Tunnel Fire Protection: A Lost Formwork System, Using PROMATECT - H
Tunnel Fire Protection: A Lost Formwork System, Using PROMATECT - H
Tunnel Fire Protection: A Lost Formwork System, Using PROMATECT - H
www.promat-tunnel.com
LOST FORMWORK SYSTEM, PROMATECT®-H
Contents
1. Project Background 3
2. Companies Involved 4
3. Technical Specification and Requirements for Fire Protection of Structural Concrete 5/7
8. PROMATECT -H Technical Data Sheet for The Palm Jumeirah Tunnel, Dubai
® .
23
This brochure describes the use of Promat fire protection lining boards installed
on the tunnel project on The Palm Jumeirah.
The photographs on the cover page and pages 2 and 3 of this brochure are reproduced courtesy
of the Taisei Corporation.
2
LOST FORMWORK SYSTEM, PROMATECT®-H
1. Project Background
The project was launched in 2001 with reclamation starting the same year.
Approximately 100 million cubic meters of sand were placed to form the The Palm Jumeirah,
which consists of a main trunk with a total of 17 fronds extending each side, all being encircled
by a Crescent, which forms a breakwater. The island extends 5 kilometres into the Arabian Gulf
area and is 5 kilometres wide.
The Crescent is connected to the trunk by a 1.4 kilometre long cut and cover, sea-crossing
tunnel. In addition to vehicular traffic, a mono rail system is being constructed from the
Gateway station for the entire length of the island’s trunk to the Atlantis station with two
intermediate stations. On completion, The Palm Jumeirah which is envisaged to be one of the
world’s premier living and tourism destinations, will contain a total of approximately 1540 villas in
a number of distinctive styles. There will also be 20 shoreline apartment buildings of 13/14 levels
containing a mixture of 1, 2 and 3 bedroom units, totalling approximately 2500 apartments.
In addition to this there will be 4 large marinas and over 30 of the world’s top hotels.
3
LOST FORMWORK SYSTEM, PROMATECT®-H
2. Companies Involved
and no transit damage was experienced. construction and programme management world-wide and specialising in transit systems,
tunnels, bridges and airports.
We decided to set up a dedicated
storage/workshop area on site, where
PARSONS DE LEUW CATHER - SUPERVISING CONSULTANTS
we could prepare the boards prior to
Internationally renowned consultants on roads and highways, transportation systems,
installation. This area was manned by a
bridges and tunnels.
team of men who prepared and cut the
boards. The same team was also responsible
for installation. TAISEI CORPORATION - DESIGN AND BUILD MAIN CONTRACTOR
One of the largest Japanese construction and engineering companies working on
Promat sent two engineers to site during
major projects world-wide. Taisei appointed Halcrow International Partnership as their
our first few days of the project to give
design partners.
advice to our installation team. Promat
continued with periodic on-site advice during
the project.
4
LOST FORMWORK SYSTEM, PROMATECT®-H
3. Technical Specification and Requirements for Fire Protection of Structural Concrete
Spalling is an umbrella term, covering different damage phenomena that may occur to a
concrete structure during fire. These phenomena are caused by different mechanisms:
pore pressure, thermal gradient, internal thermal micro-cracking, cracking around reinforcement
bars and strength loss due to chemical transitions. In different combinations of these
mechanisms, possible spalling phenomena include violent spalling, progressive gradual
spalling, explosive spalling, corner spalling and post-cooling spalling [1]*.
The Palm Jumeirah tunnel is constructed using a C40 concrete grade, which was cast in place.
If left unprotected, such concrete would typically suffer from violent spalling if it was exposed
to a typical tunnel fire, which creates temperatures up to 1200˚C within only 5 minutes.
Violent spalling is the separation of small or larger pieces of concrete from the cross section,
during which energy is released in the form of popping off of the pieces and small slices with
a certain speed, and also a popping or cracking sound. This type of spalling is caused by pore
pressure and thermal gradients [1]*.
5
LOST FORMWORK SYSTEM, PROMATECT®-H
3. Technical Specification and Requirements for Fire Protection of Structural Concrete
1400 1350
1300 1300
1200 1200
1200
1140
1000
Temperature [°C]
890
800
600
400
200
20
0
0 30 60 90 120
Time [min]
RWS fire curve, 120 minutes as applied in The Palm Jumeirah tunnel
2 216 wood pallets 6853 curve was confirmed by the Eureka tests, BRE and
240 PUR mattresses measuring 1200 x 800 x 150mm the Memorial Tunnel tests in the USA. In the frame of
a Swedish national and a European research program
3 Furniture and fixtures (tightly packed plastic and wood cabinet doors 8500
upholstered PUR arm rest, upholstered sofas, stuffed animals, on tunnel safety (UPTUN), comprehensive large scale
potted plant (plastic), toy house of wood, plastic toys). fire tests have been carried out in the abandoned
10 large rubber tyres (800kg)
Runehamar road tunnel in the western part of Norway
4 600 corrugated paper carton with interiors (600 x 400 x 500mm) 3120 in September 2003.
and 15% of total mass of unexpanded polystyrene (PS) cups
(18000 cups) and 40 wood pallets (1200 x 1000 x 150mm) In the 4 tests that were conducted during this project,
the RWS curve was confirmed to be the right choice
as a design fire curve for tunnels. Even with very limited fire loads temperatures reached up to
1250-1350˚C.
It should be noted that all combustible materials, which were used in these tests, are not listed
as hazardous/dangerous. Products like petrol, paints, resins etc were not used as combustibles.
A fire in a truckload of pallets (test 1) made the gas-temperatures rise up to 1365˚C. A small
truckload of plastic cups in cardboard boxes (test 4) created gas-temperatures of over 1200˚C.
6
LOST FORMWORK SYSTEM, PROMATECT®-H
3. Technical Specification and Requirements for Fire Protection of Structural Concrete ASSOCIATION
INTERNATIONALE DES TRAVAUX
EN SOUTERRAIN ITA
AITES
INTERNATIONAL
TUNNELING
ASSOCIATION
Towards an In Consultative Status, Category II with the
improved use United Nations Economic and Social Council
of underground http : //www.ita-aites.org
space
Working Group 6 of the ITA (International Tunnelling Association), focussing on Maintenance International Tunneling Association
Association Internationale De Travaux En Souterrain
and Repair of tunnels, has adopted the complete Runehamar report as mentioned under [2]*.
They included the Runehamar report in their final document [3]*, thus acknowledging the GUIDELINES FOR STRUCTURAL
FIRE RESISTANCE
conclusion that the RWS curve is the right choice as a design fire curve for tunnels. FOR
ROAD TUNNELS
Based on the information opposite and conducted research from all over the world, the
DIRECTIVES POUR LA RESISTANCE AU
developer decided to apply the highest and safest available standards for fire protection FEU DES STRUCTURES DE TUNNELS
ROUTIERS
of tunnels to the The Palm Jumeirah tunnel: the RWS requirements.
BY
Working Group No.6 Maintenance and Repair
o
Groupe de Travail N 6 Entretien et Repaire
May, 2004
As described in section 6.1 of this procedure, the thermal performance should comply with
RijksWaterStaat (RWS) fire, 120 minutes
the following criteria:
Protected concrete specimen
When spalling is not decisive during the 2 hours heating period the following temperature values and RWS temperature criteria
During the 2 hours heating period, the material must not fall down as a result of failure of
the offered fixing system.
7
LOST FORMWORK SYSTEM, PROMATECT®-H
4. Promat Technical Offer
The graphs below indicate the thermal performance of 27,5 mm PROMATECT®-H boards when
applied for concrete protection [5]*. As can be seen, the recorded temperatures on the interface
(approximately 320ºC) and the reinforcement (165ºC) are well below the RWS criteria of 380ºC
and 250ºC respectively.
350.0
300.0
200.0
Temperature
150.0
p
100.0
50.0
0.0
0 20 40 60 80 100 120 140
Time (min) T rebar average
T interface average
8
LOST FORMWORK SYSTEM, PROMATECT®-H
4. Promat Technical Offer
Where the tunnel is designed with sloped sections, so called haunches, B - Fixed strip of plywood serves as a ruler for the first row of boards
the edges of the boards are simply cut under an angle and installed
butt-jointed (see photograph E).
The boards can either be installed using staggered joints or straight joints. Experience from
contractors has learned that the staggered joint method results is less gaps in between the
boards, as this method allows to compensate for certain tolerances, whereas the straight joint
method does not allow for much compensation. For The Palm Jumeirah tunnel, Taisei chose
to lay the boards with straight joints.
D - The joints are just butted, no special E - The boards are cut under an angle at the haunches
treatment of the joints are required
9
LOST FORMWORK SYSTEM, PROMATECT®-H
4. Promat Technical Offer
The locations of the screws are marked on the boards, using a template and
a spray-can with red paint (see par. 5.1.), (photograph F).
Several methods are available on the market for ease of installation of the
stainless steel screws (see photographs I and J):
G - First layer on reinforcement installed, prior to inserting the screws Battery-driven drilling machines can be equipped with depth
10
LOST FORMWORK SYSTEM, PROMATECT®-H
4. Promat Technical Offer
The following advantages of the PROMATECT® H lost formwork system have been reported by
contractors over the years:
Formwork savings:
The shuttering material only has to have load-bearing properties. There is no need to apply
phenol coated plywood boards as the PROMATECT®-H boards will be laid on top of the L - Extracted formwork. Flush finish of the ceiling
formwork. The formwork elements just have to be installed properly (flush).
As the concrete will not be in direct contact with the formwork, there is no need for
de-moulding oil (no slippery surfaces). The plywood sheets will remain clean and can
be re-used.
Formwork can be installed at a distance of up to 90mm from the side walls.
The PROMATECT®-H boards can span that distance, depending on the expected load.
At this location, care should be taken with the vibrating action during pouring of the concrete.
Extraction of the formwork is much easier as it will not get stuck between the walls.
As there is no adhesion between the concrete and the formwork, it is easy to extract
the formwork
Cutting the boards on the formwork eliminates the tolerences Wall panels can also be installed using the lost formwork method Distance between formwork and wall, easing
the extraction of the formwork
11
LOST FORMWORK SYSTEM, PROMATECT®-H
4. Promat Technical Offer
Ease of installation:
Joints in between boards only have to be butt-jointed. No special treatment such as filler or
mastic is necessary from a fire performance point of view. The cement water will not run
through the joints. Where gaps of more than 1mm occur, mastic can be used to seal
the gap in order to prevent that cement water would leak through the gap, causing an
unsightly stain.
The vertical wall panels can also be installed using the lost formwork system
Curves in the tunnel can easily be dealt with by cutting the boards on the formwork
Openings in the PROMATECT®-H lining (for manholes and end-walls) can easily be made
by installing a phenol coated formwork panel instead. Afterwards standard size
PROMATECT®-H boards will close the opening by post-fixing the board into the opening.
PROMATECT®-H boards provide a heavy-duty floor surface. The abrasion resistance is such
that the surface can withstand the exposure to people walking and working on top of it,
even in wet conditions. Also, the weight of bundles of reinforcement steel and pallets in
excess of one tonne will not cause any damage to the boards.
Openings for manholes can easily be made Rapid installation method. Installation rates for the PROMATECT® -H boards of 150m2 per
by using phenol coated plywood panels
man per day have been reported on European tunnel projects.
The installation of the system does not interfere with other construction activities.
Extensive experience is available with this system in immersed and cut and cover tunnels
Other:
As the PROMATECT®-H boards are installed in the very early stages of the construction
of the tunnel, it provides fire protection during the construction phase.
The PROMATECT®-H lost formwork system provides a flush finish of the ceiling.
Inclusion of services and pipes in formwork
No obstacles like anchor-heads.
12
LOST FORMWORK SYSTEM, PROMATECT®-H
4. Promat Technical Offer
Dimensional details of this particular screw can be found in the below table and drawing.
L Length 50 -
,V ¼
K
² ¼ ²
D
D
(
²
²
²
DK
²
²
0 M
,T ¼
, Source: Heco
The design of a screw has major influence on the mechanical performance and fire performance,
in combination with PROMATECT®-H boards. Among others, properties like shaft-diameter
versus thread-diameter, sharpness of the tip and distance of the winding (thread) will influence
the stickability of the screws and the performance of the final system.
The above mentioned screw type has been tested to its pullout resistance when partially
(20 mm) inserted into dry as well as water saturated (worst case) 27,5mm PROMATECT®-H
boards [6]*. Even when tested in water saturated conditions the minimum-recorded screw
pullout strength was in excess of 500N, which was satisfactory for the client. In dry conditions
the maximum-recorded screw pullout strength exceeded 725N.
Similar screws as described above have also been used in a lost formwork system in a fire
test at TNO where PROMATECT®-H boards have been exposed to the RWS fire curve for
120 minutes, without any mechanical or thermal failure [7]*..
For the Palm Jumeirah tunnel it was decided to install the wall panels after the walls had been
constructed. The boards were installed by means of stainless steel anchors, creating fire
protection over a height of 1200mm on the wall. The boards were anchored to the concrete,
butt jointing one board next to the other. The reason for protecting the top section of the wall
is that the bending moment in the roof introduces compression stresses into the upper part of
the wall. Research has proven that concrete that is exposed to compression stress is more
vulnerable to fire exposure (spalling), as opposed to neutral (non-loaded) or tensioned concrete.
The FNA anchors are installed in combination with a circular washer, diameter 30mm, thickness
1,2mm stainless steel grade A4
Code Description Dimension (mm)
and a hole diameter of 7,5mm.
do Anchor diameter 6
This FNA anchor, including
l Length 68
the washer, was tested at TNO,
h ef Effective anchorage depth 30 Centre for Fire Research in RWS
fire conditions for 120 minutes
t fix Effective length 30
in combination with the 27,5mm
d Diameter of nailhead 13 PROMATECT®-H boards and
Fischer FNA anchor and washer
passed the test, without any
mechanical or thermal failure [5]*.
do d
h ef t fix
l * Refer to ‘References List’
on page 22.
Source: Fischer
14
LOST FORMWORK SYSTEM, PROMATECT®-H
4. Promat Technical Offer
The aforementioned anchor type, including the washer, has also been tested for its pull-through
resistance when installed in dry and water saturated (worst case) 27,5mm PROMATECT®-H
boards [8]*.
Even when tested in water saturated conditions the recorded anchor pull-through strength was
in excess of 2400N, which was satisfactory for the client. In dry conditions the recorded anchor
pull-through strength exceeded 3300N.
In general, when selecting anchors for the installation of fire protective boards in tunnels,
following items should be considered:
Preferably M6 in diameter, to avoid heat sink into the concrete in case of fire
Made of stainless steel. Grade in function of local tunnel environment (see par. 4.1.3.)
Of appropriate length to secure the panel, depending on the panel thickness
Expansion action of the anchorage shall be within the concrete and not in the
PROMATECT® panel.
Can be supplied with a nut and washer head to facilitate removal of the PROMATECT®
panels where required.
Suitable for use in the tension zone of concrete (cracked concrete).
Suitable for use where the bolts will be subject to positive and negative pressure fluctuation.
C Si Mn S Cr Mo Ni Cu
Post fixed wall: A4 1.4401 X4CrNiMo17-12-2 316 0,04 0,50 1,00 0,015 17,50 2,25 12,00 -
Fischer anchor
FNA 6x30/30
Lost formwork A2 1.4567 X3CrNiCu18-9-4 304 Cu 0,03 0,50 1,00 0,015 18,00 - 9,00 3,50
ceiling:
Screw 5 x 50mm
The above mentioned stainless steel grades were also used for the fire tests and mechanical
tests. In general, the corrosion resistance of fixing materials for fire protective boards in a tunnel
should be checked with the fixing supplier as to the suitability of application in the specific
environmental conditions of the tunnel project it is meant for.
15
LOST FORMWORK SYSTEM, PROMATECT®-H
4. Promat Technical Offer
In order to simulate this worst case scenario, dynamic load tests were conducted using a
polyethylene foil at the interface, in between the PROMATECT®-H boards and the concrete,
to avoid the adhesion effect [9]*. The whole system was exposed to dynamic loads of up to +/-
3 KPa, which is approximately 3 times the load expected in practice. No mechanical failures or
any damage to the boards were recorded. The deflection between the screws was less than
1/15.000 of the span.
16
LOST FORMWORK SYSTEM, PROMATECT®-H
4. Promat Technical Offer
can occur on the jobsite. In case minor surface damages or gaps in between the boards in Definition of
diagonal lengths
excess of 2 mm would occur, these would be filled with PROMATECT®-T compound, prior to
casting the concrete. This material comes as a dry, white to off white powder made from
calcium-aluminium silicates and additives. It will just be mixed with water and is then applied
with a spatula.
The PROMATECT®-T compound was tested to RWS conditions for a duration of 120 minutes
[10]*. A gap of 10mm width was left open in between two PROMATECT®-H panels of 27,5mm
thick. Also two holes of 10mm diameter were drilled into the panels. Both the gap and the holes
were filled with the PROMATECT®-T compound, which did not show any integrity failures during
and after the fire test. The average interface temperature at the joint (behind the PROMATECT®-T
compound) after 120 minutes of RWS fire exposure was 335ºC, which is well below the interface
criteria of 380ºC according to RWS requirements.
See the technical data sheet for more details and installation and application instructions [11]*.
17
LOST FORMWORK SYSTEM, PROMATECT®-H
5. Installation Guide and Experiences
The screw pattern of a full size board of 2500 x 1250 mm looks as detailed below, providing an
average of 12,8 screws per m2:
In The Palm Jumeirah tunnel the PROMATECT®-H boards were supplied in dimensions of
2500 x 1250 mm. The locations of the
screws were marked on the boards, using
Template for screw location a template and a spray-can with red paint.
18
LOST FORMWORK SYSTEM, PROMATECT®-H
5. Installation Guide and Experiences
19
LOST FORMWORK SYSTEM, PROMATECT®-H
5. Installation Guide and Experiences
100mm.
The anchors for cut pieces
The surface area of the panel is 2,28m2 which means that there should be a minimum of
11 anchors. In this case, the total amount is 12 anchors and the edge distance is 100mm.
The spacing distances are optimised and are almost equal (525 and 540 mm).
20
LOST FORMWORK SYSTEM, PROMATECT®-H
6. Project References in Lost Formwork Application
Throughout the world, Promat boards have been applied to protect over 120 tunnels against
the most severe tunnel fires. Amongst others, the PROMATECT®-H lost formwork system as
used in The Palm Jumeirah tunnel was also installed in following reference projects:
Tunnel under North River 1989 The Netherlands Hendrik Ido Road
Roer Tunnel, Netherlands
Ambacht
Harbour Tunnel CANA, USA Gotha Tunnel, Sweden Seitwende Tunnel, Netherlands
21
The authors are grateful to the owner of LOST FORMWORK SYSTEM, PROMATECT®-H
The Palm Jumeirah tunnel, NAKHEEL, for
7. Acknowledgement and Reference List
allowing Promat to issue this document.
REFERENCE LIST
[1] SPALLING OF CONCRETE AND FIRE PROTECTION OF CONCRETE STRUCTURES
A. J. Breunese and J. H. H. Fellinger
TNO Building and Construction Research, Centre for Fire Research, Delft/Rijswijk,
The Netherlands
[2] SUMMARY OF LARGE SCALE FIRE TESTS IN THE RUNEHAMAR TUNNEL IN
NORWAY, CONDUCTED IN ASSOCIATION WITH THE UPTUN RESEARCH PROGRAM
Jan Brekelmans, TNO Building and Construction Research, Centre for Fire Research,
René van den Bosch, Promat Tunnel Fire Protection
[3] GUIDELINES FOR STRUCTURAL FIRE RESISTANCE FOR ROAD TUNNELS
ITA, International Tunnelling Association, Working Group No.6 Maintenance and
Repair, May, 2004
[4] FIRE PROTECTION FOR TUNNELS, Part 1: Fire Test Procedure,
1998-CVB-R1161 (rev. 1)
TNO Building and Construction Research, Centre for Fire Research, Delft/Rijswijk,
The Netherlands
[5] DETERMINATION OF THE BEHAVIOUR OF A CONCRETE SLAB PROTECTED WITH
CALCIUM SILICATE BOARD TYPE PROMATECT®-H UNDER RWS FIRE
CONDITIONS, 2004-CVB-R0115[Rev.1].
TNO Building and Construction Research, Centre for Fire Research, Delft/Rijswijk,
The Netherlands
[6] SCREW PULLOUT OF PROMATECT®-H IN DRY AND WATER SATURATED
CONDITION
PRTC, Promat Research and Technology Centre, 30 November 2005
[7] DETERMINATION OF THE BEHAVIOUR OF A CONCRETE SLAB PROTECTED WITH
CALCIUM SILICATE BOARD TYPE PROMATECT®-H UNDER RWS FIRE
CONDITIONS, B-85-191(E)
TNO Building and Construction Research, Centre for Fire Research, Delft/Rijswijk,
The Netherlands
[8] PULL THROUGH TEST ON PROMATECT®-H 27,5 MM OF FISCHER FIXATIONS
AT060131
PRTC, Promat Research and Technology Centre, 2 February 2006
[9] TESTING OF DYNAMIC LOAD CYCLES IN 27,5 MM PROMATECT®-H BOARDS
(German)
6432/328-Pm/br Technical University Braunschweig, 25 July 1989
[10] DETERMINATION OF THE BEHAVIOUR OF A CONCRETE SLAB PROTECTED WITH
CALCIUM SILICATE BOARD TYPE PROMATECT®-H UNDER RWS FIRE
CONDITIONS, 2004-CVB-R0114[Rev.1].
TNO Building and Construction Research, Centre for Fire Research, Delft/Rijswijk,
The Netherlands
[11] TECHNICAL DATASHEET PROMATECT®-T COMPOUND
October 2003
22
LOST FORMWORK SYSTEM, PROMATECT®-H GENERAL DESCRIPTION
PROMATECT®-H is a non-combustible,
PROMATECT®-H Technical Data sheet for The Palm Jumeirah Tunnel, Dubai fire protective calcium silicate board.
ADDITIONAL INFORMATION
MECHANICAL PROPERTIES Waste Disposal
All physical and mechanical property values are averages based on standard production. - Refer to local legislation
The figures can change dependent on the test methods used. If a particular value is of prime - If not available: The board is not classified
as a dangerous substance and so no special
importance for a specification, please contact the Promat Technical Services department.
provisions are required regarding the carriage
and disposal of the product to landfill.
Bending strength N/mm2 Average of production: 7.0 They can be placed in an on-site skip with
(average of both directions) Minimum 95% confidence limit: 4.5 other general building waste
Promat UK Limited
The Sterling Centre, Eastern Road, Bracknell, Berkshire RG12 2TD
Telephone: +44 1344 381 300 Fax: +44 1344 381 301 www.promat.co.uk