Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                

Basics of EMI and EMC

Download as pdf or txt
Download as pdf or txt
You are on page 1of 16
At a glance
Powered by AI
The key takeaways are that earthing, equipotential bonding and proper cabling installation are important for safety and EMC compliance. A well-designed earthing and bonding system is required for all cabling systems.

Earthing and equipotential bonding are used for safety and EMI mitigation. The main functions of earthing are to protect life from electrical faults and provide a path for surges and emissions. Equipotential bonding ensures all conductive parts have the same potential.

The standards require a low impedance connection from equipment to earth electrodes and all conductive parts to be bonded to create equipotential zones. The earthing and bonding system must be designed and installed properly.

Basics of EMI and EMC

Earthing, earthing and equipotential bonding

Practical information for cabling systems

A publication of Tyco Electronics


Introduction

Earthing, equipotential bonding and earthing are a major part of all new buildings and
facilities. These have a great influence on the EMC of the system and the mitigation of EMI
wherever applicable.
As the number of electronic devices increases, every building owner is required to abide by
all applicable EMC regulations and laws. In regards to telecommunications equipment and
cabling systems, there is often an uncertainty about what to do and to find the correct way
for a proper installation.
This guide is intended to give some basic explanation of these issues as they relate to
cabling systems. In general EMC is a vast subject and there are various books and literature
available.

This guide briefly highlights the parts covering earthing, equipotential bonding and electrical
power distribution. But all parts are important in regards to EMC and are valid for shielded
and unshielded cabling systems.
There is often a misunderstanding between the requirements for earthing and equipotential
bonding for both shielded and unshielded systems.
This misunderstanding is often the problem in practise. It is often assumed that this is the
responsibility of the electrical installer or the architect and not the responsibility of the data
cabling installer. But in fact it is a responsibility shared by all parties. In regards to EMC it is
the responsibility of the consultant and or architect to ensure the installed systems are
compliant.
EMC is more and more important and therefore its relevance is crucial to understand.
Therefore European standards continue to emphasis this importance.
With 10 Gigabit Ethernet most of the existing rules have to be reconsidered. The future is
shielded and EMC is the key issue.

Thorsten Punke Dipl. Ing.


Program Manager EMEA
tpunke@tycoelectronics.com

2
Earthing and equipotential bonding
EMI and EMC are heavily dependant on sounding earthing and equipotential bonding
principles. The main functions of earthing are Safety and EMI mitigation. The primary
function of earthing is to:

Save the life of humans and animals in case of any electrical fault.

This can be achieved by installing a low impedance connection to the protective conductor.
At the other end of this conductor there is a connection to an electrode in the ground.
The main connection to ground is called the protective earth (PE) and is recognised by the
typical green/yellow insulation colour.

A second function is to have a defined path for surges in the power system, lightning and
emissions from outside sources like radar station, broadcast stations etc. It is fundamental to
understand, that only a proper earthing system can prevent harm from the issues referred to
above. The intention of European standard EN 50310 is to provide the optimum earthing and
equipotential bonding conditions for buildings. Even though the focus of this discussion is for
buildings with communication technology installation, the standard shall be applied for at
least all new buildings and if possible for existing buildings.

All office and company buildings today have a communication technology installation, and
even more so residential buildings. Many problems can result from an improper earthing
system. In practice screening, earthing and equipotential bonding will be combined. To make
it clear:

Earthing and equipotential bonding are applicable for any IT


cabling system! Furthermore, these systems apply to both
unscreened and screened cabling systems!

An earthing and equipotential bonding implementation is


necessary for EMC and safety reasons!

The latest edition of EN 50310 and EN 50174-2 state clear that these efforts are
applicable to any IT system!

Fig 1: Bonding of earthing systems


3
Safety: This is valid for all components if they are able to carry dangerous voltages and
currents in case of an electrical fault. As a rule, all metal enclosures are connected as part of
an equipotential bonding network to all other parts like metallic conduits, metal beams, steel
girders etc. The aim of an equipotential bonding network is to improve the EMC
performance.

Fig 2: Termination earthing system to steel armour for Mesehd bonding concept (Obo Bettermann)

Functional earthing: A functional earth connection serves a purpose other than providing
protection against electrical shock. In contrast to a protective earth connection, a functional
earth connection may carry a current during the normal operation of a device. Functional
earth connections may be required by devices such as surge suppression and
electromagnetic-compatibility filters, some types of antennas and various measurement
instruments. Generally the protective earth is also used as a functional earth though this
requires care in some situations.

Note: A good functional earthing system is necessary for safety reasons! A cabling
system requires a well designed earthing system to perform properly.
This is applicable for both unshielded and shielded systems! Even when a fibre optic
cabling system is installed a fully functional earthing system is mandatory (earthing
of metal enclosures)!

Any other interpretation is against electrical safety rules in most countries!

4
Equipotential bonding

This refers to the need to connect all metalwork or conducting parts within an electrical panel
or on a machine to the protective earth. Equipotential bonding has a safety and an EMC
aspect. This is also the case in a house or commercial building, where ideally all metallic
components are connected to the equipotential bonding network. These include:
• All metal conduits within the building, e.g. water and gas conduits
• All metal parts of the building or the construction
o steel girder
o Metal Facade
o Steel in cement
• Metal cabinets for data or power distribution
• Raised floors with metal uprights
• Metal cable conduit

Fig 3:Equipotential bonding connector during building phase (Obo Bettermann)

5
All connections will terminate at
the main equipotential bonding
terminal.

Note:

In regards to IT systems all


relevant disciplines shalle be
terminated at the terminal bar.

• PE Power system
• PE Telecom system
• Upright Pins of raised
floors
Fig 5: Main bonding terminal
• Metallic cable trays
• All parts of a cabinet

Fig 4:Meshed Equipotential bonding network EN 50174-2

6
Facts:
• Earthing and equipotential bonding is a must for safety and EMC reasons
• A TN-S system is mandatory for all buildings with IT!
• TN-S shall be installed and is recognised by most electrical standards
• The equipotential system (equipotential bonding) has to be part of the EMC design
• All metal parts have to be included
• A meshed equipotential bonding system is better then a star equipotential bonding
system

Power distribution System

For residential buildings and small buildings serviced directly by the power authority, 4-
conductor power cables will enter the buildings.

In the main switchboard, there is a


connection from the PEN conductor to the
equipotential terminal bar. All metallic
parts and systems which have to be part
of the equipotential bonding system will
be connected to this terminal bar.
Note: The link between the PE conductor
and the PEN conductor shall be close to
the source (transformer or point of
supply) and the only one in the whole
Fig 6: TN-S system
installation. Beyond this point all cables
shall have either 3 or 5 conductors. EN
50310 prohibits the use of a PEN
connection, in other words:

TN-S installation only!!!

This guarantees that the PE conductor


carries no current (unless there is an
electrical fault) and the return current is
only flowing through the N conductor.
Therefore the total current at the main
equipotential bonding bar is 0.
Fig 7: TN-S: Bridge between 3 transformers

Note: TN-S is preferred in EN 50310 and meanwhile the default system in accordance
to most local electrical wiring regulations!
In some countries (e.g. Australia and New Zealand, the TN-C-S earthing system is
used.

7
Installation of IT cabling systems
As any building today contains IT equipment, electrical and other standards reflect this in
their content.
This means that all rules and recommendations in regards to EMC and safety apply to any
kind of IT system. From a practical point of view, the most common equipment includes
racks and metal panels, metal path ways, raised floors with metal frames.
In regards to safety and EMC all equipment needs a defined path to EB (equipotential
bonding).
In the cabinet all patch panels must have very good electrical connection (zero dc
resistance) to the cabinet. This cabinet shall be connected to the equipotential bonding
system. All bonded panels have to
be terminated to the terminal bar
(Fig 85). The insulation colour of
the earthing conductor shall be
green/yellow as used for the PE.

Note: Bonding of panels is


applicable for both shielded and
unshielded systems!

All parts in the rack have to be


connected to the earth bar. That
includes cabinet doors and metallic Fig 8: Bonded panels in a cabinet
parts which are maybe electrically
isolated
The outlet side is terminated with
the shielded patch cord on the NIC.
The metal housing of the RJ-45
jacks on the NIC provides the
connection to earth in the device.

Fig 9: Bonded panels to the terminal bar

8
Shielded systems
New products provide automatically excellent earth
connection to the panel. The “closed” principle is
done by design. Once the cable is terminated the
jack has just to be clicked into the panel, and that’s
all.
Old technology products have UTP jacks where
the installer has to “build” the shield around it.

Fig 10: Screen transfer panel and mounted


shielded jack

By installing the shield to each jack the installer atomically fulfils the requirement of
EN 50310:
“Cable screens shall be bonded directly to racks, cabinets or where required to the
dedicated SRPP at least at each end. Circumferential (i. e. 360 °) connections are most
effective.”

Note: The only additional effort is the shield termination to the jack. This takes about
10 seconds for the integrated shielded technology designed products. The
connection to the EB system of the shielded link
is done by the panel. As stated earlier, earthing
and equipotential bonding have to be done for all
IT systems!

There are sometimes misunderstandings in regards


to screening, earthing, one side, two sides. In fact it
is very easy.
Fig 11 : Screen transfer Plug/Jack

Example: We have shielded jacks, as shielded cable


and shielded pact cords

The total channel shall contain shielded products only. The screen shall be terminated on
both sides. This is done by terminating the screen at both sides with the connecting
hardware, in our example the jacks. In case of modern die cast jacks this is done
automatically. Old fashion products need an extra connection which causes difficulties.

This complete channel shall be terminated to the equipotential bonding system. This is done
by the panel, as this has to be terminated to the equipotential system (SRPP).

In the case of die cast jacks (integrated shielded technology) the cable link includes a
connection at the fixing points in the panel, (see picture above).

9
Outlets do not have to be bonded. To improve the overall EMC performance the link is
connected at the device side to the PE of the power system. All Switches, NIC’s and
Notebooks have shielded RJ 45 ports. Those ports are connected to the PE of the power
side in the device.
In this configuration the shielded system provides additional EMC performance and support
the idea of a meshed concept.
Cable routing

With higher data rates and more electronic devices installed, cabling installation and routing
have to be done in the proper way. Much of this useful information can be found in EN
50174-1/-2.
The main issue for IT systems is the sparation from power cables, as they are mostly
commonly installed in one cable tray system.
Today EN 50174-2 contains the following table:

Type of installation Distance A

Without divider or Aluminium divider Steel divider

non-metallic divider

Unscreened power cable and 200mm 100 mm 50 mm


unscreened IT cable

Unscreened power cable and 50 mm 20 mm 5 mm


screened IT cable

screened power cable and 30 mm 10 mm 2 mm


unscreened IT cable

screened power cable and screened 0 mm 0 mm 0 mm


IT cable

As shown above, metal dividers or cable screens help to reduce the separation. This is the
best way, otherwise large separations would be required. There is no other way. Best
example is a screened power and IT cable, where therequired separation distance is 0 mm!
Note: If the cable conduit is metallic, it has to be bonded properly!

10
The fairy tales
Although the physical environment is clear, some parties propagate misleading statements
and confusion. The following pages explain basic of physics and follow existing standards
and EMC rules.
Fairy tale No. 1
If a shielded system is used, the screen is propagating EMI, is dangerous and an earth
loop is creating problems.

As mentioned we have an equipotential bonding


network. This means electrically everywhere on
the bonded network is at the same potential = 0V!
In pactice the following components are at the
same potential

• PE of electrical system
• Metallic parts of the building
• Metallic service conduits (e.g. water
conduits)
• All metal-enclosed IT devices
o Cabinet
o Panels
o Screen of IT cabling system Fig 12: Euipotential bonding

Conclusion
• No loop
• No antenna effect

There can’t be any loop as everything is at zero 0 potential. This is again the main intention
of equipotential bonding.

To propagate EMI any kind, electrical energy must be present. This can only be done, if a
conductor is carrying some kind of electrical energy. The screen of a cabling system is
terminated to to the equipotential bonding network, which, under normal conditions carries
no current and has 0V potential to earth.
Therefore the screen is unable to propagate any EMI.

11
Fairy tale No. 2

The Symmetry (Twist) is the only way to provide good EMC conditions.
To explain this we have to come back to the basics. Modern data transmission is called
symmetrical data transmission. All copper systems (UTP and STP) have the same design.
Each system contains 4 pairs which are twisted.
The degree of symmetry of a pair defines the ability of a cabling system to provide a level of
EMC. This is called coupling attenuation.
Note: Coupling attenuation is applicable to both, shielded and unshielded systems
and is part of the global cabling standard IS 11801 /EN 50173
This parameter is an indicator the quality of a cabling system is to mitigate any EMI.
There are two ways to fulfil this.

• Twisting
• Shielding
In pactice each cable is a victim of electromagnetic waves and disturbing signals from other
cables, mostly power cables.
Now the facts:

UTP STP
(Symmetry, Balanced (Symmetry, Balanced Pair,
Pair) Screen)
EMC Mitigation mechanism Twist Rate Twist Rate + EM Screen

Coupling attenuation (EMC factor) 40 dB 90 dB

Separation from power cables (EN50174- 50mm up to 200 mm No separation up to 35m,


“2 5mm up to 50mm
ANEXT margins (ISO IEC 11801 Amend.) 0 dB 25 dB

The Pair Twist is just one component of the EMI mitigation method. The complete solution to
EMI mitigation is Pair Twist and a shield. This results in 100% more coupling attenuation
and explains why all systems with PimF cable have no issues with ANEXT. The Twist Rate
of a UTP cable is higher than that of an FTP or PimF cable. This results in higher TCL. But
this is just 50% of the total. Shielded cables have a shield, therefore the Twist Rate is
different and both have to taken into consideration.

12
Fig 13: The real EMC situation

Conclusion: Only coupling attenuation is an indicator of the EMC ability of cabling


systems and UTP cabling has the weaker characteristics. The current 10G discussion
shows this dramatically.

Fairy tale No. 3


A 50 Hz field can’t be mitigated by a shield, the shield makes no sense
In general shielding is the common way to mitigate EMI. This is the common practice in any
industry. The kind of shield depends on the application and transmitting frequency (e.g. 10G
=417 MHz). With higher frequencies the shield thickness can be low, while low frequencies
need a thicker shield. This based on the skin effect.
The shield of modern PiMF cables has been designed to mitigate frequencies in the
operating spectrum (MHz). The 50 Hz field is definetly out of this scope.

13
Quick comparison:
UTP STP

Bandwidth 500 MHz 1400 MHz

Maximum Shannon Capacity 18 Gigabit/s 28 Gigabit/s

Sheath sharing with CATV (862 No Yes


MHz)
ANEXT margins 0 dB 25 dB

Background Noise Need additional protection Fulfilled by design


(IEE 802.3 an)
Complete field testing No (No reliable ANEXT and Yes, no ANEXT and AEFEXT
AEFEXT possible) testing necessary
Coupling attenuation (EMC 40 dB 90 dB
factor)
Connection to Earthing and EB Yes Yes
Margins for future applications No Yes
Lightning protection (LEMP) Low High
Patch Cords 9mm (solid conductor) 6mm (stranded conductors)
Cable diameter 9 mm 7,9 mm
Separation from power cables 50mm up to 200 mm No separation up to 35m,
(EN50174-“2) 5mm up to 50mm
Installation time About 1-2 minutes About 1-2 minutes

Accredited ISO3rd party No Yes


certifications with worst case
ANEXT conditions

Conclusion

The efforts and cost for a well designed eathing and bonding system is independent of the
kind of media that is installed. This is recognised by EN 50310 and EN 50174-2.

The illusion to save money or avoid trouble by installation of fibre optic cables or UTP cables
is an old fairy tale. All standards state this clearly in their publications. Fibre connections
shall be installed between buildings. This is applicable for large installations and plants.

With respect to 10 Gigabit Ethernet, the combination of a shielded system and a well
designed EB system provides maximum EMC performance of the building. The ANEXT and
background noise issues emphasise this.

Consultants in particular should take care of these issues during the planning phase.

14
Facts:
• Earthing and equipotential bonding are a must for safety and EMC reasons
• They are applicable without exception for any IT system
• The cable screen has to be terminated on both sides with the connecting
hardware
• The whole channel has to be bonded at least once to the EB system (Panel)
• Outlets do not have to be bonded
• The total effort for earthing and bonding is the same for all cabling systems

With 10 Gigabit over copper cabling, shielded systems show the advantage of a shield by
completely meeting the 100 m channel ANEXT performance requirement by a margin of
about 20 dB.

The overall future parameter will be Coupling Attenuation for cabling systems and their EMC
performance. While STP systems with PimF cables have about 90dB of coupling
attenuation, UTP systems have only 45 dB. In any case, for both technologies a well
designed Earthing and Bonding system is mandatory. There is no reason anymore not to
join the shielded world.

We extend an invitation to you to join

15
AMP NETCONNECT Regional Headquarters:
North America Latin America Europe Mid East & Africa Asia Pacific
Harrisburg, PA, USA Buenos Aires, Argentina Kessel-Lo, Belgium Cergy-Pontoise, France Hong Kong, China Sydney, Australia
Ph: +1-800-553-0938 Ph: +54-11-4733-2200 Ph: +32-16-35-1011 Ph: +33-1-3420-2122 Ph: +852-2735-1628 Ph: +61-2-9407-2600
Fx: +1-717-986-7406 Fx: +54-11-4733-2282 Fx: +32-16-35-2188 Fx: +33-1-3420-2268 Fx: +852-2735-1625 Fx: +61-2-9407-2519

AMP NETCONNECT in Europe, Mid East, Africa and India:


Austria - Vienna Denmark - Glostrup Greece/Cyprus-Athens Lithuania –Vilnius Romania - Bucharest Switzerland - Steinach
Ph: +43-1-90560-1204 Ph: +45-70-15-52-00 Ph: +30-1-9370-396 Ph: +370-5-2131-402 Ph: +40-1-311-3479 Ph: +41-71-447-0-447
Fx: +43-1-90560-1270 Fx: +45-43-44-14-14 Fx: +30-1-9370-655 Fx: +370-5-2131-403 Fx: +40-1-312-0574 Fx: +41-71-447-0-423
Belgium - Kessel-Lo Finland - Helsinki Hungary - Budapest Netherlands - Den Bosch Russia - Moscow Turkey - Istanbul
Ph: +32-16-35-1011 Ph: +358-95-12-34-20 Ph: +36-1-289-1007 Ph: +31-73-6246-246 Ph: +7-095-926-55-06 Ph: +90-212-281-8181
Fx: +32-16-35-2188 Fx: +358-95-12-34-250 Fx: +36-1-289-1010 Fx: +31-73-6246-958 Fx: +7-095-926-55-05 Fx: +90-212-281-8184
Bulgaria - Sofia France-Cergy-Pontoise India –Bangalore Norway - Nesbru Spain - Barcelona Ukraine - Kiev
Ph: +359-2-971-2152 Ph: +33-1-3420-2122 Ph: +91-80-2841-2433 Ph: +47-66-77-88-99 Ph: +34-93-291-0330 Ph: +380-44-206-2265
Fx: +359-2-971-2153 Fx: +33-1-3420-2268 Fx: +91-80-2841-2155 Fx: +47-66-77-88-55 Fx: +34-93-291-0608 Fx: +380-44-206-2264
Czech Rep.-Slov.-Kurim Germany - Langen Italy - Collegno (Torino) Poland - Warsaw Sweden-UpplandsVäsby UK - Stanmore, Middx
Ph: +420-541-162-112 Ph: +49-6103-709-1547 Ph: +39-011-4012-111 Ph: +48-22-4576-700 Ph: +46-8-5072-5000 Ph: +44-208-420-8140
Fx: +420-541-162-132 Fx: +49-6103-709-1219 Fx: +39-011-4012-268 Fx: +48-22-4576-720 Fx: +46-8-5072-5001 Fx: +44-208-954-7467

16 04/07 © 2007 – Tyco Electronics AMP Deutschland GmbH – All rights reserved
TYCO, AMP and NETCONNECT are trademarks. http://www.ampnetconnect.com/EMEA

You might also like