ABC Costing
ABC Costing
ABC Costing
Annual production
Machining Cost 5000
Component Cost 15,000
Set- up Costs 30,000
Packing Cost 30,000
80,000
In addition to the above (Saturn), some supplementary data is now available for Saturn Company.
Cost Driver Data Sky Bar Moon Egg Sun Bar Total
Actual production / Sales Units 500,000 150,000 250000
Machine Hours per unit 0.01 0.04 0.02
Number of production set ups 3 1 26 30
Number of components 4 6 20 30
Number of Customer orders 21 4 25 50
Required;
Calcualtion of OAR
Annual production Total cost Total cost driver OAR
Machining Cost 5000 16000 0.3125 Per Machine Hour
Component Cost 15,000 30 500 per components
Set- up Costs 30,000 30 1000 per set up
Packing Cost 30,000 50 600 per customer order
80,000
Working 1 - Total Machien Hours Sky Bar Moon Egg Sun Bar
Actual production / Sales Units 500,000 150,000 250000
Machine Hours per unit 0.01 0.04 0.02
Total 5000 6000 5000 16000
Allocation Overheads
Sky Bar Moon Egg Sun Bar
Machining Cost 1562.5 1875 1562.5 5000
Component Cost 2000 3000 10000 15000
ANNUAL PRODCTION:
COST POOL COST DRIVER
MACHINING COST 5000 MACHINE HOURS PER UNIT
COMPONENT COST 15000 NUMBER OF COMPONENTS
SET-UP COSTS 30000 NUMBER OF PRODUCTION SET UPS
PACKING COSTS 30000 NUMBER OF CUSTOMER ORDERS
80000
CALCULATION OF OAR:
OAR(OVERHEAD ABSORPTION RATE)= TOTAL OVERHEAD / COST DRIVER
ANNUAL PRODUCTIONTOTAL COST COST DRIVER OAR
MACHINING COST 5000 16000 0.3125
COMPONENT COST 15000 30 500
SET-UP COSTS 30000 30 1000
PACKING COSTS 30000 50 600
OH ALLOCATION:
SKY BAR MOON EGG SUN BAR
MACHINING COST 1562.5 1875 1562.5
COMPONENT COST 2000 3000 10000
SET-UP COSTS 3000 1000 26000
PACKING COSTS 12600 2400 15000
TOTAL OH : 19162.5 8275 52562.5
DEMAND 500000 150000 250000
OH PER UNIT 0.04 0.06 0.21
Jason (LTD) manufactures three products: P, Q, and R.
(a) Calculate the cost (and hence profit) per unit, absorbing all the overheads on the basis
of labour hours.
(b) Calculate the cost (and hence profit) per unit absorbing the overheads using an Activity
Based Costing approach.
PROFIT(LOSS)PER UNIT:
P Q R
SELLING PRICE 20 20 20
TOTAL COST PER UNIT 18.36 48.89 16.92
PROFIT(LOSS)PER UNIT: 1.64 -28.89 3.08
OVERHEADS:
COST POOL COST DRIVER
SET-UP COSTS 90000 NUMBER OF SET-UPS
RECEIVING 30000 NUMBER OF DELIVERIES RECEIVED
DESPATCH 15000 NUMBER OF ORDERS DESPACTHED
MACHINING 55000 MACHINE HOURS
190000
CALCULATION OF OAR:
OAR(OVERHEAD ABSORPTION RATE)= TOTAL OVERHEAD/COST DRIVER
OVERHEADS COST DRIVER OAR
SET-UP COSTS 90000 25 3600
RECEIVING 30000 22 1363.64
DESPATCH 15000 60 250
MACHINING 55000 94000 0.59
OVERHEAD ALLOCATION:
P Q R
SET UP COST 36000 46800 7200
RECEIVING 13636.36364 13636.363636 2727.272727273
DESPATCH 5000 5000 5000
MACHINING 29255.31915 2340.4255319 23404.25531915
TOTAL OVERHEADS 83891.68 67776.79 38331.53
DEMAND 25000 2000 20000
OH PER UNIT: 3.36 33.89 1.92
OVERHEADS:
CALCULATION OF OAR:
OVERHEADS: COST DRIVER OAR=OH/COST DRIVER
TOTAL PRODUCTION SET
UP COSTS 140000 28 5000
TOTAL INSPECTION COSTS 80000 8 10000
OTHER OVERHEAD COST 96000 48000 2
OH ALLOCATION:
HANDLING RECEIPT OF
MATERIALS 815.08
ISSUE OF GOOD TO
PRODUCTION 337.44
1152.52
OAR 3000
SET-UP COST FOR B 24000
PRODUCTION FOR B 40000
SET UP COST PER UNIT 0.60
R S
PRODUCTION UNITS 80000 60000
BATCH SIZE 100 50
NO. OF BATCHES 800 1200
SET-UPS PER BATCH 3 3
TOTAL SET-UPS 2400 3600 6000
OAR=OH/COST DRIVER
OVERHEAD 180000
COST DRIVER 6000
OAR 30
OH ALLOCATION FOR S:
MACHINE SET UP 108000
PRODUCTION 60000
SET-UP COST PER UNIT 1.8
C D
TOTAL PRODUCTION SET
UP COSTS 65000 75000
TOTAL INSPECTION COSTS 50000 30000
OTHER OVERHEAD COST 16000 80000
TOTAL OVERHEADS 131000 185000
DEMAND 1000 4000
OH PER UNIT 131 46.25