Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                
Download as pdf or txt
Download as pdf or txt
You are on page 1of 42

KEC International Limited

Power T & D Cables Railways Civil Solar

KEC International Limited 1


Focus On Technology
Presentation By
R.R.Patel
General Manager– Engineering Services
KEC International ltd.

1200 kV Transmission Line Project


at near Bina Substation
KEC International Limited 2
AGENDA

Tower Designs being Deployed


to optimize Right of
way Requirement
1. Developments in foundations to
Reduce Environmental Impact.
Major Challenges &
Considerations in design
of Tower and structures.

KEC International Limited 3


GENERATION RESOURCE MAP

Coal resources – Eastern/


Central India
Hydro potential – North –
Eastern / upper Northern
part
Lignite – Gujarat,
Rajasthan, Tamil Nadu
Load centre – Western,
Northern and Southern
States

KEC International Limited 4


FEATURES OF INDIAN TRANSMISSION
SYSTEM

Generation resources pocketed in few places, demand


spread over entire country
Transmission network accordingly spread over length
and breadth of the country.
To cater to future accelerated growth in power transfer
requirement, geographically spread transmission
network to be strengthened utilizing minimum right of
way.

KEC International Limited 5


FEATURES OF INDIAN TRANSMISSION
SYSTEM

In last decade transmission Network has increased


exponentially .

Transmission line through TBCB route has increased.

Public awareness of Right of Way has increased

KEC International Limited 6


WHAT IS RIGHT OF WAY (ROW)

KEC International Limited 7


ROW COMPENSATION
• As per MOP Guideline-2015:

• i) Compensation @ 85% of Land value determined by


Dist Magistrate based on Circle Rate /Stamp act Rate
of Tower base area (between four legs) is payable.

• ii)Compensation towards diminution of land value in


the width of Right of Way Corridor due to Laying of
Trans line and imposing certain restriction would be
decided by state as per land use ( subject to max.
15% of max circle rate)

KEC International Limited 8


IMPORTANCE OF ROW

A transmission line may pass through


different Land use areas
• Inhabited densely populated areas
• Agricultural areas
• Forest areas
• Hilly/Mountainous areas

KEC International Limited 9


IMPORTANCE OF ROW

Width of ROW Important in


• Densely Populated areas
• Non-availability of required conventional width of ROW
• High Cost of Land
• Forest areas
• To conserve flora and fauna
• Narrow constrained geography with no other alternative

KEC International Limited 10


CONSERVATION OF RIGHT-OF-WAY

STRATEGIES

• Bulk power high capacity lines

• Alternate line / Tower configurations

• Uprating of existing lines

KEC International Limited 11


CONSERVATION OF RIGHT-OF-WAY

BULK POWER HIGH CAPACITY TRANSMISSION LINES

KEC International Limited 12


CONSERVATION OF RIGHT-OF-WAY

Alternate Line & Tower Configurations

•Double circuit / Multi


circuit transmission lines

• Compact structures like


Delta Type

• Very high structures

KEC International Limited 13


KEC International Limited 14
USE OF M/C TOWER

KEC International Limited 15


KEC International Limited 16
KEC International Limited 17
EXTENDED TOWERS FOR SAVING
TREES

KEC International Limited 18


USE OF POLE STRUCTURE

19
KEC International Limited 19
DEVANHALLI CASE STYDY(KPTCL)

UNDER IMPLIMENTATION

• USE OF NARROW BASE M/C TOWER IN ROAD MEDIAN.

• THE CHIMNEY WIDTH SHOULD BE <= MEDIAN WIDTH.

• USING OF PILE FOUNDATION FOR LESSER FOUNDATION


SIZE.

KEC International Limited 20


DEVANHALLI NARROW BASE M/C TOWER

KEC International Limited 21


USE OF GIS IN PLACE OF AIS

• Space GIS requires 40% Area than AIS.


Reduced footprints leads to GIS SS within cities & underground SS in commercial complex

• Maintenance/Operation/Installation : GIS is much easier than AIS.


• Cost : Initial cost of GIS installation is high compare to AIS but overall Life Cycle Cost is low
with reduced maintenance and operational costs

KEC International Limited 22


UPRATING of existing TL
using
HIGH TEMPERATURE
CONDUCTORS

KEC International Limited 23


UPRATING of existing TL

Capacity Enhancement of Existing facilities


•Uprating of existing TL using High Temperature
Conductors.

KEC International Limited 24


TYPE OF CONDUCTORS

Conventional Conductors
•ACSR (Aluminium Conductor Steel Reinforced)
•AAAC (All Aluminium Alloy Conductor)
•ACAR (Aluminium Conductor Alloy Reinforced)
•AACSR (Aluminium Alloy Conductor Steel Reinforced)
•ACSR/AW (Aluminium Conductor Aluminium Clad Steel
Reinforced)
•AAC (All Aluminium Conductor)

High Conductivity / High Capacity Conductors


•Compact (Trapezoidal ACSR conductor)
•Higher conductivity AAAC (AL59 or eqvt)

KEC International Limited 25


TYPE OF CONDUCTORS

High Temperature Conductors


•TACSR (Thermal resistant Aluminium alloy Conductor Steel
Reinforced)

High Temperature Low Sag Conductors


•ACSS (Aluminium Conductor Steel Supported)
•INVAR Conductor
•GAP Conductor
•ACCR (Aluminium Conductor Composite Reinforced)
•ACCC (Aluminium Conductor Composite Core)

KEC International Limited 26


High Temperature Low Sag Conductors

All High Temperature Low


Sag Conductors have
following material structure
Outer aluminium alloy or
Annealed aluminium layers that
can withstand high temperatures
in the range of 150deg C to 230
deg C compared to 100 deg C for
conventional ACSR/AAAC
conductor and an

Inner core that has lesser


thermal coefficient of expansion
than composite conductor
After a certain temperature all the mechanical tension is taken up by the core dictating
the sag of the conductor

KEC International Limited 27


High Temperature Conductors-
Salient Benefits

High Temperature conductors offer following current


carrying capacity (thermal rating)
•TACSR conductor: around 1.8 times of eqvt size ACSR
•HTLS conductor: around 2 –2.5 times of eqvt size ACSR

For new high capacity 400 kV EHV lines, twin bundle


High Temperature conductors can be used in place of
quadruple bundle ACSR resulting in :
•Material savings in tower & foundations
•Reduced construction effort, time & resources
•Comparable capital cost
KEC International Limited 28
High Temperature Conductors-
Salient Benefits

For uprating of existing EHV lines, HTLS conductors


can be used in place of existing conductors resulting
in :

•Increase in power flow capacity (around 100%)

•Avoiding capital expenditure, precious ROW, resources, effort


& time on construction of additional line

KEC International Limited 29


Uprating of 400kV D/C
Siliguri-Purnea Line

Line length : 175kms

Line passes through the


chicken neck area having
serious ROW constraints

Hydro potential in NER to


be accessed through this
corridor

KEC International Limited 30


AGENDA

Tower Designs being Deployed


to optimize Right of
way Requirement
Developments in foundations to
Reduce Environmental Impact.
Major Challenges &
Considerations in design
of Tower and structures.
FOUNDATION DESIGN TO MINIMISE
ENVIRONMANTAL IMPACT

• ENVIRONMENTAL IMPACTS OF TL FOUNDATION:


• Huge consumption of construction material
• Large use of energy,
• Large use water and
• Generates Dust Pollution/Transport pollution

KEC International Limited 32


STRATAGY TO MINIMISE ENVIRONMANTAL IMPACT

Proper Use of Natural Resource:


 Lean Design : is the best method which require minimum
resource
 Innovative design to avoid Pollution
 Use of recycled/sustainability sourced product like crusher dust
 Water management by use of admixtures.
Improved Energy Efficiency
 Reduce energy consumption
 Use of Local supplies and materials
Avoiding pollution :
 Preventing dust by good site and depot management;

KEC International Limited 33


LEAN DESIGN
Minimization of Qty of Construction Material
Leading to saving Energy and Transport cost:
• Innovation in Foundation shapes:
• Introduction of New Foundation Types:
Wet Paddy/ Dry WBC etc.
• Introduction of intermediate angle foundation
• Innovation in Design Technique:
– Curtailment
– Stub as Reinforcement

KEC International Limited 34


ENVIRONMENTAL FRIENDLY DESIGNS

• Precast Foundation
• Grillage Foundation
• Auger Foundation

KEC International Limited 35


Pre – Cast Foundations

• Preferred where the period of


construction is limited.

• Dimensions of the foundations


are governed by the uplift
capacity of the cranes.

• Hooks are provided for lifting.

KEC International Limited 36


Grillage Foundation

Used in firm soil , where


concreting is costly.

It is a factory made
foundation.

KEC International Limited 37


AUGUR Foundation

KEC International Limited 38


AGENDA

Tower Designs being Deployed


to optimize Right of
way Requirement
Developments in foundations
to Reduce Environmental Impact.
Major Challenges &
Considerations in design
of Tower and structures.
MAJOR CHALLENGES IN DESIGN OF
TOWERS AND STRUCTURES
Market Demand :-

• Competition in Transmission Line Tender has


increased Many fold. Contractors are quoting
with very minimum margin
• Speed of Execution has increased drastically.
(36 months projects are being executed in 24
months)

KEC International Limited 40


MAJOR CHALLENGES IN DESIGN OF
TOWERS AND STRUCTURES
Challenges to Design of Tower & Structures:-
Maximum Optimization of Tower weight has become an essential
requirement to Save the project from loss.
Intermediate towers apart from standard (A,B.C,D) are introduced as a
strategy to make of the project cost. So No of Tower Designs are increasing.
Client wants to execute the Project at Minimum possible time. (36 Months
projects are squeezed to 24 Months). Correspondingly, there is a drastic
reduction in design time. Thus there is need of increased speed and
accuracy of design and detailing.
Scarcity of of well experienced designer and detailer to accomplish the
above challenges in design
Availability of Test bed for testing is also a big challenge industry is
facing. This impacts project completion time and untested tower is not
acceptable to customer.

KEC International Limited 41


THANK YOU
KEC International Limited 42

You might also like