Notes 2 Rate Analysis
Notes 2 Rate Analysis
ANALYSIS OF RATES
RATE ANALYSIS
The determination of rate per unit of a particular item of work from the cost of
quantities of materials, labour cost and other miscellaneous petty expenses required for its
completion is known as the analysis of rate.
It includes cost of material, labour, equipments, water charges, contractor profit and
specifications.
2. To work out the economical use of materials and processes in completing the particulars item.
3. To work out the cost of extra items which are not provided in the contract bond, but are to be
done as per the directions of the department.
4. To revise the schedule of rates due to increase in the cost of material and labour or due to
change in technique.
9 Binding wire Kg 70
BRICKS-Table
10 Per No 8
moulded
BRICKS-Wire cut
11 Per No 19
bricks
4.Unskilled- Mazdoors,sweepers
5.Driver,Cleaner
LABOUR RATES
2 Mason 500
Carpenter
7 Plumber 500
Painter
LABOUR OUTPUT
Labour in Days
work
Sl.no Description of work Unit
8 hours
Earthwork
Mazdoor-3
1 a) In ordinary soil 10 cum
Mazdoor-6
b).In dense or hard soil
Head mason-0.5,
2 Cement concrete work For foundation 10 cum mason-2, mazdoor-
10
Head mason-0.5,
3 Cement concrete for RCC work 10 cum mason-3, mazdoor-
20
Carpenter-3,
4 Centring and shuttering work 10 sqm
mazdoor-6,
Bar bender-1,
5 Reinforcement work for RCC Quintal
mazdoor-1
Head mason-
6 Brick work 10 cum 0.5,mason-
8,mazdoor-16
GST on steel
18%: On iron blocks, wire, rolls and rods.
In the Rate analysis, 10% is added towards Contractor’s Profit & Overhead Charge
➢ Overheads include
Site accommodation, setting up plant, access road, water supply, electricity and general site
arrangements , Office furniture, equipment and communications , Corporate office of contractor
,Site Supervision , Mobilization/ de-mobilization .