Case Study
Case Study
Case Study
of the Month
1. Introduction: For the last few months, the response of the readers
to the case studies on various incidents is overwhelming. Hence this
month we are again choosing the write up on similar kind of studies
for developing the synchronization of practical observation to the
theoretical concepts. The analysis of each incident being supported by
actual observations had been described during the situation to add
awareness amongst the operation, testing and commissioning engineers
to know the cause of problems and be helpful for easy rectification
of the problems. This can also help to develop economic schemes for Fig 2.1.1.a. Damaged insulator string
the smooth running of the operation and control system in the Grid
Sub-Station.
2.1. Damage of Porcelain Disc Insulator: In a typical 220KV EHT Line, it
was observed with damage of porcelain disc insulator.
Observations
1. During patrolling by line inspecting team, it was found with damage
of suspension string insulator at two different places. (Ref Fig 2.1.1.a Fig 2.1.1.b. Damaged insulator string
and Fig 2.1.1.b) 2. The intermittent discs were found damaged instead of starting or end
disc.
w w w. e l e c t r i c a l m i r r o r. n e t
in Fig 2.2.1).
the team.
Technical Analysis
1. From the above observations, the cause of failure of the
insulator discs are due to lightening effect across the discs.
2. During the case of Back Flashover and then with front
flashover, the weak discs are supposed to be suffered with Fig 2.2.1.a CT Fig 2.2.1.b CT with Double Fig 2.2.2 Burning of
groove Pad Clamp
damage if minor cracks remain in the disc. with Insulator stack Internal insulation
3. The lightening phenomenon could be explained below. 5. Both the fail CTs were investigated and found with similar
nature of failure with oozing of the oil, burning of the
internal insulation etc...
a. Suppose lightning strikes on the tower point, then surge
current should have to discharge immediately to ground Technical Analysis:
through TFR (Tower footing resistance) without developing 1. The detail TANK design was investigated and found with
any voltage rise on the tower structure. some lacunae.
b. But in the event of higher TFR and dis-continuity of earth a. This CT was having primary links with external studs in
wire etc... certain voltage is developed on the tower, more connection.
than the per phase voltage of the in service line conductor. b. Each Stud has insulator stack to separate direct touch from
So, it was observed with voltage across the insulator strings. the main tank.
c. If the potential difference becomes more that the BIL of the c. Each link has U face groove instead of round hole, that
string, flashover results across the discs from Tower point to has less contact surface.
Line Conductor (Called BACK FLASH). So the surrounding d. The final stud for connection of Double Groove Pad clamp
air medium gets ionize, causing a conducting path across and connecting jumper is not that strong to accept the
the insulator string. Now FRONT FLASH OVER does occur tension of the conductors.
from line conductor to Tower cross arm. This time the line 2. Moreover, the pattern of Double conductor connection with
trips actuating the relay at sub-station. its supporting was putting tension on the pad clamp.
4. Because of Two times flashover (BACK FLASH and then 3. As CTR is of 1200-600-300/1 with multi ratio CT has more
FRONT FLASH), the weak insulator disc may fail. hardware connection due to primary link control.
Rectification and action Taken 4. Because of these above issues, the insulator stacks (As
1. The Tower footing resistance was improvised by adding shown in white colour) used to suffer with certain stress
extra earth pit on the towers of the affected zone. and results with minor shrink and leakage of oil.
2. The combined TFR was measured and found within limit. 5. As these CTs are top Beam mounted, sometimes the
3. All earth terminal connection at the Tower top point was physical inspection is neglected by the grid personnel. If
tightened regarding the connection of earth link. left unattended, then leaking of oil may attract entry of
||www.electricalmirror.net|| || June 2022 || ELECTRICAL MIR R OR 57
Case Study
was tripping on E/F relay frequently for the load current more 1. Reduction of the impedance/resistance path of the operating
than approximately 45 Amp. Line CTR = 200/1, Setting of coil circuit.
E/F PSM= 0.1 2. DC earth leakage and development of higher voltage across
Steps attempted the operating system.
Load current was restricted to 30 amperes for measurement 3. Earthing/ touching to body during DC earth leakage condition.
of secondary current in the Back up core. The currents are
measured and tabulated as in the following Table-2.3
Observations: -
1. This observation was found both in the LOCAL and REMOTE
Table-2.3 Closing of the breaker.
Phase / Wire No. Current in m Amp. Remarks 2. Even on Hand tripping condition also.
R ph. C11 184 Doubt? 3. Sparking of auxiliary contacts (63 AGX and 47TX) relays
Y ph. C31 151 O.K on breaker cubicle for testing of individual tripping of the
B ph. C51 153 O.K breaker pole, while testing of pole discrepancies.
E/F C71 38 Doubt? 4. The pole discrepancy circuit seems to be incomplete as
C11+ C31 172 Doubt? observed.
C31+ C51 152 O.K Rectifications:
C11+ C51 176 Doubt? 1. The cables used for the remote closing and tripping of the
Conclusion of the readings breaker was checked and found in order.
From the readings of Back-up core as described in the table, it 2. While checking the LOCAL TNC switch, the fault was detected
got concluded that “R” phase CT is associated with wrong CTR, and the same was replaced by a good one and both LOCAL
may be due to saturation of core or wrong primary connection. and REMOTE closing were checked and found OK.
The detail secondary circuit of R phase was checked and found 3. Tripping operation at Local was checked by removal of the
O.K. But on physical verification it was found with the carbonized cable used for remote operation and found in order.
opening of one link on Primary side of the CT (Ref. Fig 2.3) 4. While checking the hand tripping from remote end the
following defects were again observed.
a. Auxiliary contact used for Y Phase Post Supervision purpose
found burnt (63AGX) for trip coil-2
b. TSR of this Y phase was also found defective
c. Remote TNC switch TRIP contact also found defective
5. Rectification of point (a): - Another parallel relay was