DPC Cop PV
DPC Cop PV
DPC Cop PV
This document is for your own use in reviewing content as part of the DPC process.
No further electronic copying is allowed without written permission.
You are permitted to pass on the web link (www.theiet.org/solar-pv) to the registration page;
COPYRIGHT © The IET
from which other people can register and download this document.
You are not permitted to create a direct link to any of the DPC documents.
Contents
1 INTRODUCTION ....................................................................................................................... 7
1.1 Scope and purpose ........................................................................................................... 7
1.2 Document structure ........................................................................................................... 7
NOT FOR COMMERCIAL USE OR REPRODUCTION
1 INTRODUCTION
This Code of Practice sets out the requirements for the design, specification, installation,
commissioning, operation and maintenance of grid-connected solar photovoltaic (PV) systems
installed in the UK.
NOT FOR COMMERCIAL USE OR REPRODUCTION
NOTE: while this Code of Practice does not cover systems with a voltage of less than 30VDC, many of the parts of this
Code of Practice will apply to such systems.
This Code of Practice is aimed at ensuring safe, effective and competently installed solar PV
systems. It will also be of interest to a wide range of stakeholders, including customers, owners,
investors, insurers and financiers of solar PV systems.
Draft for Comment
Standard modules are the mass-produced items seen in most PV systems. They are formed from
an assembly of interconnected crystalline silicon PV cells, encapsulated in a thin layer of resin and
laminated between a glass front and a plastic rear sheet. The laminate is then mounted in a rigid
aluminium frame.
The electrical connection to the module is provided by a pair of connecting cables that exit via a
junction box that is mounted on the laminate rear surface. Polarised plug and socket connectors
are fixed onto the cable ends.
A PV roof tile is designed to replace conventional roofing materials. While similar in many ways to
a standard module, PV roof tiles typically vary in their size and framing details.
The frame of a PV roof tile is designed to allow units to interlock and provide a weather-tight seal.
A variety of materials are used for PV tile frames, including plastics and aluminium.
Draft for Comment
PV roof tiles are also typically much smaller than standard modules, with the size selected to suit
BBIPV is a generic term that describes any module that is used to replace a standard part of a
building envelope, such as a facade or an area of glazing.
The construction of a BBIPV module will depend on the function it is intended to perform,
however, common variations from the design of a standard module include:
COPYRIGHT © The IET
A number of solar cells are wired in series to achieve the desired output voltage of the PV module.
To achieve the desired output current, a number of these series-connected strings of cells may
NOT FOR COMMERCIAL USE OR REPRODUCTION
The majority of PV modules are constructed using crystalline silicon PV cells. These cells are
comprised of a thin wafer of crystalline silicon (either mono-crystalline or poly-crystalline) that has
been chemically treated to create an internal structure that can absorb photons and produce the
desired electrical current.
Thin-film PV is an alternative to crystalline silicon cells and is formed by depositing one or more
thin layers of photovoltaic material on a substrate, typically glass. Thin film is a generic phrase
that is used to encompass a number of different technologies including amorphous silicon,
cadmium telluride (CdTe), copper indium gallium selenide (CIGS) and dye-sensitised and
other organic solar cells (OPV).
Systems shall use modules that have been certified to the following IEC standards:
Design qualification
PV Module type Safety standard
and type approval
Crystalline PV modules IEC 61215
IEC 61730
Thin-film PV modules IEC 61646
Draft for Comment
The module safety standard IEC 61730 defines module application classes and sets out the
relevant safety requirements and necessary tests that need to be performed to verify the
conformance to the requirements of that application class. Three classes are defined:
• Class A module: commonly available ‘standard’ modules. Modules are considered to meet the
requirements for safety class II.
COPYRIGHT © The IET
• Class C module: considered to meet the requirements for safety class III.
• For modules installed in coastal areas: IEC 61701 Salt mist corrosion testing of photovoltaic (PV)
modules.
• For modules installed in wet, highly corrosive agricultural atmospheres: IEC 62716 Photovoltaic (PV)
2.4 Inverters
An inverter is an electrical device that converts direct current (DC) into alternating current (AC).
As the output of a PV module is DC and the UK electricity network is AC, an inverter forms a key
component of a grid-connected PV system.
NOT FOR COMMERCIAL USE OR REPRODUCTION
Domestic-sized string inverters are designed to connect directly to PV strings and typically have
the facility for connecting between one to three separate strings. They are generally single-phase
units with ratings of up to around 4kW.
Commercial-sized string inverters are larger than their domestic counterparts with the facility to
directly connect a larger number of strings. They are generally 3-phase units and come in sizes of
COPYRIGHT © The IET
up to around 15kW.
Central inverters are large, 3-phase units that are designed to be connected to the PV array via a
series of remote combiner boxes (that combine and interconnect the PV strings). Central inverters
range from filing-cabinet sized inverters of a few tens of kW to shipping-container sized MW scale
units. Large central inverters may include an HV transformer to facilitate connection to the HV
grid.
iv. Micro-inverters
At the other end of the scale are micro inverters – small units that are designed to interface with
only one or two PV modules. Micro inverters are typically mounted directly on the rear of the
module and may even be built into the module junction box.
Solar PV CoP :: v1.6 :: Page 10 of 138
© Please do not copy or print
Please send comments – see details on page 1
v. DC optimisers
DC optimisers provide module-level maximum-power point tracking, with the units mounted on
the rear of the PV modules or incorporated into the module junction box. A DC optimiser system
requires a separate inverter to enable the grid connection. There are two distinct architectures:
those that are designed to add on, and work with, another manufacturer’s string inverter, and
NOT FOR COMMERCIAL USE OR REPRODUCTION
The difference between the two inverter types depends on the electrical separation between the
main power output circuits and PV circuits (the AC and DC sides). Inverter requirements are as set
out in IEC 62109-2.
NOTE: The electrical separation may be either integral to the inverter or provided externally, for example, an inverter
with an external isolation transformer.
Draft for Comment
An inverter with a single MPPT tracker is simpler and less expensive, but the PV system must be
designed so that all the strings possess both the same numbers of modules and the same electrical
characteristics.
An inverter with multiple MPP trackers (multiple MPP inputs) can enable strings with a different
COPYRIGHT © The IET
number or type of modules to be connected to the same inverter. Arrays with multiple
orientations or sizes (for example, two adjoining roofs) can benefit from an inverter with multiple
MPP trackers. It is also good practice to use an inverter with multiple MPP trackers (or separate
inverters) to minimize the effect of shading, by installing modules that are suffering the most
shading onto a different MPP tracker than those of the unshaded modules.
The use of microinverters or DC optimizers provides each PV module with their own individual
MPPT tracker. This allows the installation of PV modules over several roof aspects and shading
conditions, and the mixing and matching of module types, even on the same string.
Many string inverters will have a number of string connections available to the installer. It is
important to understand whether these are all interconnected (single MPP) or if they feed
different MPP trackers.
Depending on the type and scale of the system, the inverter may also need to be type tested to
Engineering Recommendation ER G83 or G59. See Section 9 for more details.
MCB
+
L
PV
ARRAY INVERTER N
-
Main earthing terminal
MCB
+ L1
L2
PV L3
ARRAY INVERTER
-
N Main earthing terminal
+
Draft for Comment
PV
INVERTER MCB
ARRAY
L1
+
COPYRIGHT © The IET
PV
ARRAY INVERTER 11kV
3.1 General
While there are many factors to consider in designing a grid-connected solar PV system, the design
of the DC side requires an understanding of three key characteristics of a PV module/array:
(a) A PV array does not have a fixed voltage and current output.
NOT FOR COMMERCIAL USE OR REPRODUCTION
It is therefore important to determine the maximum current and voltage that may occur in
order to select suitably rated system components and configurations.
Unlike most conventional circuits, the short-circuit current of a PV array is not much greater
than its operating current.
Under daylight, the output of a PV module is always live. This, combined with the current-
limiting nature that makes clearing or detecting faults more complicated, means that
particular care needs to be taken to mitigate shock and fire hazards during installation,
operation and maintenance.
Draft for Comment
The IV curve showing the relationships between V MPP, I MPP, V OC, I SC and P MPP.
To re-draw
This chart shows how the module operating and short-circuit currents are affected by changes in
irradinace whereas the open circuit voltage is only weakly affected.
Draft for Comment
Cell temperatures well above and below the STC value of 25°C can be expected in real systems.
To re-draw
include a -15°C line
This chart shows how the module’s open-circuit voltage (V OC ) is affected by cell temperature.
The chart also shows how, at low cell temperatures, the module output voltage can be considerably
above the STC value.
The relationship between module voltage and temperature is dictated by a temperature coefficient.
An example of how this can significantly affect a typical PV array is shown below:
NOT FOR COMMERCIAL USE OR REPRODUCTION
Number of modules: 10
Open Circuit voltage (STC): 37.5V
Temperature coefficient of VOC : -0.32 %/°C
• PV array open-circuit voltage at 0°C (25°C below STC) = 375 + (375 x 0.0032 x 25) = 405V
• PV array-open circuit voltage at -15°C (40°C below STC) = 375 + (375 x 0.0032 x 40) = 423V
To account for the variations in a module’s voltage and current, a system designer needs to apply a
multiplication factor to the STC values. The values to be used in the UK are explained later in this
Code of Practice (see section 5.1).
The behaviour of a PV module when shaded depends on the module construction and also on the
location and extent of the shade across the module. However, even small amounts of shade can
The current that is generated by a PV cell is proportional to the light that falls on it; hence shading
a cell reduces the output of the cell. Where a string of cells are connected together in a series,
shading any cell in the string results in the output current of the entire string falling to the level of
the shaded cell. In these circumstances, the current from the unshaded cells is driven into the
shaded cell – which, if the current is great enough, becomes reverse biased and starts to dissipate
the current flowing from the other cells. This has the effect of heating up the cell casing a ‘hot
spot’.
COPYRIGHT © The IET
Hot spot heating has the potential to cause serious damage to a module and can ultimately result
in fire. To limit the effect of shade and hot spot heating, bypass diodes are connected in parallel
across a group of cells within a module. In normal operation the bypass diode does nothing (the
diode is reverse biased so does not conduct). However, where sufficient shading occurs, the diode
becomes forward biased and conducts the current from all the unshaded cells in the module
string.
NOTE: The above diagram shows how a faulty bypass diode can result in a drop in module voltage. Bypass diodes can
often fail short-circuited, which results in a loss of output from the cells they are connected across.
To re-draw
Fault currents above the maximum series fuse rating present a safety risk and must be addressed
within the system design.
Potential Induced Degradation (PID) reduces the power output of a cell. It occurs when the
voltage between the cell and the ground drives ions from the module glass (and other parts of the
PV laminate) into the semi-conductor material of the solar cell. These ions establish shunt circuits
Certain types of PV modules are more prone to PID and the manufacturers may specify particular
earthing arrangements for the PV system. Some PID effects can be reversed, and the full output of
a module restored, by connecting one of the DC current-carrying conductors to earth (connecting
DC-negative to earth for a p-type module). This is termed ‘functional earthing’ and is covered
later in this Code of Practice (see section 5.10).
Draft for Comment
4 System performance
Similarly, financial calculations may influence the array pitch and orientation. For example,
To re-draw
Draft for Comment
(a) an increased pitch may be preferable on a site subject to regular snowfall to ensure that the
snow is shed effectively.
(b) an increased pitch will improve the self-cleaning of modules by rainfall - a minimum pitch of
15° is recommended for self-cleaning to be effective. This becomes particularly significant for
sites subject to considerable dust and dirt build-up.
(c) a flatter pitch will maximise summer generation, a steeper pitch winter generation. Certain
systems / applications may need to optimise for winter or summer generation.
NOTE: off-grid systems often install arrays with a steeper pitch to maximise winter production – a time of the year
when electricity demand may be at its highest and the sun low in the sky.
Mounting frames that track the sun can be installed to maximise the output from a PV array. Both
single-axis and dual-axis (pitch and orientation) trackers are available. While beneficial, the
increased output of a solar-tracking array has to be balanced against the increased initial cost and
subsequent maintenance requirements. Tracking systems generally only prove financially viable
for sites with wide horizons and very little shade. Alternatively, some sites may opt for the use of
Solar PV CoP :: v1.6 :: Page 21 of 138
© Please do not copy or print
Please send comments – see details on page 1
adjustable mounting systems that allow for seasonal adjustments of array pitch. A typical
seasonally adjustable system would typically pitch the array at 15° less than the site latitude for
summer and 15° more than the latitude during winter.
Table xx
Effect of orientation and pitch on array performance (% of ideal)
NOT FOR COMMERCIAL USE OR REPRODUCTION
NOTE: when using a compass to orientate a PV array, it is important to allow for magnetic variation – the array needs
As noted previously, a pitch of 15° is generally considered to be the minimum requirement for a PV
Soiling from birds can be a problem in some areas. Deterrent measures such as the use of hawk
sirens may need to be implemented on some problem sites. Suspending netting or strings above
the array is sometimes suggested, but the increased shading from such measures may not justify
the benefit from reduced soiling.
Far shading occurs due to the sun being obscured by hills or other objects away from the
immediate vicinity of the array. The effect of far shading is to reduce the number of hours that an
array receives ‘direct beam’ radiation from the sun. Far shading is typically worse during the
winter months when the sun is low in the sky. There is generally very little that can be done to
influence the impact of far shading at a given site.
Much can be done to lessen the effect of near shading. The most significant benefits can be
obtained by siting arrays away from locations affected by near shade. Removing or relocating
shade objects are also often good solutions for many sites (for example, objects such as TV aerials
are usually easy to move).
System design can also impact on the losses due to near shading. The string design of a PV array
should always consider the presence of any near shade objects. Where possible, the array should
NOT FOR COMMERCIAL USE OR REPRODUCTION
current.
(b) Over-power loss: these are losses that occur at times when the array is generating more power
than the inverter can handle. At such times the inverter will generally limit its power output to
its upper threshold.
Note: it is common practice to design a system with an inverter that has a power rating lower
than the rating of the array (see section 7.1.2).
(c) Under-power loss: occurs during periods of low irradiance when the array is generating
insufficient power for the inverter to operate.
(d) MPP voltage range losses: this occurs when the array has a voltage that falls outside of the
MPP voltage window of the inverter. For a well-designed and specified system, this should be
a rare occurrence.
Good design practice for a PV system is to achieve no more than 3% losses in the AC cables of a PV
array.
This models losses that occur due to times where the system cannot operate due to equipment
failure.
afternoon.
summer months.
(a) Any PV evaluation presented to a client shall include information on the design assumptions
NOT FOR COMMERCIAL USE OR REPRODUCTION
(b) A statement of the shade situation on the array – to include both near and far shade. Where
shade losses have been allowed for, the method used to calculate the effect of the shade shall
be shown. The estimated reduction in annual output due to shade shall also be stated.
NOTE: systems installed under the Microgeneration Certification Scheme (MCS) will need to use the MCS
performance estimation procedure to estimate the system performance.
4.6 Warranties/guarantees
When evaluating the performance of a grid-connected PV system, a number of
warranties/guaranties need to considered, including:
Draft for Comment
For example, the following calculations show the minimum voltage and current ratings for the
components in a specific PV string:
String data: Number of modules in series = 10; Module Isc = 4.3A; Module Voc = 35.0V
Due to their differing characteristics, it is not possible to provide a simple pair of multipliers to
apply to modules that are not constructed using crystalline silicon cells. For such modules
installed in the UK, individual calculations need to be performed as follows:
Using manufacturer’s data, the values of Voc and Isc shall be calculated assuming a minimum
temperature of -15°C and a maximum irradiance of 1,250 W/m2.
When calculating system component ratings, any increase to module voltage and current due to an
initial soaking-in period shall be allowed for in calculations. This shall be applied first (and in
COPYRIGHT © The IET
addition to) any other calculations, such as the temperature/irradiance calculation shown above.
NOTE: in some circumstance, the initial increase to array output parameters may be in excess of what the system
inverter is able to accept. In such cases, the array can be left disconnected for the soaking-in period.
Module class
Class A modules shall be used
(IEC 61730)
Solar PV CoP :: v1.6 :: Page 28 of 138
© Please do not copy or print
Please send comments – see details on page 1
Cables shall be selected and erected so as to minimise the risk of earth faults
DC cables and short-circuits.
NOTE: this table describes PV systems in the voltage range of 30-1,500VDC. Systems outside this band can have
different requirements.
The following tables set out the current-carrying capacity required for the DC circuit (cables,
isolators, switchgear and connectors) for a system formed of standard crystalline silicon modules:
For other module types the 1.25 multiplier used above shall be replaced by the figure calculated for
COPYRIGHT © The IET
NOTE: for systems with module power optimisers – see clause xxx.
Where the overcurrent protection device is a fuse, it shall be of a type gPV (in accordance with IEC
60269-6).
Where the overcurrent protection device is a circuit breaker, it shall be xxx (TBA).
The overcurrent protective device shall be rated for the maximum system voltage (as calculated in
section 5.2).
(a) for systems with a functional earth, be placed in all unearthed conductors.
(b) for systems without a functional earth, be placed in one of the active conductors.
String overcurrent protection shall be fitted to all PV arrays (and sub-arrays) where:
i. Device selection
Draft for Comment
The string overcurrent protective device shall be selected with an operating current (I N ) such that:
single inverter.
i. Device selection
The sub-array over-current protective device shall be selected with an operating current (I N ) such
that:
NOTE: the sub-array multiplier (1.25) is lower than the string multiplier (1.5) to allow for design flexibility. However, this approach may
result in nuisance tripping and should be avoided for sites with high irradiance levels.
NOTE: the array multiplier (1.25) is lower than the string multiplier (1.5) to allow for design flexibility. However, this approach may
result in nuisance tripping and should be avoided for sites with high irradiance levels.
The array over-current protective device shall be selected to have a sufficient interrupt rating for the
maximum prospective fault current from the battery, or other fault current source.
The PV array shall be equipped with devices for isolation and switching according to the following
table:
Minimum
Notes on application and means of isolation
NOT FOR COMMERCIAL USE OR REPRODUCTION
The DC switch-disconnector shall be tested to BS EN 60947-1 and BS EN 60947-3 and have a switching
mechanism with a ‘snap’ action (independent manual operation). DC switch-disconnectors shall not be
polarity sensitive.
COPYRIGHT © The IET
NOTE 1: the switching action of the device is of importance, because when switch contacts open a circuit under load,
there is inevitably at least a short-lived arc that must be extinguished. Excessive arcing can lead to high resistance
faults in the device. Sprung, snap action devices minimise the duration of the arc.
NOTE 2: devices must not be polarity sensitive as fault currents can flow in either direction in a PV array.
The switch-disconnector shall be labelled: “PV array DC isolator” with the ON and OFF positions clearly
indicated. The switch enclosure shall also be labelled: “Danger contains live parts during daylight”.
Where the DC switch-disconnector is built into the inverter, it shall permit the array to be safely isolated
from the inverter (for inverter maintenance/repair) by complying with one of the following:
(a) a switch-disconnector that is mechanically connected to the inverter chassis in a manner that
allows the rest of the inverter to be removed from the switch chassis without risk of electrical
hazards.
(b) a switch-disconnector arrangement that only permits access to the serviceable section of the
inverter when the switch is in the open (off) position.
NOT FOR COMMERCIAL USE OR REPRODUCTION
NOTE: these options are provided to ensure that a system using an inverter with a built-in switch-disconnector retains
some means of array isolation to permit safe inverter repair or maintenance. Smaller inverters are typically removed
for replacement and repair - in such cases the array must be safely isolated while the inverter is removed (for
example, connecting the array to the inverter by suitable plug and socket connectors) . For larger inverters, repair is
usually done by replacing internal components – in such cases the array must be safely isolated from the serviceable
portion of the inverter during works.
Combiner boxes shall be rated for the voltage and current maxima calculated for the circuit (see
sections 5.2 and 5.3).
The combiner box shall be labelled “PV array combiner box, Danger contains live parts during
daylight”.
Where plug and sockets are mated together in any part of the PV array circuit, they shall be of the
same model and from the same manufacturer.
The plug and sockets shall be rated for the voltage and current maxima calculated for the circuit
(see sections 5.2 and 5.3).
Unless installed in an area with access that is restricted to trained and authorised personnel, all
NOT FOR COMMERCIAL USE OR REPRODUCTION
Unless installed in an area with access that is restricted to trained and authorised personnel, all
plug and socket connectors shall be labelled: “Do not disconnect under load”.
Plug and sockets fixed to cable ends on site shall be assembled in accordance with manufacturer’s
instructions using designated crimp and assembly tools.
NOTE: the use of an incorrect crimp or assembly tool can have a devastating effect on the effectiveness of a PV
connector and can cause overheating and fire issues.
Voltage Rating
(a) PV array cables shall be rated for the DC voltage maxima calculated for the circuit (section 5.2).
Current rating
(a) PV array cables shall have a DC current-carrying capacity (CCC) of greater than the current
maxima calculated for the circuit (section 5.3).
(b) The cable CCC shall be calculated to include any relevant de-rating factors (installation
Draft for Comment
PV string cables shall comply with the requirements of IEC xxx (not yet published).
As discussed earlier in this Code of Practice, the particular nature of PV circuits (current limiting)
means that additional protective measures need to be applied to provide for fire and shock
protection.
All systems shall have cables selected and erected to minimise the risk of earth faults and short
circuits. All cables shall be provided with basic and reinforced insulation.
Common methods for providing basic and reinforced insulation are shown in the table:
+ Single conductor
cable - both insulated For example, PV cables to IEC xxx
and sheathed
+ -
Single conductor
+ - cable in Uncommon
conduit/trunking
Cables installed within buildings may need to meet additional requirements, such as use of LSF
(Low Smoke and Fume) cable types.
Standard PV cables (cables to IEC xxx) shall not be buried in walls or otherwise hidden in the
building structure. Where this cannot be avoided conductors shall be suitably protected from
mechanical damage. Suitable methods of protection may include the use of metallic trunking or
Where cables are buried in walls, a plan showing cable locations shall be provided in the system
Operation and Maintenance (O&M) manual.
NOTE: standard PV cables are not suitable for direct burial in walls as mechanical damage would be very difficult to
detect and could lead to a fire risk.
even after DC isolators have been operated. As a result, DC cables need to be clearly identified.
Labelling every 5-10m is generally considered sufficient on straight cable runs. Where cable routes
are more complicated, additional labels may be required.
With smaller systems and relatively short cable runs, it is cost effective to increase cable sizes so
that the losses remain small. On larger systems, however, cable sizes may need to be influenced
by the financial return calculations.
For systems of up to 50kWp, cables shall be sized such that the energy loss at the rated power
(Vmpp, Impp) is less than 3%.
(c) insulation damage due to thermal or wind cycling of cables or other components; and
(d) impact or storm damage.
While proper selection and erection of system components will minimize the likelihood of such
problems developing, it is necessary to implement isolation fault-detection measures to detect any
problems that may develop over time. These measures will typically be included within the
inverter for most systems. However, larger systems with central inverters will often use separate
NOT FOR COMMERCIAL USE OR REPRODUCTION
Both Earth Insulation Resistance and Residual Current Monitoring systems are used to detect
developing isolation faults. These measures need to be implemented together and tailored to suit
the system type.
A PV array needs to have an insulation resistance sufficiently high enough to minimise the extent
of earth leakage currents. Earth leakage currents will naturally occur in all PV arrays, primarily
from the PV modules but also from other parts such as the cabling. The purpose of the ongoing
insulation resistance measurement is to detect and prevent any significant earth leakage currents
NOTE: the extent of naturally occurring leakage currents is determined largely by the size of the PV array (the larger
the surface area, the lower the insulation resistance).
Earth insulation resistance is calculated by applying a voltage between the array and earth and
measuring the amount of current that flows. The insulation resistance can then be determined
using Ohms law.
All PV arrays shall have a system that measures the insulation resistance from the PV array to
Draft for Comment
earth. Measurements shall be performed before starting operation and at least once in every
The earth insulation fault thresholds shall be determined according to the following table:
System size (kW) Minimum resistance
≤20 30kΩ
>20 to ≤30 20kΩ
>30 to ≤50 15kΩ
>50 to ≤100 10kΩ
>100 to ≤200 7kΩ
>200 to ≤400 4kΩ
COPYRIGHT © The IET
≥400k 3kΩ
On detecting a fault, the system shall trigger the Earth Fault Alarm (see section 0).
Systems using inverters with at least simple separation: when a fault is detected, the inverter
can continue to operate.
Systems using inverters without at least simple separation: when a fault is detected, the
inverter shall shut down and isolate the PV array from the grid.
While smaller PV systems will rely on the insulation resistance measurement systems built into the
inverter, larger systems will typically use a stand-alone device. Such devices permit the fault
Solar PV CoP :: v1.6 :: Page 37 of 138
© Please do not copy or print
Please send comments – see details on page 1
threshold to be manually set during system commissioning. These devices can also be distributed
around the array, such as at combiner boxes (rather than at the inverter) to provide improved
fault discrimination.
Where stand-alone insulation monitoring devices are used, the fault thresholds shown in the table
above should be considered as minimum values and it is recommended that increasing the
thresholds be considered. A higher value will increase system safety by detecting potential faults
NOT FOR COMMERCIAL USE OR REPRODUCTION
A residual current monitoring device (RCM) monitors the current on the two cables that supply a
circuit. In an ideal fault-free system, the sum of the two currents should be zero.
For PV arrays, two types of RCM systems are implemented. The first looks for a continuous and
excessively high residual current; the second looks for a sudden or step change and is designed to
protect against fire due to the onset of a fault.
NOTE: installation of an RCM is not required for systems using an inverter with at least simple separation and
where there is no functional earth.
The RCM shall incorporate both continuous and step-change monitoring, with fault thresholds
determined according to the following table:
RCM Trip setting Response time
Draft for Comment
The RCM shall measure the total RMS current (so as to include AC and DC components).
On detecting a fault, the system shall trigger the Earth Fault Alarm (see section 0).
Systems using inverters with at least simple separation: when a fault is detected, the inverter
COPYRIGHT © The IET
Systems using inverters without at least simple separation: when a fault is detected, the
inverter shall shut down and isolate the PV array from the grid
Like the measures to implement insulation resistance monitoring, many larger systems will use a
stand-alone RCM device. Similarly, these devices can be distributed around the array, such as at
combiner boxes, to provide improved fault discrimination.
(a) continue to operate until the system is switched off or the fault is corrected;
(b) be of a type that can’t be missed (for example, visible/audible signal in a public area, or SMS
NOT FOR COMMERCIAL USE OR REPRODUCTION
(c) be accompanied with instructions to the system operator on the need to immediately
investigate the fault.
NOTE: early earth fault alarms relied solely on a flashing light on an inverter – this is not considered an effective
solution as many inverter locations mean that such warning lights can be easily missed. Consequently, the IEC inverter
standard (IEC 62019) now requires that inverters have both a local indicator and a means of remote signalling.
NOTE: the main reason functional earthing is not generally recommended is that when fitted it only takes one earth
fault to enable a fault current to flow (with an un-earthed or ‘floating’ DC system, two faults are needed before an
earth fault current can flow).
A system with functional earthing shall be specified to meet the following requirements:
•
Draft for Comment
a functional earth shall only be installed on systems that include at least simple separation
between the AC and DC sides. Simple separation can be provided by a transformer within the
• the functional earth connection shall be made at one point only and as close as possible to the
DC terminals of the inverter (or within the inverter).
• the functional earth connection shall be connected to the main earthing terminal of the
electrical installation.
COPYRIGHT © The IET
With a floating system, the inverter can detect an earth fault and signal an alarm before any further
problems occur. With a functionally earthed system, fault currents will flow immediately. To mitigate the
potential effect of this, two solutions can be adopted: connect the functional earth either via a resistor (to
limit the potential fault current) or via an overcurrent protective device (which should trip if a significant
fault current then flows).
The functional earth connection shall be either via a resistor or via an overcurrent protective device.
Where the connection is via a resistor the resistance value shall be the highest value allowable under
the module manufacturer’s instructions. The system shall also incorporate measures for insulation
monitoring as set out in section 5.9.
Where the connection is via an overcurrent protective device, the device shall meet the general DC
overcurrent protective device requirements as set out in section 5.4.
Solar PV CoP :: v1.6 :: Page 39 of 138
© Please do not copy or print
Please send comments – see details on page 1
When the functional earth interrupter operates, the system shall trigger the Earth Fault Alarm (see
section 0).
The rating of this device shall be selected according to the following table:
(a) Protective equipotential bonding is is defined in BS 7671 as an electrical connection that maintains
(c) Earthing for lightning protection is a connection to earth as part of lightning protection system (LPS).
(d) Array frame functional earthing is the connection of the array frame to earth to enable a part of the PV
Draft for Comment
system to function correctly. In general, array frame functional earthing is specified to ensure that the
As shown in the diagram below, it is necessary to determine if the array frame needs:
Where more than one of these requirements apply, the most onerous requirement needs to be
applied. Where none of these requirements apply, a functional earth connection is required.
The following diagram shall be used to determine the requirements for array frame earthing and bonding
COPYRIGHT © The IET
arrangement.
Array frame
protective
equipotential
a) Is the array frame an
bonding
extraneous conductive part?
NOT FOR COMMERCIAL USE OR REPRODUCTION
Connect to earth
NOTE: some type of connection between the array frame and earth will be required in all installations.
T he requirements described in this diagram apply only to PV arrays constructed using electrically
conducting and interconnected metallic frames. The following mounting structures do not require array
frame earthing:
• array mounting structures that are comprised wholly of non-conducting materials (for example, plastic,
wood etc).
• array mounting assemblies that use discrete metallic elements (for example, brackets, bolts) in such a
manner that there is no electrical path from the frame of one module to another.
(a) the cable shall have a cross-sectional area of not less than 2.5mm² if sheathed or otherwise provided
with mechanical protection, or 4mm² if mechanical protection is not provided.
Solar PV CoP :: v1.6 :: Page 41 of 138
© Please do not copy or print
Please send comments – see details on page 1
(b) it shall be connected to any suitable earthing terminal, such as the buildings main earthing terminal or
an earthing terminal within the device that provides the DC isolation fault detection (typically the
inverter).
(c) it shall link to each electro-mechanically interconnected array block (typically a row of modules on a
pair of aluminium mounting rails) such that all parts of the PV array frame are connected to earth.
(d) the cable shall be laid in parallel to, and in as close contact as possible with, the DC array cables
NOT FOR COMMERCIAL USE OR REPRODUCTION
NOTE: in the above diagram it is assumed that a sufficient electrical connection exists between the array mounting rail
and the PV module. In some circumstances (for example, where rubber washers are used to provide galvanic isolation
between dissimilar metals), additional earth cables may be required.
Draft for Comment
Where the PV system is connected to an installation with a TN-C-S (PME) supply AND where the PV array is
generally accessible (for example, ground mounted), a local earth electrode shall be provided at the array
location. The electrode shall be provided in accordance with BS 7671 section 542.2. The electrode shall be
bonded to the buildings main earthing terminal and also connected to the PV array frame earth.
NOTE: ground-mounted arrays that use a metal frame embedded into the ground are likely to provide a sufficient
connection to earth without the need of an additional earth electrode.
NOT FOR COMMERCIAL USE OR REPRODUCTION
Typical functional earthing arrangements for ground mounted systems connected to a TN-C-S (PME) supply).
The arguments for and against earthing an array frame are relatively complex and cannot be described in
detail within this Code of Practice. However, the approach whereby PV array frames are earthed in all
circumstances has the advantages of:
(a) allowing the DC isolation fault detection systems that are now provided within inverters to operate
correctly (earth insulation resistance; residual current monitoring);
(b) removing the shock risk due to leakage currents on systems with transformer-less inverters; and
COPYRIGHT © The IET
(c) bringing the UK in line with the approach taken in most other countries around the world (and IEC
standards/documents).
In some circumstances an installer may need to work on or inspect a system installed to a previous
standard that did not require array frame earthing:
(a) where an old inverter is being replaced by a modern device that includes DC isolation fault measures, it
is recommended that, where practical, the installation of an array frame earth be included as part of
the replacement works.
(b) where an installer is performing an inspection test on an older system, it is recommended that the lack
of an array frame earth be noted on the condition report.
IET Guidance Note 8 Earthing and Bonding contains details on how to test a part to determine if it should
NOT FOR COMMERCIAL USE OR REPRODUCTION
NOTE: while the resistance test method may be practical on domestic installations, due to the distance to the main
earthing terminal, it may be impractical on larger commercial insulations. Refer to Guidance Note 8 for further
information.
Examples
Array frame unlikely to be an extraneous Array frame likely to be an extraneous
conductive part conductive part
Where the array frame is directly fixed to a metallic structural part of the building that is in itself bonded,
providing a good electrical contact is made between the array frame and the metallic building part, an
additional bonding cable to the array frame may not be required.
Draft for Comment
As described in Section 2.3, systems using Class B modules are not permitted by (and are out of the scope
of) this Code of Practice. Consequently, all PV arrays will use either Type A or Type C modules and be
considered either Class II or Class III devices – which, by definition, are not considered exposed conductive
parts.
In some circumstance, inverters or other electrical apparatus may be bolted directly to the PV array frame.
Where any of these pieces of equipment are Class I, the array frame needs to be considered as an exposed
COPYRIGHT © The IET
conductive part.
The measures that should be adopted on the DC side of a PV system to protect the system against lightning
and overvoltage is discussed in Section 6 of this Code of Practice. However, in addition, the following
installation practices need to be addressed when specifying and installing the DC circuits:
NOT FOR COMMERCIAL USE OR REPRODUCTION
When a new structure or system is installed, consideration has to be given to the possible effects
caused by either a direct or indirect lightning strike. The safety and the protection of both life and
reliance on the uninterrupted operation of electrical and electronic systems need to be assured.
To achieve these goals it is recommended that the design, installation and testing of the lightning
and surge protection systems be carried out by a suitably qualified specialist.
NOT FOR COMMERCIAL USE OR REPRODUCTION
BS EN 62305 is the UK’s Lightning Protection standard. The complete Standard consists of four
separate documents.
The actual risk (R) is compared with the tolerable risk level (R T ), contained within the Standard to
determine if a problem exists with the specific risk being considered. Should the actual risk be
higher than the tolerable risk, the degree to which the actual risk is higher will determine the level
of solution required.
Draft for Comment
In many cases (for example, for a typical domestic PV installation), there will be no requirement
for a dedicated LPS or for any additional surge protection device (SPD) to be fitted. Where it is
considered that SPD protection is required, the presence and type of any SPD factory fitted within
an inverter should be checked, as these may prove sufficient.
NOTE: some inverters have the facility for an installer to install an additional SPD within the device.
COPYRIGHT © The IET
Solar PV installations on tall or exposed buildings, or on buildings that already have an LPS fitted,
will need particular scrutiny. Installations in open fields and/or with long cable runs will similarly
require close scrutiny.
Depending on the specific requirements of other aspects on the project, either an equipotentially
bonded or an isolated lightning protection system may be specified.
An isolated lightning protection system keeps lightning currents out of the structure or the system
being protected. Separation distances need to be calculated and maintained between the lightning
protection system, structure and metallic services. An isolated design can be applied to the whole
Solar PV CoP :: v1.6 :: Page 46 of 138
© Please do not copy or print
Please send comments – see details on page 1
structure or parts of the structure, thus making it an ideal system for roof-mounted PV systems,
etc.
An SPD operates by diverting or limiting potentially harmful surge currents. Two types of SPD
generally need to be considered:
(a) Type 1: a device designed to discharge very high levels of current. Only installed where an LPS
is present
(b) Type 2: a device intended to divert induced lightning currents and used to protect particular
components or parts of a system.
Only an SPD with a suitable rating to meet the circuit it is being installed upon (voltage rating,
NOTE: SPDs designed specifically for the installation on DC PV circuits are readily available. Many commercially
available PV combiner boxes come with SPDs pre-fitted.
Any data or control circuits that form part of the PV system also need to be considered as part of
NOTE: SPDs specifically designed for data lines are readily available.
COPYRIGHT © The IET
LPZ 0 Systems in unprotected external areas or structures. The internal systems may be
LPZ 0 Systems in external areas, but protected against direct lightning strikes. The internal
B systems may be subjected to partial
Zone where the surge current is limited by current sharing and isolating interfaces
LPZ 1 and/or by SPDs at the boundary. Spatial shielding may attenuate the lightning
electromagnetic field.
COPYRIGHT © The IET
Further Zones where the surge current may be further limited by current sharing,
LPZ 2 ..n
additional SPDs and spatial shielding.
The lightning current or surge arrester specification would be selected as a suitable means of
meeting the requirements of the zonal interface being protected as defined above.
Typical examples
When installing a PV system, a distinction is made between buildings with and without external
lightning protection.
NOT FOR COMMERCIAL USE OR REPRODUCTION
maintained.
The correct type and mounting position of the surge protection devices are largely dependent
NOT FOR COMMERCIAL USE OR REPRODUCTION
For HV connected systems, the design of any lightning protection scheme will need to be specified
in close co-ordination with the HV system design and its associated earthing scheme.
Typical examples
Where a lightning risk assessment indicates that protective measures need to be implemented, the
following provide examples of typical schemes:
7 Inverters
NOTE: worst case cell temperature values for the UK are generally taken to be -15°C to 80°C
Typical power ratios for the UK are in the range of 80-110% (for example, for a 1kWp array, an
When considering the most appropriately inverter size, the following oversizing/undersizing
considerations should be considered.
infrequently in the UK. Consequently, inverters will spend much of their time operating at
power levels below the nominal array rating.
(b) Inverter efficiency is generally lower when operating at low power levels. With a degree of
inverter undersizing, it is possible to take the normal operating regime higher up the efficiency
curve – and hence decrease inverter losses at times of normal irradiance levels.
(c) The array is located in a sub-optimal location, orientation or pitch and as such is expected to
produce a lower than normal output.
(d) When a grid-connection limit is imposed on a site it may be beneficial to considerably overrun
the inverter to gain maximum generation. An example may be a domestic inverter of 3.68kW
with a 6kW array connected so as to produce more power when in sub-optimal conditions.
Manufacturers will provide guidance on the maximum undersizing possible.
(e) While a larger inverter may provide a system with a higher output power, the increased annual
yield may not be justified by the extra cost (i.e. the system has a lower IRR).
In addition to these, the inverter will need to comply with the relevant inverter standards
described earlier in this Code of Practice.
NOTE: this can be verified from the inverter data sheet and/or by ensuring that the manufacturer’s software is set up
for a cell temperature of down to -15°C.
Inverters shall also be selected to meet the phase balancing requirements of ER G59.
NOTE: engineering recommendation ER G59 states a maximum imbalance of 16A between the highest and lowest
Draft for Comment
phases.
Inverters shall be installed in a location that is suitable to their design and the manufacturer’s
specifications.
COPYRIGHT © The IET
(a) Indoor or outdoor location: usually dictated by the inverter IP rating, however, specific
manufacturer’s instructions can sometimes also influence location.
(b) Ventilation requirements: inverters generate heat during operation. Boxing in of inverters or
placing a number of inverters in a small unventilated room can lead to thermal shutdown on
sunny days. In some cases air-conditioning may be required.
(c) Clearance distances: most manufacturers will specify minimum clearance distances from the
front, side, top and bottom of the inverter. These clearances are required to enable good air
flow over heat sinks as well as to allow sufficient access for installation and servicing.
(d) Cabling requirements: the inverter location needs to be considered with respect to the DC and
AC cable runs required. For installations within buildings, it is generally considered good
practice to minimise the length of any DC cables within the building envelope (see fire section
for further information – section 11.4). Consequently, an inverter location immediately
adjacent to the array may be most suitable.
(e) Access requirements: safe access for installation and subsequent maintenance needs to be
NOT FOR COMMERCIAL USE OR REPRODUCTION
(f) Orientation: for wall mounted inverters, some manufacturers will specify orientation
limitations.
(g) Weight: the weight of the inverter needs to be considered, both in terms of the fixings used to
mount an inverter to a wall and for lifting an inverter into its intended location.
Larger central inverters are typically installed within a purpose-built walk-in container that is
supplied pre-installed with all the necessary switchgear and wiring assemblies. For open-field
Draft for Comment
arrays the location of the inverter will need to be selected to suit AC cable routes and at a location
To re-draw
Draft for Comment
To re-draw
The PV system shall be installed on to a dedicated circuit that is connected to no other current
using equipment (other than any PV system data-logger or similar equipment).
NOT FOR COMMERCIAL USE OR REPRODUCTION
The overcurrent protective device shall be selected and erected according to the requirements of
BS 7671.
The overcurrent protective device shall also be selected in accordance with the inverter
manufacturer’s instructions. Where the device protects a circuit that feeds more than one
inverter, the device should be selected such that it is acceptable to all the inverters on that circuit.
When installing isolators in the AC circuit that feeds the inverters, cables should be connected
such that the isolator terminals labelled ‘supply’ are connected to the cables from the mains and
the terminals labelled ‘load’ are connected to the cables from the inverter(s).
Where the inverter is installed in a different room to the main isolator, a local isolator shall be
mounted adjacent to the inverter to facilitate maintenance of the inverter.
COPYRIGHT © The IET
8.5 Cables
The cables used for the AC circuit that feeds the inverter(s) in a grid-connected PV system shall be
selected and erected so as to comply with the requirements of BS 7671.
The cables used for the AC circuit that feeds the inverter(s) shall be sized so as to minimise voltage
drop and power loss.
NOT FOR COMMERCIAL USE OR REPRODUCTION
Where an installation is constructed using pre-assembled cable harnesses (for example, the cable
Draft for Comment
systems provided with some micro-inverter products), it is important to ensure that the cable
An inverter that does not include simple separation (often referred to as a ‘transformer-less
inverter’) may be able to feed a DC fault current into the AC side. This DC element may not be
picked up by a conventional RCD and may also hinder its normal operation. A Type B RCD is, by
construction, able to handle and detect both AC and DC residual currents.
Draft for Comment
NOTE: this is necessary to ensure the continued safe operation of the RCD, prevent the possibility of a fault on a
circuit continuing to be fed by the inverter for up to five seconds after an RCD has tripped, and prevent nuisance
tripping.
A G59 relay is a monitoring device that controls a contactor that sits between the PV system and
COPYRIGHT © The IET
the connection to the grid. The G59 relay monitors the grid voltage and frequency – and, if it
detects a fault, it de-energises the contactor, disconnecting the PV system from the grid.
A typical connection scheme for a G59 relay is shown in the diagram below. Important features to
note are:
(a) the sense connection should always be on the mains (grid) side of the main contactor; and
(b) auxiliary contacts on the main contactor are recommended to facilitate timing of the contactor
operation during commissioning tests.
For each of the protection settings, G59 sets out a response time (trip-delay time) that the relay
The requirements for the design, installation and testing of a G59 relay are set out in Engineering
Recommendation G59 – see Section 9.3 of this Code of Practice for more information
The design of the AC connection also needs to take into account other electrical apparatus
installed within the facility.
(a) an automatic point of isolation on the inverter AC cable that is de-energised when the genset is
brought into operation (for example, via an auxiliary set of contacts on the genset changeover
switch).
Solar PV CoP :: v1.6 :: Page 60 of 138
© Please do not copy or print
Please send comments – see details on page 1
(b) for installations that include additional G59 relay protection, isolating the G59 relay at times
when the genset is in operation (with no power to the G59 relay, the main contactor on the PV
system feed will be in the open position).
(c) connecting the PV system to the distribution board that supplies the non-essential side of any
installation (the circuits that are all automatically isolated when a genset is running).
NOT FOR COMMERCIAL USE OR REPRODUCTION
NOTE: this is necessary to ensure correct functioning of the inverter and to enable the G83/G59 protection settings to
function correctly.
Where a PV system is to be connected to an installation that includes any power factor correction
devices, the PV system shall be connected on the grid side of the power factor correction devices.
Published by the Energy Networks Association, Engineering Recommendations G59 and G83 set
out the construction and commissioning requirementsfor connecting a PV system to UK
distribution networks. The following flowchart describes the process for identifying the
appropriate procedure:
NOT FOR COMMERCIAL USE OR REPRODUCTION
NO G59
YES
Connection voltage
>230V – single phase systems
>400V – three phase systems
The process for installing a single system under Engineering Recommendation G83 is a very
straightforward ‘fit and inform’ procedure, with DNO notification only required after the
installation has occurred.
To comply with the simple G83 fit and inform process, the system should:
Due to the potentially larger impact on the electricity network, when installing multiple PV systems within a
close geographic region, approval from the DNO is required before installation proceeds:
Notification to
NOT FOR COMMERCIAL USE OR REPRODUCTION
Within Engineering Recommendation G83, the definition of close geographical proximity is taken
to be where the postcode, excluding the last two letters, is the same (for example, CA11 0xx); or
where any two planned installations are within 500m of each other.
NOTE: for systems less than 16A/phase there are no requirements to balance systems across phases. However, for
multiple installation projects, such as those on housing estates, agreement on phase balancing will need to be agreed
with the DNO.
Draft for Comment
Installation
Commissioning
While both G59 procedures are similar, with both requiring DNO approval before proceeding, the process is
simpler for smaller systems using G59 type tested inverters. The use of type-tested inverters simplifies
installation and commissioning and generally means that DNO witnessed commissioning tests are not
required.
For larger systems, the DNO will typically require the installation of a stand-alone G59 relay, the design of
which is covered earlier in this Code of Practice. The G59 relay is normally commissioned by a series of
tests that simulate grid out-of-bounds conditions (under- and over-voltage etc). For the duration of the
tests, the sense circuits on the G59 relay are temporarily disconnected from the grid and connected to a
test set with a variable voltage and frequency output. Commissioning then involves cycling the relay
through each of the G59 voltage and frequency settings and timing the response to ensure that the relay
meets the prescribed G59 values and reaction times.
Solar PV CoP :: v1.6 :: Page 64 of 138
© Please do not copy or print
Please send comments – see details on page 1
(a) notify the DNO within a reasonable time of the details of the scheme to be connected, the time the
connection is required and the maximum capacity (import and export) needed from the connection.
Alternatively, a developer may choose to approach an Independent Connection Provider (ICP) to arrange
and provide the connection. The ICP must be registered and approved by the DNO to which the connection
will be made. While the ICP may carry out the connection to the DNO network, they do not have
distribution licences, so will not be licensed to operate the connection once it is installed (the DNO will
Draft for Comment
(a) the design for the network extension and any contestable reinforcement of the existing network;
(b) procurement of equipment and materials to the DNO’s current specification for the extension;
(c) trenching and other preparation of the site;
(d) constructing the network extension and any contestable reinforcement and diversions;
(e) drawings and site records;
(f) reinstatement works; and
(g) making provision for the installation of metering equipment.
The non-contestable elements of work that can only be provided by the DNO include:
(a) determining the point of connection to the distribution system;
(b) approving contestable designs for new connections/reinforcements;
(c) planning, designing, specifying and carrying out any non-contestable works;
(d) removing or repositioning existing electrical plants and electric lines;
(e) connection to the distribution system; and
Solar PV CoP :: v1.6 :: Page 65 of 138
© Please do not copy or print
Please send comments – see details on page 1
High Voltage connections, substations and the associated earthing schemes need to be specified
by a competent person with sufficient technical expertise. This Section, together with the HV
aspects of the health and safety in Section 15, outlines some of the considerations for the design
of an HV connection to a solar PV plant. However, this Code of Practice does not attempt to
provide comprehensive guidance. Detailed design will require a suitably competent person and
NOT FOR COMMERCIAL USE OR REPRODUCTION
HV connection arrangements
Within the UK, the connection arrangement for a large-scale PV installation is normally via a tee
into a nearby high-voltage network, which can be an 11kV, 33kV, 66kV or 132kV HV system. While
a PV system developer may identify a possible location for the connection into the HV network,
the design and assessment of the connection will be performed primarily by the relevant Network
Operator and is out of the scope of this Code of Practice. This work will include specifying any
extension or reinforcement works (upgrading cables, switchgear, protection etc) that the existing
network may require.
NOTE: due to the intermittent nature of the generation of power from a solar power plant, the Network Operator will
There are a number of common types of HV system topologies used in large-scale solar systems;
Radial circuits need to be rated for the sum of all generation units and issues, such as reliability of
NOT FOR COMMERCIAL USE OR REPRODUCTION
NOTE: as an alternative to multiple connections onto a single radial circuit, a dedicated HV circuit for each individual
PV substation can be implemented. This is a reliable and safe option, but will be costly. Alternatively, generation
units can be grouped onto a number of separate radial circuits.
NOTE: ring circuits can be energised from both ends in a closed configuration and while this might be more secure it is
not recommended for a number of reasons, i.e. Network Operator systems can operate with reduced fault levels;
there will be additional complexity and costs to ensure discriminating protection and adequate backup protection for
generator step-up transformer LV side faults; and measures may be required to minimise risks from failure of an
HV/LV transformer protection and fault isolation systems.
Draft for Comment
Site constraints
The physical shape of the solar farm and the relative inverter locations within the solar plant may
also influence the choice between a radial or ring HV circuit (for example, a ring circuit in a long,
narrow site will require more cable and will cost more than one in a square site).
While the previous diagrams show an HV distribution circuit using central inverters, the same
design principles can still apply for a system using string inverters:
NOT FOR COMMERCIAL USE OR REPRODUCTION
provisions must therefore be designed and utilise specified equipment from nominated suppliers. They
must also have individual design approval, be witnessed, installed and tested to the satisfaction of the
relevant individual Network Operator.
The requirements specified within the provisions of Engineering Recommendation G81 do vary between
Network Operators. Additionally, Network Operators’ requirements are continuously being updated both in
terms of design requirements and specified equipment suppliers.
The Network Operator requirements may have a direct impact on the design, system interface and the
operational requirements of the PV system (for example, earthing and protection).
Note: while standards have no stand-alone legal status, an enforcing authority or court may apply and recognise
standards as evidence of good practice in applying the principle of ALARP (as low as reasonably practicable) to a
particular risk or activity.
Reference Title
BS EN 61936:2010 Power installations exceeding 1kV AC
NOT FOR COMMERCIAL USE OR REPRODUCTION
The location of the HV plant should consider issues of earthing, operational safety, electrical losses
and design costs. In challenging earthing situations, the location of equipment must consider third
party safety and potential damage.
The location of HV transformers and switchgear will in part be dictated by the physical constraints
of the solar site. When assessing physical constraints, consideration should be given to:
(a) access routes for plant transportation (both during and after construction);
(b) the location of the PV arrays;
The location of other underground/overhead services around the site may also influence
equipment locations.
In general the location of the HV plant should allow for safe, 24-hour vehicular access, with
restricted access to the general public and at locations not prone to flooding or other
environmental impacts. Most Network Operators will also insist that access to their incoming
substation should be direct from the highway or a public right of way.
Draft for Comment
Reference Title
Guidelines on the Positioning and Colour Coding of Underground Utilities’
NJUG
Apparatus
CIBSE Guide K Electricity in buildings
COPYRIGHT © The IET
ENA TS 12-23 Polythene protection tape for buried electricity supply cable
ENA TS 12-24 Plastic ducts for buried electric cables
ENA TS 97-1 Special backfill materials for cable installations
Framework for design and planning, materials specification, installation and
ENA ER G81 record for low voltage housing development installations and associated new
HV/LV distribution substations.
The majority of HV cables for PV installations will be laid in the ground. When planning
underground cable routes, the type of use, or foreseeable use, to which the land is or may be put
needs to be considered. Routes should avoid locations where excavation may be predicted (for
example, for gates or fence posts). In some circumstances, the burial depth may need to be
increased to keep the cable well below future land use (for example, clearing drainage ditches).
10.5 HV Switchgear
There are a number of standards that apply to high-voltage equipment and, in particular, HV
switchgear. The most relevant are shown in the table below:
Reference Title
High-voltage switchgear and control gear – Part 200: AC metal-enclosed
NOT FOR COMMERCIAL USE OR REPRODUCTION
All high-voltage switchgear incorporated and installed in solar PV systems shall comply with BS EN
62271-200:2012. In addition, the switchgear must enable the achievement of secure isolation and
compliance with HV safety rules (see Section 10.5.1).
It is regarded as good industry practice for switchgear to endeavour to meet the design safety and
operational requirements of ENA TS 41-36 or TS 41-37. Certification to ENA standards is regarded
as an optional protocol that duty holders may choose to perform to demonstrate additional
confidence in assurance arrangements.
It should be noted that standard IEC-certificated switchgear will not automatically be capable of achieving
HSE publication HSR25 (Memorandum of guidance on the Electricity at Work Regulations 1989: Guidance
on Regulations) gives guidance on isolation. Paragraphs 183 and 184 are reproduced here (with
permission):
183. Whereas Regulation 12(1)(a) requires means to be provided whereby the supply of electrical energy
can be switched off, 12(1)(b) requires that there will be available suitable means of ensuring that the supply
COPYRIGHT © The IET
will remain switched off and inadvertent reconnection prevented. This is isolation. This provision, in
conjunction with safe working practices, will enable work to be carried out on electrical equipment without
risk of it becoming live during the course of that work, for example if the work is to be done under the terms
of regulation 13.
184. In some cases the equipment used to perform the requirement under regulation 12(1)(a) may also
serve to perform the requirement under 12(1)(b). It must be understood that the two functions of switching
off and isolation are not the same, even though in some circumstances they are performed by the same
action or by the same equipment.
HSE HSR25 also gives guidance on isolation and disconnection and paragraph 189 is reproduced here (with
permission):
Isolator switches (or disconnectors) will often be employed as the means of effecting disconnection and
secure separation from the supply. In selecting appropriate equipment to perform this function particular
NOT FOR COMMERCIAL USE OR REPRODUCTION
a) the isolating distances between contacts or other means of isolation which should be in accordance with
an appropriate Standard or be otherwise equally effective;
b) the position of the contacts or other means of isolation which should either be externally visible or
clearly and reliably indicated. An indication of the isolated position, other than by direct observation of
the isolating gap, should occur when the specified isolating distance has been achieved in each pole;
c) provision to enable the prevention of unauthorised, improper or unintentional energisation, e.g. locking-
off facilities.
delay between closing and opening switches as detailed in sub-clause 5.7 of IEC 60694. The time
10.6 Transformers
There are a number of standards that apply to transformers; the most relevant are shown in the table
below:
Reference Title
BS EN 60076-1 2011 Power transformers: General
Power installations exceeding 1kV AC
COPYRIGHT © The IET
BS EN 61936:2010
(BS EN 61936-1 gives TX Bunding guidance)
ENA TS 35-1 Distribution Transformers (from 16kVA to 2000kVA)
While it is beyond the scope of this Code of Practice to detail all of the considerations applicable
to the selection and specification of an HV distribution transformer for solar farm systems, some
of the main criteria include:
The ratio of the number of primary winding turns to secondary winding turns is known as the
‘turns ratio’, which is proportional to the ratio of the primary voltage to the secondary voltage. A
transformer used in an HV solar system is referred to as a step-up transformer, indicating that in
this application there are more turns in the high-voltage winding than in the low-voltage winding.
This results in, for example, a 1:27 (400/11000) or 1:82 (400/33000) voltage ratio.
Standard transformers are manufactured with turns ratios matched to common distribution and
Draft for Comment
utilisation voltage combinations, such as 1,1000V to 400V. While these standard winding
configurations may work in some PV power plant applications, the inverter output voltage may not
In the UK the winding configuration will normally be Delta/Star for 11kV HV/LV systems (i.e
designated as Dy11; see Table xxx). However, in certain instances it may be necessary to phase-
shift 30 degrees on the transformer secondaries between individual transformers in a group in
order to reduce the overall primary level of harmonics. In the case of higher voltages (33kV/66
kV/132kV), the transformers will generally need to be star or star configured and will potentially
need to have Neutral Earthing resistors installed to limit the earth fault currents.
For compliance with Engineering Recommendation G59, the phase shift and voltage of the HV side
of the transformer will need to match the Network Operator connection configuration. There are
advantages from phase shifting on the secondary side to reduce the harmonics and ensure
compliance with the provisions of Engineering Recommendation G5/4. However, if the solar site
requires an alternative low voltage supply this would be problematical.
Example – Dy11
o Transformer primary winding – delta (D)
o Transformer secondary winding – star (y)
o Transformer phase shift - 30° leading (11)
(a) Pulse Width Modulation (PWM) capable transformers: specified where the transformer is used
as an inductor to provide filtering and designed to operate with a PWM inverter.
(b) multi-winding transformers, with multiple isolated low-voltage windings: used for inverters
that cannot be connected in parallel.
(c) standard transformers: one low-voltage winding and one high-voltage winding.
Different types of generation have different abilities to increase Network Operator fault currents
i. Winding Impedance
Impedance in transformer windings is mostly due to reactance and is an important factor in
controlling fault currents (increasing winding reactance decreases fault current). The impedance
of a transformer may be intentionally increased to overcome issues of an excessive fault current
contribution. The increased winding impedance will also reduce fault currents on the LV side of
the transformer. The effect of the transformer winding impedance on protection systems and
COPYRIGHT © The IET
There are two main types of transformer dielectric: oil-immersed transformers and cast resin
transformers.
i. Oil-immersed transformers
NOT FOR COMMERCIAL USE OR REPRODUCTION
The following standards are relevant to oil-immersed transformers for use within the UK:
Reference Title
Three-phase oil-immersed distribution transformers 50 Hz, from 50 kVA to 2 500
BS EN 50464-1 kVA with highest voltage for equipment not exceeding 36 kV.
General requirements
Three-phase oil-immersed distribution transformers 50 Hz, from 50 kVA to 2500
kVA with highest voltage for equipment not exceeding 36 kV.
BS EN 50464-4 kVA with highest voltage for equipment not exceeding 36 kV.
Requirements and tests concerning pressurised corrugated tanks
Cast resin transformers are constructed with their HV windings encapsulated in resin and provide
an alternative to traditional oil immersed transformers. Self-extinguishing and high mechanical
resistance to electro-dynamic stresses are some of the qualities of cast resin transformers. They are not
suitable for direct outdoor use and are generally housed in prefabricated containerised units or
with sheet steel ventilated enclosures and cable boxes
NOT FOR COMMERCIAL USE OR REPRODUCTION
The following standards are relevant to cast resin transformers for use within the UK:
Reference Title
Three phase dry-type distribution transformers 50 Hz, from 100 kVA to 3150 kVA,
BS EN 50541-1
with highest voltage for equipment not exceeding 36 kV. General requirements
Three phase dry-type distribution transformers 50 Hz, from 100 kVA to 3 150 kVA,
BS EN 50541-2
Where solar developers use high voltage cast resin transformers with exposed conductors,
appropriate safety measures with restricted access to exposed HV conductors must be ensured.
COPYRIGHT © The IET
Reference Title
BS7430:2011 Code of Practice for protective earthing of electrical installations
NOT FOR COMMERCIAL USE OR REPRODUCTION
The design and specification of appropriate earthing arrangements will ensure that a suitable low
impedance path is in place for earth, fault and lightning currents and that step and touch voltage
hazards are minimised.
Touch potential
Touch potential is the voltage between an energized object and the feet of a person in contact
with the object. Limits for Network Operator substation areas are provided in ENA TS 41-24.
Draft for Comment
Transfer voltage
Transfer voltage is a touch or stress voltage, which may be the full substation earth potential rise
(EPR) or part of this. Examples are:
(a) the voltage of a metallic path (such as a cable sheath) earthed in a substation, at a location
with lower EPR or at the potential of remote earth.
(b) the voltage inside a substation of a metallic path (such as a cable sheath) earthed remotely.
(c) the remote end voltage to ground of a metallic path (such as a fence) earthed or in ground
contact in an area with elevated voltage (within the zone of influence of an earth system).
(b) that they have received sufficient evidence (from the PV developer) to ensure the safe design
of substation earth systems and safe internal operating conditions.
(c) the safe installation of Network Operator equipment in its own and any associated substations.
This requires the HV equipment to be earthed to a substation earth system designed and
NOT FOR COMMERCIAL USE OR REPRODUCTION
(d) that there is sufficient information available to ensure general site safety during Network and
PV site HV earth faults.
(e) that HV system neutral points are connected to a suitable earth system containing electrodes.
HV (non LV) system neutral points may be solidly earthed or may be earthed via an impedance
to limit fault current.
(f) that any HV system connected to the Network Operator substation or equipment is safe from
earth potential rise (EPR) that may arise in the Network Operator substation. ENA ER S34
provides the Network Operator with a standard procedure for calculating the rise of earth
NOTE: depending on the design of the Network Operator and PV systems, HV earth faults in a PV system with an
extensive HV cable network may experience EPR in internal substations greater than that at the supply point from
the Network Operator network.
Connection agreements provided by the Network Operator to the PV Operator will stipulate
acceptable standards and will require the submission of appropriate design reports (such as the
design of protection and earth systems). The Network Operator will not be prepared to connect a
PV solar site until they are satisfied they have sufficient evidence that the whole site’s earth
system meets the relevant requirements.
Draft for Comment
A site where the EPR may exceed 430V or 650V (for high reliability circuits) is classified as hot, in
accordance with Table xxx (below). This table contains extracts from ENA ER S36 to show typical
COPYRIGHT © The IET
voltage limits for EPR and zones of interference of substation earth systems.
Table xxx Earth System EPR and Zone of Influence Limits in ENA ER S36
Protection Clearance Time and
Third Party Impact Threshold Voltages via Proximity Effect
Voltage Limits
Normal reliability circuits with main protection systems that clear the
>0.2 sec
earth fault current in excess of 200ms (20kV, 11kV, 6.6kV).
High reliability circuits with main protection systems that clear the earth
0.2 sec or less
fault current within 200ms (400kV, 275kV, 132kV, 66kV, 33kV, 25kV).
Third Party Infrastructure Equipment Involved
Solar PV CoP :: v1.6 :: Page 79 of 138
© Please do not copy or print
Please send comments – see details on page 1
Site services.
Isolation required on cable 430V 650V
BT and Telecommunication equipment.
Companies
Attention to main trunk lines,
1,150V 1,700V
callboxes.
Domestic residence or
Telephones and modems. 1,150V 1,700V
commercial property
NOT FOR COMMERCIAL USE OR REPRODUCTION
When the EPR exceeds the hot limit voltages as listed in Table xxx above, precautions must be
taken inside the substation working area and around the earth system. Mitigating actions that
might be adopted include isolation of HV and LV earth systems, special HV cable working
procedures and isolation of communications circuit. Examples are shown in Table XX below:
Table xxx Earth Potential Rise (EPR) and Application of Transfer Voltage Limits (TVL) for
Check proximity HV equipment to any 1,700V limit For 33kV earth faults.
˃1,700V or
third-party telecom systems and 1,150V limit for 11kV earth faults.
1,150V
equipment.
≥ 1,700V Consider telecom barriers. Consider reduction of EPR ≤1,700V.
Consider effects of separation of HV and Separation is not recommended since LV
˃1,200V LV earth systems and voltage appearing equipment in substation will exceed stress
Draft for Comment
Example PV Installation with Network Operator 33kV or 11kV Cable Network Connection
EPR=<Transfer Voltage Limit (TVL)
Network
Operator
33kV or
11kV Network
Cable Operator/PV
PVA PVA
NOT FOR COMMERCIAL USE OR REPRODUCTION
Network
Operator PVA PVA
33kV or Buried earth
11kV electrode
Cable
PV Array (PVA) with Type B
lighting protection electrode PV Array (PVA) with Type A
lighting protection electrode
Notes
All earth systems can be connected (HV&LV and lightning)
Example PV Installation with Network Operator 33kV or 11kV Overhead Line Network
Connection with Isolated LV supplies (EPR=<1200V)
Network
Operator
33kV or PVA PVA
11kV
OH Line
PV Array (PVA) with Type B
lighting protection electrode PV Array (PVA) with Type A
Notes lighting protection electrode
Network Operator & PV Substation equipment and PVA substation equipment share a common or interconnected
system
Network Operator & PV Substation and PV Array Substation earth systems are bonded with sheaths of cables or earth
system conductors
PV Array equipment and PVA Substations not connected by sheaths of cables or earth system conductors (LV
arranged as a TT system
Security fences preferably independently earthed and not connected to substation earth systems.
Horizontal earth electrode important to be buried with Network Operator loop in cables to lower EPR and divert fault
current from Network Operator & PV Substation earth system.
Example ideal maximum 1200V ground surface voltage contours are shown
PVA lightning system preferably not connected to PVA LV TT earth systems to minimise risk of damage
PVA equipment located outside TVL transfer voltage limit (TVL) contours
Example PV Installation with Network Operator 33kV or 11kV Overhead Line Network
Connection (EPR exceeds 1200V)
Caution: This diagram does not address all issues to be considered such as auxiliary power supplies, security
Network fences and isolation of telecommunication facilities and services not associated with the PV Installation
Operator
33kV or
11kV
1200V
OH Line Network 1200V
Operator/PV 1200V
NOT FOR COMMERCIAL USE OR REPRODUCTION
Example PV Installation with Network Operator 33kV or 11kV Overhead Line Network
Connection (Very High EPR)
Draft for Comment
Caution: This diagram does not address all issues to be considered such as auxiliary power supplies, security
Network fences and isolation of telecommunication facilities and services not associated with the PV Installation
electrode electrode
1700V 1700V
Notes
Network Operator & PV Substation equipment and PVA substation equipment share a common or interconnected
system
Network Operator & PV Substation and PV Array Substation earth systems are bonded with sheaths of cables or earth
system conductors
PV Array equipment and PVA Substations connected by sheaths of cables and earth system conductors (LV arranged
as a TN-S system
Security fences preferably independently earthed and not connected to substation earth systems.
Horizontal earth electrode important to be buried with Network Operator loop in cables to lower EPR and divert fault
current from Network Operator & PV Substation earth system.
Example diagramatic 1700V ground surface voltage contours shown for zone of interference on telecommunications.
Touch voltage in Network Operator/PV substation not to exceed ENA TS 41-24 limits
Touch voltage in PVA substation not exceeding BS EN 50522 limits.
Touch voltage on PVA equipment not exceeding BS EN 50522 LV transfer voltage limit (TVL)
The objective is to design and install an earthing system to satisfy the site safety requirements of
the Network Operators for step and touch potentials in order to conform to the requirements as
set out in BS EN 50522 and BS 7430.
Limits for touch, step and transfer voltages that can occur during an HV earth fault depend on the
time duration of the earth fault current and EPR which can introduce risk of electric shock. The
appropriate fault current duration will be the operating time of the appropriate protection device
The actual maximum duration of maximum EPR at each voltage level in a substation or the PV
system should be considered to establish the voltage limits
It should be noted that the worst case limit adopted at each voltage level may be the lowest of
voltage limits appropriate to several conditions of EPR and fault durations.
x
Draft for Comment
The design and specification of a suitable earthing arrangement will ensure that a suitable low
The design and specification of the whole solar PV earthing system will need to include an EPR
study at its critical points. This will look at the layout and configuration of the proposed earthing
system, data from soil resistivity tests, actual or estimated fault currents that could flow into the
earthing system, the cables used and the overall electrical design. It will also need to consider the
modelled or calculated distribution of fault current when several earth systems are
interconnected.
For the solar PV HV network, the designer shall ensure that the solar PV earthing system complies
with BS EN 50522 in terms of tolerable touch and step potentials (for the declared EPR value at the
Network Operator-Solar PV system interface). The EPR of the connection point may be declared by
the Network Operator or assessed within the PV connection project.
The design of the earthing system presented at the connection point needs to be complete and
agreed with the Network Operator before construction commences, since earthing arrangements
NOT FOR COMMERCIAL USE OR REPRODUCTION
For a substation that will be adopted by a Network Operator the designer shall ensure compliance
with the current ENA standards for substation earthing design and assessment; these are ENA TS
41-24 and ENA ER S34.
NOTE: the ENA have accepted in principle the adoption of BS EN 50522 within ENA TS 41-24 and ER S34. This change
will become part of the Distribution Code as an annex document and so the proposed change must go out for public
consultation. BS EN 50522 will be harmonized with the stated standard (subject to formal agreement by all ENA
members following consultation) in about 2015.
(a) the EPR rise of a single HV Substation connected to an overhead line is likely to be excessive even where
a large buried earth system is used. The substation area may be extended with external horizontal
electrode and earth rods to reduce resistance and lower EPR. However it may not be economic to
reduce earth system resistance to values that ensure a cold site.
Draft for Comment
(b) ground-mounted substations and independent HV equipment, such as transformers, should each have
(c) the earth system will need to be functional with sufficiently low resistance to ensure operation of the
appropriate protection relays with a damaged cable sheath and also provide reasonable equipotential
conditions inside the substation.
(d) Where EPR is excessive, the earth system will be constructed as a grid with sufficient infill electrodes to
utilise the site area and control touch and step voltages.
COPYRIGHT © The IET
(e) Network Operators will, within reason, accept a raised EPR as long as safe working conditions in
substations and in the connected systems are ensured.
(f) where earth systems of several HV substations are interconnected by sheaths of HV cables or insulated
earth conductors, each substation HV earth system can intentionally be minimal but functionally
sufficient to ensure operation of appropriate protection relays and also provide reasonable
equipotential conditions inside each substation.
(g) the minimal substation HV earth system will minimise the local zone of interference (hot zone) and LV
supplies can be more easily earthed outside the zone of interference.
(a) Network Operators currently use 430V as the transfer voltage limit (TVL) to decide whether
their HV and public LV systems are separately earthed.
(b) BS EN 50522 UK annex (NA4) touch voltage/fault duration limits (without additional personal
protection) is now the appropriate reference to use when deciding whether to separate HV and
LV earth systems.
(c) Network Operators substations providing TN-C LV supplies and earth terminals using cables
with a single conductor that provide combined neutral and earth functions (cables with
protective multiple earthing (PME) of the neutral conductor and distributed earth) can
must be segregated (see Table 2 BS EN 50522). Note that from the UK Annex to BS EN 50522
additional electrode placed to reduce EPR and avoid danger. This is a concept that is applied
within large HV power stations.
ii. Separated earth systems
When HV and LV earth systems are separated, the two systems should be physically separated,
identified, insulated and screened from cross contact and inadvertent connections.
(a) LV electrodes must be located an adequate distance from HV electrodes; and
(b) the resistance of LV electrodes must not exceed the maximum HV electrode value for reliable
HV transformer protection operations.
When HV and LV earth systems are to be interconnected, the bonding of installation structural
parts in ground contact and LV earth systems is particularly important, as doing so prevents
dangerous HV fault currents flowing in the small protective conductors of the PV installation.
While cable sheaths and earth connection conductors in the PV system will provide the general LV
system protective/bonding conductors, adequate direct bonding conductors must also be present
(to prevent excessive HV fault currents flowing in the small LV protective conductors). The bond
NOT FOR COMMERCIAL USE OR REPRODUCTION
Reliable and adequate HV and LV earth system interconnections can be achieved by:
(a) collective earth bars for both HV and LV equipment, that are connected by an earth conductor
rated for the duration of the maximum LV earth fault current; or
(b) an additional direct earth bonding conductor (again, rated for the duration of maximum LV
earth fault current) installed between the HV transformer earth point and the point of LV
neutral earthing.
The HV-LV earth system design also needs to consider any lightning and surge protection earthing
scheme that is to be implemented on the site.
Where a lightning protection system is to be installed, close coordination will be required between
Draft for Comment
the designer of the LPS system and the HV-LV earth system designer.
In addition to load calculations that are covered in the next section, there a few general rules that
apply to the design of all PV mounting systems:
NOT FOR COMMERCIAL USE OR REPRODUCTION
Module manufacturer’s instructions will specify requirements for the fixing/clamping of the
module. This may restrict what edges can be used for clamping (for example, some modules
do not allow clamping on the short edges) and may also restrict zones where clamps are
allowed.
• Corrosion: PV array frames and fixings shall be made from corrosion resistant materials that
are suitable for the lifetime of the system.
In considering corrosion, possible galvanic effects from bolting dissimilar metals together may
Draft for Comment
also need to be considered – and, where necessary, materials swapped or insulating washers
• Thermal effects: PV mounting systems shall allow for thermal expansion and contraction.
Thermal effects need particular consideration in larger systems where the array structure may
require long lengths of support rail etc. In such cases, thermal breaks and expansion gaps will
need to be designed into the system
The long-term accumulation of snow/ice should be prevented by ensuring that the design does
not trap snowfall on the module surface (for example, avoiding any up-stands at the module
bottom edge that may prevent snow sliding off during a thaw). For larger arrays, the
possibility of uneven snow loading may need to be considered if there is the potential for snow
to slide and accumulate on the bottom portion of an array.
Similarly, the potential accumulation of dirt, leaves and other debris should also be considered
in the array frame design. This is to include debris accumulation beneath an array, which can
build up and restrict good air flow beneath the array.
The installation of a PV system may affect the existing run-off patterns of rain and snow on the
site. For example:
(a) large roof arrays may speed up or deflect the natural shedding of water from a roof and
cause existing guttering systems to be overwhelmed at times of heavy rainfall.
(b) PV arrays too close to an eave or gutter may cause water to miss the gutter.
NOT FOR COMMERCIAL USE OR REPRODUCTION
• Self-shading: PV mounting systems shall be designed to minimise self-shading from the array
structure.
When designing the array frame, consideration needs to be given to the shade cast by the
structure itself. For example, module clamps that have excessive height may cast a small
• Access for maintenance: when designing an array frame, consideration needs to be given to
future access requirements – both for the array itself and for the building and the ground it is
mounted upon.
11.4).
The PV modules, array mounting structures and fixings need to be able to withstand the forces
imposed on them over the lifetime of the system. The same applies to any underlying structure
COPYRIGHT © The IET
that the PV array may be fixed to. It is therefore necessary to calculate the wind and snow loads
for the site and system in question.
Determining the wind load on a system is performed primarily to ensure that the PV mounting
structure and fixings are sufficient to withstand any uplift (suction), sliding and overturning
moments that the wind will impose. Knowledge of wind-uplift is vital in specifying fixings for PV
systems attached to buildings. Sliding and overturning moments need to be calculated for
ballasted systems.
NOTE: downward forces from the wind are generally of less importance and can be ignored in most circumstances.
The procedure for determining the forces on a PV system due to the wind is a two-step process.
The first step is to determine the peak velocity pressure that the wind will impose at the site in
question. The second step involves translating this peak pressure into a force by multiplying by
the area of the array and an appropriate pressure coefficient:
i. Wind Force
NOT FOR COMMERCIAL USE OR REPRODUCTION
Where:
Q p = peak velocity pressure
A = area of module or array
C p = pressure coefficient
SF = safety factor
In order to calculate the peak velocity pressure, the following site factors need to be taken into
account:
(a) basic mean wind velocity (varies according to location – taken from a map of the UK).
(b) altitude correction factor (accounts for the height above sea level).
(c) reference height (height of structure above ground level).
Draft for Comment
A simplified method for calculating peak velocity pressure can be found in BRE Digest 489 - Wind
loads on roof mounted solar systems.
COPYRIGHT © The IET
The pressure coefficients used in wind load calculations need to be selected according to the
BRE Digest 489 - Wind loads on roof mounted solar systems provides information on the selection
and use of pressure coefficients for PV arrays mounted on roofs. The document also provides
guidance on the application of Eurocode-1 to PV systems.
Pressure coefficients for arrays mounted on pitched or flat roofs shall be selected according to the
requirements of BRE Digest 489. Pressure coefficients for all other systems shall be taken from
Eurocode-1: BS EN 1991.
COPYRIGHT © The IET
Note: the forces on ground-mounted systems can also be calculated using the flat roof procedure within BRE Digest
489 and setting the building height to zero.
The selection of the appropriate pressure coefficient for a PV system mounted on a building also
needs to take into consideration the relative location of the array on the building. Pressure
coefficients within central zones will be lower than those at the building edges.
A safety factor needs to be applied in all wind load calculations in accordance with the
requirements of Eurocode-1.
For PV systems mounted on roofs, a safety factor of 1.35 can typically be used, in accordance with
the requirements of BRE Digest 489.
System data:
(a) pitched roof - duopitch, 30°.
Draft for Comment
Total Wind (uplift) force acting on array = Q p x A x C p x SF = 763 x 25.6 x 0.5 x 1.35 = 13.18 kN
Total Wind (uplift) force per module = Q p x A x C p x SF = 763 x 1.6 x 0.5 x 1.35 = 824N
Total Wind (down) force acting on array = Q p x A x C p x SF = 763 x 25.6 x 0.26 x 1.35 = 6.86 kN
Total Wind (down) force per module = Q p x A x C p x SF = 763 x 1.6 x 0.26 x 1.35 = 429N
the additional load of a PV array. Knowledge of snow loads may also be required when designing
array frames or where the nature of the array design may trap and accumulate snow.
The procedure for determining snow loads within the UK is contained within Eurocode-1 BS EN
1991 and the UK National Annex: BS EN 1991-1-3 Part 1-3: General actions — Snow loads.
The PV module shall be checked to ensure it can withstand the wind and snow loads calculated for
the site.
The focus of mechanical design is often on the array frame and fixings, and checking the rating of
the module is often overlooked. In some high wind load applications, such as facades, the module
may not be suitable for the loads that will be imposed.
Detailed mechanical design is beyond the scope of this Code of Practice. While off-the-shelf
mounting systems should have maximum loadings specified by the manufacturer, this will not be
the case for bespoke framing systems. In such cases, a suitably competent person will need to
ensure that the bespoke mounting system is fit for purpose.
iii. Fixings
The fixings used to secure a PV array shall be rated for the wind and snow loads calculated for the
Draft for Comment
site.
System data:
(a) total wind (uplift) force acting on array = 13.18 kN.
(b) fixing bracket rated capacity = 500N (includes safety factor).
It is important to determine whether the fixing capacity provided by the manufacturer includes a
safety factor (as this can vary between manufacturers). If no safety factor has been applied, an
appropriate factor will need to be included as part of the fixing calculations.
Not only should the correct number of fixings be installed, but their layout and deployment must
be suitable for the array frame and the structure it is connected to. For example, on a roof-
mounted system, the fixings will need to be spread appropriately across all the roof rafters
beneath the array. Fixings also need to be suitable for the structure and material to which they
are being attached.
The building structure shall be checked to ensure that it is able to withstand the imposed loads
that will be the result of the installation of the PV system. Calculations shall be undertaken by a
suitably competent person.
In general, the installation of a PV system on a building will not increase the wind uplift forces
upon the building structure. However, the increased weight of the PV array system reduces the
Hence, before installing a PV system, it is necessary to ensure that there is sufficient residual
capacity in the building structure to accept both the existing loads and the added weight of the PV
system.
Detailed structural calculations are beyond the scope of this Code of Practice.
Before fitting a PV system to an existing building, the building shall be inspected by a suitably
competent person to ensure that the existing structure is free from decay or any other factors that
Draft for Comment
could influence the suitability of the structure to accept the addition of a PV array.
NOTE: the inappropriate use of screw fixings in some roof timbers can result in cracked or split timber.
COPYRIGHT © The IET
The use of ‘through bolts’ is not permitted due to the potential for
cracked slates (by imposing some load onto the slate) and the risk of
Draft for Comment
The roof brackets used to fix a PV system to a slate or tiled roof shall:
(a) be fixed to a suitable structural member;
(b) not displace the tiles/slates in a manner that results in gaps more than those that naturally
occur across the rest of the roof;
(c) not impose any load onto the slates or tiles;
(d) not rely on silicon/mastic to provide the sole means to form a weather-tight seal; and
(e) durably seal all layers of the roof cladding.
NOTE: battens are not generally considered suitable structural members for fixing roof brackets.
Cable penetrations through a roof shall not compromise the weather-tightness of the roof. Cables
taken through the underlay shall use purpose-made glands or, if taken through a lap in the felt,
installed so as to minimise disturbance to the lap joint.
Solar PV CoP :: v1.6 :: Page 94 of 138
© Please do not copy or print
Please send comments – see details on page 1
The design of systems installed on metal or fibre cement roofs needs to consider the access
requirements for installation - an allowance for crawl-boards may be needed on some fragile
roofs. Installation on fibre cement roofs also needs to consider if there is any asbestos in the roof.
Roof-integrated PV arrays shall have a fire rating that is appropriate to the relevant local building
regulations.
Cables taken through underlay shall use purpose-made glands or, if taken through a lap in the felt,
Draft for Comment
The roof needs to be sufficient to take the weight of the PV array and
ballast.
Great care needs to be taken in the design of the fixing and roof
penetration to ensure that a lasting weather-tight seal is achieved.
Draft for Comment
The interface between the array frame and the roof membrane shall be considered and an
isolating layer inserted where necessary.
COPYRIGHT © The IET
NOTE: some membrane manufacturers recommend an isolating layer between the array and the membrane to prevent
chemical reactions that may compromise the integrity of the roof over the life of the system.
The layout of a flat roof array shall consider any requirements for general roof access and access
to any roof plant.
Good workmanship and housekeeping is essential when working on a flat roof, as great care is
needed to prevent accidental punctures to the roof membrane. Punctures can occur due to
dropped tools or components or by small/sharp objects getting trapped beneath a ballasted array
frame.
11.3.4 PV Facades
PV modules and framing systems used for a PV façade shall be capable of withstanding the design
wind loads and shall comply with the relevant building regulations.
PV modules used in a façade shall retain their integrity in the event of a breakage to the module
laminate.
NOTE: many PV modules are formed from a PV laminated clamped into a frame. A break of such a PV laminate will
11.3.5 PV glazing
PV modules used for PV glazing shall comply with the relevant building regulations for the regular
glazing they are replacing.
COPYRIGHT © The IET
The key factors to be considered in the design of a PV glazing system are similar to those of a PV
façade and include:
As well as standard considerations, the glazing frame that supports the PV modules will also need
to be checked to ensure that it does not cast shade on the PV cells and (where required) that it
provides sufficient internal space for cable routing.
NOTE: fires can also occur as a consequence of lightning – this topic is dealt with in detail in Section 6.
From the limited information available, it is generally believed that the most likely cause of a fire
on a grid-connected PV system will be a DC arc. This can occur within a faulty DC switch or a poorly
Incorrectly specified DC isolators, poor DC connections or cable containment are the most
commonly attributed causes that are under the direct influence of a PV installer.
Draft for Comment
Somerset Fire and Rescue Service Fire the potential for a DC arc
Investigation Team
Clearly, small fires starting within components can spread and cause further hazards, such as
larger fires or a shock risk from exposed conductors.
i. DC overcurrent protection
The correct selection and installation of overcurrent protective measures is essential in ensuring
good fire safety in a PV array. This includes the appropriate cable sizing and, where appropriate,
the correct selection and specification of overcurrent protective devices. DC overcurrent
protective measures are detailed in Section 5.
Standard electrical installation practices apply to the containment and securing of PV system
cables. External cables exposed to wind and thermal influences (for example, the cables directly
beneath a PV array) require particular attention and need to be adequately secured. Care should
also be taken to ensure plug and socket connections are secured in a manner that places minimal
stress from wind or thermal effects (both plug and socket sides of the connector properly
secured).
NOT FOR COMMERCIAL USE OR REPRODUCTION
Segregation between positive and negative conductors (and terminals) within combiner boxes will
also assist in minimising the risk DC arcs present.
An enclosure used to house surge arrestor devices shall be constructed from a material with self-
extinguishing properties.
are suitably rated for DC operation at the system voltage and current maxima. It is important to
NOTE: fires as a result of incorrectly specified or poorly installed DC isolators have been observed. Examples of bad
practice include the use of AC rated isolators and isolators with an insufficient DC current rating.
vi. Connections
To prevent series arcs as a result of poor connections, good installation practice requires that all
connections be verified for tightness. Torque drivers can assist with this.
Poorly assembled plug and socket connections are also a potential concern – all connections need
COPYRIGHT © The IET
to be made using the appropriate tools and assembled correctly – see Section 5.7 for more details.
i. Series arcs
NOT FOR COMMERCIAL USE OR REPRODUCTION
It is sometimes not appreciated that the sensing part of an alarm system, be it a simple domestic
smoke detector or a more sophisticated central alarm system, must be carefully sited, according to
the manufacturer’s instructions. Sensors sited where air circulation is limited (for example, in a
corner) may not be effective.
Draft for Comment
Where sensors are mounted in a building location where an alarm may not be heard (such as a loft
void) it may be necessary to link the sensor to an alarm that will sound elsewhere in the building.
i. Array layout
PV systems shall not compromise fire escape routes for building occupants or access to fire and
rescue services.
COPYRIGHT © The IET
When designing the physical layout of a PV array upon a roof, consideration needs to be given to
access routes for fire fighters and escape routes for occupants:
(a) for pitched roofs, a border free of panels around the array should be considered. Arrays
should also be kept away from roof eaves and ridges to permit ladder access.
(b) for flat roofs, PV arrays need to permit access around the roof (larger systems may need the
inclusion of access corridors) and arrays need to be kept away from any fire escape routes.
Systems mounted above roofs can act as a chimney and exacerbate the spread of flames from
upstairs or roof windows. In general, this effect only needs consideration where the roof cladding
is flammable. The installation of baffles beneath the array and/or a layout with sufficient clearance
distances should be considered in these circumstances.
The fire rating of the PV system components also needs to be considered. This is of particular
importance for BIPV systems where the PV modules replace part of the building fabric, but is also
NOT FOR COMMERCIAL USE OR REPRODUCTION
Fire safety is addressed in the building regulations - the installation of a PV system needs to take
the relevant provisions into consideration.
NOTE: from April 2014, all PV systems mounted on pitched roofs must comply with the MCS standard MCS 012 in
order to be MCS-compliant. MCS 012 includes fire exposure tests for PV systems that form part of the roof structure.
case of a fire.
Additional isolators shall comply with the requirements for the array switch-disconnector set out
in Section 5.5.1.
NOTE: determining when to fit these devices is complex. Factors that may have a bearing on the decision include:
COPYRIGHT © The IET
the building type, size and use; the length of cable within the building between array and inverter; the cable route and
containment method; the increased cost and complexity required; and the power consumption of the device (remote
switches consume power under normal operation).
Where a PV system is installed on a building, the following sign shall be installed. The sign shall be
located at the supplier’s cut-out and shall measure at least 100mm x 100mm.
The factors that will influence whether these additional measures should be specified include any
Like any other PV system, a thorough site survey is essential stage in a ground-mounted PV
development. The scope of the site survey will need to vary according to the nature of the site
and the size of the system, but points to consider may include:
Other information also required before finalising the array design includes:
COPYRIGHT © The IET
Ground screws
Ballasted solution
Concrete ballast blocks can be readily specified to match the array size
and calculated wind loads.
The spacing between module rows is dictated by the site topography and the degree of inter-row
shading that is deemed acceptable. Providing sufficient access between rows for cleaning or grass
cutting vehicles also needs to be considered.
(a) Larger gaps between rows: less inter-row shading, better kWh/kWp performance.
(b) Smaller gaps between rows: larger array (kW) can be installed.
Array pitch
Like the selection of row spacing, the choice of array pitch is dictated by the site topography and
the degree of inter-row shading that is deemed acceptable.
The choice of the array pitch may also depend on the time of year when optimum performance is
required. A shallow tilt angle gives maximum power in the summer, when the position of the sun is
high in the sky, while a larger tilt angle results in better performance during spring and autumn.
140
NOT FOR COMMERCIAL USE OR REPRODUCTION
100
80
60
40
20
0
0:00 4:48 9:36 14:24 19:12 0:00
In addition to considering inter row shading, other factors will also influence the layout of a
ground mounted PV array, including:
Draft for Comment
Tracker systems can be classified into single and twin axis trackers. Twin axis trackers will adjust
both the array orientation and tilt to keep the array at the optimum solar position.
Tracker systems can be operated via a direct sensor (which determines the brightest spot in the
sky) or via devices that compute the local celestial bearing of the sun by applying a set of
equations (using the local time, date, latitude and longitude).
The selection of a tracker system largely depends on the site-specific irradiance profile, including
both direct and diffuse irradiance components. A study would normally be undertaken to
calculate the difference in energy yield between a tracking and fixed tilt system. This is then
balanced against the additional capital cost and operational cost (maintenance) of the tracking
system.
Manual adjustment: ground-mounted array frames that facilitate manual adjustment are also
available. A typical example is a frame that has two or three tilt positions to allow the array to be
adjusted for the season (steeper for winter, shallower for summer).
NOTE: when considering shade loss between rows, module orientation (landscape vs portrait) also need to be
considered – see Section 3.6.
Variant 2
Draft for Comment
Variant 4
11.5.4 Access
Large ground-mounted PV systems (PV farms) will typically require the access roads to permit
COPYRIGHT © The IET
delivery by heavy goods vehicles, usually articulated lorries. An assessment of the access road
needs to be performed in relation to both the load bearing capacity and suitable turning radius.
Upgrading of access tracks and widening of gateways is common on many solar farm projects.
As well as the construction phase, access for O&M purposes also needs to be considered. This will
typically need to facilitate access to all module arrays, string combiner boxes, inverters and
substations.
11.5.5 Security
Typically, the security system in a large-scale PV site comprises a perimeter fence and camera
system.
The design of any security camera system needs to consider the type of camera technology, the
height of the camera posts and the terrain of the land. The visual inspection of the camera
technology and the alarm system should be able to differentiate any animal movement and a true
security breach.
In case of metal fencing, the earthing of the PV plant may need to be connected with the fencing
NOT FOR COMMERCIAL USE OR REPRODUCTION
12 System monitoring
PV system monitoring is desirable, because it allows the system owner and the installer to review the
generation and performance of a system and to pick up any potential problems. PV monitoring systems
make use of a variety of inputs and sensors in order to keep track of key parameters, and the information
can be displayed on a variety of different devices, either locally or remotely online.
NOT FOR COMMERCIAL USE OR REPRODUCTION
Additionally, most inverters will include an earth fault alarm provision. In the case of the earth fault alarm,
it is not enough for the inverter to show earth fault messages on an inverter display, and it should have
In addition to manually taking FIT readings, it is also possible to remotely and automatically obtain the
measurements. This is particularly useful where multiple systems are managed by a single entity (for
Draft for Comment
example, a council or housing association). Such systems usually work using GSM-enabled generation
For systems above 30kW, the FIT provider will require the installation of an export meter, which again
must be OFGEM- or MID-approved. This provides the information that determines the amount of ‘export
tariff’ the customer will receive. This is installed and maintained by a licensed meter provider, not the PV
installer.
COPYRIGHT © The IET
Where:
Calculated Plant Output (kWh) = Solar Irradiation × Area of Array × Module Efficiency
NOT FOR COMMERCIAL USE OR REPRODUCTION
Inverter-level monitoring allows problems to be isolated down to a particular inverter. This can be
Systems using DC optimizers or micro-inverters offer monitoring down to the module level. This
Draft for Comment
allows individual modules to be compared against each other, which in turn allows faulty, soiled or
12.4 Sensors
12.4.1 Irradiance Sensors
Often the simplest to measure, irradiance is via a reference cell. As long as the cell is of the same
type as the modules in the PV array, a reference cell provides an ideal means to characterise array
performance as it should have the same spectral, thermal and optical performance as the array.
pyranometer is designed to measure light from all angles, have a wide spectral response and to
have a stable output across a range of ambient conditions. A variety of instruments are available,
with varying degrees of accuracy and response.
For array plane monitoring, irradiance sensors should be installed so that the orientation and tilt is
identical with that of the PV array. Where there are multiple orientations, multiple devices may
be required.
Cell temperature measurements are usually achieved by the use of a resistance thermometer
device, silicon bonded to the rear of the module directly behind the middle of a cell towards the
middle of the module. Good practice is to scan the module with an infra-red camera after the
sensor has been installed to ensure that it is representative of the wider module temperature.
Data-logging systems with internet or phone access can also be configured to send status updates
and error messages via e-mail or SMS. These systems can allow low-system performance or faults
to be picked up quickly and can also facilitate remote warning of earth-faults as per Section 5.9.3.
In some cases, the information can flow in both directions - it is possible for the installer or
manufacturer to perform online firmware upgrades or adjustments to inverter parameters
remotely.
Draft for Comment
12.6 Displays
NOTE: while many inverters have a display, the inverter is usually installed in a place that does not have easy visibility,
and some form of remote display is required.
The simplest home display systems show only generation data, with this data often derived from a current
transformer clipped to the AC cable from the inverter. More complex displays may take data from the
inverter(s) or from a dedicated system data-logger.
NOTE: many home display systems operate over a wireless link. Care needs to be taken when installing such a system
that the radio signal is strong enough to maintain a connection. In the case that the signal is too weak, additional
antennas or boosters may be required.
Public displays are larger devices designed to be installed in a prominent location, such as a reception area
in an office. Again, a wide variety (size and complexity) of devices are available – from simple LED/LCD
numeric displays to LCD screens that display system performance graphs and other relevant information.
The most commonly used type of public display units rely on data from the pulsed output on the system
generation meter. In such cases, care needs to be taken to ensure that the display unit is compatible with
the kWh meter and that the distance between the display and the meter is adequate to obtain a strong
NOT FOR COMMERCIAL USE OR REPRODUCTION
13 Battery systems
This is typically done to allow the system’s owners to increase their self-consumption rate -
storing electricity at times when they have an excess, for use later in the day. It may also be
done to facilitate energy exports to the grid during times when export tariffs are higher.
For some sites, a limit may be placed on the amount of electricity that can be exported. Adding
storage to a system allows a larger system to installed, as the occasional peaks that would
otherwise exceed the export limitation can be diverted to the battery.
For the first two cases, storage is usually only required for a few hours and is limited to storing
excess energy from the PV array; consequently, the battery size can normally be kept fairly small.
However, systems designed to provide a back-up during power-cuts will typically require
considerably larger battery banks as they will need to allow for longer storage periods, prolonged
operation and the requirements of the loads they are expected to run.
A similar consideration applies to the rating of the inverter-charger. A system that is required to
provide electricity during a power cut may need an increased rating due to the size of the loads it
Draft for Comment
is expected to run.
operation
Battery
GRID
AC coupled design
DC coupled design
Battery connected via
Battery connected on
battery-inverter & regulator
PV side of inverter
on the AC side
Draft for Comment
kWh
COPYRIGHT © The IET
kWh
Battery
Battery
GRID
reduced due to the lower power draw.
The overcurrent protective device shall be installed so that the cable between the battery terminal
and protective device is kept as short as practicable.
NOTE: when determining the location of the protective device, any gasses emitted by the battery need to be taken
into consideration – see section 13.7 in this Code of Practice.
The isolator shall be installed so that the cable between the battery terminals and isolator is kept
as short as practicable.
NOT FOR COMMERCIAL USE OR REPRODUCTION
Where a battery is coupled on the DC side of the PV system, the design and specification of PV
array, sub-array or string over-current protection shall consider potential fault currents from both
the PV array and the battery.
Where a battery is coupled on the DC side of the PV system and there is the potential for fault
currents to flow from the battery into the DC side of the system:
(a) String overcurrent protective devices shall be installed to protect the PV modules where:
• I MOD_MAX_OCPR < I B or other upstream device
Where I B = rating of the main battery overcurrent protective device
Draft for Comment
(b) Overcurrent protective devices shall be installed to protect a circuit where the rating of any
In a simple system, the main battery over-current protective device may be the only device to
interrupt fault currents flowing from the battery. However, in more complex systems, additional
protective devices may be installed between the battery and the circuit under consideration. In
such cases, the device with the lowest interrupt rating is used in the above considerations.
currents to flow from the battery into the DC side of the system, all parts of that circuit (cables,
connectors, isolators etc) shall have a current rating greater than I B or other upstream device.
NOTE: as detailed in the previous section, in a simple system the main battery over-current protective device may be
the only device to interrupt fault currents flowing from the battery. However, in more complex systems, additional
over-current protective devices may be installed between the battery and the circuit under consideration. In such
cases the device with the lowest interrupt rating is used in calculations.
Where a battery is coupled on the DC side of the PV system, all parts of that circuit (cables,
connectors, isolators etc) shall have a voltage rating of at least 1.25 x the nominal battery voltage
or the maximum open-circuit array voltage (as calculated in Section 5.1) - whichever is the greater.
NOTE: on opening the battery isolator (or should the overcurrent protective device trip), the DC system voltage will
rise to the array open-circuit voltage.
Charging a battery may also result in the production of gasses such as hydrogen and oxygen that
can result in an ignition and explosion risk. Charging of a lead-acid battery produces hydrogen,
NOT FOR COMMERCIAL USE OR REPRODUCTION
The gases emitted during charging may also contain a mist of the chemicals within, such as
sulphuric acid, which can be a hazard to breathing and to eyes.
A large amount of energy can be stored within a battery, making the accidental short circuiting of
the battery terminals a particular hazard (for example, from a necklace or uninsulated spanner).
This can result in large fault currents with the risk of burns and explosion.
(a) the battery shall be installed in a location with access restricted to authorised personnel.
(d) devices that could form a spark, such as over-current protective devices and isolators, shall be
located outside battery enclosures and in a suitably ventilated zone away from areas where
there may be a build-up of explosive gasses.
NOTE 1: the ventilation required for a battery will depend on the battery type and the enclosure/room characteristics.
COPYRIGHT © The IET
In general, this will require vents at low and high levels – the sizing of these vents and a procedure for calculating
ventilation requirements is contained within BS EN 50272.
NOTE 2: the corrosion resistance required will vary depending upon the battery chemistry.
NOTE 3: battery efficiency can be significantly affected by operating temperature. Freezing may cause failure of
batteries. High temperatures can result in thermal runaway.
Where appropriate, personal protective equipment (PPE) should be located within a battery room.
The provision of eye wash and a neutralising agent may also be appropriate.
The appropriate signs will depend on the battery type. For example, for a lead acid battery, the
following sign would be appropriate:
Where a system is design to operate in islanded mode an isolator shall be installed that:
NOT FOR COMMERCIAL USE OR REPRODUCTION
Where a system is design to operate in islanded mode, a neutral-earth switch shall be installed
that forms a neutral-to-earth bond for the duration of the islanding operation only.
14 Installation
The following flowchart describes the typical phases for a small commercial or domestic PV system:
Planning application
Design and planning phase
Design modifications
Installation – site work approved, if required
submissions
Handover to client
In all cases, it recommended that the local planning authority be consulted before an installation
proceeds, particularly for sites in a conservation area or a World Heritage Site.
It is recommended that consultation with the Local Planning Authority and local community occurs
at an early stage of any large-scale PV project.
(a) utilise previously developed land, brownfield land, contaminated land or industrial land;
(b) where agricultural land is used, use land preferably classified as 3b, 4, and 5 (avoiding the use
of ‘Best and Most Versatile’ cropland where possible);
(c) aim to avoid affecting the visual aspect of landscapes and maintain the natural beauty of the
landscape;
(d) be installed on predominantly flat land;
COPYRIGHT © The IET
The planning process that a large-scale project will require is dictated by the site in question, but
will typically require some or all of the following:
(a) planning application;
(b) ecology/environmental impact assessment;
(c) location plans and elevations;
(d) design and access statements;
NOT FOR COMMERCIAL USE OR REPRODUCTION
In all cases the installation of a PV system on a building shall be notified to the Local Area Building
Control.
NOTE: installations can be notified either by a direct submission (prior to works) and subsequent inspection by a
building control officer or via a competent person scheme (such as those operated by some MCS certification bodies).
While all parts of the building regulations are relevant, of particular note to a PV system installed
on buildings are:
Draft for Comment
It is important to note that Building Regulations differ between Scotland and England and Wales
COPYRIGHT © The IET
15.1 Introduction
The Health and Safety at Work Act 1974 (the ‘Act’) provides the basis for health and safety law in
Britain. The Act sets out the duties that employers and employees have towards each other and to
members of the public. The Act requires stakeholders to examine the risks and take sensible
NOT FOR COMMERCIAL USE OR REPRODUCTION
The Management of Health and Safety at Work Regulations 1999 provides more explicit details on
the measures required to assess the risks. The regulations require companies to make a suitable
and sufficient assessment of the risks to the health and safety of its employees while at work. The
risk to persons not in their employment (arising out of, or in connection with, the conduct of the
company’s business) also needs to be assessed.
The regulations require employers to carry out a risk assessment. Following this, an employer
needs to implement the health and safety measures that were identified by the risk assessment.
Competent people also need to be identified to implement the measures. Training and
information needs to be provided for employees and a methodology of working with other people
The management of health and safety requires many other regulations and guidance to be
considered. It also requires a system of monitoring, auditing and improvement to ensure
arrangements are constantly fit for purpose and are evolving to meet changing circumstances.
However, this Code of Practice does not address in any detail these systems or procedures as they
are covered in greater detail from other sources.
NOTE: the CITB-Construction Skills publication: “Solar panel installation - What you need to know to work safely”
Draft for Comment
Duty holders are accountable for ensuring control; they are also responsible for the safe
management, design, installation, operation and maintenance of the electrical systems. To ensure
safe operation and to minimise the risk of injury, management systems will need to include:
(a) policies and procedures that cover the installation, commissioning, operation, maintenance
and removal of the equipment;
(b) definitions of responsibilities and training requirements;
In establishing and applying suitable safety policies and procedures, sufficient technical expertise
may not be available in-house to carry out a risk assessment and to decide on the appropriate
precautions. In such cases, advice from suitably competent organisations should be sought. This
may include advice from electricity distribution companies, switchgear manufacturers or from
specialist HV/LV contractors or consultants.
Draft for Comment
The following table summarises the basic legal requirements applicable to carrying out work on
• The employer must provide suitable safe systems of work. Health & Safety at Work Act
• The employee must comply with such safe systems of work. 1974 - Sections 2 and 7
Electricity at Work
• The work must be carried out in such a way as to avoid danger.
Regulations 1989
• Suitable PPE and equipment shall be provided and used.
Regs 4(3) & 4(4)
Where it is not possible to isolate or there is a need to work live: Electricity at Work
(a) the work will be carried out in accordance with a risk assessed safe Regulations 1989
method or procedure; Regs 12, 13, 14 & 16
(b) persons undertaking this work will be trained and competent to carry
out the work (or be under suitable supervision); and
(c) correct tools, equipment and PPE will be available and used.
A risk assessment is a key step in ensuring effective health and safety practices. Health and safety
regulations require employers to carry out a risk assessment prior to commencing work; where an
employer has five or more employees, the employer needs to record the significant findings of this
risk assessment. A five-step approach is usually followed:
NOT FOR COMMERCIAL USE OR REPRODUCTION
NOTE: the HSE publication INDG163 Five steps to risk assessment provides a good resource for employers assessing
health and safety risks in the workplace.
The following table provides a summary of some of the main hazards that may be encountered
during the construction, maintenance and operation of a solar PV system. Specific sites or
installation methods may incur additional hazards.
The responsibility for safety on solar installations can be broadly split into three phases:
Work Act 1974. The basic principle will be to ensure that all persons undertaking work on
construction sites under his/her control will do so in accordance with risk-assessed safe systems of
work. This requirement also applies to sub-contractors or others engaged in any work activity that
is sanctioned, coordinated or directed by the principal contractor.
When appointing sub-contractors, the principal contractor must ensure that such sub-contractors
are competent to carry out the work, have legally compliant safe systems of work and will deploy
competent personnel who will work in accordance with such safe systems of work.
The principal contractor is also responsible for ensuring that any safety issues relating to the
operational interface between the solar electrical system and the Network Operator’s system to
which the installation will ultimately be connected, are appropriately managed.
Where the owner/operator contracts out the responsibility for the operation, inspection, repair
and maintenance of the HV and LV electrical systems of a solar installation, it is incumbent upon
the owner/occupier to ensure that the contractor has the appropriate safety management
systems, legally compliant risk-assessed safe systems of work, and personnel who are trained and
competent to carry the operations or work.
Irrespective of whether the responsibility for the operation, repair and maintenance functions is
contracted out to a third party, the owner/operator is required to establish an operating policy
(a) the company’s safety management system that sets out the policy and procedures for
operating/working safely at the various voltage levels and equipment;
(b) suitable electrical safety rules and procedures for working on the systems covered within the
contract;
Draft for Comment
(c) certificated evidence of the competence of personnel who will undertake operations and work
High voltage systems associated with large utility connected solar farms vary considerably in size
and complexity and will require procedures tailored to the site.
Access to live substations or switch-rooms should be restricted to persons who are classified as
competent persons (as defined in Regulation 16 of the Electricity at Work Regulations) or are
personally supervised by a Competent Person.
15.5.5 Categories of persons with specific responsibilities under a safety management system
For the effective management and application of electrical safety management systems, the
following categories of persons with specific responsibilities are usually applicable:
i. Designated person
An individual appointed by an organisation (a Board member or a person with responsibilities to
the Board) who has overall authority and responsibility for the high-voltage and low-voltage
electricity systems within the installation and who has a duty under the Health and Safety at Work
NOT FOR COMMERCIAL USE OR REPRODUCTION
v. Competent person
A person approved and appointed in writing by the authorising engineer for defined work,
possessing the necessary technical knowledge, skill and experience relevant to the nature of the
Draft for Comment
work to be undertaken, who is able to prevent danger or, where appropriate, injury and who is
able to accept a safety document from an authorised person or senior authorised person.
16 System commissioning
The inspection and testing of the AC circuit(s) feeding a PV system can be performed in exactly the same
manner that any other AC circuit is handled. The procedure is described in BS 7671 and supporting
documents, in particular Guidance Note 3 Inspection and Testing.
The commissioning procedures required by the DNO are set out in Engineering Recommendations G83/G59
and are discussed elsewhere in this Code of Practice. HV commissioning will be carried out in close
conjunction with the Network Operator and will depend upon the details of the HV connection and circuits.
The requirements for the inspection and testing of the remainder of the PV system installation are set out
against shock
short-circuits.
(b) Check functional earth fault interrupters are fitted (where required).
bonding
(c) Check of any earthing and/or equipotential bonding.
(a) Verify wiring loops minimised.
DC system – lightning &
(b) Measures in place to protect long cables.
overvoltage
(c) SPDs, where fitted, suitably selected and erected.
(a) All DC components rated for DC and for voltage and current maxima.
(b) Wiring selected and erected to suit external influences (wind, UV etc).
DC system – equipment
(c) String/array isolation and disconnection devices correctly specified and
selection & erection
located.
(d) Plug and sockets are of same type and correctly mated.
(a) Means of isolating inverter provided on AC side.
(b) Isolators correctly connected.
AC system
(c) Inverter parameters correctly specified.
(d) RCDs correctly selected and installed (where fitted).
Labelling (a) All parts correctly labelled and suitably durable.
Solar PV CoP :: v1.6 :: Page 129 of 138
© Please do not copy or print
Please send comments – see details on page 1
Polarity test Test to ensure that all strings and arrays are correctly marked and connected.
Test to ensure that all strings are correctly connected within a combiner box (if
Combiner box test
fitted).
String open circuit Test to ensure that module strings are correctly installed and that the right
voltage test number of modules are connected within a string.
Insulation resistance
Test of the insulation resistance of PV string and array circuits.
test
Draft for Comment
In addition to the minimum sequence of tests shown in the table above, BS EN 62446 also
describes other tests that can be performed in some circumstances. These tests are more
appropriate for larger systems or for fault finding. These tests are outlined in the table below:
COPYRIGHT © The IET
(a) Will provide all key string parameters (Voc, Isc, Vmpp, Impp, Pmax).
IV curve test
(b) Can help identify module/array defects or shading issues.
Wet insulation A variation on the standard insulation resistance test – typically only used
resistance test during fault-finding exercises.
NOT FOR COMMERCIAL USE OR REPRODUCTION
Editor’s Note: NB: these tests are taken from the current CDV of IEC62446 – not the one currently
in circulation as BS EN 62446. Depending on timings – we may need to remove the BE EN 62446
reference at the head of this table. To complete following DPC.
Handover procedures can vary significantly and need to be tailored to the site in question.
System documentation shall include, as a minimum, those requirements as set out in BS EN 62446.
The following tables summarise the documentation typically provided on completion of a solar PV system:
(a) Inverter.
Manuals (b) PV modules.
(c) Data-loggers/displays.
NOT FOR COMMERCIAL USE OR REPRODUCTION
Information on the operation and maintenance requirements of the solar PV system should be
provided in the handover pack provided on completion of the system (see preceding section).
During regular operation, little or nothing should be required to enable normal system operation.
However, maintenance or servicing will typically be triggered by:
NOT FOR COMMERCIAL USE OR REPRODUCTION
The interval between periodic verifications may be specified by the client, by the installation
company or linked to service contacts, warranty conditions or performance guarantees.
For installations on buildings, as a general rule, the interval between verifications should be no
longer than that required by the AC system the solar PV system is connected to.
COPYRIGHT © The IET
All sites, no matter the scale, will benefit from an inspection regime. Faults do occasionally
develop in even the best installed and specified PV systems. Missing a fault, or any delay in
identifying a fault, can result in significant loss of income from the PV system.
NOTE: the most obvious fault is usually an inverter failure – if a system has only one inverter this can be seen by a
complete drop in system output. Most customers spot such problems pretty quickly; however, even complete failures
may go unnoticed for fairly long periods of time. This can be exacerbated by a lack of system monitoring/metering, or
due to overly complicated or poorly sited displays.
Poor system performance is sometimes difficult to spot and gets more difficult on larger systems
with multiple strings – where the loss of just one string can easily be missed. String-level
monitoring can detect such faults, but is not installed on all systems.
Sites that typically opt for a regular inspection from a PV specialist include: large systems; systems
on public buildings; and systems with multiple strings that have no string level monitoring.
NOT FOR COMMERCIAL USE OR REPRODUCTION
Under WEEE, PV companies have to ensure the recycling of damaged or end-of-life modules.
WEEE compliance can be ensured by participation in a service such as that offered by PV CYCLE
(www.pvcycle.org.uk).
Annexes
Annex A - Checklist for solar PV system design and installation (based on flowchart/key
recommendations)
Editor’s Note: To complete following DPC.
• BS EN 62446
This section illustrates typical system labels (as described elsewhere in the text). Labels need to
be clear and constructed to remain legible and affixed for the lifetime of the system.
NOT FOR COMMERCIAL USE OR REPRODUCTION