yearly
b) Every 5 years
c) Every 7 years
d) Every 2 years
172. Which of the items listed below is NOT an indication of leaks in buried piping?
173. When shall temporary leak sealing and leak dissipating device be removed and the
pipe restored to original integrity?
174. Internal visual inspection are ______________on piping unless it is a large diameter
transfer line, duct, catalyst line or other large diameter piping system
a) 12 months
b) 1 month
c) 6 months
d) 3 months
Adiestramiento para certificación
API 570 “Inspección, reparación y alteración
De Sistemas de tuberías”
178. What type of NDT is usually used to check flange and valve bonnet bolts for
corrosion?
a) AE
b) UT
c) RT
d) VT
179. During in-service inspection of welds an environmental cracking was found. Who
assess the problem?
a) Piping engineer
b) Metallurgist
c) Inspector
d) Owner-user
180. What precaution should be taken if block valves are used to isolate a piping system
for a pressure test?
a) 2 to 4
b) 4 to 6
c) 6 to 8
d) 8 to 10
182. What is taken into account by an experienced inspector when selecting TML’s?
183. Where should special attention be placed when taking thickness measurement of an
elbow?
185. Inspection of small bore piping (SBP) that is secondary and auxiliary (associated with
instruments and machinery) is ______________________
a) Depend upon the operators to watch for any changes in operations and
inform the inspectors
b) Use an experienced inspector who can visually watch for changing
temperature
c) Employ temperature indicating crayons to check for changing
temperature
d) Use tube skin thermocouples and/or infrared thermography
2. What should an inspector do, if a small pressure vessel made of 316 stainless
steel operating at 220° F in an area subject to a lot of water vapor is to be
insulated. Checking for the insulation that is to be used, he finds that it
contains chlorides?
a) Make sure the area is covered during the installation of the insulation to
avoid moisture being trapped
b) Nothing is required-the insulation is satisfactory
c) Heat the vessel to 300° F during the installation of the insulation
d) Stop the installation of the insulation and make arrangements to have
low/no chloride insulation installed
3. Chloride stress corrosion cracking (CI SCC) is surface initiated cracks found in
___________
4. Name the inspection methods for detecting the extent of metal loss due to
erosion and erosion-corrosion:
a) Carbonate
b) Iron
c) Carbide
d) Calcium
8. Which of the following is the one that can confirm through advanced Early
stages of HTHA?
a) Branching cracks
b) Transgranular cracks
c) Step laminations
d) Localized pitting under deposits or tubercles
a) VT, MT and PT
b) AET, ET and RT
c) WFMT and LT
d) ET and AE
13. A description of the damage that occurs when corrosion contributes to erosion
by removing protective films or scales, or by exposing the metal surface to
further corrosion under the combined action of erosion and corrosion is called:
a) Erosion-attrition
b) Abrasion-wear
c) Erosion-corrosion
d) Surface weathering
Adiestramiento para certificación
API 653 “Inspección, reparación y alteración
De tanques de almacenamiento
14. Key factors affecting thermal fatigue are the magnitude of the
___________________ and the _______________
15. Three factors when critically combined tend to cause brittle fracture. Which of
the four factors listed below does not belong?
16. If carbon steel is exposed in a dry rural environment. What is the atmospheric
corrosion rate?
a) < 4 mpy
b) < 1 mpy
c) < 2 mpy
d) < 3 mpy
17. A carbon steel is located next to a cooling tower with mist from the tower on
the line. T he pipe is only protected by poorly coated aluminum paint
a) 600° F
b) 800° F
c) 700° F
d) 500° F
Adiestramiento para certificación
API 653 “Inspección, reparación y alteración
De tanques de almacenamiento
21. _________ is not a proven method for the detection of HTHA damage
a) RT
b) VT
c) AET
d) WFMT
22. This material has been removed from the Nelson curves shown in Figure 5-35
of API RP 571 and in API RP 941
23. An inspector calls for low pressure steam out of equipment that has contained
caustic in preparation for weld repairs. The inspector requires that the
equipment be washed thoroughly with clean water prior to steam out. What
does this prevent?
24. What two conditions, if changed, will promote more severe cracking in caustic
embrittlement?
25. An inspector is preparing to hydrotest equipment that is made from AISI Type
304 stainless steel. One of the most important items that should be used is the:
26. During an inspection, cracks are found in the brick fireproofing of a column
supporting a vessel on a FCC unit. An inspection hole is opened to check the
condition of the column. Heavy rust scale is present and the inspector requires
the entire column to be stripped. Severe pitting to holes and serious thinning of
the column is found. What type of corrosion would this be?
31. One of the four items listed below is not equipment with mechanical loading
that is affected by mechanical fatigue cracking. Select the incorrect one
a) Tensile stresses
b) Bending stresses
c) Cyclic stresses
d) Torsional stresses
Adiestramiento para certificación
API 653 “Inspección, reparación y alteración
De tanques de almacenamiento
33. ___________is the best defense against mechanical fatigue cracking which
helps minimize stress concentration of components that are in cyclic service
a) Allowance of travel
b) Design and operation
c) Selection of materials
d) Prevention of movement
a) 5
b) 4
c) 3
d) 2
37. What inspection method would be best to find wet insulations on vessels or
damaged and missing insulation beneath an aluminum jacket on a vessel?
38. Corrosion in boiler feedwater and condensate return systems usually is caused
by
41. Post weld heat treatment to stress relieve the equipment can help effectively in
preventing caustic embrittlement cracking of carbon steel. What temperature
should be used for PWHT?
a) 1150° F
b) 650° F
c) 1450° F
d) 1550° F
Adiestramiento para certificación
API 653 “Inspección, reparación y alteración
De tanques de almacenamiento
a) Attrition
b) Erosion
c) Corrosion
d) Weathering
43. Primarily to find for caustic embrittlement (caustic stress corrosion). Where
would you inspect?
a) Branching cracks
b) Transganular cracks
c) Step laminations
d) Localized pitting under deposits or tubercles
a) Far north environments with the maximum exposure to cold and snow
b) Marine environments and moist polluted industrial environments
c) Areas exposed to the morning sun and prevailing winds
d) Desert environments, and cold dry rural environments
a) Dust
b) Bird feces
c) Snow
d) Rain
a) Chrome
b) Low carbon
c) Nickel
d) Columbium
50. Copper base alloys form sulfide at _____________ than carbon steel
a) Slower rates
b) Higher temperatures
c) Faster rates
d) Lower temperatures
51. For a hydrogen partial pressure of 2500 psi, and a temperature of 900 degrees F
and using the curves in Figure 5-35 of API RP 571. What material should be
picked for use?
a) 3 Cr-1 Mo
b) 2.25 Cr-0,5 Mo
c) Carbon steel
d) 1.25 Cr-0.5 Mo
Adiestramiento para certificación
API 653 “Inspección, reparación y alteración
De tanques de almacenamiento
52. The CI SCC surface cracks appear under the action of _______________.
Temperature and an aqueous chloride environmental
a) Stagnant conditions
b) Tensile stress
c) Compressive stress
d) High velocity products
53. Some units affected by HTHA are listed below. One of the following is usually
not considered a target. Pick the unit
a) Catalytic Reformer
b) Crude still
c) hydrotreater
d) hydrocracker
54. Depending on condition of service. What is the form most frequently for
sulfidation corrosion?
55. In most cases, brittle fracture occurs only at temperatures below the Charpy
impact _______ temperature, the point at which the toughness of the main
material off sharply
a) Stable
b) Failure
c) Transition
d) Critical
57. What increase in temperature is used as a safety factor when using API RP 941
curves for selecting an alloy steel for use?
a) 10 to 20 degrees F
b) 25 to 50 degrees F
c) 75 to 100 degrees F
d) 100 to 200 degrees F
59. Cracking and fissuring caused by HTHA are ___________and occur adjacent
to pearlite (iron carbide) areas in carbon steel
a) Intergranular
b) Laminations
c) Subsurface
d) Surface oriented
60. Select the location where CUI would not be matter at concern
61. Major factors affecting sulfidation are alloy composition temperature and
concentration of corrosive ______compounds
a) Hydrogen
b) Ammonia
c) Water
d) Sulfur
Adiestramiento para certificación
API 653 “Inspección, reparación y alteración
De tanques de almacenamiento
62. What is the cause of corrosion under insulation (CUI) of refinery and
chemical plant equipment?
a) The corrosion is caused from the use of the wrong material for the
equipment
b) The corrosion is caused by long term lack of maintenance
c) The corrosion is caused by not having an on-going and complete
inspection program
d) The corrosion results from water trapped under insulation and fire
proofing
63. What methods would you pick for inspection and monitoring atmospheric
corrosion
a) ET and MT
b) PT and WFMT
c) AE and RT
d) VT and UT
65. Pits, grooved, gullies, waves, rounded holes & valleys exhibiting a directional
pattern are characteristics of:
66. Equipments that are exposed to moving fluids and/or catalyst are subject to
erosion and erosion-corrosion. What unit is most often damaged
67. Brittle fatigue can occur during ambient temperature during a hydro-test due
to:
a) 15
b) 25
c) 10
d) 35
a) Parallel
b) Vertical
c) Perpendicular
d) At a 90 degree angle
Adiestramiento para certificación
API 653 “Inspección, reparación y alteración
De tanques de almacenamiento
a) RT
b) LT
c) PT
d) AE
74. Which of the following techniques can be used to detect fatigue cracks at
known areas of stress concentration?
a) The failure exhibits a hash mark type of fingerprint that radiates from
the crack origin
b) The failure exhibits a ragged rough type of fingerprint that emanates
from the failure point
c) The failure exhibits a wavy type of fingerprint that is random in nature
d) The failure exhibits a “clam shell” type of fingerprint that has concentric
rings called “beach marks”
a) 1 mpy
b) 0.2 mpy
c) < 0.2 mpy
d) 0.3 mpy
Adiestramiento para certificación
API 653 “Inspección, reparación y alteración
De tanques de almacenamiento
77. Sulfur compounds react with carbon steel in high temperature environments.
This reaction causes corrosion. The presence of __________ accelerates the
corrosion
a) Hydrogen
b) Water
c) Carbon dioxide
d) Oxygen
78. Name two other similar forms of alkaline stress corrosion cracking
mechanisms
a) 9 Cr-1Mo
b) 300 series stainless steel
c) Carbon steel
d) 400 series stainless steel
81. What type of on stream inspection method can detect the loss of refractory on
an operating unit?
82. What year did the ASME Boiler and Pressure Vessel Code, Section VII,
Division 1 begin to require toughness as a criteria for vessels operating at cold
temperatures?
a) 1987
b) 1995
c) 1963
d) 1942
84. Which of the following steels listed below is not susceptible to brittle
fracture?
86. How many mils per year would you expect a carbon steel line to lose if
exposed to a marine environment?
a) 15 mpy
b) 10 mpy
c) 5 mpy
d) 20 mpy
Adiestramiento para certificación
API 653 “Inspección, reparación y alteración
De tanques de almacenamiento
89. Which of the following method NDE is not effective for finding caustic
embrittlement cracking when it is tight & scaled-filled?
a) VT
b) RT
c) WFMT
d) PT
90. Damage from HTHA occurs _______ in welds or weld heat affected zones
as well as in the base metal
a) Early
b) Occasionally
c) Late
d) Randomly
a) Atmospheric corrosion
b) SCC
c) Mechanical fatigue
d) Erosion
Adiestramiento para certificación
API 653 “Inspección, reparación y alteración
De tanques de almacenamiento
a) Marine environment
b) Amplitude of vibration
c) Frequency of vibration
d) Both a & b
a) Carbon steel
b) 9 Cr-1 Mo
c) Series 300 SS
d) Aluminum
a) 160° F
b) 200° F
c) 160° F
d) 140° F
97. What percent of chlorides is safe for exposure to 300 series stainless steel?
a) 0%
b) 10%
c) 15%
d) 5%
Adiestramiento para certificación
API 653 “Inspección, reparación y alteración
De tanques de almacenamiento
a) Carbon monoxide
b) Oxygen
c) Nitrogen
d) Carbon dioxide
Adiestramiento para certificación
API 653 “Inspección, reparación y alteración
De tanques de almacenamiento
a) Interpretation
b) Viewing
c) Screening
d) Reading
2. Which of the following are the dimensions of the lead letter “B” that is
attached to the back of each film holder/cassette during exposure to determinate
if backscatter radiation is a problem?
a) Its thickness is 1/8 inch and its minimum dimension is 9/16 inch
b) Its thickness is 3/32 inch and its minimum dimension is 3/8 inch
c) Its thickness is 1/32 inch and its minimum dimension is 5/8 inch
d) Its thickness is 1/16 inch and its minimum dimension is 1/2 inch
5. Select the most common NDE methods used during weld inspection. Pick
the one that has all the correct methods
6. What will happen if a metal is subject to tensile stress to a point greater than its
yield stress? It will:
8. What does the first two numbers of a E7018 electrode identify when using
SMAW?
a) Electrode coating
b) Welder position
c) 70000 psi ultimate strength
d) Alloy of electrode
9. How is called a material or device placed against the backside of the weld
joint, or at both sides of a weld in welding, to support and retain molten weld
metal?
a) A fusion consumable
b) An assistance strip
c) Consumable insert
d) Backing
Adiestramiento para certificación
API 653 “Inspección, reparación y alteración
De tanques de almacenamiento
10. Some of the quality control items dealing with procedures and qualification
records of welder for an inspection to assess are listed below. Which of the 4
items does not belong?
11. How is called a fracture type discontinuity characterized by sharp tip and high
ratio of length and width to opening displacement?
a) A fissure
b) A fracture
c) A crack
d) A flaw
12. What should be done when a inspector completes physical checks, visual
examinations and results of NDE and unacceptable workmanship is found?
13. Select the item that must not be included on the PQR
17. What does the welding procedure specification (WPS) provide for the welder?
a) It is provides a record for the welding data and variables used to weld a
test coupon and the test result
b) It is provides a list of documents such as ASME, API 571, etc. that the
welder must follow
c) It is provides direction for the welder while making production welds to
ASME Code requirements
d) It is provides guidelines for the welder to prevent him from making
mechanical errors in welding
a) GTAW
b) SMAW
c) SW
d) SAW
Adiestramiento para certificación
API 653 “Inspección, reparación y alteración
De tanques de almacenamiento
19. What type of weld inspection technique can be made more sensitive by using
wet fluorescents and a filtered infrared light (black light)?
20. Choose the electrode size that should be used on the first weld pass on a hot
tap or an in-service weld on piping or equipment less than ¼ inches thick?
21. The two main concerns when welding on in-service piping and equipment are:
22. Two pieces of plate are to be joined by butt welding. The plates have been
beveled. The two plates are separated approximately 1/8” prior to welding.
What is this opening called?
a) A weld separation
b) A welding heating
c) Weld space
d) A root opening
a) A metallurgist
b) A welding expert
c) A welding engineer
d) A welding specialist
Adiestramiento para certificación
API 653 “Inspección, reparación y alteración
De tanques de almacenamiento
24. Which of the typo of carbon listed below removes molten metal with a jet of
air?
26. A non-standard term indicating a weld discontinuity in which fusion did not
occur between weld metal and fusion faces or adjoining weld beads is
referred to as:
a) Lack of fusion
b) Burn-through
c) Arc blow
d) Lamellar tear
a) All areas tested since the last successful calibration must have the
readings adjusted
b) All areas tested since the last successful calibration should be
reexamined
c) All areas tested since the last successful calibration should have the
readings adjusted
d) Select the areas tested since the last successful calibration should be
examined & if okay, accepted
28. _______________ is the distance the weld metal extents from the weld face
into a joint, exclusive of weld reinforcement
a) Joint penetration
b) Joint weld distance
c) Joint heat affected zone
d) Joint attachment
Adiestramiento para certificación
API 653 “Inspección, reparación y alteración
De tanques de almacenamiento
a) 200° F
b) 400° F
c) 212° F
d) 125° F
32. Why radiographic inspections (RT) are more expensive than other NDE?
33. How is called a joint root condition in a groove weld in which weld metal
does not extend through the joint thickness?
34. What would cause porosity in the weld when welding stainless steel?
a) A blemish
b) A discontinuity
c) An imperfection
d) An error
36. Remote examination of welds may use aids such as telescopes, borescopes,
fiberscope, cameras or other suitable instruments, provided:
a) The single phase zone, the dual phase metal (zone) and the base metal
b) The weld metal, the heat affected metal (zone), and the base metal
c) The filler metal, the fusion zone, and the base metal
d) The single phase zone, the pearlite zone, and parent metal
Adiestramiento para certificación
API 653 “Inspección, reparación y alteración
De tanques de almacenamiento
38. The most common measure of weldability and susceptibility to hot cracking
of austenitic stainless steels is the ferrite number of the weld metal. A number
of resources recommended a minimum of _____ to_______ferrite to prevent
cracking
a) 0.5%, 1.0%
b) 2%, 5%
c) 1%, 4%
d) 5%, 20%
39. Carbon steel is a two-phase alloy. One phase is a relatively pure form of iron
called ferrite. With the addition of more than 0.6% percent of carbon, a second
phase is formed called ____________. This adds strength to steel
a) Hermatite
b) Magnetite
c) Pearlite
d) Dendrite
40. Select the Brinnell hardness limit unit value for carbon steel in refining
service
a) 200
b) 215
c) 225
d) 241
41. If a welder “hammers” or mechanically works the metal using impact blows,
what is it called?
a) Peening
b) Knocking slag
c) Hammering
d) Mechanical stress relieving
a) Photometer
b) Positron
c) Penetrameter
d) PMI meter
Adiestramiento para certificación
API 653 “Inspección, reparación y alteración
De tanques de almacenamiento
44. This welding process produces fast a freezing weld pool and is generally
suited for joining thin sections or root passes
a) SMAW
b) GTAW
c) GMAW-S
d) FCAW
45. What should be done if a system is found to have a leak during a pressure
test?
a) Depressure the system, repair the leak per code, and repeat the test
b) Repair the leak immediately and continue with the pressure test
c) Continue with the pressure test until maximum test pressure is reached,
then repair the leak
d) Stop the leak, complete the pressure test and then repair the leak
46. Where is he heat affected zone (HAZ) assumed to be for purposes of hardness
testing?
a) The HAZ is usually assumed to be from the toe of the weld on one side
to the opposite toe
b) The HAZ is always assumed to be 1 inch on either side of the centerline
of the weld
c) The HAZ is always assumed to be 0.25 inches away from the toe of the
weld
d) The HAZ is often assumed to be just adjacent to the toe of the weld
Adiestramiento para certificación
API 653 “Inspección, reparación y alteración
De tanques de almacenamiento
47. When we talk about melting temperature, thermal heat conductivity, electrical
conductivity, the coefficient of thermal expansion and density, we are
referring to:
a) Recognition signs
b) Welding assets
c) Physical properties
d) Corrosion properties
a) GTAW
b) SAW
c) SMAW
d) GMAW
a) Stress
b) Ultimate
c) yield
d) Strain
51. Liquid flow rates in piping to be hot tapped shall be between____ feet per
second and ___ feet per second
a) 4.0, 5.0
b) 0.5, 0.3
c) 4.5, 5.5
d) 1.3, 4.0
Adiestramiento para certificación
API 653 “Inspección, reparación y alteración
De tanques de almacenamiento
a) The radiation source should pass through twice the thickness of the
material being radiographed
b) The radiation source should pass through a single thickness of the
material being radiographed
c) The radiation source should be placed a minimum of 3 feet from the
material being radiographed
d) The radiation source should be placed with a thick lead shield between
the film and the source
55. What number IQI should be selected for a welded material that is 0.625 inches
thick?
a) 20
b) 12
c) 17
d) 15
Adiestramiento para certificación
API 570 “Inspección, reparación y alteración
De Sistemas de tuberías”
a) After 8 years
b) After 5 years
c) After 10 years
d) None of the above
a) 10 years
b) 5 years
c) 3 years
d) 8 years
a) Class I
b) Class AS
c) Class 200
d) Class III
4. Tensile test have been performed on two specimens with the following characteristics
and result: Specimen #1, 0.76 in. wide, 0.52 in. thick and ultimate tensile strength of
75,265 psi. Specimen #2, 0.75 in. wide, 0.50 in. thick and ultimate tensile strength of
90,236 psi. What was the tensile machine load for each specimen?
6. Which of the following is the correct filmside IQI designation for a well that is 1.56” thick?
a) 12
b) 8
c) 10
d) 50
7. A flange (forged flange marked ASTM A182 Grade F1) class 300. You know the
operating temperature is 500° F. Which of the following pressure is permissible with this
flange?
a) 500 psi
b) 300 psi
c) 640 psi
d) 665 psi
8. The Hydrostatic test pressure for a ASTM A105 carbon steel class 400 forged flange is:
a) 1500 psi
b) 1510 psi
c) 1485 psi
d) 1450 psi
9. Minimum thickness of steel recommended for which the radioactive isotope Iridium 192
should be used:
a) 0.65”
b) 1.50”
c) 0.25”
d) 1.30”
10. You are asked to set the inspection interval for a buried pipe line. The soil resistivity
(ohm-cm) is checked and found to be 8300 ohm-cm. What would be the interval?
a) 5 years
b) 10 years
c) 2 years
d) 15 years
Adiestramiento para certificación
API 570 “Inspección, reparación y alteración
De Sistemas de tuberías”
a) 6
b) 5
c) 1
d) 4
12. What is the test pressure of a metallic piping system whose design temperature is above
the test temperature using the following conditions? NPS 6, SA106 Gr.B, 100 psi / 800°F
a) 150 psi
b) 450 psi
c) 278 psi
d) Test temperature verses design temperatures are not different
13. Actual thickness measured at a TML was 0.4 inch. The corrosion rate is 10 mpy. If next
planned thickness inspection is after 6 years, what thickness will be used for MAWP
calculation?
a) 0.4 inch
b) 0.34 inch
c) 0.28 inch
d) None of the above
14. If a single film technique was used to make a radiograph using a cobalt 60 source. The
minimum permitted density in the area of interest is __________
a) 2.8
b) 2.0
c) 3.0
d) 1.8
15. An ASTM A-53 Grade B NPS 12 pipe operates at 700 psi and 750° F. A blank fabricated
from ASTM-A285 Grade C plate is to be used for testing and later for operations. The
blank is to be used with 600 class flanges. What thickness blank will be required? The
corrosion allowance required is 0.10”. The I.D of the gaskets is 12.75”. Round the answer
to the nearest hundredth.
a) 1.23”
b) 1.43”
c) 1.31”
d) 1.51”
Adiestramiento para certificación
API 570 “Inspección, reparación y alteración
De Sistemas de tuberías”
16. An 8” diameter x 0.5 thick round lap path is to be installed as a repair to a 16” diameter
pipe. The small repair path is to be installed over several isolated pits. What is the largest
size electrode that can be used?
a) 7/32”
b) 1/4"
c) 5/32”
d) 5/16”
18. When should Injection points be checked downstream of the Injection point?
a) To the second change in flow direction or 20’ beyond the first change in flow
direction, whichever is less.
b) To the first change in direction or 25’ beyond the injection point
c) To the third change in flow direction or 30’ beyond the second change in flow
direction, whichever is less.
d) To the second change in flow direction or 25’ beyond the first change in flow
direction, whichever is less.
19. An ASTM A135 Grade A NPS 6 electric resistance welded (ERW) pipe is to be used in
a refinery for hydrocarbon service. It operates at 300 psi and 125° F. What joint factor, E,
would you use in determining the thickness for pressure only.
a) 0.85
b) 1.00
c) 0.6
d) 0.8
Adiestramiento para certificación
API 570 “Inspección, reparación y alteración
De Sistemas de tuberías”
20. How is a fluid service classified in which the potential for personnel exposure is judge to
be significant and a single exposure to a very small quantity, can produce serious health
damages by breathing or body contact, even when prompt restorative measures are
taken?
a) Category D
b) High pressure
c) Normal
d) Category M
a) Renewal
b) Rerating
c) Regurgitation
d) Retrofitting
22. You must check a NPS 6 piping system made from ASTM A-106 Grade B material. The
system operates at 400 psi and 500° F. The piping engineer has a note on the records
that a thickness of 0.15” is required for structural reasons and a corrosion allowance of
0.125” must be maintained. What thickness of pipe would you use?
a) 0.250”
b) 0.355”
c) 0.275”
d) 0.344”
23. A seamless 10” NPS pipe, ASTM A106 Gr B material, operates at 750 psi and 700°F
(maximum). The thickness of the pipe as determined by the last inspection is 0.30”. The
pipe has been in service for 10 years. The original thickness (measured when installed)
was 0.31”. The next planned inspection is scheduled for 7 years. Using the worst
corrosion rate (short or long term) determine what pressure the pipe will resist at the end
of its next inspection period?
a) 642 psi
b) 1120 psi
c) 782 psi
d) 920 psi
Adiestramiento para certificación
API 570 “Inspección, reparación y alteración
De Sistemas de tuberías”
24. Personnel performing visual examination (VT) shall have an annual visual revision to
assure natural or corrected near distance acuity. They must be capable of reading
____________________________
a) Standard U-1 letters on standard Hunter test type charts for near vision
b) Standard T-1 letters on standard Hunter test type charts for far vision
c) Standard G -1 numerals on standard Jaeger test type charts for far vision
d) Standard J -1 letters on standard Jaeger test type charts for near vision
25. A NPS 6 piping system, reflux line system of depropanizer tower, operates at 275 psi and
200°F. The pipe material is ASTM A53 Grade B. The pipe thickness when installed in 1980
was 0.375”. During an inspection in 1990 the thickness of the pipe measured was 0.30”
and for 1996 it was 0.25”. What is the value of the worst corrosion rate used to calculate
the remaining life of the pipe?
a) 0.0078 in/yr
b) 0.0830 in/yr
c) 0.0780 in/yr
d) 0.0083 in/yr
27. A seamless NPS 14, ASTM A53 Grade B material, pipe operates at 775 psi and a
maximum of 750° F. Only for pressure design, what is the minimum thickness required?
a) 0.50”
b) 0.43”
c) 0.41”
d) 0.46”
29. A NPS 12 gate valve made from ASTM A216 Grade WCB material was rolled out for
inspection. An area of the valve body was found by the inspector to be thinning. The
maximum operating pressure of the valve is 275 psi at 200° F. The casting factor, Ec, is
0.8. The owner-operator requires the Inspector to maintain a 0.125” corrosion allowance.
What is the minimum thickness for the valve body? Round answer off to the nearest
hundredth.
a) 0.31”
b) 0.24”
c) 0.15”
d) 0.28”
30. Select the hole type designation and diameter of an IQI, if a 2T hole diameter is to be
located on the source side of a 48” diameter pipe that has been welded. The wall
thickness is 0.625”
a) 20 & 0.040”
b) 30 & 0.040”
c) 25 & 0.020”
d) 17 & 0.013”
31. A welder who tests on a ½” thick plate, groove weld in the 3G position is also qualified to
weld in which other plate position?
a) Vertical only
b) Flat and horizontal
c) Vertical and Flat
d) All plate positions
32. What is the maximum length allowed for individual slag trapped in a weld in a Severe
Cyclic Conditions piping system?
a) >TW X 3
b) =TW / 3
c) =12T
d) 3/23”
Adiestramiento para certificación
API 570 “Inspección, reparación y alteración
De Sistemas de tuberías”
33. For 1 1/4” thick Carbon steel, what is the recommended preheat temperature?
a) 300°F
b) 235°F
c) 175°F
d) none
34. A NPS 10 ASTM A335 Grade P9 pipe with a wall thickness of 0.625” has a section cut
out of it for installation of weld neck flanges for a spool section. Which of the following
temperatures should be used for post weld heat treatment of the butt welds?
a) 1100-1200° F
b) 1300-1400° F
c) 1350-1450° F
d) 1100-1325° F
35. The material used for low strength bolts should not exceed _______ ksi minimum yield
strength
a) 30
b) 30000
c) 3000
d) 3
a) It is the cross section of a weld as it would appear if the weld was cut axially
b) It is the exposed surface of a weld on the side opposite from which welding was
done
c) It is the cross section of a weld as seen if cut across the groove
d) It is the exposed surface of a weld on the side from which welding was done
Adiestramiento para certificación
API 570 “Inspección, reparación y alteración
De Sistemas de tuberías”
37. A NPS 10 seamless pipe made from ASTM A53 Grade B material operates at 725 psi
and 675° F maximum. What allowable stress would you use to determinate the pipe’s
minimum thickness for pressure design?
a) 16500 psi
b) 20000 psi
c) 16750 psi
d) 17000 psi
38. A NPS 14 pipe with a wall thickness of 1.25” has to have a section 3’ long cut out and
replaced. The pipe material is ASTM A-53 Grade B. What preheat would you recommend
on the butt weld?
a) 175 degrees
b) 100 degree
c) 50 degree
d) None
39. When conducting MT, each piece of magnetizing equipment used with an ammeter shall
be calibrated at least____________, or whenever the equipment has been subjected to
major repair, overhaul or damage.
a) Quarterly
b) Twice a year
c) monthly
d) Once a year
40. What marking is not required on a B16.5 flange? Knowing that mark may be included, but
if it is, the pressure rating shall be stamp next to it
a) Size
b) Temperature
c) Rating class
d) Designation
Adiestramiento para certificación
API 570 “Inspección, reparación y alteración
De Sistemas de tuberías”
41. Which of the following includes the majority of the unit process and selected off-site
piping?
a) Class 1
b) Class 2
c) Class 3
d) Combination class 1 and 2
a) Temper embrittlement
b) Hydrogen embrittlement
c) 885 embrittlement
d) Caustic embrittlement
43. A NPS 20 piping designed to operate 500 psi and 400° F with a 0.1” corrosion allowance.
With 0.593” of thick wall made from ASTM A53 Grade B material. The allowable stress is
20000 psi. The current thickness measured is 0.42”. The pipe is seamless. If the
corrosion allowance of 0.1” is maintained, what MAWP is the pipe good for now?
a) 704 psi
b) 933 psi
c) 640 psi
d) 840 psi
44. What would you tell to a welder if a pipe has to be shortened, cutting out a section and
rewelded, the welder ask how far from the weld must the preheat temperature be
maintained? Knowing that it is A NPS 12 pipe made from ASTM A-53 Grade B with a
wall thickness of 1.125”.
a) Maintain the preheat at least 1 Plg beyond each edge of the weld
b) No preheat is required for this thickness carbon steel material
c) Maintain the preheat at least the width of the weld
d) Maintain the preheat at least 2’ beyond each edge of the weld
Adiestramiento para certificación
API 570 “Inspección, reparación y alteración
De Sistemas de tuberías”
45. As a standard technique, the temperature of the penetrant and the surface of the part to
be processed by PT shall not be below ______ nor above _____ throughout the
examination period
a) 55°F, 100° F
b) 70° F, 150° F
c) 50° F, 125° F
d) 65° F, 135° F
46. At not less than_____ , preheating may be considered an alternative to PWTH for
alterations and repairs initially PWHT as a code requirement
a) 600 F
b) 500° F
c) 300° F
d) 250° F
47. A NPS 18 piping system operates 500 psi and 400° F with 0.5” of thick wall made from
ASTM A53 Grade B material. The pipe was installed in 1991. The allowable stress is
20000 psi. The thickness measured in 1996 is 0.42”. The pipe is seamless. The next
planned inspection is in the year 2001. Calculate the MAWP in the year 2001 for this
pipe. Round answer to the nearest whole number
a) 578 psi
b) 933 psi
c) 650 psi
d) 756 psi
Adiestramiento para certificación
API 570 “Inspección, reparación y alteración
De Sistemas de tuberías”
48. Does the preheat qualified on the PQR Support the preheat specified on the WPS per
Section IX?
49. Do the mechanical tests on the PQR is to be according with the WPS per Section IX?
a). No
b). No, one tensile test specimen failed
c). Yes
d). No, one tensile test specimen failed and side bends were required
51. Which inspection technique is most appropriate for a Class 1, NPS 1, carbon steel piping
system, and that operates at 200°F?
52. What type of inspections would be most effective if as an inspector you know or are advised that
environmental cracking may be a problem in a particular piping circuit?
53. ______________ determinates if a pressure test is required after a repair is made to a piping
system?
a) Maintenance Supervisor
b) Operator
c) Owner-User
d) Inspector
54. The soil closed potential survey is being carried out for a non catholically protected system is:
a) Once in 5 year
b) Once in 3 year
c) Half of the remaining life
d) Once in 6 months
55. Which of the test method is not a material identification test method:
56. What NDE procedure would you require if an insert patch (flush patch) with full-penetration groove
welds is used as a permanent repair for a pipe in a class 1 or 2 piping system?
57. Hammer testing of piping, valve, and fittings is a method of extending the scope of measurement
to detect the presence of unexpected thin sections. Which of the following may safely be hammer
tested?
a) Cooper tubing, brass piping, or other piping made from soft materials
b) Carbon steel lines in low or non-corrosive service
c) Glass, cement or other internally coated (lined) pipe
d) Cast iron and stress-relieved lines in caustic and corrosive service
a) Affixing a full circumferential welded split sleeve over the defect, a lap patch less than ½
the diameter of the pipe over the defect, or a weld cap over the corroded area
b) Fastening an expanded split over the defect, bolting a lap patch over the defect, or
clamping a weld cap over the problem area
c) Installing a properly designed and fabricated bolted leak camp over the defect, or use a
commercial leak sealing company to fabricate a device to seal off the defect
d) Remove the defect by preparing a welded groove that removes the defect, restore the
corroded area with weld metal or cut out a cylindrical section and replacing
59. Fatigue cracking can typically be first detected at points of high-stress intensification such as
___________________
60. ASME Standard B16.5 covers pressure-temperature ratings, material, tolerances, marking, testing
and methods of designating openings for flanges and flanged fittings NPS______ through NPS
______
a) 1/2, 24
b) 3/4, 28
c) 1/8, 26
d) 1/4, 30
61. Low strength bolts shall only be used in class_____ and class____joints
a) 300, 400
b) 400, 600
c) 125, 150
d) 150, 300
62. Which of the following is cause for rejection of the “B” image on an RT film?
a) Any image
b) No image
c) Dark image in light background
d) Light image in dark background
a) Visual
b) radiographic
c) internal visual
d) ultrasonic
65. Which of the following items classified services that are flammable but do not significantly vaporize
when the leak are not located in high-activity areas?
a) Normal
b) Class 3
c) Class 2
d) Class 1
66. The piping inspection intervals for thickness measurements and external visual inspection and,
where applicable for internal and supplemental inspections are established by:
a) Maintenance supervisor
b) NBIC or ASME
c) Safety department or operations
d) Owner-user or the inspection
68. According to API 570, Table 6-1, recommended maximum thickness measurement inspection
interval in 3 years. What class piping (or other) is this interval for?
a) Class 3
b) Class 2
c) Class 1
d) Injections points
69. Localized loss in thickness exhibiting directional pattern can occur due to
a) Atmospherical corrosion
b) Microbiologically induced corrosion
c) Erosion-corrosion
d) Sulphidation
Adiestramiento para certificación
API 570 “Inspección, reparación y alteración
De Sistemas de tuberías”
70. In addition to the inspector’s authorization, alterations on a piping system must be approved by:
a) Unit inspector
b) Maintenance supervisor
c) Piping engineer
d) Lead operator
72. What is the normal temperature range specified by API Standard 570 where an insulated carbon
steel piping system is susceptible to corrosion under insulation?
73. Which of the listed should be used as regulate valves associated with the pipe?
74. Materials like carbon, low alloy and other ferritic steels may be susceptible to brittle failure at or
below ambient temperatures. Which of the items below usually is not a concern for brittle failure:
75. An external inspection for process piping, which of the following is not an item you would check for
vibration problems?
Adiestramiento para certificación
API 570 “Inspección, reparación y alteración
De Sistemas de tuberías”
76. You are asked to take thickness (UT) on a piping system of a process unit in a refinery. After you get
the proper okays and reach the piping to be measured, you realized that you cannot place your
hand on the piping; it is too hot. Checking with the operators, they tell you that the temperature of
the line is 400°F. What would you do?
a) Ask the operators to change the process and let the line cool off
b) Since the probe, when hot, reads low, estimate what this is and take the reading
c) Check to see if you have the correct probe and a temperature correction table for it
d) Make sure your couplant works; take the readings and turn them in to the owner
77. A piping system must be check by pressure test, during the process the new test pump continues to
pump over a long period of time with a very slow increase in pressure in the system being
pressured. In your opinion the possible problem may be:
78. A welder that welds a circumferential groove butt weld on a pipe with its axis inclined at 45° F to
the horizontal and welds without rotating the pipe is welding in the ____ position
a) 2G
b) 6G
c) 5G
d) 1G
79. When an inspector checks downstream of control valves, especially when flashing is occurring,
downstream of orifices, downstream of pump discharges, at any point or flow direction change.
The inspector is checking for ____________________________
a) Environmental cracking
Adiestramiento para certificación
API 570 “Inspección, reparación y alteración
De Sistemas de tuberías”
b) Fatigue cracking
c) Creep cracking
d) Erosion and corrosion/erosion
80. An injection point inspection circuit includes a recommended upstream limit from the injection
point, the greater of ______ inches or______ pipe diameters and a recommended downstream
limit of the______ change of flow direction past the injection point, or ______ feet beyond the
______ change in flow direction, whichever is less:
81. To detect interior surface breaking planar flaws the owner/user should specify?
a) Approved inspector
b) Industry qualified UT inspector
c) API qualified inspector
d) Any examiner qualified to carry END
82. What percentage of suspected insulation on a stainless steel class-3 piping operating al 300 °F
should be removed for inspection
a) 0%
b) 10%
c) 25%
d) 50%
83. Other techniques for PMI may be used for qualitative test. One of these is?
85. Thickness measurement location (TML) readings on a piping system indicate that the corrosion rate
has increased. The inspector’s most appropriate response is to:
86. A high voltage holiday detector may be used to test the integrity of the coating, for example when
checking piping that has coatings or if coatings of underground piping are repaired. This detector
shall be :
87. The corrosiveness of the soils (considering buried piping) can be determinate by a measurement of
the soil ____________
a) Impenetrability
b) Susceptibility
c) Erosivity
d) Resistivity
88. Anhydrous hydrogen chloride, hydrofluoric acid and hydrogen sulfide (greater than 3%) are all in
class ____ service
a) 4
b) 3
c) 2
d) 1
a) Low-chloride
b) Low-hydrogen
c) High-silicon
d) High-carbon
91. Local postweld heat treatment (PWHT) may be considered for piping repairs under all of the
following conditions except when the:
92. More TML’s are NOT normally selected for piping systems, what is one of the following
characteristics
93. Measurements from an inspection of a Class 3 pipe reveal an actual metal thickness of 0.35 inch
(8.89 mm). The calculated minimum thickness is 0.25 inch (6.35 mm). If the corrosion rate is .0025
inches (0.064 mm) per year, the next thickness measurement inspection should be scheduled
within:
a) 3 years.
b) 5 years.
c) 10 years.
d) 20 years.
94. On carbon, low-alloy, or other ferritic steels most brittle fracture occur:
95. Inspection of secondary, auxiliary SBP associated with instruments and machinery is:
a) Required
b) Optional
c) Necessary
d) Mandatory
96. Piping than ________ usually use Radiographic for thickness measurements.
a) NPS 3/4
b) NPS 1/2
c) NPS 1/4
d) NPS 1
97. A welder may be performance qualified by visual and mechanically examining welds made in test
coupons or by radiography of the weld test coupons. Alternately a welder may be performance
qualified for a process or mode of arc transfer by:
99. A radiographic testing for the welder qualification is not allowed for which process
d) GTAW
a) Mechanical properties
b) Chemistry
c) weldability
d) Usability characteristics
101. You are sent to check a piping system recently designed, fabricated and installed according to
ASME B31.3. Never been placed in service the owner request that you okay additional piping
that is being added to the system before start up. What would you do as an inspector?
a) Pipe positions 1G y 5G
b) Pipe positions 2G y 5G
c) Pipe positions 3G y 5G
d) None of the above
103. The corrosion rate in deadlegs can vary significantly from adjacent active piping. As an
inspector you should monitor wall thickness on selected deadlegs including:
a) NPS 2.5
b) NPS 3
c) NPS 3.5
d) NPS 2
106. When making a hardness test on piping welds, the hardness limit applied to:
107. A flanged joint is composed of three separate and independent, although interrelated
components. What are these components?
108. What happens if all the air is expelled from a system that is being pressured for a hydro-test?
a) When he has not welded with a process during a period of 6 months or more
b) When he has not welded with a process during a period of 1 months or more
c) When he has not welded with a process during a period of 12 months or more
d) When he has not welded with a process during a period of 3 months or more
110. Who authorized all the repair and alteration works before commencement?
a) Jurisdiction
b) Owner-used
c) Operators
d) Inspector
Adiestramiento para certificación
API 570 “Inspección, reparación y alteración
De Sistemas de tuberías”
111. During periodic scheduled inspections of injection point circuit inspections, more extensive
inspection, a point in a 100 straight section of NPS 3 pipe is checked. The inspector checks an
area __________ upstream of the injection nozzle and he checks downstream for at least ___.
a) 15 inches, 15 ft
b) 12 inches, 2.5 ft
c) 12 inches, 15 ft
d) 10 inches, 10 ft
112. The maximum electrode size for a hot tap root pass on a 24 in. pipe less than ¼ in. thick:
a) 5/32 in.
b) 1/4 in.
c) 3/32 in.
d) None of above
113. Following data is available to compute remaining life of a piping circuit: minimum required
thickness= 0.422, Actual thickness measured= 0.512, corrosion rate= 0.018 in/year
a) 5.0 year
b) 4,5 year
c) 6.0 year
d) None the above
114. Bolts should extend completely through their nuts. Any which fail to do so are considered
acceptable engaged if the lack of complete engagement is not more than:
a) 1/4 ”
b) Two threads
c) One thread
d) 1/2 depth of the bolt
115. All process piping systems must be categorized into different classes. On what are the
classifications selection based?
116. Flanged joints using low strength carbon steel bolts shall not be used above ____ degrees F or
below-20 degree F
a) 500
b) 400
c) 300
d) 200
117. Piping fabricated of or having components of 300 series stainless should be tested with:
a) Steam condensate
b) Water with a pH of 4
c) Water with a chloride content of less than 400 ppm chlorides
d) Water with a pH of 6
118. What is the temperature range specified where an insulated carbon steel piping system is more
critical and susceptible to corrosion under insulation?
119. The service conditions of a new piping system are being changed. In order to determinate the
probable rate of corrosion, one way is to measure the thickness of the pipe after no more than
______ of service by using nondestructive thickness measurements of the piping system.
a) 1 month
b) 6 months
c) 3 months
d) 1 year
121. Which of the following is not a method of detection for hot spots on pipe?
122. Pipe flanges and flanged fittings of ASME B16.5 are obtainable in classes 150, 300, 400,
600,____, 1500 and 2500
a) 700
b) 800
c) 900
d) 1000
123. The maximum internal pressure permitted in the piping system for continued operation at the
most severe condition of the coincident internal or external pressure and temperature
(minimum or maximum) expected during service is known as:
124. The minimum radius of the corners of a small square or rectangular repair welded patch used
to make a temporary repair to a pipe is _________
a) 1.5 inches
b) 1 inch
c) 2 inches
d) ½ inch
125. When a change is made in one or more of the _________________.Welders shall be requalified
for each welding process.
a) Essential variables
b) Testing variables
c) Supplementary variables
d) Non-essential variables
Adiestramiento para certificación
API 570 “Inspección, reparación y alteración
De Sistemas de tuberías”
a) That are flammable but do not significantly vaporize when the leak and are not located in
high-activity
b) With the highest potential of resulting in an immediate emergency if a leak occurs
c) That is not class 1 and 2
d) That is not flammable and pose no significant risk to populated areas
127. Discoloration of the soil, softening of paving asphalt, pool formation, bubbling water, puddles,
freezing of the ground, odor are all:
128. In order to achieve the most accurate projection for the next inspection of TML’s:
129. What is the maximum recommended thickness measurement inspection interval for an injection
point in hydrofluoric acid service?
a) 1 year.
b) 3 years.
c) 5 years.
d) 10 years.
130. Piping systems that are known to have a remaining life over ____ years or that are protected
against external corrosion need to not have insulation removed for the periodic external
inspection.
a) 20
b) 15
c) 5
d) 10
Adiestramiento para certificación
API 570 “Inspección, reparación y alteración
De Sistemas de tuberías”
131. Condition monitoring locations (CML) can be eliminated for piping system with the following
characteristics:
a) Higher potential for creating a safety or environmental emergency in the event of a leak
b) Extremely low potential for creating a safety or environmental emergency in the event of
a leak
c) Low potential for creating a safety or environmental emergency in the event of a leak
d) More complexity in terms of fittings, branches, deadlegs, injection points, etc
a) The date of installation shall be marked on the clamp for future identification
b) A record of the location and the date of installation shall be maintained
c) The clamped line shall be leak tested
d) No further action is required unless the piping leaks again
133. If a backing ring is used in a weld joint where the resulting crevice is detrimental (e.g., subject
to corrosion, vibration or severe cyclic conditions):
a) It should have a maximum tensile stress of at least 10% higher than the weld metal
b) Mechanical or other interlocks shall be provided to prevent separation
c) It should be removed and the internal joint face ground smooth
d) The joint should be removed radiographed to insure full penetration
134. The diameter of electrodes used to weld a small repair patch should not exceed:
a) 1/8”
b) 5/32”
c) 1/4"
d) 3/16”
135. What could happen if the flange bolts and gaskets gradually relax at temperatures in the creep
range?
a) The bolt loads will increase & possible failure may result
b) The bolt loads will reduce & leakage cold occur
c) The bolt loads will increase, causing the gasket to be crushed
d) The flanges may bend because of the temperature
Adiestramiento para certificación
API 570 “Inspección, reparación y alteración
De Sistemas de tuberías”
137. Before any piping system is opened and before some types of external inspection are
performed appropriate ___________________ shall be taken.
a) Review procedures
b) Equipment checks
c) Safety precautions
d) Operation procedures
138. For first time CUI inspections on class 1 systems, the examination should include at least ___
percent of all suspect areas and ____ percent of all areas of damaged insulation.
a) 10, 100
b) 50, 75
c) 100, 100
d) 50, 100
139. The most appropriate technique for measuring thickness of NPS 3/4 pipe is:
a) ET
b) Mechanical
c) UT
d) RT
140. Fewer TML’s can be selected for piping systems with any of the following characteristic:
a) Low potential for creating a safety or environmental emergency in the event of a leak
b) Higher potential for creating a safety or environmental emergency in the event of a leak
c) Extremely low potential for creating a safety or environmental emergency in the event of
a leak
d) More complexity in terms of fittings, branches, deadlegs, injection points, etc.
Adiestramiento para certificación
API 570 “Inspección, reparación y alteración
De Sistemas de tuberías”
141. If buried piping is uncoated, the inspector should check at the soil-to-air interface. He should
call for excavating ___ __ ___ deep to assess the potential for hidden damage.
a) 4” to 10”
b) 6” to 12”
c) 3” to 9”
d) 6” to 8”
142. A closed interval pipe to soil potential survey should be made on buried catholically protected
piping to verify that the piping has a protective potential throughout its length. For poorly
coated pipes where cathodic protection potentials are inconsistent, the survey may be
conducted at ____ intervals for verification of continuous corrosion control.
a) 5 year
b) 2 year
c) 10 year
d) 8 year
143. For Class 1 piping systems, the examination for corrosion under insulation (CUI) should include
at least ___ percent of all suspect areas
a) 50
b) 10
c) 30
d) 0
144. A new piping system normally requires a hydro-static test after completion of construction.
Why?
a) Insure tightness
b) Cover anything that might have been missed during construction
c) Satisfy the owners requirements
d) Stress the system to insure structural integrity
Adiestramiento para certificación
API 570 “Inspección, reparación y alteración
De Sistemas de tuberías”
145. The actual thickness of welded pipe used in refinery service may vary from its nominal
thickness by a manufacturing tolerance of:
a) +0.01 inch
b) +0.01 inch
c) - 0.01 inch
d) +0,01%
146. A pipe is to be hot tapped. The piping engineer has used ASME B31.3 and designed the hot tap
nozzle and the related welds. According to API 570 what other publication should be followed
when making the weld to the in-service pipe?
147. The leak test for buried piping should be for a period of ___ hours
a) 8
b) 24
c) 12
d) 4
148. NPS 2.5 and less requires ____________________ for spot radiography of girth and miter weld
149. If a “pig” is used for cleaning a pipe or if an “intelligent pig” is sued for checking for defects or
thickness the pipe line must be free of restrictions and the bends should be ______ diameter
formed bends rather than 90 degree weld for facilitation of the pigging operation
a) Four
b) Three
c) Five
d) Two
Adiestramiento para certificación
API 570 “Inspección, reparación y alteración
De Sistemas de tuberías”
150. Corrosion under insulation (CUI) that is dependent upon climate is more apt to occur
_______________________
35. A, 73. D,
36. B, 74. C,
37. D, 75. B,
38. B, 76. A,
39. D, 77. A,
40. C, 78. C,
41. C, 79. D,
42. A, 80. B,
43. D, 81. B,
44. B, 82. D,
45. B, 83. A,
46. A, 84. C,
47. C, 85. C,
48. D, 86. C,
49. C, 87. A,
50. D, 88. B,
51. C, 89. D,
52. B, 90. B,
53. A, 91. C,
54. A, 92. A,
55. D, 93. A,
56. B, 94. B,
57. C, 95. D,
58. C, 96. A,
59. B, 97. C,
60. A, 98. C,
61. D, 99. D,
62. A, 100. B,
63. C, 101. A,
64. B, 102. D,
65. A, 103. C,
66. B, 104. B,
67. C, 105. A,
68. C, 106. A,
69. D, 107. D,
70. B, 108. C,
71. A, 109. B,
72. C, 110. C, 8.1.2
111. A, 153. D,
112. A, 154. D,
113. C, 155. B,
114. D, 156. A,
115. C, 157. B,
116. B, 158. C,
117. A, 159. A,
118. C, 160. C,
161. D,
119. D, 162. B,
120. B, 163. D,
121. B, 164. A,
122. C, 165. A,
123. A, 166. B
124. B, 167. C,
125. C, 168. D,
126. D, 169. C,
127. C, 170. D
128. A, 171. B,
129. D, 172. B,
130. B, 173. A,
131. A, 174. D,
132. B, 175. C,
133. D, 176. C,
134. C, 177. C,
135. D, 178. D,
136. B, 179. A
137. A, 180. B,
138. A, 181. C,
139. B, 182. D,
140. D, 183. A
141. C, 184. A,
142. D, 185. B
143. B,
144. B,
145. B,
146. A,
147. D,
148. C,
149. D,
150. A,
151. B,
152. C,
ANSWER KEY B31.3
1. D, 44. B, 87. C,
2. A, 45. B, 88. D
3. B 46. B, 89. D,
4. C, 47. B, 90. B,
5. C, 48. C, 91. C,
6. A, 49. A, 92. D,
7. D, 50. D, 93. A,
8. C, 51. C, 94. B,
9. A, 52. D, 95. C,
10. D, 53. D 96. D,
11. D, 54. B, 97. C,
12. A, 55. A, 98. B
13. B 56. A, 99. B,
14. A 57. C, 100. B,
15. C, 58. D, 101. A,
16. C, 59. C, 102. D,
17. C 60. B, 103. C,
18. B, 61. B, 104. D,
19. A, 62. A, 105. A,
20. D, 63. D, 106. B,
21. C, 64. C, 107. C,
22. D, 65. D, 108. D,
23. B, 66. A, 109. A,
24. A, 67. D, 110. C,
25. A, 68. D, 111. D,
26. A, 69. A, 112. B,
27. D, 70. B, 113. B,
28. C, 71. A, 114. B,
29. B, 72. C, 115. D,
30. B, 73. C, 116. A,
31. A, 74. C, 117. C,
32. D, 75. B, 118. D,
33. C, 76. D, 119. A,
34. A, 77. A, 120. A,
35. B, 78. B, 121. D,
36. D, 79. B, 122. B,
37. D, 80. B, 123. B,
38. B, 81. D, 124. B,
39. A, 82. A, 125. A,
40. A 83. D, 126. C,
41. C, 84. C, 127. D,
42. A, 85. A, 128. A
43. D, 86. A, 129. C
ANSWER KEY API RP 574
1. A, 40.A, 79. A,
2. B, 41.D, 80. D,
3. C, 42.A, 81. B,
4. D, 43.B, 82. B,
5. C, 44.B, 83. C,
6. B, 45.A, 84. D,
7. B, 46.C, 85. A,
8. D, 47.B, 86. B,
9. A, 48.C, 87.C,
10.C, 49.A, 88.D,
11.C, 50.A, 89.A,
12.C, 51.D, 90.B,
13.A, 52.C, 91.B,
14.B, 53.B, 92.C,
15.D, 54.B, 93.D,
16.C, 55.D, 94.A,
17.D, 56.C, 95.D,
18.D, 57.D, 96.C,
19.D, 58.D, 97.B,
20.D, 59.B, 98.A,
21.C, 60.A, 99.A,
22.B, 61.C,
23.A, 62. B,
24.B, 63. C,
25.A, 64. A,
26.C, 65. D,
27.C, 66. D,
28.C, 67. B,
29.D, 68. B,
30.D, 69. C,
31.A, 70. D,
32.B, 71. A,
33.C, 72. B,
34.A, 73. C,
35.D, 74. D,
36.C, 75. C,
37.C, 76. C,
38. D, 77. C,
39.A, 78. B,
ANSWER KEY API RP 571
1. D, 36. A, 71. A,
2. D, 37. D, 72. B,
3. A, 38. C, 73. C,
4. B, 39. C, 74. D,
5. C, 40. B, 75. D,
6. C, 41. A, 76. C,
7. C, 42. B, 77. A,
8. C, 43. A, 78. A,
9. D, 44. C, 79. C,
10. B, 45. C, 80. B,
11. C, 46. D, 81. D,
12. A 47. B, 82. A,
13. A, 48. B, 83. D,
14. C, 49. D, 84. C,
15. C 50. D, 85. C,
16. B, 51. A, 86. D,
17. D, 52. C, 87. A,
18. D, 53. B, 88. C,
19. A, 54. D, 89. D,
20. D, 55. C, 90. D,
21. C, 56. C, 91. C,
22. D, 57. B, 92. C,
23. C, 58. C, 93. B,
24. B, 59. A, 94. D,
25. B, 60. D, 95. B,
26. A, 61. D, 96. D,
27. C, 62. D, 97. A,
28. D 63. D, 98. A
29. C, 64. D, 99. B,
30. D, 65. B,
31. A, 66. B,
32. C, 67. A,
33. C, 68. C,
34. B 69. A,
35. D, 70. D,
ANSWER KEY RP 577
46. D,
1. A, 47. C,
2. D 48. C,
3. D, 49. D,
4. C, 50. A,
5. B, 51. D,
6. A 52. C,
7. B, 53. C,
8. C, 54. B,
9. D, 55. A,
10. D,
11. C,
12. C,
13. C,
14. A,
15. B,
16. A
17. C
18. C
19. B,
20. D,
21. D,
22. D,
23. C
24. A,
25. B,
26. A,
27. B,
28. A,
29. A,
30. C,
31. D,
32. C
33. A,
34. B,
35. B
36. B
37. B,
38. D,
39. C,
40. A,
41. A,
42. C,
43. D,
44. C,
45. A,