Pekerjaan : RUMAH TYPE 40

Upah Total :
NO URAIAN PEKERJAAN VOLUME SATUAN BOBOT PROGRES PENCAPAIAN TOTAL PROGRES
A PEKERJAAN TANAH
1 Pek. Galian Tanah Pondasi 5,27 M 0,26% 100% 0,26%
2 Pek. Pemadatan tanah 6,75 m3 0,24% 100% 0,24%
3 Pek. Urugan Pasir
a Urugan Pasir Bawah Batu Kali 0,59 m3 0,06% 100% 0,06%
b Urugan Pasir Bawah Lantai 2,25 m3 0,25% 100% 0,25%
4 Pek. Urugan Tanah Kembali 7,02 m3 0,11% 100% 0,11%
5 Pek. Urugan Tanah Peninggian Lantai 13,50 m3 1,23% 100% 1,23%
B PEKERJAAN STRUKTUR
1 Pek. Aanstamping 1,76 m3 0,46% 100% 0,46%
2 Pek. Pondasi Batu Kali 7,02 m3 1,59% 100% 1,59%
3 Pek. Sloof, S1
a Beton (Site Mix K250) 2,00 m3 1,00% 100% 1,00%
b Besi 84,90 kg 0,74% 100% 0,74%
c Bekisting 22,00 m2 1,50% 100% 1,50%
4 Pek. Kolom, 0,00%
a Beton 1,00 m3 0,50% 100% 0,50%
b Besi 100,12 kg 0,87% 100% 0,87%
c Bekisting 14,40 m2 0,98% 100% 0,98%
5 Kolom Beton Teras
a Beton 0,96 m3 0,48%
b Besi 40,97 kg 0,36%
c Bekisting 9,60 m2 0,65%
6 Pek. Rabat Lantai Dasar, 0,00%
a Beton Sitemix, K 250 2,25 m3 1,12%
7 Pek. Meja Beton t= 10 0,00%
a Beton Sitemix, K 250 0,31 m3 0,16%
b Besi 25,67 kg 0,22%
c Bekisting 4,49 m2 0,31%
8 Pek. Rabat Keliling Bangunan, t = 10 1,95 m3 0,97%
9 Pek. Kanopi Beton t= 10 0,00%
a Beton Sitemix, K 250 0,25 m3 0,12%
b Besi 25,38 kg 0,22%
c Bekisting 3,17 m2 0,22%
9 Pek. Balok 0,00%
a Beton (Site Mix K250) 2,00 m3 1,00% 100% 1,00%
b Besi 84,90 kg 0,74% 100% 0,74%
c Bekisting 22,00 m2 1,50% 100% 1,50%
C PEKERJAAN ARSITEKTUR
I.1 PEKERJAAN DINDING LANTAI 1
1 Pek. Pas. Bata 149,00 m2 16,67% 100% 16,67%
2 Pek. Pas. Plesteran Batako1/2 bata, 1pc : 4psr 298,00 m2 16,54%
3 Pek. Pas. Acian 133,00 m2 3,13%
4 Pek. Pas. Acian Kanopi Beton 2,07 m2 0,05%
5 Pek.Dinding Keramik Toilet, 25 x 25 cm 10,40 m2 1,42%
6 Pek.Dinding Keramik Dapur , 25 x 25 cm 5,00 m2 0,68%
7 Pek. Openingan Kusen/Balok Litel 54,05 m1 0,00%
a Beton (Site Mix K250) 0,54 m3 0,27% 100% 0,27%
b Besi 96,46 kg 0,84% 100% 0,84%
c Bekisting 18,92 m2 1,29% 100% 1,29%
I.2 PEKERJAAN PLAFOND
1 Pek. Plafond Baja Ringan 56,00 m2 6,99%
I.3 PEKERJAAN LANTAI
1 Pek. Lantai Keramik 40 x 40 cm, Polish 38,00 m2 4,31%
2 Pek. Lantai Keramik Km/Wc dan Taras 25 x 25 cm, 5,36 m2 0,61%
3 Pek. Plint Lantai Keramik 10 x 50 cm, Polish 10,00 m1 1,14%
4 Pek. Lantai Keramik Meja Dapur 50 x 50 cm, Polish 2,00 m2 0,23%
I.4 PEKERJAAN PENGECATAN
1 Pek. Pengecatan Dinding Eksterior Weathershiled 96,00 m2 2,83%
2 Pek. Pengecatan Dinding Interior 149,00 m2 4,40%
3 Pek. Pengecatan Plafond 56,00 m2 1,65%
4 Pek. Pengecatan Kusen 54,05 m2 1,60%
I.6 PEKERJAAN SANITAIR
1 Pek. Pas. ClosetDuduk 1,00 bh 1,57%
2 Pek. Pas. Jet Washer 1,00 bh 0,24%
3 Pek. Pas. Wastafel Dinding 1,00 bh 1,09%
4 Pek. Pas. Kitchen Zink Stainless Steel 1,00 bh 0,22%
5 Pek. Pas. Kran Leher Angsa 1,00 bh 0,09%
6 Pek. Pas. Kran 1,00 bh 0,06%
7 Pek. Pas. Floor Drain 1,00 bh 0,06%
D PEKERJAAN ELEKTRIKAL
INSTALASI PENERANGAN DAN STOP KONTAK
- Kabel 50,00 m 2,27%
- Lampu DL 5" (LED) 11 Watt 2,00 Bh 0,14%
- Lampu Baret (LED) 20 Watt 5,00 Bh 0,34%
- Lampu DL 5" (LED) 5 Watt 1,00 Bh 0,07%
- Sklar Tunggal 7,00 Bh 0,85%
- Stop Kontak 8,00 Bh 0,97%
- Stop Kontak AC 3,00 Bh 0,36%
E PEKERJAAN PLUMBING
1 Pipa PVC AW 1/2" 15,00 m 0,68%
2 Pipa PVC 3" 8,00 m 0,73%
3 Bak Septitank 5,625 m3 1,00 Bh 0,00%
F PEKERJAAN TAMBAHAN
1 ATAP 61,00 m2 7,75%
TOTAL 100,00% 32,10%