S-1 General Notes
S-1 General Notes
S-1 General Notes
PURPOSES UNLESS OTHERWISE INDICATED. 1. ALL STUCTURAL STEEL SHALL CONFORM TO ASTM A-36. SEE NOTE A SEE NOTE A
5-10MMØ BARS 150MM
BAR SPACES DIA.
C. FOR ALL OTHER REQUIREMENTS , REFER TO ARCHITECTURAL , SPACED AT 200 MM O.C.
100MM
50MM
FOOTINGS : CALCULATED BOND
LENGTH BUT
NOTE E
30Ø OR 600MM
1. FOOTINGS ARE DESIGNED TO REST ON FIRM SUBGRADE
WITH MINIMUM BEARING CAPACITY OF 3, 000 psf THE ENGINEER AND THE OWNER.
2. NO FOOTING SHALL REST ON FILL. 2h 2h 5-10MMØ BARS
SPACED AT 200 MM O.C.
3. MINIMUM CONCRETE PROTECTION FOR REINFORCEMENT SHALL NO LAPS ZONE
1
SEE NOTES
D,F&G 2 SEE NOTE D FOR ALL TYPICAL SLAB DEPRESSION DETAIL
BE 70 MM CLEAR FOR CONCRETE DEPOSITED AGAINST THE SEE NOTE D MINIMUM STEEL LAPS CALCULATED
SEE NOTE B LAP LENGTH
FORMWORK. BUT 300MM
40MM CLEAR
DISTANCE (MINIMUM)
END SPAN INTERNAL
CONCRETE MIXES & PLACINGS : DETAIL - 3 SUPPORT SUPPORT
1. UNLESS OTHERWISE SPECIFIED , THE MINIMUM 28-DAY CYLINDER h 500MM
40MM CLEAR DIST.
10
40MM CLEAR
00
COMPRESSIVE STRENGTH ARE AS FOLLOWS : (MINIMUM) FOR DISTANCE (MINIMUM)
2. ALL CONCRETE MUST BE DEPOSITED , VIBRATED AND CORED IN 2-16MMØ AT MINIMUM 1-16MMØ
B. THE AREA OF BOTTOM OF STEEL PROVIDED AT THE SUPPORTS MUST EQUAL AT
TYPICAL BEAM-COLUMN EACH CORNER
ACCORDANCE WITH ACI STANDARD 318-89. INTERCONNECTION
TOP & BOTTOM FOR LEAST HALF THE AREA OF THE TOP STEEL AT THAT SECTION.
NOTE : SLABS 125MM THK.
AND OVER
50MM
3. STRIPPING FORMS AND SHORES SHALL BE AS FOLLOWS : A. STIRRUP SPACING IN PLASTIC HINGE ZONE OF LENGTH 2h OPENING C. A MIN. OF 1/4 OF THE LARGER AMOUNT OF TOP STEEL REQUIRED AT EITHER END 500MM 10MMØ TIES AT 150MM O.C.
FOUNDATION 1 DAY SHALL BE THE LEAST OF ; 1. D/4 2. 6Ø 3. 150MM. HOOK SLAB MUST CONTINUE FOR THE WHOLE LENGTH OF THE SPAN.
EXTENDED TRIMMER BAR
COLUMNS & WALLS 3 DAYS B. Ø = DIAMETER OF MAIN LONGITUDINAL BAR FOR DISTANCE REINFORCEMENT 1000MM BEYOND SIDES
OVER TRIMMER BAR OF OPENING OR AS FAR
BEAMS & GIRDERS 21 DAYS D. NO LAPS IN TOP & BOTTOM TO OCCUR WITHIN A DISTANCE OF 2h FROM FACE OF
UNDER CONSIDERATION IN TOP OR BOTTOM WHICHEVER IS AS POSSIBLE & HOOK.
SLABS 17 DAYS SUPPORT .
SMALLER.
4. CONCRETE SHALL BE DEPOSITED IN ITS FINAL POSITION WITHOUT
SEGREGATION RE-HANDLING OR FLOWING. PLACING SHALL BE
C. THIS STIRRUP SPACING CONTINUES WITHIN THE INTERMEDIATE E. LAPS ARE TO BE KEPT TO A MINIMUM AND CRANKS IF REQUIRED TO BE AS FOR TYP. BEAM DEPRESSION DETAIL
DONE PREFERABLY WITH BUGGIES , BUCKET OR WHEELBARROWS. ZONE. COLUMNS.
NO CHUTES WILL BE ALLOWED EXCEPT TO TRANSFER CONCRETE SCHEDULE - 1 PROVIDE EXTRA BAR
(NOT SHOWN) PARALLEL 1000
FROM HOPPERS TO BUGGIES , WHEELBARROWS OR BUCKETS IN TO SIDES OF EQUAL AREA F. IF h > 750MM PROVIDE EXTRA LONGITUDINAL BARS FOR 2/3 OF THE BEAM DEPTH
OF INTERRUPTED SLAB
WHICH CASE THEY SHALL NOT EXCEED SIX (6.0) IN METER IN CONCRETE HOLLOW BLOCK REINFORCEMENT REINFORCEMENT LESS FROM THE TENSION FACE WITH SPACING > 250MM.
AGGREGATE LENGHT. NO DEPOSITING OF CONCRETE SHALL BE BLOCK REINFORCEMENT NOTES AREA TRIMMER BARS.
ALLOWED WITHOUT THE USE OF VIBRATORS. UNLESS AUTHORIZED THICK HORIZONTAL VERTICAL A. MINIMUM SPLICE AT LAP = 300MM
G. LAPS IN FRAMING BARS TO BE STAGGERED RELATIVE TO LAPS IN MAIN TOP AND
B. PROVIDE RIGHT ANGLE REINF. t
75 MM 10MM AT 600MM O.C. 10MM AT 600MM O.C. DETAIL - 4
IN WRITING BY THE DESIGNERS AND ONLY FOR USUAL CONDITIONS 100MM 10MM AT 600MM O.C. 10MM AT 600MM O.C.
AT CORNERS 1000MM LONG.
C. WHERE CHB WALLS ADJOINING COLS.
BOTTOM BARS.
WHERE VIBRATORS IS EXTREMELY DIFFICULT TO ACCOMPLISH. R.C. BEAMS. WALL DOWELS W/ SAME b b ANCHORAGE OUTSIDE
150MM 12MM AT 600MM O.C. 12MM AT 600MM O.C. PANEL ZONE PQRS
SIZE AS VERT. REINF. SHALL BE
200MM
BEAMS AND GIRDERS : 12MM AT 600MM O.C. 12MM AT 600MM O.C. PROVIDED.
P Q TYP. SLAB CONSTRUCTION JOINT
1. CAMBER ALL BEAMS AND GIRDERS AT LEAST 6.50 MM FOR EVERY
3.0 M. OF SPAN. SCHEDULE - 2
h
2. FOR TWO OR MORE LAYERS OF REINFORCING BARS USE SEPARATORS
WALL REINFORCEMENT VERTICAL
SPACED AT 1.0 M. O.C. AND IN NO CASE SHALL BE LESS THAN REMARKS
THK. HORIZONTAL VERTICAL SECTION S R
TWO (2) SEPARATORS. 10MM AT 250MM O.C. 10MM AT 300MM O.C.
HORIZONTAL & CENTER VERTICAL 1-1 2-2
100MM BARS STAGGERED OUTSIDE.
125MM 10MM AT 250MM O.C. 10MM AT 250MM O.C. - DO -
3. NO SPLICE SHALL BE PERMITTED ON BEAMS AND GIRDERS WHERE BOTH FACES HORIZONTAL BEAMS FORMING PART OF A ALTERNATIVE PREFERRED b
150MM 12MM AT 250MM O.C. 12MM AT 300MM O.C
CRITICAL BENDING STRESSES IS OCCUR. TENSION SPLICE SO PERMI-
SHALL BE INSIDE.
DUCTILE MOMENT RESISTING END SUPPORT DETAIL
175MM 12MM AT 200MM O.C. 12MM AT 250MM O.C. - DO -
TTED SHALL BE 60 DIAMETER FOR PLAIN BARS AND 40 DIAMETER 200MM 12MM AT 300MM O.C. E.F. 12MM AT 300MM O.C. BOTH FACES HORIZONTAL FRAMEWORK
SHALL BE OUTSIDE.
12Ø
FOR DEFORMED BARS. 225MM 12MM AT 200MM O.C. E.F. 12MM AT 250MM O.C. E.F. - DO -
- DO -
- DO -
CONCRETE COLUMNS : PLAN
CONF'T
WIRED TOGETHER UNLESS OTHERWISE SPECIFIED. TOP BARS AT MID-
ZONE
L1
325MM 12MM AT 200MM O.C. E.F. 12MM AT 250MM O.C. E.F. - DO -
SPAN , BOTTOM BARS AT SUPPORT , BEND BARS AT BED POINTS IN
SUPERSTRUCTURE. WELDED SPLICES SHALL DEVELOP IN TENSION AT
350MM 16MM AT 250MM O.C. E.F. 12MM AT 300MM O.C. E.F. - DO -
A. Li = LARGEST OF :
LEAST 125% OF THE SPECIFIED YIELD STRENGTH OF THE BAR. NOT 1. h (h>b)
INTERMEDIATE ZONE
MORE THAN 50% OF THE BARS AT ANY ONE SECTION SHALL BE
PERMITTED TO BE SPLICED.
200
1
200 2. Lo/6 1000MM
Lo
LINTEL BEAM STIFFENER
CONF'T
FOR TENSION AND 20 DIAMETER FOR COMPRESSION BARS.
ZONE
L1
MAXIMUM SPACING OS 0.20 b , 6Ø OR 200MM. h
CONNECTION
THE AREA OF CONFINEMENT LINKS SHOULD BE DE-
SEE NOTE
BEAM-COL
SHALL BE AS SHOWN ON DETAIL-1.
D&E
6. UNLESS OTHERWISE NOTED IN PLANS OR SPECIFICATIONS , CAMBER
TERMINED.
Sh1/2
1 - 16MMØ
SEE NOTE
C. Sh : = SPACING FOR ALL LINKS & TIES IN INTERMEDIATE 10MMØ TIES 2-12MMØ ON
CONF'T
ALL BEAMS AND GIRDERS AT LEAST 6.5 MM FOR EVERY 3.0 M OF
ZONE
VERTICAL BAR
L1
B&C
AT 150MM O.C. BOTH SIDES
(TYPICAL)
SPAN EXCEPT CANTILEVERS FOR WHICH THE CAMBERS SHALL BE AS
NOTED IN PLANS OR AS ORDERED BY THE DESIGNER , BUT IN CASE
ZONE. SPACING TO BE THE LEAST OF :
SECTION
INTERMEDIATE ZONE
LESS THAN 7.5 MM FOR EVERY 3.0 M OF FREE SPAN. 1. 12Ø
SEE NOTE C
Lo
2. 400MM
0.2 Sh1
Ø = DIAMETER OF SMALLEST LONGITUDINAL BAR
CONF'T
ZONE
BOTTOM OF SLAB.
L1
2. FOR TWO-WAY SLAB BARS ALONG SHORTER SPAN SHALL BE PLACED IN COLUMN.
Sh
100-150MMØ PIPE
BELOW THOSE ALONG THE LONGER SPAN AT CENTER AND OVER THE D. SPACING AND TOTAL CROSS-SECTIONAL AREA OF HOOPS
LONGER SPAN BARS NEAR THE SUPPORT. UNLESS OTHERWISE INDICA- ELEVATION ELEVATION
b
TED OR SHOWN IN DETAILS THE SPACING OF THE BARS AT THE a
& TIES THROUGH THE BEAM COLUMN CONNECTION
COLUMN STRIPS CAN BE APPROXIMATELY 1-1/3 TIMES OF THE MIDDLE CHB WALL
STRIP BUT IN NO CASE GREATER THAN 2-1/3 TIMES THE SLAB THICK-
(OR ANY OTHER CONNECTING MEMBER). h
SUPPLEMENTARY
NESS. 300MM DOWEL(SAME DIAMETER
CROSS TIES (SEE
NOTE H)
E. ALL HOOP ARRANGEMENTS MUST ALSO BE CAPABLE
AS CHB VERTICAL REINF.)
3. UNLESS OTHERWISE DETAILED IN CONTINOUS SLABS HAVING SAME REIN- 300MM h
OF RESISTING THE APPLIED SHEARS THROUGHOUT
b
HOOPS 12MMØ ON
FORCEMENT RUNNING IN ONE DIRECTION REINFORCING SHALL BE BENDED
2-12MMØ TOP BAR b/a > 10 THE WHOLE COLUMN LENGTH INCLUDING THE BEAM BOTH SIDES
150MM
b > 300MM
20MM
FOR PERMIT
ARCHITECT: ENGINEER: PROJECT NAME: CLIENT NAME: SHEET CONTENTS: SHEET NO:
CONSTRUCTION NOTES
Proposed 3-Storey Residence w/ Deck & 2-Storey
DEBBIE ANN S. LUA JEFFERSON M. VILLARAZA
Multipurpose Bldg.
Mr. Kirk Chester Dy S-1
ARCHITECT ENGINEER