Impact of Food Waste Disposal On WWTP
Impact of Food Waste Disposal On WWTP
Impact of Food Waste Disposal On WWTP
Disposal on WWTP
Final Report
110773584 – Town of
Canmore Impact of FWD
on WWTP Evaluation
Prepared for:
The Town of Canmore
Prepared by:
Stantec Consulting Ltd.
EXECUTIVE SUMMARY
The Town of Canmore (The Town) is pursuing organics recycling, which could include using Food
Waste Disposals (FWDs) to grind household organic waste, and using the treatment plant
(WWTP) to process the organic material. FWDs are installed in sinks and are used to grind food
waste before being washed into the municipal sewer. Benefits of organics recycling include:
For these reasons, the town is investigating the potential of encouraging residents on installing
and daily use of FWDs. There are variety of names a FWD is referred to within the market, such as
in-sink grinders, garburators, insinkerators etc.
EPCOR Water Services (EPCOR) retained Stantec Consulting Ltd. (Stantec) to conduct a
feasibility-level evaluation of the effect on The Town’s wastewater collection system and WWTP
with the use of FWDs.
This report was complete in three stages, each commencing with the submission of a technical
memorandum (TM).
Technical Memorandum 1 provided a summary of the literature review which was completed by
Stantec and developed the design basis for current and expected flows and loads if the Town
were to implement FWDs.
Technical Memorandum 2 updates the existing WWTP capacity based on the revised current
flow and load projections developed in TM 1. This TM will serve as the basis for the impact of
upgrade requirements caused by implementation of FWDs.
Technical Memorandum 3 estimates the impact of implementing FWDs on the major process at
the WWTP by using the loading estimates developed in TM1 and the capacity assessment in TM
2. A high-level cost evaluation was completed to provide the town with a high-level opinion of
probable cost for the identified upgrades.
Based on the evaluation findings, using FWDs does not significantly increase household water
consumption. As such, there would be no impact to the hydraulically limited processes at the
IMPACT OF FOOD WASTE DISPOSAL ON WWTP
FINAL REPORT
WWTP. The implementation and use of FWDs will only impact biological and solids handling
systems at the WWTP.
The major upgrades caused by the implementation of the FWDs will be to the BAF system and
DAF system. All other solids handling processes either have sufficient capacity, or will require an
upgrade even without the implementation of FWDs.
At a FWD saturation rate of 50% the required WWTP upgrades would cost approximately $8.8M
over a 20-year design horizon. At a saturation rate of 100%, the upgrade cost would increase to
$10.7M over the same 20-year design horizon.
With the existing infrastructure, the WWTP will not be able to capitalize on the additional biogas
that can be produced from the digestion of organic waste. This increase in biogas, and its
utilization for power and heat at the WWTP, is considered the biggest benefit to WWTPs who
accept FWD waste. Literature suggests that if this can offset a significant portion of the
increased capital and operations and maintenance at the WWTP which is associated with FWDs,
making organics recycling at the WWTP an economical alternative when compared to
collection for disposal in landfill or composting. It should be noted that unlike the Canmore
WWTP, the WWTPs who listed additional biogas generation as a benefit were operating
anaerobic digesters before the implementation of FWDs. Construction of an anaerobic
digestion system and combined heat and power facility to generate and utilize biogas would
not be economically viable at this scale.
Implementation of FWDs can have additional risk which cannot be easily quantified. There is
potential that increased solids cause reduced capacity in conveyance systems, a potential
increase in odour production, and potential damage to equipment such as pumps.
IMPACT OF FOOD WASTE DISPOSAL ON WWTP
FINAL REPORT
TECHNICAL MEMORANDUM 1
Design Basis
Impact of Food Waste
Disposal on WWTP
Technical Memorandum 1
Design Basis
Prepared for:
The Town of Canmore
Prepared by:
Stantec Consulting Ltd.
This document entitled Impact of Food Waste Disposal on WWTPTechnical Memorandum 1 Design
Basis was prepared by Stantec Consulting Ltd. (“Stantec”) for the account of EPCOR (the “Client”).
Any reliance on this document by any third party is strictly prohibited. The material in it reflects
Stantec’s professional judgment in light of the scope, schedule and other limitations stated in the
document and in the contract between Stantec and the Client. The opinions in the document are
based on conditions and information existing at the time the document was published and do not
take into account any subsequent changes. In preparing the document, Stantec did not verify
information supplied to it by others. Any use which a third party makes of this document is the
responsibility of such third party. Such third party agrees that Stantec shall not be responsible for
costs or damages of any kind, if any, suffered by it or any other third party as a result of decisions
made or actions taken based on this document.
Prepared by
(signature)
Taha Lotia
Reviewed by
(signature)
Matthew MacPhail
Approved by
(signature)
Julian Xheko
IMPACT OF FOOD WASTE DISPOSAL ON WWTP
TECHNICAL MEMORANDUM 1 DESIGN BASIS
Table of Contents
1.0 BACKGROUND ............................................................................................................1.1
10.0 REFERENCES...............................................................................................................10.1
LIST OF TABLES
Table 3.1: Population Growth Distribution over next 20-years ............................................. 3.1
Table 3.2: Town of Canmore Population Projection (2014 - 2037)...................................... 3.1
Table 4.1: Wastewater Influent Flows ...................................................................................... 4.3
Table 4.2: Wastewater per Capita Influent Mass Loading................................................... 4.4
Table 4.3: Updated Wastewater per Capita Influent Mass Loading (2015 and 2016
Data) ............................................................................................................................ 4.4
Table 4.4: Wastewater Influent Mass Loading for next 20-years ......................................... 4.5
Table 5.1: Reference 1 (KITCHEN DISPOSAL UNITS (KDU) IN STOCKHOLM, 2008)
Data .............................................................................................................................. 5.1
Table 5.2: References Data indicating Percent Increase with the daily use of
FWDs at 100% Population Saturation ....................................................................... 5.2
Table 6.1: Impact to Wastewater Loading from FWD .......................................................... 6.4
Table 7.1: Impact to Wastewater Loading from FWD as a Percent Increase .................. 7.4
Table 7.2: Flow and Mass Loading Percent Increase with the use of FWDs ...................... 7.5
Table 7.3: Town of Canmore per Capita Wastewater Flows and Loads, including
the use of FWDs at 1% Population Saturation ......................................................... 7.5
Table 7.4: Town of Canmore per Capita Wastewater Flows and Loads, including
the use of FWDs at 50% Population Saturation ....................................................... 7.6
Table 7.5: Town of Canmore per Capita Wastewater Flows and Loads, including
the use of FWDs at 100% Population Saturation ..................................................... 7.6
IMPACT OF FOOD WASTE DISPOSAL ON WWTP
TECHNICAL MEMORANDUM 1 DESIGN BASIS
Background
August 30, 2017
1.0 BACKGROUND
EPCOR Water Services (EPCOR) retained Stantec Consulting Ltd. (Stantec)to conduct a
feasibility-level evaluation of effect on The Town of Canmore (The Town) wastewater collection
system and treatment plant (WWTP) with the usage of Food Waste Disposals (FWDs), which are
installed in sinks and are used to grind food waste before washed into the municipal sewer. The
Town is pursuing organics recycling, which could include using FWDs to grind household organic
waste and using the WWTP to process the organic material. Benefits of organics recycling
include:
For these reasons, the town is investigating the potential of encouraging residents on installing
and daily use of FWDs. There are variety of names a FWD is referred to within the market, such as
in-sink grinders, garburators, insinkerators etc.
The WWTP biosolids are currently composted at an open windrow facility in Penhold. As such,
organics disposed of using an FWD would be collected with the biosolids and composted at this
facility.
The Town of Canmore population from May 2014 civic census listed on Town’s website is 13,077
for permanent residents and additional 3,980 being non-residents. A total population of 16,967,
in addition to the population growth forecasts in the Canmore Utility Master Plan (2017), is used
as the base point of population growth.
Stantec feasibility analysis of Town’s current WWTP ability to handle the additional flow and
loading from the use of FWDs is provided in the following Technical Memorandums (TMs):
This TM is presenting a design basis for a subsequent TM which will examine the impacts on WWTP
treatment processes and associated costs of treating organics which have been disposed of by
ways of an FWD. This assessment can then be used by the Town to compare against other
methods of organics collection and treatment to determine cost-benefit and feasibility.
mm u:\110773584\water\design\report\tm1\rpt_tm1_dbm_20170629_final_r3.docx 1.1
IMPACT OF FOOD WASTE DISPOSAL ON WWTP
TECHNICAL MEMORANDUM 1 DESIGN BASIS
Work scope - TM 1
August 30, 2017
The Design Basis Memorandum (DBM) develops the design basis to evaluate the of Town’s
existing WWTP capacity to handle additional future loads and flows from the of FWDs. The
implementation of FWDs usage in the daily life at increasing Population Saturation rate is spread
out between next 20-year population projection.
First, using the population projections detailed in the “Town of Canmore Utility Master Plan (UMP),
Water and Sanitary (W899-012-.12) prepared by CIMA (2017)”, Stantec extrapolated the
population growth from 2014 to the end of the next 20-year design horizon.
Second, Stantec assessed Town’s WWTP historical influent flows and loads from available
resources and past studies to establish wastewater generation rate which were carried forward
to predict future wastewater flows and loads.
Third, Stantec researched available case studies online and literature sources effecting sewage
strength using FWDs. The researched data is extrapolated to summarize the design basis in
percent increase in sewage strength.
To conclude, we present a realistic average day and maximum month expected increase in
sewage strength and flows for the WWTP based on the literature review. This increase in loads
and flows will be used to assess the impact on the WWTP in following TMs, along with the
identifying potential risks caused by fats oils and grease and increased odour production in the
collection and treatment systems.
mm u:\110773584\water\design\report\tm1\rpt_tm1_dbm_20170629_final_r3.docx 2.1
IMPACT OF FOOD WASTE DISPOSAL ON WWTP
TECHNICAL MEMORANDUM 1 DESIGN BASIS
Population Projection
August 30, 2017
This evaluation utilizes the population growth spread out over four development horizons
detailed in Table 2 of the UMP. The population growth rates are applied to subsequent
population projection horizon of next 20 years.
The base population of year 2014 is presented as “Current” year in the UMP with growth
distribution over 6, 10, 15 year horizons, with combine service population from Town of Canmore,
Deadman’s Flats, and Harvie Heights.
The Town’s Utilities Master Plan “Current” (2014) population = 16,967 (Canmore) + 500
(Deadman’s Flats) + 400 (Harvie Heights) = 17,867
Table 3.1 presents yearly population growth rate used to determine population projection for
next 20-years horizon.
Table 3.1: Population Growth Distribution over next 20-years
Year Range Utilities Master Plan Time Line (years) Yearly Population Growth
2014-2019 0-5 455
2020-2024 6-10 458
2025-2029 11-15 520
2030-2037 16-23 478
The population horizon for the next 20-years based on this growth is presented in Table 3.1, and
will be used to estimate the sewage generation rate and strength in subsequent stages of the
evaluation.
mm u:\110773584\water\design\report\tm1\rpt_tm1_dbm_20170629_final_r3.docx 3.1
IMPACT OF FOOD WASTE DISPOSAL ON WWTP
TECHNICAL MEMORANDUM 1 DESIGN BASIS
Influent flows to the plant changes on an hourly, daily, and seasonal basis due to variation in
usage and seasonal conditions. This result in several important flow conditions to consider in the
feasibility study including:
• Average Day Flow (ADF) – The average daily flow rate occurring over the available data
period, which is used to develop flow rate ratios, establish long-term trends, and estimate
pumping and chemical cost. However, ADF is typically not a limiting capacity criteria;
• Maximum Day Flow (MDF) – The maximum flow rate occurring over a 24-hour period, which is
used in sizing equalization basins and sludge pumping systems;
• Maximum Month Flow (MMF) - The largest volume of flow anticipated to occur during a
continuous 30-day period, expressed as a daily average, which is used to indicate overall
plant capacity;
• Peak Hour Flow (PHF) – The peak flow sustained for a period of one hour during a 24-hour
period, which is used for hydraulic sizing of pumping facilities, conduits, physical unit
operations, and disinfection
• Day Load (DL) – The mass loading occurring over a 24-hour period, which is used in
estimating maximum month load; and
• Maximum Month Load (MML) – The maximum daily loads sustained for continuous 30-day
period, which is used to establish the sustained-load capacity requirements for the facility
since effluent discharge limits are permitted based on a monthly arithmetic or geometric
mean. The MML is also used for record keeping and reporting.
The ADF is calculated using current and future referenced wastewater generated flow rates
listed in the UMP, Section 4.1.7, and populating projection from Table 3.2. Following are the
referenced wastewater generation rates listed in Utilities Master Plan:
mm u:\110773584\water\design\report\tm1\rpt_tm1_dbm_20170629_final_r3.docx 4.2
IMPACT OF FOOD WASTE DISPOSAL ON WWTP
TECHNICAL MEMORANDUM 1 DESIGN BASIS
ADF
Year
(L/s)
2017 92.5
2018 94.4
2019 96.3
2020 98.2
2021 100.1
2022 102.1
2023 104.0
2024 105.9
2025 108.0
2026 110.2
2027 112.4
2028 114.5
2029 116.7
2030 118.7
2031 120.7
2032 122.7
2033 124.7
2034 126.6
2035 128.6
2036 130.6
2037 132.6
A review of the WWTP influent flow rates is currently being conducted in parallel as part of the
Influent Lift Station Phase 2 Upgrade Project. The results of that analysis, once finalized, will be
included and used for the evaluations conducted in the TM 2 and TM 3 for this project.
The historical wastewater loads per capita and monthly peaking factors are referenced from
Town’s WWTP Capacity Evaluation Report, Table 2.3. The per capita flows and loads generation
rate are listed in Table 4.2.
mm u:\110773584\water\design\report\tm1\rpt_tm1_dbm_20170629_final_r3.docx 4.3
IMPACT OF FOOD WASTE DISPOSAL ON WWTP
TECHNICAL MEMORANDUM 1 DESIGN BASIS
In review of the provided 2015 and 2016 data for influent ammonia (summarized as kg/d) and
the 2016 influent BOD, TSS, and TP (summarized as mg/L), along with an average 2016 flow rate
of 7,265 MLD and 2016 population estimate of 18,777 people, the most recent per capita
loadings are as summarized in Table 4.3.
Table 4.3: Updated Wastewater per Capita Influent Mass Loading (2015 and 2016 Data)
Based on the most recent data, it appears the per capita loadings are increasing; however, the
peaking factors have remained the same or decreased. For this evaluation, the updated per
capita loads will be used to estimate the influent mass loading for the next 20 years.
The projected wastewater loads for horizon of next 20-years are calculated using the above
projected population, historical loading per capita, and monthly loading peaking factor and
are summarized in Table 4.4, if the Town’s ratio of domestic, commercial, and industrial
wastewater contribution remains the same.
mm u:\110773584\water\design\report\tm1\rpt_tm1_dbm_20170629_final_r3.docx 4.4
IMPACT OF FOOD WASTE DISPOSAL ON WWTP
TECHNICAL MEMORANDUM 1 DESIGN BASIS
For this feasibility study, maximum month sustained loads are selected as the design basis of the
process treatment system to meet effluent discharge limits that are permitted based on a
monthly arithmetic or geometric mean. Peak hourly flow is selected as the design basis for
hydraulic sizing of influent pumping, conduits, and physical unit operations (screening, grit/scum
removal)
mm u:\110773584\water\design\report\tm1\rpt_tm1_dbm_20170629_final_r3.docx 4.5
IMPACT OF FOOD WASTE DISPOSAL ON WWTP
TECHNICAL MEMORANDUM 1 DESIGN BASIS
To evaluate the increase in Town of Canmore sewage strength with the use of FWDs, Stantec
reviewed available literature sources to estimate the change in the assessed flows and loadings.
15 case studies/literature were reviewed on the topic of usage and increase in waste in result of
using FWDs. Of the multiple articles and case study reviewed, six provided directly comparable
data to extrapolate a basis of design for the Town of Canmore. The rest either did not provide
proper context or the context was not applicable for the conclusion for this study. For example,
one study expresses the overall loading increase from FWDs would have minimal impact on
WWTP, but the waste is being generated by a small population and being treated in a large
WWTP in a nearby City Population Saturation.
The six references present projected change in sewage strength and additional water
requirement for a certain service area/town/city with implementation of the FWDs in daily
usage. Six of the case studies evaluated the effect on sewage strength from residential use and
one case study evaluated the effect from commercial use of FWDs.
In Section 5 of the KITCHEN DISPOSAL UNITS (KDU) IN STOCKHOLM, 2008 (Reference 1) the
increase in per capita mass loading associated with the use of FWD is presented in a table. The
percent increase was calculated for this report based on the per capita mass loadings
presented for household wastewater without FWD (called KDU in study) and the fraction of
organic material estimated to be added by FWDs.
Table 5.1: Reference 1 (KITCHEN DISPOSAL UNITS (KDU) IN STOCKHOLM, 2008) Data
1. Data from Reference 1, presented under Appendix 9, Table: Henriksdal’s sewage treatment plant
data from usage of FWDs at 100% Population Saturation.
The compiled data from each reference source have been converted into percent increase in
mass loading and summarized in Table 5.2. The reference material used for this study is listed
under the reference section of this document.
mm u:\110773584\water\design\report\tm1\rpt_tm1_dbm_20170629_final_r3.docx 5.1
IMPACT OF FOOD WASTE DISPOSAL ON WWTP
TECHNICAL MEMORANDUM 1 DESIGN BASIS
Table 5.2: References Data indicating Percent Increase with the daily use of FWDs at
100% Population Saturation
mm u:\110773584\water\design\report\tm1\rpt_tm1_dbm_20170629_final_r3.docx 5.2
IMPACT OF FOOD WASTE DISPOSAL ON WWTP
TECHNICAL MEMORANDUM 1 DESIGN BASIS
In an email provided by the Town to EPCOR (Andreas Comeau to Tam Tran), on July 12, 2017, it
was stated that the Town collected 3,100 tonnes of domestic waste (assumed to be annual
mass for 2016). In a discussion with the Town on August 23, 2017, it was advised that there are
dwellings which utilize private waste disposal which has not been included in the total waste
generation estimates, around 10% of the population. As such, the potential waste generated is
approximately 3,410 tonnes.
In the Regional Waste Characterization Study completed for the Town of Banff and Canmore
(2016), it was identified that the fraction of waste generated in the Town of Canmore which
would be considered organic matter (food/soiled paper) and suitable for disposal through FWD
is 36% of the overall waste generated.
To estimate the impact of introducing this organic stream into the Town’s wastewater the
following assumptions were used:
• 67% of potential organics would be processed through FWD (Kitchen Disposal Units (Kdu)
In Stockholm, 2008)
• Fraction of TSS in waste organics = 30% (Kitchen Disposal Units (Kdu) In Stockholm, 2008)
• Fraction of BOD in waste organics = 15% (Kitchen Disposal Units (Kdu) In Stockholm, 2008)
• Fraction of TAN in waste organics = 0.7% (Kitchen Disposal Units (Kdu) In Stockholm, 2008)
• Fraction of TP in waste organics = 0.1% (Kitchen Disposal Units (Kdu) In Stockholm, 2008)
Based on a total organic mass load of 1,227 tonnes (3,410 tonnes of total waste x 36% organics)
and assuming 67% of this stream will be processed using an FWD, approximately 822 tonnes/yr of
organics will be added into the wastewater collection system at 100% FWD saturation. Assuming
a 2016 population of 18,777 people, this is the equivalent of 43.8 kg/c/yr or 120 g/c/d.
Table 6.1 summarizes the increase in TSS, BOD, TAN, and TP based on the loading fractions stated
above and the organics generation estimate of 120 g/c/d.
mm u:\110773584\water\design\report\tm1\rpt_tm1_dbm_20170629_final_r3.docx 6.3
IMPACT OF FOOD WASTE DISPOSAL ON WWTP
TECHNICAL MEMORANDUM 1 DESIGN BASIS
Data Summary
August 30, 2017
TSS 76 36 112 32
BOD 85 18 103 17
Table 7.1 summarizes the percent increases in wastewater parameter based on the literature
review and the estimates developed based on the organics waste currently generated within
the town.
TSS 24 22 33 42 32 30 42
BOD 23 34 24 55 17 30 55
NH3 14 30 9 11 30
Total P 8 8.7 7 28 5 18 28
Table 7.2 presents the impact of FWD when applied at a 1%, 50%, and 100% population
saturation.
mm u:\110773584\water\design\report\tm1\rpt_tm1_dbm_20170629_final_r3.docx 7.4
IMPACT OF FOOD WASTE DISPOSAL ON WWTP
TECHNICAL MEMORANDUM 1 DESIGN BASIS
Data Summary
August 30, 2017
Table 7.2: Flow and Mass Loading Percent Increase with the use of FWDs
BOD %
0.3 0.6 15 28 30 55
Total P %
0.1 0.3 6 14 11 28
TAN1 %
0.2 0.3 9 15 18 30
Additional L/capita/d
water ay 0.04 0.04 2 2 4 4
usage
1. Reporting NH3 as TAN (Total Ammonia Nitrogen) assuming the parameters are directly
comparable. The research sources report as Ammonia (NH3), and in the Town of Canmore
available data reports as TAN (NH3 and NH4+ in water).
The total wastewater flows and mass loadings generated per capita is calculated by adding the
flow and mass loading generated by FWD listed in Table 7.2 to the Town’s estimated flows and
loadings presented in Section 4.0. Table 7.3, Table 7.4, and Table 7.5 presents Town’s per capita
wastewater flows and loads with the use of FWDs at 1%, 50%, and 100% Population Saturation.
Table 7.3: Town of Canmore per Capita Wastewater Flows and Loads, including the use
of FWDs at 1% Population Saturation
mm u:\110773584\water\design\report\tm1\rpt_tm1_dbm_20170629_final_r3.docx 7.5
IMPACT OF FOOD WASTE DISPOSAL ON WWTP
TECHNICAL MEMORANDUM 1 DESIGN BASIS
Data Summary
August 30, 2017
Table 7.4: Town of Canmore per Capita Wastewater Flows and Loads, including the use
of FWDs at 50% Population Saturation
Table 7.5: Town of Canmore per Capita Wastewater Flows and Loads, including the use
of FWDs at 100% Population Saturation
mm u:\110773584\water\design\report\tm1\rpt_tm1_dbm_20170629_final_r3.docx 7.6
IMPACT OF FOOD WASTE DISPOSAL ON WWTP
TECHNICAL MEMORANDUM 1 DESIGN BASIS
To evaluate the impact of FWDs on the Canmore WWTP, Stantec recommends the following
approach:
• Assess total Plant capacity assuming an implementation rate of 25%, 50%, 75% and100%
residential saturation for the 20 year design horizon.
If agreed upon, this approach will be carried forward for the evaluation completed in TM 3 and
will provide the Town with an aggressive and conservative impact and resulting upgrade
schedule for the Plant.
mm u:\110773584\water\design\report\tm1\rpt_tm1_dbm_20170629_final_r3.docx 8.1
IMPACT OF FOOD WASTE DISPOSAL ON WWTP
TECHNICAL MEMORANDUM 1 DESIGN BASIS
Closing
August 30, 2017
9.0 CLOSING
Upon review and confirmation by EPCOR, the population, flow, mass load, percent increase,
and saturations rates will be utilized as part of TM 3 to assess the impact on the WWTP.
mm u:\110773584\water\design\report\tm1\rpt_tm1_dbm_20170629_final_r3.docx 9.2
IMPACT OF FOOD WASTE DISPOSAL ON WWTP
TECHNICAL MEMORANDUM 1 DESIGN BASIS
References
August 30, 2017
10.0 REFERENCES
EDDY, M. &. (2013). Wastewater Engineering: Treatment and Resource - Fifth Edition. McGraw-Hill
Education; 5 edition (Sept. 3 2013).
Karlberg, T., & Norm, E. (1999). Food Waste Disposers - Effécts on Wastewater Treatment Plants .
Retrieved from A Study from the Town of Surahammar:
http://citeseerx.ist.psu.edu/viewdoc/download;jsessionid=19BABE9B076D429BF23184440E
6DFB68?doi=10.1.1.535.2690&rep=rep1&type=pdf
KITCHEN DISPOSAL UNITS (KDU) IN STOCKHOLM. (2008, May). Retrieved from Stockholm Water's
pre-study on the preconditions, options and consequences of introducing KBU:
http://food-waste-disposer.org.uk/images/downloads/2008-05-stockhlom-water-
kkskvarnar-final-english.pdf
Koning, D. J. (n.d.). FOOD WASTE DISPOSER. Retrieved from Effects on wastewater treatment
focused on additional production of biogas: http://food-waste-
disposer.org.uk/images/downloads/2004-0414-koning-j-de-food-waste-disposers-english-
tu-de.pdf
Lawitts, S. W. (2008, December 31). New York City Department of Environmental Protection.
Retrieved from COMMERCIAL FOOD WASTE DISPOSAL STUDY:
http://www.nyc.gov/html/dep/pdf/dep_commercial_food_waste_disposal_study_12312
008.pdf
NYC DEPARTMENT OF ENVIRONMENTAL PROTECTION. (1995, June). Retrieved from The Impact of
Food Waste Disposers in Combined Sewer Areas of New York City: http://food-waste-
disposer.org.uk/images/downloads/1999-nyc-dep-impact-of-fwd.pdf
mm u:\110773584\water\design\report\tm1\rpt_tm1_dbm_20170629_final_r3.docx 10.1
IMPACT OF FOOD WASTE DISPOSAL ON WWTP
FINAL REPORT
TECHNICAL MEMORANDUM 2
110773584 – Wastewater
Treatment Plant Capacity
Update
Prepared for:
The Town of Canmore
Prepared by:
Stantec Consulting Ltd.
This document entitled Impact of Food Waste Disposal on WWTP Technical Memorandum 2 WWTP
Capacity Update was prepared by Stantec Consulting Ltd. (“Stantec”) for the account of EPCOR
(the “Client”). Any reliance on this document by any third party is strictly prohibited. The material in it
reflects Stantec’s professional judgment in light of the scope, schedule and other limitations stated
in the document and in the contract between Stantec and the Client. The opinions in the
document are based on conditions and information existing at the time the document was
published and do not take into account any subsequent changes. In preparing the document,
Stantec did not verify information supplied to it by others. Any use which a third party makes of this
document is the responsibility of such third party. Such third party agrees that Stantec shall not be
responsible for costs or damages of any kind, if any, suffered by it or any other third party as a result
of decisions made or actions taken based on this document.
Prepared by
(signature)
Matthew MacPhail
Reviewed by
(signature)
Julian Xheko
IMPACT OF FOOD WASTE DISPOSAL ON WWTP
TECHNICAL MEMORANDUM 2 WWTP CAPACITY UPDATE
Table of Contents
1.0 BACKGROUND ............................................................................................................1.1
5.0 SUMMARY....................................................................................................................5.1
LIST OF TABLES
Table 3.1: Town of Canmore Population Projection (2014 - 2037)...................................... 3.1
Table 3.2: Wastewater Influent Flow Rates............................................................................. 3.2
Table 3.3: Per Capita Mass Loadings ...................................................................................... 3.2
Table 4.1: Influent Liftstation Capacity at Peak Flow............................................................ 4.2
Table 4.2: Influent Screen Capacity........................................................................................ 4.2
Table 4.3: Aerated Grit Chamber Capacity.......................................................................... 4.3
Table 4.4: Primary Clarifier Capacity ...................................................................................... 4.4
Table 4.5: Primary Effluent Screening Capacity .................................................................... 4.4
Table 4.6: UV Disinfection Capacity ....................................................................................... 4.4
Table 4.7: Solids Production Estimates .................................................................................... 4.5
Table 4.8: Revised Solids Production Estimates...................................................................... 4.5
Table 4.9: Primary Sludge Pumping Capacity ....................................................................... 4.6
Table 4.10: Recommended BAF Loading Rates ................................................................... 4.6
Table 4.11: BAF Capacity with Sidestream Treatment ......................................................... 4.7
Table 4.12: Sludge Storage Tank Capacity............................................................................ 4.8
Table 4.13: Digested Sludge Pump Capacity ....................................................................... 4.8
Table 4.14: Solids Dewatering System Capacity (Centrifuges) ........................................... 4.9
Table 5.1: Capacity and Upgrade Summary ........................................................................ 5.1
IMPACT OF FOOD WASTE DISPOSAL ON WWTP
TECHNICAL MEMORANDUM 2 WWTP CAPACITY UPDATE
Background
August 30, 2017
1.0 BACKGROUND
EPCOR Water Services (EPCOR) retained Stantec Consulting LTd. (Stantec)to conduct a
feasibility-level evaluation of effect on The Town of Canmore (The Town) wastewater collection
system and treatment plant (WWTP) with the usage of Food Waste Disposals (FWDS), which are
installed in sinks and are used to grind food waste before washed into the municipal sewer.
The Canmore Wastewater Treatment Plant (WWTP) was placed in service in 1997 and utilizes an
advanced secondary treatment process known as biological aerated filtration (BAF). The
wastewater treatment system consists of the following major components:
• Septage receiving;
• Equalization storage;
• Influent pumping;
• Mechanically cleaned influent screening;
• Aerated grit removal;
• Flash mix chemical addition;
• Enhanced primary clarification;
• Primary effluent screening;
• Two stage biological aerated filtration (BAF)
• Dissolved air flotation (DAF) for sidestream treatment of BAF backwash waste (BWW)
• Ultraviolet (UV) disinfection;
• Aerobic digestion; and
• Sludge dewatering.
The WWTP is currently required to meet the following Alberta Environment and Parks effluent
standards:
Technical memorandum 1 Design Basis establishes the flow, load, and population projections
used in this TM.
Work scope - TM 2
August 30, 2017
This technical memorandum (TM2) summarize the existing WWTP capacity based the revised
current flow and load projections developed in TM 1 and updates the upgrade timing which
was presented as part of the Canmore WWTP Capacity Evaluation (Stantec, 2012). The revised
timing for the upgrades will serve as a basis for comparing the change in upgrade timing which
is a result of implementing FWDs.
Average flow conditions were developed and presented as part of TM 1 based the per capita
wastewater generation and population growth detailed in the Canmore Utility Master Plan
(UMP), developed by BSEI. The UMP does not present the average and peak flow rates on a
yearly basis. Instead it presents an ultimate flow rate based on per capita wastewater
generation rates, the ultimate population, a calculated peaking factor, and inflow and
infiltration rate applied to a total build out of 1099.5 Ha.
The UMP states that when the population reaches 35,762 people (build out of 1099.5 Ha) the
peak wet weather flow, which includes inflow and infiltration (I/I), will be 749.1 L/s, or the
equivalent of 1810 L/c/d. With the current population of 19,232 (2017), this per capita flow rate
would result in a peak flow of 34.8 ML/d.
Using the same approach, the peak wet weather flow rates have been estimated and
summarized in Table 3.2
ADF PHF
Year
(ML/d) (ML/d)
2017 7.4 34.8
2018 7.6 35.6
2019 7.8 36.5
2020 8.0 37.3
2021 8.2 38.1
2022 8.4 38.9
2023 8.6 39.8
2024 8.8 40.6
2025 9.0 41.5
2026 9.2 42.5
2027 9.3 43.4
2028 9.6 44.4
2029 9.8 45.3
2030 10.0 46.2
2031 10.2 47.0
2032 10.4 47.9
2033 10.6 48.8
2034 10.8 49.6
2035 11.0 50.5
2036 11.2 51.4
2037 11.4 52.2
Table 3.3 shows the updated per capita mass loadings that were developed as part of TM1.
The following section evaluates and updates the existing WWTP capacity based on work
previously completed as part of the Canmore WWTP Capacity Evaluation (Stantec, 2012). The
previous evaluation had a less conservative approach to calculating peak flows. Peak flows
were calculated based on a peaking factor of 3.45 x average annual flows. As such, the peak
hourly flow for year 2037 was calculated to be around 45 MLD.
Since that evaluation, the Town experienced a flooding event in 2013 and high peak flows
during the wet weather seasons, and the resulting approach to peak hourly flow rates have
been revised. These peak flow rates are significantly higher than the 2012 evaluation, as
presented above, and will have a significant impact on the recommended upgrade timing
presented below.
This evaluation will look at the major processes and equipment and assess both the hydraulic
and mass loading capacities when applicable.
The influent liftstation (ILS) receives raw sewage from the Town’s collection system prior to
pumping it to the WWTP. This station consists of 4 centrifugal pumps and two parallel forcemains
which tie into the influent channel (2 pumps per forcemain). An upgrade was completed in
2015 which replaced two pumps with new larger pumps. A third new large pump is set to be
installed early in 2018. Following this installation, the ILS will have 1 small pump and 3 large
pumps. Due to the higher head of the larger pumps, the single small pump is only able to
operate when the large pump, which shares the same forcemain, is not in operation.
For the purpose of this evaluation, it will be assumed that the well contains three of the large
pumps. Based on the piping configuration, the pumps will have the following capacities:
Table 4.1 summarizes the process capacity of the ILS at peak flow rates.
With the 3 large pumps in operation, the Town should have sufficient capacity to handle a peak
flow event through to 2029.
Raw wastewater is currently screened through a single duty 6 mm mechanically cleaned bar
screen that was installed during the last stage of upgrades. The screen removes large materials
that can negatively affect downstream processes. A bypass channel is also available which
contains the original 15 mm coarse bar screen. Both screens are rated for 34 ML/d. Table 4.2
summarizes the process capacity of screens at peak flow conditions.
The existing screen configuration does not have sufficient capacity to handle the estimated
peak flow that could be experienced at this time. In the event of a peak that exceeds 34 ML/d,
the bypass channel can provide an additional 34 ML/d capacity, which exceeds the peak flow
during the 20-year design horizon.
Following the bar screens, wastewater enters the aerated grit chamber. Recommended
detention times for grit chambers are between 2 and 5 minutes to allow for satisfactory grit
removal.
Table 4.3 summarizes the process capacity of the grit chamber at peak flow conditions.
With a 5-minute detention time, the existing grit chamber has sufficient capacity to provide grit
removal at peak flows until 2019. However, at a minimum detention time, the grit chamber can
provide sufficient peak flow capacity past the 20-year design horizon.
The grit chamber is also designed to provide removal of fats, oils and grease (FOG) through
aerated fine bubble diffusion. The FOG is floated to the surface and transferred to sludge
processing by grease pumps. The purpose of FOG removal is to remove substances that can
interference with downstream processes, as heavy grease loads can clog pumps and pipes and
negatively affect BAF performance. Although the Canmore WWTP has had problems with
grease in the past, this has not been a significant problem since the BAF Stage III upgrade was
completed. Prior to the upgrade, there was blockage of the BAF aeration nozzles and mudball
formation in the media, part of which was attributed to fat, oil and grease carryover. Since the
upgrade, the BAFs have been operating at a higher hydraulic loading rate which has reduced
operational problems associated with the BAF system.
In the Canmore WWTP Engineering Design Evaluation, dated March 2005. CH2M Hill
recommended installing a dedicated FOG removal process to remove fat, oils and grease, or
retrofitting the existing primary clarifiers for this purpose. Based on limited problems with FOG at
this time, this upgrade will likely not be required. However, should problems arise with FOG in the
future, these upgrades may have to be reconsidered.
The Canmore WWTP has two rectangular primary clarifiers, each with a surface area of 218 m2.
The primary clarifiers used to treat a combination of influent wastewater and filter backwash
wastewater (BWW). Since they implementation of the filter backwash waste sidestream
treatment system, the clarifiers treat only influent wastewater during normal operation.
Recommended surface overflow rates (SOR) for primary clarifiers without secondary solids
recirculation are:
Table 4.4 shows the hydraulic capacity of the primary clarifiers assuming a maximum surface
overflow rate of 50 m3/m2/d for average flow rates and 120 m3/m2/d for peak flow conditions.
At average and peak flow conditions the existing primary clarifiers have sufficient capacity to
provide the recommended SOR through the 20-year horizon with both clarifiers in service.
Clarified water passes through primary effluent screening before entering the BAF. There are two
(2) automatic arc screens with 2 mm openings. The purpose of the screens is to remove large
materials that can negatively affect BAF performance. Each screen has a capacity of 46.0
ML/d, while still providing 100% redundancy.
At peak flow conditions a single effluent screen does not has sufficient capacity through the 20-
year horizon. With both screens in services, there is sufficient capacity through 2037.
The current ultraviolet disinfection (UV) system has been designed to handle a peak flow of 35.0
ML/d. The system consists of two (2) UV channels, each with a capacity of 17.5 ML/d. Each
channel has one bank of 42 Trojan 3000Plus UV lamps designed for a UV transmittance (UVT) of
65%.
The UV system does not have sufficient capacity to treat the future peak flow rates.
For that analysis, a mass balance was developed which predicted the sludge generation rates
based on the following parameters:
From the mass balance the following sludge flow rates, mass, and solids concentrations were
calculated and summarized in Table 4.7.
However, since the per capita loading used in this analysis has increased from that presented
above, the solids production estimates have been adjusted by the same percent increase in TSS
loading (23%). Table 4.8 summarizes the solids production estimates with the new per capita TSS
loading.
Sludge is drawn from several locations in the plant including the sludge and scum pumps from
the primary clarifiers and the grease pumps from the grit chamber. The sludge, scum and grease
pumps are all air operated diaphragm pumps sized for 11 L/s. This flow rate is the equivalent of
950 m3/d. Therefore, as summarized in Table 4.9, the pumps have sufficient capacity to handle
all primary sludge flow from the existing clarifier, as they were oversized during the original
construction.
Pump Capacity (L/s) Total Volume (m3/d) Population Equivalent Upgrade Year
The Canmore WWTP has a two stage biological aerated filtration (BAF) system comprised of five
(5) C-side filters followed by five (5) N-side filters. The purpose of the C-side filters is to remove
suspended solids and BOD, while the primary purpose of the N-side filters is to remove ammonia-
nitrogen.
Using the mass balance developed as part of the Canmore WWTP Capacity Evaluation
(Stantec, 2012) with the updated per capita influent loads developed in TM 1, the influent load
to the BAF with the implementation of backwash sidestream treatment is:
To meet plant effluent requirements, the maximum unit loading rates should be limited to the
unit loadings provided in Table 4.10. These loading rates were established based on an analysis
of plant operating data completed for the 2012 capacity evaluation.
Table 4.11 summarizes the updated process capacity based on the recommended BAF loading
rates and per capita loads to the BAF assuming 4 filters online, with one filter available for
standby capacity.
With four filters online and sidestream treatment of BWW in operation, the BAF system has
capacity to treat average day BOD loads through to 2019. Without the DAF in operation, which
is designed to remove 90% TSS and BOD in the recycle stream back to the primary clarifier, the
influent loading to the BAF would be significantly higher and an additional C-side filter would be
required immediately.
Operation of 5 C-side BAF cells will provide sufficient capacity to treat the BOD load through
2029. Therefore, it is recommended that 7 sets of filters be installed (6 duty + 1 standby) to
provide sufficient treatment capacity through the 20-year design horizon.
This assessment is based on the BAF providing removal efficiencies which are in line with the
original design basis and historical performance. However, the BAF system has been struggling
to provide sufficient TAN removal since December 2016. Investigation as to what has caused
the TAN removal efficiencies to decline through the BAF system is currently ongoing.
The backwash waste sidestream process, dissolved air flotation (DAF) has been installed to
reduce the total TSS and BOD loading to the BAF by reducing the recycle stream from the BAF
BWW back to the primary clarifier. The system is designed to treat a maximum daily backwash
flow of 3,600 m3/d. This flow corresponds to one (1) N-side backwash per filter per day and two
(2) C-side backwashes per filter per day, assuming 5 C-side and 5 N-side filters online.
At this time, the backwash schedule detailed herein is considered aggressive and represents a
worst-case scenario. It may be possible to reduce the number of daily backwashes, which
would reduce the load to the DAF. Based on the current backwash strategy and the upgrade
requirements for the BAF, additional sidestream treatment would be required when the WWTP
begins to operate 6 BAF trains, approximately in 2029. It is likely that the WWTP could operate
with a revised backwash schedule or revised DAF throughput and not require addition DAF
capacity through the 20-year horizon.
Initially, the sludge storage tanks were designed as aerobic digesters to stabilize primary sludge.
The two digesters each have a volume of 1,155 m3 and required to provide 40 days retention
time to provide full stabilization of the sludge. Instead of maintaining the digestion process, the
tanks are now utilized as sludge storage tanks for dewatered sludge (DAF and primary sludge)
prior to hauling the sludge away to be composted.
Table 4.12 summarizes the sludge storage capacity for the sludge storage tanks.
The existing sludge storage tanks have sufficient storage capacity to provide approximately 9
days storage though to the 20-year design horizon.
There are two (1 duty, 1 standby) digested sludge pumps which transfer sludge from the
digesters to the dewatering facility. Each pump has a capacity of 8.9 L/, which is the equivalent
of 769 m3/d.
The digested sludge pumps have sufficient capacity to surpass the 20-year design horizon.
At present, the Plant dewaters sludge using a belt filter press but is currently in the process of
replacing this system with new centrifuges. For this evaluation, it will be assumed that the existing
filter belt press will be replaced with centrifuges (Scenario-A from the proposal provide by HAUS
Centrifuge Technologies Archer Separation Processes).
• No of units 3
• Model HAUS DD 4042
• Maximum Hydraulic Capacity 33 m3/h
• Maximum Processing Capacity 21.5 m3/h
o Max Sludge Flow 215 m3/day @ 1.8% TSS
With two centrifuges in operation the system has sufficient capacity through to 2027. At this time
the system will need to be expanded or the dewatering operation modified to allow for more
sludge to be processed.
Summary
August 30, 2017
5.0 SUMMARY
A summary of the major processes capacities, driver for upgrade, equivalent population which
triggers upgrades and the year are summarized in Table 5.1
TECHNICAL MEMORANDUM 3
110773584 – Wastewater
Treatment Plant Capacity
Update
Prepared for:
The Town of Canmore
Prepared by:
Stantec Consulting Ltd.
September 1, 2017
Revision Description Author Independent Review Independent Review
A Issued for Matthew 2017- Julian 2017- Simon Meikle 2017-08-29
Review MacPhail 08-21 Xheko 08-21
B Final Matthew 2017-
MacPhail 10-18
Sign-off Sheet
This document entitled Impact of Food Waste Disposal on WWTP Technical Memorandum 3 Impact
of FWD and WWTP Upgrade Requirements was prepared by Stantec Consulting Ltd. (“Stantec”) for
the account of EPCOR (the “Client”). Any reliance on this document by any third party is strictly
prohibited. The material in it reflects Stantec’s professional judgment in light of the scope, schedule
and other limitations stated in the document and in the contract between Stantec and the Client.
The opinions in the document are based on conditions and information existing at the time the
document was published and do not take into account any subsequent changes. In preparing the
document, Stantec did not verify information supplied to it by others. Any use which a third party
makes of this document is the responsibility of such third party. Such third party agrees that Stantec
shall not be responsible for costs or damages of any kind, if any, suffered by it or any other third
party as a result of decisions made or actions taken based on this document.
Prepared by
(signature)
Matthew MacPhail
Reviewed by
(signature)
Simon Meikle
IMPACT OF FOOD WASTE DISPOSAL ON WWTP
TECHNICAL MEMORANDUM 3 IMPACT OF FWD AND WWTP UPGRADE REQUIREMENTS
Table of Contents
1.0 BACKGROUND ............................................................................................................1.1
8.0 SUMMARY....................................................................................................................8.1
LIST OF TABLES
Table 3.1: Town of Canmore Per Capita Wastewater Flows and Loads with FWD .......... 3.1
Table 3.2: Capacity and Upgrade Summary (without FWDs) ............................................. 3.1
Table 4.1: Hydraulic Impact Caused By FWD ........................................................................ 4.1
Table 4.2: Recommended BAF Loading Rates ..................................................................... 4.2
Table 4.3: BAF Capacity with Sidestream Treatment with Various FWD Saturation ......... 4.2
Table 4.4: Revised Solids Production Estimates with 100% FWD Saturation ....................... 4.3
Table 4.5: Sludge Storage Tank Capacity.............................................................................. 4.4
Table 4.6: Digested Sludge Pump Capacity ......................................................................... 4.5
Table 4.7: Solids Generation (Volume) Generated .............................................................. 4.5
Table 5.1: Impact of FWD Opinion of Probable Cost ........................................................... 5.1
IMPACT OF FOOD WASTE DISPOSAL ON WWTP
TECHNICAL MEMORANDUM 3 IMPACT OF FWD AND WWTP UPGRADE REQUIREMENTS
BACKGROUND
September 1, 2017
1.0 BACKGROUND
The Town of Canmore (The Town) is pursuing organics recycling, which could include using Food
Waste Disposals (FWDs) to grind household organic waste, and using the treatment plant
(WWTP) to process the organic material. FWDs are installed in sinks and are used to grind food
waste before washed into the municipal sewer. Benefits of organics recycling include:
For these reasons, the town is investigating the potential of encouraging residents on installing
and daily use of FWDs. There are variety of names a FWD is referred to within the market, such as
in-sink grinders, garburators, insinkerators etc.
EPCOR Water Services (EPCOR) retained Stantec Consulting Ltd. (Stantec) to conduct a
feasibility-level evaluation of the effect on The Town’s wastewater collection system and WWTP
with the use of FWDs.
The WWTP biosolids are currently composted at an open windrow facility in Penhold, AB. As
such, organics disposed of using an FWD would be collected with the biosolids and composted
at this facility.
The Canmore WWTP was placed in service in 1997 and utilizes an advanced secondary
treatment process known as biological aerated filtration (BAF). The wastewater treatment system
consists of the following major components:
• Septage receiving;
• Equalization storage;
• Influent pumping;
• Mechanically cleaned influent screening;
• Aerated grit removal;
• Flash mix chemical addition;
• Enhanced primary clarification;
• Primary effluent screening;
• Two stage biological aerated filtration (BAF)
• Dissolved air flotation (DAF) for sidestream treatment of BAF backwash waste (BWW)
• Ultraviolet (UV) disinfection;
• Aerobic digestion; and
• Sludge dewatering.
BACKGROUND
September 1, 2017
The WWTP is currently required to meet the following Alberta Environment and Parks EP) effluent
standards:
Technical Memorandum 1 establishes the flow, load, and population projections and Technical
Memorandum 2 establishes a high-level process capacity evaluation to use as a basis to
compare the impacts of implementing FWDs.
WORK SCOPE - TM 3
September 1, 2017
This technical memorandum (TM3) estimates the impact of implementing FWDs on the major
processes at the WWTP by using the loading estimates developed as part of TM 1 and the
capacity update for the WWTP completed in TM 2. This evaluation will utilize a saturation rate of
25%, 50%, 75%, and 100% to determine the impact to the WWTP over a 20-year design period.
High level costs have been included for the identified upgrades. The costs presented provide
The Town with a reasonable order of magnitude opinion of probable cost to help determine the
direction for organics recycling (FWDs vs compost) within The Town.
In addition to estimating the impact to the WWTP process, this TM will identify and discuss other
potential benefits and risks which may result for the implementation of FWDs but are not
quantifiable for this level of evaluation.
Established as part of TM 1 and through an extensive literature review, the anticipated per
capita flow and load increases which would result from implementing FWDs is summarized in
Table 3.1 and will be used to assess the impact to the WWTP.
Table 3.1: Town of Canmore Per Capita Wastewater Flows and Loads with FWD
Table 3.2 summarizes the updated WWTP upgrade requirements for The Town without the
implementation of FWDs, as presented in TM 2.
The following section evaluates the impact of implementing FWDs at saturation rates of 25%,
50%, 75% and 100% over a 20-year period. This evaluation will look at the major processes and
equipment and assess both the hydraulic and mass loading capacities when applicable.
• Influent Screening;
• Aerated Grit Chamber;
• Primary Clarifiers;
• Primary Effluent Screening; and
• UV Disinfection;
Based on the literature research, the increase in hydraulic load from FWDs is the equivalent of up
to 4 liters per capita per day (L/c/d). Table 4.1 summarizes the total hydraulic increase to the
plant at the various FWD saturation rates in 2037 assuming a population of 28,850 people.
Assuming a worst-case condition with 100% saturation rate adopted by year 2037, the increase
in flow rate the WWTP attributable to FWDs is only 0.1 MLD. Therefore, there should be no
significant impact to the process at the WWTP caused by increased hydraulic loading.
From TM 2 it was determined that the BAF system was limited by the influent BOD loading and
would require five sets of operational cells in 2019 and six sets of operational cells in 2029.
Similar to TM 2, using the mass balance that was developed as part of the Canmore WWTP
Capacity Evaluation (Stantec, 2012) along with increased loading which results from
implementation of FWDs and applying the maximum monthly load peaking factors, the influent
load to the BAF system is as follows:
In order to meet plant effluent requirements, the maximum unit loading rates should be limited
to the unit loadings provided in Table 4.2. These loading rates were established based on an
analysis of Plant operating data completed for the 2012 Canmore WWTP Capacity Evaluation.
Table 4.3 summarizes the updated process capacity based on the recommended BAF loading
rates and per capita loads to the BAF assuming 4 filters online, with one filter available for
standby capacity, and an FWD saturation of 25%, 50%, 75%, and 100%.
Table 4.3: BAF Capacity with Sidestream Treatment with Various FWD Saturation
Load BAF 25% Saturation 50% Saturation 75% Saturation 100% Saturation
Condition Capacity
Population Year Population Year Population Year Population Year
Equivalent Equivalent Equivalent Equivalent
Max 1600 kg/d 19,047 2016 <17,867 <2014 <17,867 <2014 <17,867 <2014
Month
BOD
Max 1600 kg/d 26,229 2036 24,615 2028 23,529 2026 22,535 2024
Month TSS
Max 200 kg/d 20,533 2023 20,080 2018 19,665 2017 19,249 2017
Month
TAN
With four filters online and sidestream treatment of BWW in operation, the BAF system requires an
immediate additional C side filter to have capacity to treat the influent BOD loading for all FWD
saturation rates evaluated.
An evaluation was completed using the model with the various FWD saturation loading rates to
determine the number of filters which will be required at the end of the 20-year design horizon.
For each scenario, BOD was the limiting parameter which triggers an upgrade. The number of
BAF cells ultimately required is detailed below:
Similar to the approach in TM 2 for estimating the solids production at the WWTP, revised sludge
production estimates have been adjust based on the increased load contributed by FWDs
(estimated to be 30%).
Table 4.4: Revised Solids Production Estimates with 100% FWD Saturation
The current sludge pumps have a capacity of 11 L/s or 950 m3/d. Assuming a 100% FWD
saturation rate, the revised total primary sludge generation rate is 195 m3/d, which is still
significantly less than the total pumping capacity. Therefore, no upgrades are required for the
primary sludge pumps.
The sidestream backwash waste treatment system, or dissolved air flotation (DAF), is designed to
treat a maximum daily backwash flow of 3,600 m3/d. This flow corresponds to one (1) N-side
backwash per filter per day and two (2) C-side backwashes per filter per day. Since there are
five (5) C-side and five (5) N-side filters this corresponds to a maximum of fifteen (15)
backwashes per day.
It is possible that additional sidestream treatment capacity is not required if one or two
additional BAF cells are added to the process. Instead, backwash frequencies and rates, and
polymer dosing to the DAF could be used to help control the flow to the DAF system.
Based on this, it is possible that no additional sidestream treatment would be required with a 25%
FWD saturation rate. However, at 50% the WWTP would require 2 additional C-side filters and 1
additional N-side filter to be in operation, which would likely require trigger expansion to the DAF
system.
Initially, the sludge storage tanks were designed as aerobic digesters to stabilize primary sludge.
The two digesters each have a volume of 1,155 m3 and are required to provide 40 days retention
time to provide full stabilization of the sludge. Instead of maintaining the digestion process, the
tanks are now utilized as sludge storage tanks for dewatered sludge (DAF and primary sludge)
prior to hauling the sludge away to be composted.
Table 4.5 summarizes the sludge storage capacity for the sludge storage tanks.
The existing sludge storage tanks have sufficient storage capacity to provide approximately 7
days storage though to the 20-year design horizon. The WWTP will not require additional sludge
storage capacity through the 20-year design horizon as a result of the implementation of FWDs.
There are two digested sludge pumps (1 duty, 1 standby) which transfer sludge from the
digesters to the dewatering facility. Each pump has a capacity of 8.9 L/s, which is the equivalent
of 769 m3/d.
The digested sludge pumps have sufficient capacity to surpass the 20-year design horizon even
with a 100% FWD saturation rate.
As in TM 2, Stantec assumes that the existing filter belt press will be replaced with centrifuges
(Scenario-A from the proposal provide by HAUS Centrifuge Technologies Archer Separation
Processes).
Table 4.7 summarizes the estimated total sludge volume which will need to be dewatered for the
various saturation rates at the 20-year design horizon.
25 274
50 293
75 313
100 332
Based on the current upgrade assumptions for the new dewatering facility, each centrifuge has
a capacity of 107 m3/d. If The Town were to see a 25% saturation rate of FWDs, the dewatering
facility would be required to operate up to 3 centrifuges per day, or extend dewatering
activities past 7 hours/d.
With a saturation rate of 100%, the WWTP would need to operate 3 centrifuges and extend the
dewatering activities past 7 hours/d to eliminate the need for a 4th centrifuge.
Based on the evaluation completed in TM 2, the WWTP is expected to require a dewatering
facility expansion even if it does not implement FWDs. Therefore, for this exercise it has been
assumed that no additional costs are associated with the FWDs for a future dewatering facility
expansion.
The following section develops a Class D order of magnitude (+/- 30%, ASTM E 2516-01) opinion
of probable cost for the impact of the FWDs at the various saturation rates. Based on the
capacity impact evaluation previously presented herein, the processes which require upgrades
are:
Costs for the BAF expansion will be based on the construction cost for the last BAF expansion,
which was tendered in 2008 for $5.7M and included the construction of one C-side and one N-
side filter (with channels and ancillary equipment). Applying an inflation rate of 12.6% (Bank of
Canada) for 2008 to 2017, this expansion would cost $6.4M today. For this evaluation, we have
estimated that the installation of a single BAF cell would be approximately 70% of the total cost,
or $4.5M to the fixed costs of a new construction project.
Costs for expanding the sidestream treatment facility will be based on the tender cost for the
original DAF expansion, which was tendered in 2014 for $4.3M. With inflation, this cost would be
$4.5M in 2017 dollars.
Table 5.1 summarizes the upgrade requirements and estimated cost based on the impact of the
various FWD saturation rates. The upgrade requirements listed are for upgrades which would be
directly attributable to the FWDs and do not include upgrades identified for the WWTP in TM 2
(with no FWDs).
FWD Saturation Rate (%) Process Upgrade Upgrade Cos (2017 CAD)t
Total $0
50 BAF – One C-Side Filter $4.5M
DAF – Expansion Required $4.5M
Total $9.0M
75 BAF – One C-Side Filter $4.5M
DAF – Expansion Required $4.5M
Total $9.0M
100 BAF – Two C-Side Filter $6.4M
DAF – Expansion Required $4.5M
Total $10.9M
It should be noted that, additional upgrades to the solids system will be required with or without
the implementation of FWDs, such as the expansion of dewatering facility. Implementation of
FWDs will accelerate the upgrade schedule to the affected solids systems.
Implementation of FWDs will also increase the operations cost at the WWTP. Based on the
current installed equipment and additional equipment necessary for the expanded BAF and
DAF systems, the WWTP could expect an increase in the total power consumption of about 10 -
12%.
Additional solids generated at the WWTP could also increase the wear on existing equipment
and will need to be handled and hauled away. This additional operational effort caused by
FWDs is difficult to estimate. The findings within literature vary and suggest it is dependent on the
WWTP design and its flexibility/durability. However, additional operating costs would be partially
offset by reducing the amount of waste pickup/hauling within the town.
Literature suggest that there are potential benefits to WWTPs who accept FWD processed
organic household waste. These benefits include:
Currently, the WWTP does not digest their biosolids. There are two aerobic sludge tanks which
are used to store the sludge that is to be dewatered before it is trucked to away. In order to
generate and utilize biogas the WWTP would require the construction of two anaerobic digester
tanks (approx. 25 - 30m diameter) with new digester pumphouse and equipment, and a new
heat and power facility. The significant cost to construct these upgrades would make
anaerobic digesters economically unviable at this scale. As such, the potential benefits of
increased biogas production have not been further evaluated as part of this TM.
With the BOD loading having been previously identified as the limiting factor on the BAF system,
the increased carbon load is not considered beneficial to the Town’s WWTP.
• Sedimentation
• Odour
• Fats Oils and Grease (FOG)
• Equipment Damage
• Carbon to Nutrient Ratios
7.1 SEDIMENTATION
With the increased suspended solids, there is a concern that there would be increased settling,
or sedimentation, within the collection system. Sedimentation can lead to unwanted deposits
within lift stations and pipes, which can reduce capacity through pipes, and create septic
conditions within lift stations wet wells. Discussions in literature show there is no clear link
between FWDs and inherent issues with sedimentation. This would be expected as any
sedimentation issue would be isolated and completely dependent on the design and operation
of the specific sections of the collection system.
In discussion with EPCOR operators, existing sedimentation concerns have been identified within
the collection system especially during periods with lower flow rates. During these periods, the
velocity in the forcemains are quite low upstream of the lift stations, which causes solids to settle.
At this time, there is no way to flush or inspect these sections of forcemain.
Areas where sedimentation is or has been an issue, increased solids generated by FWDs would
represent a further risk to that section of the collection system.
7.2 ODOUR
With the increase in organics, another concern for the collection system is the potential for
increased hydrogen sulfide production, or odour. This would be more predominant if increased
sedimentation were to occur in the collection system. Organics concentration, residence time,
and oxygenation govern hydrogen sulfide production. Given that typical municipal wastewater
has a significant quantity of organics already, any further increase in organics loading in the
collection system is unlikely to cause increased hydrogen sulfide production and corresponding
odour issue unless an issue already persists. Odour issues would most likely occur in stagnant
water (wet wells), anaerobic pressure systems, and ultimately at the WWTP.
Currently, odour complaints are typically caused from the WWTP or where forcemains switch to
gravity mains in sewer manholes. Lift Station 10 also generates some odour complaints.
However, there is conflicting evidence in literature regarding the impact of increased FOG
caused by FWDs. Some of the reviewed literature and studies state there is no noticeable
increase in FOG or blockages within the sewer system resulting from the implementation of FWDs
(for example, Evan TD et al. Surhammer: A Case Study on the Impacts of Installing Food Waste
Disposers in 50% of Households. 2010). Other studies suggest that FWD will result in an increase in
FOG and sewer blockages (For example, NYC Department of Environmental Protection. The
Impact of Food Waste Disposers in Combined Sewer Areas of New Your City. 1999).
While FOG can cause severe fouling within the collection system, there has been no definitive
link between FWDs and a significant negative impact to the sewer system. Areas which already
have a noticeable FOG problem, or problems in the past, such as the WWTP, would be more
susceptible to increased problems caused by increased FOG loading.
EPCOR has stated that there have been some serious blockages due to grease buildup in mains.
This is mostly attributed to local restaurants in the commercial areas. Large amounts of grease
have been cleared during routine flushing of commercial areas such as Railway Ave, Main St.
and Bow Valley Trail. At the WWTP, FOG has been attributed to plugging nozzles in the BAF.
Given that each municipality has a unique collection system (varying pressure, interconnections,
capacities, gravity vs pressurized, etc.) it is difficult to quantify the impacts of implementing FWDs
on The Town’s collection system. A reasonable approach would be to assume that
implementing FWDs would likely compound existing known issues within the collection system,
but should not cause any significant risk to areas that are currently operating normally.
load, or ratio, to properly remove nutrients carbon, nitrogen, and phosphorus. Typically, this ratio
is 100 carbon : 10 nitrogen : 1 phosphorus. If the WWTP does not have sufficient nitrogen or
phosphorus, the biological system will not be able handle a significant increase in carbon
loading.
Currently, the Plant operates using 6mm mechanically cleaned screens located at the head of
the plant, followed by primary clarification and then 2.3mm arc screens ahead of the BAF
system. A fraction of FWD processed organics will be captured at the influent screens but the
majority (60%) has been shown to settle in the primary clarifiers. Solids carry over in the primary
effluent will be captured on the screens if larger than 2.3mm. Solids captured on the arc screen
and primary sludge are both sent to the sludge storage tank, where they are dewatered and
sent for composting.
Based on this current operation, there is minimal risk of FWD waste being diverted to landfill
from the WWTP. Only the FWD solids that are collected on the 6mm bar screen would be sent
to landfill at this time.
Summary
September 1, 2017
8.0 SUMMARY
Using FWDs does not significantly increase household water consumption. As such, there would
be no impact to the hydraulically limited processes at the WWTP. The implementation and use
of FWDs will only impact biological and solids handling systems at the WWTP.
The major upgrades caused by the implementation of the FWDs will be to the BAF system and
DAF system. All other solids handling processes either have sufficient capacity, or will require an
upgrade even without the implementation of FWDs.
It is not anticipated that there would be a significant impact to the WWTTP with an FWD saturation
rate of 25%. However, at a FWD saturation rate of 50% the required WWTP upgrades would cost
approximately $8.8M over a 20-year design horizon. At a saturation rate of 100%, the upgrade
cost would increase to $10.7M over the same 20-year design horizon.
With the existing infrastructure, the WWTP will not be able to capitalize on the additional biogas
that can be produced from the digestion of organic waste. This increase in biogas, and its
utilization for power and heat at the WWTP, is considered the biggest benefit to WWTPs who
accept FWD waste. Literature suggests that if this can offset a significant portion of the
increased capital and operations and maintenance at the WWTP which is associated with FWDs,
making organics recycling at the WWTP an economical alternative when compared to
collection for disposal in landfill or composting. It should be noted that unlike the Canmore
WWTP, the WWTPs who listed additional biogas generation as a benefit were operating
anaerobic digesters before the implementation of FWDs. Construction of an anaerobic
digestion system and combined heat and power facility to generate and utilize biogas would
not be economically viable at this scale.
Implementation of FWDs can have additional risk which cannot be easily quantified. There is
potential that increased solids cause reduced capacity in conveyance systems, a potential
increase in odour production, and potential damage to equipment such as pumps.