Best Practice in Acquiring A Mine Closure Certificate - A Critical Analysis of The de Beers Oaks Diamond Mine, South Africa
Best Practice in Acquiring A Mine Closure Certificate - A Critical Analysis of The de Beers Oaks Diamond Mine, South Africa
Best Practice in Acquiring A Mine Closure Certificate - A Critical Analysis of The de Beers Oaks Diamond Mine, South Africa
Beersing (eds)
© 2011 Australian Centre for Geomechanics, Perth, ISBN 978-0-9870937-1-4
doi:10.36487/ACG_rep/1152_108_Botham
N.D. Botham Department of Geography, Environmental Management and Energy Studies, University of
Johannesburg, South Africa
C.J. Kelso Department of Geography, Environmental Management and Energy Studies, University of
Johannesburg, South Africa
H.J. Annegarn Department of Geography, Environmental Management and Energy Studies, University of
Johannesburg, South Africa
Abstract
The Minerals Act 50 of 1991 set a precedent in South Africa for mining and environmental legislation as it
considered all factors pertaining to mining, specifically with respect to mine rehabilitation and closure. The
Minerals Act No. 50 of 1991 was replaced by the Mineral and Petroleum Resource Development Act
(MPRDA) No. 28 of 2002, which included far more stringent conditions related to mine closure. In addition,
as of 2010, mining became a listed activity and the environmental provisions of the National Environmental
Management Act (NEMA) 107 of 1998 now also apply to mine closure certification resulting in mines having
to comply with stipulations of this act too before qualifying for closure. No mine closure certificate has ever
been issued under either the Minerals Act of 1991 or the Mineral and Petroleum Resource Development Act
of 2002. The authorities are reluctant to accept responsibility for granting closure, without being persuaded
beyond doubt that all risks (environmental, social, health and safety) have been adequately and sustainably
dealt with. In this paper, the authors use a case study and interview approach to critically examine the mine
closure procedure of the De Beers Oaks Diamond Mine, Limpopo, as it is anticipated that this mine will be
the first in South Africa to acquire a full mine closure certificate, as it has stringently followed all relevant
legislation and policy directives, and openly communicated with relevant departments at all levels of
government. The objectives of the paper are to stipulate the legal requirements for mine closure certification
in South Africa and to critically analyse the mine closure procedures that were followed in the closure plan
for the Oaks Diamond Mine. Specific challenges and actions taken to implement the closure plan are
highlighted. Results indicate that the most effective way of acquiring a mine closure certificate is to integrate
legislation with procedures throughout the life cycle of a mine.
1 Introduction
In South Africa, mining contributes significantly to the economy, generates economic growth and
employment opportunities. For example, in 2010 mining and quarrying contributed 5.5% of the South
African GDP, which is far greater than the 2.2% contribution of agriculture, forestry and fishing, but less
than the 15.3% contributed by manufacturing (StatsSA, 2011). However, beyond its significant economic
benefits, mining has also impacted negatively on the environment, producing impacts such as land surface
subsidence, air and water pollution, and disruption in drainage systems (Cao, 2007). Thus it has created a
significant negative economic, social and environmental legacy in South Africa (Swart, 2003). Development
priorities in South Africa are currently focussed on addressing the inequalities created under apartheid
policies, which have led to an emphasis on “black economic empowerment, bridging the historical wealth
divide and providing access to land” (Limpitlaw, 2004). Limpitlaw (2004) predicts that mining in South
Africa will continue regardless of the fact that associated environmental losses may outweigh economic
benefits because of its economic importance.
More recent South African mining legislation has shifted the responsibility and the cost of mitigating all
negative environmental impacts of the mining process onto mining companies. This has been done through
the establishment of stringent mine closure regulations, as part of the Mineral and Petroleum Resource
Development Act 28 (MPRDA) in 2002. All mines now have to acquire a mine closure certificate in order to
effectively close a mine. Mines should also comply with sections of the National Environmental
Management Act (NEMA) 107 of 1998 and the National Water Act 36 (NWA) of 1998, in order for the
closure certificate to be obtained. However, no mine in South Africa has yet been able to acquire a closure
certificate as required by the Department of Mineral Resources, or its predecessor the Department of
Minerals and Energy. This paper seeks to highlight the best possible mine closure practices through the
review of all applicable legislation and a critical examination of the closure procedure of the Oaks Diamond
Mine (Oaks Mine) owned by De Beers Consolidated Mines Ltd (henceforth known as De Beers), anticipated
to be the first mine to obtain a closure certificate, as a possible model for acquiring mine closure
certification.
be noted that this legislation should be utilised in the closure of other mines in South Africa; however, in
other cases additional legislation may also apply depending on the specific nature of the mine and its
processing activities. Future changes and additions in the applicable laws will also need to be taken into
account.
substance that was/is likely to cause pollution of a water resource (Lala, 2008). This was achieved through
the effective design of a pit to capture all polluted groundwater (discussed further in Section 4.1).
Tool 2 rapidly assesses the existing mine closure plan in order to determine gaps in knowledge, and
identifies the level of detail still needed to be included in the closure plan, comparative to the current time
constraints. An assessment was carried out in order to ensure that all objectives were being met and that
effective closure was taking place. This rapid assessment assesses: physical closure criteria; bio-physical and
rehabilitation criteria; stakeholder engagement and social closure criteria; closure cost estimates; programme
and cash flow criteria; and the integrated closure plan. Tool 3 determines the best ways to fill in the gaps in a
closure plan by selecting the best approaches, technologies and resources (Mban, 2008).
applications were submitted to the DME in 2009 so that the closure approval process and issuing of a closure
certificate could commence. De Beers’s main objective in terms of closure was to strive toward achieving
closure that would be wholly acceptable and serve as a benchmark for other De Beers mines (ERM, 2008).
Therefore, the Oaks Mine served as a reference site which provided a credible site for rehabilitation and
provided extensive information on the way in which the rehabilitation progressed and was achieved
(Tongway, 2008).
The objectives developed by De Beers for physical and bio-physical closure were divided into two sections.
Firstly, the reclamation objectives for restorable land which include the provisos that: the land must be left in
a safe condition; the land must be chemically and physically stable; waste will be managed responsibly and
in line with legislation; all infrastructure not required for post-closure land use will be removed; a sustainable
growth medium and indigenous vegetation layer must be established; and the land must be restored to a state
that is suitable for wild life. Secondly, the rehabilitation objectives for non-restorable land which include the
provisos that: the land must be left in a safe condition; the land must be chemically and physically stable;
waste will be managed responsibly and in line with legislation; and a suitable growth medium and
indigenous vegetation layer must be established (ERM, 2008).
(2008) proposed that the concrete be covered with approximately 1 m of waste rock and 300 mm of topsoil,
and then ameliorated and seeded. This proposal was used as it does not affect land availability as the plant
area was less than 0.05% of the total 5,300 ha. The concrete is also inert and does not pose a threat to the
environment. Once this was achieved the area was rehabilitated to match the surrounding topographical
profile so that it is presently indistinguishable from the surrounding terrain.
monitored bi-annually for three growing seasons by an external consultant (Prof. Faan van Wyk) and thus far
the results have indicated a good re-establishment of vegetation cover, both annuals and perennials. In
addition, woody species are establishing as well.
The final closure plan states that prior to the sale of the land, De Beers would manage and monitor the area
in order to ensure that the vegetation was growing effectively and the biodiversity continued to strengthen.
On this particular mine, the actual mining area is small in comparison to other mines, with most of the
property undisturbed by mining activities and as a result is in pristine condition, thus resulting in a small
monitoring area. Monitoring of the site includes identifying and eradicating alien invasive species; biannual
surveying of the area until fully restored; and evaluating the populations of faunal species to ensure that these
species do not exceed the sites carrying capacity. The good condition of the farmland surrounding the mine
is largely due to the removal of cattle in the early days of the mine which were replaced with game on a
controlled basis.
5 Conclusions
The most effective way of acquiring a mine closure certificate is to integrate legislation with procedures
throughout the life cycle of a mine. In the case of the Oaks Mine, legislation was integrated with the AAplc
toolbox establishing an effective way for acquiring closure. Even though planning was accelerated towards
the end of the life of mine, all physical and biophysical objectives were met. All reclamation objectives were
met and done in an effective manner, resulting in the area resembling that of its surroundings. Most of the
rehabilitation objectives were also met but some risks were still present, for example the possible pit wall
failure and alternatives to backfilling of the pit having to be sought. De Beers addressed these issues by
developing a safety zone and constructing a game fence surrounding the pit.
In terms of the socio-economic closure parameters, De Beers did cater for all employees and ensured that
they had employment after closure. De Beers also ensured that the community was socially and
economically uplifted by providing the necessary tools to manage and operate farms and mines as well as
renovating and rebuilding schools and day care centres in the area. Government was also consulted
constantly, in order to establish a good relationship and to fulfil all legal closure requirements, thus
strengthening the ability of the Oaks Mine to acquire a closure certificate. Even though some stakeholders
were dissatisfied with the outcomes, De Beers did comply with legislation and achieved all social goals
developed.
In conclusion, it is anticipated that the Oaks Mine will be the first mine in South Africa to acquire a full
closure certificate. With the exception of one or two steps that needed to be adapted during the closure
process, most of the processes and many of the lessons could be used as a benchmark for all other mines
wishing to achieve closure. The main lesson learnt is that one should design, plan and operate a mine
understanding the closure vision and final land use plan and not see closure planning as a event at the end of
the life of mine that will be addressed in the final five year of operating life. Even though the Oaks Mine did
experience some problems during the closure process, closure was still effective and resulted in a restored
natural and social environment with minimal impacts. Thus achieving the company’s main objective and
fulfilling the main legal closure requirements, which was to avert or minimise negative environmental
impacts and to create a self-regulating natural ecosystem.
Acknowledgements
The authors thank De Beers and Anglo American for providing extensive information on the Oaks Mine, its
closure procedures, and the AAplc toolbox. A special thanks to Chris Sivertsen, Ruldoph Botha, Chantelle
Du Plessis, Mphoya Thobela, and Philadelphia Lala for being part of the interview process and providing all
relevant information for the completion of this paper.
References
Botha, P.R. and Coombes, P. (2007) Anglo American Mine Closure Toolbox Version 1, Compiled for Anglo American
plc, by Anglo Technical Division, Johannesburg.
Cao, X. (2007) Regulating mine land reclamation in developing countries: the case of China, Land Use Policy, Elsevier,
Vol. 24, July 2007, pp. 472–483.
DEAT (1998) Department of Environmental Affairs and Tourism. National Environmental Management Act,
Government Gazette, Vol. 401, No. 19519.
DEAT (2004) Department of Environmental Affairs and Tourism. National Environmental Management: Air Quality
Act, Government Gazette, Vol. 476, No. 27381.
DME (2002) Department of Minerals and Energy. Minerals and Petroleum Resources Development Act, Government
Gazette, Vol. 448, No. 23922.
DWAF (1998) Department of Water Affairs and Forestry. National Water Act, Government Gazette, Vol. 398,
No. 19182.
ERM (2008) Environmental Resource Management. Final Closure Plan (July), The Oaks Mine, report prepared for De
Beers Consolidated Mines, Johannesburg (confidential, cited with permission).
Garcia, D.H. (2008) Overview of international mine closure guidelines, in International Professional Geology
Conference, 20–24 September, Flagstaff, USA, American Institute of Professional Geologist, Flagstaff, pp. 1–9.
Lala, M.P. (2008) Statutory obligations with regards to the closure of the Oaks Diamond Mine (January, 2008), created
for De Beers Consolidated Mines, Johannesburg (confidential, cited with permission).
Limpitlaw, D. (2004) Mine closure as a framework for sustainable development, in Proceedings Sustainable
Development Practices on Mine Sites – Tools and Techniques, 8–10 March, Johannesburg, South Africa,
University of the Witwatersrand, Johannesburg, pp. 1–11.
Mban, M. (2008) Planning for mine closure at De Beers Consolidated Mines – an integrated approach, Proceedings
Third International Seminar on Mine Closure (Mine Closure 2008), A.B. Fourie and M. Tibbett, I.M. Weiersbye,
P. Dye (eds), 14–17 October 2008, Johannesburg, South Africa, Australian Centre for Geomechanics, Perth,
pp. 21–26.
Peck, P. and Sinding, K. (2009) Financial assurance and mine closure: stakeholder expectations and effects on operating
decisions, Resources Policy, Elsevier, Vol. 34, March 2009, pp. 227–233.
StatsSA (2011) Statistics South Africa. Statistical Release P0441, Gross Domestic Product, Fourth Quarter 2010,
Pretoria, p. 10.
Swart, E. (2003) The South African legislative framework for mine closure, The Journal of the South African Institute
of Mining and Metallurgy, Vol. 103, pp. 489–492.
Tongway, D.J. (2008) Facilitating mine closure with a continuous analysis and review system, Proceedings Third
International Seminar on Mine Closure (Mine Closure 2008), A.B. Fourie and M. Tibbett, I.M. Weiersbye,
P. Dye (eds), 14–17 October 2008, Johannesburg, South Africa, Australian Centre for Geomechanics, Perth,
pp. 195–206.