FCI- POLE 20FT DATASHEET

20ft Steel Pole Installation


1. Select a suitable site for the Steel Pole and prepare the pad site using a hole 36" x 36" x
36" deep. The top of the concrete foundation should be flush with the ground.
2. Be sure that there are no underground electric or phone cables, gas or water lines in the
area where the pole will be located.
Special attention must be paid to the size of the wiring conduit and its location within the
concrete foundation and jig. The Wiring Conduit can be up to 2" in diameter. Use reducers if
necessary. Also, make sure that the Wiring Conduit is in the center of the foundation and
Anchor Jig during installation.
3. To help reinforce the concrete foundation, place (12) 1/2” diameter x 32” long
Reinforcement Bars (”rebar”). Use suitable preparation methods to place the rebar.
4. FOR ANCHOR BOLT INSTALLATIONS:
Pour concrete per directions on the dimensions of the bolt pattern and suspend
appropriate bolts in the concrete around the wiring conduit. Leave 2” to 3” of the BOLTS
protruding above the pad. If you are using leveling nuts, leave 4” to 6” protruding.
Prepare the concrete per manufacturer's directions. The concrete must have a
compressive strength of 3000 psi, and must be fabricated following ACI318-89
requirements. Allow the concrete foundation to cure thoroughly before proceeding with the
installation.
Be sure that the pole is oriented properly, with the carriage
5. Place the pole on the pad with the holes on the Base Plate aligned with the bolts of the
anchor bolts or anchor jig
6. Remove the access opening plates at the bottom and top.
7. Insert the wiring into the 3" diameter hole in the base of the pole up, into and out of the
bottom access opening. Make sure all slack is pulled completely through.
8. Insert connecting wiring into the bottom access opening, run through the pole up to the
top access opening. Insert the end through the housing connecting hole. Close the top
access opening and make necessary wiring connections at the bottom access opening
9. Slowly lift the pole into the upright position, aligning the holes of the Base Plate with the
Bolts in the concrete pad
10. Secure the pole to the pad with fasteners
11. Thread two (2) nuts onto each of the (4) bolts). The end with 6" of clearance will be the
top of the Anchor Jig, the end with 1 1/2" clearance will be the bottom.
Because of surface conditions it may be necessary to use leveling nuts. See step 5 below
for information.
12. Place the short end of each Bolt into the outside holes of the Cross Strap. Place Hex
Nuts onto each Bolt and finger tighten
13. Turn the Anchor Jig over and place Single Straps over the Bolts.Use the inside hole of
each strap. Place Hex Nuts onto each Bolt and finger tighten.

14. Before using the Anchor Jig verify that the center to center dimensions between the bolts
are even. If not, adjust accordingly. Firmly tighten all Hex Nuts.
15. Standard installation without leveling nuts.
16. If, due to conditions or other requirements, leveling nuts are needed, adjustments will
have to be made to the Anchor Jig. Leveling nuts and washers are NOT provided with the
pole.
17. The Flat Washers, Lock Washers, and remaining Hex Nuts will be used to fasten the
pole to the Anchor Jig.