Vishakhapatnam Steel Plant, Vishakhapatnam.: Conducted at
Vishakhapatnam Steel Plant, Vishakhapatnam.: Conducted at
Vishakhapatnam Steel Plant, Vishakhapatnam.: Conducted at
REPORT
OF
SAFETY AUDIT
CONDUCTED AT
2
CONTENTS
PART – 1 GENERAL 1
1.1 Introduction 1
1.2 About the organization 1
1.3 Scope 42
1.4 Objective of Audit 42
1.5 Methodology 42
1.6 Opening Meeting 43
1.7 Study of Document 43
1.8 Closing Meeting 43
1.9 Audit Report 43
1.10 Disclaimer 44
PART – 2 EXECUTIVE SUMMARY 45
4.9 SOP 88
4.10 MOC/ New Equipment / Review System 89
4.11 Monitoring of Workplace & Stack Emission 89
4.12 Housekeeping 90
4.13 Personnel Protective Equipment 91
4.14 Work Permit System 91
4.15 Statutory warning 92
4.16 Road Safety 92
PART - 5 CHEMICAL & PROCESS SAFETY 94
5
PART – 1
GENERAL
1.1 INTRODUCTION
The safety audit was conducted by a 4-member team from 20-26th February, 2019.
Rashtriya Ispat Nigam Limited (RINL), a Navratna Public Sector Enterprise (PSE) is
the corporate entity of Visakhapatnam Steel Plant (VSP). VSP is the India’s first
shore-based integrated Steel Plant built with state-of-the-art technology and a
prime producer of long steel products in the country having extensive market in
infrastructure, construction, automobile, electrical and forging industry. With an
annual turnover of over Rs16000 crores, VSP is gearing up production to achieve
rated capacity of 7.3 Mtpa liquid steel. The plant is situated in Visakhapatnam,
Andhra Pradesh on the coast of Bay of Bengal.
The total area of the plant including township is 9219 hectares while the plant built-
up area is 2439 hectares.
There are about 17,052 regular employees and 16,229 contract workers working in
the plant in 04 shifts, one being the General shift.
VSP meets its iron ore requirements from Bailadilla mines of National Mineral
Development Corporation at Chattisgarh, Coking coal requirements through imports
and coal washeries of Coal India Limited, SMS grade limestone through imports,
quartzite requirements through purchase and boiler coal from the coal mines of
Mahanadi Coal Limited. SMS Lime Stone from Dubai, Boiler Coal from Indonesia,
Coking Coal from Australia / US, Medium Coking Coal (MCC) from Kathara /
Swang / Rajarappa / Kedla & LAM Coke from China.
Iron and steel plant has been notified as an industry with hazardous process and
specified in the first schedule of factories act 1948.There are many production
operations involving safety and health hazards which include- molten metal
handling, storage of toxic and inflammable gas and exposure to dust, fume, noise,
heat, radiation etc. Further, there are many operations in the steel plant, such as
Grinding, shot blasting, iron making, foundries and handling of corrosive
6
substances are declared as dangerous operations as per sec.87 of factories act
and state factories rules.
7
RAW MATERIAL FLOW CHART TPP Power
Steam coal
Coking coal
CHP To BF
PCI coal BF Coke CO&CCP
Sinter
RMHP
SP
Sized iron ore/ Mn Lump/ LD Slag
Quartzite lump/ PELLETS
Raw materials
Oxygen
WRM-1
MMSM
Hot Metal Liquid Steel Crude Steel
SBM
Blooms/Billets
for sale
Slag
Pig Iron WRM-2
Blast Converter Caster
Furnace
SM
8
The brief manufacturing process of steel making is given below.
Raw material handling plant (RMHP) is a unit where various raw materials are
received. RMHP is covered under QMS, EMS, EnMS and OHSAS. The raw
materials in railway wagons are tippled in wagon tipplers and then through a series
of conveyors and stacking machines, the raw materials are stacked in the assigned
beds. Imported coking coal, imported boiler coal and pulverized coal are
predominantly received from Gangavaram port limited in two streams of conveyors.
A small tonnage of raw materials is received by road. Depending on the
requirements of the consuming departments, various raw materials are sent
through a series of reclaiming machines and conveyor systems. The Iron Ore
Fines, Iron Ore Lumps, Sized Iron Ore, Limestone (BF& SMS grade), Dolomite (BF
& SMS grades), Dolo Chips, Sand, Quartzite, Manganese fines & lumps and
Fluorspar are stocked in Ore & Flux Yard and an additional storage facility for
stacking Iron ore lumps and sized Iron ore, Iron ore fines (IOSA) is also available.
The Imported Coking Coal (ICC), Medium Coking Coal (MCC) and Boiler Coal are
stocked in Coal Yard. The boiler coal is sent to Thermal power plant (TPP), the
imported coking coal and medium coking coal is processed and sent to coal
preparation plant of Coke ovens (COCCP). The Iron ore fines and crushed lump
ore (sized iron ore) Limestone (BF), Manganese Lump, Quartzite is sent to Blast
furnace (BF). BF grade lime stone, BF grade dolomite, sand, Manganese ore & iron
ore fines are sent to Sinter Plant (SP). SMS grade Lime stone and Dolomite, Dolo
chips are sent to Calcining plant (CRMP). SMS grade Dolomite, Fluorspar, Sized
Iron Ore are sent to SMS. The layout is designed in a spacious area for orderly
movement of materials. The raw material like coking coal, boiler coal received is
compacted using machinery and stored in various beds to prevent self ignition. Fire
hydrant pipeline and landing valves are provided all along the conveyor galleries.
Similarly fire hydrant connections are provided by the side of coal yard. Fire
detection and alarm systems are provided in all important areas. Emergency filling
tanks are provided at coal tipplers and coal junction house no.5. To control the
generation of dust, dust suppression (sprinkling water) and dust extraction systems
are provided at all the ore and coal tipplers and conveyors. All equipment like
tipplers, conveyors, stackers, reclaimers etc. are provided with safety devices and
interlocks. Fencing, alarm signaling systems are provided to avoid incidents related
to locos & wagons. The dust generated while sizing and at all material transfer
points during handling of raw materials is collected by aspiration systems and
cleaned in cyclones/bag filters. Water spraying system is provided in the stockyards
for dust abatement. Dry fog system is being run in at the ring granulator (RG)
building for dust suppression. Also one additional water sprinkling system is
provided in boiler coal beds.
CO & CCP: COKE OVENS & COAL CHEMICALS PLANT (CCP) can be broadly
classified under the following sections:
There are 4 coke oven batteries with 67 ovens each which receive blended coal
from coal preparation plant (CPP) where coal from the storage yard, the coking coal
is sent to foreign material removing section and iron traps to remove foreign
matters and ferromagnetic particles respectively. For averaging and proportioning
of coal, 16 bins each of 800 T capacity are provided along with continuous feeders
of 100 TPH. There are two stages of crushing. The primary crushing is carried out
by reversible hammer crushers. Then it is fed to pneumatic separation to produce
fine and coarse products. The coarse product is sent to secondary crushing in
reversible hammer crushers. The crushed and blended coal from pneumatic
separation section is conveyed to two coal towers each of 4000 T capacity. Weigh
bridges are provided under coal towers to weigh the coal charged. Coal is fed from
Coal Tower into the Charging Car which in turn is charged into the Ovens. The
primary objective of coke ovens is to produce metallurgical coke by carbonization of
coal where coal is heated in the coke ovens in the absence of air to produce coke.
CO and BF Gas are used as the fuel energy (mixed gas) for firing the ovens,
electrical energy is used for driving various electrical equipments, process steam is
used during charging of coal into coke ovens, compressed air is used for gunniting.
The coke is then pushed by a pusher car into coke bucket through a Door Extractor
cum Guide Car. During the coking process enormous amount of volatile matter/gas
(known as CO Gas) is liberated which is collected in a Gas Collecting Main. The
collected gas is then cooled with chilled water in primary gas cooler and treated in
the Coal chemical plant with Ammonical Liquor Solution, purified and distributed
throughout the plant as a fuel. Automatic valves for gas pressure control in gas
collecting mains are mounted on the cross over pipe line on the pusher and coke
sides and on the common branch pipe. A provision is also made for hydraulic wash
out of tar sludge in the gas collecting main. The battery is of under jet compound
10
type having twin heating flues and recirculation of waste gases. CO Gas yield from
Batteries is 330 NM3/T of Coal with CV of 4250 Kcal/Nm3. The metallurgical coke
is cooled in Coke dry cooling plant (CDCP), where the coke from Coke Ovens is
pushed into the bucket placed on the coke car and transported by electric loco to
the coke dry cooling plant. A hoist lifts the bucket to the chamber top. The bucket is
then placed above the charging hopper and the coke is charged into the cooling
chamber. The upper part of the chamber serves as a collecting chamber into which
the red-hot coke is charged and resides there about two hours. The lower part
serves as a chamber where the cooling process is taking place. Cooling of coke is
done with circulating (N2) gases. The gas is circulated by smoke fan and flows
upwards to counter current to the coke flow and is heated on its way. The hot
circulating gas from top of the chamber enters the ring channel from where it is sent
to dust catching bunker to waste heat boiler then through cyclones. It is further
recycled into the cooling chamber. The waste heat from circulating nitrogen is
recovered to produce SH steam (39 ata) and used in two Back pressure type steam
turbine station for generation of 2X7.5 MW power and simultaneous generation of
process steam extracted from the low pressure outlet of BPTG is used in Coal
Chemical Plants. Back pressure steam generated at BPTG is further used in
Chilled water plant -1, which operates on the principle of vapor absorption system,
for production of chilled water. From the cooling chamber, cooled coke (1.7 T) is
discharged continuously onto the conveyor to Coke sorting plant (CSP).
At the Coke Sorting Plant coke from the coke dry cooling plant coke is discharged
into de-dusting units by conveyors. De-dusting units are provided with equalising
bunkers and belt feeders to compensate for irregularity of coke discharge from dry
cooling plant. From the de-dusting unit coke is conveyed to crushing section. It is
first separated into +70mm and -70mm fractions. The +70 mm fraction is fed to two
roller toothed crusher. The crushed product along with -70 mm fraction is conveyed
to screening plant where 20 to 70 mm and 0 to 20 mm fractions are separated and
20 to 70 mm coke is conveyed to blast furnaces for use as fuel and reducing agent.
Bunkers of 600 T capacities are also provided for loading into wagons/lorries.
Coal Chemical plant’s (CCP) the coke oven gas released from coke oven batteries
during carbonization of coal is processed in the coal chemical plant. The primary
object is to clean coke oven gas released from coke oven batteries and send it
back for using it as fuel in batteries and for other consumers. The cleaning of gas is
done in recovery unit which is one of the primary units of coal chemicals plant. The
CO gas leaves coke oven chambers at a temperature of 800 deg. C and goes to
the gas collecting main where it is cooled to 80 deg. C by spraying Ammonical
Liquor. In this process, the major part of the tar is condensed and the particulate
matter settles as sludge. Tar and sludge is separated and the flushing liquor from
the separators goes along with sludge and tar to mechanized decanters of the Tar
Distillation Plant. Due to the difference in densities, the flushing liquor clarified from
tar and sludge flows out from top continuously by gravity into flushing liquor
collecting tanks. From these tanks flushing liquor is pumped to the CO Battery gas
collecting mains for spraying again. The tar settled down in the decanters flows
continuously through telescopic pipe to tar collecting tank. From tar decanters the
tar free sludge and water flows by gravity through the telescopic pipe to collecting
tank from where it is sent to startup tank in tar distillation section. Then the tar is
pumped to first stage of pipe still furnace along with 8% soda solution to neutralize
the tar.
Tar is heated to about 130 deg C in the convection zone of the furnace and fed to
first stage evaporator, where water and portion of light oil present in tar are
evaporated. The water and light oil vapors are condensed and sent to a separator
and further to separate tanks for storage. The vapor mixture from the top of the
second stage evaporation is fed to the fractionating column. Super heated steam is
supplied at the bottom of the fractionating column. Anthracine (II) fraction is drawn
off as the bottom product from the fractionating column through a level controller.
The next fraction is wash oil drawn between 12th and 20th trays which is cooled
and routed to storage tank. The next fraction is naphthalene oil drawn between
24th and 30th trays and it is cooled and sent to storage tank. The next product is
phenol fraction drawn from 44th and 48th trays which is cooled and sent to a
storage tank. The vapors from the fractionating column top are condensed. These
vapors are light oil and phenolic water and in the separator light oil and phenolic
water are separated and sent to respective storage tanks. Light oil is pumped as
reflux to the top of the fractionating column to control the top temperature. Pitch
12
from second stage evaporator is received in over head tanks and taken into still
reactors. Softening point of pitch is increased by giving compressed air in the
bubbler of still reactor. Air flow is controlled to control the temp of the pitch. The
reaction between pitch and air is exothermic. Oil fractions present in pitch are
carried away with air and are condensed in vapor washer. Hard pitch from still
reactor is drained to horizontal hard pitch tanks which is pumped to over head tanks
and loaded in tankers. Naphthalene fraction is received in an over head tank of
NAFC section from Tar distillation plant. Naphthalene is fed into a drum crystallizer
bath by gravity. The drum is cooled by spray water. Layer of Naphthalene formed
on the ribbed surface of the drum is cut off by knives and transported by a screw
conveyor to mixer of hydraulic press, through a chute. The Naphthalene generated
in the crystallization of pressed oil is pumped to the over head tank and fed to the
pressed oil mixer directly. The Naphthalene flakes and molten Naphthalene are
kept homogeneous in the mixer and charged into the filter of hydraulic press. The
hot pressed Naphthalene cake of 20-40 kgs weight goes to the crushing and
bagging section where it is crushed by jaw crusher and bagged in 50 kg. bags.
During pressing operation Naphthalene oil is squeezed out and goes to pressed oil
tank. The pressed oil containing about 60-70 % Naphthalene is pumped to the over
head tank and from there it is charged into scraper crystallizer. Anthracine -I
fraction is pumped to over head tank in NAFC section. From the over head tank it is
charged into scrapper crystallizer. The crystallized mass after atmospheric cooling
upto 55oC is cooled to 35oC by external water and drained to a mixer. The crystal
slurry is centrifuged. The oil is separated from crystals and goes to a collecting
tank. The crystals fall on to a conveyor which take them to storage bunker. Crystals
are bagged and dispatched. The centrifuged oil is pumped to pitch cooling and
loading area for making tar. The CO gas is then cooled to 35 deg. C in PGC and
the water vapors, the remaining tar and Naphthalene are condensed. Drops of Tar
fog left in the gas after PGC are separated in ESP and collected in the seal pots
from where it is transferred to gas condensate tank. Then this purified and cooled
gas is supplied by exhausters to Ammonium Sulphate Plant at 50 deg.C and 3000
mm W.C Ammonia is recovered in the form of ammonium sulphate in the
AMMONIUM SULPHATE PLANT (A S P) where the CO gas after the exhauster
enters the saturator where ammonia is almost completely absorbed by sulphuric
acid in the form of Ammonium Sulphate according to the following exothermic
Reaction:
Crystals of Ammonium Sulphate from the saturator is taken out by centrifugal pump
and sent to crystal receiving tank. The mother liquor is freed from Sulphate crystals
and sent back into saturator. Ammonium Sulphate crystals from crystal receiving
tank are sent to centrifuge for separation of mother liquor while Sulpahte crystals
are sent to drier and the dried Sulphate is sent to storage.
The CO gas then enters the final gas cooler at 55 deg C. Naphthalene present in
CO-gas is scrubbed by water and separated tar is taken out and stored in tanks
and sent to Tar Distillation Plant for processing. The coke oven gas is at 35-42 deg
C and 600 mm WC after the final gas cooler/pre cooler flows to two Benzol
scrubbers (60,000 Nm3/hour capacities) of Benzol Recovery Plant where Benzol is
scrubbed using “Solar” oil as scrubbing medium. Benzol hydrocarbon is scrubbed
with the circulating
13
debenzolised oil flowing in a counter current direction of the gas flow. The temp. of
the oil is maintained at 2 to 3 deg C higher than the CO gas to avoid condensation
of water vapor in the gas. The benzolised oil is pumped to Benzol Distillation plant.
In Benzol distillation Plant, the benzolised oil is preheated in oil dephlegmator with
hot Benzol hydrocarbons from Benzolised oil stripping column. The benzolized oil is
finally heated to 180 deg C in steam preheater before it enters the stripping column
(BT/107). Direct steam is supplied to the Benzol striping column to strip the
Benzolvapors from the benzolised oil. The hot debenzolised oil from the bottom of
the stripping column passes through heat exchangers and finally through a water
cooler and enters an oil decanter (BT/137). A small quantity of makeup water is
sprayed in oil decanter to facilitate sludge removal from oil. The debenzolised oil is
circulated back to Benzol recovery plant. Sludge is separated out in the form of
emulsion and transferred to emulsion breaker (BT/139). Mixture of Benzolvapors
and steam from the top of the stripping column (BT/107) enters the dephlegmators
(BT.101 & 102) where vapors are partially condensed. The phlegma condensed in
the dephlegmators consists of high boiling hydrocarbons along with water. Phlegma
is separated from water and the water sent to water settling tank (BT/130) for
separation of entrained oil.
Naphthalene is also absorbed along with Benzol from CO gas in Benzol scrubbers.
Absorbed Naphthalene is removed in Naphthalene stripper. A part of the Phlegma
is fed to stripping column (BT/107) as reflux and the rest is fed to Naphthalene
stripper. Both direct and indirect steam is used in Naphthalene column for better
control of process. Steam along with light boiling fraction from the top of the
Naphthalene column enters the stripping column (BT/107) near its top.
Naphthalene rich oil from the bottom (BT/111) is routed to collecting tank (BT/128).
The crude Benzol is fractionated in to two fractions i.e., Crude Benzol-I (Boiling up
to 150 deg C) and crude Benzol-II (boiling above 150 deg. C) in a single steam.
The mixture of Benzol and water vapor from dephlegmators (BT-112) is fed to
rectification column for crude Benzol I (BT-112). Heat for fractionation is supplied
by reboiler (BT/114). The vapors of crude Benzol-I and water from the top of the
C.B.I column enter the condenser (BT/116). After separation of water, crude Benzol
- I overflows to reflux tank (BT-124). A part of crude Benzol I is pumped as reflux to
C.B.I. Column (BT/112) and the balance to crude Benzol-I tank (BT/125). Heavy
Benzol leaving as bottoms from C.B-I column (BT/112) enters crude Benzol II
column (BT/113). The vapors from the top of the column (BT/113) returns to crude
Benzol-I column (BT/112). Crude Benzol-II leaving from the bottom of crude Benzol
II column (BT/113) is cooled and sent to collecting tank (BT/126).
The crude benzol-1 from crude Benzol-I tank (BT/125) is pumped to crude benzol
tank of crude finished product storage area from where it is pumped to intermediate
storage tanks of Hydro-refining section. In Hydro refining crude benzol is purified by
using pure hydrogen to produce BTXS. This BTXS is distilled in pressure distillation
column where BT and XS are separated. The BT fraction is processed in Extractive
distillation column by using a solvent NFM to separate pure aromatics and non-
aromatics. The NFM absorbs non aromatics from BT fraction. The NFM solvent is
recovered from nonaromatics in solvent recovery column and non-aromatics
product is pumped to storage tank at CFPS. The pure aromatics with NFM are
processed in stripper column where NFM and pure aromatics are separated. The
NFM separated is recirculated to extractive distillation column and pure aromatics
are sent to B/T separation column where Benzene and Toluene are produced. The
14
XS separated in pressure distillation is charged into batch still where light solvent oil
is produced by giving indirect steam. The LSO is transferred to CFPS tanks by
gravity. All the finished products like Benzene, Toluene, Light solvent oil, Heavy
crude benzol, High boiling fraction are stored in CFPS tanks. The cleaned gasses
without pollutants are collected from various places of coal chemical plant and
discharged into the atmosphere. Stainless steel saturators are installed for better
results. The ammonia liquor and water from the coke ovens and coke chemicals
plant which is contaminated with chemicals like phenol, cyanides, etc. It is collected
and treated in two stages, the “mechanical biological and chemical treatment plant”.
The treated effluent is treated further in the effluent treatment plant. The hazardous
wastes generated in the coal chemicals plant are mixed with coal and charged into
the coke oven batteries. All the liquid and gas products of coal chemicals plant are
fire hazardous in nature.
In the design of layout of coal chemicals plant care has been taken to maintain
sufficient distance between the three sections of CCP, namely recovery, tar plant
and benzol plant. This has been done to minimize the effect on other units in case
any-On site emergency situation develops in any unit. The following special OH&S
facilities are provided in coke ovens in addition to the general safety provisions:
- Automatic opening of gas bleeder valves in case of high pressure in gas collecting
mains of battery.
- Auto stopping of heating in batteries in case of low inlet gas pressure
- The coke oven and mixed gas line network has been provided with seal pots for
condensate removal
- Steam and nitrogen purging facility is available in all gas lines
- Safety flaps are provided in circulation gas track in CDCP
A fire station and a first aid station are provided in coal chemicals plant zone. Bund
wall is built around the storage tanks. For CO gas line net work isolation valves are
provided to isolate CO gas to any section. Provision of steam and nitrogen injection
to CO gas lines is available. In reagent storage where sulphuric acid is unloaded
and stored, the storage tank and the area are lined with acid proof bricks. The
pipelines and pumps handling acid is made of stainless steel. In Ammonium
Sulphate unit the saturator handling 5% sulphuric acid are made up of stainless
steel. Also the whole unit area flooring is made of acid proof bricks. A separate fire
fighting pump house with static water tank exists for fire fighting in tar plant. All
overhead pitch tanks and reactor have been provided with nitrogen line. Steam
purging facility is available to all tanks and equipments. For furnace, steaming
facility is available to smoother the fire which can occur in case of pipeline leak. For
NAFC go down, smoke detector and water sprinkler system is available. A
dedicated fire fighting pump house with static water tank is available for water shell
spray to all tanks and also for foam injection to all vertical storage tanks in CFPS.
Benzene monitor is fixed at sensitive location to detect the benzene leak. If in
ambient air, benzene content is greater than 20 PPM, siren will blow to alert the
employees. In HRED, in case of leak in HP circuit, facility is available to de-
pressurize line quickly and feed nitrogen into the circuit. Nitrogen purging facility is
available to all equipment of HRED. In Benzol distillation plant, facility is available to
empty oil of any equipment to emptying tank in case of emergency.
15
Sinter Plants covered under QMS, EMS, EnMS and OHSAS, are units where sinter
is produced from Iron Ore fines, Lime stone, Coke, Dolomite and Sand from RMHP
and Metallurgical Wastes such as the fine iron dust, metallurgical wastes from the
water treatment plants in blast furnaces, steel melting shop & rolling mills, flue dust,
mill scales, coke breeze, coke dust, lime dust, Stock House Dust, Cast House Dust,
Gas torch sludge, CC Scales, BF Gas Cleaning Sludge, LD Gas Cleaning Sludge
etc., etc. collected from various units in the plant are re-used as feed for sinter
making. These raw materials are received in Raw Material Bins, raw materials
preparation plant for Base Mix preparation: Base mix is a mix of above materials in
required proportion to meet the Blast Furnace quality requirement. After
proportioning, the raw materials are mixed in the primary mixing drum and stored in
base mix yard. Secondary Mixing, Moistening and Palletizing of sinter mix is carried
out in the palletizing drum to ensure uniform mix of all the burden components.
Then the Sinter Mix is charged on the grating above hearth layer of 60 to 80mm
thick .The Sinter mix with coke breeze as solid fuel, is then ignited in the furnace
using Mixed Gas. The temperature maintained is in the range of 1150o-1250oC.
Sintering is done on the grating of the Sinter machine due to air suction in the
downward direction and high temperature created by burning carbon of the sinter
mix layers. Hot sinter discharged from sintering machine at 700oC is crushed to
150mm size in a spiked single roll crusher. Unsintered grains are liberated as sinter
returns. After crushing, the sinter is screened. The +8mm hot sinter is cooled on
straight line circular sinter coolers by forcing atmospheric air through sinter bed.
This is further conveyed to Blast Furnace after eliminating -5mm sinter fraction.
Electricity is used for operating exhausters for maintaining better vacuum and
blowers fan for cooling of sinter. Further, Electricity is also used in for de-dusting,
ACP fans, ESPs etc for dust evacuation and reducing dust emissions. In addition to
the above, various types of carbonaceous dust is recycled in to sinter machine.
Sinter plant is also using lime stone and dolomite as fluxing agents to maintain
basicity. Sinter plant recycles the LD slag generated at steel melt shop to replace
lime stone. Within the sinter plant, there are a vast network of conveyor systems,
equipments, stacking and reclaiming machines and two sinter machines (each with
312 sqm grate area / 276 sqm of sintering area) in SP-1 and one Sinter
machine(408m2) in SP-2. The large amount of gases containing particulate matter
evolved during the sintering process are collected and cleaned in electrostatic
precipitators to reduce the dust content from 3000 mg/Ncum to below 50 mg/Ncum
(115 mg/Ncum for SP-1) before letting out to the atmosphere through 120 m tall
chimney. The dusty air from various other material transfer points is also collected
and cleaned in wet scrubbers and the sludge processed through SDPM (Slime
Dewatering Pump House) is reused in SP-1.
Blast furnace (BF): There are three blast furnaces. Each blast furnace (each with
3800 cum useful volume) is capable of producing 2.5 MT of hot metal (liquid iron)
per year. Blast furnaces are covered under QMS, EMS, EnMS and OHSAS. The
burden (raw materials) like-blast furnace coke from CSP, sinter from SP, sized iron
ore, limestone, LD-slag and at times additives (Mn ore & quartzite) from RMHP are
received through conveyor system in the stock houses through a junction house.
These are screened before stock house to remove fines. Each material is fed
simultaneously by two hopper scales according to the predetermined furnace
charging programme. Automatic system is provided for batching, weighing and
feeding of the burden to the furnace top. Paulwurth bell-less top system is installed
16
for furnace charging from the top through a conveyor. It consists of two bunkers of
65 M3 capacities each, charging/moving hopper and rotating trough. Semi -cleaned
BF gas and Nitrogen are used for pressure equalization in charging bunkers.
Nitrogen is also used for cooling rotating trough drive and for blowing off stock twin
gates and sealing valves of charging arrangement. One mechanical gauge rod and
two ultrasonic probes are provided for measuring stock level. There are four hot
blast stoves for BF-1 and BF - 2 and three stoves for BF-3. These are heated by a
mixture of BF & CO gas at a pressure of 600 mm W.C. Combustion air is supplied
by three fans of 120,000 M3/Hr. The cold blast received from the thermal power
plant turbo blowers is heated in the hot blast stoves to 12500C in BF-3 and 9500C
in BF-1 before it is sent to the tuyeres via hot blast mains. It is taken out from top as
Hot Blast and sent to BF for melting the burden stock. Hot air is blown through
tuyeres into the blast furnaces. The blast furnaces produce normally basic grade
pig iron suitable for steel making. Each blast furnace has four tap holes and a
circular cast house for BF-1 and BF-2, flat cast house for BF-3. Hot metal and liquid
slag are tapped through the tap holes. Hot metal is separated from liquid slag at the
cast house. The liquid hot metal is collected in the hot metal ladles by rocking
runners in cast house. Hot metal ladle cars are moved by a car pusher. There are
four railway tracks for hot metal transportation to SMS and PCM. Slag is discharged
from the furnace 16 to 20 times a day, duration of each discharge being 60
minutes. The molten slag produced by the furnaces is fed to cast house slag
granulation plant (SGP), through the slag runners, for granulation by water jets.
Granulated slag is conveyed to slag storage yard from where it is dispatched. Four
double strand pig casting machines of 1700TPD capacity are installed to treat off-
grade metal and metal diverted due to off-stoppage in SMS. The machine can
handle one furnace production. Each PCM is served by a 75T overhead trolley to
tilt the 140 T hot metal ladle. Refractory masses required in cast house viz. Runner
mass, Mud gun mass, Tap hole frame mass are prepared in Masses and
Compound Shop. During Blast Furnace operation, enormous amount of gas is
generated and this gas coming out from Blast Furnace at a pressure of 2.5 kg/cm2
and temperature of 170oC, recovered from the furnace top, is first cleaned in the
dust catchers which removes major portion of dust particles and thereafter in the
scrubbers of the Gas Cleaning Plant, where water is sprayed to further clean the
gas from fine Dust particles. From scrubber, the gas is passed to Cyclone Mist
Eliminator through an Adjustable Venturi. While passing through the Venturi, the
gas pressure is reduced and the differential pressure across the Venturi is always
maintained. Any mist present in the gas is separated in the Cyclone Mist Eliminator.
Further, it is sent to Gas Expansion Turbine Station (GETS) which generates 12
MW Power. The pressure of gas before GETS is 1.75 KSCG and after GETS is
0.15 KSCG. GETS generates electric power utilizing potential energy (pressure
energy) of the compressed BF gas. Part of BF gas generated is also reused in the
BF stoves. The GETS operates for 8000 hours/year with annual generation of
123.8 to 184.6 x 106 KWH. The dust level in the gas is thus reduced to 4 mg/N cum
and is then sent to the BF Gas Line Network for use as fuel by various consumers
in the plant as fuel. The scrubbed water contaminated with dust is sent to water
treatment plants TP-1 and TP-2 where the dust particles are separated in the
clarifiers and clean water is re-circulated in the gas cleaning plants. The slurry from
bottom of clarifiers is sent to a settling pond. The settled sludge, after sun-drying, is
sent to sinter plant as feed material. The exhaust fumes generated at the runners
and while tapping hot metal into the open hot metal ladles/ torpedo ladles are
exhausted and cleaned in electrostatic precipitators before being vented to the
17
atmosphere through 100 m tall chimneys. The dust laden air generated at all the
transfer points of blast furnace burden handling systems is aspirated, cleaned in
electrostatic precipitators and the clean air is vented to the atmosphere through 80
m tall chimneys. The dust content at the outlet of above electrostatic precipitators is
limited to 50 mg/Ncum. BF gas flare stacks are provided to flare the excess gas.
These Flare Stacks are the heart of the Gas Line Network (GLN) throughout the
plant. It is these flare stacks which maintain the network pressure at the desired
value. If the pressure anywhere in the GLN increases, the gas is led to atmosphere
through these flare stacks by means of automatic control systems. At the top of the
stack the let out gases are burnt completely by means of pilot burners. The hot
metal is distributed to the steel melting shop and to the pig casting machine (PCM).
Pig iron, produced in the pig casting machine is stored in pig storage yard from
where it is dispatched to different customers. The following special OH&S features
are provided in BF in addition to the general OH&S provisions: The furnaces are
equipped with bleeders and relief valves to take care of excess pressure condition.
The stoves are operated in a sequence with safety interlocks. Auto isolation
schemes are provided in case of power failure, low pressure in gas line etc.
The tap hole drilling machines, mud guns, pusher cars and rocking runners are
provided for safe handling of liquid metal and slag. The furnace is designed to
prevent gas leaking while charging of materials. Emergency water supply tank is
provided for the cooling of the furnace in case of power failure. The feeding
conveyors to blast furnace area are provided with material tracking system. Failure
of nitrogen, hydraulic system for hot blast control valve etc. are monitored with
alarms in the control room. The slag granulation plant is provided with safety
controls and monitoring of critical items like flooding of pump house, drop in
pressure of compressed air, pump tripping, interlocks for dehydrator movement and
slag vibrator for dumping. All equipment like conveyors, mud guns, drilling
machines, cranes, pusher cars, combustion air fans, furnace top charging system
etc. are provided with various safety interlocks and devices.
The CRMP comprises of two units i) Calcining plant, where it calcines limestone
and dolomite into flux which is required mainly for steel making and ii) brick plant,
where it undertakes manufacturing of refractory bricks required for lining of
converters and ladles in steel melting shop.
Calcining Plant of (CRMP), covered under QMS, EMS, EnMS and OHSAS,
receives limestone and flux grade dolomite from RMHP through a series of
conveyor belts. These raw materials are processed in rotary kilns at 1200 O C -
1300O C by burning coal tar as fuel (CTF)/ pitch creosote mixture fuel (PCM). The
resultant product i.e. flux is cooled, screened and stored in the bunkers, and
dispatched to SMS as and when required. Electricity is consumed for driving of
rotating equipment like ID fans, Primary Air fan, Secondary Air fan, pumps etc.
Each rotary kiln is installed with pre-heater where in outgoing flue gases sensible
heat is used for preheating of raw material. Process steam is used for atomization
of Coal Tar fuel and compressed air is also used for general housekeeping
purposes. The flue gasses from each rotary kiln is cleaned in a cyclone and then
finally in a pulse jet-type bag house to a dust content of below 50 mg/Ncum before
venting to the atmosphere through 60 m tall chimneys.
18
Brick plant of CRMP: Brick plant manufactures bricks, bottom jointing mass and
back filling mass for lining of the converters and ladles of Steel Melting Shop. The
brick plant receives sea water magnesia (SWM) of 0-25 mm size from the refractory
stores in polythene bags. The SWM is crushed, screened and the different fractions
of SWM obtained are stored in classified bunkers. Pitch is received in tankers from
coal chemical plant (CCP) and stored in storage tanks. Predetermined quantities of
different size fractions of SWM and pitch are taken and mixed in the mixer, and the
mix is charged into the press hopper and pressed into the required shape of bricks
as per the settings. Then the bricks are tempered in the tempering kiln after which
they are packed and sent to SMS as and when required. The dust generated at the
material processing and handling areas in flux storage building, kiln building and
brick plant is collected and cleaned in various bag filters and clean air is let out into
the atmosphere. The lime fines generated are partly converted into briquettes for
charging into converters in steel melting shop and the balance is transported to
sinter plant as well as marketed to outside parties.
The following special OH&S features are provided in CRMP department in addition
to the general provisions:
Bund wall around the individual tanks are provided like in CTF/PCM pump house of
calcining plant and pitch storage tanks in brick plant pump house. The tanks are
provided with interlocks for high level. All the belt conveyors are provided with
safety interlocks. In CTF/PCM pump house, all lights and motors are flame proof.
Fuel safety shut off valve provided in firing system of flux kiln burner is provided
with safety interlocks. The vibro tube mill area is enclosed within sound proof walls.
All equipment in calcining plant and brick plant are provided with safety interlocks.
Steel melting shop-1 (SMS-1) is covered under QMS, OHSAS, EMS, and EnMS.
The liquid metal/ Hot Metal from the blast furnace is taken to SMS in ladles by
locos. It is poured into two hot metal mixers (1300 T cap.) for intermediate storage.
Hot metal from mixer or torpedo ladles is charged, after adding scrap additives
received from scrap salvage department (SSD), into LD converter to make liquid
steel in two 133 cum & one 150cum capacity top blown oxygen LD converters.
Alloying elements from the metal such as carbon, Silicon, Manganese and
Phosphorus are added in proper proportion to produce required grades of steel.
Primarily the carbon content of hot metal is reduced by blowing oxygen called
lancing operation. The total cycle time for one heat is 50 mins yielding 140 to 150 T
of liquid steel. LD converters are equipped with suppressed combustion system to
recover the converter LD gas which is used as fuel in the plant, by blowing Oxygen
(from Air separation plant) from top lance and simultaneously Nitrogen or Argon are
introduced from bottom through tuyers for better slag formation and better process
control. Calcined Lime & Dolomite from CRMP are added as flux for facilitating slag
formation and ensuring the slag basicity. The gases, CO & CO2 formed and are
captured through gas cleaning system. Refining of molten pig iron in LD Converters
releases gas rich in carbon monoxide and laden with significant amount of dust.
The hot gases are collected above the converter mouth by a skirt, cooled through a
hood and tack and cleaned in scrubbing installation in Gas Cleaning Plant. This
cleaned gas is either flared in a flare stack or stored in a gas holder for further
utilization by means of a Change over Valve (COV) installed at ID fan discharge
which ensures the gas switching either to flare stack or to the gas recovery. Gas is
19
routed to holder when CO is more than 30% and O2 is less than 2% and is routed
to flare stack when the above conditions are not satisfied. The recovered gas is
stored in the holder at a pressure of 180 to 250 mm WC. The capacity of the holder
is 80000 m3. The stored gas is further cleaned in an Electrostatic Precipitator
(ESP) and boosted to a pressure of 1500 mm WC and injected into the BF Gas
Main going towards Rolling Mills. The liquid steel at the desired temperature is
tapped from converter into steel ladles and taken to Argon Rinsing Station, where
IR-UT (injection refining – up temperature) & ladle furnace facilities exist, for
equalizing the temperature, averaging chemical composition and for lowering steel
temperature, if necessary, by adding small size scrap. The slag retained
inConverter is splashed by introducing N2 from top with O2 lance to coat the
Converter lining. The treatment time is about 3 to 6 min. There are three argon
rinsing stations having facilities for PROCESSES of lance, charging scrap,
measuring temperature, charging heat insulating mixture and lance assembly and
preparation. Liquid steel after rinsing with argon is cast into blooms of nominal size
(250mm x 320mm and 250mm x 250 mm) in six numbers, 4 strands radial type with
base radius of 12m, continuous casting machines. One of the machines namely
CCM#2 is equipped with Automatic mould level controller and Electromagnetic
Stirrer for production of high quality blooms. The tundish capacity is 25T. Cast
blooms are cut by flame cutting machines to about 5.8 to 6.1m(M)/ 6.0 to 6.4m(L)
length and short length bloom pieces are moved to cooling bed. After cooling to
500oC, they are transferred to racks. This is then lifted by 16 T magnet crane and
piled for further cooling and stored in bloom storage yard. During process of steel
making, ladles are used for transfer of hot metal, Coke oven gas is used for ladle
heating and tundish drying, electricity is consumed at Induced Draft fans for
evacuating waste gases from converter, Central ventilation fan systems, IRUT
furnaces. Oxygen is blown in to the converter and Nitrogen is used for slag
splashing of converter bottom. Compressed air is used for general housekeeping
purposes. The converter gas produced during steel making is collected, cooled and
then cleaned in wet gas cleaning system consisting of a kinpactor (adjustable throat
venturi) and a quencher. The gas is cleaned to 100 mg/Ncum of dust and is either
burnt at the outlet of 82 m tall flare stacks or is collected in the gas holder
depending on the carbon monoxide and oxygen content in the gas. The gas is
further cleaned in electrostatic precipitators to a dust content of maximum 10
mg/Ncum and is then used as fuel in the plant. The dust-laden fumes generated
while charging the hot metal into mixers or while pouring hot metal from the mixers
into hot metal ladles are exhausted and cleaned in electrostatic precipitator of the
central ventilation system and discharged into atmosphere through 80 m tall
chimney. The dust-leden air aspirated from material transfer points and screens
etc. of the bulk material charging system is also cleaned in the electrostatic
precipitator of the central ventilation system. The dust content at the outlet of the
chimney is kept below 50 mg/Ncum. The water contaminated with dust from the
converter gas cleaning plants is treated in clarifiers of treatment plant (TP-3) and
recycled for cooling and cleaning the converter gas. The water contaminated with
scale & oil from continuous casting machines is treated in a treatment plant (TP-4)
and recycled. The collected sludge from bottom of clarifiers at TP-3 and TP-4 is
recovered and used as feed material in sinter plant. The oil collected from scale pit
of pump house no.15 is processed in oil reclamation unit. The collected scale from
scale pit is transported by wagons to sinter plant for being used as feed material.
The steam generated in the secondary cooling chambers of continuous casting
machines is vented to atmosphere by exhaust fans. The slag and debris generated
20
in steel melting shop are transported to the slag and debris dump located outside
the plant boundary after recovery of steel scrap from the slag. The following are few
important safety provisions made in steel melting shop (in addition to the general
safety provisions). The LD converters and the continuous casting machines are
provided with safety interlocks. The oxygen lances are lifted automatically in
emergency with the help of battery/pneumatic lifting. The gas cleaning plant is
provided with process safety interlocks. Explosion in the system is prevented by
suitable process instrumentation. Overhead water tank is provided to supply water
to the continuous casting machines in the case of power failure. Special fire fighting
systems like CO2 flooding systems, Inergen flooding systems and fire fighting
pump house are provided. The slide gate of steel ladle closes automatically in case
of power failure. The magnet cranes of bloom storage yard are provided with
fingers to prevent falling of blooms in the event of power failure. The hot metal and
liquid steel handling cranes are provided with two sets of brakes in the main hoists.
Steel melting shop-2(SMS-2) is presently covered under QMS. The liquid metal/
Hot Metal from the blast furnace is taken to SMS in torpedo ladles by locos. Hot
metal from torpedo ladles is poured into hot metal ladles for charging, after adding
scrap additives received from scrap salvage department (SSD),into LD converter to
make liquid steel in two 150 cum capacity top blown oxygen LD converters.
Impurities from the metal such as carbon, Silicon, Manganese and Phosphorus are
removed & then alloying elements added in proper proportion to produce required
grades of steel. Primarily the carbon content of hot metal is reduced by blowing
oxygen called lancing operation. The total cycle time for one heat is 50 mins
yielding 150 T of liquid steel. LD converters are equipped with suppressed
combustion system to recover the converter LD gas which is used as fuel in the
plant, by blowing Oxygen (from Air separation plant) from top lance and
simultaneously Nitrogen or Argon are introduced from bottom through tuyers for
better slag formation and better process control. Calcined Limestone & Dolomite
from CRMP are added as flux for facilitating slag formation and ensuring the slag
basicity. The gases, CO & CO2 formed and are captured through gas cleaning
system. Refining of molten pig iron in LD Converters releases gas rich in carbon
monoxide and laden with significant amount of dust. The hot gases are collected
above the converter mouth by a skirt, cooled through a hood and stack and cleaned
in scrubbing installation in Gas Cleaning Plant. This cleaned gas is either flared in a
flare stack or stored in a gas holder for further utilization by means of a Change
over Valve (COV) installed at ID fan discharge which ensures the gas switching
either to flare stack or to the gas recovery. Gas is routed to holder when CO is
more than 30% and O2 is less than 2% and is routed to flare stack when the above
conditions are not satisfied. The recovered gas is stored in the holder at a pressure
of 180 to 250 mm WC. The capacity of the holder is 80000 m3. The stored gas is
further cleaned in an Electrostatic Precipitator (ESP) and boosted to a pressure of
1500 mm WC and injected into the BF Gas Main going towards Rolling Mills. The
liquid steel at the desired temperature is tapped from converter into steel ladles and
taken to On line Rinsing Station for homogenization, sample & temperature
measurement. Then the liquid steel is sent to ladle furnaces for temperature &
chemical analysis adjustment. The slag retained in Converter is splashed by
introducing N2 from top with O2 lance to coat the Converter lining. The treatment
time is about 3 to 6 min. There are three one on line Rinsing Station for each
Converter. There are two Ladle Furnaces for temp. & Chemical analysis adjustment
for the liquid steel. There is one RH Degasser for removal of hydrogen if required.
21
Liquid steel after rinsing with argon is cast into billetsooms of nominal size (150mm
x 150mm and 200mm x 200 mm) in two numbers, 6 strands radial type with base
radius of 10m, continuous casting machines. One of the machines namely CCM#1
is equipped facility to cast either 150 mmX150 mm square or rounds of sizes 220
mm, 280 mm & 350 mm size. All the caster are equipped with Automatic mould
level controller and Electromagnetic Stirrer for production of high quality billets. The
tundish capacity is 35T. Cast billets are cut by flame cutting machines to about 12
m length and moved to cooling bed. After cooling to 500oC, they are transferred to
racks. This is then lifted by 16 T magnet crane and piled for further cooling and
stored in billet storage yard.
During process of steel making, ladles are used for transfer of hot metal, Coke oven
gas is used for ladle heating and tundish drying, electricity is consumed at Induced
Draft fans for evacuating waste gases from converter, Central ventilation fan
systems, Ladle furnaces. Oxygen is blown in to the converter and Nitrogen is used
for slag splashing of converter bottom. Compressed air is used for general
housekeeping purposes. The converter gas produced during steel making is
collected, cooled and then cleaned in wet gas cleaning system consisting of a
adjustable throat venturi and a quencher. The gas is cleaned to 100 mg/Ncum of
dust and is either burnt at the outlet of 82 m tall flare stacks or is collected in the
gas holder depending on the carbon monoxide and oxygen content in the gas. The
gas is further cleaned in electrostatic precipitators to a dust content of maximum 10
mg/Ncum and is then used as fuel in the plant. The dust-laden fumes generated
while charging the hot metal into Converters, while pouring hot metal from torpedo
ladles into hot metal ladles & during tapping are exhausted and cleaned in
electrostatic precipitator of the Secondary Emission Control System and discharged
into atmosphere through 80 m tall chimney. The dust-leden air aspirated from
material transfer points and screens etc. of the bulk material charging system is
also cleaned in the bag house of MHS Dedusting system. The dust content at the
outlet of the chimney is kept below 50 mg/Ncum. The water contaminated with dust
from the converter gas cleaning plants is treated in clarifiers of and recycled for
cooling and cleaning the converter gas. The water contaminated with scale & oil
from continuous casting machines is treated in a treatment plant and recycled. The
collected sludge from bottom of clarifiers is recovered and used as feed material in
sinter plant. The collected scale from scale pit is transported by dumpers to sinter
plant for being used as feed material. The steam generated in the secondary
cooling chambers of continuous casting machines is vented to atmosphere by
exhaust fans. The slag and debris generated in steel melting shop are transported
to the slag and debris dump located outside the plant boundary after recovery of
steel scrap from the slag.
The following are few important safety provisions made in steel melting shop (in
addition to the general safety provisions).
The LD converters and the continuous casting machines are provided with safety
interlocks. The oxygen lances are lifted automatically in emergency with the help
pneumatic system. The gas cleaning plant is provided with process safety
interlocks. Explosion in the system is prevented by suitable process
instrumentation. Overhead water tank is provided to supply water to the continuous
casting machines in the case of power failure. Special fire fighting systems like CO2
flooding systems, Inergen flooding systems and fire fighting pump house are
22
provided. The slide gate of steel ladle closes automatically in case of power failure.
The hot metal and liquid steel handling cranes are provided with two sets of brakes
in the main hoists.
Light and medium merchant mill (LMMM), consists of LMMM and Special Bar Mill
(SBM), covered under QMS, EMS, EnMS and OHSAS. LMMM is at an elevation of
5m level except the charging grids and consists of a break down mill of seven
stands and a Bar mill which is a 2 strand continuous multilane mill consisting of 26
stands. It is a combined billet mill and merchant bar mill. The mill has been
envisaged to produce 18,57,000 T of billets, out of which 7,26,000 T for in line bar
mill to produce 7,10,000 T of finished bar product, 8,85,000 T for feeding to wire
rod mill and 2,49,000 T for sale. The feeding material for the mill is continuous cast
blooms of 320 x 250 mm with a nominal length of 6.3 m from SMS Continuous
Casting Dept. carried by magnet cranes for charging onto the charging grids of 150
T each. Defective blooms can be sorted out and rejected onto two take-off grids
provided along the charging roller table. Blooms from the charging grid are fed into
the charging roller table one by one and then elevated to working platform. The
cold blooms are charged into a walking beam furnace (2 nos) to heat up to rolling
temperature i.e. 1200o C. Normally one furnace is intended to feed hot blooms for
production of billets, and depositing on to cooling bed while the other furnace is
intended to feed hot blooms for onward transmission of billets to in line bar mill.
Billet Mill consumes mixed gas for reheating of blooms in reheating furnace which
is equipped with dual firing to attain rolling temperature, Once rolling temperature is
achieved, blooms are rolled into billets. The reheating furnace is walking beam type
use DM water for cooling of furnace skids and posts. During the cooling of skids
and post, the DM water is re-circulated and the furnace is equipped with
evaporative cooling system for generation of process steam. The process steam
generated can be used for driving steam turbine for running ECS pump incase of
emergency and in normal circumstances, the process steam recovered is sent to
plant process steam network. The walking beam furnace is equipped with Waste
heat recovery system for recovering sensible heat of hot flue gases and air
recuperator is installed for recovering waste energy. The bar mill reheating furnace
consumes mixed gas and is installed with waste heat recovery system. Billet mill
uses electrical energy for stands, combustion air fans and for hydraulics,
lubrication, ventilation and lighting system. Bar mill consumes electrical energy for
driving of rolling stands, running of blowers, for hydraulic, lubrication, ventilation
and lighting system. In addition to the above bar mill consumes various utilities
such as oxygen, nitrogen, steam, etc. The hot blooms are rolled into 125 x 125 mm
billets in billet mill consisting of 4 horizontal and 3 vertical stands. The billets
intended to be sent to wire rod mill or for sale, are cut in to three pieces with head
and tail cropped and off loaded on to “turn over type cooling bed”. The billets for bar
mill are cut only at head-end and at tail end with a normal length of 31.6 m. Billets
get cooled on cooling bed and are lifted by magnetic cranes for stacking in yard
and for onward supply to wire rod mill. Saleable billets are loaded onto
wagons/trailers by magnetic cranes for dispatch. The billets for bar mill are sent
through bar mill reheating furnace and transported with a speed of about 2m/sec to
the in-line two strand RH furnace via a switch arranged in front of RH furnace. The
bar mill consists of three groups, comprising an eight stand roughing train, 2x5
stand intermediate train, and 2x4 stand finishing train. The output from the finishing
23
trains is cut into the cooling bed lengths by rotary shear. The products are cut to
required length and are bundled at finishing area of bar mill for shipment. Billets
meant for wire rod mill and for sale are taken to billet storage yard through two turn
over type cooling beds. The products of bar mill are rounds, reinforcement bars.
The mill incorporates Material tracking through online system (SAP/PPC) along with
heat identification / colour coding facilitates product identification and traceability,
walking beam furnace temperature control facilitates the heating process
depending on the grade of the material, rolling process stage wise size control
facilitates finished product size control, tempcore process of controlled cooling
facilities and quality inspection facilities for the production of quality output and
branded reinforcement bars. The MOU’s with EMD, RS&RS, DNW, WMD, L&H etc;
controls the quality of Mixed gas, Rolls, Guides, power, water, lub& hydraulics etc;
respectively received as input to the mill.
The following special safety features are provided in addition to the general safety
provisions in LMMM:
All normal operations of the mill are done from control pulpits which are enclosed
and air conditioned making them free from noise, dust and heat. Concrete
barricades are provided near shift office-2, to prevent cobble material reaching the
shift office. Furnace gas lines are provided with auto shut off valves, which are
closed automatically on emergency. Auto Nitrogen purging is provided in gas line of
WBF (Walking Beam Furnace) & RHF(Roller Hearth Furnace) to avoid back firing in
the gas lines. Automatic fire fighting system (foam flooding system) is provided for
oil cellars. Battery backup for electromagnetic lifting cranes are provided to prevent
the falling of material in the case of power failures. Cobble detection schemes are
provided to initiate the chopping and closing of snap shear, to avoid spreading of
cobble material to more areas. All equipments are provided with various safety
interlocks and devices.
SBM : SBM is at an elevation of 5 m level except the charging tables and coil line
which are at 0 m level, consists of total 21 stands of which 6 are roughing stands, 6
are intermediate stands, 6 are pre-finishing stands and 3 are finishing stands. The
mill is envisaged to produce 7,50,000 T of plain rounds of size from 20 mm to 45
mm, with provision to roll 16 mm and 18 mm, both in straight and coil form. The
input material is continuous cast blooms of 150 x 150 mm of cross section and 12
m of length, 2.15 T of weight, from SMS-2 Continuous Casting Dept. carried by
magnetic cranes and placed on the charging tables of SBM at 0 m level. The
blooms are elevated to 5 m level by the elevator equipment and placed on the
charging roller tables. The defective blooms can be identified and is ejected from
charging roller tables using billet ejector arm. The blooms are charged in to
reheating furnace through the charging door by the charging rollers, which are
inside the furnace. The reheating furnace is walking beam type and uses mixed gas
for fuel and indirect water cooling system for cooling skids, charging rollers and
doors. The walking furnace is equipped with air recuperators, for waste gas heat
recovery from flue gas, which pre-heats the combustion air from combustion fans
before combustion. Inside the furnace the blooms can be heated up to the rolling
temperature of around 1200°C. The heated blooms are discharged from furnace
through the side discharging door and are send to the roughing train of the mill for
rolling process. The blooms are rolled in six roughing strands, six intermediate
stands, 6 finishing stands and 3 finishing stands. Head cut of bloom is done in
24
pendulum shear if required before entering the stand-1. There are shears installed
at entry of first intermediate stand, first pre-finishing stand and first finishing stand
for head cutting, if required, chopping in case of emergency and cobbles. The
number of intermediate and pre-finishing stands in line varies depending upon final
size requirement of the bars. Before the stock is fed into finishing stands, it is
passed through PQS cooling stretch 1 & 2, for enabling low temperature rolling in
finishing stands. After final rolling the bars are cooled in cooling stretch-3 and are
either sent to bar line or coil line. In Bar line, bars are cut in dividing shear and sent
to cooling bed for cooling. From cooling bed the bars are shifted to roller table by
chain transfer system and then cut to final required size in cold shear. Finally, the
bars are bundled together in 2 sets of bar bundling machines and sent to Bar
storage yard for stacking and dispatch. In coil line, the bars are coiled in three
numbers of garret coilers. The coils are placed on walking beam type coil transfer
system in which it is cooled by blower fans. The coils are then tilted and placed on
power C- hook conveyors and then finally compacted and strapped in three number
of compactor machines after which it is transferred to coil storage yard for storage
and dispatch. All control operations are done from control pulpits, which are
enclosed and air-conditioned making them free from noise and dust. PLC based
control system is provided for reheating furnace with nitrogen purging system and
interlocks for closure of shut-off valves in case of emergencies/ interruption.
Emergency overhead water tank with diesel pump back-up will cater to furnace
cooling and emergency needs in case of power trip and pump house trip. Process
control/ PLCs are having inbuilt safety interlocks to prevent damage of equipment
and working personnel’s. Area wise loudspeaker announciation and inter-com
systems are provided for communication of problems and emergencies. Wide
network of fire and drinking water with fire hydrants at various locations are
provided in mill and cellars to deal with possible fire accidents. All cranes and other
equipments are provided with safety interlocking devices.
Wire rod mill consists of WRM & Wire Rod Mill-2 (WMR-2), covered under QMS,
EMS, EnMS and OHSAS.
Wire Rod Mill (WRM) is a 5.38 m level, high speed, continuous mill designed to
produce 850,000 of wire road coils. It consists of 4 strands x 7 stand roughing mill,
4 strands x 6 stand intermediate mill, 4 strands x 2 stand each pre-finishing group
and 4 strands x 10 stand each finishing group, total 61 stands. The mill is equipped
with pre-finishing blocks, morgan finishing blocks incorporating no twist rolling,
stelmor line with controlled cooling and power and free hook conveyors for handling
wire rod coils. The mill is designed to produce plain wire rods from 5.5 mm to 14.0
mm. dia in coil form and rebars in 8, 10 and 12 mm dia., from rolled billets of 125 ±
3%mm. x 125± 3% mm. x 98000-104000 mm, rhombodity : 3.5%. The billets
received from billet mill (LMMM) are placed at +0.00 level by magnet crane on
charging grid I and II through on-line inspection for quality traceability of heat
number. The billets deposited are moved towards billet cross transfer which takes
over individual billets and carries them to billet elevator. Billets elevator takes the
billets one by one to the mill floor situated at +5.350 m level. Billets are transported
to the reheating furnace by means of the furnace approach roller table. The walking
beam of furnace collects the billets from roller table and charges them into furnace
for reheating. The billets are heated as per the grade & size following process
parameters document. The reheating furnace at WRM Mill consumes mixed gas for
reheating of blooms in reheating furnace. The reheating furnace is walking beam
25
type uses indirect cooling water for cooling of furnace skids and posts. During the
cooling of skids and post, the indirect cooling water is cooled in cooling tower and
returned as cooling water. The walking beam furnace is equipped with Waste heat
recovery system for recovering sensible heat of hot flue gases and air recuperartor
and gas recuperartor is installed for recovering waste energy, with this, the furnace
is supplied with hot air and hot gas. Once rolling temperature is achieved, the billets
are discharged into groove of mill stand no.1. A four position shiftable billet switch
feeds the billets to the 4 strands of the mill individually. The roughing mill comprises
of seven continuous 4 strand horizontal two high stands. The pass design is oval-
round sequence. Four rotating crop and cobble shears are provided after stand-7,
one for each line. The intermediate group comprises of 6 two high horizontal
stands. The stock is reduced to 21-23 mm. round. This is fed to 4 individual
finishing lines. The stock is reduced to 17-19 mm. dia in the prefinishing blocks.
The stock passes through water cooling stretch for partial cooling before final
rolling. Horizontal loopers are provided before prefinishing blocks for tension free
rolling. 10 stand no twist finishing blocks are used for final rolling of wire rods. In
process checks are carried out for expected stock outputs at various stages and
final dimension of wire rods. All the 10 stand finishing blocks are used for 5.5 to 6.5
mm. size wire rod rolling, for 7 to 8 mm only 8 stands are used, for 9 to 10 mm. only
6 stands are used and for 12 and for 14 mm only 2 stands are used. After final
rolling, wire rods are cooled in stelmor cooling system by setting cooling
parameters as per the supplied grade. The quality of the rolled product depends on
the heating, rolling & cooling effects the final mechanical & metallurgical properties
of wire rods with respect to their tensile strength, yield point, drawability and the
physical properties affects the surface quality of end product. The coils are formed
in coil forming chamber. The coils are loaded onto C-hook. A total of 180 hooks are
provided for handling the production. The C-hooks are carried by a power and free
hook conveyor circuit. The coils are compacted and tied at automatic compacting
and tying machines. The size and mechanical properties are tested and the
appropriate grade is fed to the production control computer at express lab.
Identification labels and colour code are attached to the coils as per declared grade
taking reference from production control computer and display units. The coils are
stacked with the help of EOT magnet cranes. All controls operations are done from
control pulpits, which are enclosed and air-conditioned making them free from
noise, heat and dust. Microprocessor based control system is provided for
reheating furnace with interlocks for closure of shut off valves in case of
emergencies/ interruption. Process control computer/PLCs are having inbuilt safety
interlocks to prevent damage of equipment and injuries to working personnel. Area
wise annunciation is provided in all control pulpits/ECR to indicate
problems/emergencies. Wide network of fire and drinking water system with fire
hydrants at various locations are provided in the mill and cellars to deal with
possible fire accidents. Automatic fire fighting pump house (foam filing system) is
provided for all cellars with back up diesel pumps to deal with power failure
situation. Fire detection alarm systems are provided in ECRS and cable tunnels.
Fire check doors are provided for cable tunnels. All cranes and other equipment are
provided with safety interlocking devices.
Wire rod mill-2(WMR-2) is at +5.50 m level, high speed, continuous mill designed to
produce 600,000 tons of wire rod coils. It consists of a single strand x 6 stand Fast
Roughing mill( both Vertical & horizontal), 2 strands x (6+4) stands intermediate
mill, 2 lines of 2 stands each of pre-finishing group, 10 stand each finishing group(
26
NTM) & (2+2) stands of each RSM, total 30 stands for each line. The mill is
equipped with pre-finishing blocks, finishing blocks incorporating no twist rolling,
stelmor line with controlled cooling and power and free hook conveyors for handling
wire rod coils. The mill is designed to produce plain wire rods from 5.5 mm to 20.64
mm. dia in coil form, from SMS-2 caster blooms of 150 x 150 x 12000 mm.
However, Rolled Billets of 125 mm x 125 mm from Billet Mill (LMMM) square cross
section & length ranging from 9.9 m to 10.4 m also can be rolled as per mill builder.
The blooms are received from SMS-2 placed at +0.0 level on 3 Nos. of Charging
Grids in the BSY by magnetic cranes after inspection for quality & traceability of
heat number. The blooms deposited and moved on the Grid towards LLBRT at 0.0
mt level and transferred to it for forwarding them to the Elevator one by one. At the
Elevator Blooms are lifted to the +5.7mt level FART. Billets are transported to the
reheating furnace by means of the furnace approach roller table (FART). The
charging roller table of the furnace collects the blooms from the approach roller
table and charges them into furnace for reheating after ensuring measured length
of the blooms. The blooms are heated to rolling temperatures of 1050 to 1200° C
as per the grade & size of the output as per process parameters. The reheating
furnace at WRM-2 consumes in-house generated mixed gas for reheating of
blooms. The reheating furnace is walking beam type uses indirect cooling water for
cooling of furnace skids and posts. The return indirect cooling water is cooled in
cooling tower and recirculated as cooling water in a closed circuit. The walking
beam furnace is equipped with Waste heat recovery system for recovering sensible
heat of hot flue gases using an air recuperator installed in the flue duct. Thus, the
furnace is supplied with hot air and Mixed gas for combustion to achieve rolling
temperature. The blooms are discharged using discharging roller tables to Stand
no-1 (vertical) of the FRM, through the De-scaler, SSIRT, Pinch roll & pendulum
shear. The roughing mill comprises of six continuous vertical & horizontal two high
stands alternatively. The pass design is Box-Boxoval- round sequence. The stock
size is reduced to 73 round by gradual reduction in the roughing group. A rotating
950mm shear is provided after stand-6 followed by a TSIRT to feed either strands
of the two strand, 10 Horizontal stand intermediate mill group. The bar from
Intermediate mill is fed to individual lines starting with 2 stand pre-finishing mill, 8
stand no twist mill and four stand reducing and sizing mill (V configuration modules)
alternately in line A and line B. The process from intermediate mill is a continuous
rolling process with provision for chopping and cropping at shears located in
intermediate and no twist mill areas. The process line is also equipped with pinch
rolls before pre-finishing, no-twist mill and after reducing sizing mill for rod feeding,
complemented by Loopers for tension free rolling. The stock is reduced to 21-23
mm. round after Stand-16. The stock is further reduced to 17-19 mm. dia in the
prefinishing blocks. The stock passes through water cooling stretch and covered
equalizing troughs for partial cooling & normalizing before final rolling. Water
cooling boxes are located between No-twist mill , Reducing sizing mill & Laying
Head for controlling the temperature of feed stock during the rolling process. In
process checks are carried out for expected stock outputs at various stages and
final dimension of wire rods. As per the output size required the stands of the NTM
& Intermediate Mill are put into line or bypassed using dummy stands/ inserts. The
finished wire rod from reducing & sizing mill is made into coil form at inclined laying
heads and further handled on stelmor roller conveyor by setting cooling parameters
as per the grade under rolling. The controlled cooling process is achieved by
stelmor cooling conveyor where coiled wire rod loops are cooled with air using
optiflex system. The coil is formed at the end of the stelmor in coil forming station
27
with the support of ring distributor provided in the forming stations. The formed coil
in free form is collected at twin mandrel station and is transferred to a waiting hook
by a transfer car at the zero level of the mill. The Hook conveyor system is provided
for handling the free coils formed at coil forming station passes through various
processes like trimming, compacting, weighing and tagging before delivering the
finished coils to unloading stations for further handling and shipping. The hooks are
driven /carried by three sets of power and free hook conveyor circuits. The quality
of the rolled product depends on the heating, rolling & cooling which effects the
final mechanical & metallurgical properties of wire rods with respect to their tensile
strength, yield point, drawability and the physical properties The size and
mechanical properties are tested and the appropriate grade is fed into the system
at the metallurgical lab located in finishing area beside Mill bay at the zero level.
Identification labels and color code are attached to the coils as per declared grade
taking reference from the system/process control computer and display units. 6
Nos. of EOT cranes for carrying out material handling activities are provided in the
Mill, Furnace & Roll shop areas. Another 6 Nos. of RT Magnetic cranes are
provided for handling of coils for stacking & loading in the shipping bay. Dispatches
are coordinated with Traffic, Marketing &PPM for yard management to keep the mill
rolling without space constraint. All cranes and other equipment are provided with
safety interlocking devices. The Plant is equipped with Roll Shop in a separate bay
for turning and grinding of roll grooves, rings & guide rollers. It has facilities &
equipment for servicing of stand housings both for housing less stands and high
speed areas. A facility for servicing of guides and work shop for carrying out repairs
of equipment is also provided. 6 Nos. of lubrication systems, 10 Nos. Hydraulic
systems, 4 Nos. of Oil-Air systems, 5 Nos. of Grease Systems & 1 No. Descalar
Pump house are located in Cellars provided for various plant equipments located at
0.0mt level & sub-zero level in the main mill bay. Electrical Power & control
equipments are provided in Electrical Control Rooms I & II. ECR-I caters to Furnace
and Mill equipments and ECR II for Finishing & Dispatch Area Equipments. ECR-I
is located outside the Mill bay consisting of four floors along the intermediate & high
speed mill area. ECR II is located in finishing area beside Mill bay in Single Floor at
the zero level finishing mill area. 3 Nos. of Control Pulpits are provided for the
Furnace, Mill and Finishing Areas for various groups of equipments. All controls
operations are done from control pulpits, which are enclosed and air-conditioned
making them free from noise, heat and dust. PLC based control systems provided
for reheating furnace with interlocks for closure of shut off valves in case of
emergencies/ interruption. Process control computer/PLCs are having inbuilt safety
interlocks to prevent damage of equipment and injuries to working personnel. Area
wise annunciation is provided in all control pulpits/ECR to indicate
problems/emergencies. Wide network of fire water system with fire hydrants at
various locations & portable extinguishers are provided in the mill and cellars to
deal with possible fire accidents. Dedicated automatic fire fighting pump house with
back up diesel pumps to deal with power failure situation is provided. Fire detection
alarm systems & CO2 flooding system are provided for the cellars. Clean Agent
flooding system along with Intelligent Addressable Microprocessor based automatic
fire detection and alarm system (FDA) with state of art and technology with fire
alarm panel (FAP) each in ECR-1 & 2 along with repeater panel has been provided
for the ECR’s. The cable tunnels are provided with FDA system along with portable
fire extinguishers for fire fighting. Fire check doors are provided at various points for
cable tunnels.
28
Medium merchant and structural mill consists of MMSM and Structural Mill (STM),
covered under QMS, EMS, EnMS and OHSAS.
MMSM is a single-strand continuous mill provided with two walking beam type
reheating furnaces connected with a chimney, 8 stand roughing mill, 6 stand
intermediate mill & 6 stand finishing mill, double sided rake type cooling bed, on
line straighteners and cold saws. The mill is envisaged to produce 8,50,000 tons of
merchant and structural products. It is capable of rolling medium merchant size
rounds, squares, flats, equal angles, unequal angles, T-bars, channels and IPE and
HEA beams. The mill incorporates facilities for rolling universal beams. The input
for the mill is 250 x 250 mm, continuous cast blooms of 6 m length from SMS-2 are
also being used now as an alternate input. In addition to this 200X200mm
continuous cast blooms of 12 m length from SMS-1. The cold blooms are charged
in walking beam reheating furnace to heat up to the rolling temperature i.e. 1200o
C. The reheating furnace consumes mixed gas for reheating of blooms in reheating
furnace. The reheating furnace uses DM water for cooling of furnace skids and
posts. During the cooling of skids and post, the DM water is recirculated and the
furnace is equipped with evaporative cooling system for generation of process
steam. The process steam generated can be used for driving steam turbine for
running ECS pump in case of emergency and in normal circum stances, the
process steam recovered is sent to plant process steam network. The walking
beam furnace is equipped with Waste heat recovery system for recovering sensible
heat of hot flue gases and air recuperartor and gas recuperartor is installed. The
heated blooms are fed into the mill and rolled through roughing mill train (RMT),
intermediate mill train (IMT) and finishing mill train (FMT) to get the desired profile
as per rolling programme of that particular profile. The maximum speed of mill is 9
m/ sec. The material coming out of exit stand is cut into multiples of 12 m.
(customer length in general) and is cooled in cooling bed which is designated as
RHS (right hand side) and LHS (left hand side). The cooled material on cooling bed
is sent to batching through straightner (for structural’s) and directly in case of
merchant products. The finished products are cut into customer length at cold saw
and sent to piling in case of structural’s and squares and to bundling in case of
rounds. The products are piled / bundled to a maximum weight of 9 tonnes and
sent to collecting grid. Color coding is done as per the grades rolled and tags are
fixed to identify the material. Then these are lifted by EOT cranes and stacked for
shipping and dispatch. Electricity is consumed in running of combustion air fans,
rolling mill strands, ventilation systems, hydraulic pumps. Lighting systems. On line
PPC system is in place for product identification and traceability of products right
from bloom stage to the packing, stacking and dispatch stage. This user friendly
system enables data entry in First in First out (FIFO) manner thus helps maintain
data integrity and avoid quality mix up. The Implementation of Maintenance
Management System (MAMS) ensures availability of equipment through
systemization of maintenance planning activities and systematic analysis of
breakdowns for avoiding recurrence. Implementation of Strapping of finished
products brought in improvement in quality of packaging and dispatching. On-line
rolls management system (ROMANS) is installed for On-line information of rolls
data, cassettes data to facilitate in strategic decision making related to
technological requirement of pass/cassette/section changing. Due to the installation
of PLC in furnace control, efficient & uniform heating process in the re-heating
furnaces through dynamic air-gas ratio correction system with respect to varying
calorific value of mixed gas is achieved. The following special OH&S features are
29
provided in MMSM in addition to the general OH&S provisions: CO2 flooding
systems 1 and 2 are provided to fight any fires in the oil cellars. High pressure
water system is provided for fighting fire in the lub oil enclosures. The furnace is
provided with safety interlocks. The mill trips in the case of lubrication oil failure.
Interlock is provided for the cooling bed so that in case of any tripping of equipment
of cooling bed, further material feeding is stopped (800 KNS goes into chopping
mode). The saw areas, batching areas and piling areas are provided with safety
interlocks. All cranes and other equipment are provided with safety interlocking
devices.
Structural mill (STM), is a single-strand continuous mill provided with one walking
beam type reheating furnace of capacity 200 Tons/hr, 7 stand roughing mill in H-V
configuration, 5 stand intermediate mill & 5 stand finishing mill, with H-V-U
configurations each, a double sided rake type cooling bed, on line strengtheners
,cold saws and stackers The mill is envisaged to produce 7,00,000 tons per year of
structural Products with a provision to produce 8,50,000 tons per year in future. It is
capable of rolling medium merchant size rounds, squares, flats, equal angles,
unequal angles, T-bars, channels and IPE and HEA beams. The input for the mill is
200 x 200 mm, continuous cast blooms of 8 to 12 m length from SMS. The billets
received from SMS are placed at +0.00 level by magnet crane on the three
charging grids.. The blooms deposited are moved towards the elevator. The
elevator takes the blooms one by one to the mill floor situated at +5.0 m level.
Blooms are transported to the reheating furnace by means of the furnace approach
roller table. The cold blooms are charged in walking beam reheating furnace to
heat up to the rolling temperature i.e. 1200˙C. The reheating furnace consumes
mixed gas for reheating of blooms in reheating furnace. The walking beam furnace
is equipped with Waste heat recovery system for recovering sensible heat of hot
flue gases and recuperartor is installed. The heated blooms are fed into the mill and
rolled through roughing mill train (RMT), intermediate mill train (IMT) and finishing
mill train (FMT) to get the desired profile as per rolling programme of that particular
profile. The maximum speed of mill is 12 m/ sec. The material coming out of exit
stand is cut into multiples of 12 m. (customer length in general) and is cooled in
cooling bed which is designated as RHS (right hand side) and LHS (left hand side).
The cooled material on cooling bed is sent to batching through straightner (for
structural’s) and directly in case of merchant products. The finished products are
cut into customer length at cold saw and sent to stacker for stacking. The products
are strapped and sent to collecting grid and tags are fixed to identify the material.
Then these are lifted by EOT cranes and stacked for shipping and dispatch. Here in
STM, the Roll Shop is attached to the Mill. It caters to the requirement of roll pass
design, Roll turning, Stand preparation and guide assemblies. It is equipped with
sophisticated CNC Lathes, CNC Milling m/c’s, Branding M/c etc.
The above mills are provided with reheating furnaces suitable for firing mixed gas
(mixture of blast furnace gas, coke oven gas and converter gas). The furnaces in
LMMM are also suitable for firing low sulphur heavy stock (LSHS) or furnace oil.
The flue gases from the furnaces are let out into the atmosphere through 4 nos
chimneys. The direct cooling water used for cooling the rolled products in WRM,
LMMM, MMSM, WRM-2 is contaminated with oil / grease / scale and is collected in
the scale pit of pump house no.12 where the scales are separated, collected and
transported to sinter plant as feed material. The floating oil is skimmed, collected
30
and processed in oil reclamation unit. The treated water from the clarifier is cooled
and recycled.
Roll shop & repair shop (RS&RS) is a prime service department to the Rolling Mills
LMMM, WRM & MMSM and is covered under QMS, EMS, EnMS and OHSAS. It
caters to the requirement of roll pass design, roll set assemblies, guide assemblies
and repairs / manufactures of mechanical spares to all the three rolling mills. It
comprises of the following :
Roll shop & repair shop has been built to exacting international standards in design
and engineering with the state of the art technology which includes the following
salient technological features :
Thermal power plant (TPP) and blower house, covered under QMS, EMS, EnMS
and OHSAS, produces high pressure steam, electric power and cold blast for the
blast furnaces. The estimated power requirement for VSP is 490 MW at 6.3 MT
stages, the peak load being 500 MW and essential load being 80 MW. The
generating capacity is 520MW, comprising of 315 MW from Main TPP 120MW from
PP2, 24MW from gas expansion turbine, 15MW from Back Pressure Turbine
Station, 20MW from NEDO, 14 MW from COB4 and 13 MW from TRT. Apart from
meeting part of the power requirements, the power plant and blower house supply
cold blast air to blast furnaces and steam at 13KSCA and 4KSCA to the plant. TPP
has 3 turbo generator units of 60MW each and two units of 67.5MW, 3 turbo
blowers each having a capacity of 6067 NM3/min, one turbo blower having a
capacity of 7000 NM3/min and 6 boilers each of 330 T/hr capacity at 101 KSCA at
540oC. The steam generating sets are of multi-fuel firing design and the rating of
each steam generation while firing various fuels is 100%MCR with pulverized fuel
and coke oven gas, 50% MCR with blast furnace gas and 25% MCR with fuel oil.
The power produced can be synchronized with the power grid of Andhra Pradesh
Transmission Corporation. The unit supplies power to emergency units in case of
failure of external power supply. The high pressure steam produced in this unit is
for meeting the requirements of turbo blowers and turbo generators as well as for
other process requirements in the steel plant. Thermal Power Plant and blower
house has six high pressure boilers, five turbo generators and four turbo blowers.
The boilers are multi fuel type, suitable for firing with coke oven gas, blast furnace
31
gas, furnace oil and coal. A number of other facilities like water system, ash
handling system, flue gas handling system etc. are provided. Furnace oil is used for
flame stabilization and High Speed Diesel (Diesel) is used during startups of
Boilers. Part of the High pressure steam generated at Boilers is sent to Turbo
blowers for generation of blast air and remaining steam is sent to Turbo generators
for generation of electricity. The Steam Turbines are envisaged with Condensing
and Extraction type and process steam of 13 ata and 4 ata is extracted. 13 ata
steams extracted from Steam Turbines partially used internally in Power Plant and
remaining sent to Plant process steam network to meet requirements at CO, BF,
SMS, Mills and ASP. 4 ata Steam extracted from Steam Turbines is used for
Demineralised Plant for production of DMDA water for make up in Boiler feed water
circuit and CDCP boilers. Chilled water plant -2 operates on vapor absorption
system use 4 ata steam extracted from steam turbine for generation of chilled
water. Steam is cooled in condenser and Cooling water requirements are met from
Pump House-4. Electricity is used for driving of motors of rotating machinery like
Boiler feed pump, Primary Air fan, Coal Bowl mills, Induced draft fans, Ash Slurry
pumps etc. The auxiliary units comprise of 16 nos of waste heat boilers which
produce steam by recovering heat from hot nitrogen in coke dry cooling plant, 2 nos
of back pressure turbo-generators and one number condensing type turbo
generator generating power from the above and 3 nos of gas expansion turbo-
generators generating power by expansion of blast furnace top gas. The boiler
quality water is produced in the dematerialized (DM) treatment plant. During the
production of DM water, acidic effluents are generated which are collected and
neutralized before discharging into the storm water drain. The flue gases from the
high pressure boilers are cleaned in electrostatic precipitators to a final dust content
of below 50mg/Ncum and vented through a 180 m tall multi-flue chimney. The fly
ash and the bottom ash from the thermal power plant and blower house is collected
and conveyed through a wet system to the ash slurry pump house from where it is
pumped to the ash pond located outside the plant boundary wall. The water so
contaminated is about 1500 cum/hr (8 mgd). The clarified water from the ash pond
is pumped back to the thermal power plant for ash handling. Power plant 2 consists
of two BF gas fired boilers and one condensing type turbo generator of 120 MW
along with associated equipment.
The following special OH&S features are provided in TPP in addition to the general
OH&S provisions:
The boilers are provided with safety valves and furnace safe guard supervisory
system. The turbines and blowers are provided with over speed and high vibration
protection. The generators are provided with automatic CO2 flooding system,
differential and earth fault protection systems against fire and short circuits. The
lube oil cellars are provided with automatic CO2 flooding system. The cable cellars
are provided with water sprinkler system. A separate fire fighting pump house is
provided. Fire detection and alarm systems are provided in important areas. All
operations are carried out from air conditioned control rooms.
Distribution Network Department (DNW), covered under QMS, EMS, EnMS and
OHSAS, handles power at 220KV, 33KV and 6.6 KV levels. Power at 220KV level
is received from AP TRANSCO at Switching Station of DNW. Power is further
extended through three numbers of 220 kV cable feeders to Main Receiving Station
(MRS) of DNW and from Thermal Power Plant (TPP) at Load Block Step down
32
Substation-5 (LBSS-5). MRS is inter-connected through the Tie Lines with LBSS-5
i.e. TPP switchyard. The power generated in TPP at 11KV level is stepped up at
220KV level and synchronized with AP TRANSCO grid supply. Power is distributed
to various plant units at 33KV, 11KV and 6.6KV levels through LBSS-1, LBSS-2,
LBSS-3 LBSS-4, LBSS-6 and LBSS-7 by DNW department. Switchgear
equipments of 33KV, 11LV and 6.6KV are housed in substation buildings whereas
the outdoor equipment of 220KV and 33KV are surrounded with boundary walls to
prevent un-authorized entry. All the circuit breakers and isolators are provided with
safety interlocks. Fire detection & alarm system is provided in substations. DNW
department maintains equipment related to power distribution up to 6.6KV to the
plant units in close conjunction with Thermal Power Plant and Andhra Pradesh
Eastern Power Distribution Co. Ltd. During the process of maintenance used
transformer oil and used lead acid batteries are generated. It collects and stores
the used transformer oil and used lead acid batteries for further disposal. Periodic
reports are sent to EnMD department as required by the Hazardous Wastes
(Management, Handling and Transboundary movement) Rules, 2008, and
amendment thereof& Batteries (Management & Handling) rules, 2001.
Energy management department (EMD), covered under QMS, EMS, EnMS and
OHSAS, undertakes monitoring and distribution of various fuel gases produced in
the steel plant as well as various utilities like nitrogen and chilled water through the
SCADA system. EMD also operates the BF gas cleaning plants, converter gas
recovery plant, CO gas boosting station, gas mixing stations and central fuel oil
station. EMD also have the flare stacks for coke oven gas and blast furnace gas
under its control. EMD monitors overall Energy consumption of plant and advise all
departments on proper course of action on energy conservation. EMD ensures
optimum distribution of fuels and utilities and try to minimize fuels and utilities
losses. Further, EMD consumes electrical energy in running of booster fans at
COGBS and LDGRP and pumping system at GCP-1&2. Electricity is also used in
lighting system. The following special OH&S features are provided in energy
management department in addition to the general provisions:
LD gas recovery plant consists of a gas holder of 80000 m3 capacity, gas boosters
and electrostatic precipitators. It is provided with necessary safety features like
interlocks for high and very high level and low and very low level and high pressure.
The gas boosters are provided with safety features viz., bypass across the booster
and tripping of booster in case of abnormal conditions sensed through
instrumentation. Similarly the electrostatic precipitators are also provided with
safety interlocks for abnormal operating conditions sensed through instruments.
The gas mixing station no.5 is also provided with alarms and annunciations. The
blast furnace gas cleaning plants BFGCP-1 and BFGCP-2 are provided with
various safety signals like failure of water supply, failure of water seal in scrubber
and high differential pressure across venturies. The coke oven gas boosting station
has low pressure booster and high pressure booster. These are provided with
various safety interlocks and alarms for abnormal conditions like low suction
pressure, booster vibration high, discharge pressure high and failure of cooling
water supply. The energy management department also takes care of gas pipeline
network of BF gas line, mixed gas line and coke oven gas line. These lines are
provided with drip pots and nitrogen injection facility when the line pressure is low.
The pipelines are also connected to BF gas flare stack and coke oven gas flare
33
stack. In case of low pressure in the gas line, certain consumers are cut-off
automatically.
Lubrication and hydraulic department (L&H), covered under QMS, EMS, EnMS and
OHSAS, renders service to all the user departments in the plant by arranging
supplies of required types, quantity of lubricating/ hydraulic oils, greases, hoses, O-
rings & oil seals for effective running of the plant. It stores and issues lubricants and
hydraulic oil to consumers (bulk oil management), collects used lubrication and
hydraulic oils from various departments, operates and carry’s out reclamation of
collected used oils for reuse in various identified units (used oil management) and
maintains the oil reclamation unit, various hydraulic equipment & lifts. Checking the
correctness of the specification & up gradation of specification in line with
technological developments are carried out to procure quality inputs. Centrifuges,
oil purification system, on-line contamination checking (6-channel), condition
monitoring for all large centralized critical hydraulic systems are employed in
reclamation process. It stores the waste lubricants and hydraulic oils, oil sludge, de-
toxified empty drums and grease barrels for further disposal in accordance with the
hazardous wastes (management & handling) rules, 1989 as amended up to 2003.
Utilities department:
The utilities department, covered under QMS, EMS, EnMS and OHSAS, operates
and maintains the following units:
a. Air separation plant: I, II, III, IV for generation and distribution of oxygen, nitrogen
and gaseous argon.
b. Compressor house: I, II for supply of compressed air, Instrumentation air & dry
air.
c. LPG
d. Chilled water plant: III, IV, V, VI &VII for supply of chilled water for air
conditioning.
It also undertakes filling & issue of gaseous Oxygen, Nitrogen, Argon. It procures
LPG as per requirement of CCD and also supplies LPG cylinders to various
maintenance sections. The utilities department also controls the consumption /
leakages and phasing out of the ozone depleting substance (ODS) and takes
necessary action for complying with the ‘Ozone depletion substances (regulation
and control) rules, 2000.
There are five chilled water plants which operate with vapor compression principle
and uses R-134 A as refrigerant. Electricity is used for running of chillers’ and other
associated equipment. Chilled water plant -3 meets the cooling requirement of
SMS-I, ASP and rolling mills. Chilled water plant -4 meets cooling requirements of
central computer centre, energy & telecom building and pay & PF section. Chilled
water plant – 5 meets the cooling requirements of SMS-2 and WRM-2 while Chilled
water plant – 6 meets that of Blast Furnace – 3 and Chilled water plant -7 that of
Sinter plant -3.
LPG cylinders of 49.5 kgs capacity at 5 to 7 kscg pressure are procured from public
sector oil companies. These cylinders are connected to manifolds and supplied to
35
consumers at a pressure of 0.92 – 0.93 kscg through the Vapour Off Take (VOT)
method. Filled Acetylene gas cylinders are also procured from outside and
delivered to the various consumers inside the plant on demand.
The following special OH&S features are provided in Utilities Department in addition
to the general OH&S provisions:
The following special OH&S features are provided in the LPG distribution unit: Anti
spark tools are used. Ventilation is provided at ground and roof level to prevent
accumulation of gas.. Nitrogen gas purging facilities for equipments/pipelines are
provided. Flash-back arresters are provided at discharge manifolds. LPG pressure
and flow rates are monitored carefully. In case of too low a pressure or too high a
flow, alarms are generated and follow up action is initiated.RCC walls are provided
in between discharge manifold cylinder racks to minimize the effects of
fire/explosion. Barbed wire fencing is provided around the plant. In order to avoid
rise of pressure in the piping / equipment systems, safety relief valves are provided
at manifolds and pipelines.
The following EnMS features are provided in the Utilities department: Structured
packing columns which consume 15% less energy have been procured in the new
units .Variable frequency drives are employed in most of the new equipments.
Compact fluorescent lamps which are more energy efficient are used instead of
normal fluorescent lamps. Energy efficient screw chillers are used . Operating
strategies are tuned to operate the units at their highest efficiency range. Personnel
are trained on energy efficient operating practices and energy audits are
undertaken frequently.
Water management department (WMD), covered under QMS, EMS, EnMS and
OHSAS, receives water into the Kanithi balancing reservoir and distributes it as per
the requirement to various units of the plant after required chemical treatment. The
water in circulation is about 260000 cum/hr which is mainly used for cooling of
equipment. The heated water is cooled in 38 nos. of induced draft cooling towers
and is recycled. The water used for gas cleaning, dust separation, mill scale / fine
36
particle flushing etc. gets contaminated by suspended solids and oil. The waste oil
is removed by oil skimmers provided at scale pit pump housees-12,15, SMS 2 and
Mills 2 Scale pit PH. The contaminated water is treated in 10 non treatment plants
consisting of radial settling tanks, etc; and recycled after removing the
contaminated solids. The slurry containing metallurgical wastes from treatment
plants TP- 1,2,3,4,7 & 8 is pumped to a Metallurgical pond. The clarified water from
the metallurgical pond is being discharged to sea. Water is used for fire fighting,
equipment cooling, steam generation, drinking and sanitary use. Water
management department has one reservoir for raw water and another for ash (ash
pond).is recycled for use through ash pond. It has 47 re-circulating water pump
houses, 10 overhead tanks, 38 cooling towers, 10 treatment plants, 13 sewage
pump houses, 7 sludge pump houses, 2 nos. of filter press units etc. Plant has also
3 reverse osmosis units to achieve zero discharge goals. These plants are in very
advance stage of commissioning. Plant water is treated at raw water treatment
plant and is stored in two compartments, which are located at pump house-01.
Make up water is supplied to different recirculation water pump houses by makeup
water pipeline network. The makeup water is also sent to fire and drinking pumps
which are located at pump house-02. It is further treated and stored in overhead
tank and on ground reservoir. It is supplied throughout the plant by using fire and
drinking water pipe network. In stage 2 waste treated water line network is there for
firefighting makeup water which caters to fire fighting pump house built for
individual zone. Electricity is used for running rotating machinery like Pumps,
Cooling tower fans, and lighting systems.
Fire alarm signal is provided at pump house-02 where emergency fire fighting
pumps are available. Chlorine leak detector is available at chlorine dozing points.
For chlorine cylinders, neutralization tank is available. Dewatering pumps are
installed with alarm and auto operation to take care of flooding. At acid dozing
tanks, showers are available.
Traffic department, covered under QMS, EMS, EnMS and OHSAS, receives raw
material rakes from Railways in the pre-tippler lines of Raw material handling plant.
After emptying of wagons, the rakes are handed back to Railways within the plant.
Traffic also coordinates with Railways for supply of rakes required for the outward
dispatch of the products. It also undertakes various rail movements inside the plant
including movement of hot metal from Blast furnaces to the Steel melting shops or
to the pig casting machines and pig iron from the pig casting machines to the pig
storage yard. The diesel locomotives used for hauling the rakes and the captive
wagons used for transporting various materials within the plant are maintained in
the Loco & wagon repair shop. The installations and machinery of Traffic
department are provided with inbuilt safety devices. Route relay interlocking
(RRI)/Solid state interlocking (SSI) system is provided in the following areas: Blast
furnace yard, Mixed goods marshalling yard, Rolling mills product sorting yard, Raw
material unloading yard. All the diesel locomotives are provided with standard
safety interlocks. The cranes and machines in the Loco & wagon repair shop are
provided with the standard limit switches to prevent over travel. The rail-road
37
crossings in the RRI/SSI areas are provided with signal lights and hooters. Diesel is
used as fuel in diesel locomotives and Electricity is used in buildings, yards and the
Loco & wagon repair shop.
Research & Development department, covered under QMS, identifies, selects and
handles R&D projects both internal with inhouse expertise and resources and
externally in collaboration with other organizations related to design and
development of new steel products. Pilot oven /pot sintering is used for carrying out
R&D activities. It is instrumental in improving the process/ product quality and
enhancing the brand image of the product.
Scrap and salvage department (SSD) covered under QMS, EMS and OHSAS,
carries out the collection & processing of various types of iron and steel scrap
generated in the plant and makes arrangements for supply of scrap to steel melting
shops I & II by SSD as well as disposal to external customers. Different types of
refractory bricks are collected by SSD and supplied to DF Bay (SMS-I), Five clay
type (SMS for emergency containers) and SMS converters, Mag-carbon for patch
work or transported to stores department for disposal. All the debris and solid
wastes which could not be recycled or sold are transported to designated slag and
debris dump located near Appikonda gate. All the hired vehicles engaged for
transportation are ‘PUC’ certified.
Refractory engineering department, covered under QMS, EMS, EnMS and OHSAS,
helps sinter plant, blast furnace department, steel melting shop, and rolling mills in
rendering repair and maintenance of refractory works in various reheating furnaces,
converters relining, ladle lining continuously.
Capital repair group (CRG), covered under QMS, EMS, EnMS and OHSAS, carries
out refractory repair/maintenance of all relevant equipments of CO&CCP including
jobs during capital repairs and also mechanical repair/ maintenance of anchorage
system, gas withdrawal system, heating system and doors of coke oven batteries.
CRG also specializes in providing acid proof lining to protect against corrosion in all
relevant installations in coal chemical plant & refractory maintenance of benzol
plant, tar distillation unit, Coke dry cooling plant, coke sorting plant etc. It is
instrumental in replacing the asbestos rope with environmental friendly ceramic
rope and performing effective maintenance and modifications to reduce stack
emissions and fugitive emissions in coke ovens.
a. Monitoring of ambient air quality with ambient air quality monitoring system,
water quality, effluent quality, stack emission with Online stack monitoring
system , fugitive emissions, effluent quality, waste generation / handling /
disposal, ambient noise-level and work-zone environment as per prescribed
statutory norms, wherever applicable.
Safety engineering department, covered under QMS, EMS, EnMS and OHSAS,
closely monitors actions related to safety of plant, equipment and personnel and
coordinates activities with statutory safety authorities. It advises and assists the
management in the fulfillment of the obligation concerning prevention of incidents
and maintaining a safe working environment. SED imparts safety training as well as
refresher safety training to the regular employees as well as contractor workers.
SED conducts safety inspections and co-ordinates with the department for
corrective actions in respect of unsafe conditions and unsafe actions. SED
conducts safety campaigns and competitions amongst the employee to promote
safety. SED ensures that high quality safety appliances are procured and issued to
the employees. SED has been conducting comprehensive Safety Audit,
comprehensive Risk Assessment & Management (HAZOP, HAZAN, Quantitative
Risk Assessment, Consequence Analysis, Hazard Analysis & Risk Assessment-
HARA, Emergency Action Plan) for entire plant including the newly commissioned
units and updating the On-site Emergency Plan SED co-ordinating with
departments for updating Work Procedures, Work Instructions, HIRAs, Legal &
Other requirements, conducting Internal & External Safety Audits, monitoring NCRs
& Observations raised during the audits and follow-up for compliance. SED
Conducting regular meetings with the OHSMS Co-ordinators for reviewing the
status of implementation of OHSMS.
Covered under QMS, EMS and OHSAS, offers comprehensive services to all
employees complying with the statutory obligations by carrying out man preventive
maintenance activities like periodical medical examination of the employees,
industrial hygiene surveys & services, toxicological evaluation, noise measurement
studies etc. The health records of employees are stored safely for periodic retrieval
and analysis. A specific coding system is developed and followed for efficient and
systematic placement. Efforts are in progress to store the historical employee
health data in soft form and for online working. Two, Fully–equipped, round the
clock functioning Emergency Medical care units provide services inside the Plant. It
coordinates emergency medical care services, provides first aid facilities and
training in Health Education Programme (class-room & shop-floor based) &first aid
& emergency care with the help of the training department. Two first-aid stations
are located in the plant, functioning round the clock with qualified doctors,
paramedical staff and ambulances. Supporting facilities for providing specialist care
are available at the Visakha General Hospital.
Air conditioning systems (ACS), covered under QMS, EMS, EnMS and OHSAS,
department maintains water coolers and the air conditioning units required for
operation of various equipments in the plant. These units consume electricity for
running of this ventilation systems equipment. The latest technology such as
backward curved fans, double skinned insulation, variable frequency drives for high
capacity motors with motor protection relay and three way mixing valve is installed
40
in air handling units to improve the quality of performance, reduce energy
consumption, heat loss, noise level etc;. The refrigerant recovery unit is used to
evacuate refrigerant from unit to avoid loss of refrigerant. The replacement of
reciprocating compressors with energy efficient scroll compressors and rotary
compressors (in case of window/split A/c) along with phase reversal protection for
scroll (unidirection) compressor is value addition towards better quality of service. It
controls the consumption / leakages / phasing out of ODS while carrying out the
operation and maintenance of their equipment and takes actions to comply with the
provisions of ‘Ozone depleting substances (regulation and control) rules, 2000’.
Engineering Shops & Foundry is covered under QMS, EMS, EnMS, OHSMS and all
the systems are at sustenance stage. In addition to these systems, ES&F is a 5S
implemented department having 640 employees and 200contract workmen. ES&F
is a set up to meet the requirements of Ferrous & non-ferrous spares of different
departments and for repair major equipments. ES&F is divided into 5 shops and
they are Central Machine Shop (CMS), Steel Structural Shop (SSS), Forge shop
(FS), Foundry (FDY), and Utility equipment repair shop (UERS). All the shops
except Foundry operate on two-shift basis for 300 days in a year and Foundry
operates in three Shifts.
CENTRAL MACHINE SHOP: At CMS, for preparing the raw material for machining,
material saws, facing and centering machines, hacksaws, and gas cutting facilities
are provided. The machining section has over 100 major machines including lathes,
milling, boring, and planning, slotting, shaping, grinding and other machines. The
assembly section undertakes medium repair and general overhauling of mechanical
equipment. Horizontal and vertical presses, washing tanks, oil berths etc. are
provided. The tool room has facilities for manufacturing of special tools, jigs and
fixtures, re-grinding of tools and cutter and brazing of tipped tools. The heat
treatment section is provided with annealing, normalizing, tempering furnaces,
carbonizing furnaces, high frequency hardening machine, quenching tanks will oil
cooling arrangements, welding generator and transformers for normal welding, sub-
merged arc welding machines etc. Facilities for surface grinding, pipe bending and
threading are also provided. The inputs to CMS are Iron & Steel castings, forgings,
rolled sections, repair and rectification parts, non ferrous castings and the products
& Services of CMS, are Shafts, Pinions, Gears, Crane Wheels, Rollers, Machining
41
of various fabrication jobs, Repair & reconditioning of various assembly jobs like
L&T Column, TK stands, pulleys, revisioning of gear boxes.
FORGE SHOP
In heavy forging section of FS, open die forgings of long shafts, gear blanks,
couplings etc. are being made with the help of 3 ton & 2-ton bridge type pneumatic
hammers. Each hammer will be provided with twin chamber heating furnaces. Floor
type manipulator and Jib Crane are provided for handling heavy jobs. In general
forging section, 1 ton, 500 Kg, and 200 Kg hammers with separate heating
furnaces are provided. A 2-ton drop stamp hammer with a heating furnace trimming
press etc. is provided for stamping. For cutting them to size, a band saw, a cold
saw, a billet shear and gas cutting facilities are provided. For stress relieving, a
bogie type-annealing furnace is provided. The Inputs are Ingots from Foundry,
blooms from SMS, billets, rods from Mills and higher size rounds with different
material specification from outside market. The products & services are raw
material for shafts, couplings, gears, pinions, flanges bull head hammers,
straightening of pallet middle frames of SP, shafts, gears, drill rods for BF, v-hooks
for SMS.
STRUCTURAL SHOP
For marking, cutting to size, forming and bending, guillotine shear, circular saw
plate bender, gas cutting unit etc. are provided. For welding, transformer, automatic
and semi-automatic machines and submerged arc welding machines are provided.
Thermit welding process is established for repairing Slag pots of SMS using thermit
mix powder. In Tool room, lathe, shaper, drilling machines etc. are provided for
running repair of shop equipment. The inputs are various sizes of plates, angles,
channels, beams, flats, rounds for fabrication of jobs and the products & Services
are all types of fabrication jobs, repair of slag pots, tundishes, Scrap boxes, ladles,
crane beams of SMS, BDH-24 fan shaft of sinter plant, KAMAG body of FMD, scrap
buckets of rolling mills.
FOUNDRY
Foundry operates in three Shifts out of which 2 shifts are for production and third
shift i.e C shift, is meant for maintaining the temperature of induction furnace. A
medium frequency furnace of 2-ton capacity and a 5T capacity main frequency
induction furnace are provided for cast iron jobs. There is a centralized sand
preparation unit. A drier and bins are provided for green sand. Belt conveyors
transport green sand, prepared mix and burnt sand. Moulds and cores are dried in
3 ovens. Lip & bottom pouring ladles with capacity up to 15 tons are provided for
handling hot metal. Two swing frame grinders and two pedestal grinders are
provided for finishing of iron castings. The inputs are Pig Iron, MS scrap, Ferro
alloys, graphite electrodes, sodium silicate, silica sand CO2 gas, moulding additives
etc. and the products & services are Steel, cast iron &non ferrous castings,
Emergency containers, tundish covers, bull gear for SMS, hot metal runners, ladle
paw for blast furnace, coke roll liners, sprockets, pallets for sinter plant, manganese
cast steel casings like bowl liner, lower mantle for RMHP, guide troughs for WRM,
slag pot segments for SSS repair, ingots for forge shop, non ferrous castings like
Mud-gun nuts for BF etc. Steel castings up to maximum piece weight of 10 T and
42
Steel Ingots up to 2 tons for forging are produced. An 8 Ton arc furnace and a two-
ton medium frequency electric induction furnace is installed for melting of steel
scrap and pig iron. A bogie hearth furnace for annealing/ normalizing of plain
carbon steel castings and fixed hearth furnace for heat treatment of manganese
steel castings with quenching facility is provided. The pattern shop manufactures
wooden, thermo coal patterns for making moulds. The principal equipment for
pattern making are saws, disc grinding, wood working lather, adequate facilities are
provided for saw grinding, painting, timber and pattern storage etc.
The inputs are sheets, plates, channels, angles, beams, billets, rounds for forge
shop for manufacturing Shafts, steel & iron castings and the products& Services
are manufacturing and repair of impellers, repair of GCP Id fan, repair of steam
exhausters for SMS, supply of cones & ducts of various sizes, in house
manufacturing of MBC impeller for CCCD, buildup& machining of various
components, reclamation jobs like valve repairs, conveyor idlers, PCM rollers etc.
Repair of ventilation, air conditioning and water supply equipment is carried out.
There is a machining section having 15 major machines like lathes, milling, slotting,
shaping and grinding machines, Sheet bending machines, Guillotine shear & semi-
folding machine are provided in fabrication section. 250 kg pneumatic hammer with
necessary facilities and a welding section for semi automatic, automatic and
shielded arc welding machines are provided in plumbing section. There is a
separate equipment repair section All shops are provided with separate Stores
facility for keeping operational, electrical and mechanical spares and consumables
related to their processes to meet the day to day requirements. In addition to these
shops, mechanical and electrical sections are provided for mechanical and
electrical maintenance requirements of equipments of all shops, for ensuring
equipment availability paying timely attention to running complaints and break down
and to take up-gradation and technological improvements activities to overcome
the problems of obsolete equipments.
Plant Design department, covered under QMS, EMS, EnMS and OHSAS, renders
services to various production departments for developing drawings of equipment
spare parts/assembles/sub-assemblies through Reverse Engineering for the
purpose of import substitutes & proprietary substitutes and in-house manufacturing.
It develops drawings for modification of spare parts/assemblies for better
operational efficiency and enhanced machine availability by re-engineering, thus
improving the quality of product. It also archives the developed drawings for
reprographic use. The development of drawing is done by using Autocad package
and white prints are produced by using wide format scanner cum printer. The
developed drawings are issued to the respective departments for producing spares.
In addition, it digitizes the available drawings using the wide format scanner cum
printer and making it available on-line at the intranet site. All the above activities are
controlled through an IT application namely “DRAWMAN” which is an Enterprise
Drawing Management System. It enables for customer to place their requirement
on line and get updates feedback through mail and mobile. This not only eliminates
the usage of paper but also makes the drawing accessible to the user department
by the click of the mouse.
Technical Improvement Cell (TIC), covered under QMS, is a nodal agency for
coordinating and monitoring all functions and activities related to AMR (Additions,
Modifications and Replacement) Schemes for Works and Mines in Planning,
Scrutinizing the schemes, budgeting , obtaining approval and monitoring the
implementation of schemes in a time bound manner till completion. The cell also
acts as an interface between the Owner Department and Related Departments like
Contract Awarding Departments and Work Execution departments etc.
Technical services (TS) department, covered under QMS, EMS, EnMS and
OHSAS, monitors the health of critical equipment of various departments through
condition monitoring in which vibration analysis (ad per IS 10816), wear debris
analysis, current data analysis and thermal images analysis etc. is done using the
Vibration analyzer, Motor current analyzer, acoustic emission meter, vibration
meters and thermography equipment for obtaining best quality results.
Central Maintenance Electrical (CME), covered under QMS, EMS, EnMS and
OHSAS, carries out electrical maintenance activities such as routine maintenance
& inspection to improve the performance of motors, periodic overhaul of motors
above 200KW at the work shop and large motors at user site, alignment of motors
with mechanism, electrical maintenance of ED (W), stores complex and other
buildings, street & tower lighting inside the plant, cranes & weigh bridges under its
scope. The overhauled / repaired motors are again reinstalled at site. The handling
& storage of motors are carried out under controlled conditions.
Electrical Repair Shop (ERS), covered under QMS, EMS, EnMS and OHSAS,
carries out repairs, rewinding of the electrical equipment which includes AC / DC,
LT/ HT motors and other electrical equipment with quality of raw materials
confirmed to applicable BIS, and IPSS standards. It plans for procurement of
related spares for carrying out the said services. It renders services on routine as
well as during capital repairs of various production departments.
Electro technical laboratory (ETL), covered under QMS, EMS and OHSAS, helps
the shop electrical of all the production shops in maintaining the thyristorised AC
and DC drives, uninterrupted power supply systems, programmable logic
controllers, crane controls etc. It also repairs all the electronic cards used in the
above drives and systems in its Electronic laboratory.
Spares Management Department (SMD), covered under QMS, EMS and EnMS, is
a nodal department between Works and MM department. Major activities are
procurement of rationalized spares, processing of material indents including MBC
/SMC and technical recommendation files of all Works departments. Maintains
budgetary control and Inventory control.
Cost Monitoring Group, covered under QMS, monitors the production cost and
provides MIS reports on costs.
Works contracts department, covered under QMS, mainly deals with the award of
contracts required for sustaining the production and maintenance of various
departments/units in the plant. In order to provide quality service Works Contracts
adheres to 3-tier scrutiny system supported by the contract procedures, legal and
commercial aspects of contract management, amendments, delegation of powers,
circulars, issued by management from time to time to select the suitable contractor
to perform the required task.
45
Civil engineering department, covered under QMS, EMS, EnMS and OHSAS,
carries out all the civil maintenance works, garbage handling, afforestation and
horticulture inside the plant.
Structural Engineering Department, covered under QMS, EMS, EnMS and OHSAS,
carries out inspection maintenance and painting activities of various steel structures
in the plant. St. ED undertakes replacement of translucent sheets of various yards
and bay.
The Main Receiving Station (MRS) is an Air Insulated Substation, which receives
Incoming power from APTRANSCO through 2x220 KV OH lines. It is connected
with LBSS-5, through three no 220 KV OH line called Main Lines 1,2,3 & one spare
220 KV OH line. LBSS-5 (Load Block Substation-5) is the main load distribution
center.
1x14 MW TRT (Top Recovery Turbine run by Hot Gas from Blast Furnace -3) and
1x14 MW COB(Hot Gas from Coke Oven Battery -4) are connected to 11 KV,
GSB#2 & 3 respectively, which in turn feed power to Extended-LBSS-5(GIS)
through 1x 50 MVA , 11/11/220 KV Transformers (called T9).
LBSS-1 Load is fed from 220 KV double circuit OH line from LBSS-5 (AIS).
Township Load is fed from MRS through 220 KV/33KV Transformer
LBSS-2, 3, 4, 6 are fed through 220 KV double circuit OH line.
Total Vizag Steel Generating capacity (TPP & CPP) is added = 522.6 MW
46
Category-I (Imported load) of 80 MW, fed from 11KV GSB#1.
Category-I (Imported load) of 30 MW, fed from 33KV GSB#4.
1.3 SCOPE
The safety audit was carried out on the guidelines as mentioned in Indian Standard
IS: 14489 - 1998 on “Code of Practice on Occupational Safety and Health Audit”.
The broad elements covered in the Safety Audit are as under:
The main objectives of the audit were to particularly examine Health & Safety (H &
S) systems prevalent in the Factory, identify potential H & S hazards and suggest
corrective actions wherever necessary. The success of the audit exercise lies in
implementation of the recommendations made in the report. Due care has been
exercised while framing the recommendations to make them simple, practicable,
feasible and thereby workable. It is the responsibility of the top management to
make available the necessary resources to implement the recommendations of this
report.
1.5 METHODOLOGY
47
1.6 OPENING MEETING
As intimated in advance by NSC, there was a meeting with senior officers and audit
team on 20th February, 2019 at 10:00 hr.
The Team made the following points:
In order to check and assess the status of the H & S Management System
prevalent in the plant and facilities, many documents such as safety policy, work
permit system, pre & periodic medical examination records of all employees,
operating & maintenance procedures, inspection schedules & reports and records
of testing of critical plant equipment, earthing systems, fire extinguishers, etc. were
perused.
On 26th February, 2019 at 15:45 hrs a Closing Meeting was organized. Company
executives attended the meeting. The Audit Team presented some important
observations and recommendations in this Meeting. There was a discussion on the
recommendations, which was useful in clarifying the doubts.
48
1.10 Disclaimer:
49
PART – 2
EXECUTIVE SUMMARY
A four member audit team from National Safety Council carried out the Safety audit of
Vishakhapatnam Steel Plant, Vishakhapatnam from 20-26th February, 2019. The
objective is to carry out a critical appraisal of potential hazards at workplace and ensure
that OSH system fully satisfies the legal and other requirements. Indian Standard, IS
14489:1998 was used as a guide.
SAFETY MANAGEMENT
• Most of the statutory requirements are found to be complied with. Factory License,
Boiler License, Petroleum license; chlorine license and Consent to operate the plant
from Andhra Pradesh Pollution Control Board are available in the plant.
• RINL Vishakhapatnam Steel Plant was IMS certified company and all the procedures
were documented in the OHSAS safety manual which was available in the portal of
RINL Company for ready reference of company employees.
• Company was having safety organization for looking after safety aspects of company,
the roles and responsibilities were defined in the safety manual. The qualified safety
officer was available in the company as required under Section 40 B of the Factories
Act, 1948.
• The company has prepared Quality, Health Safety and Environment policy in English &
Hindi version and Signed by occupier in October 2017 however the occupier was
changed in recent past, the policy should be signed by the current Occupier and
copies should be displayed in company premises.
• As Steel industry was listed in Schedule I of The Factories Act, 1948 and having more
than eighteen thousand workers working in the plant. Central Safety Committee was
formed for better co operation between management and workers related to Safety,
health and environment aspects of workers which was required under Section 41 G of
the Factories Act, 1948. The frequency was once in every quarter and tenure was as
per the trade union member’s elections. Departmental safety Committees were formed
under the Head of Departments chairmen’s ship for looking after the shop floor safety ,
health and environment aspects and meetings were conducted every monthly, format
for same was prepared and records were available with most of the departments.
• Safety trainings were imparted to the workers; training calendar for the entire year was
prepared and circulated to all the departments for allocating the participants. After
training imparted feedback was obtained from participants on the subject. This year
external faculty from NSC, Navi Mumbai was called for imparting trainings to the
employees.
• In company First Aid training was imparted to more than one thousand workers and
these were working in shift schedule for attending first aid injury cases inside the
company however out of that some certified first aider were undergone training on year
2015/ 2016 whose refresher training should be planned for being first aider as required
under the statues.
• Hazard Identification and Risk Assessment (HIRA) study has been carried out in the
company for more than five thousand operations to know the hazards and the risk in
the operations. During visit some of the HIRA study was perused it was found that
general safety and use of PPEs were mentioned in the control measures. HIRA study
should be reviewed by incorporating the existing control measures available to
eliminate or reduce the risk within acceptable level such as training, SOP, Interlocks
available, engineering control, administrative control, work permit system etc so that
detailed control measures will be mentioned in the study and study will productive.
• HAZOP study was carried out in year 2015 for most of the departments like BF,
COCCP, EMD, TPP, MMSM etc. The HAZOP study observations compliance report
was not available for all points raised during study.
• More than one thousand numbers of First Aid boxes were provided in the company for
treatment of first aid cases as required under Section 45 of the Factories Act, 1948
however, qualified first aider was available in the company for treating first aid cases.
The content of first aid box was suggested by OHC of six contents. The replenishment
was carried out by certified first aiders.
• OHC was available in the company handled by qualified doctor as required under Rule
61 (SC) B (2) (1) of the AP Factories Rules, 1950. The OHC was available for
conducting periodic medical examinations of workers and in case of emergency the
injured person was treated in the colony hospital. The numbers of doctors required in
the OHC should be as per Rule 61 (SC) (B) (C) (i) of the AP Factories Rules, 1950.
• Three first aid centers and Ambulance vans were available in the company for
treatment and transportation of injured cases at OHC, CO CCP, BF areas respectively.
51
• Periodic medical examinations of workers were conducted in OHC around thirty to forty
workers medical examinations can be conducted daily in the OHC. The frequency of
Periodical medical examinations was defined in the OHC safety manual and
accordingly medical examinations were carried out. The medical test records were
maintained separately in the portal. Each worker was having separate file and access
was given to worker for knowing the medical tests details through person login and
pass word on the portal. In this year out of 8500 workers 8300 workers undergone
medical examinations. As per the diagnosis by OHC for last year periodic medical
examinations there were cases of hypertension, diabetics, anemia, vertigo, ringing in
the years, hearing impairment, refractory errors, Asthma cases etc. Special care or
attention should be given to these cases for maintaining their health.
MECHANICAL SAFETY
• Heat sensing arrangement may be installed along with sprinkler system in coal yard to
take early action to avoid frequent fire which results with lot of air pollution and loss of
coal.
• Safety valves on pressure vessels should be tested regularly and records maintained.
• All the pressure gauges should be marked at SWP with a red mark.
• The guarding of rotating parts of machines was missing in most of the places which
may lead to accidents and positive guarding was required for that survey should be
conducted.
• Standard Operating Procedures were prepared for most of the operations and
available in the departments for ready reference. Some of the SOPs of Emergency
shut down operations were reviewed it was found that general instructions like isolation
valves should be closed however isolation valves numbers were not mentioned, for
making full proof SOP for particular operation specific numbers of isolation valves,
location and blinds etc should be mentioned in the SOP.
• The gas cylinders used stored and handled in the company at most of the
departments. During visit it was found that the cylinders were not properly secured to
avoid fall, end caps were missing and moreover 2007, 2011, 2013 hydro testing due
dated gas cylinders were used inside the company. It was suggested that survey
should be conducted for all the gas cylinders for due date of Hydro testing and make
sure that only valid i.e. hydro tested gas cylinders were used, stored, handled inside
the company premises.
• Vehicles are plying at much higher speed then prescribed speed limit of 30 KM/hr.
52
• Pedestal grinder should be maintained well with respect to gap between wheel & tool
rest and wheel guard. A notice should be displayed near grinder as per statutory
provision under sec 30 of The Factories Act 1948.
ELECTRICAL
• It is suggested to carry out Infrared Thermograph once in 6 month after mapping all
probable hot points. DGA of all HT Transformer is to be done once /year. The DGA
report & all other Electrical test results are to be shared by DNW with all concerned
area HODs for making action plan & trend analysis by individual section.
• Designated Electrical Safety Officer from within the organization is not recorded by
individual department which is required under CEA regulation 2010 number 5.
• Two or more Gas masks shall be provided & installed & maintained at accessible
places in every Generating station with capacity of 5 MW & above and enclosed
substation with transformation capacity of 5 MVA & above for use in the event of Fire &
smoke. Ref CEA Reg 2010, Reg no 27 (4)
• It may be noted that all Transformers of rating 10 MVA & above are to be provided with
HVW spray system (design, installation as per IS 15325) or Nitrogen Injection Fire
Protection System. Ref CEA Regn no 44 (2)(ix). Urgent attention is required for
protection of these Transformers.
• Fire water systems, which are available at cable gallery, may be kept in service.
• Standard Maintenance schedule & Practices (SMP) of all electrical equipments are to
be prepared as per O&M manual & experience of repeated failure if any. This is to be
followed & record is to be kept for reference.
53
• Lockout & Tag out (LOTO) system for Permit work system is not followed. Manual
Permit format is used & a PTW register with all details is maintained. Start LOTO
system
• Electrical Hand tools are to be tested at least once a year either by centralized
Electrical Lab at DNW or by an NABL accredited testing lab & record of the same is to
be kept. Defective tools shall be replaced with new ones immediately
• It was observed that temporary wiring with joints & without plug/sockets is used which
may lead to accidents, follow CEA regulation 2010 for temporary wiring.
• Flame proof light fittings and flame proof enclosure for motor terminal box of exhaust
fan were not used in Battery Room which may lead to explosion due to spark
generation during operation.
• Earth resistance measurement record was maintained in register. But during site visit,
it was found that, many Earth Pits were found not exposed, (buried in earth/debris), not
cleaned, not accessible & not identified & earth resistance measured with date/due
date were not displayed near the pit. It appears that at these locations, the earth pit
resistance was not taken regularly.
• Electrical Zone classification should be carried out for installations of electrical fittings.
• The factory being a steel plant is of High Hazard Fire Occupancy, Sub Category A,
both as per National Building Code and TAC. Compatible with the fire risk, the factory
has adequate fire fighting capability in terms of manpower and other resources.
• The factory is a Major Accident Hazard (MAH) factory due to storage of ‘flammable
gas’ (LD gas) above the threshold limit (>200 MT) as per schedule 2 part 2 of MSIHC
Rules. The factory is in compliance with the requirement as per MSIHC Rules.
• Adequate fire water availability is ensured for more than 4 hours of fire fighting as the
fire water tanks are inter-connected. Automatic starting and stopping systems for
jokey pump and main pump may be implemented for the phase 1 fire water pumps.
• Inspection procedure and up keeping of PFE and fixed firefighting equipment are
good and records are well maintained.
• Fire training attendance for employees is not satisfactory. Fire training plays key role
in prevention of fire at first place, prevention of a large fire by controlling at initial
stage and in rescue & evacuation. A mandatory fire training schedule may be
prepared for all employees and contractor workers. All employees should receive fire
training at least once in a year.
• The Factory may ensure that valid Fire NOC is in place as it was not available for
review.
• As per SMPV Rules every pressure vessel (gas bullets containing O2, N2, Argon.
LPG etc.) Should have label or name plate containing tank number, chemical name,
design pressure, test pressure, etc.
• A tank farm containing 4 gas storage tanks in PRMS 1 may be maintained as per
SMPV Rules if it is in operation. Otherwise, the tanks may be removed or the tanks
may be isolated and a board saying ‘Not in Use’ may be displayed.
• Earthing confirmation system may be installed for class A chemicals loading or LPG
unloading, which will confirm if proper earthing is established. This can be interlocked
with starting of filling pump or unloading compressor.
• The high CO alarm may be made audible in control room also in SMS 1.
• For LPG tankers, safety certificates of tankers, test certificate of safety valves and
excess flow check valves may be checked before unloading. Drivers need to be
trained in transportation of hazardous chemicals as per CMV Rules.
• LPG cylinders discharge manifold area may be provided with leak detectors.
• Dry vegetation in and the gas holder premises may be promptly removed.
• The booster compressor by pass line in GH 2 may be provided with jumpers across
the flanges. The earthing for the line may also be ensured. This is important as the
line may pick up static charges from the ESP.
• Welding job earthing may be provided closest to the job to avoid hazard.
• Dust extractors, wherever not working, may be repaired and more may be installed to
reduce dust pollution in CRMP.
• In Crude and Finished Product Storage area of CCP it is observed that tank roof of
benzene storage tank has holes, some other class A chemical tank roofs are
corroded and vents are open and continuity clamps across flanges are missing in
many places. These may be looked into.
• The factory is in compliance with Consent for Operation by State PCB and
Hazardous Waste Management Rules. The factory may try to achieve zero liquid
discharge. Online real time monitoring system of effluent may be commissioned as it
is a requirement of CPCB.
***
55
OBSERVATION RECOMMENDATION
PART – 3
SAFETY MANAGEMENT SYSTEM
During visit it was found that old The policy should be displayed in a
version of QHSE policy displayed on language understood by majority of
some of the departments which was workers at plant premises.
after some time corrected by concern
person, the policy was displayed in
English version in most of the
departments at few places it was
displayed in local language.
New departments like special bar mill The policy should be reviewed as
etc were formed for different types of often as may be appropriate, but it
products manufacturing. shall necessarily be revised under the
following circumstances, namely
56
OBSERVATION RECOMMENDATION
58
OBSERVATION RECOMMENDATION
The last two safety committee meeting All the observations raised during
was held as per following dates. safety committee meeting should be
completed as per the target dates and
06/12/2018 in which total fourteen records should be documented for
points were raised and around nine verification.
points were complied.
59
OBSERVATION RECOMMENDATION
Safety inspections were carried out by It was suggested that the safety
Zonal safety officer and Departmental inspections should be carried out by
Safety Coordinator mostly at shop head of departments regularly so that
floor unsafe acts and unsafe the actual conditions at shop floor was
conditions were found out. The known to them and corrective actions
procedure for safety inspections was can be taken on priority.
documented.
The total accidents happened in VSP The statistics shows that the
including contract workers are as per reportable incidents were happened
following: every year, company should focus
about reducing the reportable
year NR RE Fatal accidents for that nearmiss accident
17/18 12 11 0 reporting at shop floor should be
16/17 23 07 06 enhanced.
15/16 10 11 03
14/15 03 13 05 Nearmiss accident reporting is an vital
tool to find out the unsafe act and
During visit we found that less number unsafe condition which may lead to
of nearmiss accidents was reported. fatal accident hence educate and
trained the shop floor workers for
reporting of nearmiss accidents and
good nearmiss accident reporting may
be rewarded to motivate the workers.
3.6 SAFETY EDUCATION & TRAINING (INCLUDING FIRST AID AND FIRE
TRAINING )
training program.
The faculty for imparting training was This is a good practice to involve the
internal as well as external faculty was external faculty for imparting the
also called from organization like training to company workers so that
National Safety Council, Mumbai. the good practices and advance
techniques which was being at other
company will be shared to the workers
and these good practices can be
implemented at site.
The first aid training was imparted to Survey should be carried out for
around 1153 numbers of employees refresher first aid certified training of
from different departments through these workers and fresh training
Saint John Ambulance agency should be arranged for them.
however during visit we found that the
refresher first aid training was required
to be arranged as the validity of first
aid training was expired for example
the first aid training was imparted in
year 2015/2016 for workers which was
not rearranged.
To promote safety and health in the In order to improve the Safety &
plant, the National Safety Day was Health awareness among employees
celebrated in the plant on 4th March. these campaign, observance &
motivation programmes should be
Last Safety Day/week was celebrated conducted in future also.
from 4 to 10th March 2018.
operations (around five thousand reduce the risk within acceptable level
operations activities HIRA study such as training, SOP, Interlocks
conducted) to know the hazards and available, engineering control,
the risk in the operations however few administrative control, work permit
Operations HIRA study was checked system etc so that detailed control
at BF plant it was found that HIRA measures will be mentioned in the
study was having three by three study and study will productive.
matrix, In study general safety
practices such as use of PPEs were The HIRA study should be known to
considered as a control measures. the concern workers who were
working on the operation. This HIRA
study will provide the information
about Hazards’ available during the
operations, what will be the risk and
what are the control measures
available to reduce the risk.
Every department was having their The copy of safety manual should be
departmental safety manual in portal easily accessible to workers.
of RINL Vishakhapatnam.
AR items 4.3 cr
Non AR items 2.0 cr
respectively.
This was the first time National Safety There was necessity to conduct
Council; Navi Mumbai has conducted structured safety audit to assess the
the external safety audit for year safety standard of the Company
2018/2019. Unless audit was done an
organization cannot prepare effective
plant safety management programme
of their organization. As such internal
67
OBSERVATION RECOMMENDATION
Company has provided more than As per Section 45 of the Factories Act,
eleven hundred first aid boxes at 1948.
different departments for attending
first aid cases at site level. First-aid appliances.
The OHC doctor has suggested six 1) There shall in every factory be
contents for first aid boxes as three provided and maintained so as to
numbers of First aid centers were be readily accessible during all
provided at the company premises. working hours first-aid boxes or
cupboards equipped with the
The first aid boxes were replenished prescribed contents, and the
by the certified first aiders and number of such boxes or
frequency of replenishment was cupboards to be provided and
defined in the OHC safety manual. maintained shall not be less than
The names of the first aiders were one for every one hundred and fifty
displayed near the wall of the most workers ordinarily employed 1*[at
departments with contact numbers, any one time] in the factory.
they were available in each shift
however during visit some first aiders 2) Nothing except the prescribed
was undergone first aid training in contents shall be kept in a first-aid
year 2015 but refresher first aid box or cupboard.
training was not arranged for them.
3) Each first-aid box or cupboard
There were three first aid centers also shall be kept in the charge of a
provided for attending first aid cases, separate responsible person
The first aid center was attended by 3*[who holds a certificate in first-
an MBBS doctor, male nurse 24X7. aid treatment recognized by the
One doctor was available to attend the State Government] and who shall
cases. always be readily available during
the working hours of the factory].
The OHC was handled by Doctor This is in order as per Rule 61 (SC) B
Madhavi (MD and AFIH) thus having (2) (1) of the AP Factories Rules,
the required qualification as per the 1950.
AP Factories Rules, 1950.
There were four doctors available in The number of doctors at OHC shall
the OHC and first aid centre for be, as per Rule 61 (SC) (B) (C) ( i ) of
treatment of workers in case of injury. the AP Factories Rules, 1950
OHSAS OHC safety manual was Ensure that these procedures should
available on portal in which sixteen be known to the operating staff for that
work procedures for OHC (QSHE-P- Periodic trainings may be arranged on
OHS revision dated 11/2/2018) was these procedures for refreshing the
defined out of sixteen procedures on knowledge of operating staff.
procedure was universal procedure for
needle stick injury/ accident for
exposures also available for ready
reference.
The colony hospital was having the This is in order as per BMW Rules,
Consent and authorization number 2016.
18145/APPCB/ZO-VSP/CPO/W &
A/2018-318 dated 02/06/2018 Bio
medical authorization under Rule 10
of Bio Medical Waste Management
Rules, 2016.
70
OBSERVATION RECOMMENDATION
The total staff of the OHC was Maintain staff as per the Rule 61 (SC)
sixteen. Fourteen numbers were staff (B) (C) of the AP Factories Rules,
and two numbers were male nurse 1950.
attendants.
Two LPG cylinders were used which These LPG cylinders should be
last hydro tested in year 2007 and till immediately replaced with new hydro
date it was being used in the tested cylinders.
laboratory.
Total nine filled and one empty Survey should be conducted in the
cylinder were stored in the ward room OHC and in company for hydro test
near the door however it was found date of gas cylinders. Ensure that the
that the one oxygen cylinder last tested gas cylinders were used in the
hydro tested in 2010 but still it was company premise which was required
being used in the OHC ward room. as per Gas cylinders Rule, 2016.
As per the diagnosis by OHC for last Special care has to be taken for these
year periodic medical examinations cases to avoid further detoriation of
there were cases of hypertension, health.
diabetics, anemia, vertigo, ringing in
the ears, hearing impairment,
refractory errors, Asthma cases etc.
It was informed by the doctor that the Ensure that the eye vision testing was
eye vision was checked by the carried out the qualified person as
optometrist at the OHC. required under the AP Factories
Rules, 1950.
the plant.
Mock Drill
preparedness.
For 2017 and 2016 only one Mock drill Being a statutory requirement all Mock
report for each year are available. Drill records should be preserved and
available for review.
Mutual Aid
***
77
OBSERVATION RECOMMENDATION
PART – 4
MECHANICAL & PHYSICAL HAZARDS
During visit it was found that in most The identification nos. should be given
of the departments the No and test certificates should be issued
identification nos. is given to pressure as per identification number.
vessels.
The test details like SWL, Test Date, The test details should be displayed
Due date etc were not displayed on on the pressure vessels like Id No.,
some of the pressure vessels. Capacity, SWP, Test date, Hyd. Test
Pressure and Next due date.
Coal & Ore handling tipplers are Warning lights at each tippler may be
installed in two sheds and are in considered at the time of tippler
operation. operation for additional safe operating.
Barricading at common shaft to be
installed. Barricading at both ends
required being potential tripping
hazards
List of pressure vessel and hydro test It is in order. Compliance as per Sec.
report by competent person is 31 of FA 1948.
available in MMSM.
Pressure gauges are not marked for Pressure gauge installed on vessels
Max. Safe working pressure in WRM- should be marked with Red mark for
1, WRM-2, SBM, Structural Mill, Max. safe working pressure.
LMMM & MMSM.
In TPP the air receivers which were It should be tested and results should
not tested as per the section 31 of the be displayed on the air receivers.
Factories Act, 1948.
Jack is available. Load test certificate indicating test date & next due date.
from competent authority is available
in WRM-1.
EOT Cranes-17 Nos. and Jib Cranes- All the EOTs, Jib Cranes and other
14 Nos. are in operation in SBM. lifting tools should be load tested by
However the load test of the cranes by competent person and maintain the
the competent person is overdue. record. Compliance is not there as per
Similarly other lifting tools such as Sec. 29 of FA 1948.
Chain pulley block, wire rope slings,
D-shackles etc, required to be load
tested and record maintained.
List of EOTs and lifting tools & tackles Compliance as per Sec. 29 of FA
are available in MMSM. The load test 1948. Display board required for Test
certificate issued by competent person date and next due date on all EOTs.
is available. Eye test records for crane operators
are available.
The test details are not displayed on The test details should be displayed
lifting machines. on all lifting machines. ID No., SWL,
Test date, Test load, Next due date
should be written.
during visit it was found that hook All the hooks should have safety latch
latch on some of the hooks of EOT for locking the sling.
Cranes, chain pulley blocks, Hydra
etc. were missing
The gas cylinders were not properly All the gas cylinders should be kept
secure to avoid fall of gas cylinders. vertically in a shed with proper
chaining arrangement to avoid fall.
Gas cylinders were lying on the floors
and at few places filled and empty
cylinders were stored together.
At cutting and welding sets flash back Flash back arrestors should be
arrestors were not provided at both provided on both the ends of gas
the sides (torch end and gas cylinders cutting and welding sets to avoid back
end) to avoid back fire till the source. fire.
In many places the gas cylinders Survey should be carried out in the
hydro tested date was over even company for all gas cylinders and due
though they were being used in the dates gas cylinders hydro testing
company. should be carried out & then only
these cylinders should be used which
was required as per Gas cylinders
Rules, 2016.
RMHP
Coal & Ore handling tipplers are Warning lights at each tippler may be
installed in two sheds and are in considered at the time of tippler
operation. operation for additional safe operating.
Barricading at common shaft to be
82
OBSERVATION RECOMMENDATION
Cable cellar man entry is partially Cable cellar man entry area to be
open at coal tippler shed. barricaded to avoid accidental
slippage.
Coal conveyor 28 & 29; tail pulley side Side area of conveyor should be
area is open. covered to avoid accident.
LPG hose and welding machines is in Welding machine should be kept away
close proximity leading unsafe from LPG supply points.
situation in CCS.
Due to positioning of scrape bin, path Scrap bin should be shifted to other
is obstructed and someone head may location to avoid possible head injury.
hit canopy.(Photo below)
Uptakes gas pipe lines at 45 mts. Uptakes gas pipe lines should be
elevation is potential hazard for burn provided protection from burn.
at BF-3.
Monkey ladder (for hot blast valve Monkey ladder (for hot blast valve
telfer) cage is not as per standard & telfer) cage should be extended down
potential safety hazard at BF-3. to avoid accidental fall.
Area is exposed at both sides along Barricading at both sides along the
the moving bed. exposed area to be provided.
Water pipes at low elevation on Display board for taking care of Head
platform above A6 conveyor are should be available.
potential safety hazard for head injury.
Fence cover for rotating parts at Roll Compliance as per sec 21(i) of FA
Chock not there WRM-2. 1948 is not there. Fence cover should
be installed at Roll Chock as safety
measure.
End stoppers for transfer cars are End stoppers for transfer cars should
potential tripping hazard at Special be properly covered to avoid tripping
Bar Mill. hazards.
Open area at roller table after shear Provide barricading for safety.
No.3 at Structural Mill.
Partial ramp near stand 17 to avoid Provide ramp in the entire width.
tripping hazards at Structural Mill.
Tilter in front of stand No.7 is exposed Tilter in front of stand No. 7 should be
to movement of workers at Structural provided with hooter and beacon light
Mill. for safety during its operation.
Hot bloom rejection area is open at Provide barricading and display board
Structural Mill. that rejected material is hot and do not
touch.
Pusher end of furnace 1 & 2 is open & Provide barricading to avoid accident.
unsafe at MMSM.
End stoppers are potential tripping End stoppers for transfer cars to be
hazard at MMSM. covered to avoid tripping when not in
use.
Stair case leading to scale tunnel is Stair case leading to scale tunnel to
unsafe at MMSM. be blocked (Near column no. 45) if not
in use to avoid incidental fall.
Drains at all exit points (3 Nos.) are Provide cover on drains at all exit
not covered at SMS-2.(Photo below) points for safety.
Cross over platform are not provided Provide railing at cross over platform.
with railings after plant 21 at Special
Bar Mill.
86
OBSERVATION RECOMMENDATION
High level of noise observed near ID Noise survey required for the area
Fans in ID Fan House at SMS-1. near ID Fans. Display board for “high
noise -use of ear plugs near ID Fan”
should be installed in ID Fan House.
Illumination is not upto the mark in the More lights may be provided after
area in SP-1. proper illumination survey which is
pending.
Illumination survey record for day time Illumination survey should also be
survey is available in LMMM. done at late evening.
Lighting is very poor on all the floors in Additional lights based on Illumination
Junction House 5 in RMHP. survey.
89
OBSERVATION RECOMMENDATION
4.12 HOUSEKEEPING
90
OBSERVATION RECOMMENDATION
Shunting Porters are wearing not May visit “Safety Standard on Loco
Retro-reflective jacket in Traffic. Operation in Steel Industry- IPSS:1-
11-033-17” adopted in January 2017
for required improvement. Retro-
reflective jacket for Shunting Porter
may be considered for easy
identification. Many safety precautions
listed may be reviewed for adoption as
required.
Company was having work permit The work permit was a written
system to work on any job. statement given by the concern
person that the work can be executed
The validity of the permit system was as the necessary isolations were done
mention on the permit was one day, if and safe to work. It should be
any work was required extension then followed.
the permit was extended by the
authorized person.
During visit we checked the filled work All the details asked in the Work
permit copies, it was found that all permit format should be filled fully as it
permit columns were not filled, was for the safety of the people
concerned person signature was not working on the job.
91
OBSERVATION RECOMMENDATION
Speed limit boards are not available Speed limit boards should be visible
on road side. along the road.
92
OBSERVATION RECOMMENDATION
Two wheeler persons are not using Helmet should be made compulsory &
helmet and sometimes three persons not more than two persons should be
are riding. allowed to move on two wheelers.
***
93
OBSERVATION RECOMMENDATION
PART – 5
CHEMICAL & PROCESS SAFETY
There is no training given to the The drivers may be given on the spot
drivers in the factory. training/ advice regarding handling of
hazardous chemicals.
HIRA study has been carried out for Now a day’s Central Electricity
twenty five activities of the QATD but Authority Regulation 2010 was used in
in this study the legal requirement of INDIA instead of IE Rules, 1956 hence
IE rules were considered. the legal requirement as per CEA
2010 should be considered in HIRA
study.
If any chemical spilled on the floor Emergency spill kit should be provided
then it was cleaned with the help of at laboratory for handling the spillage
cotton and then placed in the dust bin. of hazardous chemicals in the
laboratory.
Laboratory worker was not aware Ensure that the working staff should
about the hazardous properties of the be having knowledge of hazardous
chemicals handled during the titration chemicals properties and first aid
work. measures in case of spilled on body
part.
Eye washer and safety shower was Eye washer and safety shower was
provided in the corridor of the necessary in case of any chemicals
laboratory premises but there was no were spilled on the body part hence it
water flow coming from same. should be always in working condition
as it was considered as emergency
handling equipment.
During visit it was found that the PFEs All PFEs should be installed on the
were placed on the floor and the wall as required under AP Factories
combustible materials were stored Rules and fire potential materials
inside the panel box number 34 of should not be placed in the electrical
electrical supply which may lead to panel boards.
fire.
A color code is used for the chemical Pipelines may be painted using color
lines in the factory. The code followed code as per IS 2379 (1990).
is not strictly as per IS 2379 (1990) in
all places. In one area in LPG tank
farm LPG pipeline is seen painted in
violet color.
***
97
OBSERVATION RECOMMENDATION
PART – 6
FIRE PREVENTION, PROTECTION AND MITIGATION
A. The factory being a steel plant is of The factory has adequate fire fighting
High Hazard Fire Occupancy, Sub capability in terms of manpower and
Category A, as per para 7.2.3 of other resources compatible with the
TAC Fire Protection Manual. fire risk.
i) A steel plant
ii) Has bulk storage of flammable
liquids
iii) Engaged in manufacturing
chemicals with F.P. <230 C.
The Fire department in the Factory is Fire department is well organized and
managed and manned by CISF. There all team members are adequately
are totally 246 CISF personnel qualified.
engaged in the Fire Department. The
organizational set up for Fire
Department is:
98
OBSERVATION RECOMMENDATION
GM (SHE)
6 Inspectors
1) Fire coy commander & In-
charge of Main Fire Station
2) Fire Store
3) Fire Operation
4) In-charge CO-CCP Fire Station
5) Fire MT section
6) Fire Prevention & In-charge of
New Fire Station
Sub-Inspector (2)
ASI (2)
99
OBSERVATION RECOMMENDATION
6.3 FIRE STATION, FIRE TENDER, FIRE HYDRANT SYSTEM & MONITORS,
There are 3 fire stations in the factory, The fire hydrant system is adequate
viz, the Main Fire Station, CO-CCP and well maintained.
Fire Station and New Fire Station. All
are manned in 24X7.
There are 28 fire water pump houses Adequate fire water availability is
in different locations in the factory. All ensured for more than 4 hours as the
pump hoses have electrical main fire water tanks are inter-connected.
pump, diesel pump and jockey pumps.
• LMMM oil cellar 7 foam flooding In LMMM oil cellar 7 foam flooding
system. It is observed that foam is system may be reviewed as the foam
unable to flood the oil tanks as the is unable to flood the tank and
area is not closed. The plant area is spreading on floor only.
poorly illuminated.
101
OBSERVATION RECOMMENDATION
102
OBSERVATION RECOMMENDATION
The following fire related documents This OK. Records and documents are
have been reviewed: well maintained in Fire Station.
• Fire Order
• Fire manual
• Fire call register
• Hydrant layout
• Maintenance record for PFE and
fixed firefighting equipment
• HPT certificates for extinguishers,
etc.
Fire NOC for the factory was not The Factory should ensure that valid
available for review. Fire NOC is in place.
***
104
OBSERVATION RECOMMENDATION
PART – 7
ELECTRICAL SAFETY
Sufficient number of First Aid Boxes Address & Tel no of nearest doctor,
are not provided & maintained at ambulance service & fire service is to
appropriate locations. Ref CEA Reg be displayed near chart & near First
2010 no 27(3) & IS: 13115. aid box.
107
OBSERVATION RECOMMENDATION
All Designated Person (s) are not At least one designated person must
trained in CPR & First Aid & the list of be available in a shift who is trained in
such persons are not entered in a CPR & First aid
register.
system)
• Many Fire buckets are found empty. • Fire Buckets, filled with clean dry
sand, in addition to fire
extinguishers, are to be marked &
kept in every enclosed substations
& switching stations in convenient
location. Ref CEA Reg 2010, Reg
no: 27(1)
• The locations of fire extinguishers & • The locations of fire extinguishers &
first aid boxes, Gas masks & first aid boxes, Gas masks &
artificial Respirator are not artificial Respirator shall be
displayed & Artificial respirator is not displayed in the control room &
provided operator cabin.
attended.
• Cable entry/exit holes are not • Power & control cable entry/exit
sealed with fire resistance paste holes at floor or wall, are to be
sealed with fire resistant paste to
prevent propagation of fire from one
location to another location
• It was observed that Fire water • Fire water systems, which are
system is available at 11 KV cable available at cable gallery, may be
gallery of TPP, but it is NOT kept in kept in service.
service
Lockout & Tag out (LOTO) system for Start LOTO system. Requisition Copy
Permit work system is not followed. (either red or blue) of PTW form may
Manual Permit format is used & a be kept on a separate file, after
PTW register with all details is completion of job & signature by
maintained. concerned designated person(s). It is
suggested to review PTW format for
Caution tag is used at electrical supply introducing column for mechanical
source, but in some cases without isolation or Gas isolation, if any.
PTW number or name of person who
Issued or received the PTW. PTW is
issued after getting written clearance
from Operator of equipment on the
PTW format. In some cases, white
copy of PTW is not signed after
cancellation & normalization
Electrical Hand tools like Insulation Electrical Hand tools are to be tested
Tester- 500V & 5 KV, Hand gloves, at least once a year either by
pliers, spanners, Multimeters are centralized Electrical Lab at DNW or
used by Electrical operator for by an NABL accredited testing lab &
testing/isolation/normalization. record of the same is to be kept.
No record regarding testing of all Defective tools shall be replaced with
these instruments are found during new ones immediately
111
OBSERVATION RECOMMENDATION
Electrical Arc Flash suit are not used Electrical Arc Flash suit should be
during Isolation/Normalization of used during Isolation/Normalization of
Electrical supply Electrical supply
112
OBSERVATION RECOMMENDATION
It is observed that, flame proof light These fittings are to be used in areas
fittings and flame proof enclosure for where flammable /petrochemical/oil
motor terminal box of exhaust fan are vapors and/or pulverized coal dust
not used in Battery Room exist or potential to exist, so that
explosion or flames may be produced
within them due to arcs, sparks while
switching the lights) Flame proof
Equipments/motors are designed to
withstand any damage due to the
pressure caused by an internal
explosion & also to prevent flame
propagation outside.
Insulation stick.
It was observed that at TPP Ref: CEA Reg 2010, Sec 19(2),
switchyard, Safety helmet & safety
shoes are not used by contractor Every person who is working on an
Employees during shutdown bay electrical supply line or apparatus or
maintenance work on 21 Feb 2019. both shall be provided with PPE, tools
& devices such as rubber gloves (IS
4770) suitable for working voltage,
Safety footwear (IS 15298), safety
belts for working at height (IS 3521),
non conductive ladder, earthing
devices of appropriate class, helmet
115
OBSERVATION RECOMMENDATION
117
OBSERVATION RECOMMENDATION
118
OBSERVATION RECOMMENDATION
• SLD at all electrical locations are not • It is suggested to fix Single Line
available Diagram (SLD) of Electrical system
at all switchgear room & substation
& operator’s control room.
120
OBSERVATION RECOMMENDATION
121
OBSERVATION RECOMMENDATION
***
122
OBSERVATION RECOMMENDATION
PART-8
AREAWISE OBSERVATION
Coal & Ore handling tipplers are Warning lights at each tippler may be
installed in two sheds and are in considered at the time of tippler
operation. operation for additional safe operating
Barricading at common shaft to be
installed
Workers found not using Hand gloves Hand gloves & dust mask should be
& dust mask while there are lot of used by the workers engaged in
dust. manual handling & cleaning.
Cable cellar man entry is partially Cable cellar man entry area to be
open at coal tippler shed. barricaded to avoid accidental
slippage.
Lighting is very poor on all the floors. Additional lights based on Illumination
survey.
123
OBSERVATION RECOMMENDATION
Coal conveyor 28 & 29; tail pulley side Side area of conveyor should be
area is open. covered to avoid accident.
The pull cord was not available on the Pull cord was a safety device provided
conveyor belt number 48, 45 of coal on the conveyor belt for emergency
yard and only hydrant points were stop it should be provided on all
provided nearby conveyors as fire conveyors wherever missing for that
fighting media. survey should be carried out.
124
OBSERVATION RECOMMENDATION
There are total 3 Nos of BOF BOF has adequate in built process
converters, operations of which are safety.
controlled in 2 control rooms with
DCS. 4 CCTV are provided to each
converter. Converters are visible from
control room through IR proof glass
windows.
Old drums, replaced equipment and Housekeeping in the ID fan area may
pipes are seen lying in ID fan area. be improved.
Fixed CO meters are provided in each The high CO alarm may be made
floor. The hooter for high CO alarm is audible in control room also.
audible only in field and not in control
room.
Material is lying all around and area Area requires proper stacking of
requires housekeeping. material and housekeeping to provide
safe environment.
126
OBSERVATION RECOMMENDATION
High level of noise observed near ID Noise survey required for the area
Fans in ID Fan House. near ID Fans. Display board for “high
noise -use of ear plugs near ID Fan”
should be installed in ID Fan House.
127
OBSERVATION RECOMMENDATION
PRMS 1
The cylinders are mostly not secured Gas cylinders stored vertically may be
128
OBSERVATION RECOMMENDATION
Drains at all exit points (3 Nos.) are Provide drains to cover at all exit
not covered.(Photo below) points for safety.
Permit system- Permits are cleared by May be reviewed and Permits records
129
OBSERVATION RECOMMENDATION
LPG hose and welding machines is in Welding machine should be kept away
close proximity leading unsafe from LPG supply points.
situation.
On EOTs, test date and next due date On all EOTs, test date and next due
are not displayed. date should be displayed.
Due to positioning of scrap bin, path is Scrap bin should be shifted to other
130
OBSERVATION RECOMMENDATION
obstructed and someone head may hit location to avoid possible head injury.
canopy.
Two wheelers are parked inside the Vehicles should not be allowed to park
plant. Even one four wheeler also inside plant area.
seen parked inside the plant.
• Charged Panel doors are found It should be closed to avoid any short
open. Lizard/rat may enter to cause circuit or person can come in contact
flashover with live supply.
BF-3
The plant has pulverized coal injection The plant has adequate in built
system which is energy efficient. The process safety. The safety systems
energy from top gas recovered in top may be maintained in future also.
gas turbine. The BF gas is sent to gas
network at 1200 mm H2O.
Uptakes gas pipe lines at 45 mts. Uptakes gas pipe lines should be
elevation is potential hazard for burn. provided protection from burn.
Monkey ladder (for hot blast valve Monkey ladder (for hot blast valve
telfer) cage is not as per standard & telfer) cage should be extended down
potential safety hazard. to avoid accidental fall.
EOT-2 Nos.( 35Ton/10 Ton) are for It is in order. Load test certificate from
second floor operation. competent person is available.
EMD
Gas Holders
The gas holders have 3 Nos of online Good system to be maintained and
oxygen analyzers between the ID Fan calibrated as per the schedule.
and Gas Holder to eliminate possibility
of oxygen ingress.
Dry vegetation is observed in and Dry vegetation in and the gas holder
around the premises. premises may be promptly removed.
134
OBSERVATION RECOMMENDATION
Gas system
The gas system is maintained at 1200 The gas system has adequate safety
mm H2O line pressure using booster considered in detail engineering.
compressor and pressure control
valves. The SOPs may be followed and
system be maintained in future also.
The line pressure is controlled by
pressure control valves set at 1200
mm H2O. The discharge of control
valve is released through flare stacks.
There are 3 such flare stacks in the
system.
Coke Oven
The plant was commissioned 1989 This is good and may be maintained in
135
OBSERVATION RECOMMENDATION
CCP
136
OBSERVATION RECOMMENDATION
Following points are observed in the As per Petroleum Rules, for Class A
tank farm: petroleum storage, following may be
looked into:
• No wind sock is seen in the location. • A wind sock may be provided near
the tank farm.
• Tank farm fencing is open in some • The licensed premise should have
sections and second gate is not continuous fencing with two gates.
provided.
• Vent nozzles in some tanks are • Tank vents may be kept closed.
open.
Hydrogen plant: Jumpers (bonding for All hydrogen line flanges may be
static electricity) across the flanges provided with continuity clamps or
are missing in many places in jumpers as the flammability range of
hydrogen gas lines. Hydrogen was 4 to 74 % if any spark
generated then it can be explosion/
fire.
• Lot of hanging cables seen in the • The loose cables may be properly
tank farm clamped in cable trays.
SINTER PLANT-1
Area is exposed at both sides along Barricading at both sides along the
the moving bed. exposed area to be provided.
Illumination is not upto the mark in the More lights may be provided after
area. proper illumination survey.
138
OBSERVATION RECOMMENDATION
Hot material coming out from spillage Ensure workers use proper PPEs
hopper of Cinter Single Roller before starting the job.
Crusher. Workers were at job for
removal of hot material without proper
safety precautions.
Water pipes at low elevation on Display board for taking care of Head
platform above A6 conveyor are should be available.
potential safety hazard for head injury.
Lot of dust seen around in plant. As there were lot of dust around,
necessary precautions such as using
dust mask by working person should
be mandatory to use.
Pressure gauges are not marked for All the pressure gauges should be
Max. safe working pressure. marked with RED mark for Max. SWP.
140
OBSERVATION RECOMMENDATION
List of EOTs, wire rope slings, D- This is in order. Install display board
shackle, Chain pulley block, Hydraulic on EOTs indicating test date & next
Jack is available. Load test certificate due date.
from competent authority is available.
Pressure gauges are not marked for Pressure gauge installed on vessels
Max. Safe working pressure. should be marked with Red mark for
Max. Safe working pressure.
Safety board in front of FRM not Display board for safety instruction in
available. front of Fast Roughing Mill (FRM).
Fence cover for rotating parts at Roll Fence cover should be installed at
Chock not there. Roll Chock as safety measure.
Safety board is not available near Provide display board near TSIRT as
TSIRT. reject material is hot.
141
OBSERVATION RECOMMENDATION
EOT Cranes-17 Nos. and Jib Cranes- All the EOTs, Jib Cranes and other
14 Nos. are in operation. However the lifting tools should be load tested by
load test of the cranes by the competent person and maintain the
competent person is overdue. record.
Similarly other lifting tools such as
Chain pulley block, wire rope slings,
D-shackles etc, required to be load
tested and record maintained.
End stoppers for transfer cars are End stoppers for transfer cars should
potential tripping hazard. be properly covered to avoid tripping
hazards.
Cross over platform are not provided Provide railing at cross over platform.
with railings after plant 21.
Flash back arrestors are not provided Flash back arrestors should be
at cylinder ends- is potential safety provided at both ends (Cylinder side
hazards. as well as torch side) in cutting set.
Two oxygen cylinders were used Valid Hydro tested gas cylinders
which hydro test was valid up to 2016. should be used in the company.
Two pin was not used for industrial fan Two pin should be used for industrial
and moreover two supplies was given fan. Standard practice for supply
143
OBSERVATION RECOMMENDATION
from one button making the system should be followed in the company to
overloaded. avoid any incident due to wrong
practice followed.
In furnace gas was used but color Color code of pipe lines should be
code of pipelines was not displayed in displayed for awaring the workers in a
the respective areas for ready language understood by majority of
reference. workers.
STRUCTURAL MILL
EOT Cranes and Jib Cranes-30 apart It is in order. Install display board on
from manual chain hoist are in use. All EOTs indicating test date & next due
are load tested by the competent date.
person and records are available.
Open area at roller table after shear Provide barricading for safety.
No.3.
Partial ramp near stand 17 to avoid Provide ramp in the entire width.
tripping hazards.
Tilter in front of stand No.7 is exposed Tilter in front of stand No. 7 should be
to movement of workers. provided with hooter and beacon light
for safety during its operation.
Hot bloom rejection grid may be Provide barricading and display board
approached as area is open. that rejected material is hot and do not
touch.
Flash back arrestors are not provided Flash back arrestors should be
at cylinder ends- is potential safety provided at both ends (Cylinder side
hazards. as well as torch side) in cutting set.
Below stacker lot of water was logged Drainage system should be checked.
on the floor.
As per information safety valves are Safety valves testing records should
tested, however records are not be maintained.
maintained.
List of EOTs and lifting equipment and It is in order. Display board required
load test certificate in Form No. 38 for Test date and next due date on all
issued by competent person is EOTs. Eye test records for crane
available. operators are available.
Scale chute of pump house 17 is Provide proper barricading to avoid
potential safety hazard. accidental slippage.
Illumination survey record for day time Illumination survey should also be
survey is available. done at late evening.
MMSM
Pusher end of furnace 1 & 2 is open & Provide barricading to avoid accident.
unsafe.
End stoppers are potential tripping End stoppers for transfer cars to be
hazard. covered to avoid tripping when not in
use.
Lighting inside the mill seems to be Action should be taken to improve the
inadequate. lighting based on the illumination
survey.
Stair case leading to scale tunnel is Stair case leading to scale tunnel to
unsafe. be blocked (Near column no. 45) if not
in use to avoid incidental fall.
Sampling saw area is unsafe as lot of Caution board required near Sampling
spark during cutting operation. Saw Area & Cooling Bed Area to
avoid any accident.
TRAFFIC
Oil drums & empty drums are lying Proper area should be developed for
and there is no proper area marked. used oil drums and for empty drums.
Fire extinguisher and first aid box are
available in loco.
147
OBSERVATION RECOMMENDATION
Vehicle fitness certificate is available. All vehicles should be checked for its
However the condition of vehicle condition for enhance safety.
found to be not up to mark.
No first aid box and fire extinguisher First aid box should be available in all
vehicles.
Hoist limit switch is not working which Hoist limit switch should work as it is
is safety hazard safety device.
Fire extinguisher and first aid box not Fire extinguisher should be kpt in
available. crane.
ENVIRONMENT
L&H
149
OBSERVATION RECOMMENDATION
GENERAL OBSERVATIONS
• Two wheelers are parked inside the Vehicles should be made to park in
plants which is unsafe. parking area only.
• Vehicles are plying at much higher More speed limit boards should be
speed then prescribed speed limit. installed & department should take
initiative to educate workers.
RS &RS
DNW
150
OBSERVATION RECOMMENDATION
TPP
• Dry Grass inside outdoor yard is to • Dry grass should be cut which was
be removed immediately potential for fire.
• Bus duct silica gel to be changed. • Bus silica color was changed hence
it should be replaced.
In main control room lighting is not Lighting should be improved inside the
proper. control room.
No trip bypass register was available Separate register may be prepared for
however abnormal cases of bypass same.
were noted in the logbook but no easy
record perusal.
151
OBSERVATION RECOMMENDATION
AHU system was not working it was To maintain fresh air/ air changes at
under break down. working area AHU should be made
operational at the earliest.
Pull cord was not available on total Pull cord should be provided on the
conveyor belt number 133 cc. conveyor belt and lot of coal dust was
lying on the conveyor belt surrounding
area it should be cleaned.
Manual call point was not working in Non working MCPs survey may be
the boiler area. carried out in the plant and same
should be attended as it will be useful
for declaring fire emergency.
152
OBSERVATION RECOMMENDATION
During visit it was found that the water The area should be cleaned and water
was logging in the loading area. logging should be attended. As the
person has to go on the vehicle for
operation of the manhole life line may
be fixed and safety belt should be
provided to avoid fall of person as the
height was more.
Oxygen cylinder which hydro testing Gas cylinder Rules, 2016 regarding
was last carried out in 2015 was in hydro testing of gas cylinders should
use and it was lying on the floor. be strictly followed to avoid any
emergency.
One chlorine detector was provided The setting level should be lowered to
near chlorine tonner for leak detection 0.5 ppm from 1.2 ppm as the revised
however it was set on 1.2 PPM. TLV laid down is 0.5 ppm in the
Second Schedule to the Factories Act,
1948 as well as ACGIH-2013.
The water supply line was taken from The fire water should be used for
fire water network. emergency handling only its use for
other purpose should be stopped.
Wind sock was not available on the Wind socks should be provided for
chlorination building to know the wind knowing the wind direction.
direction.
modeling was carried out but the dispersion modeling effects for
working staff was not aware of same. enhancing the awareness of workers.
The person was working was knowing The SCBA set should have the
the leakage handling procedures. maximum pressure inside so that it
can be utilized for maximum time in
case of emergency.
Utilities
ASU 5:
Visited ASU 5. The gas bullets As per SMPV Rules every pressure
containing oxygen, nitrogen and argon vessel should have label or name
are installed in licensed premise as plate containing tank number,
per SMPV rules. chemical name, design pressure, test
pressure, etc.
License numbers are displayed at the
fence or gate.
LPG storage
The LPG tankers unloading instruction LPG tanker before unloading may be
(in display) does not mention to check checked to confirm if proper test
safety certificate of the tanker (like, certificates for tanker, safety valves
test certificate of tanker, safety valves and excess flow check valves are
and excess flow check valve etc.) available. The driver should also be
qualified to transport hazardous
chemicals.
WMD
Observations:
• Lot of sludge in noticed in the SMS • VSP may try to achieve zero liquid
2 waste water treatment plant. discharge.
• The Factory has valid Consent for • Waste water sludge may be
Operation for water pollution and collected in a truck trailer without
authorization for hazardous waste allowing it fall and spread in the plant
management from state PCB. area.
• The Factory has submitted the • Annual returns as per Consent for
annual returns, Form 5, for water Operation meet the legal
pollution as per Consent for requirement.
Operation for the year 2017-18. The
concentration of pollutants in trade
effluent is within the prescribed
standard.
CRMP
• Eye washers are hardly seen in the • In view of high dust, eye washers
plant. may be placed in suitable locations
(avoiding lime area).
156
OBSERVATION RECOMMENDATION
There were five empty carbon di oxide It should be stored in designated area
cylinders stored but not chained. and should be properly secured to
avoid fall.
Lot of empty drums were stored near These drums should be discarding
AB bay. through proper channel and area
should be made free.
Resin sand drums were stored without Trays should be provided below such
trays to restrict the spillage and drums.
avoiding the soil pollution.
Bench grinder was not having guards Every motor should be earthed
and moreover earthing was not properly.
available to motor.
emergency.
In electric MCC room FDA system FDA system may be provided in such
was not provided for early detection of MCC rooms.
fire / smoke.
CMS
Welding and gas cutting set doesn’t At Both end flash back arrestors
have two flash back arrestors. should be provided to avoid back fire
up to source.
Earth pit lay out diagram was It should be maintained and resistance
available and there were ninety five of all earth pits should be checked and
earth pits. records should be maintained.
Hydra was not having safety latch. Every hydra should be checked before
driver or operator starts the machine
any non conformity should be
attended at the earliest.
Asle marking was done on the flooring It should be reviewed and ensure that
for walk way of man and machine the walk way should be free from
however due to space constrain the obstruction.
materials were not stored within the
aisle marking.
PFEs were installed more than 1 PFEs should be installed as per the
meter from the ground which will AP factories Rules, 1950.
create stress to person while lifting the
PFE.
The hazards associated with PFEs During fire fighting trainings hazards
like CO2 was not known to concern should be made known to workers.
workers while handling same.
158
OBSERVATION RECOMMENDATION
The drums of oil lubricating, servo oil The grass should be cut regularly to
stored in open yard where no electric avoid the fire which is one of the
lighting provided except high mast sources for fire.
tower at the entrance but it was found
that lot of grass was grown near the
electric panel JB which may lead to
fire.
There was EOT crane which having Ensure that emergency exit should be
two staircases one for going up to the free from any obstruction.
cabin and other was for exit however
material was stacked at the exit
159
OBSERVATION RECOMMENDATION
STED
The permits required for the height This is a good system it should be
work job was taken in shift starting continued.
and the permits entry was made in the
register for knowing the number of
permits issued during the date and
records were available for verification.
STED has planned the structural
stability for sixteen structures of the
company for that contract was allotted
to competent agency M/s Nova
Nirmaan Engineering and Architect
WO number 4410002218 and scope
of work was Inspection of Steel
Structures by competent authority for
stability certificate.
Monthly schedule for painting of all This was a good practice same should
types of things were prepared and be continued.
accordingly inspections were carried
out and remarks were mentioned on
the inspection records, these records
were maintained in a file for
verification.
***
160