: CONSTRUCTION OF FOUR STOREY RESIDENTIAL & COMERCIAL
Project Title BLDG.
Project Location : BRGY. SAN ANGEL, SAN JOSE, ANTIQUE
Physical Target : 375 sq. m.
Total Project Cost ₱ 8,914,811.49
Implementation Mode By Contract
Project Duration 298 Calendar Days
Construction of Three Storey Commercial & Apartment Bldg. includes; (1) Site Works; (2) Concrete Works; (3) Formworks & Scaffolding; (4)
Masonry Works; (5) Metal Works; (6) Painting Works; (7) Electrical & Lighting Works; (8) Plumbing Works; (9) Doors & Windows; (10) Tile
Works; (11) Septic Tank
PROJECT SUMMARY
BREAKDOWN OF ESTIMATED EXPENDITURE % OF TOTAL AMOUNT
I. ESTIMATED COST.
A. Direct Cost:
1. Materials 46.82% ₱ 4,173,826.10
1.1 Supply / Delivery
1.2 Testing of Materials
2. Direct Labor: 27.43% ₱ 2,445,573.51
3. Equipment Expenses:
3.1 Rental 2.08% ₱ 185,800.00
323
St. Anthony's College
ENGINEERING AND TECHNOLOGY DEPARTMENT
San Angel, San Jose, Antique
A. Indirect Cost:
1. Overhead, Contingency & Miscellaneous (Up to 15% of EDC) 11.45% ₱ 1,020,779.94
2. Profit (Up to 10% of EDC) 7.63% ₱ 680,519.96
3. VAT (5% of EDC, B1, B2 & B4) 3.82% ₱ 340,259.98
4. Mobilization/Demolition (Up to 1% of EDC) 0.76% ₱ 68,052.00