SCADA System Fundamentals-R1
SCADA System Fundamentals-R1
SCADA System Fundamentals-R1
P: (877) 322-5800
info@cedengineering.com
SCADA System Fundamentals
INTRODUCTION
Just as different countries have their own languages so do different technologies. The first step
to understanding a new technology is learning the unique language of that technology. This
course is intended to provide you with an understanding of the terms and equipment associated
with Supervisory Control and Data Acquisition (SCADA) systems.
SCADA systems at their fundamental level are Industrial Control Systems. They are computer
based control systems that monitor and control industrial processes that exist in the physical
world. SCADA systems can be found in manufacturing facilities, oil production and processing,
pharmaceuticals, energy, water treatment and distribution, and the list goes on. They are the best
control method for processes that have large amounts of data that need gathering and analyzing,
or are spread over large distances, or require critical control in fast paced processes.
• DI – Discrete Input
• DO – Discrete Output
Discrete signals (also called Digital signals) provide an ON or OFF input to a SCADA system.
This is the same binary signal format used in computer processors.
• AI – Analog Input
• AO – Analog Output
Analog signals are continuous. A change in signal value reflects change in the parameters being
monitored. Examples of analog signals are temperature and pressure.
The signals generated by the instruments being monitored by a SCADA system are voltage or
current based. Analog signals can be formatted as: 4-20 mA, 0-20 mA, 1-5VDC, 0-5VDC,
-10VDC to 10VDC.
Values (whether discrete or analog), when used in a SCADA system, they need to be seen by
Operators to be of any use.
OIT’s provide a local interface, typically in a remote location or into an isolated system like skid
mounted equipment. Screens to display information have a simple layout since displays are not
large; anywhere from 4 inches to 14 inches.
HMI software is used at the Central Control location. Software is installed on computers with
faster processors and larger monitors so the screens display more information. They also make
use of animation to emphasize critical data or focus operator attention to important areas of a
process or annunciate an alarm.
The work horse of the SCADA system that effectively grabs data from instruments, converts the
information to a format a computer program can understand, and handles high speed
communication is the:
The Programmable Logic Controller (PLC) was invented in 1968 to support the automobile
industry by Bedford Associates’ engineer Dick Morley. The first PLC was called a MOdular
DIgital CONtroller, aka MODICON.
Over time variations of the PLC have developed. The two primary ones are:
The Remote Telemetry Unit (RTU) was developed to gather data and then transmit that data to a
remotely located processor. A RTU has communication capabilities of a PC and the IO
capability of a PLC, as well as being industrial hardened. However, it does not control processes
using an internal program. It functions as a Data logger that can transmit data at a certain time to
Central or when polled. A hybrid version of the RTU contains a PLC that does control local
processes and performs the communication functions of a RTU.
A PAC is the next generation of a PLC. It has the same form and function as a PLC but its
processor is more related to a computer in its speed and computing methods. Its greatest
advantage is the communication function which allows it to work more effectively with modern
communication networks that are Ethernet based.
Data gathering and system control at the highest level is broken into two basic systems:
Definition of SCADA is a Monitoring and/or Control System that utilizes a central computer for
storing information, and onsite/remote hardware to monitor facilities and processes. Control may
be automatic or manual and may occur at the remote units or the central computer.
Definition of DCS is a Monitoring and/or Control System that utilizes a central computer for
storing information and onsite/remote hardware to monitor facilities and processes. Control may
be automatic or manual and may occur at the remote units or the central computer.
While a SCADA system and a DCS system are essentially the same at all levels, there is a very
basic difference. A SCADA system is event driven and operator concentric. It is data gathering
orientated. Data is stored in database and control is usually remotely originated. Whereas, a
DCS is process state driven. It is directly connected with field devices and control is done
locally and automatically. The operator is just informed of what has happened.
A SCADA master station generally considers changes of state (both status points and analogue
changes leading to alarms) as the main criteria driving the data gathering and presentation
system. Any undetected changes of state simply cannot be missed. A change of state will cause
the system to generate all alarms, events, database updates and any special processing required
relating to that. Event lists and alarm lists are of major importance to the operator, sometimes
more so than data screens. S is for Supervisory - an Operator takes action.
Conversely, DCS systems are process control systems that are state based and consider the
process variable's present and past states to be the main criteria driving the DCS. PLC protocols
are generally register scanning based, with no specific change of state processing provided.
Should a point toggle between scans, it will not be seen by the DCS. If any change of states are
critical (as some would be for a DCS used for SCADA applications), a point must be latched on
until it is confirmed it has been scanned, which can be difficult and non-deterministic. DCS
software tasks are generally run sequentially, rather than event driven. If a process starts to
move from a set parameter, the DCS responds to maintain that parameter value. Notifying the
Operator is a secondary consideration. Events and alarm lists are secondary in importance to the
process displays, and filtering may not be as complex and flexible. On the up side, the
generation and display of data, especially analogue trends and standard process blocks, is far
more user friendly and easier for both operators and engineers.
Original SCADA systems were proprietary. The Manufacturer built all the hardware, software,
installed the equipment and did all the programming.
• Field Instruments
• Central Computer Station including HMI Software – Proprietary for specific RTUs or
open including interfacing many products
A. FIELD INSTRUMENTS
a. Limit switches
b. Pushbuttons
c. Float switches
e. Relay contacts
f. Selector switches
Analog signals generally come from instruments and motion controlling equipment. The most
common instrument is the analyzer. Analyzers are test equipment located in the field for
monitoring the quality of a process. Analyzer primary signal output is analog but there are
typically some discrete contacts for alarms. Below are some examples of analyzers:
Below is a Chlorine Analyzer used to measure the level of chlorine in water leaving a treatment
plant to ensure it is safe for humans.
• Running (Discrete)
• Fault (Discrete)
PLC’s come in a wide variety of sizes and shapes. They are used from controlling nuclear power
plants to controlling a sump pump in a parking garage.
High end PLC’s can handle multiple racks of IO modules, various communication modules, and
may be installed in a redundant configuration so the loss of a power supply or processor will not
stop control of a facility.
The latest step in the evolution of PLC’s is the Programmable Automation Controller (PAC).
A PAC has a computer processor so it works better with Ethernet networks (routers/switches)
which are becoming prevalent in SCADA systems. Programming can also be done in more main
stream programs (C++, etc)
Programming is usually simple. Sometimes the programming can even be done with the keys on
the front of the PLC. Relay Ladder Logic was the first programming language for PLC’s. It
mimicked the wiring diagrams electricians were used to seeing in control panels in software. In
fact, electricians were the first PLC programmers.
As hardware and software changed, the companies making the products started diverging. It
became apparent that standards had to be developed so the software and hardware could work
together. There also started to be programmers who were familiar with multiple high level
programming languages and never saw the inside of a control panel. In Europe IEC developed
standard 61131 which specified five styles of programming to be used in PLC’s:
• Structure Text
• Instruction List
PLC’s cannot be mounted to a wall and left unprotected. They are mounted in enclosures that
protect them from hostile environments. A typical PLC panel is shown below with high end
PLC’s configured with redundant processors and power supplies.
This is an example of a control panel that shows the customized approach taken to building
control panels. This is designed for a site with a large number of physical IO. A radio will be
This style reflects the original design on RTU’s. It has a processor to handle communications
via the radio mounted on the door. It receives signals from field devices which it passes through
to Central for display by the SCADA HMI. It then passes any commands from Central to the
field devices.
Autodialers (shown below) are a very basic form of RTU. This device receives site alarms as
Digital Input signals. It then calls a Duty Operator over a standard telephone line (POTS) or a
cell phone. The Operator can acknowledge the alarm using the telephone keyboard. Higher end
Autodialers also allow the Operator to do basic controls via the keyboard such as starting a
backup pump or operate valves.
Radios are the most common communication method in large SCADA systems. Licensed radios
were originally used. Then in 1987 the FCC marked a radio frequency band segment for
Industrial Scientific Medical (ISM) use. This was an unlicensed segment that was opened for
use and did not require a license. The ISM is in the low 900MHz range.
The ISM band is limited to a maximum of 1 Watt transmitting power. This was the method
selected to reduce interference by limiting the range of the transmissions. Licensed radios are
still used in SCADA systems for operators who have a long distance that needs to be covered
between sites.
• Up to 5 Watts Power
A recent trend in SCADA system has been the incorporation of video cameras and still cameras
to provide Operators real time images of what is happening at remote sites. The need for
increased security was the driving force behind this trend.
Images contain a lot of data. In order to transmit images over a radio link and make them
practical, frequencies in the 2.4 GHz and 5.8 GHz are used.
As electronics improved, radios became smaller while still keeping the same performance
capabilities. This style of radio is designed to be mounted on DIN rail.
The two basic workhorse antennas of SCADA systems are YAGI and Omni.
YAGI OMNI
An omni antenna will be used at a SCADA Central site to broadcast to RTU’s at many different
locations. The yagi antenna transmits radio signals in the direction the antenna is pointing.
As higher radio frequencies (2.4 GHz and 5.8 GHz) have come into use for transmitting more
data (e.g. video signals), panel and parabolic antennas are now common in SCADA Systems.
Another application using radios is wireless IO. This is a paired set of radios that have terminals
for connecting physical IO signals (discrete or analog). One radio is for connecting field
devices: a pressure transmitter or a high level float. The second radio receives the signals with
the field devices values and retransmits the signals over wires connected to a PLC.
The two radios are paired to work together. They cannot communicate to any other radios. This
system eliminates all the conduits and wires that would have been installed to connect the field
devices to the PLC. No special communication configuration had to be designed to allow the
radio to talk to the PLC. This is a way to save money when needing to pick up a single point and
tie it into a SCADA system.
Originally serial communications were conducted over special cables with various protocols
(Fieldbus, ControlNET, Modbus RTU, etc). These were the standards for many years and they
are still used frequently.
The late comer Ethernet has recently made big move into the field. As the electronics became
industrialized, the ability to use the same communication in a SCADA system (that the IT
Department was familiar with) became a money saver.
It also streamlined the interface between PLC and SCADA computers. It has simplified SCADA
communications by allowing the gathering of data from “smart” devices such as VFD’s, power
monitors, analyzers, etc. with just a single cable.
In addition to the traditional radio and serial cable communications, SCADA systems also use:
• Wireless Internet
• DSL Broadband
D. Central Computers
One of the first steps in designing a SCADA system is to determine which Communication
Protocol will be used. The most common protocols used are:
• DEVICENET
• CONTROLNET
• Profibus
• Foundation Fieldbus
• DH+, DF1
• DNP3
Protocols are the languages that the equipment uses to communicate. Just as people speak
English, French, German, etc., so have different protocols been developed by different
manufacturers. These different protocols are intended to maximize the hardware benefits of their
equipment. Some of these protocols are open for anyone to use and some are proprietary.
Also, there is hardware and software to interface with the operators. This side of the process is
very graphic oriented.
• SCADA Fundamentals
• Alarm Annunciation
• Remote Control
• Alarming
• Reporting
• Security
• Auto-Dialer / Pager
• Remote Monitoring
The SCADA HMI software is written to provide these services to the Operators for their day to
day operations:
• SCADA Fundamentals
• Analog Summary
• Detail Report
• Water Quality
Another very important feature of SCADA HMI software is documentation for historical
purposes. The data collected is achieved and then distributed in various formats. This
information helps with maintenance as well as reporting to supervisory organizations.
A typical graphics screen allows the operator in a quick glance to see the status of all the critical
equipment and processes in an area.
CONCLUSION
SCADA systems are a vital tool for keeping our society going. As electronics and
communications have improved, so have the capabilities of SCADA systems. SCADA systems
make controlling large and small processes easier for Operators whether they are in
telecommunications, water treatment, manufacturing, energy production, oil production,
transportation, etc.