Analysis of Rates
Analysis of Rates
Analysis of Rates
• Contractor ‘ s profit = 10 %
Terminology
Labour : May be classified into three types.
• Skilled Ist class
• Skilled IInd class
• Unskilled
Labour charges can be obtained from Schedule of Rates.
30% of the skilled labour in data should be taken as Ist
class and remaining 70% as IInd class.
Lead Statement: The distance between the source of
availability of material and construction site is known as
Lead and is calculated in km. The conveyance cost of
material depends on lead
The lead statement will give the total cost of materials per
unit item including first cost, conveyance loading-
unloading, stacking charges etc.
Typical example of lead statement
Solution.
Ratio = 1:4:8 (cement,sand and aggregate)
Sum = 1+4+8=13
cont..
Total dry mortar for 1 cu m cement concrete
=1.54 cu m
Therefore the following materials are
required:
Cement = (1*1.54*1)/13=0.1184*(1440/50)
= 3.41 bags
Sand = (4*1.54*1)/13
= 0.47 cu m
cont..
Aggregate (Brick ballast) = (8*1.54*1)/13
= 0.94 cu m
so materials for 1 cu m cement concrete
1:4:8.
Solution:
Ratio = 1:2 (lime,surkhi)
Sum = 1+2
=3
Total dry mortar for 1 cu m lime concrete
= 0.40 (lime, surkhi mortar)
Therefore the following materials are
required.
Lime = (1*0.40)/3
= 0.13 cu m
Surkhi = (2*0.40)/3
= 0.27 cu m
Lime 0.13 cu m
(b)labour for % cu m
Mazdoor 33 nos.@ 250.00/day = 8250.00
Mason 1 no. @ 450.00 = 450
Sundries and T & P 3% on labour= 0.03* 8700 = 261
Total=8700+261
=8961